SlideShare a Scribd company logo
1 of 1
Form # HSEQ – HSEA (Rev 2 – Sep 18)
HSE ALERT # 055
Arabtec Construction
HSEQ & Org. Risk Dept.
HOT WORKS FIRE RISK
(Non-Arabtec Project)
During waterproofing hot works on the roof of a non-Arabtec project, a fire started when the
flame of a welding torch ignited plastic wrapping covering stored polystyrene insulating
sheets. Due to high winds the flames quickly spread to other materials and installed air
handling units. Despite attempts by the contractor’s emergency team to tackle the fire using
extinguishers, the fire continued to spread and was eventually extinguished by Civil Defense.
Key Points
 Although a hot work permit had been obtained, the permit receiver was not trained
on the procedure and the conditions of the permit were not followed. In particular,
removal or covering of combustible material had not been undertaken.
 There were communication barriers between the supervisor and work team which
impacted communication of the permit controls.
 The pre-start activity briefing had not been conducted.
 The hot work permit training provided did not correlate with the approved procedure.
Recommendations
 Review hot work procedures, training and work practices to ensure they are aligned.
 Identify verbal and written communication barriers on your project; consider the need
for translators and availability of permits to work in multiple languages.
 Ensure permits are only used for high risk activities, with safety critical works subject
to increased focus, review and audit from consultants, site managers and health and
safety professionals.

More Related Content

Similar to Hse alert 55 hot works fire risk

PRESENTATION- APS GEMPOL EXPANSION PROJECT.pptx
PRESENTATION- APS GEMPOL EXPANSION PROJECT.pptxPRESENTATION- APS GEMPOL EXPANSION PROJECT.pptx
PRESENTATION- APS GEMPOL EXPANSION PROJECT.pptx
Bachtiar Candra
 
JHA06_Installation of Transversal beams in Flare Pipe Rack_Rev00.pdf
JHA06_Installation of Transversal beams in Flare Pipe Rack_Rev00.pdfJHA06_Installation of Transversal beams in Flare Pipe Rack_Rev00.pdf
JHA06_Installation of Transversal beams in Flare Pipe Rack_Rev00.pdf
JESUSBASILIOANTONIO
 
Safety Moment - Hydrogen Release at AB Specialty Silicones.pdf
Safety Moment - Hydrogen Release at AB Specialty Silicones.pdfSafety Moment - Hydrogen Release at AB Specialty Silicones.pdf
Safety Moment - Hydrogen Release at AB Specialty Silicones.pdf
Shofwan Hilal
 
Interim Life Safety Measures in Healthcare Construction
Interim Life Safety Measures in Healthcare ConstructionInterim Life Safety Measures in Healthcare Construction
Interim Life Safety Measures in Healthcare Construction
teeterkeene
 
HSE Fire Prevention & Protection Plan
HSE Fire Prevention & Protection PlanHSE Fire Prevention & Protection Plan
HSE Fire Prevention & Protection Plan
Dwarika Bhushan Sharma
 
Hot welding cutting
Hot welding cuttingHot welding cutting
Hot welding cutting
theblues2708
 
Safeworkpmits
SafeworkpmitsSafeworkpmits
Safeworkpmits
istrain
 
update Khalid safety cv1
update Khalid safety cv1update Khalid safety cv1
update Khalid safety cv1
Khalid Deragun
 
Hot Work Training by Bowling Green State University
Hot Work Training by Bowling Green State UniversityHot Work Training by Bowling Green State University
Hot Work Training by Bowling Green State University
Atlantic Training, LLC.
 
INDERPAL SINGH CV AS QC
INDERPAL SINGH CV AS QCINDERPAL SINGH CV AS QC
INDERPAL SINGH CV AS QC
Inder Singh
 

Similar to Hse alert 55 hot works fire risk (20)

PRESENTATION- APS GEMPOL EXPANSION PROJECT.pptx
PRESENTATION- APS GEMPOL EXPANSION PROJECT.pptxPRESENTATION- APS GEMPOL EXPANSION PROJECT.pptx
PRESENTATION- APS GEMPOL EXPANSION PROJECT.pptx
 
JHA06_Installation of Transversal beams in Flare Pipe Rack_Rev00.pdf
JHA06_Installation of Transversal beams in Flare Pipe Rack_Rev00.pdfJHA06_Installation of Transversal beams in Flare Pipe Rack_Rev00.pdf
JHA06_Installation of Transversal beams in Flare Pipe Rack_Rev00.pdf
 
Safety Moment - Hydrogen Release at AB Specialty Silicones.pdf
Safety Moment - Hydrogen Release at AB Specialty Silicones.pdfSafety Moment - Hydrogen Release at AB Specialty Silicones.pdf
Safety Moment - Hydrogen Release at AB Specialty Silicones.pdf
 
Interim Life Safety Measures in Healthcare Construction
Interim Life Safety Measures in Healthcare ConstructionInterim Life Safety Measures in Healthcare Construction
Interim Life Safety Measures in Healthcare Construction
 
2008 Cfsa Seminar A Wong
2008 Cfsa Seminar A Wong2008 Cfsa Seminar A Wong
2008 Cfsa Seminar A Wong
 
HSE Fire Prevention & Protection Plan
HSE Fire Prevention & Protection PlanHSE Fire Prevention & Protection Plan
HSE Fire Prevention & Protection Plan
 
Hot welding cutting
Hot welding cuttingHot welding cutting
Hot welding cutting
 
2120 Ch 13 PowerPoint.pptx
2120 Ch 13 PowerPoint.pptx2120 Ch 13 PowerPoint.pptx
2120 Ch 13 PowerPoint.pptx
 
CV@JOMY NEW
CV@JOMY NEWCV@JOMY NEW
CV@JOMY NEW
 
English_EHS13A_Hot_Work_English_Rev1.1.pdf
English_EHS13A_Hot_Work_English_Rev1.1.pdfEnglish_EHS13A_Hot_Work_English_Rev1.1.pdf
English_EHS13A_Hot_Work_English_Rev1.1.pdf
 
Safeworkpmits
SafeworkpmitsSafeworkpmits
Safeworkpmits
 
update Khalid safety cv1
update Khalid safety cv1update Khalid safety cv1
update Khalid safety cv1
 
SAFE WORK PERMIT
SAFE WORK PERMITSAFE WORK PERMIT
SAFE WORK PERMIT
 
419237835-Safe-Work-Permit-1-ppt.ppt
419237835-Safe-Work-Permit-1-ppt.ppt419237835-Safe-Work-Permit-1-ppt.ppt
419237835-Safe-Work-Permit-1-ppt.ppt
 
Hot Work Training by Bowling Green State University
Hot Work Training by Bowling Green State UniversityHot Work Training by Bowling Green State University
Hot Work Training by Bowling Green State University
 
Weekly PPT 21-28th Aug-1.pptx
Weekly PPT 21-28th Aug-1.pptxWeekly PPT 21-28th Aug-1.pptx
Weekly PPT 21-28th Aug-1.pptx
 
Practical assessment 4 - Identify construction work hazards and select risk c...
Practical assessment 4 - Identify construction work hazards and select risk c...Practical assessment 4 - Identify construction work hazards and select risk c...
Practical assessment 4 - Identify construction work hazards and select risk c...
 
4. Assessment Practical.docx
4. Assessment Practical.docx4. Assessment Practical.docx
4. Assessment Practical.docx
 
INDERPAL SINGH CV AS QC
INDERPAL SINGH CV AS QCINDERPAL SINGH CV AS QC
INDERPAL SINGH CV AS QC
 
4-Hot-Work-Fire-Watch.ppt
4-Hot-Work-Fire-Watch.ppt4-Hot-Work-Fire-Watch.ppt
4-Hot-Work-Fire-Watch.ppt
 

More from Dwarika Bhushan Sharma

PRE-START BRIEFING Form # HSEQ - PSB Rev 2 -.docx
PRE-START BRIEFING Form # HSEQ - PSB  Rev 2 -.docxPRE-START BRIEFING Form # HSEQ - PSB  Rev 2 -.docx
PRE-START BRIEFING Form # HSEQ - PSB Rev 2 -.docx
Dwarika Bhushan Sharma
 
LIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docx
LIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docxLIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docx
LIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docx
Dwarika Bhushan Sharma
 
LIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docx
LIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docxLIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docx
LIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docx
Dwarika Bhushan Sharma
 
LABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docx
LABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docxLABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docx
LABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docx
Dwarika Bhushan Sharma
 
INCIDENT INVESTIGATION REPORT Form # HSEQ - IIR Rev 9 -.docx
INCIDENT INVESTIGATION REPORT  Form # HSEQ - IIR Rev 9 -.docxINCIDENT INVESTIGATION REPORT  Form # HSEQ - IIR Rev 9 -.docx
INCIDENT INVESTIGATION REPORT Form # HSEQ - IIR Rev 9 -.docx
Dwarika Bhushan Sharma
 
HSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.doc
HSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.docHSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.doc
HSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.doc
Dwarika Bhushan Sharma
 

More from Dwarika Bhushan Sharma (20)

4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdf
4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdf4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdf
4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdf
 
5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdf
5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdf5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdf
5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdf
 
3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdf
3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdf3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdf
3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdf
 
2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdf
2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdf2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdf
2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdf
 
1-HAZARDOUS CHEMICALS.pdf
1-HAZARDOUS CHEMICALS.pdf1-HAZARDOUS CHEMICALS.pdf
1-HAZARDOUS CHEMICALS.pdf
 
PRE-START BRIEFING Form # HSEQ - PSB Rev 2 -.docx
PRE-START BRIEFING Form # HSEQ - PSB  Rev 2 -.docxPRE-START BRIEFING Form # HSEQ - PSB  Rev 2 -.docx
PRE-START BRIEFING Form # HSEQ - PSB Rev 2 -.docx
 
FIRE PREVENTION REQUIREMENTS Form # HSEQ - Rev 2.docx
FIRE PREVENTION REQUIREMENTS Form # HSEQ -  Rev 2.docxFIRE PREVENTION REQUIREMENTS Form # HSEQ -  Rev 2.docx
FIRE PREVENTION REQUIREMENTS Form # HSEQ - Rev 2.docx
 
SUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docx
SUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docxSUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docx
SUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docx
 
STORE INSPECTION Form # HSEQ - Form 2 Rev 2.docx
STORE INSPECTION Form # HSEQ - Form 2 Rev 2.docxSTORE INSPECTION Form # HSEQ - Form 2 Rev 2.docx
STORE INSPECTION Form # HSEQ - Form 2 Rev 2.docx
 
WITNESS STATEMENT FORM.docx
WITNESS STATEMENT FORM.docxWITNESS STATEMENT FORM.docx
WITNESS STATEMENT FORM.docx
 
PROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docx
PROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docxPROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docx
PROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docx
 
HSE FORMS (COVER PAGE)2 Form # HSEQ - Rev 2.docx
HSE FORMS (COVER PAGE)2 Form # HSEQ -  Rev 2.docxHSE FORMS (COVER PAGE)2 Form # HSEQ -  Rev 2.docx
HSE FORMS (COVER PAGE)2 Form # HSEQ - Rev 2.docx
 
LIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docx
LIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docxLIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docx
LIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docx
 
LIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docx
LIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docxLIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docx
LIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docx
 
MOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docx
MOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docxMOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docx
MOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docx
 
LABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docx
LABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docxLABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docx
LABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docx
 
INCIDENT INVESTIGATION REPORT Form # HSEQ - IIR Rev 9 -.docx
INCIDENT INVESTIGATION REPORT  Form # HSEQ - IIR Rev 9 -.docxINCIDENT INVESTIGATION REPORT  Form # HSEQ - IIR Rev 9 -.docx
INCIDENT INVESTIGATION REPORT Form # HSEQ - IIR Rev 9 -.docx
 
HSE INDUCTION Form # HSEQ - HSEI Rev 2 -.doc
HSE INDUCTION Form # HSEQ - HSEI Rev 2 -.docHSE INDUCTION Form # HSEQ - HSEI Rev 2 -.doc
HSE INDUCTION Form # HSEQ - HSEI Rev 2 -.doc
 
HSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.doc
HSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.docHSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.doc
HSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.doc
 
OFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docx
OFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docxOFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docx
OFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docx
 

Recently uploaded

The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
heathfieldcps1
 
Call Girls in Uttam Nagar (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in  Uttam Nagar (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in  Uttam Nagar (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in Uttam Nagar (delhi) call me [🔝9953056974🔝] escort service 24X7
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Spellings Wk 4 and Wk 5 for Grade 4 at CAPS
Spellings Wk 4 and Wk 5 for Grade 4 at CAPSSpellings Wk 4 and Wk 5 for Grade 4 at CAPS
Spellings Wk 4 and Wk 5 for Grade 4 at CAPS
AnaAcapella
 

Recently uploaded (20)

How to Add a Tool Tip to a Field in Odoo 17
How to Add a Tool Tip to a Field in Odoo 17How to Add a Tool Tip to a Field in Odoo 17
How to Add a Tool Tip to a Field in Odoo 17
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
 
Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptx
Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptxExploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptx
Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptx
 
Graduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - EnglishGraduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - English
 
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptxHMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
 
FICTIONAL SALESMAN/SALESMAN SNSW 2024.pdf
FICTIONAL SALESMAN/SALESMAN SNSW 2024.pdfFICTIONAL SALESMAN/SALESMAN SNSW 2024.pdf
FICTIONAL SALESMAN/SALESMAN SNSW 2024.pdf
 
Call Girls in Uttam Nagar (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in  Uttam Nagar (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in  Uttam Nagar (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in Uttam Nagar (delhi) call me [🔝9953056974🔝] escort service 24X7
 
This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.
 
21st_Century_Skills_Framework_Final_Presentation_2.pptx
21st_Century_Skills_Framework_Final_Presentation_2.pptx21st_Century_Skills_Framework_Final_Presentation_2.pptx
21st_Century_Skills_Framework_Final_Presentation_2.pptx
 
How to Manage Call for Tendor in Odoo 17
How to Manage Call for Tendor in Odoo 17How to Manage Call for Tendor in Odoo 17
How to Manage Call for Tendor in Odoo 17
 
Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)
 
Food safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdfFood safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdf
 
Details on CBSE Compartment Exam.pptx1111
Details on CBSE Compartment Exam.pptx1111Details on CBSE Compartment Exam.pptx1111
Details on CBSE Compartment Exam.pptx1111
 
Tatlong Kwento ni Lola basyang-1.pdf arts
Tatlong Kwento ni Lola basyang-1.pdf artsTatlong Kwento ni Lola basyang-1.pdf arts
Tatlong Kwento ni Lola basyang-1.pdf arts
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
 
Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docx
 
How to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSHow to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POS
 
Spellings Wk 4 and Wk 5 for Grade 4 at CAPS
Spellings Wk 4 and Wk 5 for Grade 4 at CAPSSpellings Wk 4 and Wk 5 for Grade 4 at CAPS
Spellings Wk 4 and Wk 5 for Grade 4 at CAPS
 
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdf
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdfUnit 3 Emotional Intelligence and Spiritual Intelligence.pdf
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdf
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan Fellows
 

Hse alert 55 hot works fire risk

  • 1. Form # HSEQ – HSEA (Rev 2 – Sep 18) HSE ALERT # 055 Arabtec Construction HSEQ & Org. Risk Dept. HOT WORKS FIRE RISK (Non-Arabtec Project) During waterproofing hot works on the roof of a non-Arabtec project, a fire started when the flame of a welding torch ignited plastic wrapping covering stored polystyrene insulating sheets. Due to high winds the flames quickly spread to other materials and installed air handling units. Despite attempts by the contractor’s emergency team to tackle the fire using extinguishers, the fire continued to spread and was eventually extinguished by Civil Defense. Key Points  Although a hot work permit had been obtained, the permit receiver was not trained on the procedure and the conditions of the permit were not followed. In particular, removal or covering of combustible material had not been undertaken.  There were communication barriers between the supervisor and work team which impacted communication of the permit controls.  The pre-start activity briefing had not been conducted.  The hot work permit training provided did not correlate with the approved procedure. Recommendations  Review hot work procedures, training and work practices to ensure they are aligned.  Identify verbal and written communication barriers on your project; consider the need for translators and availability of permits to work in multiple languages.  Ensure permits are only used for high risk activities, with safety critical works subject to increased focus, review and audit from consultants, site managers and health and safety professionals.