Establishing exclusion zones • Personnel in area • Unauthorized access to test area;
• Workers struck by flying materials;
• Worker struck by High pressure water release;
Signage to test area • Personnel in area • Unauthorized access to test area;
• Inadequate signage to test area;
Pressure testing • High pressure to pipework; • Uncontrolled Stored Energy release;
• Rupture/failure in Pipe lines during testing;
• Valve/connection failure;
• Instrument failure resulting in system over-pressurization;
• End caps/plugs ejecting under high pressure;
• Weld/seal/fitting failure, flying objects;
• High pressure water/air injection.
Emergency procedures • High pressure to pipework; • Emergency procedures not briefed to task workers;
• Poor response in the event of an emergency;
Re-testing in the event of failure • Re-testing with high pressure • Injury due to uncontrolled testing;
• Worker injury due to working on pressurized system;
• Injury due to failure to ensure adequate pre-checks undertaken;
Establishing exclusion zones • Personnel in area • Unauthorized access to test area;
• Workers struck by flying materials;
• Worker struck by High pressure water release;
Signage to test area • Personnel in area • Unauthorized access to test area;
• Inadequate signage to test area;
Pressure testing • High pressure to pipework; • Uncontrolled Stored Energy release;
• Rupture/failure in Pipe lines during testing;
• Valve/connection failure;
• Instrument failure resulting in system over-pressurization;
• End caps/plugs ejecting under high pressure;
• Weld/seal/fitting failure, flying objects;
• High pressure water/air injection.
Emergency procedures • High pressure to pipework; • Emergency procedures not briefed to task workers;
• Poor response in the event of an emergency;
Re-testing in the event of failure • Re-testing with high pressure • Injury due to uncontrolled testing;
• Worker injury due to working on pressurized system;
• Injury due to failure to ensure adequate pre-checks undertaken;
Overhead crane, crane safety, lifting operation, EHS, Safety, Testing of Crane, Commissioning of Cranes,
for soft copy please email me at dawoodibrar@hotmail.com
Concrete Pump checks on arrival to site
PRIOR TO SITE ACCESS
Formwork for slab for temporary support
Falsework to provide temporary support to formwork
Rebar to slabs
Access of mobile pump and delivery trucks to work areas
Siting and setting up of concrete pump
Pumping concrete
(Pump Operator)
Pumping operation supervision
Dismantling of form-work
Striking of false-work
Project Fire Risk Assessment Report
(Quarterly) By: App: Project Relevant legislation:
• Federal Law No. 8 – Chapter 5 Article 92 ;
• DM Code of Construction Practice – Chapter 5;
• Regulation NO. 5 2009 Railways in the Emirate of Dubai (RED);
• Railway Protection Code of Practice (RWPCOP);
• UAE Fire and Life Safety Code of Practice – Chapter 12 (FLSCOP);
• Abu Dhabi Occupational Safety and Health Center – Code of Practise (OSHAD – CoP)
Issued: Rev.
Area: Assessment Date:
Next Assessment date:
Report compiled by:
Designation:
ASSESSMENT CRITERIA FIRE AND EMERGENCY CONTROL MEASURES AND LEGAL REQUIREMENTS RELEVANT LEGISLATION IMPLEMENTED PROJECT CONTROLS FOR COMPLIANCE COMMENTS FROM LAST FIRE ASSESSMENT
1. Site set up of temporary offices and cabins
Incl. Fire risk assessment; • Fire risk assessment undertaken on site set up and maintained/amended as project progresses;
• A copy of the fire risk assessment is maintained by HSE personnel;
• Separation distances between buildings under construction and construction-related structures, such as temporary offices, trailers, sheds, and other facilities for the storage of tools and materials having combustible construction or contents;
• No offices to be erected within the 70m Metro Protection Zone; FLSCOP Chapter 12 Table 12.1
RWPCOP
Section 4.6.1
DM Chapter 5.4
OSHAD CoP 8.0 & 43.0 •
2. Use of Portable gas heating or cutting equipment.
(all areas) • Ensure equipment is used in accordance with MAS and adequately maintained;
• Ensure suitable extraction is in place in confined areas and equipment is suitably maintained, extractors regularly maintained/cleaned;
• Ensure suitable fire- fighting equipment available nearby;
• Ensure use of Hot Works and Permits to Work as per section 5 and OSHAD CoP 21.0 and CoP 28.0;
• Ensure flashback arrestors fitted, hoses and connections sound and leak proof (as per inspection regime);
• Gas cylinder storage detailed in Section 7 and OSHAD CoP 49.0; FLSCOP Chapter 12 Section 7
DM Chapters 5, 15
OSHAD CoP 21.0, 28.0 & 49.0 •
3. Electrical equipment (portable and fixed installation)
• Portable electrical equipment to be tested every 6 months. Test stickers on appliances for date of last testing;
• Ensure fixed/temporary installations are checked by a competent person monthly and that this check is recorded and registered;
• Ensure that socket/DB outlets are not overloaded and connections are correct to standards;
• Correct rated fuses and breakers to be installed;
• DB’s to be waterproof and mounted on metal frames if on site;
• All site supply cables to be armoured;
• Install overhead cable frames where practicable in congested areas;
• Damaged equipment and cords shall be removed from service and quarantined until repaired or destroyed;
• Temporary lights shall not be suspended by their electrical cords unless such cords and lights have been designed for that purpose; FLSCOP Chapter 12 Section 14
DM Chapters 5.6, 16 & 17
O
9 Lifting Operations with Tower crane Risk Assessment Templates
Access of Tower crane sections to work areas
Tower crane foundations
Siting, setting up and testing of Tower crane
Lifting of equipment and material
(Tower crane Operator)
Tower Crane supervision
Jumping and dismantling of Tower Crane
2 Fire Risk Assessment Template Risk Assessment Templates
1. Site set up of temporary offices and cabins
Incl. Fire risk assessment;
2. Use of Portable gas heating or cutting equipment.
(all areas)
3. Electrical equipment (portable and fixed installation)
4. Smoking prevention, controls and arrangements within the Project
5. Hot Works activity controls
(Grinding, Welding, Cutting etc.)
6. Waste disposal: Combustible materials controlled and disposed of correctly.
(E.g. paper, cardboard plastics or wood.)
7. Storage of Flammable Gas within the project
(Acetylene, propane, butane, LPG etc.)
8. Flammable or highly flammable materials or substances on site and point of use.
(e.g. solvents, paints, adhesives, aerosols etc.)
9. Steps to reduce the potential sources of oxygen to a fire.
10. Any operations (or proposed) that may affect the Fire risk assessment
11. Clear access to electrical components and equipment.
12. Suspended ceilings within temporary buildings
(Offices, cabins etc.)
13. Alterations to structure and installations designed to prevent fire spread
14. Arson Prevention
(including security)
15. Smoke/heat detectors installed in high risk areas
16. Fire call points (break glass) installation.
17. Audible/visual fire alarms.
1. Project Information: (To be filled by initiator/originator)
Project Name: Permit No.:
Project Location:
Requesting Contractor/Company
2. Permit Issuance Details: (To be filled by initiator/originator)
THIS PERMIT IS ONLY FOR ONE SHIFT AND NOT EXTENDABLE
Description of Task:
Detail of Surroundings:
Permit Validity:
Time (from): __________Hrs.
Time (To): __________Hrs.
Date:
Type :
Work at height without guardrails
Work at height on fragile surfaces
3. Prerequisites: (To be filled by initiator/originator and verified by Evaluator) Yes-No-NA
Method Statement and Risk Assessment developed, approved and communicated? ☐ ☐ ☐
Area barricaded & proper signage are posted? ☐ ☐ ☐
Qualified and briefed workers? ☐ ☐ ☐
PPE of workers available & inspected as per MS/RA? ☐ ☐ ☐
Tools/Equipment inspected? ☐ ☐ ☐
Safe means of access/ Egress? ☐ ☐ ☐
Lifeline available and inspected? ☐ ☐ ☐
Fragile surface covered / work surface protected? ☐ ☐ ☐
Dimensions of platform and restrain lanyard match safety requirement? ☐ ☐ ☐
Harness with double lanyard provided and its use briefed to workforce? ☐ ☐ ☐
Harness anchorage point checked? ☐ ☐ ☐
Load bearing capacity of anchoring point checked? ☐ ☐ ☐
Load bearing capacity of fragile service checked? ☐ ☐ ☐
Emergency response procedure and rescue plan are developed & communicated? ☐ ☐ ☐
Others ( Specify) ☐ ☐ ☐
4. Acknowledgement by Initiator and Evaluator:
☐ Acknowledge that all above precautions have been taken. These have also been fully explained to the operatives, and I consider them competent to do it safely.
Initiator/Originator Name: Designation:
Signature: Date /Time:
☐ Acknowledge that I have checked above control measures and consider the work area safe to carry out the activity
Evaluator (HSE Team): Designation:
Signature: Date /Time
Comments (if any):
5. Authorization (PM/CM):
Name: Designation:
Signature: Date /Time:
6. Completion/Cancelation of Permit:
☐ Acknowledge that the area have been restored to a safe and orderly condition.
Initiator Signature: Time:
☐ Acknowledge that I have checked the area and been restored to a safe and orderly condition.
Evaluator Signature : Time:
An inherent physical or chemical characteristic that has the potential for causing harm to people, the environment, or property1
Hazards are intrinsic to a material, or its conditions of use
Examples
Hydrogen sulfide – toxic by inhalation
Gasoline – flammable
Moving machinery – kinetic energy, pinch points
At Wilcox Door, we understand the importance of a fully-functioning, safe loading dock area. Through our installation, maintenance and quality products, we'll help keep your shipping/receiving areas operating efficiently. Accessories such as dock lights, bumpers, shelters and truck restraints are also available.
After an extensive yet informative course, a project was created to demonstrate a learning experience. This assignment provides an opportunity for future lecturers and trainers in the professional business world to create an instructional design. Hopefully, this priceless experience will benefit others in a positive manner.
Overhead crane, crane safety, lifting operation, EHS, Safety, Testing of Crane, Commissioning of Cranes,
for soft copy please email me at dawoodibrar@hotmail.com
Concrete Pump checks on arrival to site
PRIOR TO SITE ACCESS
Formwork for slab for temporary support
Falsework to provide temporary support to formwork
Rebar to slabs
Access of mobile pump and delivery trucks to work areas
Siting and setting up of concrete pump
Pumping concrete
(Pump Operator)
Pumping operation supervision
Dismantling of form-work
Striking of false-work
Project Fire Risk Assessment Report
(Quarterly) By: App: Project Relevant legislation:
• Federal Law No. 8 – Chapter 5 Article 92 ;
• DM Code of Construction Practice – Chapter 5;
• Regulation NO. 5 2009 Railways in the Emirate of Dubai (RED);
• Railway Protection Code of Practice (RWPCOP);
• UAE Fire and Life Safety Code of Practice – Chapter 12 (FLSCOP);
• Abu Dhabi Occupational Safety and Health Center – Code of Practise (OSHAD – CoP)
Issued: Rev.
Area: Assessment Date:
Next Assessment date:
Report compiled by:
Designation:
ASSESSMENT CRITERIA FIRE AND EMERGENCY CONTROL MEASURES AND LEGAL REQUIREMENTS RELEVANT LEGISLATION IMPLEMENTED PROJECT CONTROLS FOR COMPLIANCE COMMENTS FROM LAST FIRE ASSESSMENT
1. Site set up of temporary offices and cabins
Incl. Fire risk assessment; • Fire risk assessment undertaken on site set up and maintained/amended as project progresses;
• A copy of the fire risk assessment is maintained by HSE personnel;
• Separation distances between buildings under construction and construction-related structures, such as temporary offices, trailers, sheds, and other facilities for the storage of tools and materials having combustible construction or contents;
• No offices to be erected within the 70m Metro Protection Zone; FLSCOP Chapter 12 Table 12.1
RWPCOP
Section 4.6.1
DM Chapter 5.4
OSHAD CoP 8.0 & 43.0 •
2. Use of Portable gas heating or cutting equipment.
(all areas) • Ensure equipment is used in accordance with MAS and adequately maintained;
• Ensure suitable extraction is in place in confined areas and equipment is suitably maintained, extractors regularly maintained/cleaned;
• Ensure suitable fire- fighting equipment available nearby;
• Ensure use of Hot Works and Permits to Work as per section 5 and OSHAD CoP 21.0 and CoP 28.0;
• Ensure flashback arrestors fitted, hoses and connections sound and leak proof (as per inspection regime);
• Gas cylinder storage detailed in Section 7 and OSHAD CoP 49.0; FLSCOP Chapter 12 Section 7
DM Chapters 5, 15
OSHAD CoP 21.0, 28.0 & 49.0 •
3. Electrical equipment (portable and fixed installation)
• Portable electrical equipment to be tested every 6 months. Test stickers on appliances for date of last testing;
• Ensure fixed/temporary installations are checked by a competent person monthly and that this check is recorded and registered;
• Ensure that socket/DB outlets are not overloaded and connections are correct to standards;
• Correct rated fuses and breakers to be installed;
• DB’s to be waterproof and mounted on metal frames if on site;
• All site supply cables to be armoured;
• Install overhead cable frames where practicable in congested areas;
• Damaged equipment and cords shall be removed from service and quarantined until repaired or destroyed;
• Temporary lights shall not be suspended by their electrical cords unless such cords and lights have been designed for that purpose; FLSCOP Chapter 12 Section 14
DM Chapters 5.6, 16 & 17
O
9 Lifting Operations with Tower crane Risk Assessment Templates
Access of Tower crane sections to work areas
Tower crane foundations
Siting, setting up and testing of Tower crane
Lifting of equipment and material
(Tower crane Operator)
Tower Crane supervision
Jumping and dismantling of Tower Crane
2 Fire Risk Assessment Template Risk Assessment Templates
1. Site set up of temporary offices and cabins
Incl. Fire risk assessment;
2. Use of Portable gas heating or cutting equipment.
(all areas)
3. Electrical equipment (portable and fixed installation)
4. Smoking prevention, controls and arrangements within the Project
5. Hot Works activity controls
(Grinding, Welding, Cutting etc.)
6. Waste disposal: Combustible materials controlled and disposed of correctly.
(E.g. paper, cardboard plastics or wood.)
7. Storage of Flammable Gas within the project
(Acetylene, propane, butane, LPG etc.)
8. Flammable or highly flammable materials or substances on site and point of use.
(e.g. solvents, paints, adhesives, aerosols etc.)
9. Steps to reduce the potential sources of oxygen to a fire.
10. Any operations (or proposed) that may affect the Fire risk assessment
11. Clear access to electrical components and equipment.
12. Suspended ceilings within temporary buildings
(Offices, cabins etc.)
13. Alterations to structure and installations designed to prevent fire spread
14. Arson Prevention
(including security)
15. Smoke/heat detectors installed in high risk areas
16. Fire call points (break glass) installation.
17. Audible/visual fire alarms.
1. Project Information: (To be filled by initiator/originator)
Project Name: Permit No.:
Project Location:
Requesting Contractor/Company
2. Permit Issuance Details: (To be filled by initiator/originator)
THIS PERMIT IS ONLY FOR ONE SHIFT AND NOT EXTENDABLE
Description of Task:
Detail of Surroundings:
Permit Validity:
Time (from): __________Hrs.
Time (To): __________Hrs.
Date:
Type :
Work at height without guardrails
Work at height on fragile surfaces
3. Prerequisites: (To be filled by initiator/originator and verified by Evaluator) Yes-No-NA
Method Statement and Risk Assessment developed, approved and communicated? ☐ ☐ ☐
Area barricaded & proper signage are posted? ☐ ☐ ☐
Qualified and briefed workers? ☐ ☐ ☐
PPE of workers available & inspected as per MS/RA? ☐ ☐ ☐
Tools/Equipment inspected? ☐ ☐ ☐
Safe means of access/ Egress? ☐ ☐ ☐
Lifeline available and inspected? ☐ ☐ ☐
Fragile surface covered / work surface protected? ☐ ☐ ☐
Dimensions of platform and restrain lanyard match safety requirement? ☐ ☐ ☐
Harness with double lanyard provided and its use briefed to workforce? ☐ ☐ ☐
Harness anchorage point checked? ☐ ☐ ☐
Load bearing capacity of anchoring point checked? ☐ ☐ ☐
Load bearing capacity of fragile service checked? ☐ ☐ ☐
Emergency response procedure and rescue plan are developed & communicated? ☐ ☐ ☐
Others ( Specify) ☐ ☐ ☐
4. Acknowledgement by Initiator and Evaluator:
☐ Acknowledge that all above precautions have been taken. These have also been fully explained to the operatives, and I consider them competent to do it safely.
Initiator/Originator Name: Designation:
Signature: Date /Time:
☐ Acknowledge that I have checked above control measures and consider the work area safe to carry out the activity
Evaluator (HSE Team): Designation:
Signature: Date /Time
Comments (if any):
5. Authorization (PM/CM):
Name: Designation:
Signature: Date /Time:
6. Completion/Cancelation of Permit:
☐ Acknowledge that the area have been restored to a safe and orderly condition.
Initiator Signature: Time:
☐ Acknowledge that I have checked the area and been restored to a safe and orderly condition.
Evaluator Signature : Time:
An inherent physical or chemical characteristic that has the potential for causing harm to people, the environment, or property1
Hazards are intrinsic to a material, or its conditions of use
Examples
Hydrogen sulfide – toxic by inhalation
Gasoline – flammable
Moving machinery – kinetic energy, pinch points
At Wilcox Door, we understand the importance of a fully-functioning, safe loading dock area. Through our installation, maintenance and quality products, we'll help keep your shipping/receiving areas operating efficiently. Accessories such as dock lights, bumpers, shelters and truck restraints are also available.
After an extensive yet informative course, a project was created to demonstrate a learning experience. This assignment provides an opportunity for future lecturers and trainers in the professional business world to create an instructional design. Hopefully, this priceless experience will benefit others in a positive manner.
Fitness-For-Service (FFS) assessments are quantitative engineering evaluations that are performed to demonstrate the structural integrity of an in-service component that may contain a flaw or damage.
PetroSync with Mr. Mandar Mulay organizing a 5 days training on ASME VIII Division 1 & 2 - Pressure Vessel Series. ASME VIII Div. 1 is the most commonly adopted code which is simple and used friendly, where as, ASME VIII Div 2 is an alternative code which provides a better engineered vessel with detailed stresses calculations and more rigorous testing, and allows for savings in material costs (thinner parts may be used).
Asme section viii division 1 and 2 pressure vessel series ( CONFIRM RUN )Putri Kolopaking
ASME Section VIII Division 1 & 2 – Pressure Vessel Series
11th - 15th September 2017, Bandung - Indonesia
20th – 24th November 2017, Kuala Lumpur, Malaysia
PetroSync together with Mr. Mandar Mulay, organizing a 5 days training on ASME Section VIII Division 1 & 2 – Pressure Vessel Series. This Five-day program offers detailed insight and thorough understanding of the most common ASME codes, pertaining to design/ engineering and testing of the pressure vessels namely Section VIII Div. 1 and Section VIII Div. 2. This course emphasizes understanding of ‘stated’ and ‘implied’ requirements (i.e. content and intent) of the codes. The participants would be explained in detail the mechanics of adopting and applying the code rules and design formulas for different Design conditions and Services.
Objectives:
• Familiarize participants with the concepts and technical terms of the codes
• Design for external pressure and Jacketed vessels
• Discover the fabrication requirements, assembly and welding requirements.
• How to carry out pressure testing, certification and stamping of Pressure Vessels.
• Understand salient features and differences between Div 1 and Div 2
CLICK HERE TO SEE THE BROCHURE
Who should join:
The course is designed for, but not limited to, mechanical, maintenance, and inspection / QAQC professionals who are involved in pressure vessel equipment:
• Design Engineers / Managers
• Mechanical Engineers / Managers
• Maintenance Engineers / Managers
• QAQC Engineers / Managers
• Inspection Engineers / Managers
• Reliability Engineers / Managers
Our Expert Speaker:
Mandar Mulay has about 20 years hands on experience in design and integrity assessment of Piping Systems, Reactors & Storage Tanks, Pressure Vessels, Power Boiler, and Heat Exchanger. He is well conversant with the major industry codes & standards such as ASME Sec. I, ASME B 31.1, B31.3 , B31.4 and B31.8, ASME Sec VIII, BS-5500, TEMA, API -650, IS 803, API 579, ASME PCC-2 etc. He has also conducted several Training Courses ( ASME Sec. I, ASME Sec. VIII, ASME B 31.3 Piping Codes , API 579 FFS code, ASME PCC-2 Repair practices, and Heat Exchanger Design Operations & Maintenance ) in Saudi Arabia, Qatar, Bahrain and UAE for engineers from companies like Saudi Aramco, SABIC group of Companies, Qatar Petroleum, ADNOC, BAPCO, DEWA, Gulf Petrochemicals etc. He has already conducted many times the training courses in API 579, where the participants rated him “Excellent” for these courses.
Presentation by Richard Miller at the Single Ply Roofing Association Conference 2019 at Heythrop Park, Oxfordshire.
More information:https://spra.co.uk/events/spra-awards-2019-live-blog/
A joint program between industry, agency & academia to test and certify material testers in California to ensure they meet minimum qualifications. Presentation delivered during the CalAPA Fall Asphalt Pavement Conference Oct. 26-27, 2016 in Sacramento, Calif.
Using Mahara ePortfolios for Vocational Industry CurrencyMahara Hui
Presentation at Mahara Hui 2017 by Christine Nicholas (Gouldburn Ovens Institute of TAFE) in Auckland, New Zealand, on 6 April 2017.
YouTube presentation link can be found here: https://youtu.be/VyHRyGWBJ98
Optimizing Gas Turbines and Life ManagementWalter Lee
A practical and comprehensive course on condition & life
assessments for gas turbines with the aim of improving gas
turbine operational & maintenance practices, minimizing
the likelihood of failures, prolonging asset life & reducing
maintenance costs.
PetroSync - API 570 Piping Inspector coursePetroSync
Piping Inspection Code 570 Inspection, Repair, Alteration, and Rerating of In-Service Piping Systems is recognized and used with confidence worldwide. The Piping Inspector Certification Program (PICP) is developed for the continual high level of efficiency and safety through emphasizing professional credibility and process integrity.
The South Arkansas STEPS meeting on April 5 at Bonanza Creek in Magnolia featured a presentation on trenching and excavation from Brian Monistere, with Professional Safety Services, based in Mississippi.
A process server is a authorized person for delivering legal documents, such as summons, complaints, subpoenas, and other court papers, to peoples involved in legal proceedings.
This session provides a comprehensive overview of the latest updates to the Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (commonly known as the Uniform Guidance) outlined in the 2 CFR 200.
With a focus on the 2024 revisions issued by the Office of Management and Budget (OMB), participants will gain insight into the key changes affecting federal grant recipients. The session will delve into critical regulatory updates, providing attendees with the knowledge and tools necessary to navigate and comply with the evolving landscape of federal grant management.
Learning Objectives:
- Understand the rationale behind the 2024 updates to the Uniform Guidance outlined in 2 CFR 200, and their implications for federal grant recipients.
- Identify the key changes and revisions introduced by the Office of Management and Budget (OMB) in the 2024 edition of 2 CFR 200.
- Gain proficiency in applying the updated regulations to ensure compliance with federal grant requirements and avoid potential audit findings.
- Develop strategies for effectively implementing the new guidelines within the grant management processes of their respective organizations, fostering efficiency and accountability in federal grant administration.
Presentation by Jared Jageler, David Adler, Noelia Duchovny, and Evan Herrnstadt, analysts in CBO’s Microeconomic Studies and Health Analysis Divisions, at the Association of Environmental and Resource Economists Summer Conference.
Understanding the Challenges of Street ChildrenSERUDS INDIA
By raising awareness, providing support, advocating for change, and offering assistance to children in need, individuals can play a crucial role in improving the lives of street children and helping them realize their full potential
Donate Us
https://serudsindia.org/how-individuals-can-support-street-children-in-india/
#donatefororphan, #donateforhomelesschildren, #childeducation, #ngochildeducation, #donateforeducation, #donationforchildeducation, #sponsorforpoorchild, #sponsororphanage #sponsororphanchild, #donation, #education, #charity, #educationforchild, #seruds, #kurnool, #joyhome
Russian anarchist and anti-war movement in the third year of full-scale warAntti Rautiainen
Anarchist group ANA Regensburg hosted my online-presentation on 16th of May 2024, in which I discussed tactics of anti-war activism in Russia, and reasons why the anti-war movement has not been able to make an impact to change the course of events yet. Cases of anarchists repressed for anti-war activities are presented, as well as strategies of support for political prisoners, and modest successes in supporting their struggles.
Thumbnail picture is by MediaZona, you may read their report on anti-war arson attacks in Russia here: https://en.zona.media/article/2022/10/13/burn-map
Links:
Autonomous Action
http://Avtonom.org
Anarchist Black Cross Moscow
http://Avtonom.org/abc
Solidarity Zone
https://t.me/solidarity_zone
Memorial
https://memopzk.org/, https://t.me/pzk_memorial
OVD-Info
https://en.ovdinfo.org/antiwar-ovd-info-guide
RosUznik
https://rosuznik.org/
Uznik Online
http://uznikonline.tilda.ws/
Russian Reader
https://therussianreader.com/
ABC Irkutsk
https://abc38.noblogs.org/
Send mail to prisoners from abroad:
http://Prisonmail.online
YouTube: https://youtu.be/c5nSOdU48O8
Spotify: https://podcasters.spotify.com/pod/show/libertarianlifecoach/episodes/Russian-anarchist-and-anti-war-movement-in-the-third-year-of-full-scale-war-e2k8ai4
Jennifer Schaus and Associates hosts a complimentary webinar series on The FAR in 2024. Join the webinars on Wednesdays and Fridays at noon, eastern.
Recordings are on YouTube and the company website.
https://www.youtube.com/@jenniferschaus/videos
Jennifer Schaus and Associates hosts a complimentary webinar series on The FAR in 2024. Join the webinars on Wednesdays and Fridays at noon, eastern.
Recordings are on YouTube and the company website.
https://www.youtube.com/@jenniferschaus/videos
What is the point of small housing associations.pptxPaul Smith
Given the small scale of housing associations and their relative high cost per home what is the point of them and how do we justify their continued existance
PPT Item # 9 - 2024 Street Maintenance Program(SMP) Amendment
ANSI/ASSE Z390.1 H2S Changes
1. ANSI/ASSE Z390.1 – 2017 Accepted
Practices for Hydrogen Sulfide (H2S)
Training Programs
Changes
PRESENTED BY:
RICHARD EMBERLING, COSS
SENIOR AUDIT,TRAINING & DEVELOPMENT SPECIALIST
PEC SAFETY
2. Brief History of the Committee
•The Committee was formed in 1993, and the
ANSI/ASSE Z390.1 Standard has consistently
been one of ANSI’s most valued publications.
•The guidelines in ANSI/ASSE Z390.1 establish
content and instructional practices for training
personnel with potential exposure to
hydrogen sulfide (H2S).
Arkansas STEPS Network 8-17-2017 2
3. Brief History of the Committee
• The Standard includes detailed training
recommendations concerning H2S properties and
characteristics, respiratory protection, gas
detection, emergency response, and more.
• These guidelines are used extensively in the oil and
gas industry, in petrochemical operations, and in a
variety of other industries worldwide.
Arkansas STEPS Network 8-17-2017 3
4. ANSI Z-390.1 Hydrogen Sulfide
Training Requirements
Arkansas STEPS Network 8-17-2017
•Little changed since initial adoption
•Last formal revision 2006
•Latest revision is comprehensive
• User friendly
• Less prescriptive
• Tackles changing safe exposure levels
4
5. Committee Priorities
•Protect the safety and health of workers
•Minimize the burden on industry to the extent
possible
•When in conflict, default to protecting
workers
Arkansas STEPS Network 8-17-2017 5
6. Why Revision?
Arkansas STEPS Network 8-17-2017 6
Oilfield / Petrochem
focus
References to
obsolete instructional
technology and
resources
Required
presentation of
material not
pertinent to most
workers
7. Why Revision?
Arkansas STEPS Network 8-17-2017
7
Structure and
content in need of
editorial
improvement
Uneasiness with
Visitor Training
Uneasiness with
abbreviated
Refresher
8. Oilfield / Petrochem Focus
•Curriculum included oilfield / Petrochem
subjects
•Failed to consider non-oilfield hazards
•New sections added to address research lab
training
•Future revisions will likely address other
industry’s training issues
Arkansas STEPS Network 8-17-2017 8
10. Editorial Improvement of Document
•Changed to single column format
•Eliminated redundant material
•Eliminated dated references
•Improved logical flow of the paragraph
structure
Arkansas STEPS Network 8-17-2017 10
11. What is in the Standard?
• Section 1. - SCOPE, PURPOSE, AND APPLICATION
• Section 2. – Definitions
• Section 3. -Training Criteria for H2S Certification
• Section 4. - Required Course Content
• Section 5. - Instructor Qualification and Proficiency
• Section 6. - Documentation and Recordkeeping
• Section 7. - Student Competency and Qualification
Arkansas STEPS Network 8-17-2017 11
12. What is in the Standard?
• Section 8. -TrainingTechniques, Language and Literacy Factors
• Section 9. – Related Standards
• Appendix A - Occupations with Potential H2S Exposure
• Appendix B -TrainingTechniques, Language and Literacy Factors
• Appendix C – Sample Certification Course Outline
• Appendix D – Site SpecificTraining forWorking above the
Occupational Exposure Limit of H2S
• Appendix E - Site SpecificTraining for H2S in Laboratories and
EnclosedWork Areas
Arkansas STEPS Network 8-17-2017 12
13. What has changed in the Standard?
Arkansas STEPS Network 8-17-2017 13
14. 2.16Visitor
An individual who is visiting a job site for a
short period of time, and who is not required to
provide any of the operational or control
activities at the site.
Visitors are not exempt from the initial and
annual H2S training.
Arkansas STEPS Network 8-17-2017 14
15. 2.16Visitor
•Visitor training eliminated as a abbreviated
course
•Visitors must receive the full worker training
program
•You’re either exposed or you’re not…….
•This is the one area of the revision that is
significantly stricter
Arkansas STEPS Network 8-17-2017 15
16. 3.TRAINING CRITERIA for H2S
Certification
•Designed for individuals who have the
potential to be exposed to H2S in
concentrations greater than the Occupational
Exposure Limit.
•All of the objectives in Appendix C shall be
met.
Arkansas STEPS Network 8-17-2017 16
17. 3.TRAINING CRITERIA for H2S
Certification
•This certification training should be a
minimum of 3-4 hours in length.
Arkansas STEPS Network 8-17-2017 17
18. 3.TRAINING CRITERIA for H2S
Certification
•The certification is valid for a period of 1
year.
•A H2S Certification card stating ANSI Z390.1-
2017 compliant shall be presented to the
attendee.
•Retraining shall include all of the information
contained in 3.2.
Arkansas STEPS Network 8-17-2017 18
19. 3.TRAINING CRITERIA for H2S
Certification
• Personnel subject to working under respiratory
protection, shall also have successfully completed a
respiratory protection training program, to
include medical evaluation and fit-testing if they are to
wear tight-fitting air supplied respirators in these
hazardous atmospheres according toANSI Z88
and/or OSHA CFR 1910.134 or applicable local
regulatory requirements.
Arkansas STEPS Network 8-17-2017 19
20. 3.3 Minimum Course Content for H2S
Train theTrainer
•Course content shall include sufficient
instruction to assure competency with
regard to the topics required in the H2S
certification.
Arkansas STEPS Network 8-17-2017 20
21. 3.3 Minimum Course Content for H2S
Train theTrainer
• Additionally, the student shall receive adequate
instruction on the following topics from Criteria for
Accepted Practices in Safety Health and Environmental
Training (Z490.1)
• Training Program Administration and Management
• Training Development
• Training Delivery
• Training Evaluation
• Documentation and Record Keeping
Arkansas STEPS Network 8-17-2017 21
22. 3.4 Minimum Requirements for Site
Specific Orientation
•In addition to the annual H2S Certification
training, a Site Specific Orientation is
required for individuals who have the potential to
be exposed to H2S in concentrations greater than
the Occupational Exposure Limit. At a minimum,
personnel shall be briefed on;
• Route(s) of egress,
• Use and location of wind indicators
• Emergency assembly area(s),
Arkansas STEPS Network 8-17-2017 22
23. 3.4 Minimum Requirements for Site
Specific Orientation
• Applicable warning signals,
• How to respond in the event of an emergency,
• Use and location of personal protective
equipment
•Hands-on training with the specific H2S
detector to be used in the field is required prior
to use (HANDOUT see Appendix D pg.3)
Arkansas STEPS Network 8-17-2017 23
24. 4. Required Course Content
•Section 4. deals with the course content
(HANDOUT see Appendix C pg. 1 )
Arkansas STEPS Network 8-17-2017 24
25. 5. INSTRUCTOR QUALIFICATION AND
PROFICIENCY
•Completed an appropriate H2STrain-the-
Trainer development course
•Deemed qualified if they possess significant
past experience in instructing in this field
Arkansas STEPS Network 8-17-2017 25
26. 5. INSTRUCTOR QUALIFICATION AND
PROFICIENCY
•The instructors shall be able to demonstrate
his/her knowledge of the technical aspects of
H2S training and proficiency in training
techniques relating to H2S.
•Training credentials or certification from a
recognized or accredited training
authority constitutes qualification under this
section.
Arkansas STEPS Network 8-17-2017 26
27. 5. INSTRUCTOR QUALIFICATION AND
PROFICIENCY
•H2S instructors should conduct a minimum of
two H2S training classes each year.
Documentation should be maintained to
substantiate evidence of these sessions.
•As a minimum, instructors shall participate
in an H2S instructor refresher course every
three years.
Arkansas STEPS Network 8-17-2017 27
28. 6. DOCUMENTATION AND
RECORDKEEPING
• 6.3 Certification Card. A certification card shall
be provided, which shall include, but not limited
to, the following to include the:
• Name of the student
• Date of training
• Name of the training provider with which the
instructor is affiliated
•Statementthat the program conformsto
ANSI Z390.1 -2017
Arkansas STEPS Network 8-17-2017 28
29. 7. STUDENT COMPETENCY AND
CERTIFICATION
• Documented proof of student competency shall be
required at the end of the training in order to receive
certification.
• Common forms of performance-based evaluation
include written tests and where applicable,
documented skills demonstration.
• Due to the extreme hazard involved in H2S operations,
each individual covered by this standard shall be
retrained annually.
Arkansas STEPS Network 8-17-2017 29
30. 8.TRAININGTECHNIQUES, LANGUAGE
AND LITERACY FACTORS
• CertificationTraining shall always be delivered by
a qualified instructor in an appropriate and
organized teaching space, safe and free from
hazardous conditions and other requirements as
required in ANSI 490.
• H2S training shall be delivered in a language that
ensures student comprehension
Arkansas STEPS Network 8-17-2017 30
32. Contact Information
Richard Emberling, COSS
Senior AuditTraining & Development Specialist,
PEC Safety
D 580-364-8022 M 337-356-5489
Email - remberling@pecsafety.com
Arkansas STEPS Network 8-17-2017 32