SlideShare a Scribd company logo
Close-out ABO Extension Project
       Nigeria -OML 125
    Major project milestones
  – Ennio Nitti – Engineering Manager Nigerian projects- San
                        Donato Milanese –
                      End of March 2008
OML 125 -ABO Extension project



              Field production avg data per year during ABO Ext Phase
                         Green line: produced gas consumed for motive
                         power of FPSO
               50                                        Additional flow rate of ABO 10 .11 (March 2009 trend) approx 18.000 BOPD
               40
                       31,002                                                                          33,96
                                                                                                   28,8
               30                          25,147                   28,06
                                                26,48
                                                                                     23,83
                                                                                18,014
               20                                               16,816

               10

                0
                     Prod 2005         Prod 2006             Prod 2007       Prod 2008       Expected 2009
                                                                                                  March
                                                                                             (assuming 50%
                                                                                              production yr 2
                                                                                                from start)



                                                        Crude Avg Production
                                                        Gas injection trend (1 GI)


• Note – Approx Indication in Barrel Per Day for crude and MillionSCFD per injected or produced gas



                                                                                                                            2
OML 125 -ABO Extension project
                Location of Nae Block




                                        3
OML 125 -ABO Extension project




                   CHARACTERISTICS                                       DATA
                   Past Name / Present                    GREY WARRIOR / ABO
                   Name                                   FPSO
                                                                                                     ABO FPSO
                   Built in / Converted in                1976 / 2002

                   Length overall                         280,4 m

                   Breadth                                53,6 m
VESSEL MAIN DATA




                   Depth                                  20 m
                                                          160.000 Metric Tons
                   Dead weight
                                                          (approx)


                   Cargo oil tanks                        951.658 bbls
                   capacity


                             FPSO conversion an field positioning : 2002/2003 March ( Abo Central)


                                                                                                                4
OML 125 -ABO Extension project

Current Porch Configuration
  Riser hang-off systems were
  designed to be located at
  same FPSO side (even for
  future expansion)

  Hang-off of risers in a free
  hanging configuration from a
  deck balcony configuration


  Control Umbilical through
  I-Tube located on the vessel
  side (see red line)

  Total hang-off available
  systems:       5 + 4 (spares)
  for risers and 1 + 1 spare for
  umbilical



                                   5
ABO Extension = Schematic Block Diagram of the FPSO Facilities
                          (Receiving manifolds, separation, gas compression, oil handling, water handling)
           Data regarding actual design envelope for liquid expressed in BPD (Barrel per Day); for gas expressed in Million
                                                                SCFD
                                                     Design envelope:         Only from
                      Design envelope HP             44 Million SCFD +         Second             Design envelope:
                        Flare:49 Million                10% = 48,4           Compressor           48,4 Million SCFD
                             SCFD                      Million SCFD             Stage
      Heating       Utility and    Relief System     Fuel Gas                                     Fuel Gas
    System for     Instrument         to Flare     Reciprocating          Dehydration                for
    Oil Treating         Air         ( HP, LP)      Compressor               Glycol               Internal            Sea Water
                                                     (3*50%                Contactor              Process                Lift
        Fire                                                               Unit and
      Fighting                                     capacity ABO                                     Use
                                                   Central) over             Regen                 within
       Deluge                                                               Package
      System                                       Three Stages                                    FPSO
   Design envelope First Stage                           From 1st
    Separator: 40000 BPD +                                 Stage
     10% (= 44000 BPD) of                                Separato        Gas Handling
                                           Via Booster                                                Re-
    Liquid (Oil+Water) with a                                r           and 2*100 %                                                   Cooling for
                                           Compressor                                             Injection                                           Overboard
   Maximum Peak of Water of                                 only           Booster                                    Sea Water
                                                                                                    Water                              Compressor
    9000 BWPD + 44 Million                                               Compressors                                   Filtering
                                                                                                    Pumps                                and Oil
           SCFD of Gas                                                                                                                  Handling
                                                                                                   to Wells
            Well ABO 9                                        LP
                                                            Stages
          Well ABO 10                                                                           Design envelope
         Well ABO 11            Flow lines          Inlet Crude                                    Booster: 5,5
                                   and              separation                                 Million SCFD + 5,5
        Existing ABO            manifolds          (1st and 2nd           Oil Treating             Million SCFD
     Central; Wells 2,3,4       (1st, 2nd                                                                             Sea Water
                                                       Stage                   (i.e                                                Design envelope:
    Existing ABO Central;                                                                      Design envelope        Degassing
                                  stage)            Separators,           Stabilizing
           Wells 6,7                                                                          Crude Stabilization                     9000 BPD
                               interfacing         Electrostatic               and
     Abo Central Gas                                                                           : 40000 BLPD +
                              Subsea Risers        Dehydrator)            Desalting)
     Injector Well 5               and                                                          10% (= 44000
                                                                                               BLPD) + 5 Million
                               Umbilicals
                                                                                                  SCFD Gas
    Design envelope Test                                                  Design envelope
     Separator :17000              Chemical                              Hydrocyclons 12000
        BOPD+4000                  Injection                                    BPD                                   Sea Water
    BWPD+19000 MSCFD                                Produced               +12000 BPD as
                                    Skidded                                                      Crude Oil             Boosting
                                                      Water                    spare                                                 Design envelope:
                                   Units for                                                     Storaging               and
                                                    Treatment                                                                        30000 BPD + 10
 SEE SLIDE 4 FOR                  Subsea and                                                    within FPSO            Pumping
                                                                           Design envelope:                                                 %
INTERCONNECTION                    Topsides                                                                             System
                                                                           9000 BPD + 2000
    SEQUENCE                                                                  BPD from
                       Chemicals loading
                                                    Water Overboard            Desalting
                                                     30PPM Quality         (=11000 BPD) +
                                                                                                  Oil to Export
                                                                                 10%
                                                                                                      FPSO



                                                                                                                                                           6
OML 125 -ABO Extension project
                       Actual design parameters of ABO Topside
                                    Facilities FPSO
Design Parameter                                     Value / Policy

Life design of existing facilities                   10 years (starting from 2002)
Oil design flow rate                                 40000 BOPD + 10 % overdesign

Maximum design temperature process side              50 °C


Maximum design pressure at manifold inlet            21 barg
Design capacity of gas treatment                     44 MMscfd + 10% = 48.4 MMscfd

Gas injection line design                            42MMscfd + 10% (total 44 MMscfd at exit of 3rd stage
                                                     injection compressor when two trains operating in
                                                     parallel; one in stand by)

Maximum gas injection pressure at gas lift line to   250 barg (@ porch)
existing ABO_5
Gas Strategy                                         Gas reinjection into the Reservoir


Maximum water production handling flowrate           9000 BWPD; overboard water quality (Oil in Water)
                                                     discharged to sea: < 30 ppm




                                                                                                            7
Abo – Extension Project -OML 125
                Actual FPSO mooring system and existing flow lines arrangement
                               with indication of the new wells




                                      ABO 11c -producer

                                                ABO 9b –
                                              Gas injector
                               ABO 10- producer
proposed oordinates wells at
       sanctioning
ABO 9B 661919.0 E 631920.0 N
ABO 10 660343.7 E 631713.1 N
ABO11C 660653.0 E 632729.0 N
                                                             Mooring chain number 3
                                                             required to be lowered for
                                                             installation




                                                                                          8
OML 125 -ABO Extension project


                                                n
   TOPSIDE EVENTS MAJOR MILESTONES OF ABO
   EXTENSION




                                            9
OML 125 -ABO Extension project

  Project follow up by subcontractors from project start up
                       till completion

  The engineering “volume” of manhours associated with the extension works is
    as follow:

    Subsea EPC:                          manhours (Pm+Eng). Approx:                 75000
    Topsides-FPSO Vessel:                manhours (Pm + Eng):12000

    Engineering Follow -up:              manhours (13000)
    Installation contractor:             manhours (100000)


             Note :    Documents issued by Install contractor:  approx 220
                       Documents issued by Subsea EPC supplier: approx 500
                       Documents issued by FPSO owner: app. 150 (new); 330
                                                            (revision of exixting one)




                                                                                            10
Abo – Extension Project -OML 125




                                                Release 1_A of Nae
                                             3229.41.000.L.DL.FC88001
                                         Field lay-out without bathymetry
                           ABO 9b –Gas
                             injector
             Abo Ext




                                                                            11
Abo – Extension Project -OML 125




                                   12
Abo – Extension Project -OML 125



  Subsea lines scope of installation.

      Description   Service                  From       To           Length (m)
      RG2           GI riser                 FPSO       ABO-9        950
                    GI flowline              FPSO       ABO-9        1976
      R10           6” production riser      FPSO       ABO -10      850
                    6” production riser      FPSO       ABO -10      3630
      R11           6” production riser      FPSO       ABO -11      850
                    6” production riser      FPSO       ABO -11      3573
      F10-11        Pigging loop             ABO-10     ABO -11      1286
      UM2           Dynamic Umbilical        FPSO       UTA-UM2      2825
                    (including riser 745.5
                    m to TDP
      UP-10         Infield umbilical        UTA-UP10   UTA-UP10 B   1630
                                             A
      UP-11         Infield umbilical        UTA-UP11   UTA-UP11 B   1580
                                             A


                                                                                  13
Abo – Extension Project -OML 125
        Porch area:well connections

    AFT
    SIDE
                                                                               FORE SIDE
                                                                      New sequence approved during detailed
                                  DECK SIDE
                                                                                  engineering
                                                                       Abo   Spare       New     Abo   Abo   AFT SIDE

                                                                       11    slot        Umbi    9     10
                                                                                         lical

                       Umbilical ABO
                         Central




                                                                                                 ABO FPSO vessel



                                                     Existing Water injct
                                                          (ABO 6 ,7)
        Existing ABO GI (ABO 5)

Existing ABO 2 (Prod)
                   Existing ABO 4 Producer
                                              Existing ABO 3 (prod)          FORE SIDE




                                                                                                                   14
Abo – Extension Project -OML 125
        Daisy chain : proposed arrangement of the new production wells.




                                                Final configuration as per
                                                       attached P&I




                                      ABO
                                       10
                    ABO 11




        Dinamic Flowline


                                                  Pig receiving line
                                     ABO 11 – Production Header Riser to Pig Receiver
                  Pig launcher line
                  ABO 10 – Production Header Riser to Pig Launcher



                                                                                        15
OML 125 -ABO Extension project




                                 16
Abo – Extension Project -OML 125

     TOPSIDE FACILITIES
     B. Areas of FPSO deck interested in ABO Central Upgrade
1.    MANIFOLD/PORCH AREA:
       •    i.e. interconnections between new risers and existing manifolds; winch refurbishment
2.    RACK AREA BETWEEN PROCESS AND INJECTION/BOOSTER COMPRESSOR MODULES:
       •    i.e. new line to new gas injector well and associated control ( nearby process equipment
            module) ;
3.    RISERS AND UMBILICAL (AND SUBSEA FOR FACILITIES):
       •    i.e. new risers and umbilical at porch, complete of greylock, venting and necessary wiring
            and tubing;
4.    HPU area/TUTU1 area:
       •    installation of new skid packages (i.e. new HPU, new TUTU) for control of subsea equipment
            on deck as well as new Topside chemical injection unit;
5.    DCS control room area/Instrument technical room upgrade for the new wells:
       •    expansion of the existing subsea control dedicated to the new subsea users; interface with
            existing UPS;
       •    modification of existing DCS for new topside users;
6.    MCC and Engine room area:
       •    new power supply lines to ABO Ext equipment/ instrument;
7.    FWD Crane Area:
       •    tie-ins for methanol and wax inhibitors for new producer well using existing installations or
            new wax inhibitors and methanol pump motor skid for new producer well.and installation of
            proper heat radiation shields where required due to higher flare gas flow rates originated
            from subsea fields ( namely ABO2 field)
8.    Aft Crane Area:
       •    Minor servicing of existing winches for chain slackening.




                                                                                                            17
Abo – Extension Project -OML 125

   – FPSO arrangement- Areas interested by
   modifications


                   affected areas:




                                             Crane area
           DCS            Rack area
           MCC          (compressor )
           area                                 Flare area
                             Manifold area
           Exist HPU -TUTU
           and main winch
                                Porch area



ABO FPSO

                                                             18
OML 125 - ABO Extension project

     Offshore Installation –Topsides works in support of Vetco Control topside installations (1)
                                           Major works recap




            Description                        Scope                     Notes

  ABS certification of subsea           HPU, TUTU and Control
  Topside items                         container

  Upgrade of Container design to        Fireproofing     with
  meet safety ABS requirements          Chartek 7 to     ABS
  due to deck “C” installation          requirements
  Transformer installation to suit
  available on-board power supply
                                           Engineering and
  (440 V /3 phase) to the power
                                           Material supply
  supply rating of the container (220
  V monophase




Note (1) = Whole installation process completed safely with “0” LTI


                                                                                                   19
Abo – Extension Project -OML 125
Engineering
developed by FPSO vessel owner in support of their EPC (1/1)


   -P&I’ s of new elaboration/ rework:
          - Chemical injection system methanol and wax inhibitor units servicing
            the new TUTU, supplied by VETCO and Instrument air, Nitrogen, closed
            drain , sea water cooling
          - new manifold area P&I scheme in order to show new the pig
            launcher( x-234) and receiver (x-235)
          - Reissue new P&Is pig launcher-receiver equipment/ instrumentation
            as well as show piping connections with inhibitors lines
          - Manage tie-ins on existing schemes
          - Provide support for SIMPOP-HAZID-HAZOP
          - Activation of MTO of piping valves and in line material



     -General arrangement drawings (Layouts and Piping):
        -elevation and plan drawings at porch area and manifold area
         -New plot plan drawing(s) of the new pumps and relevant
         installation
         -Installation drawing(s) of the new TUTU
         Installation drawing of the New HPU
         -plot plan of FPSO areas where new technical room of the new ECS
         Cabinets has to be installed. Wire connections to ITR existing in
         order to ensure DCS-ESD and subsea datalogging continuity.



                                                                                   20
Abo – Extension Project -OML 125


  TOPSIDE FACILITIES
  Engineering developed by FPSO vessel owner “2/2”



 Specification /BoQ-MTO
       New duty specifications of new equipment,piping, instrumentation and electric HW
       supply, including Chocke valves, SDV and miscellanea.
       Provide BoQ and isometric drawings for piping and valves
 Instrumentation and control ( “Cause –effect” ) documents:
       Provide instrumentation list with settings and main design data
       Revision of the EDS/PSD diagram
       Review of the UPS connectiona
       Revision of the Juncion box connection diagrams
       Interfaces with I/0 of new subsea
       Implementation of new video pages for existing DCS
 Electrical distribution drawing:
       New wiring from diatribution 440 V/3ph engine switchgear room associated ones to
       feed new HPU ,TUTU,ECS panels by VETCO
       Revise diagrams and terminals for miscellanea ( instrumentation feed)
       Provide BoQ of cabling of new supply for different cable design specification
       Update / procure cable ways when required


                                                                                          21
OML 125 -ABO Extension project

                Offshore Installation –Topsides works in support of Flow line installation (1)
                                                     Major works         recap


               Description                                Scope                                      Notes
                                                 Load re-testing and ABS
                                                                                 Additional certification for deck winch (22t) and
  Main FPSO winch (75t design capacity)          recertification, (including
                                                                                 tugger winch (5t)
                                                 pulling wire)

                                                Leak testing and    tubing
  Greylock fittings of flow lines               routing for venting     of
                                                connection

  Abo 9 injection; 10, and 11 production
  pipelines statisfactorily tested at 270 bar          ABS certified
  and 240 bar respectively

  Mooring analysis and procurement of
  new parts (chain links) for slackening of
  chain number 3 and additional works/                ABS supervised
  personnel to achieve the installation
  Technip schedule

  Support for precommissioning flow             Support to safely dewater
  lines                                         and diesel fill new flowlines

                                                  Cleaning bellmouth and
  Diving squad in support of installation         fixing / installing new
                                                  umbilicals




Note (1) = Whole installation process completed safely with “0” LTI


                                                                                                                                     22
OML 125 -ABO Extension project



  TOPSIDE FACILITIES
  B. Areas interested in ABO Central Upgrade
  RACK AREA BETWEEN PROCESS
  AND INJECTION/BOOSTER
  COMPRESSOR MODULES (i.e. new
  line to new gas injector well ABO 9 )




     Abo 10
                                          Rack Xssing Foreside-Aft side



                                 Abo 9




                                                                          23
OML 125 -ABO Extension project



 TOPSIDE FACILITIES
 B. Areas interested in ABO Central Upgrade

  MANIFOLD/PORCH AREA (i.e.
  interconnections between new risers and
  existing manifolds)




                                              24
OML 125 -ABO Extension project

    TOPSIDE FACILITIES
    B. Areas interested in ABO Central Upgrade


•    RISERS AND UMBILICAL (AND
     SUBSEA FOR FACILITIES - i.e.
    new risers and umbilical at porch)




                                                 25
OML 125 -ABO Extension project



 TOPSIDE FACILITIES
 B. Areas interested in ABO Central Upgrade
                        HPU area/TUTU1 area -
    installation of new skid packages (i.e. new HPU, new TUTU)
         for control of subsea equipment on deck ( Abo central
                               pkgs shown)




                                                                 26
OML 125 -ABO Extension project

  TOPSIDE FACILITIES
  B. Areas interested in ABO Central Upgrade

   DCS control room area/Instrument technical room ‘B’ (expansion of the
      existing subsea control dedicated to the new subsea users; interface
                                with existing UPS
       modification of existing DCS for new topside users)-Cabinet of abo
                       extension located elsewhere ( Deck ‘C’)




                                                                             27
OML 125 -ABO Extension project



 TOPSIDE FACILITIES
 B. Areas interested in ABO Central Upgrade

                           FWD Crane Area -
         tie-ins for methanol and wax inhibitors for new producer
             well using existing installations or new wax inhibitors
               and methanol pump motor skid for new producer
                                       well




                                                                       28
OML 125 -ABO Extension project

  TOPSIDE FACILITIES




Engineering/Procurement Activities by FPSO vessel owner (1/2)

 Project Management throughout the project;
 Site visit by designer to verify the design /installation if required, including surveys for subsea-
 installation contractor and precommissioning of flow lines ;
 Design, engineering, procure, install and hydraulic testing of new piping pertaining to production
 header tie-ins and gas injection header tie-ins, using local content labor;
 Prepare piping isometrics for piping pre-fabrication with the aim of minimizing hotwork and shutdown
 requirements; Shut down minimized in march 2008 for manifold line tie-ins ( HP,LP,Header,testing
 line)
 Procurement of piping, valves, control valves, shutdown valves, instrumentation systems, cables,
 tubing, cable trays and etc. as required to tie-in the new wells from the riser porch dummy spool;
 Support and assist Company in refurbishing mooring line ( required for chain slackening #3) as
 well as maintain and service existing hydraulic winches for umbilical and flowlines installation




                                                                                                        29
OML 125 -ABO Extension project

 TOPSIDE FACILITIES




Engineering/Procurement Activities (2/2)

  Revise all relevant existing drawings, safety plans, P&ID's, cause and effect, vessel general
  arrangement, instrument drawings etc to incorporate the new modifications;
  Develop modifications to the process control system to reflect the new equipment;
  Obtain Class approvals as required to implement the changes; obtain permits, license and
  authority approvals (Support Documentation for approval of Nigerian authorities, Support
  Documentation for approval of ABS);
  Perform HAZOPS, HAZIDS for the construction and operations phases;
  Develop Job Cards and Procedures for the offshore installation as well as implement installation
  details in Office Project for all the installation activities ( Prosafe scope and interface scope) ;
  Logistics, Coordination of shipments and Offshore Construction works in cooperation with Nae;
  Revise Operating Manuals to suit the modifications;
  Monitor punch lists after First oil.
  As-built all drawings preparation and final documentation affected by the change.




                                                                                                         30
OML 125 -ABO Extension project



 TOPSIDE FACILITIES

Offshore Installation (1/3)



    Mobilise construction crews to offshore for installation of mechanical, electrical, controls and
    instrument scope of work;
    Transport all equipment, tools, and materials to offshore;
    Install all valves, instruments, tubing, piping and cabling to connect the new equipment;
    Modify the process control system (DCS) to include the new wells (field instrumentation);
    Preserve the system ready for riser pull-in (final dummy spool -if required- and one section of
    pipe to be left intact for later removal during riser pull-in should these activities not be
    combined;
    Obtain ABS Class Supervision during key installation phases




                                                                                                       31
OML 125 -ABO Extension project


 TOPSIDE FACILITIES

 Offshore Installation (2/3)
 Subsea Control System Interface activities:

  - Coordinate with Subsea Contractor regarding supply and
     installation of hydraulic tubing from the HPU/TUTU to the riser
     porch JB according NAS 6 quality standard;
  - Supply, install and test hydraulic tubing as required to suit the
    new well control requirements;
  - Cabling and hook up tubing for subsea controls, terminating in new
    junction box at riser porch;
  - Mobilise specialists for process system software changes and
    perform site modifications for the subsea control system
    interface.
  - Keep under control POB during crucial installation phase ( off-shore)




                                                                            32
OML 125 -ABO Extension project


 Offshore Installation –Topsides (3/3)

                                 Key Parameters                (internal
                              evaluation based on FPSO vessel owner final
                                        numbers for 2+1 wells)



                                                          Installation
     Description                                                                             Installation Manhours
                                                          Parameters


     Piping and Ancillaries (1)                             30.000 kg
                                                                                                Indicative data from
                                                                                                OIM:
     Packaged Equipment (2)                                                                     10000 – 13000
                                                            20.000 kg


     Cable/Cableways
                                                              3000 m                                   4500
     (Power and Control)

     NOTES   (1) It includes approx 8000 Kg of valves and light steelwork for support;
              (2) it includes 2 off pigs, 1TUTU,1HPU, 1 control cabinet 1 Chemical injection skid




                                                                                                                       33
OML 125 -ABO Extension project

                                 installation contractor sub-orders ( major)
Description                                       Scope                         Company
Flexible pipe and ancillary equipment (Hang off   Material, shop production,    FlexiFrance (France)
collar, Bend stiffner and Bend stiffner spacer)   shop testing
Anodes for flowlines                              Material, production, shop    Impalloy (UK)
                                                  testing
Insulation Covers                                 Material, production, shop    Bardot (France)
                                                  testing
Precommisioning Service (FPSO and Installation    Detail Engineering and        BJ (UK)
Vessel)                                           Offshore rental equipment
                                                  - labour for commissioning
                                                  activities
Steel Bend Restrictor                             Material, shop production,    Asturfeito (Spain)
                                                  shop testing
Survey Service                                    Detail Engineering,           DOF (UK)
                                                  offshore personnel, labour
                                                  and ancillary tools /
                                                  equipment
Turning points                                    Material, shop fabrication,   COMETRA (France)
                                                  testing                       AMS (Nigeria)*
Umbilical Tether Base & Tether                    Material, fabrication,        COMETRA (France)
                                                  testing
NOTE : (*) Spare items
Note (1) = Whole installation process completed safely with “0” LTI. - main subcontractors list for
ABO Extension. (Installation of all items managed by Installation contractor)

                                                                                                       34
                        Technip
OML 125 -ABO Extension project

       Major subcontractor packages for Topsides FPSO works
         Description                                 Scope                     Company
         Mooring equipment for chain        Material (air shipped) and
                                                                          Noble Denton Singapore
         number 3 slackening                           labour
         Overhaul and refurbish 75,25,5       Laad cell monitoring,          Mc-Gregor Plinsol
         tonn winches                       service parts and labour         Singapore
         Personnel assistance during           Labour in support of         Noble Denton- Mc
         hook-up phase                        operations by Technip         Gregor
                                             Labour, tools and tool –
         HP Tubing and Chemical tubing
                                               service container to
         on board of vessel up to                                           Hulliburton Nigeria
                                              perform NAS 6 quality
         Umbilical plate
                                                     flushing
                                            Labor and logistic to clean
         Diving and divers equipment        bellmouth and install / fix      Ken-dive Nigeria
                                                 new umbilical
         Small bore spare valves for
                                                 Material supply                   Alton
         piping works
                                            Material (air shipped) and
         Flare radiation shields                                              Thermolimitec
                                                   engineering
                                               Material supply for
                                             continuty of installation
         Dummy fittings                                                        Dormen long
                                               between piping and
                                                    flowlines

         Prefabricated piping (above 2”)    Material supply, support
         for all pipework from porch area   during installation, field    Amber resources Nigeria
         back to manifold an Pigs            welding Xray testing

                                                                            ABS Singapore and
         ABS supervision/ approval               Process review
                                                                            connected offices


                                                                                                    35
Abo – Extension Project -OML 125

         Estimated subsea contractor delivery schedule (only Items
                          interfacing topsides )




                                                                     Final delivery for
                                                                     installation : trees
                                                                     between February
                                                                     2008 and April 2008

                                                                     Topside control End
                                                                     of June 2008




                                                                                            36
OML 125 -ABO Extension project-Installation of FPSO
modification




                                                      37
OML 125 -ABO Extension project




                                 38
OML 125 -ABO Extension project




                                 39
OML 125 -ABO Extension project
  The scope of supply for Integrated Control and Safety System modifications included but was
  not limited to following:
    • Design, Engineering, Procurement, Programming, Configuration, Software, Graphics, Logics, Fabrication,
    Assembly, Testing and Commissioning, Preparation for Shipment, packing and supply of System hardware with
    cabinets, I/O Modules, and Controllers for the “ modification of existing control system at offshore (on the FPSO).
    Integrated Control and Safety System (ICSS) consisted of :
• Process Control System (PCS)
• Process Shutdown System (PSD)
• Emergency Shutdown & Fire and Gas System (ESD/F&G)

• Specifically :
    • Updating the existing configuration and configuring additional I/O Modules, Spare Channels and Marshalling
    Termination
    • Configuration and integration with new ECS system HPU system supplied by Vetco with existing PCS.
    • Modification to existing graphics and build new graphics.
    • Upgrading of the redundant controllers for 6MB Capacity.
    • Supply of IS barrier for intrinsically safe signals.
    • Review existing M-NET capabilities for additional nodes and its adequacy.
    • Configuration of existing Tag server database for new I/O’s and its adequacy.
    • Configuration of existing Historian Server database for new I/O’s.
    • 4-mation Configuration
    • Software Configuration and testing (on-shore-offshore)
    • Configuration of alarm functions for existing inputs-3 Nos
    • FAT,SAT & Commissioning assistance.
    • Update Client’s comments at site.
    • RS485/RS 232 serial link connectors and required network adaptors.
    • Engineer site deputation for installation, testing and commissioning at ABO FPSO.
    • Packing and Shipment.
    • Tagging and labelling.
    • Supply of special tools.
    • Documentation.

                                                                                                                          40
OML 125 -ABO Extension project

  ITEM 5.1 -TOPSIDE FACILITIES-modification of overall subsea control system to be integrated with ABO
  central ( Using Multi drop communication system protocol)




                                                                                                         41
OML 125 -ABO Extension project

  TOPSIDE FACILITIES-Control system

    © ABB - 1   Extended architecture




                                        42
OML 125 -ABO Extension project




  Location Deck “C” where Container will be placed




                                                 Internal view Container hosting sub sea




                                                                                           43
OML 125 -ABO Extension project




                                 44
OML 125 -ABO Extension project
   Offshore Installation field precommissioning (sample of
   signed hand over document)
  TOPSIDE FACILITIES- List of commissioned sub-system




                                                             45
OML 125 -ABO Extension project



 FIELD START-UP EFFECTIVE DATES OF ABO EXTENSION
       Wells start-up dates of ABO COMBINED PROFILE (CENTRAL + ABO EXTENSION) :




              Wells                             Date


          ABO 11 (P1)                     14° February 2009


          ABO 10 (P2)                     15° February 2009


           ABO 9 (GI)                    20° February 2009


                            Test of production : mid 2009




                                                                                  46

More Related Content

What's hot

Offshore Engineering Kavin Engneering Fpso Corporate Profile 2012
Offshore Engineering Kavin Engneering Fpso Corporate Profile 2012Offshore Engineering Kavin Engneering Fpso Corporate Profile 2012
Offshore Engineering Kavin Engneering Fpso Corporate Profile 2012
ggurudev
 
iFluids Tank Inspection services
iFluids Tank Inspection servicesiFluids Tank Inspection services
iFluids Tank Inspection services
John Kingsley
 
Lokman's Resume-Rotating Equipment
Lokman's Resume-Rotating EquipmentLokman's Resume-Rotating Equipment
Lokman's Resume-Rotating Equipment
Lokman Ali P.Eng.
 
Introduction to Petroleum Engineering
Introduction to Petroleum EngineeringIntroduction to Petroleum Engineering
Introduction to Petroleum Engineering
Amey Perry
 
Senior HVAC & Plumbing Engineer & QC Inspector
Senior HVAC & Plumbing Engineer & QC Inspector  Senior HVAC & Plumbing Engineer & QC Inspector
Senior HVAC & Plumbing Engineer & QC Inspector
SYED MUQTAAR AHAMED
 
Subsea completion and control system
Subsea completion and control systemSubsea completion and control system
Subsea completion and control system
Amit Nitharwal
 
FPSO SYSTEMS-1.pdf
FPSO SYSTEMS-1.pdfFPSO SYSTEMS-1.pdf
FPSO SYSTEMS-1.pdf
BnBn25
 

What's hot (20)

Subsea pipeline Repair and Maintenance
Subsea pipeline Repair and Maintenance Subsea pipeline Repair and Maintenance
Subsea pipeline Repair and Maintenance
 
Workover job ppe
Workover job ppeWorkover job ppe
Workover job ppe
 
Ppt report on offshore Platform Designs
Ppt report on offshore Platform DesignsPpt report on offshore Platform Designs
Ppt report on offshore Platform Designs
 
Offshore Engineering Kavin Engneering Fpso Corporate Profile 2012
Offshore Engineering Kavin Engneering Fpso Corporate Profile 2012Offshore Engineering Kavin Engneering Fpso Corporate Profile 2012
Offshore Engineering Kavin Engneering Fpso Corporate Profile 2012
 
Semi submersible
Semi submersibleSemi submersible
Semi submersible
 
Gas Lift Design: Comparative Study of Continuous and Intermittent Gas Lift (C...
Gas Lift Design: Comparative Study of Continuous and Intermittent Gas Lift (C...Gas Lift Design: Comparative Study of Continuous and Intermittent Gas Lift (C...
Gas Lift Design: Comparative Study of Continuous and Intermittent Gas Lift (C...
 
iFluids Tank Inspection services
iFluids Tank Inspection servicesiFluids Tank Inspection services
iFluids Tank Inspection services
 
Lokman's Resume-Rotating Equipment
Lokman's Resume-Rotating EquipmentLokman's Resume-Rotating Equipment
Lokman's Resume-Rotating Equipment
 
Introduction to Petroleum Engineering
Introduction to Petroleum EngineeringIntroduction to Petroleum Engineering
Introduction to Petroleum Engineering
 
Offshore platforms
Offshore platformsOffshore platforms
Offshore platforms
 
Senior HVAC & Plumbing Engineer & QC Inspector
Senior HVAC & Plumbing Engineer & QC Inspector  Senior HVAC & Plumbing Engineer & QC Inspector
Senior HVAC & Plumbing Engineer & QC Inspector
 
Additional oil recovery by gas recycling BY Muhammad Fahad Ansari 12IEEM14
Additional oil recovery by gas recycling BY Muhammad Fahad Ansari 12IEEM14Additional oil recovery by gas recycling BY Muhammad Fahad Ansari 12IEEM14
Additional oil recovery by gas recycling BY Muhammad Fahad Ansari 12IEEM14
 
Basic whp presentation(1)
Basic whp presentation(1)Basic whp presentation(1)
Basic whp presentation(1)
 
Lloyd's Register Ship emergency response service - USCG requirements for NTV
Lloyd's Register Ship emergency response service - USCG requirements for NTVLloyd's Register Ship emergency response service - USCG requirements for NTV
Lloyd's Register Ship emergency response service - USCG requirements for NTV
 
Well work over
Well work overWell work over
Well work over
 
C1. Introduction to Offshore Production Tech
C1. Introduction to Offshore Production TechC1. Introduction to Offshore Production Tech
C1. Introduction to Offshore Production Tech
 
Subsea completion and control system
Subsea completion and control systemSubsea completion and control system
Subsea completion and control system
 
INIO2014 Presentation
INIO2014 PresentationINIO2014 Presentation
INIO2014 Presentation
 
Oil 101 - Introduction to Production
Oil 101 - Introduction to ProductionOil 101 - Introduction to Production
Oil 101 - Introduction to Production
 
FPSO SYSTEMS-1.pdf
FPSO SYSTEMS-1.pdfFPSO SYSTEMS-1.pdf
FPSO SYSTEMS-1.pdf
 

Viewers also liked

1020120046332
10201200463321020120046332
1020120046332
Young Oh
 
Miclyn Endurance Jan 2010 Rev 3 (Ps)
Miclyn Endurance Jan 2010 Rev 3 (Ps)Miclyn Endurance Jan 2010 Rev 3 (Ps)
Miclyn Endurance Jan 2010 Rev 3 (Ps)
philipsim
 

Viewers also liked (20)

Fpso – general overview of conversion & topside process description -abstract
Fpso – general overview of conversion & topside process description -abstractFpso – general overview of conversion & topside process description -abstract
Fpso – general overview of conversion & topside process description -abstract
 
Classification and Regulatory Standards used in Novel Design Concepts for Dee...
Classification and Regulatory Standards used in Novel Design Concepts for Dee...Classification and Regulatory Standards used in Novel Design Concepts for Dee...
Classification and Regulatory Standards used in Novel Design Concepts for Dee...
 
Floting Production Storage and Offloading
Floting Production Storage  and OffloadingFloting Production Storage  and Offloading
Floting Production Storage and Offloading
 
Mg Innovation Flng Cn 2010 R1
Mg Innovation Flng Cn 2010 R1Mg Innovation Flng Cn 2010 R1
Mg Innovation Flng Cn 2010 R1
 
1020120046332
10201200463321020120046332
1020120046332
 
Miclyn Endurance Jan 2010 Rev 3 (Ps)
Miclyn Endurance Jan 2010 Rev 3 (Ps)Miclyn Endurance Jan 2010 Rev 3 (Ps)
Miclyn Endurance Jan 2010 Rev 3 (Ps)
 
apl-brochure
apl-brochureapl-brochure
apl-brochure
 
Offshore Rig Life Extension
Offshore Rig Life ExtensionOffshore Rig Life Extension
Offshore Rig Life Extension
 
Development of Guidelines and Standards for Life Extension
Development of Guidelines and Standards for Life ExtensionDevelopment of Guidelines and Standards for Life Extension
Development of Guidelines and Standards for Life Extension
 
Wood Group - A Holistic Approach to Life Extension
Wood Group - A Holistic Approach to Life ExtensionWood Group - A Holistic Approach to Life Extension
Wood Group - A Holistic Approach to Life Extension
 
FPSO Conference Workshop - Legal Risks in FPSO Conversion & Associated Contracts
FPSO Conference Workshop - Legal Risks in FPSO Conversion & Associated ContractsFPSO Conference Workshop - Legal Risks in FPSO Conversion & Associated Contracts
FPSO Conference Workshop - Legal Risks in FPSO Conversion & Associated Contracts
 
Cost Effective Debottleneck Expansions
Cost Effective Debottleneck Expansions Cost Effective Debottleneck Expansions
Cost Effective Debottleneck Expansions
 
Offshore platform slot recovery process
Offshore platform slot recovery processOffshore platform slot recovery process
Offshore platform slot recovery process
 
Case Study:Field Proven Innovations for Impact Protection and Life Extension
Case Study:Field Proven Innovations for Impact Protection and Life ExtensionCase Study:Field Proven Innovations for Impact Protection and Life Extension
Case Study:Field Proven Innovations for Impact Protection and Life Extension
 
FPSO Redeployment
FPSO RedeploymentFPSO Redeployment
FPSO Redeployment
 
FPSO Requirements
FPSO RequirementsFPSO Requirements
FPSO Requirements
 
Advanced Methods for ULS and FLS
Advanced Methods for ULS and FLSAdvanced Methods for ULS and FLS
Advanced Methods for ULS and FLS
 
Life extension of aging petroleum production facilities offshore
Life extension of aging petroleum production facilities offshoreLife extension of aging petroleum production facilities offshore
Life extension of aging petroleum production facilities offshore
 
Process Optimization for Small-Scale LNG Plants
Process Optimization for Small-Scale LNG PlantsProcess Optimization for Small-Scale LNG Plants
Process Optimization for Small-Scale LNG Plants
 
Dynamic positioning
Dynamic positioningDynamic positioning
Dynamic positioning
 

Similar to Abo Oml125 (20)

01.06.2009 Presentation of Investor Relations Executive Manager, Theodore M....
01.06.2009  Presentation of Investor Relations Executive Manager, Theodore M....01.06.2009  Presentation of Investor Relations Executive Manager, Theodore M....
01.06.2009 Presentation of Investor Relations Executive Manager, Theodore M....
 
Sigma Presentation
Sigma PresentationSigma Presentation
Sigma Presentation
 
Nal operational map montages
Nal operational map montagesNal operational map montages
Nal operational map montages
 
New osx project update_agosto_final_inglês
New osx project update_agosto_final_inglêsNew osx project update_agosto_final_inglês
New osx project update_agosto_final_inglês
 
07 04-2011-project-update
07 04-2011-project-update07 04-2011-project-update
07 04-2011-project-update
 
Sigma Presentation 4
Sigma Presentation 4Sigma Presentation 4
Sigma Presentation 4
 
Hale wayne
Hale wayneHale wayne
Hale wayne
 
CO2 - EOR and its role in CCS
CO2 - EOR and its role in CCSCO2 - EOR and its role in CCS
CO2 - EOR and its role in CCS
 
Tdb vrf dvm s standard for turkey (odu 50 hz hp) ver.1.0
Tdb vrf dvm s standard for turkey (odu 50 hz hp) ver.1.0Tdb vrf dvm s standard for turkey (odu 50 hz hp) ver.1.0
Tdb vrf dvm s standard for turkey (odu 50 hz hp) ver.1.0
 
Osx project update agosto_final_inglês
Osx project update agosto_final_inglêsOsx project update agosto_final_inglês
Osx project update agosto_final_inglês
 
BDC VUB # 150 TTRC modified oct 26_KDK
BDC VUB # 150 TTRC modified oct 26_KDKBDC VUB # 150 TTRC modified oct 26_KDK
BDC VUB # 150 TTRC modified oct 26_KDK
 
Fxlq
FxlqFxlq
Fxlq
 
Fxuq
FxuqFxuq
Fxuq
 
Innovating for the future
Innovating for the futureInnovating for the future
Innovating for the future
 
Fxaq
FxaqFxaq
Fxaq
 
SPDC Flares Reduction Programme
SPDC Flares Reduction ProgrammeSPDC Flares Reduction Programme
SPDC Flares Reduction Programme
 
Project update.29.04
Project update.29.04Project update.29.04
Project update.29.04
 
nuclear power
nuclear powernuclear power
nuclear power
 
Fxhq
FxhqFxhq
Fxhq
 
Fxmq
FxmqFxmq
Fxmq
 

Abo Oml125

  • 1. Close-out ABO Extension Project Nigeria -OML 125 Major project milestones – Ennio Nitti – Engineering Manager Nigerian projects- San Donato Milanese – End of March 2008
  • 2. OML 125 -ABO Extension project Field production avg data per year during ABO Ext Phase Green line: produced gas consumed for motive power of FPSO 50 Additional flow rate of ABO 10 .11 (March 2009 trend) approx 18.000 BOPD 40 31,002 33,96 28,8 30 25,147 28,06 26,48 23,83 18,014 20 16,816 10 0 Prod 2005 Prod 2006 Prod 2007 Prod 2008 Expected 2009 March (assuming 50% production yr 2 from start) Crude Avg Production Gas injection trend (1 GI) • Note – Approx Indication in Barrel Per Day for crude and MillionSCFD per injected or produced gas 2
  • 3. OML 125 -ABO Extension project Location of Nae Block 3
  • 4. OML 125 -ABO Extension project CHARACTERISTICS DATA Past Name / Present GREY WARRIOR / ABO Name FPSO ABO FPSO Built in / Converted in 1976 / 2002 Length overall 280,4 m Breadth 53,6 m VESSEL MAIN DATA Depth 20 m 160.000 Metric Tons Dead weight (approx) Cargo oil tanks 951.658 bbls capacity FPSO conversion an field positioning : 2002/2003 March ( Abo Central) 4
  • 5. OML 125 -ABO Extension project Current Porch Configuration Riser hang-off systems were designed to be located at same FPSO side (even for future expansion) Hang-off of risers in a free hanging configuration from a deck balcony configuration Control Umbilical through I-Tube located on the vessel side (see red line) Total hang-off available systems: 5 + 4 (spares) for risers and 1 + 1 spare for umbilical 5
  • 6. ABO Extension = Schematic Block Diagram of the FPSO Facilities (Receiving manifolds, separation, gas compression, oil handling, water handling) Data regarding actual design envelope for liquid expressed in BPD (Barrel per Day); for gas expressed in Million SCFD Design envelope: Only from Design envelope HP 44 Million SCFD + Second Design envelope: Flare:49 Million 10% = 48,4 Compressor 48,4 Million SCFD SCFD Million SCFD Stage Heating Utility and Relief System Fuel Gas Fuel Gas System for Instrument to Flare Reciprocating Dehydration for Oil Treating Air ( HP, LP) Compressor Glycol Internal Sea Water (3*50% Contactor Process Lift Fire Unit and Fighting capacity ABO Use Central) over Regen within Deluge Package System Three Stages FPSO Design envelope First Stage From 1st Separator: 40000 BPD + Stage 10% (= 44000 BPD) of Separato Gas Handling Via Booster Re- Liquid (Oil+Water) with a r and 2*100 % Cooling for Compressor Injection Overboard Maximum Peak of Water of only Booster Sea Water Water Compressor 9000 BWPD + 44 Million Compressors Filtering Pumps and Oil SCFD of Gas Handling to Wells Well ABO 9 LP Stages Well ABO 10 Design envelope Well ABO 11 Flow lines Inlet Crude Booster: 5,5 and separation Million SCFD + 5,5 Existing ABO manifolds (1st and 2nd Oil Treating Million SCFD Central; Wells 2,3,4 (1st, 2nd Sea Water Stage (i.e Design envelope: Existing ABO Central; Design envelope Degassing stage) Separators, Stabilizing Wells 6,7 Crude Stabilization 9000 BPD interfacing Electrostatic and Abo Central Gas : 40000 BLPD + Subsea Risers Dehydrator) Desalting) Injector Well 5 and 10% (= 44000 BLPD) + 5 Million Umbilicals SCFD Gas Design envelope Test Design envelope Separator :17000 Chemical Hydrocyclons 12000 BOPD+4000 Injection BPD Sea Water BWPD+19000 MSCFD Produced +12000 BPD as Skidded Crude Oil Boosting Water spare Design envelope: Units for Storaging and Treatment 30000 BPD + 10 SEE SLIDE 4 FOR Subsea and within FPSO Pumping Design envelope: % INTERCONNECTION Topsides System 9000 BPD + 2000 SEQUENCE BPD from Chemicals loading Water Overboard Desalting 30PPM Quality (=11000 BPD) + Oil to Export 10% FPSO 6
  • 7. OML 125 -ABO Extension project Actual design parameters of ABO Topside Facilities FPSO Design Parameter Value / Policy Life design of existing facilities 10 years (starting from 2002) Oil design flow rate 40000 BOPD + 10 % overdesign Maximum design temperature process side 50 °C Maximum design pressure at manifold inlet 21 barg Design capacity of gas treatment 44 MMscfd + 10% = 48.4 MMscfd Gas injection line design 42MMscfd + 10% (total 44 MMscfd at exit of 3rd stage injection compressor when two trains operating in parallel; one in stand by) Maximum gas injection pressure at gas lift line to 250 barg (@ porch) existing ABO_5 Gas Strategy Gas reinjection into the Reservoir Maximum water production handling flowrate 9000 BWPD; overboard water quality (Oil in Water) discharged to sea: < 30 ppm 7
  • 8. Abo – Extension Project -OML 125 Actual FPSO mooring system and existing flow lines arrangement with indication of the new wells ABO 11c -producer ABO 9b – Gas injector ABO 10- producer proposed oordinates wells at sanctioning ABO 9B 661919.0 E 631920.0 N ABO 10 660343.7 E 631713.1 N ABO11C 660653.0 E 632729.0 N Mooring chain number 3 required to be lowered for installation 8
  • 9. OML 125 -ABO Extension project n TOPSIDE EVENTS MAJOR MILESTONES OF ABO EXTENSION 9
  • 10. OML 125 -ABO Extension project Project follow up by subcontractors from project start up till completion The engineering “volume” of manhours associated with the extension works is as follow: Subsea EPC: manhours (Pm+Eng). Approx: 75000 Topsides-FPSO Vessel: manhours (Pm + Eng):12000 Engineering Follow -up: manhours (13000) Installation contractor: manhours (100000) Note : Documents issued by Install contractor: approx 220 Documents issued by Subsea EPC supplier: approx 500 Documents issued by FPSO owner: app. 150 (new); 330 (revision of exixting one) 10
  • 11. Abo – Extension Project -OML 125 Release 1_A of Nae 3229.41.000.L.DL.FC88001 Field lay-out without bathymetry ABO 9b –Gas injector Abo Ext 11
  • 12. Abo – Extension Project -OML 125 12
  • 13. Abo – Extension Project -OML 125 Subsea lines scope of installation. Description Service From To Length (m) RG2 GI riser FPSO ABO-9 950 GI flowline FPSO ABO-9 1976 R10 6” production riser FPSO ABO -10 850 6” production riser FPSO ABO -10 3630 R11 6” production riser FPSO ABO -11 850 6” production riser FPSO ABO -11 3573 F10-11 Pigging loop ABO-10 ABO -11 1286 UM2 Dynamic Umbilical FPSO UTA-UM2 2825 (including riser 745.5 m to TDP UP-10 Infield umbilical UTA-UP10 UTA-UP10 B 1630 A UP-11 Infield umbilical UTA-UP11 UTA-UP11 B 1580 A 13
  • 14. Abo – Extension Project -OML 125 Porch area:well connections AFT SIDE FORE SIDE New sequence approved during detailed DECK SIDE engineering Abo Spare New Abo Abo AFT SIDE 11 slot Umbi 9 10 lical Umbilical ABO Central ABO FPSO vessel Existing Water injct (ABO 6 ,7) Existing ABO GI (ABO 5) Existing ABO 2 (Prod) Existing ABO 4 Producer Existing ABO 3 (prod) FORE SIDE 14
  • 15. Abo – Extension Project -OML 125 Daisy chain : proposed arrangement of the new production wells. Final configuration as per attached P&I ABO 10 ABO 11 Dinamic Flowline Pig receiving line ABO 11 – Production Header Riser to Pig Receiver Pig launcher line ABO 10 – Production Header Riser to Pig Launcher 15
  • 16. OML 125 -ABO Extension project 16
  • 17. Abo – Extension Project -OML 125 TOPSIDE FACILITIES B. Areas of FPSO deck interested in ABO Central Upgrade 1. MANIFOLD/PORCH AREA: • i.e. interconnections between new risers and existing manifolds; winch refurbishment 2. RACK AREA BETWEEN PROCESS AND INJECTION/BOOSTER COMPRESSOR MODULES: • i.e. new line to new gas injector well and associated control ( nearby process equipment module) ; 3. RISERS AND UMBILICAL (AND SUBSEA FOR FACILITIES): • i.e. new risers and umbilical at porch, complete of greylock, venting and necessary wiring and tubing; 4. HPU area/TUTU1 area: • installation of new skid packages (i.e. new HPU, new TUTU) for control of subsea equipment on deck as well as new Topside chemical injection unit; 5. DCS control room area/Instrument technical room upgrade for the new wells: • expansion of the existing subsea control dedicated to the new subsea users; interface with existing UPS; • modification of existing DCS for new topside users; 6. MCC and Engine room area: • new power supply lines to ABO Ext equipment/ instrument; 7. FWD Crane Area: • tie-ins for methanol and wax inhibitors for new producer well using existing installations or new wax inhibitors and methanol pump motor skid for new producer well.and installation of proper heat radiation shields where required due to higher flare gas flow rates originated from subsea fields ( namely ABO2 field) 8. Aft Crane Area: • Minor servicing of existing winches for chain slackening. 17
  • 18. Abo – Extension Project -OML 125 – FPSO arrangement- Areas interested by modifications affected areas: Crane area DCS Rack area MCC (compressor ) area Flare area Manifold area Exist HPU -TUTU and main winch Porch area ABO FPSO 18
  • 19. OML 125 - ABO Extension project Offshore Installation –Topsides works in support of Vetco Control topside installations (1) Major works recap Description Scope Notes ABS certification of subsea HPU, TUTU and Control Topside items container Upgrade of Container design to Fireproofing with meet safety ABS requirements Chartek 7 to ABS due to deck “C” installation requirements Transformer installation to suit available on-board power supply Engineering and (440 V /3 phase) to the power Material supply supply rating of the container (220 V monophase Note (1) = Whole installation process completed safely with “0” LTI 19
  • 20. Abo – Extension Project -OML 125 Engineering developed by FPSO vessel owner in support of their EPC (1/1) -P&I’ s of new elaboration/ rework: - Chemical injection system methanol and wax inhibitor units servicing the new TUTU, supplied by VETCO and Instrument air, Nitrogen, closed drain , sea water cooling - new manifold area P&I scheme in order to show new the pig launcher( x-234) and receiver (x-235) - Reissue new P&Is pig launcher-receiver equipment/ instrumentation as well as show piping connections with inhibitors lines - Manage tie-ins on existing schemes - Provide support for SIMPOP-HAZID-HAZOP - Activation of MTO of piping valves and in line material -General arrangement drawings (Layouts and Piping): -elevation and plan drawings at porch area and manifold area -New plot plan drawing(s) of the new pumps and relevant installation -Installation drawing(s) of the new TUTU Installation drawing of the New HPU -plot plan of FPSO areas where new technical room of the new ECS Cabinets has to be installed. Wire connections to ITR existing in order to ensure DCS-ESD and subsea datalogging continuity. 20
  • 21. Abo – Extension Project -OML 125 TOPSIDE FACILITIES Engineering developed by FPSO vessel owner “2/2” Specification /BoQ-MTO New duty specifications of new equipment,piping, instrumentation and electric HW supply, including Chocke valves, SDV and miscellanea. Provide BoQ and isometric drawings for piping and valves Instrumentation and control ( “Cause –effect” ) documents: Provide instrumentation list with settings and main design data Revision of the EDS/PSD diagram Review of the UPS connectiona Revision of the Juncion box connection diagrams Interfaces with I/0 of new subsea Implementation of new video pages for existing DCS Electrical distribution drawing: New wiring from diatribution 440 V/3ph engine switchgear room associated ones to feed new HPU ,TUTU,ECS panels by VETCO Revise diagrams and terminals for miscellanea ( instrumentation feed) Provide BoQ of cabling of new supply for different cable design specification Update / procure cable ways when required 21
  • 22. OML 125 -ABO Extension project Offshore Installation –Topsides works in support of Flow line installation (1) Major works recap Description Scope Notes Load re-testing and ABS Additional certification for deck winch (22t) and Main FPSO winch (75t design capacity) recertification, (including tugger winch (5t) pulling wire) Leak testing and tubing Greylock fittings of flow lines routing for venting of connection Abo 9 injection; 10, and 11 production pipelines statisfactorily tested at 270 bar ABS certified and 240 bar respectively Mooring analysis and procurement of new parts (chain links) for slackening of chain number 3 and additional works/ ABS supervised personnel to achieve the installation Technip schedule Support for precommissioning flow Support to safely dewater lines and diesel fill new flowlines Cleaning bellmouth and Diving squad in support of installation fixing / installing new umbilicals Note (1) = Whole installation process completed safely with “0” LTI 22
  • 23. OML 125 -ABO Extension project TOPSIDE FACILITIES B. Areas interested in ABO Central Upgrade RACK AREA BETWEEN PROCESS AND INJECTION/BOOSTER COMPRESSOR MODULES (i.e. new line to new gas injector well ABO 9 ) Abo 10 Rack Xssing Foreside-Aft side Abo 9 23
  • 24. OML 125 -ABO Extension project TOPSIDE FACILITIES B. Areas interested in ABO Central Upgrade MANIFOLD/PORCH AREA (i.e. interconnections between new risers and existing manifolds) 24
  • 25. OML 125 -ABO Extension project TOPSIDE FACILITIES B. Areas interested in ABO Central Upgrade • RISERS AND UMBILICAL (AND SUBSEA FOR FACILITIES - i.e. new risers and umbilical at porch) 25
  • 26. OML 125 -ABO Extension project TOPSIDE FACILITIES B. Areas interested in ABO Central Upgrade HPU area/TUTU1 area - installation of new skid packages (i.e. new HPU, new TUTU) for control of subsea equipment on deck ( Abo central pkgs shown) 26
  • 27. OML 125 -ABO Extension project TOPSIDE FACILITIES B. Areas interested in ABO Central Upgrade DCS control room area/Instrument technical room ‘B’ (expansion of the existing subsea control dedicated to the new subsea users; interface with existing UPS modification of existing DCS for new topside users)-Cabinet of abo extension located elsewhere ( Deck ‘C’) 27
  • 28. OML 125 -ABO Extension project TOPSIDE FACILITIES B. Areas interested in ABO Central Upgrade FWD Crane Area - tie-ins for methanol and wax inhibitors for new producer well using existing installations or new wax inhibitors and methanol pump motor skid for new producer well 28
  • 29. OML 125 -ABO Extension project TOPSIDE FACILITIES Engineering/Procurement Activities by FPSO vessel owner (1/2) Project Management throughout the project; Site visit by designer to verify the design /installation if required, including surveys for subsea- installation contractor and precommissioning of flow lines ; Design, engineering, procure, install and hydraulic testing of new piping pertaining to production header tie-ins and gas injection header tie-ins, using local content labor; Prepare piping isometrics for piping pre-fabrication with the aim of minimizing hotwork and shutdown requirements; Shut down minimized in march 2008 for manifold line tie-ins ( HP,LP,Header,testing line) Procurement of piping, valves, control valves, shutdown valves, instrumentation systems, cables, tubing, cable trays and etc. as required to tie-in the new wells from the riser porch dummy spool; Support and assist Company in refurbishing mooring line ( required for chain slackening #3) as well as maintain and service existing hydraulic winches for umbilical and flowlines installation 29
  • 30. OML 125 -ABO Extension project TOPSIDE FACILITIES Engineering/Procurement Activities (2/2) Revise all relevant existing drawings, safety plans, P&ID's, cause and effect, vessel general arrangement, instrument drawings etc to incorporate the new modifications; Develop modifications to the process control system to reflect the new equipment; Obtain Class approvals as required to implement the changes; obtain permits, license and authority approvals (Support Documentation for approval of Nigerian authorities, Support Documentation for approval of ABS); Perform HAZOPS, HAZIDS for the construction and operations phases; Develop Job Cards and Procedures for the offshore installation as well as implement installation details in Office Project for all the installation activities ( Prosafe scope and interface scope) ; Logistics, Coordination of shipments and Offshore Construction works in cooperation with Nae; Revise Operating Manuals to suit the modifications; Monitor punch lists after First oil. As-built all drawings preparation and final documentation affected by the change. 30
  • 31. OML 125 -ABO Extension project TOPSIDE FACILITIES Offshore Installation (1/3) Mobilise construction crews to offshore for installation of mechanical, electrical, controls and instrument scope of work; Transport all equipment, tools, and materials to offshore; Install all valves, instruments, tubing, piping and cabling to connect the new equipment; Modify the process control system (DCS) to include the new wells (field instrumentation); Preserve the system ready for riser pull-in (final dummy spool -if required- and one section of pipe to be left intact for later removal during riser pull-in should these activities not be combined; Obtain ABS Class Supervision during key installation phases 31
  • 32. OML 125 -ABO Extension project TOPSIDE FACILITIES Offshore Installation (2/3) Subsea Control System Interface activities: - Coordinate with Subsea Contractor regarding supply and installation of hydraulic tubing from the HPU/TUTU to the riser porch JB according NAS 6 quality standard; - Supply, install and test hydraulic tubing as required to suit the new well control requirements; - Cabling and hook up tubing for subsea controls, terminating in new junction box at riser porch; - Mobilise specialists for process system software changes and perform site modifications for the subsea control system interface. - Keep under control POB during crucial installation phase ( off-shore) 32
  • 33. OML 125 -ABO Extension project Offshore Installation –Topsides (3/3) Key Parameters (internal evaluation based on FPSO vessel owner final numbers for 2+1 wells) Installation Description Installation Manhours Parameters Piping and Ancillaries (1) 30.000 kg Indicative data from OIM: Packaged Equipment (2) 10000 – 13000 20.000 kg Cable/Cableways 3000 m 4500 (Power and Control) NOTES (1) It includes approx 8000 Kg of valves and light steelwork for support; (2) it includes 2 off pigs, 1TUTU,1HPU, 1 control cabinet 1 Chemical injection skid 33
  • 34. OML 125 -ABO Extension project installation contractor sub-orders ( major) Description Scope Company Flexible pipe and ancillary equipment (Hang off Material, shop production, FlexiFrance (France) collar, Bend stiffner and Bend stiffner spacer) shop testing Anodes for flowlines Material, production, shop Impalloy (UK) testing Insulation Covers Material, production, shop Bardot (France) testing Precommisioning Service (FPSO and Installation Detail Engineering and BJ (UK) Vessel) Offshore rental equipment - labour for commissioning activities Steel Bend Restrictor Material, shop production, Asturfeito (Spain) shop testing Survey Service Detail Engineering, DOF (UK) offshore personnel, labour and ancillary tools / equipment Turning points Material, shop fabrication, COMETRA (France) testing AMS (Nigeria)* Umbilical Tether Base & Tether Material, fabrication, COMETRA (France) testing NOTE : (*) Spare items Note (1) = Whole installation process completed safely with “0” LTI. - main subcontractors list for ABO Extension. (Installation of all items managed by Installation contractor) 34 Technip
  • 35. OML 125 -ABO Extension project Major subcontractor packages for Topsides FPSO works Description Scope Company Mooring equipment for chain Material (air shipped) and Noble Denton Singapore number 3 slackening labour Overhaul and refurbish 75,25,5 Laad cell monitoring, Mc-Gregor Plinsol tonn winches service parts and labour Singapore Personnel assistance during Labour in support of Noble Denton- Mc hook-up phase operations by Technip Gregor Labour, tools and tool – HP Tubing and Chemical tubing service container to on board of vessel up to Hulliburton Nigeria perform NAS 6 quality Umbilical plate flushing Labor and logistic to clean Diving and divers equipment bellmouth and install / fix Ken-dive Nigeria new umbilical Small bore spare valves for Material supply Alton piping works Material (air shipped) and Flare radiation shields Thermolimitec engineering Material supply for continuty of installation Dummy fittings Dormen long between piping and flowlines Prefabricated piping (above 2”) Material supply, support for all pipework from porch area during installation, field Amber resources Nigeria back to manifold an Pigs welding Xray testing ABS Singapore and ABS supervision/ approval Process review connected offices 35
  • 36. Abo – Extension Project -OML 125 Estimated subsea contractor delivery schedule (only Items interfacing topsides ) Final delivery for installation : trees between February 2008 and April 2008 Topside control End of June 2008 36
  • 37. OML 125 -ABO Extension project-Installation of FPSO modification 37
  • 38. OML 125 -ABO Extension project 38
  • 39. OML 125 -ABO Extension project 39
  • 40. OML 125 -ABO Extension project The scope of supply for Integrated Control and Safety System modifications included but was not limited to following: • Design, Engineering, Procurement, Programming, Configuration, Software, Graphics, Logics, Fabrication, Assembly, Testing and Commissioning, Preparation for Shipment, packing and supply of System hardware with cabinets, I/O Modules, and Controllers for the “ modification of existing control system at offshore (on the FPSO). Integrated Control and Safety System (ICSS) consisted of : • Process Control System (PCS) • Process Shutdown System (PSD) • Emergency Shutdown & Fire and Gas System (ESD/F&G) • Specifically : • Updating the existing configuration and configuring additional I/O Modules, Spare Channels and Marshalling Termination • Configuration and integration with new ECS system HPU system supplied by Vetco with existing PCS. • Modification to existing graphics and build new graphics. • Upgrading of the redundant controllers for 6MB Capacity. • Supply of IS barrier for intrinsically safe signals. • Review existing M-NET capabilities for additional nodes and its adequacy. • Configuration of existing Tag server database for new I/O’s and its adequacy. • Configuration of existing Historian Server database for new I/O’s. • 4-mation Configuration • Software Configuration and testing (on-shore-offshore) • Configuration of alarm functions for existing inputs-3 Nos • FAT,SAT & Commissioning assistance. • Update Client’s comments at site. • RS485/RS 232 serial link connectors and required network adaptors. • Engineer site deputation for installation, testing and commissioning at ABO FPSO. • Packing and Shipment. • Tagging and labelling. • Supply of special tools. • Documentation. 40
  • 41. OML 125 -ABO Extension project ITEM 5.1 -TOPSIDE FACILITIES-modification of overall subsea control system to be integrated with ABO central ( Using Multi drop communication system protocol) 41
  • 42. OML 125 -ABO Extension project TOPSIDE FACILITIES-Control system © ABB - 1 Extended architecture 42
  • 43. OML 125 -ABO Extension project Location Deck “C” where Container will be placed Internal view Container hosting sub sea 43
  • 44. OML 125 -ABO Extension project 44
  • 45. OML 125 -ABO Extension project Offshore Installation field precommissioning (sample of signed hand over document) TOPSIDE FACILITIES- List of commissioned sub-system 45
  • 46. OML 125 -ABO Extension project FIELD START-UP EFFECTIVE DATES OF ABO EXTENSION Wells start-up dates of ABO COMBINED PROFILE (CENTRAL + ABO EXTENSION) : Wells Date ABO 11 (P1) 14° February 2009 ABO 10 (P2) 15° February 2009 ABO 9 (GI) 20° February 2009 Test of production : mid 2009 46