 Overview of NTPC
 Thermal power plant
 Process of power generation
 Major elements in TPP
 Control and Instrumentation
 Laboratories in C&I
 Pollution control systems
 Conclusion
 Bibliography
2
NTPC
 Founded by Government of India in 1975
 Known as “MAHARATNA” of India
 Current power generating capacity - 34,854 MW
 NTPC plants
 Coal based Plants - 17
 Gas based Plants - 07
 Planning to generate 75,000 MW by 2017
3
Thermal Power Plant
 A Thermal Power Plant converts the heat
energy of coal into electrical energy
 Power plant in which the prime mover
is steam driven
 Thermal Power Plants constitute 75.43%
of the total installed captive and non-captive
power generation in India
 In thermal generating stations coal, oil, natural gas etc. are employed as primary sources of
energy
4
Process of Power Generation 5
Electricity From Coal
Process of power generation.........
 Water Intake
 Boiler Heating
 Steam Turbine
 Generator
 Special Mountings
 Ash collection system
6
Elements of TPP
 D.M Plant
 Deaerator
 Boiler feed Pump
 Economizer
 Air Pre-Heater
 Boiler
 Super Heater
 Turbine
7
Control and Instrumentation
 Control and instrumentation in any process industry,
can be compared to the nerve system in the human being
 C&I, as the name indicates, is a branch in engineering
which deals with various measurement, indication,
transmission and control in different technical field.
 The main work is to observe, control and manipulate
electrical as well as non-electrical quantities like
temperature, pressure, vibrations.
8
Objectives of C & I
 Efficient Operation of the plant
 Economic Operation of the plant
 Safe operation of the plant
 Pollution control
9
Laboratories in C&I
 Manometry Lab
 Protection and Interlocks Lab
 Automation Lab
 Electronics Lab
 Water Treatment Plant
 Furnaces Safety Supervisory System Lab
10
POLLUTION CONTROL SYSTEMS
In order to ensure that NTPC comply with all the stipulated environment norms,
various pollution control systems / devices as discussed below have been installed to
control air and water pollution
 Electrostatic Precipitators
 Flue Gas Stacks
 Neutralization pits
 Cooling Towers
 Ash Water Recycling System
11
Conclusion
 Industrial training being an integral part of engineering curriculum provides not only easier
understanding but also helps acquaint an individual with technologies.
 It exposes an individual to practical aspect of all things which differ considerably from
theoretical models
 The training at NTPC Singrauli was all together an exotic experience, since work, culture and
mutual cooperation was excellent here
12
Bibliography
 “Company History – NTPC Ltd.”. Economic Times.
 “Power major NTPC lists at premium”. The Hindu.
 www.ntpc.co.in/NTPC singrauli Detail.
 www.hindustantimes.com/india-news/pm-dedicates-ntpc-power-plant-in-
singrauli/article1-1124296.
13
14

Ajay ntpc

  • 1.
    “Control and Instrumentation” A INDUSTRIALTRAINING PRESENTATION ON 1 Submitted To: Submitted By: Mr. Prabhakar Agarwal AJAY PRATAP SINGH Mr. Ashutosh Kumar Singh 1213331018 ECE - VII A
  • 2.
    CONTENT  Overview ofNTPC  Thermal power plant  Process of power generation  Major elements in TPP  Control and Instrumentation  Laboratories in C&I  Pollution control systems  Conclusion  Bibliography 2
  • 3.
    NTPC  Founded byGovernment of India in 1975  Known as “MAHARATNA” of India  Current power generating capacity - 34,854 MW  NTPC plants  Coal based Plants - 17  Gas based Plants - 07  Planning to generate 75,000 MW by 2017 3
  • 4.
    Thermal Power Plant A Thermal Power Plant converts the heat energy of coal into electrical energy  Power plant in which the prime mover is steam driven  Thermal Power Plants constitute 75.43% of the total installed captive and non-captive power generation in India  In thermal generating stations coal, oil, natural gas etc. are employed as primary sources of energy 4
  • 5.
    Process of PowerGeneration 5 Electricity From Coal
  • 6.
    Process of powergeneration.........  Water Intake  Boiler Heating  Steam Turbine  Generator  Special Mountings  Ash collection system 6
  • 7.
    Elements of TPP D.M Plant  Deaerator  Boiler feed Pump  Economizer  Air Pre-Heater  Boiler  Super Heater  Turbine 7
  • 8.
    Control and Instrumentation Control and instrumentation in any process industry, can be compared to the nerve system in the human being  C&I, as the name indicates, is a branch in engineering which deals with various measurement, indication, transmission and control in different technical field.  The main work is to observe, control and manipulate electrical as well as non-electrical quantities like temperature, pressure, vibrations. 8
  • 9.
    Objectives of C& I  Efficient Operation of the plant  Economic Operation of the plant  Safe operation of the plant  Pollution control 9
  • 10.
    Laboratories in C&I Manometry Lab  Protection and Interlocks Lab  Automation Lab  Electronics Lab  Water Treatment Plant  Furnaces Safety Supervisory System Lab 10
  • 11.
    POLLUTION CONTROL SYSTEMS Inorder to ensure that NTPC comply with all the stipulated environment norms, various pollution control systems / devices as discussed below have been installed to control air and water pollution  Electrostatic Precipitators  Flue Gas Stacks  Neutralization pits  Cooling Towers  Ash Water Recycling System 11
  • 12.
    Conclusion  Industrial trainingbeing an integral part of engineering curriculum provides not only easier understanding but also helps acquaint an individual with technologies.  It exposes an individual to practical aspect of all things which differ considerably from theoretical models  The training at NTPC Singrauli was all together an exotic experience, since work, culture and mutual cooperation was excellent here 12
  • 13.
    Bibliography  “Company History– NTPC Ltd.”. Economic Times.  “Power major NTPC lists at premium”. The Hindu.  www.ntpc.co.in/NTPC singrauli Detail.  www.hindustantimes.com/india-news/pm-dedicates-ntpc-power-plant-in- singrauli/article1-1124296. 13