SlideShare a Scribd company logo
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308
__________________________________________________________________________________________
IC-RICE Conference Issue | Nov-2013, Available @ http://www.ijret.org 390
ANALYSIS OF FACTORS CONTRIBUTING DELAYS AND CLAIMS IN
CONSTRUCTION PROJECTS
Ketki S. Kamble1
, A. R. Kambekar2
1
PG. Student, Const. Management, 2
Assistant Professor, CED, SPCE Andheri (W), Mumbai 400058, Maharashtra,
ketki08@gmail.com
Abstract
Construction activities are the most competitive and it involves higher risk with minimum profitability due to competition.
Construction of any infrastructural work involves complex management skills related to manpower, materials, plant, machineries,
new technologies etc. It also involves many agencies interdependent on each other like the planners, structural and functional
designers including various types of specialized engineers and it also includes support of financial institutions, insurers, contractors
and specialized contractors. As there are prevailing labour bye laws it needs special care of their well beings. In such kind of complex
and intense framework some disputes is quite natural between the agencies involved in such activities which further results in claims
management as the unsettled dispute finally leads to financial claims. Higher incidences of disputes are generally reported from the
construction contract. Even if there is an appropriate understanding of construction contract clauses from the agencies in the
agreement yet claims seems to be a major crisis in the construction sector. The research reported in this paper aims in identifying the
major factors responsible of project delay that may give rise to claims for delay damages. The in this paper research mainly highlights
on finding the major components of claims with perspective of contractor for delay damages.
Keywords: Claims, delay, damages, construction industry, disputes.
--------------------------------------------------------------------***---------------------------------------------------------------------
1. INTRODUCTION
Claims as per Hughes [1] “It is a demand, a request or
application for something to which a contractor considers,
believes or contends he is entitled but in respect of which
agreement has not yet been reached”. As per Harris [2] the
major five causes of disputes in Asian construction projects
are as follows:
• Failure to make interim awards on extensions of time
and to give associated compensation
• Unrealistic risk transfer from employers to
contractors
• Conflicting party interests
• An unrealistic contract completion date being defined
at tender stage
• Incomplete design information or employer
requirements.
In general it was reported in literature that the construction
sector involves disputes from the sources like changes which
includes variation, alteration, addition, deletion, delays and
suspensions, differing site conditions, unjust enrichment by
owners. It was also observed that there are five potential areas
which can give rise to disputes: document errors, estimation
errors, change in conditions, implied promises and agencies
involved. Claims however fall under two major categories
based on their occurrence i.e. during (i) execution of contract
and (ii) administration of contract. Execution of contract
includes claims due to change in design and drawing, delays in
handing over site/issuance of drawings/getting clearance
certificate from appropriate authorities, claims due to original
scope of work change, claims due to differing site conditions
and claims due to variation in methodology. Similarly during
administration of contract claims may be due to delay in
payment of running account bills and claims due to
foreclosure/termination of contract. Similarly delays in
schedules of construction projects are one of the most
common types of disputes in the construction industry. The
client and contractor works for a common objective i.e. to
complete the project within scheduled time as well as cost.
Time overrun is the most common failure of objective that in
turn leads to cost overrun and hence failure in the objective of
timely completion leads to failure of overall project budget
which ultimately gives rise to disputes. The reasons for delays
could be caused by client, contractor, force majeure i.e. act of
God, change in laws, rules and regulations, improper co-
ordination between client and contractors, non-availability of
required skilled labour, non-availability of required special
material, differing site conditions, non-issuance of working
drawing and changes in work leading to change in
methodology. Delays can be further classified as excusable or
non-excusable. Some of the practical cases of non-excusable
delays are incompetent sub-contractor, financial incompetency
of the contractor, labour disputes hindering work progress,
poor workmanship leading to rework, poor material quality
and delay in handing over the site by client and excusable
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308
__________________________________________________________________________________________
IC-RICE Conference Issue | Nov-2013, Available @ http://www.ijret.org 391
delay includes sudden floods, natural calamities like
earthquake, tsunami etc. riots, labour strike, non-foreseeable
situation. Critical delay are defined as a delay in any given
activity which results in delay of total project and non-critical
delay is defined as delays which may not upset total time
frame of the contract [1].
This paper mainly focuses on delay damage claims related to
additional cost incurred by the contractor due to delay caused
by the client. Evaluation of delay damages are when a
contractor bids for a tender, a number of factors are considered
apart from the labour, material and equipment that are
required to execute the work. In tender the duration required to
complete the work is generally mentioned and hence the
contractor quotes accordingly. The quote includes material
cost, labour cost, plant and machinery cost, shuttering
material, human resource cost, financial cost, site overheads
and above all profit. In an event of prolongation of contract,
the major factors that are affected are additional overheads,
plant and machinery, labour and material cost, loss of
productivity, loss of profit, loss of new business opportunities
and early mobilization.
2. METHODOLOGY ADOPTED
Following methodology is adopted for this research work.
This includes identification of claims that occur, factors
responsible for delay, prolongation claim if any, focus on
factors that are affected due to delay in completion the project,
factors mostly considered while setting up prolongation claim,
ranking based on case studies to understand the major factor
affecting the delay damages claim finally recommendations
based on the study. The delays which occur in construction
projects are due to various reasons. Analysis of three projects
have been carried out details of the same is given in Table 1.
Project cost, value of claims and claim in % of project cost for
(i) construction of mall in Mumbai, (ii) construction of hotel
and casino in Goa and (iii) construction of power transmission
tower in Raigad district of Maharashtra is considered in this
paper. The range of delay claims by contractor was in the
range of around 1.08 % to 400% of the project cost. This may
due to various reasons.
Table1. Analysis of delay damages in construction projects.
Sr. No
Project
description
Project
cost
(Lakhs
Rs.)
Value
of claim
(Lakhs
Rs.)
Claim
in % of
project
cost
1
Construction
of mall in
Mumbai.
4314 623.58 14.45%
2
Construction
of hotel and
casino in
Goa.
3494 37.68 1.08%
3
Construction
of power
transmission
tower
foundation
in Raigad
district.
12.43 49.64 400%
2.1 Project 1: Construction of Mall in Mumbai
Construction of a mall in Mumbai was taken as first case study
for delay claims. The project cost was around 4314 Lakhs Rs.,
claim amount by contractor was 623.58 Lakhs Rs. and delay
was almost of 7 months. Various reasons for claims observed
in this case includes the mainly due to delay in approved
drawings. The total built up area was around 6,77,000 Sq.ft.
and large quantity of MS shuttering material was required to
be deployed on site. Since the work was suspended in the
middle of project, the resources like staff, machinery was
demobilized and transferred to other project, but it was
difficult to transfer the shuttering material to other site since
the cost of transportation for demobilizing and again
mobilizing when the work resumes was observed as a
governing factor. Hence in this project 81% of Claim
constitutes for M.S Shuttering Material. Details of claim for
various reasons in % for project 1 are shown in Table 2. This
includes claims for MS shuttering material, labour, overheads
and machinery. Next section gives similar analysis for
construction of hotel and casino in Goa.
Table2 Details of claim for project 1
Sr.
No.
Description
Claim
amount
(In Lakhs
Rs.)
Claim
in % of
project
cost
Importance
as per
claim
amount
1
M.S.
Shuttering
Material
503.08 81% 1
2 Labour 58.24 9% 2
3 Overheads 47.50 8% 3
4 Machinery 14.75 2% 4
Total claim
(In Lakhs Rs.)
623.58
2.2 Project 2: Construction of Hotel and Casino in
Goa
The construction of hotel and casino in Goa was having
estimated project cost of 3494 Lakhs Rs. and the claim was
37.68 Lakhs Rs with delay of 1 month. It was noted that the
work order given shows the site mobilization within 15 days
and in the tender it was also mentioned the minimum staff
cadre and equipment needs to be deployed on site at the time
of mobilization. Table 3 gives details of claim for various
reasons in % for project 2 showing importance as per claim
IJRET: International Journal of Research in Engineering and Technolo
__________________________________________________________________________________________
IC-RICE Conference Issue | Nov-2013, Available @
amount. As per the conditions the contractor mobilized the s
with the required resources but there was a delay of 1 month
in handing over the site. In this case the amount of
M.S. shuttering material, overheads and machinery
same, since the claim was at the start of the project hence the
minimum resources were deployed. The third case study
includes the construction of power transmis
foundation in Raigad district detailed analysis is given in the
next section.
Table3. Details of claim for project 2.
Sr.
No.
Description
Claim
amount
(In
Lakhs
Rs.)
Claim in
% of
project
cost
1
M.S
shuttering
material
10.93 29%
2 Overheads 10.60 28%
3 Machinery 9.55 25%
4 Labour 6.60 18%
Total claim
(In Lakhs Rs.)
37.68
2.3 Project 3. Construction of Power Transmission
Tower Foundation in Raigad District
The scope of work in this case study was to construct RCC
power transmission tower foundation at
locations. Table 4 gives details of claim for project 3.
work was supposed to be executed after getting unhindered
land at all the four locations along with the necessary
9%
2% 8%
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319
__________________________________________________________________________________________
2013, Available @ http://www.ijret.org
ontractor mobilized the site
ut there was a delay of 1 month
this case the amount of claim for
achinery was almost
at the start of the project hence the
The third case study
includes the construction of power transmission tower
foundation in Raigad district detailed analysis is given in the
project 2.
Claim in
project
Importance
as per
claim
amount
1
2
3
4
Power Transmission
was to construct RCC
foundation at four different
Table 4 gives details of claim for project 3. The
to be executed after getting unhindered
along with the necessary
approvals from the local authorities. It was
that all four locations would
project. The duration of project was 45 days. The contractor
mobilized the site with adequate resources
of all the four location was not
working drawing was not issued
local authorities was not taken by the
cost was 12.43 Lakhs Rs., c
and the delay resulted the work to be completed in 14.5
months leading to total delay of
details of claims by contractor for project 1, 2 and 3 on various
elements of the respective projects.
Table4. Details of
Sr.
No.
Description
Claim
amount
(In
Lakhs
Rs.)
1 Labour 21
2
M.S
Shuttering
Material
10
3 Overheads 10
4 Machinery 6.
Total claim
(In Lakhs Rs.)
49
(a)
81%
8%
Project 1.
M.S. Shuttering Material
Labour
Machinery
Overheads
eISSN: 2319-1163 | pISSN: 2321-7308
__________________________________________________________________________________________
392
from the local authorities. It was also mentioned
ould be made available at the start of
project. The duration of project was 45 days. The contractor
mobilized the site with adequate resources but the possession
location was not allotted to the contractor. The
not issued and the permission from the
not taken by the client. The total project
Rs., claim amount was 49.64 Lakhs Rs.
sulted the work to be completed in 14.5
total delay of 13 months. Figure 1 shows
details of claims by contractor for project 1, 2 and 3 on various
elements of the respective projects.
Details of claim for project 3
Claim
amount
(In
Lakhs
Rs.)
Claim in
% of
project
cost
Importance
as per claim
amount
21.58 40% 1
10.79 20% 2
10.79 20% 2
.47 12% 3
49.64
M.S. Shuttering Material
IJRET: International Journal of Research in Engineering and Technolo
__________________________________________________________________________________________
IC-RICE Conference Issue | Nov-2013, Available @
Fig1. Details of claims by contractor for
CONCLUSIONS
The investigation in this work was to identify the major
factors responsible for project delay that may give rise to
claims for delay damages for three major projects of 1.
Construction of mall, 2. Construction of hotel and casino and
3. Construction of power transmission tower at various
locations of India. The main highlights in this study are to find
out the major components of claims with perspective of
contractor for delay damages. For mall project it can be seen
that M.S. shuttering material is most affected factor of delay
damages. This is because normally mall constructions are
wide spread and the area required for construction is more and
hence shuttering required to support the plywood is required in
huge quantities. If the project is suspended or
charges for the material mounts to a huge expenditure. In case
of hotel and casino construction delay in project was
due to handing over of site hence all the M.S shuttering
material, labour, staff, equipment which were mobilized
underutilized. In this case it was observed that all
25%
18%
20%
20%
12%
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319
__________________________________________________________________________________________
2013, Available @ http://www.ijret.org
Details of claims by contractor for (a) project 1, (b) project 2 and (c) project 3 on various elements
The investigation in this work was to identify the major
project delay that may give rise to
claims for delay damages for three major projects of 1.
Construction of mall, 2. Construction of hotel and casino and
wer transmission tower at various
locations of India. The main highlights in this study are to find
out the major components of claims with perspective of
all project it can be seen
ffected factor of delay
damages. This is because normally mall constructions are
wide spread and the area required for construction is more and
hence shuttering required to support the plywood is required in
huge quantities. If the project is suspended or delayed the idle
charges for the material mounts to a huge expenditure. In case
in project was mainly
due to handing over of site hence all the M.S shuttering
which were mobilized but
underutilized. In this case it was observed that all four factors
are equally contributing delay.
for power transmission tower
was due to not handing over
unhindered at the same time
project was supposed to be completed in
time was the key factor and t
complete project but work front
labour factor was the majo
RECOMMENDATIONS
Following are some of the
contractors of the construction projects
(1) Recommendations for Client:
have proper of planning before awarding the work.
The design and drawing should be ready before hand
to avoid any delay in work.
completely handed over instead of piece meal.
analysis of all factors which may lead to delay in
work from their end should be taken
(b)
(c)
29%
28%
18%
Project 2.
M.S. Shuttering Material
Labour
Machinery
Overheads
40%
20%
Project 3.
M.S. Shuttering Material
Labour
Overheads
Machinery
eISSN: 2319-1163 | pISSN: 2321-7308
__________________________________________________________________________________________
393
3 on various elements
ng delay. In case of claims by contractor
ower foundation project, the delay
handing over of all the four locations
at the same time and delay in drawings. Since the
be completed in one and half months,
the key factor and the contractor mobilized for the
complete project but work front was not given. Hence the
major affected factor in this case.
RECOMMENDATIONS
are some of the recommendations for clients and
contractors of the construction projects
Recommendations for Client: the client should
have proper of planning before awarding the work.
and drawing should be ready before hand
to avoid any delay in work. The site should be
completely handed over instead of piece meal. Risk
analysis of all factors which may lead to delay in
end should be taken care of.
M.S. Shuttering Material
Machinery
Overheads
M.S. Shuttering Material
Overheads
Machinery
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308
__________________________________________________________________________________________
IC-RICE Conference Issue | Nov-2013, Available @ http://www.ijret.org 394
(2) Recommendation for Contractor: It is the duty of
the contractor to validate the drawings given by client
at the time of bidding the tender. The contractor must
also analyze all the factors which may lead to delays
from government bodies, changes in rules and
regulations. The contractor should also be financially
stable to digest the cost overrun leading to delays
REFERENCES
[1] ED-ON Centre lecture notes: “One day workshop on
Contract Administration and Arbitration”. Pages 37-43.
[2] E. C. Harris: “Global Construction Disputes 2012:
Moving in the Right Direction” Pages 3-5 (2012)

More Related Content

Similar to Analysis of factors contributing delays and claims in construction projects

"Types and Causes of Construction Claims"
"Types and Causes of Construction Claims""Types and Causes of Construction Claims"
"Types and Causes of Construction Claims"
Abhishek Shah
 
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET Journal
 
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...
IRJET Journal
 
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET Journal
 
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECTHOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
IRJET Journal
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
IOSR Journals
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
IOSR Journals
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
IOSR Journals
 
B012140812
B012140812B012140812
B012140812
IOSR Journals
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET Journal
 
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
IJMER
 
Literature review on_ extension of time
Literature review on_ extension of timeLiterature review on_ extension of time
Literature review on_ extension of time
Joseph Sangpang
 
Effect of construction delays on project time overrun
Effect of construction delays on project time overrunEffect of construction delays on project time overrun
Effect of construction delays on project time overrun
eSAT Publishing House
 
Effect of construction delays on project time overrun
Effect of construction delays on project time overrunEffect of construction delays on project time overrun
Effect of construction delays on project time overrun
eSAT Journals
 
IRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET- Effects of Project Cost Analysis and Factors Affecting InflationIRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET Journal
 
Contractual implications of cash flow on owner and contractor in villa constr...
Contractual implications of cash flow on owner and contractor in villa constr...Contractual implications of cash flow on owner and contractor in villa constr...
Contractual implications of cash flow on owner and contractor in villa constr...
eSAT Publishing House
 
Analysis of Cost Over Run in Construction Projects
Analysis of Cost Over Run in Construction ProjectsAnalysis of Cost Over Run in Construction Projects
Analysis of Cost Over Run in Construction Projects
IRJET Journal
 
Implementing eichelay formula in govt. construction projects
Implementing eichelay formula in govt. construction projectsImplementing eichelay formula in govt. construction projects
Implementing eichelay formula in govt. construction projectsIAEME Publication
 
IRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay AnalysisIRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET Journal
 
IRJET - Causes, Effects and Minimizing Methods of Construction Projects D...
IRJET -  	  Causes, Effects and Minimizing Methods of Construction Projects D...IRJET -  	  Causes, Effects and Minimizing Methods of Construction Projects D...
IRJET - Causes, Effects and Minimizing Methods of Construction Projects D...
IRJET Journal
 

Similar to Analysis of factors contributing delays and claims in construction projects (20)

"Types and Causes of Construction Claims"
"Types and Causes of Construction Claims""Types and Causes of Construction Claims"
"Types and Causes of Construction Claims"
 
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
 
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...
 
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
 
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECTHOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
 
B012140812
B012140812B012140812
B012140812
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction Project
 
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
 
Literature review on_ extension of time
Literature review on_ extension of timeLiterature review on_ extension of time
Literature review on_ extension of time
 
Effect of construction delays on project time overrun
Effect of construction delays on project time overrunEffect of construction delays on project time overrun
Effect of construction delays on project time overrun
 
Effect of construction delays on project time overrun
Effect of construction delays on project time overrunEffect of construction delays on project time overrun
Effect of construction delays on project time overrun
 
IRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET- Effects of Project Cost Analysis and Factors Affecting InflationIRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
 
Contractual implications of cash flow on owner and contractor in villa constr...
Contractual implications of cash flow on owner and contractor in villa constr...Contractual implications of cash flow on owner and contractor in villa constr...
Contractual implications of cash flow on owner and contractor in villa constr...
 
Analysis of Cost Over Run in Construction Projects
Analysis of Cost Over Run in Construction ProjectsAnalysis of Cost Over Run in Construction Projects
Analysis of Cost Over Run in Construction Projects
 
Implementing eichelay formula in govt. construction projects
Implementing eichelay formula in govt. construction projectsImplementing eichelay formula in govt. construction projects
Implementing eichelay formula in govt. construction projects
 
IRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay AnalysisIRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay Analysis
 
IRJET - Causes, Effects and Minimizing Methods of Construction Projects D...
IRJET -  	  Causes, Effects and Minimizing Methods of Construction Projects D...IRJET -  	  Causes, Effects and Minimizing Methods of Construction Projects D...
IRJET - Causes, Effects and Minimizing Methods of Construction Projects D...
 

More from eSAT Journals

Mechanical properties of hybrid fiber reinforced concrete for pavements
Mechanical properties of hybrid fiber reinforced concrete for pavementsMechanical properties of hybrid fiber reinforced concrete for pavements
Mechanical properties of hybrid fiber reinforced concrete for pavements
eSAT Journals
 
Material management in construction – a case study
Material management in construction – a case studyMaterial management in construction – a case study
Material management in construction – a case study
eSAT Journals
 
Managing drought short term strategies in semi arid regions a case study
Managing drought    short term strategies in semi arid regions  a case studyManaging drought    short term strategies in semi arid regions  a case study
Managing drought short term strategies in semi arid regions a case study
eSAT Journals
 
Life cycle cost analysis of overlay for an urban road in bangalore
Life cycle cost analysis of overlay for an urban road in bangaloreLife cycle cost analysis of overlay for an urban road in bangalore
Life cycle cost analysis of overlay for an urban road in bangalore
eSAT Journals
 
Laboratory studies of dense bituminous mixes ii with reclaimed asphalt materials
Laboratory studies of dense bituminous mixes ii with reclaimed asphalt materialsLaboratory studies of dense bituminous mixes ii with reclaimed asphalt materials
Laboratory studies of dense bituminous mixes ii with reclaimed asphalt materials
eSAT Journals
 
Laboratory investigation of expansive soil stabilized with natural inorganic ...
Laboratory investigation of expansive soil stabilized with natural inorganic ...Laboratory investigation of expansive soil stabilized with natural inorganic ...
Laboratory investigation of expansive soil stabilized with natural inorganic ...
eSAT Journals
 
Influence of reinforcement on the behavior of hollow concrete block masonry p...
Influence of reinforcement on the behavior of hollow concrete block masonry p...Influence of reinforcement on the behavior of hollow concrete block masonry p...
Influence of reinforcement on the behavior of hollow concrete block masonry p...
eSAT Journals
 
Influence of compaction energy on soil stabilized with chemical stabilizer
Influence of compaction energy on soil stabilized with chemical stabilizerInfluence of compaction energy on soil stabilized with chemical stabilizer
Influence of compaction energy on soil stabilized with chemical stabilizer
eSAT Journals
 
Geographical information system (gis) for water resources management
Geographical information system (gis) for water resources managementGeographical information system (gis) for water resources management
Geographical information system (gis) for water resources management
eSAT Journals
 
Forest type mapping of bidar forest division, karnataka using geoinformatics ...
Forest type mapping of bidar forest division, karnataka using geoinformatics ...Forest type mapping of bidar forest division, karnataka using geoinformatics ...
Forest type mapping of bidar forest division, karnataka using geoinformatics ...
eSAT Journals
 
Factors influencing compressive strength of geopolymer concrete
Factors influencing compressive strength of geopolymer concreteFactors influencing compressive strength of geopolymer concrete
Factors influencing compressive strength of geopolymer concrete
eSAT Journals
 
Experimental investigation on circular hollow steel columns in filled with li...
Experimental investigation on circular hollow steel columns in filled with li...Experimental investigation on circular hollow steel columns in filled with li...
Experimental investigation on circular hollow steel columns in filled with li...
eSAT Journals
 
Experimental behavior of circular hsscfrc filled steel tubular columns under ...
Experimental behavior of circular hsscfrc filled steel tubular columns under ...Experimental behavior of circular hsscfrc filled steel tubular columns under ...
Experimental behavior of circular hsscfrc filled steel tubular columns under ...
eSAT Journals
 
Evaluation of punching shear in flat slabs
Evaluation of punching shear in flat slabsEvaluation of punching shear in flat slabs
Evaluation of punching shear in flat slabs
eSAT Journals
 
Evaluation of performance of intake tower dam for recent earthquake in india
Evaluation of performance of intake tower dam for recent earthquake in indiaEvaluation of performance of intake tower dam for recent earthquake in india
Evaluation of performance of intake tower dam for recent earthquake in india
eSAT Journals
 
Evaluation of operational efficiency of urban road network using travel time ...
Evaluation of operational efficiency of urban road network using travel time ...Evaluation of operational efficiency of urban road network using travel time ...
Evaluation of operational efficiency of urban road network using travel time ...
eSAT Journals
 
Estimation of surface runoff in nallur amanikere watershed using scs cn method
Estimation of surface runoff in nallur amanikere watershed using scs cn methodEstimation of surface runoff in nallur amanikere watershed using scs cn method
Estimation of surface runoff in nallur amanikere watershed using scs cn method
eSAT Journals
 
Estimation of morphometric parameters and runoff using rs & gis techniques
Estimation of morphometric parameters and runoff using rs & gis techniquesEstimation of morphometric parameters and runoff using rs & gis techniques
Estimation of morphometric parameters and runoff using rs & gis techniques
eSAT Journals
 
Effect of variation of plastic hinge length on the results of non linear anal...
Effect of variation of plastic hinge length on the results of non linear anal...Effect of variation of plastic hinge length on the results of non linear anal...
Effect of variation of plastic hinge length on the results of non linear anal...
eSAT Journals
 
Effect of use of recycled materials on indirect tensile strength of asphalt c...
Effect of use of recycled materials on indirect tensile strength of asphalt c...Effect of use of recycled materials on indirect tensile strength of asphalt c...
Effect of use of recycled materials on indirect tensile strength of asphalt c...
eSAT Journals
 

More from eSAT Journals (20)

Mechanical properties of hybrid fiber reinforced concrete for pavements
Mechanical properties of hybrid fiber reinforced concrete for pavementsMechanical properties of hybrid fiber reinforced concrete for pavements
Mechanical properties of hybrid fiber reinforced concrete for pavements
 
Material management in construction – a case study
Material management in construction – a case studyMaterial management in construction – a case study
Material management in construction – a case study
 
Managing drought short term strategies in semi arid regions a case study
Managing drought    short term strategies in semi arid regions  a case studyManaging drought    short term strategies in semi arid regions  a case study
Managing drought short term strategies in semi arid regions a case study
 
Life cycle cost analysis of overlay for an urban road in bangalore
Life cycle cost analysis of overlay for an urban road in bangaloreLife cycle cost analysis of overlay for an urban road in bangalore
Life cycle cost analysis of overlay for an urban road in bangalore
 
Laboratory studies of dense bituminous mixes ii with reclaimed asphalt materials
Laboratory studies of dense bituminous mixes ii with reclaimed asphalt materialsLaboratory studies of dense bituminous mixes ii with reclaimed asphalt materials
Laboratory studies of dense bituminous mixes ii with reclaimed asphalt materials
 
Laboratory investigation of expansive soil stabilized with natural inorganic ...
Laboratory investigation of expansive soil stabilized with natural inorganic ...Laboratory investigation of expansive soil stabilized with natural inorganic ...
Laboratory investigation of expansive soil stabilized with natural inorganic ...
 
Influence of reinforcement on the behavior of hollow concrete block masonry p...
Influence of reinforcement on the behavior of hollow concrete block masonry p...Influence of reinforcement on the behavior of hollow concrete block masonry p...
Influence of reinforcement on the behavior of hollow concrete block masonry p...
 
Influence of compaction energy on soil stabilized with chemical stabilizer
Influence of compaction energy on soil stabilized with chemical stabilizerInfluence of compaction energy on soil stabilized with chemical stabilizer
Influence of compaction energy on soil stabilized with chemical stabilizer
 
Geographical information system (gis) for water resources management
Geographical information system (gis) for water resources managementGeographical information system (gis) for water resources management
Geographical information system (gis) for water resources management
 
Forest type mapping of bidar forest division, karnataka using geoinformatics ...
Forest type mapping of bidar forest division, karnataka using geoinformatics ...Forest type mapping of bidar forest division, karnataka using geoinformatics ...
Forest type mapping of bidar forest division, karnataka using geoinformatics ...
 
Factors influencing compressive strength of geopolymer concrete
Factors influencing compressive strength of geopolymer concreteFactors influencing compressive strength of geopolymer concrete
Factors influencing compressive strength of geopolymer concrete
 
Experimental investigation on circular hollow steel columns in filled with li...
Experimental investigation on circular hollow steel columns in filled with li...Experimental investigation on circular hollow steel columns in filled with li...
Experimental investigation on circular hollow steel columns in filled with li...
 
Experimental behavior of circular hsscfrc filled steel tubular columns under ...
Experimental behavior of circular hsscfrc filled steel tubular columns under ...Experimental behavior of circular hsscfrc filled steel tubular columns under ...
Experimental behavior of circular hsscfrc filled steel tubular columns under ...
 
Evaluation of punching shear in flat slabs
Evaluation of punching shear in flat slabsEvaluation of punching shear in flat slabs
Evaluation of punching shear in flat slabs
 
Evaluation of performance of intake tower dam for recent earthquake in india
Evaluation of performance of intake tower dam for recent earthquake in indiaEvaluation of performance of intake tower dam for recent earthquake in india
Evaluation of performance of intake tower dam for recent earthquake in india
 
Evaluation of operational efficiency of urban road network using travel time ...
Evaluation of operational efficiency of urban road network using travel time ...Evaluation of operational efficiency of urban road network using travel time ...
Evaluation of operational efficiency of urban road network using travel time ...
 
Estimation of surface runoff in nallur amanikere watershed using scs cn method
Estimation of surface runoff in nallur amanikere watershed using scs cn methodEstimation of surface runoff in nallur amanikere watershed using scs cn method
Estimation of surface runoff in nallur amanikere watershed using scs cn method
 
Estimation of morphometric parameters and runoff using rs & gis techniques
Estimation of morphometric parameters and runoff using rs & gis techniquesEstimation of morphometric parameters and runoff using rs & gis techniques
Estimation of morphometric parameters and runoff using rs & gis techniques
 
Effect of variation of plastic hinge length on the results of non linear anal...
Effect of variation of plastic hinge length on the results of non linear anal...Effect of variation of plastic hinge length on the results of non linear anal...
Effect of variation of plastic hinge length on the results of non linear anal...
 
Effect of use of recycled materials on indirect tensile strength of asphalt c...
Effect of use of recycled materials on indirect tensile strength of asphalt c...Effect of use of recycled materials on indirect tensile strength of asphalt c...
Effect of use of recycled materials on indirect tensile strength of asphalt c...
 

Recently uploaded

DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
Vijay Dialani, PhD
 
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
ssuser7dcef0
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
AmarGB2
 
Basic Industrial Engineering terms for apparel
Basic Industrial Engineering terms for apparelBasic Industrial Engineering terms for apparel
Basic Industrial Engineering terms for apparel
top1002
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
BrazilAccount1
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
gestioneergodomus
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
ChristineTorrepenida1
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
SyedAbiiAzazi1
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
ClaraZara1
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
symbo111
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Soumen Santra
 
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERSCW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
veerababupersonal22
 

Recently uploaded (20)

DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
 
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
 
Basic Industrial Engineering terms for apparel
Basic Industrial Engineering terms for apparelBasic Industrial Engineering terms for apparel
Basic Industrial Engineering terms for apparel
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
 
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERSCW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
 

Analysis of factors contributing delays and claims in construction projects

  • 1. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 __________________________________________________________________________________________ IC-RICE Conference Issue | Nov-2013, Available @ http://www.ijret.org 390 ANALYSIS OF FACTORS CONTRIBUTING DELAYS AND CLAIMS IN CONSTRUCTION PROJECTS Ketki S. Kamble1 , A. R. Kambekar2 1 PG. Student, Const. Management, 2 Assistant Professor, CED, SPCE Andheri (W), Mumbai 400058, Maharashtra, ketki08@gmail.com Abstract Construction activities are the most competitive and it involves higher risk with minimum profitability due to competition. Construction of any infrastructural work involves complex management skills related to manpower, materials, plant, machineries, new technologies etc. It also involves many agencies interdependent on each other like the planners, structural and functional designers including various types of specialized engineers and it also includes support of financial institutions, insurers, contractors and specialized contractors. As there are prevailing labour bye laws it needs special care of their well beings. In such kind of complex and intense framework some disputes is quite natural between the agencies involved in such activities which further results in claims management as the unsettled dispute finally leads to financial claims. Higher incidences of disputes are generally reported from the construction contract. Even if there is an appropriate understanding of construction contract clauses from the agencies in the agreement yet claims seems to be a major crisis in the construction sector. The research reported in this paper aims in identifying the major factors responsible of project delay that may give rise to claims for delay damages. The in this paper research mainly highlights on finding the major components of claims with perspective of contractor for delay damages. Keywords: Claims, delay, damages, construction industry, disputes. --------------------------------------------------------------------***--------------------------------------------------------------------- 1. INTRODUCTION Claims as per Hughes [1] “It is a demand, a request or application for something to which a contractor considers, believes or contends he is entitled but in respect of which agreement has not yet been reached”. As per Harris [2] the major five causes of disputes in Asian construction projects are as follows: • Failure to make interim awards on extensions of time and to give associated compensation • Unrealistic risk transfer from employers to contractors • Conflicting party interests • An unrealistic contract completion date being defined at tender stage • Incomplete design information or employer requirements. In general it was reported in literature that the construction sector involves disputes from the sources like changes which includes variation, alteration, addition, deletion, delays and suspensions, differing site conditions, unjust enrichment by owners. It was also observed that there are five potential areas which can give rise to disputes: document errors, estimation errors, change in conditions, implied promises and agencies involved. Claims however fall under two major categories based on their occurrence i.e. during (i) execution of contract and (ii) administration of contract. Execution of contract includes claims due to change in design and drawing, delays in handing over site/issuance of drawings/getting clearance certificate from appropriate authorities, claims due to original scope of work change, claims due to differing site conditions and claims due to variation in methodology. Similarly during administration of contract claims may be due to delay in payment of running account bills and claims due to foreclosure/termination of contract. Similarly delays in schedules of construction projects are one of the most common types of disputes in the construction industry. The client and contractor works for a common objective i.e. to complete the project within scheduled time as well as cost. Time overrun is the most common failure of objective that in turn leads to cost overrun and hence failure in the objective of timely completion leads to failure of overall project budget which ultimately gives rise to disputes. The reasons for delays could be caused by client, contractor, force majeure i.e. act of God, change in laws, rules and regulations, improper co- ordination between client and contractors, non-availability of required skilled labour, non-availability of required special material, differing site conditions, non-issuance of working drawing and changes in work leading to change in methodology. Delays can be further classified as excusable or non-excusable. Some of the practical cases of non-excusable delays are incompetent sub-contractor, financial incompetency of the contractor, labour disputes hindering work progress, poor workmanship leading to rework, poor material quality and delay in handing over the site by client and excusable
  • 2. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 __________________________________________________________________________________________ IC-RICE Conference Issue | Nov-2013, Available @ http://www.ijret.org 391 delay includes sudden floods, natural calamities like earthquake, tsunami etc. riots, labour strike, non-foreseeable situation. Critical delay are defined as a delay in any given activity which results in delay of total project and non-critical delay is defined as delays which may not upset total time frame of the contract [1]. This paper mainly focuses on delay damage claims related to additional cost incurred by the contractor due to delay caused by the client. Evaluation of delay damages are when a contractor bids for a tender, a number of factors are considered apart from the labour, material and equipment that are required to execute the work. In tender the duration required to complete the work is generally mentioned and hence the contractor quotes accordingly. The quote includes material cost, labour cost, plant and machinery cost, shuttering material, human resource cost, financial cost, site overheads and above all profit. In an event of prolongation of contract, the major factors that are affected are additional overheads, plant and machinery, labour and material cost, loss of productivity, loss of profit, loss of new business opportunities and early mobilization. 2. METHODOLOGY ADOPTED Following methodology is adopted for this research work. This includes identification of claims that occur, factors responsible for delay, prolongation claim if any, focus on factors that are affected due to delay in completion the project, factors mostly considered while setting up prolongation claim, ranking based on case studies to understand the major factor affecting the delay damages claim finally recommendations based on the study. The delays which occur in construction projects are due to various reasons. Analysis of three projects have been carried out details of the same is given in Table 1. Project cost, value of claims and claim in % of project cost for (i) construction of mall in Mumbai, (ii) construction of hotel and casino in Goa and (iii) construction of power transmission tower in Raigad district of Maharashtra is considered in this paper. The range of delay claims by contractor was in the range of around 1.08 % to 400% of the project cost. This may due to various reasons. Table1. Analysis of delay damages in construction projects. Sr. No Project description Project cost (Lakhs Rs.) Value of claim (Lakhs Rs.) Claim in % of project cost 1 Construction of mall in Mumbai. 4314 623.58 14.45% 2 Construction of hotel and casino in Goa. 3494 37.68 1.08% 3 Construction of power transmission tower foundation in Raigad district. 12.43 49.64 400% 2.1 Project 1: Construction of Mall in Mumbai Construction of a mall in Mumbai was taken as first case study for delay claims. The project cost was around 4314 Lakhs Rs., claim amount by contractor was 623.58 Lakhs Rs. and delay was almost of 7 months. Various reasons for claims observed in this case includes the mainly due to delay in approved drawings. The total built up area was around 6,77,000 Sq.ft. and large quantity of MS shuttering material was required to be deployed on site. Since the work was suspended in the middle of project, the resources like staff, machinery was demobilized and transferred to other project, but it was difficult to transfer the shuttering material to other site since the cost of transportation for demobilizing and again mobilizing when the work resumes was observed as a governing factor. Hence in this project 81% of Claim constitutes for M.S Shuttering Material. Details of claim for various reasons in % for project 1 are shown in Table 2. This includes claims for MS shuttering material, labour, overheads and machinery. Next section gives similar analysis for construction of hotel and casino in Goa. Table2 Details of claim for project 1 Sr. No. Description Claim amount (In Lakhs Rs.) Claim in % of project cost Importance as per claim amount 1 M.S. Shuttering Material 503.08 81% 1 2 Labour 58.24 9% 2 3 Overheads 47.50 8% 3 4 Machinery 14.75 2% 4 Total claim (In Lakhs Rs.) 623.58 2.2 Project 2: Construction of Hotel and Casino in Goa The construction of hotel and casino in Goa was having estimated project cost of 3494 Lakhs Rs. and the claim was 37.68 Lakhs Rs with delay of 1 month. It was noted that the work order given shows the site mobilization within 15 days and in the tender it was also mentioned the minimum staff cadre and equipment needs to be deployed on site at the time of mobilization. Table 3 gives details of claim for various reasons in % for project 2 showing importance as per claim
  • 3. IJRET: International Journal of Research in Engineering and Technolo __________________________________________________________________________________________ IC-RICE Conference Issue | Nov-2013, Available @ amount. As per the conditions the contractor mobilized the s with the required resources but there was a delay of 1 month in handing over the site. In this case the amount of M.S. shuttering material, overheads and machinery same, since the claim was at the start of the project hence the minimum resources were deployed. The third case study includes the construction of power transmis foundation in Raigad district detailed analysis is given in the next section. Table3. Details of claim for project 2. Sr. No. Description Claim amount (In Lakhs Rs.) Claim in % of project cost 1 M.S shuttering material 10.93 29% 2 Overheads 10.60 28% 3 Machinery 9.55 25% 4 Labour 6.60 18% Total claim (In Lakhs Rs.) 37.68 2.3 Project 3. Construction of Power Transmission Tower Foundation in Raigad District The scope of work in this case study was to construct RCC power transmission tower foundation at locations. Table 4 gives details of claim for project 3. work was supposed to be executed after getting unhindered land at all the four locations along with the necessary 9% 2% 8% IJRET: International Journal of Research in Engineering and Technology eISSN: 2319 __________________________________________________________________________________________ 2013, Available @ http://www.ijret.org ontractor mobilized the site ut there was a delay of 1 month this case the amount of claim for achinery was almost at the start of the project hence the The third case study includes the construction of power transmission tower foundation in Raigad district detailed analysis is given in the project 2. Claim in project Importance as per claim amount 1 2 3 4 Power Transmission was to construct RCC foundation at four different Table 4 gives details of claim for project 3. The to be executed after getting unhindered along with the necessary approvals from the local authorities. It was that all four locations would project. The duration of project was 45 days. The contractor mobilized the site with adequate resources of all the four location was not working drawing was not issued local authorities was not taken by the cost was 12.43 Lakhs Rs., c and the delay resulted the work to be completed in 14.5 months leading to total delay of details of claims by contractor for project 1, 2 and 3 on various elements of the respective projects. Table4. Details of Sr. No. Description Claim amount (In Lakhs Rs.) 1 Labour 21 2 M.S Shuttering Material 10 3 Overheads 10 4 Machinery 6. Total claim (In Lakhs Rs.) 49 (a) 81% 8% Project 1. M.S. Shuttering Material Labour Machinery Overheads eISSN: 2319-1163 | pISSN: 2321-7308 __________________________________________________________________________________________ 392 from the local authorities. It was also mentioned ould be made available at the start of project. The duration of project was 45 days. The contractor mobilized the site with adequate resources but the possession location was not allotted to the contractor. The not issued and the permission from the not taken by the client. The total project Rs., claim amount was 49.64 Lakhs Rs. sulted the work to be completed in 14.5 total delay of 13 months. Figure 1 shows details of claims by contractor for project 1, 2 and 3 on various elements of the respective projects. Details of claim for project 3 Claim amount (In Lakhs Rs.) Claim in % of project cost Importance as per claim amount 21.58 40% 1 10.79 20% 2 10.79 20% 2 .47 12% 3 49.64 M.S. Shuttering Material
  • 4. IJRET: International Journal of Research in Engineering and Technolo __________________________________________________________________________________________ IC-RICE Conference Issue | Nov-2013, Available @ Fig1. Details of claims by contractor for CONCLUSIONS The investigation in this work was to identify the major factors responsible for project delay that may give rise to claims for delay damages for three major projects of 1. Construction of mall, 2. Construction of hotel and casino and 3. Construction of power transmission tower at various locations of India. The main highlights in this study are to find out the major components of claims with perspective of contractor for delay damages. For mall project it can be seen that M.S. shuttering material is most affected factor of delay damages. This is because normally mall constructions are wide spread and the area required for construction is more and hence shuttering required to support the plywood is required in huge quantities. If the project is suspended or charges for the material mounts to a huge expenditure. In case of hotel and casino construction delay in project was due to handing over of site hence all the M.S shuttering material, labour, staff, equipment which were mobilized underutilized. In this case it was observed that all 25% 18% 20% 20% 12% IJRET: International Journal of Research in Engineering and Technology eISSN: 2319 __________________________________________________________________________________________ 2013, Available @ http://www.ijret.org Details of claims by contractor for (a) project 1, (b) project 2 and (c) project 3 on various elements The investigation in this work was to identify the major project delay that may give rise to claims for delay damages for three major projects of 1. Construction of mall, 2. Construction of hotel and casino and wer transmission tower at various locations of India. The main highlights in this study are to find out the major components of claims with perspective of all project it can be seen ffected factor of delay damages. This is because normally mall constructions are wide spread and the area required for construction is more and hence shuttering required to support the plywood is required in huge quantities. If the project is suspended or delayed the idle charges for the material mounts to a huge expenditure. In case in project was mainly due to handing over of site hence all the M.S shuttering which were mobilized but underutilized. In this case it was observed that all four factors are equally contributing delay. for power transmission tower was due to not handing over unhindered at the same time project was supposed to be completed in time was the key factor and t complete project but work front labour factor was the majo RECOMMENDATIONS Following are some of the contractors of the construction projects (1) Recommendations for Client: have proper of planning before awarding the work. The design and drawing should be ready before hand to avoid any delay in work. completely handed over instead of piece meal. analysis of all factors which may lead to delay in work from their end should be taken (b) (c) 29% 28% 18% Project 2. M.S. Shuttering Material Labour Machinery Overheads 40% 20% Project 3. M.S. Shuttering Material Labour Overheads Machinery eISSN: 2319-1163 | pISSN: 2321-7308 __________________________________________________________________________________________ 393 3 on various elements ng delay. In case of claims by contractor ower foundation project, the delay handing over of all the four locations at the same time and delay in drawings. Since the be completed in one and half months, the key factor and the contractor mobilized for the complete project but work front was not given. Hence the major affected factor in this case. RECOMMENDATIONS are some of the recommendations for clients and contractors of the construction projects Recommendations for Client: the client should have proper of planning before awarding the work. and drawing should be ready before hand to avoid any delay in work. The site should be completely handed over instead of piece meal. Risk analysis of all factors which may lead to delay in end should be taken care of. M.S. Shuttering Material Machinery Overheads M.S. Shuttering Material Overheads Machinery
  • 5. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 __________________________________________________________________________________________ IC-RICE Conference Issue | Nov-2013, Available @ http://www.ijret.org 394 (2) Recommendation for Contractor: It is the duty of the contractor to validate the drawings given by client at the time of bidding the tender. The contractor must also analyze all the factors which may lead to delays from government bodies, changes in rules and regulations. The contractor should also be financially stable to digest the cost overrun leading to delays REFERENCES [1] ED-ON Centre lecture notes: “One day workshop on Contract Administration and Arbitration”. Pages 37-43. [2] E. C. Harris: “Global Construction Disputes 2012: Moving in the Right Direction” Pages 3-5 (2012)