www.lets-global.com
IIW Document XIII-2430r1-12
Specimens sprayed with artificial salt water
Specimens
Specimens
The As-welded corroded specimens exhibited a slight improved
fatigue strength compared to the As-welded non corroded
specimens.
The surface layer with detrimental residual tensile stresses may
be removed by the corrosion process
and/or
Possible stress concentrations such as weld toe notches and
corrosion pits are ‘softened’ by corrosion
The reduction of the compressive layer (induced by the Ultrasonic Peening treatment) due
to corrosion is detrimental to the fatigue life improvement.
Only a improvement factor of 1.6 was observed after 7.5 years of corrosion
Compare real situation to drawings and/or finite element models
A bracket, which had not been taken into account in the FE model had
been installed at the fatigue hot-spot after a crack repair
The original planned extent of Ultrasonic Peening:
Is this extent of treatment sufficient?
Just because something is written in ink does not mean it is true
Just because something is written in ink does not mean it is true
Visual inspection of fatigue hot-
spots is strongly recommended
prior to planning of work.
Difficulties with access can easily
be assessed on site, but can be
hard to predict from a drawing
and/or from a picture.
ASSET INTEGRITY
Is a result of optimizing the combination of:
• understanding of plant or structure criticality
• degradation mechanisms
• appropriate design
• construction
• plant operation
• maintenance
ASSET INTEGRITY MANAGEMENT
Actions to ensure that a critical equipment or
structure is:
– designed
– constructed
– and operated
so that it remains safe and fit-for-purpose
throughout its entire intended life
ASSET INTEGRITY ASSURANCE
is a combination of many factors of
which Risk Based Inspection
is one important component
Is the optimized application of appropriate
inspection methodology to equipment or
structures based on the risk and consequence of
their failure in such a manner as to provide
reliable information on condition and
deterioration rates
RISK BASED INSPECTION
• Helps understanding the current condition
• Provides information about rate of degradation
when baseline data as
– design philosophy
– operating conditions
– maintenance regimes
– other such data
are also known and linked in to the condition
assessments and prediction.
Benefits of Risk Based Inspection
RBI is an evolution from
• prescriptive regulations
• is a method for optimizing the inspection process
• supports good Asset Integrity Management
It relies on knowledge of other factors in order to
design the RBI programme and,
• to interpret the results
• to predict future condition
Designing a RBI System for an FPSO
• define the key stakeholder objectives
• agree on key project issues such as
– data availability
– baselines
– database selection
– database inputs and outputs.
RBI system depends on
• complete and accurate data
• at the set up stage
• throughout the asset life.
• This data includes:
– Line / Vessel Lists
– Material of construction
– Operating temperatures and pressures
– Design temperatures and pressures (if operating values not available)
– Insulation / lining / cladding details
– System criticality information
– Basic fluid composition
– Heat and Material Balance
– Process System Description
– Materials selection basis
– Fabrication drawings, Datasheets etc
– Plus many others
RISKScreeningMatrix
SCREENING
• Screening can be performed at any level such as a
complete facility or process unit, down to multiple
or individual pieces of equipment. It is
recommended to do a good quality risk screening
where data is readily available such as a complete
process line list/vessel list.
• If data is less readily available a risk screening by
system/structural component may be more
appropriate.
Structural Integrity Life Extension
for FPSO
a) b)
d)
c)
a) b)
d)
c)
a) b)
d)
c)
a) b)
d)
c)
a) b)
d)
c)
1 2 3
?
4
Possible number of people in a confined space
- Alternative escape route
- Escape route length
- Company policy
- Not a exact science….
5
A temporary platform is spot-welded
into a bulkhead.
All personnel continuously secured
with Rope Access methods
No extensive testing/safety measure of
the platform itself is necessary before
work can start.
Advantages:
-Quick to set up
-Improves working quality
Drawbacks:
-Hot-work
malcolm.hedmar@lets-global.com
LETS Global Ultrasonic Peening
Procedure
Lloyd’s Approval
- Fatigue hot-spots found in four FPSO cargotanks
- Bulkhead and bracket welds treated by UP rope access team
- January 2011 to February 2012
malcolm.hedmar@lets-global.com
Transverse cargo tank bracket; 6 hours required
Ultrasonic Peening treated area;
- 300mm on each side of bracket
Transverse cargo tank bracket
Bulkhead connection; 8 hours required
Scenario
Fatigue hot-spot located in cargo oil tank
Weld improvement method; Ultrasonic Peening
12m
-Quick to install
-Good access to fatigue hot-spot
-Equipment can rest on platform
Fatigue hot-spot
Drawings recieved from client;
Planned extent of Ultrasonic Peening
Offshore Rig Life Extension
Offshore Rig Life Extension

Offshore Rig Life Extension

  • 3.
  • 4.
  • 5.
    Specimens sprayed withartificial salt water Specimens
  • 6.
  • 7.
    The As-welded corrodedspecimens exhibited a slight improved fatigue strength compared to the As-welded non corroded specimens.
  • 8.
    The surface layerwith detrimental residual tensile stresses may be removed by the corrosion process and/or Possible stress concentrations such as weld toe notches and corrosion pits are ‘softened’ by corrosion
  • 9.
    The reduction ofthe compressive layer (induced by the Ultrasonic Peening treatment) due to corrosion is detrimental to the fatigue life improvement. Only a improvement factor of 1.6 was observed after 7.5 years of corrosion
  • 10.
    Compare real situationto drawings and/or finite element models
  • 12.
    A bracket, whichhad not been taken into account in the FE model had been installed at the fatigue hot-spot after a crack repair The original planned extent of Ultrasonic Peening: Is this extent of treatment sufficient?
  • 13.
    Just because somethingis written in ink does not mean it is true
  • 14.
    Just because somethingis written in ink does not mean it is true
  • 18.
    Visual inspection offatigue hot- spots is strongly recommended prior to planning of work. Difficulties with access can easily be assessed on site, but can be hard to predict from a drawing and/or from a picture.
  • 19.
    ASSET INTEGRITY Is aresult of optimizing the combination of: • understanding of plant or structure criticality • degradation mechanisms • appropriate design • construction • plant operation • maintenance
  • 20.
    ASSET INTEGRITY MANAGEMENT Actionsto ensure that a critical equipment or structure is: – designed – constructed – and operated so that it remains safe and fit-for-purpose throughout its entire intended life
  • 21.
    ASSET INTEGRITY ASSURANCE isa combination of many factors of which Risk Based Inspection is one important component
  • 22.
    Is the optimizedapplication of appropriate inspection methodology to equipment or structures based on the risk and consequence of their failure in such a manner as to provide reliable information on condition and deterioration rates RISK BASED INSPECTION
  • 23.
    • Helps understandingthe current condition • Provides information about rate of degradation when baseline data as – design philosophy – operating conditions – maintenance regimes – other such data are also known and linked in to the condition assessments and prediction. Benefits of Risk Based Inspection
  • 24.
    RBI is anevolution from • prescriptive regulations • is a method for optimizing the inspection process • supports good Asset Integrity Management It relies on knowledge of other factors in order to design the RBI programme and, • to interpret the results • to predict future condition
  • 25.
    Designing a RBISystem for an FPSO • define the key stakeholder objectives • agree on key project issues such as – data availability – baselines – database selection – database inputs and outputs.
  • 26.
    RBI system dependson • complete and accurate data • at the set up stage • throughout the asset life. • This data includes: – Line / Vessel Lists – Material of construction – Operating temperatures and pressures – Design temperatures and pressures (if operating values not available) – Insulation / lining / cladding details – System criticality information – Basic fluid composition – Heat and Material Balance – Process System Description – Materials selection basis – Fabrication drawings, Datasheets etc – Plus many others
  • 27.
  • 28.
    SCREENING • Screening canbe performed at any level such as a complete facility or process unit, down to multiple or individual pieces of equipment. It is recommended to do a good quality risk screening where data is readily available such as a complete process line list/vessel list. • If data is less readily available a risk screening by system/structural component may be more appropriate.
  • 29.
    Structural Integrity LifeExtension for FPSO
  • 30.
  • 31.
  • 32.
  • 33.
  • 34.
  • 35.
    1 2 3 ? 4 Possiblenumber of people in a confined space - Alternative escape route - Escape route length - Company policy - Not a exact science…. 5
  • 38.
    A temporary platformis spot-welded into a bulkhead. All personnel continuously secured with Rope Access methods No extensive testing/safety measure of the platform itself is necessary before work can start. Advantages: -Quick to set up -Improves working quality Drawbacks: -Hot-work
  • 40.
    malcolm.hedmar@lets-global.com LETS Global UltrasonicPeening Procedure Lloyd’s Approval
  • 41.
    - Fatigue hot-spotsfound in four FPSO cargotanks - Bulkhead and bracket welds treated by UP rope access team - January 2011 to February 2012 malcolm.hedmar@lets-global.com
  • 42.
    Transverse cargo tankbracket; 6 hours required Ultrasonic Peening treated area; - 300mm on each side of bracket
  • 43.
  • 44.
    Bulkhead connection; 8hours required
  • 45.
    Scenario Fatigue hot-spot locatedin cargo oil tank Weld improvement method; Ultrasonic Peening
  • 46.
  • 47.
    -Quick to install -Goodaccess to fatigue hot-spot -Equipment can rest on platform
  • 48.
  • 49.
    Drawings recieved fromclient; Planned extent of Ultrasonic Peening