SlideShare a Scribd company logo
QSRA: Introduction for risk/planning
professionals and decision-makers
Tony McDonald
James Kimmance
Graham Nicol
Welcome and Introduction
• Welcome on behalf of the Risk & PMC SIGs
• Today’s presenters
– Tony McDonald, Costain
– James Kimmance, Jacobs
– Graham Nicol, Turner and Townsend
• Many thanks to Maya and Anna from APM and
members of both SIGs
• Risk SIG Conference 2019 - Using Risk to Influence
the Future (26 Mar 19 in Birmingham)
Why is QSRA best practice and what do decision-
makers need from it?
• QSRA answers 3 key questions concerning overrunning project schedules
– Can overruns be predicted with some degree of accuracy?
– Can causes of risk be identified upfront, helping project to stop them happening
through effective response actions?
– Can risk professionals determine causes of why projects frequently overrun their
initial schedules?
• Overwhelmingly the answer is yes!
• Addresses head-on the fact that don’t know how long activities will take
• Allows investigation of activity ‘uncertainty’ to establish its effects on a project schedule
– How likely is the project to achieve the key dates & milestones in the schedule?
– How much schedule contingency is needed to provide acceptable degree of
certainty?
– Where is the greatest risk in the schedule?
• QSRA outputs provide a strong indication to key decision-makers of the key activities
and risks that will impact the project if not managed correctly project
References: ‘Practical Schedule Risk Analysis’ Hulett, David 2009’
QSRA is based on a good project schedule
• Scheduling is a challenging discipline
• Vital that a project’s risk and scheduling functions work closely together to
conduct QSRA, fully involving project managers/decision-makers from the start
– Build high-level analysis network derived from the project schedule
– Utilise schedulers knowledge of project schedule to ensure that all areas
are explored for potential risk
• QSRA high-level analysis network ‘criteria’
– Left-to-right, logic driven
– ‘Finish-to-Start’ or ‘Start-to-Finish’ predecessors & ‘Finish-to-Start’ or
‘Finish-to-Finish’ successors
– Not a ‘rolled up’ project schedule
– Overall activity durations/dates match project schedule
– Minimal/no use of constraints especially Late-Date constraints
– No dangling logic ‘danglers’
– Minimal/no use of lag/leads(‘negative lag’)
References: ‘Practical Schedule Risk Analysis’ Hulett, David 2009’
Quantitative Schedule Risk
Analysis
Uncertainty and Risk
Content
• Introduction
• A Simplified QSRA Process
• Project Uncertainty and Risk
• Cautionary observations
• The benefits The biggest uncertainty in risk
analysis is whether we started
off analysing the right thing and
in the right way
Introduction- QSRA objectives
• Quantitative Schedule Risk Analysis primarily
used to:
– provide risk based confidence forecasts of key
milestones
– support quantification of a projects schedule (and
cost) contingency requirements
– ......also drives other ‘good’ project behaviours
Introduction (contd)
• A wide variety of tools are available:
• Oracle PRA / Acumen Fuse Risk/ Safran Risk
• A large volume of quality literature and guides
are available
• Hulett, Hillson, GAO (USA), APM etc
• Aim is to provide a:
– ‘Quick Start’ introduction
– Do’s, Maybe’s and Don’ts
A Simplified QSRA Process
• Key simplified stages – appear straightforward
Schedule
Preparation
Assign
Activity
Uncertainty
MapRisk(s)
toActivities
ApplyRisk
Correlations
Incorporate
Probabilistic
Branching
Apply
Weather
Risk
Schedule
Health
Check
Run
Analyses
Review
Analyses
andModel
Interpretive
Report
* Not covered here
Maybe Not That Simple
• Schedule suitable for QSRA may need a ‘logic’
rework:
– Constraints (e.g. expected finish); lags etc
– Size/level ideally 200 – 500 activities, but 2000 possible
• Many things in ‘Risk’ are intuitively understood -
but in practice need clarification. Risk and
Uncertainty are two terms that often lack
clarity, consistency in application, and are often
confused / seen as interchangeable.
Schedule
Preparation
Assign
Activity
Uncertainty
MapRisk(s)
toActivities
Risk & Uncertainty
• A lot has been written in the Project (Risk)
Management space differentiating between
Risk & Uncertainty
• Defining Risk
• Many ‘variations’ – but on a theme with a large consistency
• APM PMBOK.. ‘an uncertain event or condition that, if it occurs,
has a positive or negative effect on the project objective’
• Typically: event based; quantifiable with probabilities of
occurrence; and impact on the project
Risk & Uncertainty (contd.)
• Defining Uncertainty….
• Uncertainty definitions in Project Management are less ubiquitous
and more nebulous
• “Uncertainty is a lack of certainty”; …….”uncertainty is understood
in its most basic form as not knowing for sure, due to lack of
information or ambiguous information”;…………
• Common themes are: absence of information; unknowing;
variability; ambiguity; and lack of clarity; a degree of ‘randomness’
about an average
Risk vs. Uncertainty
• For practical day to day purposes:
– A risk is a discrete event with a probability of
occurrence. The risk effect is only felt if the event
occurs
– Uncertainty is an occurrence that has no
probability, and you know that you don’t know the
actual value
• Effectively a normal activity i.e. – but for which there is
an inherent ‘variability’ caused by a variety of factors
• The variability can be captured as a range based on
‘experience’
Creating the model and data
• Key players are the Scheduler, Risk Manager,
Subject Matter Experts, and Project Managers
– Review and amend the schedule with logic in
mind (using schedule health check tool)
– Estimate activity uncertainty
• Individual activities – SME knowledge and experience –
or maybe even data sets from similar activities
• Possibly in groups of similar activities (quick templating)
for example Civils, M&E, ICT, New Technology,
Integration and Commissioning
Creating the model and data (contd.)
– Determine and map schedule impacting risks
• Assumptions analysis – capture necessary risks
• Review existing risk register
• Determine probabilities, and distribution type
– Typically Triangular, or Trigen, Uniform and BetaPert
• Map to activities in the schedule model
• Doing this properly requires significant
resources
• But there are significant benefits – at all stages of the
project
Cautionary Observations
• The schedule and uncertainty data are the key
building blocks upon which the QSRA relies:
• Don’t skimp on creating a suitably sized schedule, with
logic suitable for an analysis
• Look for and capture assumptions
• Prepare, and then challenge activity uncertainty with
SME’s
• Risks
• Don’t just ‘drag and dump’ risks from a general risk
register into the model
Cautionary Observations (contd.)
• With a QSRA model - do not
• Leave the process until last / when you have a ‘finished’
schedule
– It will be rushed / tick box exercise
– You will not get many of the benefits of investing
– May suggest you have a ‘potential’ nightmare (typically just
before you have to submit for finding approval)
• Miss out the SME’s and PM’s because they are ‘busy’
• Try to ‘game’ the result
– Often reflected in some strange outputs and reports
Benefits
• QSRA’s can be resource consuming so
maximising benefits are important.
• Even at an early stage:
– Overruns can be associated with a lack of in depth
analysis / challenge at the planning (or even
bidding) stage. When we can more easily change
things………..
– Unrealistic or overly optimistic plans identified.
– Going through the process can identify what you
don’t know (and need to focus on) as much as
what you think you know.
Benefits (contd.)
• Subsequent stages
• We identify those activities and risks which are having
the biggest impact on our schedule (and costs)
• Prioritise and support the development of mitigation
activities
Interpretation of QSRA Outputs
Interpretation of QSRA Outputs
• The interpretation of QSRA Outputs and how
they are reported is probably the most critical
aspect of the QSRA process
• A lot of work will have gone into producing
the outputs
• However, the QSRA outputs can be extremely
sensitive if presented without context or
without challenge!
Challenges with QSRA Outputs
• Key messages can often be hidden away in
lengthy QSRA reports
• Single Pnumbers i.e P50 confidence – Date ‘X’
don’t actually inform a decision
• Decision makers struggle to grasp what QSRA
outputs are telling them and the value of the
QSRA process is often lost on them
• Often Practitioners can’t explain what’s driving
the analysis or what’s gone into the model
Interpretation of QSRA Outputs- Back
to Basics
• Why do QSRAs in the first place?
– Inform contingency discussions/arrangements
– Provide confidence and assurance regarding
schedule assumptions and integrity
– Identify key risks to delivery and highlight
sensitive areas within the project schedule
– Provides a range of outcomes
– Model various scenarios
Risk Practitioner Questions to Ask…
When questioned by decision makers/senior
management re. QSRA outputs…can I:
– Detail the quality of inputs that went into the model i.e.
management signed off schedules, uncertainty and risk
inputs
– Outline what scenarios have been modelled and any
assumptions and exclusions
– Demonstrate that the QSRA process was iterative and
involved all key stakeholders
– Agree what are the base dates, milestones etc in the
schedule that the QSRA outputs should be compared
against…doesn’t always have to just be the end date!
QSRA Outputs-Distribution Outputs (Pre-Mit)
Pre-mitigated position (assuming no mitigation in place or effective)
1% chance of hitting the base date (Gold arrow)
P50 output (Blue arrow)- 10/04/2024…some 534 days after base date!
QSRA Outputs-Distribution Outputs (Post-Mit)
Post- mitigated position (assuming identified mitigation successful!)
26% chance of hitting the base date (Gold arrow)
P50 output (Blue Arrow)- 25/07/2023…now 274 days after base date an
improvement of 260 days!
QSRA Outputs - Distribution Analyser
Plan Outcomes with
Uncertainty and Pre-Mitigated
RiskPlan Outcomes with
Uncertainty and Post-
Mitigated Risk
Potentially 260 days saving
if the proposed mitigations
are successful at P50!
QSRA Outputs - Tornado Graphs
What’s causing these
top 2 risks to drive the
QSRA model?
Why are delivery to site
activities so sensitive to
uncertainty and risk?
QSRA Outputs – Scatter Graphs
Interpretation of QSRA Outputs
• Be clear on what has gone into the model in terms of
quality inputs
• Present ranges rather than Single Pnumbers…
– P50 date is ‘X’ but considering the P75 output would give an
additional 2 weeks time risk allowance?
• Present the delta of the analysis compared to base data
• Be clear on pre and post-mitigated positions
– Why are certain risks more prominent than others?
– What drives reduction in exposure?
– Are mitigations robust to merit the reduction in exposure?
Q&A
Questions?
Thank You
This presentation was
delivered
at an APM webinar
To find out more about upcoming webinars
please visit our website
www.apm.org.uk/events

More Related Content

Similar to APM QSRA webinar; introduction for risk and planning professionals and decision makers

Essentials of Entry Level Project Management - Rev A
Essentials of Entry Level Project Management - Rev AEssentials of Entry Level Project Management - Rev A
Essentials of Entry Level Project Management - Rev A
Steve Kiester
 
Project management
Project managementProject management
Project management
Heather Marie Wells
 
Project Management Principles and Process
Project Management Principles and ProcessProject Management Principles and Process
Project Management Principles and Process
Charles Cotter, PhD
 
Projectriskmanagement pmbok5
Projectriskmanagement pmbok5Projectriskmanagement pmbok5
Projectriskmanagement pmbok5
Dhamo daran
 
Ppt.pptx
Ppt.pptxPpt.pptx
Ppt.pptx
nayeembanu1
 
Getting the basics right
Getting the basics rightGetting the basics right
Getting the basics right
Thomas Cream
 
Project Management - principles, practice and process
Project Management - principles, practice and process Project Management - principles, practice and process
Project Management - principles, practice and process
Charles Cotter, PhD
 
Project management by Dr. Huda Hassan
Project management by Dr. Huda HassanProject management by Dr. Huda Hassan
Project management by Dr. Huda Hassan
Dr Ghaiath Hussein
 
Mitigating cost and schedule risk with oracle primavera risk analysis - Oracl...
Mitigating cost and schedule risk with oracle primavera risk analysis - Oracl...Mitigating cost and schedule risk with oracle primavera risk analysis - Oracl...
Mitigating cost and schedule risk with oracle primavera risk analysis - Oracl...
p6academy
 
2. PAE AcFn621 Ch-2 Principle ppt.pptx
2. PAE AcFn621 Ch-2 Principle ppt.pptx2. PAE AcFn621 Ch-2 Principle ppt.pptx
2. PAE AcFn621 Ch-2 Principle ppt.pptx
ProfDrAnbalaganChinn
 
PROJECT CHARTER TEMPLATE GENERAL PROJECT INFORMATIONProject Na.docx
PROJECT CHARTER TEMPLATE GENERAL PROJECT INFORMATIONProject Na.docxPROJECT CHARTER TEMPLATE GENERAL PROJECT INFORMATIONProject Na.docx
PROJECT CHARTER TEMPLATE GENERAL PROJECT INFORMATIONProject Na.docx
wkyra78
 
Integrating risk with earned value
Integrating risk with earned valueIntegrating risk with earned value
Integrating risk with earned value
Glen Alleman
 
Peoject Risk Management(quantative&qualitive)
Peoject Risk Management(quantative&qualitive)Peoject Risk Management(quantative&qualitive)
Peoject Risk Management(quantative&qualitive)
Evgeni Tsonev
 
Advanced project risk reporting webinar, 21 September 2022
Advanced project risk reporting webinar, 21 September 2022Advanced project risk reporting webinar, 21 September 2022
Advanced project risk reporting webinar, 21 September 2022
Association for Project Management
 
Risk management - A short course
Risk management  - A short courseRisk management  - A short course
Risk management - A short course
Malcolm Peart
 
Risk Event Modeling and Event Chains
Risk Event Modeling and Event ChainsRisk Event Modeling and Event Chains
Risk Event Modeling and Event Chains
Intaver Insititute
 
Quantitative Project Risk Analysis
Quantitative Project Risk AnalysisQuantitative Project Risk Analysis
Quantitative Project Risk Analysis
Intaver Insititute
 
3. PAE AcFn621 Ch-3 Project Planning.ppt
3. PAE AcFn621 Ch-3 Project Planning.ppt3. PAE AcFn621 Ch-3 Project Planning.ppt
3. PAE AcFn621 Ch-3 Project Planning.ppt
ProfDrAnbalaganChinn
 
Quantitative Project Risk Analysis
Quantitative Project Risk AnalysisQuantitative Project Risk Analysis
Quantitative Project Risk Analysis
Intaver Insititute
 
Price.rick
Price.rickPrice.rick
Price.rick
NASAPMC
 

Similar to APM QSRA webinar; introduction for risk and planning professionals and decision makers (20)

Essentials of Entry Level Project Management - Rev A
Essentials of Entry Level Project Management - Rev AEssentials of Entry Level Project Management - Rev A
Essentials of Entry Level Project Management - Rev A
 
Project management
Project managementProject management
Project management
 
Project Management Principles and Process
Project Management Principles and ProcessProject Management Principles and Process
Project Management Principles and Process
 
Projectriskmanagement pmbok5
Projectriskmanagement pmbok5Projectriskmanagement pmbok5
Projectriskmanagement pmbok5
 
Ppt.pptx
Ppt.pptxPpt.pptx
Ppt.pptx
 
Getting the basics right
Getting the basics rightGetting the basics right
Getting the basics right
 
Project Management - principles, practice and process
Project Management - principles, practice and process Project Management - principles, practice and process
Project Management - principles, practice and process
 
Project management by Dr. Huda Hassan
Project management by Dr. Huda HassanProject management by Dr. Huda Hassan
Project management by Dr. Huda Hassan
 
Mitigating cost and schedule risk with oracle primavera risk analysis - Oracl...
Mitigating cost and schedule risk with oracle primavera risk analysis - Oracl...Mitigating cost and schedule risk with oracle primavera risk analysis - Oracl...
Mitigating cost and schedule risk with oracle primavera risk analysis - Oracl...
 
2. PAE AcFn621 Ch-2 Principle ppt.pptx
2. PAE AcFn621 Ch-2 Principle ppt.pptx2. PAE AcFn621 Ch-2 Principle ppt.pptx
2. PAE AcFn621 Ch-2 Principle ppt.pptx
 
PROJECT CHARTER TEMPLATE GENERAL PROJECT INFORMATIONProject Na.docx
PROJECT CHARTER TEMPLATE GENERAL PROJECT INFORMATIONProject Na.docxPROJECT CHARTER TEMPLATE GENERAL PROJECT INFORMATIONProject Na.docx
PROJECT CHARTER TEMPLATE GENERAL PROJECT INFORMATIONProject Na.docx
 
Integrating risk with earned value
Integrating risk with earned valueIntegrating risk with earned value
Integrating risk with earned value
 
Peoject Risk Management(quantative&qualitive)
Peoject Risk Management(quantative&qualitive)Peoject Risk Management(quantative&qualitive)
Peoject Risk Management(quantative&qualitive)
 
Advanced project risk reporting webinar, 21 September 2022
Advanced project risk reporting webinar, 21 September 2022Advanced project risk reporting webinar, 21 September 2022
Advanced project risk reporting webinar, 21 September 2022
 
Risk management - A short course
Risk management  - A short courseRisk management  - A short course
Risk management - A short course
 
Risk Event Modeling and Event Chains
Risk Event Modeling and Event ChainsRisk Event Modeling and Event Chains
Risk Event Modeling and Event Chains
 
Quantitative Project Risk Analysis
Quantitative Project Risk AnalysisQuantitative Project Risk Analysis
Quantitative Project Risk Analysis
 
3. PAE AcFn621 Ch-3 Project Planning.ppt
3. PAE AcFn621 Ch-3 Project Planning.ppt3. PAE AcFn621 Ch-3 Project Planning.ppt
3. PAE AcFn621 Ch-3 Project Planning.ppt
 
Quantitative Project Risk Analysis
Quantitative Project Risk AnalysisQuantitative Project Risk Analysis
Quantitative Project Risk Analysis
 
Price.rick
Price.rickPrice.rick
Price.rick
 

More from Association for Project Management

Including Mental Health Support in Project Delivery, 14 May.pdf
Including Mental Health Support in Project Delivery, 14 May.pdfIncluding Mental Health Support in Project Delivery, 14 May.pdf
Including Mental Health Support in Project Delivery, 14 May.pdf
Association for Project Management
 
Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...
Association for Project Management
 
Spatium Project Simulation student brief
Spatium Project Simulation student briefSpatium Project Simulation student brief
Spatium Project Simulation student brief
Association for Project Management
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across Sectors
Association for Project Management
 
Projecting for the Future: Harmonising Energy and Environment, APM North West...
Projecting for the Future: Harmonising Energy and Environment, APM North West...Projecting for the Future: Harmonising Energy and Environment, APM North West...
Projecting for the Future: Harmonising Energy and Environment, APM North West...
Association for Project Management
 
New to Nuclear - Transition into nuclear from other sectors, APM North West N...
New to Nuclear - Transition into nuclear from other sectors, APM North West N...New to Nuclear - Transition into nuclear from other sectors, APM North West N...
New to Nuclear - Transition into nuclear from other sectors, APM North West N...
Association for Project Management
 
Tell us what to do, not how to do it, APM North West Network Conference, Syne...
Tell us what to do, not how to do it, APM North West Network Conference, Syne...Tell us what to do, not how to do it, APM North West Network Conference, Syne...
Tell us what to do, not how to do it, APM North West Network Conference, Syne...
Association for Project Management
 
The Future is Fractional, APM North West Network Conference, Synergies Across...
The Future is Fractional, APM North West Network Conference, Synergies Across...The Future is Fractional, APM North West Network Conference, Synergies Across...
The Future is Fractional, APM North West Network Conference, Synergies Across...
Association for Project Management
 
Lessons learned across projects, APM North West Network Conference, Synergies...
Lessons learned across projects, APM North West Network Conference, Synergies...Lessons learned across projects, APM North West Network Conference, Synergies...
Lessons learned across projects, APM North West Network Conference, Synergies...
Association for Project Management
 
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...
Association for Project Management
 
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...
Association for Project Management
 
Leadership - the project professionals secret weapon, 24 April 2024
Leadership - the project professionals secret weapon, 24 April 2024Leadership - the project professionals secret weapon, 24 April 2024
Leadership - the project professionals secret weapon, 24 April 2024
Association for Project Management
 
APM Project Management Awards - Hints and tips for a winning award entry webi...
APM Project Management Awards - Hints and tips for a winning award entry webi...APM Project Management Awards - Hints and tips for a winning award entry webi...
APM Project Management Awards - Hints and tips for a winning award entry webi...
Association for Project Management
 
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
Association for Project Management
 
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Association for Project Management
 
Staurt Earl - ARCC Programme for APM Awards.pptx
Staurt Earl - ARCC Programme for APM Awards.pptxStaurt Earl - ARCC Programme for APM Awards.pptx
Staurt Earl - ARCC Programme for APM Awards.pptx
Association for Project Management
 
If AI changes everything – do feelings still matter?
If AI changes everything – do feelings still matter?If AI changes everything – do feelings still matter?
If AI changes everything – do feelings still matter?
Association for Project Management
 
AI in the project profession: examples of current use and roadmaps to adoptio...
AI in the project profession: examples of current use and roadmaps to adoptio...AI in the project profession: examples of current use and roadmaps to adoptio...
AI in the project profession: examples of current use and roadmaps to adoptio...
Association for Project Management
 
Katharine Fox, WRAP - Valuing sustainability
Katharine Fox, WRAP - Valuing sustainabilityKatharine Fox, WRAP - Valuing sustainability
Katharine Fox, WRAP - Valuing sustainability
Association for Project Management
 
The silent project disruptor: Building AI solutions
The silent project disruptor: Building AI solutionsThe silent project disruptor: Building AI solutions
The silent project disruptor: Building AI solutions
Association for Project Management
 

More from Association for Project Management (20)

Including Mental Health Support in Project Delivery, 14 May.pdf
Including Mental Health Support in Project Delivery, 14 May.pdfIncluding Mental Health Support in Project Delivery, 14 May.pdf
Including Mental Health Support in Project Delivery, 14 May.pdf
 
Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...
 
Spatium Project Simulation student brief
Spatium Project Simulation student briefSpatium Project Simulation student brief
Spatium Project Simulation student brief
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across Sectors
 
Projecting for the Future: Harmonising Energy and Environment, APM North West...
Projecting for the Future: Harmonising Energy and Environment, APM North West...Projecting for the Future: Harmonising Energy and Environment, APM North West...
Projecting for the Future: Harmonising Energy and Environment, APM North West...
 
New to Nuclear - Transition into nuclear from other sectors, APM North West N...
New to Nuclear - Transition into nuclear from other sectors, APM North West N...New to Nuclear - Transition into nuclear from other sectors, APM North West N...
New to Nuclear - Transition into nuclear from other sectors, APM North West N...
 
Tell us what to do, not how to do it, APM North West Network Conference, Syne...
Tell us what to do, not how to do it, APM North West Network Conference, Syne...Tell us what to do, not how to do it, APM North West Network Conference, Syne...
Tell us what to do, not how to do it, APM North West Network Conference, Syne...
 
The Future is Fractional, APM North West Network Conference, Synergies Across...
The Future is Fractional, APM North West Network Conference, Synergies Across...The Future is Fractional, APM North West Network Conference, Synergies Across...
The Future is Fractional, APM North West Network Conference, Synergies Across...
 
Lessons learned across projects, APM North West Network Conference, Synergies...
Lessons learned across projects, APM North West Network Conference, Synergies...Lessons learned across projects, APM North West Network Conference, Synergies...
Lessons learned across projects, APM North West Network Conference, Synergies...
 
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...
 
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...
 
Leadership - the project professionals secret weapon, 24 April 2024
Leadership - the project professionals secret weapon, 24 April 2024Leadership - the project professionals secret weapon, 24 April 2024
Leadership - the project professionals secret weapon, 24 April 2024
 
APM Project Management Awards - Hints and tips for a winning award entry webi...
APM Project Management Awards - Hints and tips for a winning award entry webi...APM Project Management Awards - Hints and tips for a winning award entry webi...
APM Project Management Awards - Hints and tips for a winning award entry webi...
 
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
 
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
 
Staurt Earl - ARCC Programme for APM Awards.pptx
Staurt Earl - ARCC Programme for APM Awards.pptxStaurt Earl - ARCC Programme for APM Awards.pptx
Staurt Earl - ARCC Programme for APM Awards.pptx
 
If AI changes everything – do feelings still matter?
If AI changes everything – do feelings still matter?If AI changes everything – do feelings still matter?
If AI changes everything – do feelings still matter?
 
AI in the project profession: examples of current use and roadmaps to adoptio...
AI in the project profession: examples of current use and roadmaps to adoptio...AI in the project profession: examples of current use and roadmaps to adoptio...
AI in the project profession: examples of current use and roadmaps to adoptio...
 
Katharine Fox, WRAP - Valuing sustainability
Katharine Fox, WRAP - Valuing sustainabilityKatharine Fox, WRAP - Valuing sustainability
Katharine Fox, WRAP - Valuing sustainability
 
The silent project disruptor: Building AI solutions
The silent project disruptor: Building AI solutionsThe silent project disruptor: Building AI solutions
The silent project disruptor: Building AI solutions
 

Recently uploaded

Structural Design Process: Step-by-Step Guide for Buildings
Structural Design Process: Step-by-Step Guide for BuildingsStructural Design Process: Step-by-Step Guide for Buildings
Structural Design Process: Step-by-Step Guide for Buildings
Chandresh Chudasama
 
Best Forex Brokers Comparison in INDIA 2024
Best Forex Brokers Comparison in INDIA 2024Best Forex Brokers Comparison in INDIA 2024
Best Forex Brokers Comparison in INDIA 2024
Top Forex Brokers Review
 
Observation Lab PowerPoint Assignment for TEM 431
Observation Lab PowerPoint Assignment for TEM 431Observation Lab PowerPoint Assignment for TEM 431
Observation Lab PowerPoint Assignment for TEM 431
ecamare2
 
Business storytelling: key ingredients to a story
Business storytelling: key ingredients to a storyBusiness storytelling: key ingredients to a story
Business storytelling: key ingredients to a story
Alexandra Fulford
 
2024-6-01-IMPACTSilver-Corp-Presentation.pdf
2024-6-01-IMPACTSilver-Corp-Presentation.pdf2024-6-01-IMPACTSilver-Corp-Presentation.pdf
2024-6-01-IMPACTSilver-Corp-Presentation.pdf
hartfordclub1
 
Authentically Social by Corey Perlman - EO Puerto Rico
Authentically Social by Corey Perlman - EO Puerto RicoAuthentically Social by Corey Perlman - EO Puerto Rico
Authentically Social by Corey Perlman - EO Puerto Rico
Corey Perlman, Social Media Speaker and Consultant
 
Innovation Management Frameworks: Your Guide to Creativity & Innovation
Innovation Management Frameworks: Your Guide to Creativity & InnovationInnovation Management Frameworks: Your Guide to Creativity & Innovation
Innovation Management Frameworks: Your Guide to Creativity & Innovation
Operational Excellence Consulting
 
HOW TO START UP A COMPANY A STEP-BY-STEP GUIDE.pdf
HOW TO START UP A COMPANY A STEP-BY-STEP GUIDE.pdfHOW TO START UP A COMPANY A STEP-BY-STEP GUIDE.pdf
HOW TO START UP A COMPANY A STEP-BY-STEP GUIDE.pdf
46adnanshahzad
 
3 Simple Steps To Buy Verified Payoneer Account In 2024
3 Simple Steps To Buy Verified Payoneer Account In 20243 Simple Steps To Buy Verified Payoneer Account In 2024
3 Simple Steps To Buy Verified Payoneer Account In 2024
SEOSMMEARTH
 
Digital Marketing with a Focus on Sustainability
Digital Marketing with a Focus on SustainabilityDigital Marketing with a Focus on Sustainability
Digital Marketing with a Focus on Sustainability
sssourabhsharma
 
-- June 2024 is National Volunteer Month --
-- June 2024 is National Volunteer Month ---- June 2024 is National Volunteer Month --
-- June 2024 is National Volunteer Month --
NZSG
 
The APCO Geopolitical Radar - Q3 2024 The Global Operating Environment for Bu...
The APCO Geopolitical Radar - Q3 2024 The Global Operating Environment for Bu...The APCO Geopolitical Radar - Q3 2024 The Global Operating Environment for Bu...
The APCO Geopolitical Radar - Q3 2024 The Global Operating Environment for Bu...
APCO
 
How are Lilac French Bulldogs Beauty Charming the World and Capturing Hearts....
How are Lilac French Bulldogs Beauty Charming the World and Capturing Hearts....How are Lilac French Bulldogs Beauty Charming the World and Capturing Hearts....
How are Lilac French Bulldogs Beauty Charming the World and Capturing Hearts....
Lacey Max
 
Industrial Tech SW: Category Renewal and Creation
Industrial Tech SW:  Category Renewal and CreationIndustrial Tech SW:  Category Renewal and Creation
Industrial Tech SW: Category Renewal and Creation
Christian Dahlen
 
Income Tax exemption for Start up : Section 80 IAC
Income Tax  exemption for Start up : Section 80 IACIncome Tax  exemption for Start up : Section 80 IAC
Income Tax exemption for Start up : Section 80 IAC
CA Dr. Prithvi Ranjan Parhi
 
Creative Web Design Company in Singapore
Creative Web Design Company in SingaporeCreative Web Design Company in Singapore
Creative Web Design Company in Singapore
techboxsqauremedia
 
Unveiling the Dynamic Personalities, Key Dates, and Horoscope Insights: Gemin...
Unveiling the Dynamic Personalities, Key Dates, and Horoscope Insights: Gemin...Unveiling the Dynamic Personalities, Key Dates, and Horoscope Insights: Gemin...
Unveiling the Dynamic Personalities, Key Dates, and Horoscope Insights: Gemin...
my Pandit
 
2022 Vintage Roman Numerals Men Rings
2022 Vintage Roman  Numerals  Men  Rings2022 Vintage Roman  Numerals  Men  Rings
2022 Vintage Roman Numerals Men Rings
aragme
 
How to Implement a Real Estate CRM Software
How to Implement a Real Estate CRM SoftwareHow to Implement a Real Estate CRM Software
How to Implement a Real Estate CRM Software
SalesTown
 
Lundin Gold Corporate Presentation - June 2024
Lundin Gold Corporate Presentation - June 2024Lundin Gold Corporate Presentation - June 2024
Lundin Gold Corporate Presentation - June 2024
Adnet Communications
 

Recently uploaded (20)

Structural Design Process: Step-by-Step Guide for Buildings
Structural Design Process: Step-by-Step Guide for BuildingsStructural Design Process: Step-by-Step Guide for Buildings
Structural Design Process: Step-by-Step Guide for Buildings
 
Best Forex Brokers Comparison in INDIA 2024
Best Forex Brokers Comparison in INDIA 2024Best Forex Brokers Comparison in INDIA 2024
Best Forex Brokers Comparison in INDIA 2024
 
Observation Lab PowerPoint Assignment for TEM 431
Observation Lab PowerPoint Assignment for TEM 431Observation Lab PowerPoint Assignment for TEM 431
Observation Lab PowerPoint Assignment for TEM 431
 
Business storytelling: key ingredients to a story
Business storytelling: key ingredients to a storyBusiness storytelling: key ingredients to a story
Business storytelling: key ingredients to a story
 
2024-6-01-IMPACTSilver-Corp-Presentation.pdf
2024-6-01-IMPACTSilver-Corp-Presentation.pdf2024-6-01-IMPACTSilver-Corp-Presentation.pdf
2024-6-01-IMPACTSilver-Corp-Presentation.pdf
 
Authentically Social by Corey Perlman - EO Puerto Rico
Authentically Social by Corey Perlman - EO Puerto RicoAuthentically Social by Corey Perlman - EO Puerto Rico
Authentically Social by Corey Perlman - EO Puerto Rico
 
Innovation Management Frameworks: Your Guide to Creativity & Innovation
Innovation Management Frameworks: Your Guide to Creativity & InnovationInnovation Management Frameworks: Your Guide to Creativity & Innovation
Innovation Management Frameworks: Your Guide to Creativity & Innovation
 
HOW TO START UP A COMPANY A STEP-BY-STEP GUIDE.pdf
HOW TO START UP A COMPANY A STEP-BY-STEP GUIDE.pdfHOW TO START UP A COMPANY A STEP-BY-STEP GUIDE.pdf
HOW TO START UP A COMPANY A STEP-BY-STEP GUIDE.pdf
 
3 Simple Steps To Buy Verified Payoneer Account In 2024
3 Simple Steps To Buy Verified Payoneer Account In 20243 Simple Steps To Buy Verified Payoneer Account In 2024
3 Simple Steps To Buy Verified Payoneer Account In 2024
 
Digital Marketing with a Focus on Sustainability
Digital Marketing with a Focus on SustainabilityDigital Marketing with a Focus on Sustainability
Digital Marketing with a Focus on Sustainability
 
-- June 2024 is National Volunteer Month --
-- June 2024 is National Volunteer Month ---- June 2024 is National Volunteer Month --
-- June 2024 is National Volunteer Month --
 
The APCO Geopolitical Radar - Q3 2024 The Global Operating Environment for Bu...
The APCO Geopolitical Radar - Q3 2024 The Global Operating Environment for Bu...The APCO Geopolitical Radar - Q3 2024 The Global Operating Environment for Bu...
The APCO Geopolitical Radar - Q3 2024 The Global Operating Environment for Bu...
 
How are Lilac French Bulldogs Beauty Charming the World and Capturing Hearts....
How are Lilac French Bulldogs Beauty Charming the World and Capturing Hearts....How are Lilac French Bulldogs Beauty Charming the World and Capturing Hearts....
How are Lilac French Bulldogs Beauty Charming the World and Capturing Hearts....
 
Industrial Tech SW: Category Renewal and Creation
Industrial Tech SW:  Category Renewal and CreationIndustrial Tech SW:  Category Renewal and Creation
Industrial Tech SW: Category Renewal and Creation
 
Income Tax exemption for Start up : Section 80 IAC
Income Tax  exemption for Start up : Section 80 IACIncome Tax  exemption for Start up : Section 80 IAC
Income Tax exemption for Start up : Section 80 IAC
 
Creative Web Design Company in Singapore
Creative Web Design Company in SingaporeCreative Web Design Company in Singapore
Creative Web Design Company in Singapore
 
Unveiling the Dynamic Personalities, Key Dates, and Horoscope Insights: Gemin...
Unveiling the Dynamic Personalities, Key Dates, and Horoscope Insights: Gemin...Unveiling the Dynamic Personalities, Key Dates, and Horoscope Insights: Gemin...
Unveiling the Dynamic Personalities, Key Dates, and Horoscope Insights: Gemin...
 
2022 Vintage Roman Numerals Men Rings
2022 Vintage Roman  Numerals  Men  Rings2022 Vintage Roman  Numerals  Men  Rings
2022 Vintage Roman Numerals Men Rings
 
How to Implement a Real Estate CRM Software
How to Implement a Real Estate CRM SoftwareHow to Implement a Real Estate CRM Software
How to Implement a Real Estate CRM Software
 
Lundin Gold Corporate Presentation - June 2024
Lundin Gold Corporate Presentation - June 2024Lundin Gold Corporate Presentation - June 2024
Lundin Gold Corporate Presentation - June 2024
 

APM QSRA webinar; introduction for risk and planning professionals and decision makers

  • 1. QSRA: Introduction for risk/planning professionals and decision-makers Tony McDonald James Kimmance Graham Nicol
  • 2. Welcome and Introduction • Welcome on behalf of the Risk & PMC SIGs • Today’s presenters – Tony McDonald, Costain – James Kimmance, Jacobs – Graham Nicol, Turner and Townsend • Many thanks to Maya and Anna from APM and members of both SIGs • Risk SIG Conference 2019 - Using Risk to Influence the Future (26 Mar 19 in Birmingham)
  • 3. Why is QSRA best practice and what do decision- makers need from it? • QSRA answers 3 key questions concerning overrunning project schedules – Can overruns be predicted with some degree of accuracy? – Can causes of risk be identified upfront, helping project to stop them happening through effective response actions? – Can risk professionals determine causes of why projects frequently overrun their initial schedules? • Overwhelmingly the answer is yes! • Addresses head-on the fact that don’t know how long activities will take • Allows investigation of activity ‘uncertainty’ to establish its effects on a project schedule – How likely is the project to achieve the key dates & milestones in the schedule? – How much schedule contingency is needed to provide acceptable degree of certainty? – Where is the greatest risk in the schedule? • QSRA outputs provide a strong indication to key decision-makers of the key activities and risks that will impact the project if not managed correctly project References: ‘Practical Schedule Risk Analysis’ Hulett, David 2009’
  • 4. QSRA is based on a good project schedule • Scheduling is a challenging discipline • Vital that a project’s risk and scheduling functions work closely together to conduct QSRA, fully involving project managers/decision-makers from the start – Build high-level analysis network derived from the project schedule – Utilise schedulers knowledge of project schedule to ensure that all areas are explored for potential risk • QSRA high-level analysis network ‘criteria’ – Left-to-right, logic driven – ‘Finish-to-Start’ or ‘Start-to-Finish’ predecessors & ‘Finish-to-Start’ or ‘Finish-to-Finish’ successors – Not a ‘rolled up’ project schedule – Overall activity durations/dates match project schedule – Minimal/no use of constraints especially Late-Date constraints – No dangling logic ‘danglers’ – Minimal/no use of lag/leads(‘negative lag’) References: ‘Practical Schedule Risk Analysis’ Hulett, David 2009’
  • 6. Content • Introduction • A Simplified QSRA Process • Project Uncertainty and Risk • Cautionary observations • The benefits The biggest uncertainty in risk analysis is whether we started off analysing the right thing and in the right way
  • 7. Introduction- QSRA objectives • Quantitative Schedule Risk Analysis primarily used to: – provide risk based confidence forecasts of key milestones – support quantification of a projects schedule (and cost) contingency requirements – ......also drives other ‘good’ project behaviours
  • 8. Introduction (contd) • A wide variety of tools are available: • Oracle PRA / Acumen Fuse Risk/ Safran Risk • A large volume of quality literature and guides are available • Hulett, Hillson, GAO (USA), APM etc • Aim is to provide a: – ‘Quick Start’ introduction – Do’s, Maybe’s and Don’ts
  • 9. A Simplified QSRA Process • Key simplified stages – appear straightforward Schedule Preparation Assign Activity Uncertainty MapRisk(s) toActivities ApplyRisk Correlations Incorporate Probabilistic Branching Apply Weather Risk Schedule Health Check Run Analyses Review Analyses andModel Interpretive Report * Not covered here
  • 10. Maybe Not That Simple • Schedule suitable for QSRA may need a ‘logic’ rework: – Constraints (e.g. expected finish); lags etc – Size/level ideally 200 – 500 activities, but 2000 possible • Many things in ‘Risk’ are intuitively understood - but in practice need clarification. Risk and Uncertainty are two terms that often lack clarity, consistency in application, and are often confused / seen as interchangeable. Schedule Preparation Assign Activity Uncertainty MapRisk(s) toActivities
  • 11. Risk & Uncertainty • A lot has been written in the Project (Risk) Management space differentiating between Risk & Uncertainty • Defining Risk • Many ‘variations’ – but on a theme with a large consistency • APM PMBOK.. ‘an uncertain event or condition that, if it occurs, has a positive or negative effect on the project objective’ • Typically: event based; quantifiable with probabilities of occurrence; and impact on the project
  • 12. Risk & Uncertainty (contd.) • Defining Uncertainty…. • Uncertainty definitions in Project Management are less ubiquitous and more nebulous • “Uncertainty is a lack of certainty”; …….”uncertainty is understood in its most basic form as not knowing for sure, due to lack of information or ambiguous information”;………… • Common themes are: absence of information; unknowing; variability; ambiguity; and lack of clarity; a degree of ‘randomness’ about an average
  • 13. Risk vs. Uncertainty • For practical day to day purposes: – A risk is a discrete event with a probability of occurrence. The risk effect is only felt if the event occurs – Uncertainty is an occurrence that has no probability, and you know that you don’t know the actual value • Effectively a normal activity i.e. – but for which there is an inherent ‘variability’ caused by a variety of factors • The variability can be captured as a range based on ‘experience’
  • 14. Creating the model and data • Key players are the Scheduler, Risk Manager, Subject Matter Experts, and Project Managers – Review and amend the schedule with logic in mind (using schedule health check tool) – Estimate activity uncertainty • Individual activities – SME knowledge and experience – or maybe even data sets from similar activities • Possibly in groups of similar activities (quick templating) for example Civils, M&E, ICT, New Technology, Integration and Commissioning
  • 15. Creating the model and data (contd.) – Determine and map schedule impacting risks • Assumptions analysis – capture necessary risks • Review existing risk register • Determine probabilities, and distribution type – Typically Triangular, or Trigen, Uniform and BetaPert • Map to activities in the schedule model • Doing this properly requires significant resources • But there are significant benefits – at all stages of the project
  • 16. Cautionary Observations • The schedule and uncertainty data are the key building blocks upon which the QSRA relies: • Don’t skimp on creating a suitably sized schedule, with logic suitable for an analysis • Look for and capture assumptions • Prepare, and then challenge activity uncertainty with SME’s • Risks • Don’t just ‘drag and dump’ risks from a general risk register into the model
  • 17. Cautionary Observations (contd.) • With a QSRA model - do not • Leave the process until last / when you have a ‘finished’ schedule – It will be rushed / tick box exercise – You will not get many of the benefits of investing – May suggest you have a ‘potential’ nightmare (typically just before you have to submit for finding approval) • Miss out the SME’s and PM’s because they are ‘busy’ • Try to ‘game’ the result – Often reflected in some strange outputs and reports
  • 18. Benefits • QSRA’s can be resource consuming so maximising benefits are important. • Even at an early stage: – Overruns can be associated with a lack of in depth analysis / challenge at the planning (or even bidding) stage. When we can more easily change things……….. – Unrealistic or overly optimistic plans identified. – Going through the process can identify what you don’t know (and need to focus on) as much as what you think you know.
  • 19. Benefits (contd.) • Subsequent stages • We identify those activities and risks which are having the biggest impact on our schedule (and costs) • Prioritise and support the development of mitigation activities
  • 21. Interpretation of QSRA Outputs • The interpretation of QSRA Outputs and how they are reported is probably the most critical aspect of the QSRA process • A lot of work will have gone into producing the outputs • However, the QSRA outputs can be extremely sensitive if presented without context or without challenge!
  • 22. Challenges with QSRA Outputs • Key messages can often be hidden away in lengthy QSRA reports • Single Pnumbers i.e P50 confidence – Date ‘X’ don’t actually inform a decision • Decision makers struggle to grasp what QSRA outputs are telling them and the value of the QSRA process is often lost on them • Often Practitioners can’t explain what’s driving the analysis or what’s gone into the model
  • 23. Interpretation of QSRA Outputs- Back to Basics • Why do QSRAs in the first place? – Inform contingency discussions/arrangements – Provide confidence and assurance regarding schedule assumptions and integrity – Identify key risks to delivery and highlight sensitive areas within the project schedule – Provides a range of outcomes – Model various scenarios
  • 24. Risk Practitioner Questions to Ask… When questioned by decision makers/senior management re. QSRA outputs…can I: – Detail the quality of inputs that went into the model i.e. management signed off schedules, uncertainty and risk inputs – Outline what scenarios have been modelled and any assumptions and exclusions – Demonstrate that the QSRA process was iterative and involved all key stakeholders – Agree what are the base dates, milestones etc in the schedule that the QSRA outputs should be compared against…doesn’t always have to just be the end date!
  • 25. QSRA Outputs-Distribution Outputs (Pre-Mit) Pre-mitigated position (assuming no mitigation in place or effective) 1% chance of hitting the base date (Gold arrow) P50 output (Blue arrow)- 10/04/2024…some 534 days after base date!
  • 26. QSRA Outputs-Distribution Outputs (Post-Mit) Post- mitigated position (assuming identified mitigation successful!) 26% chance of hitting the base date (Gold arrow) P50 output (Blue Arrow)- 25/07/2023…now 274 days after base date an improvement of 260 days!
  • 27. QSRA Outputs - Distribution Analyser Plan Outcomes with Uncertainty and Pre-Mitigated RiskPlan Outcomes with Uncertainty and Post- Mitigated Risk Potentially 260 days saving if the proposed mitigations are successful at P50!
  • 28. QSRA Outputs - Tornado Graphs What’s causing these top 2 risks to drive the QSRA model? Why are delivery to site activities so sensitive to uncertainty and risk?
  • 29. QSRA Outputs – Scatter Graphs
  • 30. Interpretation of QSRA Outputs • Be clear on what has gone into the model in terms of quality inputs • Present ranges rather than Single Pnumbers… – P50 date is ‘X’ but considering the P75 output would give an additional 2 weeks time risk allowance? • Present the delta of the analysis compared to base data • Be clear on pre and post-mitigated positions – Why are certain risks more prominent than others? – What drives reduction in exposure? – Are mitigations robust to merit the reduction in exposure?
  • 33. This presentation was delivered at an APM webinar To find out more about upcoming webinars please visit our website www.apm.org.uk/events