DSC 2322 – Operations Management
Project Report
By
R.B.K.K.B.Jamarasinghe (MC/63751),(CPM 8344)
L.E.M.Kaushalya (MC/63814),(CPM 8407)
K.V.C.I.Kumarasinghe (MC/63855),(CPM 8448)
W.K.H.Lakshan (MC/63878),(CPM 8471)
U.A.M.M.Perera (MC/64032),(CPM 8625)
R.M.A.Y.I.Rathnayake (MC/64102),(CPM 8695)
H.R.S.Sandamali (MC/64143),(CPM 8736)
S.G.P.Sandaruwan (MC/64148),(CPM 8741)
R.M.T.D.Senevirathne (MC/64177),(CPM 8770)
D.P.Wickramanayake (MC/64285),(CPM 8878)
An Analysis of Layout Planning of Royal CeramicPLC
A project report submitted in partial fulfillment of requirements of the subject
DSC 2322 – Operations Management conducted by the
Department of Decision Sciences of the
Faculty of Management Studies and Commerce
of the
University of Sri Jayewardenepura
2012
ii
ABSTRACT
The purpose of this report is to study regarding the Layout Planning of Royal Porcelain
(Private) Ltd which is afully owned subsidiary of Royal ceramics lanka PLC. They
manufacture and distribute porcelain tiles under the well-known brand name “Rocell”. This
factory was started by a foreign investor in early 90’s and abandoned the plant due to some
technical failures almost at the inception. Then Rocell has acquired this plant and started
operations by correcting those technical failures. Rocell has two main tile manufacturing
plants in Horana and Ehaliyagoda. Horana plant is the smallest one with daily production
capacity of 1000 square foot. Rocell is the leading tile maker in Sri Lanka and they stand for
both highest quality and elegant designs.
For our study we focused our attention on Layout Planning. Layout has numerous strategic
implications because it establishes an organization’s competitive priorities with regard to
capacity, processes, flexibility and cost, quality of work life, customer contact and image.
Through our study we identified strengths & weaknesses of the existing layout of the Royal
porcelain (Private) Ltd as follows. Their strengths are having a screen printing machine
which can digitally print designs which helps to produce tiles with different designs, having
adjustable press machines which can press differentsizes of tiles and having adjustable
production lines which can be adjusted according to the tile size.
Weaknesses of the existing layout plan of Royal porcelain (Private) Ltd is not having an
emergency exit in the factory, having a defect rate of vary in between 8%-10% and not
having enough space to add additional production lines.
In order to increase the strengths & eliminate the weaknesses our major recommendations is
to establish a separate primary plant to process raw material in order to reduce current higher
defect rate.
iii
Table of Contents
01. INTRODUCTION ...............................................................................................................1
02. SELECTED FUNCTION WITHIN THE ORGANIZATION ............................................1
03.LITERATURE......................................................................................................................2
04. DETAILED ANALYSIS OF THE PRODUCTION( see appendix 2)................................3
05. RECOMMENDATION.......................................................................................................6
06. CONCLUSION....................................................................................................................7
APPENDICES
REFERENCES
1
01. INTRODUCTION
As management students, knowledge & application about operations management is
extremely critical in this dynamic business environment to be successful business leaders in
the future. Within the class room, discussing the application part of the theories are much
difficult because different organizations use unique way to apply theories to their own
operations. Therefore as part of our study program we are expected to gain the knowledge
about real world applications of theories.
To study the real world business scenarios we went to a tile manufacturing plant located in
Horana which is owned by Royal Porcelain (Private) Ltd a fully owned subsidiary of Royal
ceramics lanka PLC. They manufacture and distribute porcelain tiles under the well-known
brand name “Rocell”. This factory was started by a local investor in early 90’s and
abandoned the plant due to some technical failures almost at the inception. Then Rocell has
acquired this plant and started operations by correcting those technical failures.
Rocell has two main tile manufacturing plants. And the Horana factory is the smallest one
with daily production capacity of 1000 square foot. Rocell is the leading tile maker in Sri
Lanka and they stand for both highest quality and elegant designs.
02. SELECTED FUNCTION WITHIN THE ORGANIZATION
Our study mainly focuses on Plant layout and the product layout of the factory.
Plant layout consists of two warehouses, one for raw material and for finished goods. Raw
material warehouse has the capability of storing raw materials needed for 2 ½ months
production. And the finished good warehouse has a capacity of keeping one week production.
The manufacturing plant can be divided in two main parts for ease the analysis. The primary
plant prepares the raw material mixture needed to make the tiles and has a daily capacity of
7200kg.
This factory has 3 production belts in secondary plant and capable of manufacturing 3
different variety of tile at once (one belt only one tile at a given time). Each belt has separate
kiln powered by gas. Kiln is the major constraint in this plant and these 3 belts capable of
manufacturing 10000 square foot per day. This factory continuously operates 24 hours in 365
days to avoid huge shutdown and start-up costs (specially kiln). And the monthly energy cost
is approximately 100 million rupees (both electricity & LP gas). The defect rate fluctuates in
between 8%-10%. These 3 production belts are fully automated and human contribution to
the production is very minimum. Plant only has 21 workers.
2
03. LITERATURE
Operations management is one of the most critical functions in any organization. Under this
function planning a proper facility layout is very essential for smooth work flow. This is
called as Layout Planning. This involves deciding where to put all the facilities machines,
equipment, departments & staff in order to continue the manufacturing process more
efficient.
Keeping a proper layout within the organization affects the efficiency of the material
utilization, machines utilization, attitudes of the employees and the customers positively. It
reduces the cost of material usage, reduces the movements of the materials and the employees
& improves the flexibility.
A layout planning is an arrangement of everything needed for production of goods or
delivery of services or it can be defined as arrangement of machine tool, a work centre, a
manufacturing cell, a machine shop, a department, a warehouse, etc. In practical world there
are several types of layout formats within an organization. Among those different layout
formats this study is only focused on plant layout and the product layout of the Rocell tile
manufacturing plant situated in Horana.
Plant Layout
Plant layout refers to the arrangement of physical facilities such as machines, equipment,
tools, furniture etc. in such a manner so as to have quickest flow of material at the lowest cost
and with the least amount of material handling in processing the product from the receipt of
raw material to the delivery of the final product. Primary objectives of plant layout should be:
 Minimal material handling costs.
 Minimal investments.
 Minimal throughput time.
 Flexibility.
 Efficient use of space.
 Reduce accidents.
 Reduce hazards to personnel.
Product Layout
Product layout is also called flow-shop or straight line layout. It involves the arrangement of
equipment according to the progressive steps by which a product is made. Raw materials are
fed continuously into the first machine and thereafter it passes through subsequent operations
rapidly while the finished products are coming out from the last one.
3
04. DETAILED ANALYSIS OF THE PRODUCTION (see appendix 2)
An analysis of the production with it'ssteps and the strengths & weaknesses of the process are
discussed below.
No 01:Raw material warehouse
Manufacturing process begins in the warehouse where the raw materials are received and
stored.
No 02: Weighting Scale
Using weighting scale, raw materials are measured according to the pre-determined
standards.After that the raw materials are transported to the grinding mill via conveyor belts.
No 03:Mill
The mills grind the raw materials in water to obtain slurry required for pressing. The mills are
large cylindrical containers that work 24 hours per day.
No 04:Under Tank
The slurry is transported to the under tank. Then the litter contaminated to the bottom of the
tank. Then the slurry is passed through magnetic field in order to remove unwanted litter.
Then slurry is passed to spray dryer tanks.
No 05:Tanks
Tanks contain all the liquid which remove any remaining litter. Then it passes to spray dryer.
No 06:Spray Dryer
Spray drying is an extremely important stage in manufacturing process. Spray dryer convert
slurry into an atomized powder ready to be pressed.
No 07:Belt
The powder passes to two tanks which can contain buffer stock. Then powder is pumped to
the pressing machines.
No 08:Pressing
Pressing is the shaping process used for porcelain tile. First air is removed from the powder.
A pressure of more than 7500 PSI is used to definitively compact each round shaped practical
in the body.
No 09:Drying.
The drying operation is important to eliminate the moisture from the suppressed products.
The fast, hot, vertical and horizontal air dryers are located to achieve heating of material.
No 10:Glazing
4
Glazing is the production phase where two coats of color are applied on the surface of the
product before it is fired. This phase consists of printing a given design. First paint is applied
on the slab by a water fall system and then design is printed on the surface of the tile using
the cylinders which gives a unique design to each tile.
No 11:Protection Layout
Protection Layoutis poured to the surface of the tile.
No12:Car System
Transport painted tiles to the kiln.
No 13:Firing
Firing is the major stage of the production process. Firing operation is carried out
continuously using three layer kilns.
No 14:Robot Arms
Fired tiles are punched by 3 robot arms at the end of firing process and arrange them on the
floor in order to transport to the inventory handling area.
No 15:Sorting
Next phase of the process is sorting. The main objective of the sorting is elimination of
defective tiles with inferior quality.
No 16: Packaging
Tiles are automatically packed in special cardboard cartoons according to computerized
instructions.
No17:Warehousing
The packed tiles are transported to the warehouse.
Strengths of the product and plant layout
1. One production belt consists ofa screen printing machine which can digitally print designs
on the surface of tiles. It adds further flexibility to the plant.
2. Plant consists of adjustable press machines, which can press different size of
tiles.According to the size of the pressing tile, entire production line can be adjusted.
3.Raw material warehouse is capable of keeping raw materials which can be used for 2 ½
month production.
4. Primary plant has an excess storing capacity and it is enough to operate 9.6 hours if any
breakdown occurs in the primary plant. (See appendix 1)
4. Digital scanners are used to sort tiles which ensure no defect tile goes to the market
5
5. Horana plant is located in a strategically valuable point since it is by the Colombo-Gall
highway. Asaresult,there is quick access to Colombo (main market) and both Colombo and
Hambanthota ports.
6. Sunlight is being used for day production through transparent roof sheets; it saves the
electricity power in the day time.
7.All machineriesare made by world renowned Italian and American manufactures for tile
machinery.
Weaknesses of the product and plant layout
1. One entry route is used for both entrances to the plant & exit from the plant.
2. Defect rate of the plant vary in between 8%-10%. As a result, amount of energy wasted
approximately is 7 million rupees per month. (See appendix 2)
3.There is no proper safety in the plant,because jumbled wires are lying everywhere.
4. There is a high possibility of strong sudden fire since plant heavily uses LP gas.
Theexisting firefighting system is not adequate to prevent a strong sudden fire.
5. They are not in a position to expand their production by adding additional product lines to
the layout. So it is difficult to get the maximum advantages from their strategically valuable
location.
6. Weight scale is used to weight the raw material which is essential for preparing the mixture
according to the standard ratio. There is only one weight scale in the plant. Therefore if the
weight scale breaks down whole production process have to be stopped. There is no
alternative for the weight scale.
7. Since plant is arranged according to the product layout, if a breakdown occurs at any given
point whole production line have to be stopped.
8. The factory & the office have been established close to each other. It cannot be seen as a
good thing because in an emergency situation, as an example in a fire, office premise will be
affected by the fire.
9. As there is a distance between the finished goods store & factory it is difficult to move
finished goods from factory to stores in rainy days.
10. They handle a buffer stock of raw materials for two months. Two months buffer stock is
too much when compared with the capacity of the factory.
6
05. RECOMMENDATION
Major Recommendation
Major cause behind 10%-8% high defect rate is the unprocessed (not refined materials) raw
material used for production. Therefore major recommendation is targeted towards reducing
such significant defect rate.
Rocell should use processed raw material for the production. But there is no additional space
in the current plant to refine raw material.
The only option is to establish a separate plant for processing raw material. Rocell has
another plant for manufacturing tiles in Ehaliyagoda. Horana plant and Ehaliyagoda plant are
located close to each other. Therefore they should find a land somewhere between
Ehaliyagoda& Horana and build up a separate factory for processing material and preparing
powder needed for production of tiles.
As a result manufacturing plant can focus on production and new plant can focus on quality
of the raw material and powder. This approach is heavily used by Japanese and Italian tile
makers and they have reduced their defect rate to 1%-2%.
If the proposed approach is implemented a prevailing bottleneck will be eliminated which
facilitates to achieve long term flexibility as a group.
Recommendation for the plant layout
1. Production lines should be arranged vertically. That is, kiln and sorting lines should be
established vertical to the earlier parts of the production line. It helps to utilize factory
space more efficiently and achieve long term flexibility. (see appendix 3)
2. Strong fire fighter system should be established to face strong sudden fires.
3. Since plant has high exposure to sudden strong fire emergency doors should be
established. (see appendix 3)
4. Finished goods warehouse should be established closer to the main manufacturing line. It
will reduce unnecessary material handling cost. (see appendix 1)
5. LED lighting system should be placed for night shifts of production. It will help to reduce
the electricity cost of the factory.
6. High pressure water posts should be placed around the plant to fight against strong fires.
7. Separate entry and exit routes should be established to enter the plant and exit from the
plant. It will help to minimize risk and allow smooth flow of material and finished goods
within the factory.
7
06. CONCLUSION
Analysis reveals that there are lots of inefficiencies within the plant than strengths. Top
management mainly focuses about product design and marketing activities and they pay little
attention to improve production efficiencies. Currently 10% abnormal loss is charged from
customers. And the main cause behind such significant defect rate is of using unprocessed
raw materials to prepare raw material powder and during the production,defects occur as a
result of that. As shown in appendix 1, within the current plant location, there is no additional
space available to process raw materials. Therefore the only option available to reduce such
significant defect rate is establishing a separate plant for making the raw material powder and
this technique is highly practiced by Japanese firms and they have reduced their defect rate
up to 1% to 2%.
Further, when analyzing the primary plant it can supports onlyone extra belt. But no more
than that. By shifting this primary plant to another location company can eliminate a major
bottle neck within their plant. This is vital to increase the longer term capacity of the plant.
The smooth inflow of high quality processed raw material powder to the plant will help to
reduce their defect rate up to 1% to 2%. And this would be essential to achieve cost
leadership in the market.
The proposed approach will help the existing plant to focuson product design and the quality
of the production. It will reduce the burden on management also. With the low cost and long
term flexibility within the proposed plant "Rocell" can achieve sustainable growth in the
future.
As shown in the appendix 5 plant would be able to reduce their defect rate up to 1%-2%. And
the energy cost saving would be 71.4 million per annum. According to the project appraisal
shown in appendix 6 this project generates a positive NPV of Rs. 99.1 million even we have
used 5 year project duration. (In reality benefits would be perpetual) Therefore the project
should be accepted and implemented.
8
9
10
11
Appendix 4
Primary plant capacity analysis
1mn * 5Kg * 60 * 24 =7200Kg/day  Full capacity( 1 minute 5kg output)
7200/ 0.7 = 5040 Kg use( 70% uses for daily production)
7200-5040 =2160Kg extra (Hence buffer stock in kg)
7.2/ hr buffer( buffer stock in hours)
Appendix 5
Financial benefits
Current energy cost – 70 million per month (only for LP gas)
Loss of energy due to defect rate = 70 million * 0.1
= 7 million
Major reason behind effects rate is the unprocessed raw materials. If raw processed materials
are used for production, defect rate would be in between 1%-2%.
Hence maximum energy cost saving = 70 million * 0.09 = 6.3 million
Minimum energy cost saving = 70 million * 0.8 = 5.6 million
On average energy cost saving would be= 5.95 * 12= 71.4 million.
Appendix 6
Initial investment Rs.500 million
Capital allocation for existing plant* Rs.200 million
Benefits: energy cost saving** + electricity saving + raw material
saving
Rs.100 million per
annum
NPV evaluated at 20% cost of capital in a 5 year duration
=Annual saving * [1-(1+r)-n
/ r] – Initial investment
Rs.99.1 million
* Let’s assume they allocate Rs.200 million capital cost to current plant since it’s smaller
than Ehaliyagoda plant
** Rs. 71.4 million directly from gas saving
12
References
Books
 Operation Management for Competitive Advantage, Richard B. Chase. Nichols J. Aquilano,
F. Robbert Jacobs, 10th
ed., Mcgraw-Hill, 2003.
Web sites
 Rocell Annual Report 2011
 Rocell.com
 You Tube.com

More Related Content

Similar to An Analysis Of Layout Planning

Application of value stream mapping tool to reduce wastes in bearing industry
Application of value stream mapping tool to reduce wastes in bearing industryApplication of value stream mapping tool to reduce wastes in bearing industry
Application of value stream mapping tool to reduce wastes in bearing industry
ijmech
 
processes : from raw bauxite to refractory alumina bricks
processes : from raw bauxite to refractory alumina bricksprocesses : from raw bauxite to refractory alumina bricks
processes : from raw bauxite to refractory alumina bricks
Parth Vaishnav
 
IARE_PLMH_PPT.pdf
IARE_PLMH_PPT.pdfIARE_PLMH_PPT.pdf
IARE_PLMH_PPT.pdf
Jay Parmar
 
Lecture_1_J_Tanyanyiwa.pptx
Lecture_1_J_Tanyanyiwa.pptxLecture_1_J_Tanyanyiwa.pptx
Lecture_1_J_Tanyanyiwa.pptx
Bekithemba2
 
IRJET-Production of Hybrid Aluminium Matrix Composite with Welding Slag and F...
IRJET-Production of Hybrid Aluminium Matrix Composite with Welding Slag and F...IRJET-Production of Hybrid Aluminium Matrix Composite with Welding Slag and F...
IRJET-Production of Hybrid Aluminium Matrix Composite with Welding Slag and F...
IRJET Journal
 
Study of Fabrication of Multipurpose Tooling Machine
Study of Fabrication of Multipurpose Tooling MachineStudy of Fabrication of Multipurpose Tooling Machine
Study of Fabrication of Multipurpose Tooling Machine
IRJET Journal
 
Designing Facility Layout and Effective Material Handling for a Ceramic Insul...
Designing Facility Layout and Effective Material Handling for a Ceramic Insul...Designing Facility Layout and Effective Material Handling for a Ceramic Insul...
Designing Facility Layout and Effective Material Handling for a Ceramic Insul...
IRJET Journal
 
DG KHAN CEMENT
DG KHAN CEMENT DG KHAN CEMENT
DG KHAN CEMENT
MUHAMMADUMAR103036
 
Lay out
Lay outLay out
Finalelectricalreport
FinalelectricalreportFinalelectricalreport
Finalelectricalreport
NAVEENGEHLOT5
 
Addis Ababa City Administration Technical, Vocational, Education And Training...
Addis Ababa City Administration Technical, Vocational, Education And Training...Addis Ababa City Administration Technical, Vocational, Education And Training...
Addis Ababa City Administration Technical, Vocational, Education And Training...
Haileyesus Wondwossen
 
Case study furniture industry
Case study   furniture industryCase study   furniture industry
Case study furniture industry
Ganesh TN
 
Mechanical maintenance-of-cement-rotary-kiln
Mechanical maintenance-of-cement-rotary-kilnMechanical maintenance-of-cement-rotary-kiln
Mechanical maintenance-of-cement-rotary-kiln
mkpq pasha
 
The Performance Analysis of a Fettling Shop Using Simulation
The Performance Analysis of a Fettling Shop Using SimulationThe Performance Analysis of a Fettling Shop Using Simulation
The Performance Analysis of a Fettling Shop Using Simulation
IOSR Journals
 
Pl and material
Pl and materialPl and material
Pl and material
ShkelzenShabani3
 
Reformation in Existing Micro Size Laundry System by using Product Design and...
Reformation in Existing Micro Size Laundry System by using Product Design and...Reformation in Existing Micro Size Laundry System by using Product Design and...
Reformation in Existing Micro Size Laundry System by using Product Design and...
IRJET Journal
 
Plant Layout
Plant LayoutPlant Layout
Plant Layout
Snigdha Vashishth
 
Intec Business Plan
Intec Business PlanIntec Business Plan
Intec Business Planrashmichatur
 

Similar to An Analysis Of Layout Planning (20)

Application of value stream mapping tool to reduce wastes in bearing industry
Application of value stream mapping tool to reduce wastes in bearing industryApplication of value stream mapping tool to reduce wastes in bearing industry
Application of value stream mapping tool to reduce wastes in bearing industry
 
processes : from raw bauxite to refractory alumina bricks
processes : from raw bauxite to refractory alumina bricksprocesses : from raw bauxite to refractory alumina bricks
processes : from raw bauxite to refractory alumina bricks
 
IARE_PLMH_PPT.pdf
IARE_PLMH_PPT.pdfIARE_PLMH_PPT.pdf
IARE_PLMH_PPT.pdf
 
Lecture_1_J_Tanyanyiwa.pptx
Lecture_1_J_Tanyanyiwa.pptxLecture_1_J_Tanyanyiwa.pptx
Lecture_1_J_Tanyanyiwa.pptx
 
IRJET-Production of Hybrid Aluminium Matrix Composite with Welding Slag and F...
IRJET-Production of Hybrid Aluminium Matrix Composite with Welding Slag and F...IRJET-Production of Hybrid Aluminium Matrix Composite with Welding Slag and F...
IRJET-Production of Hybrid Aluminium Matrix Composite with Welding Slag and F...
 
Study of Fabrication of Multipurpose Tooling Machine
Study of Fabrication of Multipurpose Tooling MachineStudy of Fabrication of Multipurpose Tooling Machine
Study of Fabrication of Multipurpose Tooling Machine
 
Designing Facility Layout and Effective Material Handling for a Ceramic Insul...
Designing Facility Layout and Effective Material Handling for a Ceramic Insul...Designing Facility Layout and Effective Material Handling for a Ceramic Insul...
Designing Facility Layout and Effective Material Handling for a Ceramic Insul...
 
CLUTCH BELL EDITED
CLUTCH BELL EDITEDCLUTCH BELL EDITED
CLUTCH BELL EDITED
 
DG KHAN CEMENT
DG KHAN CEMENT DG KHAN CEMENT
DG KHAN CEMENT
 
Lay out
Lay outLay out
Lay out
 
Finalelectricalreport
FinalelectricalreportFinalelectricalreport
Finalelectricalreport
 
Addis Ababa City Administration Technical, Vocational, Education And Training...
Addis Ababa City Administration Technical, Vocational, Education And Training...Addis Ababa City Administration Technical, Vocational, Education And Training...
Addis Ababa City Administration Technical, Vocational, Education And Training...
 
Case study furniture industry
Case study   furniture industryCase study   furniture industry
Case study furniture industry
 
Mechanical maintenance-of-cement-rotary-kiln
Mechanical maintenance-of-cement-rotary-kilnMechanical maintenance-of-cement-rotary-kiln
Mechanical maintenance-of-cement-rotary-kiln
 
The Performance Analysis of a Fettling Shop Using Simulation
The Performance Analysis of a Fettling Shop Using SimulationThe Performance Analysis of a Fettling Shop Using Simulation
The Performance Analysis of a Fettling Shop Using Simulation
 
Pl and material
Pl and materialPl and material
Pl and material
 
Pmm
PmmPmm
Pmm
 
Reformation in Existing Micro Size Laundry System by using Product Design and...
Reformation in Existing Micro Size Laundry System by using Product Design and...Reformation in Existing Micro Size Laundry System by using Product Design and...
Reformation in Existing Micro Size Laundry System by using Product Design and...
 
Plant Layout
Plant LayoutPlant Layout
Plant Layout
 
Intec Business Plan
Intec Business PlanIntec Business Plan
Intec Business Plan
 

More from Dereck Downing

How To Write Dialogue A Master List Of Grammar Techniques
How To Write Dialogue A Master List Of Grammar TechniquesHow To Write Dialogue A Master List Of Grammar Techniques
How To Write Dialogue A Master List Of Grammar Techniques
Dereck Downing
 
Writing Paper Service Educational Blog Secrets To Writing Blog Even
Writing Paper Service Educational Blog Secrets To Writing Blog EvenWriting Paper Service Educational Blog Secrets To Writing Blog Even
Writing Paper Service Educational Blog Secrets To Writing Blog Even
Dereck Downing
 
Scholarship Essay Essays Terrorism
Scholarship Essay Essays TerrorismScholarship Essay Essays Terrorism
Scholarship Essay Essays Terrorism
Dereck Downing
 
Best Nursing Essay Writing Services - Essay Help Online
Best Nursing Essay Writing Services - Essay Help OnlineBest Nursing Essay Writing Services - Essay Help Online
Best Nursing Essay Writing Services - Essay Help Online
Dereck Downing
 
The Federalist Papers By Alexander Hamilton Over
The Federalist Papers By Alexander Hamilton OverThe Federalist Papers By Alexander Hamilton Over
The Federalist Papers By Alexander Hamilton Over
Dereck Downing
 
Example Of Acknowledgment
Example Of AcknowledgmentExample Of Acknowledgment
Example Of Acknowledgment
Dereck Downing
 
Writing Paper Or Write My Paper -
Writing Paper Or Write My Paper -Writing Paper Or Write My Paper -
Writing Paper Or Write My Paper -
Dereck Downing
 
Observation Report-1
Observation Report-1Observation Report-1
Observation Report-1
Dereck Downing
 
Third Person Narrative Essay - First, Second, And Third-Person Points
Third Person Narrative Essay - First, Second, And Third-Person PointsThird Person Narrative Essay - First, Second, And Third-Person Points
Third Person Narrative Essay - First, Second, And Third-Person Points
Dereck Downing
 
007 Apa Essay Format Example Thatsnotus
007 Apa Essay Format Example Thatsnotus007 Apa Essay Format Example Thatsnotus
007 Apa Essay Format Example Thatsnotus
Dereck Downing
 
Writing Paper - Etsy
Writing Paper - EtsyWriting Paper - Etsy
Writing Paper - Etsy
Dereck Downing
 
Research Paper For Cheap, Papers Online Essay
Research Paper For Cheap, Papers Online EssayResearch Paper For Cheap, Papers Online Essay
Research Paper For Cheap, Papers Online Essay
Dereck Downing
 
Law Essay Example CustomEssayMeister.Com
Law Essay Example CustomEssayMeister.ComLaw Essay Example CustomEssayMeister.Com
Law Essay Example CustomEssayMeister.Com
Dereck Downing
 
Good Introductions For Research Papers. How To
Good Introductions For Research Papers. How ToGood Introductions For Research Papers. How To
Good Introductions For Research Papers. How To
Dereck Downing
 
How To Write Better Essays - Ebooksz
How To Write Better Essays - EbookszHow To Write Better Essays - Ebooksz
How To Write Better Essays - Ebooksz
Dereck Downing
 
Handwriting Without Tears Worksheets Free Printable Fr
Handwriting Without Tears Worksheets Free Printable FrHandwriting Without Tears Worksheets Free Printable Fr
Handwriting Without Tears Worksheets Free Printable Fr
Dereck Downing
 
Inspirational Quotes For Writers. QuotesGram
Inspirational Quotes For Writers. QuotesGramInspirational Quotes For Writers. QuotesGram
Inspirational Quotes For Writers. QuotesGram
Dereck Downing
 
What Is Abstract In Research. H
What Is Abstract In Research. HWhat Is Abstract In Research. H
What Is Abstract In Research. H
Dereck Downing
 
Anecdotes Are Commonly Use
Anecdotes Are Commonly UseAnecdotes Are Commonly Use
Anecdotes Are Commonly Use
Dereck Downing
 
Synthesis Journal Example. Synthesis Examples. 2022-1
Synthesis Journal Example. Synthesis Examples. 2022-1Synthesis Journal Example. Synthesis Examples. 2022-1
Synthesis Journal Example. Synthesis Examples. 2022-1
Dereck Downing
 

More from Dereck Downing (20)

How To Write Dialogue A Master List Of Grammar Techniques
How To Write Dialogue A Master List Of Grammar TechniquesHow To Write Dialogue A Master List Of Grammar Techniques
How To Write Dialogue A Master List Of Grammar Techniques
 
Writing Paper Service Educational Blog Secrets To Writing Blog Even
Writing Paper Service Educational Blog Secrets To Writing Blog EvenWriting Paper Service Educational Blog Secrets To Writing Blog Even
Writing Paper Service Educational Blog Secrets To Writing Blog Even
 
Scholarship Essay Essays Terrorism
Scholarship Essay Essays TerrorismScholarship Essay Essays Terrorism
Scholarship Essay Essays Terrorism
 
Best Nursing Essay Writing Services - Essay Help Online
Best Nursing Essay Writing Services - Essay Help OnlineBest Nursing Essay Writing Services - Essay Help Online
Best Nursing Essay Writing Services - Essay Help Online
 
The Federalist Papers By Alexander Hamilton Over
The Federalist Papers By Alexander Hamilton OverThe Federalist Papers By Alexander Hamilton Over
The Federalist Papers By Alexander Hamilton Over
 
Example Of Acknowledgment
Example Of AcknowledgmentExample Of Acknowledgment
Example Of Acknowledgment
 
Writing Paper Or Write My Paper -
Writing Paper Or Write My Paper -Writing Paper Or Write My Paper -
Writing Paper Or Write My Paper -
 
Observation Report-1
Observation Report-1Observation Report-1
Observation Report-1
 
Third Person Narrative Essay - First, Second, And Third-Person Points
Third Person Narrative Essay - First, Second, And Third-Person PointsThird Person Narrative Essay - First, Second, And Third-Person Points
Third Person Narrative Essay - First, Second, And Third-Person Points
 
007 Apa Essay Format Example Thatsnotus
007 Apa Essay Format Example Thatsnotus007 Apa Essay Format Example Thatsnotus
007 Apa Essay Format Example Thatsnotus
 
Writing Paper - Etsy
Writing Paper - EtsyWriting Paper - Etsy
Writing Paper - Etsy
 
Research Paper For Cheap, Papers Online Essay
Research Paper For Cheap, Papers Online EssayResearch Paper For Cheap, Papers Online Essay
Research Paper For Cheap, Papers Online Essay
 
Law Essay Example CustomEssayMeister.Com
Law Essay Example CustomEssayMeister.ComLaw Essay Example CustomEssayMeister.Com
Law Essay Example CustomEssayMeister.Com
 
Good Introductions For Research Papers. How To
Good Introductions For Research Papers. How ToGood Introductions For Research Papers. How To
Good Introductions For Research Papers. How To
 
How To Write Better Essays - Ebooksz
How To Write Better Essays - EbookszHow To Write Better Essays - Ebooksz
How To Write Better Essays - Ebooksz
 
Handwriting Without Tears Worksheets Free Printable Fr
Handwriting Without Tears Worksheets Free Printable FrHandwriting Without Tears Worksheets Free Printable Fr
Handwriting Without Tears Worksheets Free Printable Fr
 
Inspirational Quotes For Writers. QuotesGram
Inspirational Quotes For Writers. QuotesGramInspirational Quotes For Writers. QuotesGram
Inspirational Quotes For Writers. QuotesGram
 
What Is Abstract In Research. H
What Is Abstract In Research. HWhat Is Abstract In Research. H
What Is Abstract In Research. H
 
Anecdotes Are Commonly Use
Anecdotes Are Commonly UseAnecdotes Are Commonly Use
Anecdotes Are Commonly Use
 
Synthesis Journal Example. Synthesis Examples. 2022-1
Synthesis Journal Example. Synthesis Examples. 2022-1Synthesis Journal Example. Synthesis Examples. 2022-1
Synthesis Journal Example. Synthesis Examples. 2022-1
 

Recently uploaded

A Survey of Techniques for Maximizing LLM Performance.pptx
A Survey of Techniques for Maximizing LLM Performance.pptxA Survey of Techniques for Maximizing LLM Performance.pptx
A Survey of Techniques for Maximizing LLM Performance.pptx
thanhdowork
 
Acetabularia Information For Class 9 .docx
Acetabularia Information For Class 9  .docxAcetabularia Information For Class 9  .docx
Acetabularia Information For Class 9 .docx
vaibhavrinwa19
 
Unit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdfUnit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdf
Thiyagu K
 
JEE1_This_section_contains_FOUR_ questions
JEE1_This_section_contains_FOUR_ questionsJEE1_This_section_contains_FOUR_ questions
JEE1_This_section_contains_FOUR_ questions
ShivajiThube2
 
Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
Celine George
 
Digital Artifact 2 - Investigating Pavilion Designs
Digital Artifact 2 - Investigating Pavilion DesignsDigital Artifact 2 - Investigating Pavilion Designs
Digital Artifact 2 - Investigating Pavilion Designs
chanes7
 
Best Digital Marketing Institute In NOIDA
Best Digital Marketing Institute In NOIDABest Digital Marketing Institute In NOIDA
Best Digital Marketing Institute In NOIDA
deeptiverma2406
 
S1-Introduction-Biopesticides in ICM.pptx
S1-Introduction-Biopesticides in ICM.pptxS1-Introduction-Biopesticides in ICM.pptx
S1-Introduction-Biopesticides in ICM.pptx
tarandeep35
 
The Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptxThe Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptx
DhatriParmar
 
Chapter 3 - Islamic Banking Products and Services.pptx
Chapter 3 - Islamic Banking Products and Services.pptxChapter 3 - Islamic Banking Products and Services.pptx
Chapter 3 - Islamic Banking Products and Services.pptx
Mohd Adib Abd Muin, Senior Lecturer at Universiti Utara Malaysia
 
Francesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptxFrancesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptx
EduSkills OECD
 
Synthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptxSynthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptx
Pavel ( NSTU)
 
How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...
Jisc
 
Executive Directors Chat Leveraging AI for Diversity, Equity, and Inclusion
Executive Directors Chat  Leveraging AI for Diversity, Equity, and InclusionExecutive Directors Chat  Leveraging AI for Diversity, Equity, and Inclusion
Executive Directors Chat Leveraging AI for Diversity, Equity, and Inclusion
TechSoup
 
"Protectable subject matters, Protection in biotechnology, Protection of othe...
"Protectable subject matters, Protection in biotechnology, Protection of othe..."Protectable subject matters, Protection in biotechnology, Protection of othe...
"Protectable subject matters, Protection in biotechnology, Protection of othe...
SACHIN R KONDAGURI
 
The basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptxThe basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptx
heathfieldcps1
 
How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17
Celine George
 
Pride Month Slides 2024 David Douglas School District
Pride Month Slides 2024 David Douglas School DistrictPride Month Slides 2024 David Douglas School District
Pride Month Slides 2024 David Douglas School District
David Douglas School District
 
South African Journal of Science: Writing with integrity workshop (2024)
South African Journal of Science: Writing with integrity workshop (2024)South African Journal of Science: Writing with integrity workshop (2024)
South African Journal of Science: Writing with integrity workshop (2024)
Academy of Science of South Africa
 
Digital Artifact 1 - 10VCD Environments Unit
Digital Artifact 1 - 10VCD Environments UnitDigital Artifact 1 - 10VCD Environments Unit
Digital Artifact 1 - 10VCD Environments Unit
chanes7
 

Recently uploaded (20)

A Survey of Techniques for Maximizing LLM Performance.pptx
A Survey of Techniques for Maximizing LLM Performance.pptxA Survey of Techniques for Maximizing LLM Performance.pptx
A Survey of Techniques for Maximizing LLM Performance.pptx
 
Acetabularia Information For Class 9 .docx
Acetabularia Information For Class 9  .docxAcetabularia Information For Class 9  .docx
Acetabularia Information For Class 9 .docx
 
Unit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdfUnit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdf
 
JEE1_This_section_contains_FOUR_ questions
JEE1_This_section_contains_FOUR_ questionsJEE1_This_section_contains_FOUR_ questions
JEE1_This_section_contains_FOUR_ questions
 
Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
 
Digital Artifact 2 - Investigating Pavilion Designs
Digital Artifact 2 - Investigating Pavilion DesignsDigital Artifact 2 - Investigating Pavilion Designs
Digital Artifact 2 - Investigating Pavilion Designs
 
Best Digital Marketing Institute In NOIDA
Best Digital Marketing Institute In NOIDABest Digital Marketing Institute In NOIDA
Best Digital Marketing Institute In NOIDA
 
S1-Introduction-Biopesticides in ICM.pptx
S1-Introduction-Biopesticides in ICM.pptxS1-Introduction-Biopesticides in ICM.pptx
S1-Introduction-Biopesticides in ICM.pptx
 
The Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptxThe Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptx
 
Chapter 3 - Islamic Banking Products and Services.pptx
Chapter 3 - Islamic Banking Products and Services.pptxChapter 3 - Islamic Banking Products and Services.pptx
Chapter 3 - Islamic Banking Products and Services.pptx
 
Francesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptxFrancesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptx
 
Synthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptxSynthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptx
 
How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...
 
Executive Directors Chat Leveraging AI for Diversity, Equity, and Inclusion
Executive Directors Chat  Leveraging AI for Diversity, Equity, and InclusionExecutive Directors Chat  Leveraging AI for Diversity, Equity, and Inclusion
Executive Directors Chat Leveraging AI for Diversity, Equity, and Inclusion
 
"Protectable subject matters, Protection in biotechnology, Protection of othe...
"Protectable subject matters, Protection in biotechnology, Protection of othe..."Protectable subject matters, Protection in biotechnology, Protection of othe...
"Protectable subject matters, Protection in biotechnology, Protection of othe...
 
The basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptxThe basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptx
 
How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17
 
Pride Month Slides 2024 David Douglas School District
Pride Month Slides 2024 David Douglas School DistrictPride Month Slides 2024 David Douglas School District
Pride Month Slides 2024 David Douglas School District
 
South African Journal of Science: Writing with integrity workshop (2024)
South African Journal of Science: Writing with integrity workshop (2024)South African Journal of Science: Writing with integrity workshop (2024)
South African Journal of Science: Writing with integrity workshop (2024)
 
Digital Artifact 1 - 10VCD Environments Unit
Digital Artifact 1 - 10VCD Environments UnitDigital Artifact 1 - 10VCD Environments Unit
Digital Artifact 1 - 10VCD Environments Unit
 

An Analysis Of Layout Planning

  • 1. i DSC 2322 – Operations Management Project Report By R.B.K.K.B.Jamarasinghe (MC/63751),(CPM 8344) L.E.M.Kaushalya (MC/63814),(CPM 8407) K.V.C.I.Kumarasinghe (MC/63855),(CPM 8448) W.K.H.Lakshan (MC/63878),(CPM 8471) U.A.M.M.Perera (MC/64032),(CPM 8625) R.M.A.Y.I.Rathnayake (MC/64102),(CPM 8695) H.R.S.Sandamali (MC/64143),(CPM 8736) S.G.P.Sandaruwan (MC/64148),(CPM 8741) R.M.T.D.Senevirathne (MC/64177),(CPM 8770) D.P.Wickramanayake (MC/64285),(CPM 8878) An Analysis of Layout Planning of Royal CeramicPLC A project report submitted in partial fulfillment of requirements of the subject DSC 2322 – Operations Management conducted by the Department of Decision Sciences of the Faculty of Management Studies and Commerce of the University of Sri Jayewardenepura 2012
  • 2. ii ABSTRACT The purpose of this report is to study regarding the Layout Planning of Royal Porcelain (Private) Ltd which is afully owned subsidiary of Royal ceramics lanka PLC. They manufacture and distribute porcelain tiles under the well-known brand name “Rocell”. This factory was started by a foreign investor in early 90’s and abandoned the plant due to some technical failures almost at the inception. Then Rocell has acquired this plant and started operations by correcting those technical failures. Rocell has two main tile manufacturing plants in Horana and Ehaliyagoda. Horana plant is the smallest one with daily production capacity of 1000 square foot. Rocell is the leading tile maker in Sri Lanka and they stand for both highest quality and elegant designs. For our study we focused our attention on Layout Planning. Layout has numerous strategic implications because it establishes an organization’s competitive priorities with regard to capacity, processes, flexibility and cost, quality of work life, customer contact and image. Through our study we identified strengths & weaknesses of the existing layout of the Royal porcelain (Private) Ltd as follows. Their strengths are having a screen printing machine which can digitally print designs which helps to produce tiles with different designs, having adjustable press machines which can press differentsizes of tiles and having adjustable production lines which can be adjusted according to the tile size. Weaknesses of the existing layout plan of Royal porcelain (Private) Ltd is not having an emergency exit in the factory, having a defect rate of vary in between 8%-10% and not having enough space to add additional production lines. In order to increase the strengths & eliminate the weaknesses our major recommendations is to establish a separate primary plant to process raw material in order to reduce current higher defect rate.
  • 3. iii Table of Contents 01. INTRODUCTION ...............................................................................................................1 02. SELECTED FUNCTION WITHIN THE ORGANIZATION ............................................1 03.LITERATURE......................................................................................................................2 04. DETAILED ANALYSIS OF THE PRODUCTION( see appendix 2)................................3 05. RECOMMENDATION.......................................................................................................6 06. CONCLUSION....................................................................................................................7 APPENDICES REFERENCES
  • 4. 1 01. INTRODUCTION As management students, knowledge & application about operations management is extremely critical in this dynamic business environment to be successful business leaders in the future. Within the class room, discussing the application part of the theories are much difficult because different organizations use unique way to apply theories to their own operations. Therefore as part of our study program we are expected to gain the knowledge about real world applications of theories. To study the real world business scenarios we went to a tile manufacturing plant located in Horana which is owned by Royal Porcelain (Private) Ltd a fully owned subsidiary of Royal ceramics lanka PLC. They manufacture and distribute porcelain tiles under the well-known brand name “Rocell”. This factory was started by a local investor in early 90’s and abandoned the plant due to some technical failures almost at the inception. Then Rocell has acquired this plant and started operations by correcting those technical failures. Rocell has two main tile manufacturing plants. And the Horana factory is the smallest one with daily production capacity of 1000 square foot. Rocell is the leading tile maker in Sri Lanka and they stand for both highest quality and elegant designs. 02. SELECTED FUNCTION WITHIN THE ORGANIZATION Our study mainly focuses on Plant layout and the product layout of the factory. Plant layout consists of two warehouses, one for raw material and for finished goods. Raw material warehouse has the capability of storing raw materials needed for 2 ½ months production. And the finished good warehouse has a capacity of keeping one week production. The manufacturing plant can be divided in two main parts for ease the analysis. The primary plant prepares the raw material mixture needed to make the tiles and has a daily capacity of 7200kg. This factory has 3 production belts in secondary plant and capable of manufacturing 3 different variety of tile at once (one belt only one tile at a given time). Each belt has separate kiln powered by gas. Kiln is the major constraint in this plant and these 3 belts capable of manufacturing 10000 square foot per day. This factory continuously operates 24 hours in 365 days to avoid huge shutdown and start-up costs (specially kiln). And the monthly energy cost is approximately 100 million rupees (both electricity & LP gas). The defect rate fluctuates in between 8%-10%. These 3 production belts are fully automated and human contribution to the production is very minimum. Plant only has 21 workers.
  • 5. 2 03. LITERATURE Operations management is one of the most critical functions in any organization. Under this function planning a proper facility layout is very essential for smooth work flow. This is called as Layout Planning. This involves deciding where to put all the facilities machines, equipment, departments & staff in order to continue the manufacturing process more efficient. Keeping a proper layout within the organization affects the efficiency of the material utilization, machines utilization, attitudes of the employees and the customers positively. It reduces the cost of material usage, reduces the movements of the materials and the employees & improves the flexibility. A layout planning is an arrangement of everything needed for production of goods or delivery of services or it can be defined as arrangement of machine tool, a work centre, a manufacturing cell, a machine shop, a department, a warehouse, etc. In practical world there are several types of layout formats within an organization. Among those different layout formats this study is only focused on plant layout and the product layout of the Rocell tile manufacturing plant situated in Horana. Plant Layout Plant layout refers to the arrangement of physical facilities such as machines, equipment, tools, furniture etc. in such a manner so as to have quickest flow of material at the lowest cost and with the least amount of material handling in processing the product from the receipt of raw material to the delivery of the final product. Primary objectives of plant layout should be:  Minimal material handling costs.  Minimal investments.  Minimal throughput time.  Flexibility.  Efficient use of space.  Reduce accidents.  Reduce hazards to personnel. Product Layout Product layout is also called flow-shop or straight line layout. It involves the arrangement of equipment according to the progressive steps by which a product is made. Raw materials are fed continuously into the first machine and thereafter it passes through subsequent operations rapidly while the finished products are coming out from the last one.
  • 6. 3 04. DETAILED ANALYSIS OF THE PRODUCTION (see appendix 2) An analysis of the production with it'ssteps and the strengths & weaknesses of the process are discussed below. No 01:Raw material warehouse Manufacturing process begins in the warehouse where the raw materials are received and stored. No 02: Weighting Scale Using weighting scale, raw materials are measured according to the pre-determined standards.After that the raw materials are transported to the grinding mill via conveyor belts. No 03:Mill The mills grind the raw materials in water to obtain slurry required for pressing. The mills are large cylindrical containers that work 24 hours per day. No 04:Under Tank The slurry is transported to the under tank. Then the litter contaminated to the bottom of the tank. Then the slurry is passed through magnetic field in order to remove unwanted litter. Then slurry is passed to spray dryer tanks. No 05:Tanks Tanks contain all the liquid which remove any remaining litter. Then it passes to spray dryer. No 06:Spray Dryer Spray drying is an extremely important stage in manufacturing process. Spray dryer convert slurry into an atomized powder ready to be pressed. No 07:Belt The powder passes to two tanks which can contain buffer stock. Then powder is pumped to the pressing machines. No 08:Pressing Pressing is the shaping process used for porcelain tile. First air is removed from the powder. A pressure of more than 7500 PSI is used to definitively compact each round shaped practical in the body. No 09:Drying. The drying operation is important to eliminate the moisture from the suppressed products. The fast, hot, vertical and horizontal air dryers are located to achieve heating of material. No 10:Glazing
  • 7. 4 Glazing is the production phase where two coats of color are applied on the surface of the product before it is fired. This phase consists of printing a given design. First paint is applied on the slab by a water fall system and then design is printed on the surface of the tile using the cylinders which gives a unique design to each tile. No 11:Protection Layout Protection Layoutis poured to the surface of the tile. No12:Car System Transport painted tiles to the kiln. No 13:Firing Firing is the major stage of the production process. Firing operation is carried out continuously using three layer kilns. No 14:Robot Arms Fired tiles are punched by 3 robot arms at the end of firing process and arrange them on the floor in order to transport to the inventory handling area. No 15:Sorting Next phase of the process is sorting. The main objective of the sorting is elimination of defective tiles with inferior quality. No 16: Packaging Tiles are automatically packed in special cardboard cartoons according to computerized instructions. No17:Warehousing The packed tiles are transported to the warehouse. Strengths of the product and plant layout 1. One production belt consists ofa screen printing machine which can digitally print designs on the surface of tiles. It adds further flexibility to the plant. 2. Plant consists of adjustable press machines, which can press different size of tiles.According to the size of the pressing tile, entire production line can be adjusted. 3.Raw material warehouse is capable of keeping raw materials which can be used for 2 ½ month production. 4. Primary plant has an excess storing capacity and it is enough to operate 9.6 hours if any breakdown occurs in the primary plant. (See appendix 1) 4. Digital scanners are used to sort tiles which ensure no defect tile goes to the market
  • 8. 5 5. Horana plant is located in a strategically valuable point since it is by the Colombo-Gall highway. Asaresult,there is quick access to Colombo (main market) and both Colombo and Hambanthota ports. 6. Sunlight is being used for day production through transparent roof sheets; it saves the electricity power in the day time. 7.All machineriesare made by world renowned Italian and American manufactures for tile machinery. Weaknesses of the product and plant layout 1. One entry route is used for both entrances to the plant & exit from the plant. 2. Defect rate of the plant vary in between 8%-10%. As a result, amount of energy wasted approximately is 7 million rupees per month. (See appendix 2) 3.There is no proper safety in the plant,because jumbled wires are lying everywhere. 4. There is a high possibility of strong sudden fire since plant heavily uses LP gas. Theexisting firefighting system is not adequate to prevent a strong sudden fire. 5. They are not in a position to expand their production by adding additional product lines to the layout. So it is difficult to get the maximum advantages from their strategically valuable location. 6. Weight scale is used to weight the raw material which is essential for preparing the mixture according to the standard ratio. There is only one weight scale in the plant. Therefore if the weight scale breaks down whole production process have to be stopped. There is no alternative for the weight scale. 7. Since plant is arranged according to the product layout, if a breakdown occurs at any given point whole production line have to be stopped. 8. The factory & the office have been established close to each other. It cannot be seen as a good thing because in an emergency situation, as an example in a fire, office premise will be affected by the fire. 9. As there is a distance between the finished goods store & factory it is difficult to move finished goods from factory to stores in rainy days. 10. They handle a buffer stock of raw materials for two months. Two months buffer stock is too much when compared with the capacity of the factory.
  • 9. 6 05. RECOMMENDATION Major Recommendation Major cause behind 10%-8% high defect rate is the unprocessed (not refined materials) raw material used for production. Therefore major recommendation is targeted towards reducing such significant defect rate. Rocell should use processed raw material for the production. But there is no additional space in the current plant to refine raw material. The only option is to establish a separate plant for processing raw material. Rocell has another plant for manufacturing tiles in Ehaliyagoda. Horana plant and Ehaliyagoda plant are located close to each other. Therefore they should find a land somewhere between Ehaliyagoda& Horana and build up a separate factory for processing material and preparing powder needed for production of tiles. As a result manufacturing plant can focus on production and new plant can focus on quality of the raw material and powder. This approach is heavily used by Japanese and Italian tile makers and they have reduced their defect rate to 1%-2%. If the proposed approach is implemented a prevailing bottleneck will be eliminated which facilitates to achieve long term flexibility as a group. Recommendation for the plant layout 1. Production lines should be arranged vertically. That is, kiln and sorting lines should be established vertical to the earlier parts of the production line. It helps to utilize factory space more efficiently and achieve long term flexibility. (see appendix 3) 2. Strong fire fighter system should be established to face strong sudden fires. 3. Since plant has high exposure to sudden strong fire emergency doors should be established. (see appendix 3) 4. Finished goods warehouse should be established closer to the main manufacturing line. It will reduce unnecessary material handling cost. (see appendix 1) 5. LED lighting system should be placed for night shifts of production. It will help to reduce the electricity cost of the factory. 6. High pressure water posts should be placed around the plant to fight against strong fires. 7. Separate entry and exit routes should be established to enter the plant and exit from the plant. It will help to minimize risk and allow smooth flow of material and finished goods within the factory.
  • 10. 7 06. CONCLUSION Analysis reveals that there are lots of inefficiencies within the plant than strengths. Top management mainly focuses about product design and marketing activities and they pay little attention to improve production efficiencies. Currently 10% abnormal loss is charged from customers. And the main cause behind such significant defect rate is of using unprocessed raw materials to prepare raw material powder and during the production,defects occur as a result of that. As shown in appendix 1, within the current plant location, there is no additional space available to process raw materials. Therefore the only option available to reduce such significant defect rate is establishing a separate plant for making the raw material powder and this technique is highly practiced by Japanese firms and they have reduced their defect rate up to 1% to 2%. Further, when analyzing the primary plant it can supports onlyone extra belt. But no more than that. By shifting this primary plant to another location company can eliminate a major bottle neck within their plant. This is vital to increase the longer term capacity of the plant. The smooth inflow of high quality processed raw material powder to the plant will help to reduce their defect rate up to 1% to 2%. And this would be essential to achieve cost leadership in the market. The proposed approach will help the existing plant to focuson product design and the quality of the production. It will reduce the burden on management also. With the low cost and long term flexibility within the proposed plant "Rocell" can achieve sustainable growth in the future. As shown in the appendix 5 plant would be able to reduce their defect rate up to 1%-2%. And the energy cost saving would be 71.4 million per annum. According to the project appraisal shown in appendix 6 this project generates a positive NPV of Rs. 99.1 million even we have used 5 year project duration. (In reality benefits would be perpetual) Therefore the project should be accepted and implemented.
  • 11. 8
  • 12. 9
  • 13. 10
  • 14. 11 Appendix 4 Primary plant capacity analysis 1mn * 5Kg * 60 * 24 =7200Kg/day  Full capacity( 1 minute 5kg output) 7200/ 0.7 = 5040 Kg use( 70% uses for daily production) 7200-5040 =2160Kg extra (Hence buffer stock in kg) 7.2/ hr buffer( buffer stock in hours) Appendix 5 Financial benefits Current energy cost – 70 million per month (only for LP gas) Loss of energy due to defect rate = 70 million * 0.1 = 7 million Major reason behind effects rate is the unprocessed raw materials. If raw processed materials are used for production, defect rate would be in between 1%-2%. Hence maximum energy cost saving = 70 million * 0.09 = 6.3 million Minimum energy cost saving = 70 million * 0.8 = 5.6 million On average energy cost saving would be= 5.95 * 12= 71.4 million. Appendix 6 Initial investment Rs.500 million Capital allocation for existing plant* Rs.200 million Benefits: energy cost saving** + electricity saving + raw material saving Rs.100 million per annum NPV evaluated at 20% cost of capital in a 5 year duration =Annual saving * [1-(1+r)-n / r] – Initial investment Rs.99.1 million * Let’s assume they allocate Rs.200 million capital cost to current plant since it’s smaller than Ehaliyagoda plant ** Rs. 71.4 million directly from gas saving
  • 15. 12 References Books  Operation Management for Competitive Advantage, Richard B. Chase. Nichols J. Aquilano, F. Robbert Jacobs, 10th ed., Mcgraw-Hill, 2003. Web sites  Rocell Annual Report 2011  Rocell.com  You Tube.com