The document provides a project update on the Açu Shipyard in Brazil. Key points include:
1) Construction is underway and licenses have been obtained. 2) An industrial district is being established to cluster heavy industry. 3) The shipyard setup includes areas for platform construction, modules, and administration buildings. 4) Advantages of the site include welding cost savings, optimal weather, soil conditions, and proximity to oil fields. 5) Current capital expenditures and order books for FPSOs and WHPs are outlined.
The document provides a project update for Açu Shipyard in Brazil. It discusses the licensing process for the shipyard, the construction of an industrial district, and details on the shipyard's setup. Advantages of the site include welding and energy savings as well as optimal weather. The document outlines the projected capex and provides details on current orders, including progress on FPSO OSX 1 and systems for OSX 2-3. Finally, it notes the purchase of two VLCCs for conversion to FPSOs OSX 4-5.
The document provides a project update on the Açu Shipyard in Brazil. It discusses the shipyard's licensing process and outlines its site layout. Advantages of the Açu site over an alternative in Biguaçu are presented, including lower construction costs from larger steel plates and better weather. The capital expenditure budget is given along with details of OSX's current order book from OGX, including timelines and costs for 5 FPSOs and 2 WHPs. Construction progress updates are provided for the first FPSO.
1) The document provides a project update for OSX Shipbuilding in September 2011. It summarizes progress on the FPSO OSX-1, including its sail away ceremony in early October 2011 and journey to Brazil.
2) Details are given on the OSX-2/WHP-1 system timelines, with the FPSO OSX-2 under construction in Singapore and the WHP-1 to start construction in 4Q 2011 for load out in 2Q 2013.
3) Financing is committed for both projects through long term debt with major banks and contractors signed or under negotiation for engineering and construction.
1) The document provides a project update for OSX Shipbuilding in September 2011, including progress on the FPSO OSX-1 project. FPSO OSX-1 has achieved milestones like sail away and receiving its preliminary license.
2) Details are given on the construction timeline and financing for the Açu Shipyard in Brazil, with over $1.9 billion being spent on dredging, buildings, and infrastructure.
3) Upcoming projects discussed include the FPSO OSX-2 and WHP-1 system for OGX's offshore fields, with construction of both underway.
The document provides a project update for OSX Shipbuilding in September 2011. Key highlights include:
- FPSO OSX-1 is scheduled to arrive in Brazil in early October after its sail away ceremony. Financing is committed for FPSO OSX-2 and construction is underway.
- WHP-1 and WHP-2 construction will begin in 4Q 2011. Financing is being finalized for FPSO OSX-3, WHP-1 and WHP-2.
- The Itamarati Naval Technology Institute aims to qualify 3,100 personnel by end of 2012 to support the shipyard workforce, utilizing existing technical schools.
- Upcoming milestones include the
This project update provides information on the development of the Açu Industrial Complex in Rio de Janeiro, Brazil. The complex will cover 90 square kilometers and include areas for platform construction, module construction, dry dock facilities, and administrative buildings. Licensing and construction are underway, with initial areas and quays expected to be completed in 2012-2014. The complex will support the construction and integration of FPSO vessels and related offshore oil and gas infrastructure for projects with OGX Petroleo e Gas Participacoes S.A.
TVSA-T fuel assembly for “Temelin” NPP. Main results of design and safety ana...myatom
The document summarizes the design and safety analyses of the TVSA-T fuel assembly developed for the Temelin NPP in the Czech Republic. Key points include:
1) TVSA-T is based on the proven TVSA design with additional modifications like combined spacer grids and a longer fuel column.
2) Extensive testing and analyses were conducted to validate the TVSA-T design including thermohydraulic tests, mechanical tests, and safety analyses.
3) The design was successfully licensed for use at Temelin NPP unit 1 and meets all safety criteria for normal operation and accident conditions.
The document discusses the evolution and advanced designs of VVER reactors. It describes the current challenges facing nuclear power plants and how generation 3+ designs, such as the VVER-1200, aim to address these through extended lifetimes, reduced costs and construction times. Future innovative designs discussed include the VVER-600, VVER-SCP generation 4 supercritical water cooled reactor, and concepts using tight fuel assemblies for a closed nuclear fuel cycle. The VVER-1200 design for project AES-2006 forms the basis for the further developed MIR-1200 design being implemented in the Czech Republic.
The document provides a project update for Açu Shipyard in Brazil. It discusses the licensing process for the shipyard, the construction of an industrial district, and details on the shipyard's setup. Advantages of the site include welding and energy savings as well as optimal weather. The document outlines the projected capex and provides details on current orders, including progress on FPSO OSX 1 and systems for OSX 2-3. Finally, it notes the purchase of two VLCCs for conversion to FPSOs OSX 4-5.
The document provides a project update on the Açu Shipyard in Brazil. It discusses the shipyard's licensing process and outlines its site layout. Advantages of the Açu site over an alternative in Biguaçu are presented, including lower construction costs from larger steel plates and better weather. The capital expenditure budget is given along with details of OSX's current order book from OGX, including timelines and costs for 5 FPSOs and 2 WHPs. Construction progress updates are provided for the first FPSO.
1) The document provides a project update for OSX Shipbuilding in September 2011. It summarizes progress on the FPSO OSX-1, including its sail away ceremony in early October 2011 and journey to Brazil.
2) Details are given on the OSX-2/WHP-1 system timelines, with the FPSO OSX-2 under construction in Singapore and the WHP-1 to start construction in 4Q 2011 for load out in 2Q 2013.
3) Financing is committed for both projects through long term debt with major banks and contractors signed or under negotiation for engineering and construction.
1) The document provides a project update for OSX Shipbuilding in September 2011, including progress on the FPSO OSX-1 project. FPSO OSX-1 has achieved milestones like sail away and receiving its preliminary license.
2) Details are given on the construction timeline and financing for the Açu Shipyard in Brazil, with over $1.9 billion being spent on dredging, buildings, and infrastructure.
3) Upcoming projects discussed include the FPSO OSX-2 and WHP-1 system for OGX's offshore fields, with construction of both underway.
The document provides a project update for OSX Shipbuilding in September 2011. Key highlights include:
- FPSO OSX-1 is scheduled to arrive in Brazil in early October after its sail away ceremony. Financing is committed for FPSO OSX-2 and construction is underway.
- WHP-1 and WHP-2 construction will begin in 4Q 2011. Financing is being finalized for FPSO OSX-3, WHP-1 and WHP-2.
- The Itamarati Naval Technology Institute aims to qualify 3,100 personnel by end of 2012 to support the shipyard workforce, utilizing existing technical schools.
- Upcoming milestones include the
This project update provides information on the development of the Açu Industrial Complex in Rio de Janeiro, Brazil. The complex will cover 90 square kilometers and include areas for platform construction, module construction, dry dock facilities, and administrative buildings. Licensing and construction are underway, with initial areas and quays expected to be completed in 2012-2014. The complex will support the construction and integration of FPSO vessels and related offshore oil and gas infrastructure for projects with OGX Petroleo e Gas Participacoes S.A.
TVSA-T fuel assembly for “Temelin” NPP. Main results of design and safety ana...myatom
The document summarizes the design and safety analyses of the TVSA-T fuel assembly developed for the Temelin NPP in the Czech Republic. Key points include:
1) TVSA-T is based on the proven TVSA design with additional modifications like combined spacer grids and a longer fuel column.
2) Extensive testing and analyses were conducted to validate the TVSA-T design including thermohydraulic tests, mechanical tests, and safety analyses.
3) The design was successfully licensed for use at Temelin NPP unit 1 and meets all safety criteria for normal operation and accident conditions.
The document discusses the evolution and advanced designs of VVER reactors. It describes the current challenges facing nuclear power plants and how generation 3+ designs, such as the VVER-1200, aim to address these through extended lifetimes, reduced costs and construction times. Future innovative designs discussed include the VVER-600, VVER-SCP generation 4 supercritical water cooled reactor, and concepts using tight fuel assemblies for a closed nuclear fuel cycle. The VVER-1200 design for project AES-2006 forms the basis for the further developed MIR-1200 design being implemented in the Czech Republic.
Key Features of MIR.1200 (AES-2006) design and current stage of Leningrad NP...myatom
The document discusses the key features and current construction status of the MIR.1200/AES-2006 nuclear power plant design and Leningrad NPP-2, which uses this design. The MIR.1200 design is an evolution of previous VVER reactor designs with improved safety features like a double containment structure and passive safety systems. Leningrad NPP-2 Units 1 and 2 are currently under construction in Russia using this design. The design provides enhanced safety, economics, and project attractiveness through an evolutionary approach and leveraging designs already implemented in other plants.
The document provides information about the Clinton Climate Initiative's Clean Energy Program presentation to the Asian Development Bank on June 15, 2009. It introduces the CCI's solar park concept and discusses concentrated solar thermal power and photovoltaic technologies. Key points covered include the benefits of developing utility-scale solar parks, the status of CCI's solar project in South Africa, and summaries of parabolic trough and power tower technologies.
The document provides an overview and status update of the Thorntonbank offshore wind farm project in Belgium. It summarizes that the project involves building the wind farm in three phases to reach a total capacity of 325.7 MW. Phase 1 with 6 turbines is already operational. Contracts are being finalized for Phase 2 in 2011-2012 and Phase 3 in 2012-2013, which will each involve installing 24 larger 6 MW turbines. Financing is expected to close in Q3 2010 to allow construction to proceed.
Business opportunities in PHWR and technical preparedness from vendors Philip...ProSIM R & D Pvt. Ltd.
The document outlines NPCIL's plans to build nuclear reactors in India in a "fleet mode" whereby 10 reactors of 700MWe each will be constructed simultaneously over the next 10-12 years, presenting challenges for standardized engineering, establishing a robust supply chain, and developing adequate human resources for the nuclear industry to support the rapid expansion.
This document provides a project update on the Açu Industrial Complex shipbuilding unit in Rio de Janeiro, Brazil. Key details include:
- Construction is underway on infrastructure like buildings, quays, and utilities, with partial deliveries expected starting in 2012.
- Financing of $1.9 billion is secured from the Merchant Marine Fund for the project.
- FPSO OSX-1 has begun operations for OGX, and schedules and financing plans are outlined for additional FPSOs and production units through 2014.
- Partnerships with Korean companies and training institutes are helping to develop the local workforce and supply chain for the offshore and shipbuilding industries in Brazil.
The document provides design details for a supported conical roof tank, including summaries of shell course design, roof design, bottom design, and anchor bolt design. Key specifications include a tank diameter of 31.16 feet, shell height of 35.43 feet, and material thicknesses between 0.315 and 0.3937 inches. The roof requires a minimum thickness of 0.3055 inches and has 14 rafters. The bottom has a flat annular design.
Gas Recovery Systems Vopak VCM Sphere ProjectFred Reyes
The Gas Recovery System
Sphere Recovery Presentation
Presents
Vopak Royal Inc.
2001 Vopak 6650 CBM VCM Sphere
Decontamination & Degassing
Project
Teesside, UK
ESS Bilbao Initiative Workshop Talk. Javier BermejoESS BILBAO
This document outlines a proposed superconducting proton linac design for the ESS-Bilbao accelerator. Key points include:
- The design proposes using existing superconducting spoke and elliptical cavities to accelerate a proton beam to 1400 MeV, requiring fewer sections and frequency jumps than the baseline ESS design.
- The superconducting section would extend down to 30 MeV, taking advantage of mature superconducting technology.
- Design goals include minimizing length and cost while achieving high accelerating gradients up to 30 MV/m.
- Key research and development issues include controlling higher-order modes and wakefield effects at high beam currents up to 150 mA.
- Collaboration
The JET EP2 enhancement program aims to upgrade JET to support ITER-relevant experiments. Key upgrades include installing an ITER-like beryllium wall and tungsten divertor (ILW), increasing the neutral beam injection power, and improving plasma control and diagnostics. Over 60 contracts have been signed to complete these upgrades, with many contracts experiencing delays. Careful synchronization will be needed during the upcoming shutdown to complete the installation of all components before restarting plasma operations in late 2010. The upgrades aim to allow experimentation with ITER-relevant plasma scenarios while optimizing lifetime, performance and tritium retention in preparation for ITER.
Marine Demands for 2020-2030: Local Content and opportunities in a new enviro...Petrobras
Marine Demands for 2020-2030:
Local Content and opportunities
in a new environment
Petrobras' Technical Seminar
Paulo Sergio Rodrigues Alonso
Petrobras Local Content Advisor to the CEO
Executive Coordinator of PROMINP
Offshore Technology Conference (OTC)
Houston, 04th May 2015
The document provides a project update on the Açu Industrial Complex in Rio de Janeiro, Brazil. Construction is underway on infrastructure including quays, buildings, and dredging canals. Delivery of key areas and equipment is expected between 2012-2014. The FPSO OSX-1 arrived in December 2011 and began production in January 2012. Long term financing of $1.9 billion was secured for construction through government funds and private banks. Additional FPSOs and production platforms are on order to develop fields for oil company OGX according to milestones in 2012-2013.
OSX's order book includes contracts to build and lease several FPSOs and WHPs to OGX, as well as a PLSV to Sapura and two FPSOs to Petrobras. The current orders are estimated at over $9 billion and will help utilize the new shipbuilding facility in Açu, Brazil, which began operations in early 2013. Delivery of the units is scheduled between 2013-2017. OSX also awaits specifications from OGX for additional potential orders.
This management presentation provides an overview of OGX Petróleo e Gás S.A., a Brazilian oil and gas exploration company. It summarizes that OGX has a highly experienced management team, a world-class portfolio of 34 blocks (30 in Brazil, 4 in Colombia), and over 10.8 billion barrels of potential recoverable resources. A key focus of OGX is the Campos Basin offshore Brazil, where they have already discovered over 4 billion barrels of oil and are developing the Tubarão Azul and Tubarão Martelo fields.
18 09-2008 José Miranda Formigli Filho na Rio oil and Gas Expo Conference no ...Petrobras
The presentation discusses development plans for pre-salt oil fields in the Santos Basin offshore Brazil. It provides technical details on key fields like Tupi and Iara, outlining the challenging reservoir characteristics, production design for Tupi's pilot project, and technological hurdles. It then summarizes Petrobras' strategic approach to infrastructure development through its PLANSAL program, focusing on standardized production platforms, subsea pipelines, and contracting drilling rigs to enable significant production by 2017.
This management presentation discusses OGX, a large oil and gas exploration company. It outlines OGX's portfolio of 10.8 billion barrels of potential oil and gas resources across Brazil and Colombia. The presentation notes that OGX has achieved a high exploration success rate above 90% and made several multi-billion barrel discoveries. It also describes OGX's cash position, operational experience, and the growth opportunities in Brazil's historically under-explored oil and gas fields. However, the presentation includes numerous disclaimers around the uncertainties and risks inherent in projections and resource estimates for a development stage company.
2014 Global Energy Conference – Credit SuissePetrobras
Rudimar Lorenzatto (Exploration & Production)
AGENDA
• BUSINESS AND MANAGEMENT PLAN 2014-2018
• PRODUCTION UPDATE-RAMPING UP NEW SYSTEMS-MAINTAINING EXISTING SYSTEMS
• PER BOE ANALYSIS
• PRE-SALT UPDATE
• NEW UNITS
June, 2014
The document provides a project update on the Açu Shipyard and FPSO OSX-1. Key points include:
1) Construction began in July at the Açu Shipyard, which will allow for simultaneous integration of multiple FPSOs and WHPs.
2) FPSO OSX-1 is nearing completion, with mechanical works finished and commissioning underway. Delivery to Brazil is expected in 3Q 2011.
3) The document outlines timelines and progress for the construction of future projects like FPSO OSX-2, WHP-1, and others, establishing Açu Shipyard as a hub for offshore oil and gas development.
The document provides updates on several projects at OSX shipbuilding. It summarizes that:
1) FPSO OSX-1 has achieved sail away and is scheduled to arrive in Brazil in early October. OSX-2/WHP-1 engineering is underway with construction starting in late 2011.
2) OSX-3/WHP-2 timelines have VLCC acquisition and engineering beginning in 2012.
3) Standardization efforts and the OSXflex engineering concept aim to accelerate future FPSO delivery timelines starting with OSX-4 and OSX-5.
4) ITN phase 1 will provide workforce training with enrollment through late 2011 and classes starting in early 2012
This document provides a project update for OSX Shipbuilding's Açu Industrial Complex in November 2011. Key details include:
- Construction is underway on infrastructure and buildings at the complex, including quays, dry docks, industrial buildings, and administrative facilities.
- Licensing and permitting is on schedule, with preliminary licenses issued and installation licenses expected in mid-2011.
- The shipbuilding unit is on track to deliver areas for jacket and module assembly starting in late 2012 through 2014.
- Financing is in place through the Merchant Marine Fund to cover 80% of the project's capital expenditures.
- FPSO OSX-1 is undergoing customization work and is scheduled to arrive at
This document provides a project update for an offshore shipbuilding complex in Brazil. It includes details on licensing and construction schedules, estimated partial deliveries from 2012-2014, financing from the Merchant Marine Fund, and current order books for FPSOs and wellhead platforms. Pictures show progress on constructing the industrial complex, canals, breakwaters and terrain work. Ship specifications and crew details are given for the FPSO OSX-1, and systems are outlined for the OSX-2/WHP-1 project and planned OSX-3/WHP-2 project.
This document provides a project update for OSX Shipbuilding in November 2011. It discusses the construction progress of the UCN Açu industrial district, including licensing schedules and estimated delivery dates for construction areas and sections. It also provides details on the current order book status for OGX, including specifications and estimated delivery dates for FPSOs and wellhead platforms. Construction updates are given for FPSO OSX-1, the OSX-2/WHP-1 system, and the planned OSX-3/WHP-2 system.
This document provides a project update for November 2011. It summarizes progress on several fronts:
1) Construction is underway at the UCN Açu shipbuilding facility, with key areas and infrastructure under development. Licensing was obtained and construction began in July 2011.
2) Several FPSOs and production units are under construction or nearing completion. FPSO OSX-1 will achieve first oil for OGX in December 2011. OSX-2, OSX-3, and related production units are progressing on schedule.
3) Plans are outlined for qualifying thousands of personnel for heavy industry jobs through the ITN training program by end of 2012, using facilities in Campos and other cities.
Key Features of MIR.1200 (AES-2006) design and current stage of Leningrad NP...myatom
The document discusses the key features and current construction status of the MIR.1200/AES-2006 nuclear power plant design and Leningrad NPP-2, which uses this design. The MIR.1200 design is an evolution of previous VVER reactor designs with improved safety features like a double containment structure and passive safety systems. Leningrad NPP-2 Units 1 and 2 are currently under construction in Russia using this design. The design provides enhanced safety, economics, and project attractiveness through an evolutionary approach and leveraging designs already implemented in other plants.
The document provides information about the Clinton Climate Initiative's Clean Energy Program presentation to the Asian Development Bank on June 15, 2009. It introduces the CCI's solar park concept and discusses concentrated solar thermal power and photovoltaic technologies. Key points covered include the benefits of developing utility-scale solar parks, the status of CCI's solar project in South Africa, and summaries of parabolic trough and power tower technologies.
The document provides an overview and status update of the Thorntonbank offshore wind farm project in Belgium. It summarizes that the project involves building the wind farm in three phases to reach a total capacity of 325.7 MW. Phase 1 with 6 turbines is already operational. Contracts are being finalized for Phase 2 in 2011-2012 and Phase 3 in 2012-2013, which will each involve installing 24 larger 6 MW turbines. Financing is expected to close in Q3 2010 to allow construction to proceed.
Business opportunities in PHWR and technical preparedness from vendors Philip...ProSIM R & D Pvt. Ltd.
The document outlines NPCIL's plans to build nuclear reactors in India in a "fleet mode" whereby 10 reactors of 700MWe each will be constructed simultaneously over the next 10-12 years, presenting challenges for standardized engineering, establishing a robust supply chain, and developing adequate human resources for the nuclear industry to support the rapid expansion.
This document provides a project update on the Açu Industrial Complex shipbuilding unit in Rio de Janeiro, Brazil. Key details include:
- Construction is underway on infrastructure like buildings, quays, and utilities, with partial deliveries expected starting in 2012.
- Financing of $1.9 billion is secured from the Merchant Marine Fund for the project.
- FPSO OSX-1 has begun operations for OGX, and schedules and financing plans are outlined for additional FPSOs and production units through 2014.
- Partnerships with Korean companies and training institutes are helping to develop the local workforce and supply chain for the offshore and shipbuilding industries in Brazil.
The document provides design details for a supported conical roof tank, including summaries of shell course design, roof design, bottom design, and anchor bolt design. Key specifications include a tank diameter of 31.16 feet, shell height of 35.43 feet, and material thicknesses between 0.315 and 0.3937 inches. The roof requires a minimum thickness of 0.3055 inches and has 14 rafters. The bottom has a flat annular design.
Gas Recovery Systems Vopak VCM Sphere ProjectFred Reyes
The Gas Recovery System
Sphere Recovery Presentation
Presents
Vopak Royal Inc.
2001 Vopak 6650 CBM VCM Sphere
Decontamination & Degassing
Project
Teesside, UK
ESS Bilbao Initiative Workshop Talk. Javier BermejoESS BILBAO
This document outlines a proposed superconducting proton linac design for the ESS-Bilbao accelerator. Key points include:
- The design proposes using existing superconducting spoke and elliptical cavities to accelerate a proton beam to 1400 MeV, requiring fewer sections and frequency jumps than the baseline ESS design.
- The superconducting section would extend down to 30 MeV, taking advantage of mature superconducting technology.
- Design goals include minimizing length and cost while achieving high accelerating gradients up to 30 MV/m.
- Key research and development issues include controlling higher-order modes and wakefield effects at high beam currents up to 150 mA.
- Collaboration
The JET EP2 enhancement program aims to upgrade JET to support ITER-relevant experiments. Key upgrades include installing an ITER-like beryllium wall and tungsten divertor (ILW), increasing the neutral beam injection power, and improving plasma control and diagnostics. Over 60 contracts have been signed to complete these upgrades, with many contracts experiencing delays. Careful synchronization will be needed during the upcoming shutdown to complete the installation of all components before restarting plasma operations in late 2010. The upgrades aim to allow experimentation with ITER-relevant plasma scenarios while optimizing lifetime, performance and tritium retention in preparation for ITER.
Marine Demands for 2020-2030: Local Content and opportunities in a new enviro...Petrobras
Marine Demands for 2020-2030:
Local Content and opportunities
in a new environment
Petrobras' Technical Seminar
Paulo Sergio Rodrigues Alonso
Petrobras Local Content Advisor to the CEO
Executive Coordinator of PROMINP
Offshore Technology Conference (OTC)
Houston, 04th May 2015
The document provides a project update on the Açu Industrial Complex in Rio de Janeiro, Brazil. Construction is underway on infrastructure including quays, buildings, and dredging canals. Delivery of key areas and equipment is expected between 2012-2014. The FPSO OSX-1 arrived in December 2011 and began production in January 2012. Long term financing of $1.9 billion was secured for construction through government funds and private banks. Additional FPSOs and production platforms are on order to develop fields for oil company OGX according to milestones in 2012-2013.
OSX's order book includes contracts to build and lease several FPSOs and WHPs to OGX, as well as a PLSV to Sapura and two FPSOs to Petrobras. The current orders are estimated at over $9 billion and will help utilize the new shipbuilding facility in Açu, Brazil, which began operations in early 2013. Delivery of the units is scheduled between 2013-2017. OSX also awaits specifications from OGX for additional potential orders.
This management presentation provides an overview of OGX Petróleo e Gás S.A., a Brazilian oil and gas exploration company. It summarizes that OGX has a highly experienced management team, a world-class portfolio of 34 blocks (30 in Brazil, 4 in Colombia), and over 10.8 billion barrels of potential recoverable resources. A key focus of OGX is the Campos Basin offshore Brazil, where they have already discovered over 4 billion barrels of oil and are developing the Tubarão Azul and Tubarão Martelo fields.
18 09-2008 José Miranda Formigli Filho na Rio oil and Gas Expo Conference no ...Petrobras
The presentation discusses development plans for pre-salt oil fields in the Santos Basin offshore Brazil. It provides technical details on key fields like Tupi and Iara, outlining the challenging reservoir characteristics, production design for Tupi's pilot project, and technological hurdles. It then summarizes Petrobras' strategic approach to infrastructure development through its PLANSAL program, focusing on standardized production platforms, subsea pipelines, and contracting drilling rigs to enable significant production by 2017.
This management presentation discusses OGX, a large oil and gas exploration company. It outlines OGX's portfolio of 10.8 billion barrels of potential oil and gas resources across Brazil and Colombia. The presentation notes that OGX has achieved a high exploration success rate above 90% and made several multi-billion barrel discoveries. It also describes OGX's cash position, operational experience, and the growth opportunities in Brazil's historically under-explored oil and gas fields. However, the presentation includes numerous disclaimers around the uncertainties and risks inherent in projections and resource estimates for a development stage company.
2014 Global Energy Conference – Credit SuissePetrobras
Rudimar Lorenzatto (Exploration & Production)
AGENDA
• BUSINESS AND MANAGEMENT PLAN 2014-2018
• PRODUCTION UPDATE-RAMPING UP NEW SYSTEMS-MAINTAINING EXISTING SYSTEMS
• PER BOE ANALYSIS
• PRE-SALT UPDATE
• NEW UNITS
June, 2014
The document provides a project update on the Açu Shipyard and FPSO OSX-1. Key points include:
1) Construction began in July at the Açu Shipyard, which will allow for simultaneous integration of multiple FPSOs and WHPs.
2) FPSO OSX-1 is nearing completion, with mechanical works finished and commissioning underway. Delivery to Brazil is expected in 3Q 2011.
3) The document outlines timelines and progress for the construction of future projects like FPSO OSX-2, WHP-1, and others, establishing Açu Shipyard as a hub for offshore oil and gas development.
The document provides updates on several projects at OSX shipbuilding. It summarizes that:
1) FPSO OSX-1 has achieved sail away and is scheduled to arrive in Brazil in early October. OSX-2/WHP-1 engineering is underway with construction starting in late 2011.
2) OSX-3/WHP-2 timelines have VLCC acquisition and engineering beginning in 2012.
3) Standardization efforts and the OSXflex engineering concept aim to accelerate future FPSO delivery timelines starting with OSX-4 and OSX-5.
4) ITN phase 1 will provide workforce training with enrollment through late 2011 and classes starting in early 2012
This document provides a project update for OSX Shipbuilding's Açu Industrial Complex in November 2011. Key details include:
- Construction is underway on infrastructure and buildings at the complex, including quays, dry docks, industrial buildings, and administrative facilities.
- Licensing and permitting is on schedule, with preliminary licenses issued and installation licenses expected in mid-2011.
- The shipbuilding unit is on track to deliver areas for jacket and module assembly starting in late 2012 through 2014.
- Financing is in place through the Merchant Marine Fund to cover 80% of the project's capital expenditures.
- FPSO OSX-1 is undergoing customization work and is scheduled to arrive at
This document provides a project update for an offshore shipbuilding complex in Brazil. It includes details on licensing and construction schedules, estimated partial deliveries from 2012-2014, financing from the Merchant Marine Fund, and current order books for FPSOs and wellhead platforms. Pictures show progress on constructing the industrial complex, canals, breakwaters and terrain work. Ship specifications and crew details are given for the FPSO OSX-1, and systems are outlined for the OSX-2/WHP-1 project and planned OSX-3/WHP-2 project.
This document provides a project update for OSX Shipbuilding in November 2011. It discusses the construction progress of the UCN Açu industrial district, including licensing schedules and estimated delivery dates for construction areas and sections. It also provides details on the current order book status for OGX, including specifications and estimated delivery dates for FPSOs and wellhead platforms. Construction updates are given for FPSO OSX-1, the OSX-2/WHP-1 system, and the planned OSX-3/WHP-2 system.
This document provides a project update for November 2011. It summarizes progress on several fronts:
1) Construction is underway at the UCN Açu shipbuilding facility, with key areas and infrastructure under development. Licensing was obtained and construction began in July 2011.
2) Several FPSOs and production units are under construction or nearing completion. FPSO OSX-1 will achieve first oil for OGX in December 2011. OSX-2, OSX-3, and related production units are progressing on schedule.
3) Plans are outlined for qualifying thousands of personnel for heavy industry jobs through the ITN training program by end of 2012, using facilities in Campos and other cities.
The document provides a project update for November 2011 regarding OSX's shipbuilding operations. Key details include:
- Construction is underway at the UCN Açu industrial district site for modules, quays, buildings and other infrastructure to support FPSO integration.
- The FPSO OSX-1 is scheduled to arrive in Rio de Janeiro in October 2011 and achieve first oil for OGX in December 2011.
- Other FPSOs and production units are in various stages of procurement, conversion, and scheduled delivery between 2012-2014 to support OGX's production plans.
- Project accelerators like standardizing equipment and using flexible engineering are aimed to reduce costs and timelines for future FPS
This project update provides information on the Açu Industrial Complex located in Rio de Janeiro, Brazil. Key points include:
- The 90km2 industrial complex will include areas for platform construction, module construction, dry dock facilities, and administrative buildings.
- Construction is underway, with licensing obtained in early 2011 and initial construction starting in late 2011.
- OSX is constructing several FPSO and production units for the OGX fields through 2014. The first FPSO, OSX-1, will be delivered in 3Q 2011.
- Infrastructure at the Açu complex like quays, buildings and utilities will be delivered in phases through 2014 to support integration and operation of the FPSO
This document provides a project update for November 2011 on several OSX shipbuilding initiatives. Key details include:
- Construction is underway at the 90km2 Açu Industrial Complex in Brazil, with licensing obtained and construction of various areas and infrastructure progressing.
- The order book includes FPSOs OSX-1 through OSX-5 along with WHP-1 and WHP-2, with delivery timelines ranging from late 2011 through 2014.
- Progress is outlined on the individual FPSO and WHP units, including customization work, integration timelines at the Açu facility, and financing arrangements.
- Plans are discussed to accelerate future projects through standardization, engineering innovations
The document provides a project update on the Açu Industrial Complex in Rio de Janeiro, Brazil. Key points include:
1) Construction is underway on the 90km2 industrial complex which will include areas for platform construction, module construction, dry docks, and more.
2) Several milestones have been achieved including licensing, mobilization, and beginning of construction. Delivery of the first FPSO (OSX-1) to OGX is scheduled for 3Q 2011.
3) Future plans include continued construction of infrastructure and delivery of additional FPSOs and production units to support oil production for OGX through 2014.
ASL Shipyard is a subsidiary of ASL Marine Holdings Ltd, a marine company headquartered in Singapore that owns and operates three shipyards in Singapore, Indonesia, and China. ASL Shipyard provides shipbuilding, ship repair, and marine engineering services. It has successfully navigated economic cycles through steady growth and profitability by integrating shipbuilding and repair capabilities. Going forward, ASL Shipyard aims to expand its service range and improve capabilities to continue serving customers from different industries and regions.
ARGOMARINE final conference - EU presentation - Maurizio MaggioreARGOMARINE
The European Commission Framework Programmes support EU maritime safety research through several projects focused on issues like ship safety, oil pollution elimination, tanker wreck remediation, and oil spill response. Over 45 million euros have been invested in 17 waterborne transportation projects between 2007 and 2013 addressing these topics. Maritime safety is an important priority for the European Commission's transport research directorate.
Offshore Engineering has 10 years of experience providing engineering design and quality validation services for offshore oil and gas projects. They have expertise in FPSO and topside design, and have worked on numerous projects in various countries, including designing modules for FPSOs with oil processing, water injection, gas compression, and flare systems. Offshore Engineering partners with Kavin Engineering to leverage their combined expertise in executing FPSO projects.
AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)coderweb
The document describes the design of an ultra deep water rigid and flexible pipelay/heavy lift/DP3 construction vessel. Some key details include:
It is 178 meters long with a breadth of 46 meters and draft of 15.6 meters. It can accommodate 239 people and has a deadweight of 11,000 tons. It is equipped with a 3000 ton crane, 1200 ton reels, 1250 ton carousels, and dynamic positioning system. Extensive analyses and testing were performed to optimize the hull design and ensure operational safety in various sea states.
This document provides specifications for two offshore construction vessels, the Posh Endurance and Posh Endeavour. Some key details include:
- They were built in 2014 in Singapore and are 88 meters long with a beam of 20 meters.
- Each vessel has a cargo deck area of around 760 square meters and can carry up to 3,200 tons of cargo at a 6 meter draft.
- Propulsion is provided by azimuth propellers powered by electric motors, with generators run on marine diesel oil. Dynamic positioning is aided by GPS and laser systems.
- Accommodations include rooms for 90 passengers, offices, recreation areas, and segregated quarters for a crew of 38.
This document provides an introduction and progress update for runway works being conducted at Air Force Station Bagdogra. Some key details include:
- The project started in January 2019 with a target completion date of January 2023 after extensions. Physical progress is currently at 80% as of October 2022.
- The scope of work involves construction and improvements to the main runway, parallel taxi track, links, dispersal areas, drains, and other infrastructure.
- Monthly targets are outlined to complete the remaining work by the January 2023 deadline, focusing on tasks like paving, drainage installation, and finishing works.
- Challenges mentioned are non-availability of aggregates, inadequate drainage work, and needing
The document provides procedures for applying a neoprene coating to riser pipes, clamps, and field joints for the Umm Al Dalakh Field Early Production Scheme project. It outlines materials requirements, including that the neoprene coating must withstand temperatures from -100°C to +92°C and have a minimum design life of 40 years. It also describes surface preparation, application of primer and coating, inspection and testing requirements, and addresses handling, storage, and potential repairs. Prequalification tests are specified to ensure the coating meets project specifications.
This document discusses Float Inc.'s Pneumatically Stabilized Platform (PSP) technology for use as a deep ocean offshore floating platform. The PSP technology was validated through testing by the Defense Advanced Research Projects Agency and Office of Naval Research in the 1990s and 1990s. The PSP uses air buoyancy within cylinders to stabilize the platform and reduce wave motion by 50-94%, even with 20 meter incident waves. The modular PSP design allows for extension and reconfiguration. Float Inc. proposes an Offshore Ocean Energy System placed on a PSP that would incorporate offshore wind, wave, and current energy generation as well as potential energy storage and other applications like aquaculture. Preliminary estimates for a site off
Similar to Osx project update agosto_final_inglês (20)
A OSX tem como objetivo construir e operar FPSOs no Brasil para atender a demanda da OGX. A empresa já construiu o FPSO OSX-1 e está construindo os FPSOs OSX-2 e OSX-3 na Ásia, com entrega prevista para 2013. A OSX planeja construir futuros FPSOs em seu estaleiro no Açu.
The document provides an overview of OSX's organizational structure, shipbuilding unit, and current order book. OSX has a controlling shareholder and strategic partnership with Hyundai for its shipbuilding operations. Its shipyard in Açu, Brazil will be the largest in the Americas once completed and has an order book including FPSOs, WHPs, and other vessels for clients like OGX and Sapura totaling billions in value.
1) A apresentação descreve a estrutura organizacional da OSX, uma empresa brasileira que fornece equipamentos e serviços para a indústria de petróleo e gás.
2) A OSX tem como pilares a demanda da OGX, suas condições de mercado atraentes no Brasil, o requerimento de conteúdo local e sua parceria estratégica com a Hyundai.
3) A empresa tem uma equipe experiente de mais de 1.080 funcionários com foco em construção naval, operações, engenharia e outros serviços para
Osx corporate presentation english_february [modo de compatibilidade]osxri
This document provides an overview of OSX's organizational structure and strategy. OSX is a Brazilian company that is 77.5% owned by EBX Group and 22.5% owned as free float. It aims to become an integrated offshore oil and gas equipment and services provider. OSX sees opportunities in Brazil's growing offshore oil and gas sector given local content requirements and underdeveloped local shipbuilding capacity. It has partnered with Hyundai to build South America's largest shipyard to produce offshore equipment and create over 3,000 technical jobs by 2013.
Osx apresentação corporativa português_fevereiro [modo de compatibilidade]osxri
O documento apresenta a estrutura organizacional da OSX, com ênfase na construção naval no Complexo Industrial do Açu, Rio de Janeiro. A OSX planeja iniciar as operações da Unidade de Construção Naval no Açu no primeiro trimestre de 2013, com a construção de um navio para a Sapura. A carteira de pedidos da OSX inclui 5 FPSOs encomendados pela OGX.
This document provides an overview of OSX's organizational structure and strategy. OSX is a holding company with subsidiaries in shipbuilding, leasing, and services. It has a strategic partnership with Hyundai, the largest shipbuilder, to build ships in Brazil. OSX aims to serve the growing offshore oil and gas industry in Brazil by meeting local content requirements and training Brazilian technicians. However, existing Brazilian shipyards lack capacity and technology to meet the expected demand, presenting an opportunity for OSX's new shipyard.
Este documento apresenta a estrutura organizacional e os principais pilares da OSX, uma empresa brasileira de construção naval e serviços para a indústria de petróleo e gás. A OSX tem parceria com a Hyundai para construir o maior estaleiro das Américas no Complexo Industrial do Açu, com capacidade para construir simultaneamente 11 FPSOs e 8 plataformas. A OSX também fornece serviços de engenharia, construção, integração e operação de unidades marítimas.
OSX provides an overview of its organizational structure and shipbuilding operations. It owns shipbuilding and leasing subsidiaries and has Hyundai as a strategic partner. Construction is underway on its shipyard in the Açu Superport industrial complex, which will be the largest in the Americas. The current order book includes FPSOs, WHPs, and other units for clients like OGX and Sapura with delivery dates through 2017.
Este documento apresenta a estrutura organizacional e os pilares da OSX, empresa brasileira de construção naval e serviços para a indústria de petróleo e gás. A OSX possui parceria estratégica com a Hyundai e planeja construir o maior estaleiro das Américas no Complexo Industrial do Açu. Atualmente, a carteira de pedidos da OSX inclui vários FPSOs e plataformas de produção para a OGX.
The document provides an overview of OSX, an integrated offshore equipment and services provider in Brazil. It details OSX's organizational structure, with Hyundai as its strategic partner. It outlines OSX's shipbuilding unit and order book, including FPSOs, WHPs, and other vessels being constructed for clients like OGX and Petrobras. The largest shipyard in the Americas is being built by OSX in the Açu Superport industrial complex in Brazil.
O documento apresenta a estrutura organizacional e os pilares da empresa OSX. A OSX possui uma carteira de pedidos significativa da OGX que inclui FPSOs e plataformas para produção e armazenamento de petróleo e gás. A OSX construiu um estaleiro no Complexo Industrial do Açu para atender a demanda crescente do setor de petróleo e gás no Brasil.
O documento apresenta a estrutura organizacional e os pilares da empresa OSX, incluindo sua parceria estratégica com a Hyundai para a construção do maior estaleiro das Américas no Distrito Industrial do Superporto do Açu. A OSX tem uma carteira de pedidos atual com 4 FPSOs para a OGX, sendo o primeiro construído na Coreia e os demais em estaleiros de Cingapura, com o quarto potencialmente construído no novo estaleiro da OSX no Brasil.
Here is a 3 sentence summary of the key points from the document:
[SUMMARY] The document outlines OSX's organizational structure and shipbuilding projects. It details the construction of its shipyard in Açu, Brazil, which will be the largest in the Americas, and provides an update on the construction and delivery timelines of various floating production, storage and offloading units (FPSOs) and wellhead platforms (WHPs) under contract for OGX and other clients. It also notes a contract with Petrobras to build 2 FPSO replicas.
The document provides information on OSX's organizational structure and shipbuilding operations. It outlines that OSX has a 76.64% controlling shareholder in EBX and plans to be the largest shipyard in the Americas through its partnership with Hyundai. It also details OSX's order book, which includes contracts to build FPSOs, WHPs, and other vessels for OGX and others, with delivery dates ranging from 2013 to 2017.
Este documento apresenta a estrutura organizacional e os pilares da empresa OSX, incluindo sua parceria estratégica com a Hyundai para a construção do maior estaleiro das Américas no Distrito Industrial do Superporto do Açu. A OSX tem uma equipe experiente e uma carteira de pedidos atual que inclui vários FPSOs para a OGX.
This document provides an overview of OSX's organizational structure and strategy. OSX is a Brazilian offshore oil and gas services company that is 76.64% owned by EBX Group and 23.36% owned by free float. It has strategic partnerships with Hyundai for shipbuilding and technical training. OSX aims to serve the growing offshore oil and gas market in Brazil through its integrated services and by meeting high local content requirements. However, existing Brazilian shipyards currently lack the capacity and technology to meet the country's offshore equipment demand.
Este documento apresenta a estrutura organizacional e os pilares da empresa OSX, incluindo sua parceria estratégica com a Hyundai para a construção do maior estaleiro das Américas no Distrito Industrial do Superporto do Açu. A OSX tem uma equipe experiente e uma carteira de pedidos atual que inclui vários FPSOs para a OGX.
1) O documento apresenta a estrutura organizacional e os pilares da empresa OSX, incluindo sua parceria com a Hyundai para a construção naval no estaleiro do Açu.
2) A OSX tem uma carteira de pedidos atual que inclui dois FPSOs (unidade flutuante de produção) para a OGX no valor de US$ 1,4 bilhão.
3) O estaleiro no Açu, o maior das Américas, tem capacidade para integrar simultaneamente 11 FPSOs e 8 plataformas e tem entregas par
OSX's order book includes 5 FPSOs and 4 WHPs for OGX with estimated total prices of over $5 billion and delivery between 2013-2017. OSX also has contracts for 2 FPSOs from Petrobras for over $900 million each with delivery in 2016-2017 and will construct the units at its shipyard in Brazil. Additionally, OSX has an order from Sapura for an unspecified PLSV to be delivered in 2014.
1) O documento apresenta a estrutura organizacional e os pilares da empresa OSX, incluindo sua parceria com a Hyundai para a construção naval no Brasil.
2) É descrito o estaleiro da OSX no Complexo Industrial do Açu, o maior das Américas, com capacidade para integrar até 11 FPSOs e 8 WHPs simultaneamente.
3) A carteira de pedidos atual da OSX inclui dois FPSOs para a OGX, o OSX-1 e o OSX-2.
63662490260Kalyan chart, satta matta matka 143, satta matka jodi fix , matka boss OTC 420, Indian Satta, India matka, matka ank, spbossmatka, online satta matka game play, live satta matka results, fix fix fix satta namber, free satta matka games, Kalyan matka jodi chart, Kalyan weekly final anl matka 420
Unlocking WhatsApp Marketing with HubSpot: Integrating Messaging into Your Ma...Niswey
50 million companies worldwide leverage WhatsApp as a key marketing channel. You may have considered adding it to your marketing mix, or probably already driving impressive conversions with WhatsApp.
But wait. What happens when you fully integrate your WhatsApp campaigns with HubSpot?
That's exactly what we explored in this session.
We take a look at everything that you need to know in order to deploy effective WhatsApp marketing strategies, and integrate it with your buyer journey in HubSpot. From technical requirements to innovative campaign strategies, to advanced campaign reporting - we discuss all that and more, to leverage WhatsApp for maximum impact. Check out more details about the event here https://events.hubspot.com/events/details/hubspot-new-delhi-presents-unlocking-whatsapp-marketing-with-hubspot-integrating-messaging-into-your-marketing-strategy/
SATTA MATKA DPBOSS KALYAN MATKA RESULTS KALYAN CHART KALYAN MATKA MATKA RESULT KALYAN MATKA TIPS SATTA MATKA MATKA COM MATKA PANA JODI TODAY BATTA SATKA MATKA PATTI JODI NUMBER MATKA RESULTS MATKA CHART MATKA JODI SATTA COM INDIA SATTA MATKA MATKA TIPS MATKA WAPKA ALL MATKA RESULT LIVE ONLINE MATKA RESULT KALYAN MATKA RESULT DPBOSS MATKA 143 MAIN MATKA KALYAN MATKA RESULTS KALYAN CHART
AI Transformation Playbook: Thinking AI-First for Your BusinessArijit Dutta
I dive into how businesses can stay competitive by integrating AI into their core processes. From identifying the right approach to building collaborative teams and recognizing common pitfalls, this guide has got you covered. AI transformation is a journey, and this playbook is here to help you navigate it successfully.
During the budget session of 2024-25, the finance minister, Nirmala Sitharaman, introduced the “solar Rooftop scheme,” also known as “PM Surya Ghar Muft Bijli Yojana.” It is a subsidy offered to those who wish to put up solar panels in their homes using domestic power systems. Additionally, adopting photovoltaic technology at home allows you to lower your monthly electricity expenses. Today in this blog we will talk all about what is the PM Surya Ghar Muft Bijli Yojana. How does it work? Who is eligible for this yojana and all the other things related to this scheme?
SATTA MATKA DPBOSS KALYAN MATKA RESULTS KALYAN CHART KALYAN MATKA MATKA RESULT KALYAN MATKA TIPS SATTA MATKA MATKA COM MATKA PANA JODI TODAY BATTA SATKA MATKA PATTI JODI NUMBER MATKA RESULTS MATKA CHART MATKA JODI SATTA COM INDIA SATTA MATKA MATKA TIPS MATKA WAPKA ALL MATKA RESULT LIVE ONLINE MATKA RESULT KALYAN MATKA RESULT DPBOSS MATKA 143 MAIN MATKA KALYAN MATKA RESULTS KALYAN CHART INDIA MATKA KALYAN SATTA MATKA 420 INDIAN MATKA SATTA KING MATKA FIX JODI FIX FIX FIX SATTA NAMBAR MATKA INDIA SATTA BATTA
Best Competitive Marble Pricing in Dubai - ☎ 9928909666Stone Art Hub
Stone Art Hub offers the best competitive Marble Pricing in Dubai, ensuring affordability without compromising quality. With a wide range of exquisite marble options to choose from, you can enhance your spaces with elegance and sophistication. For inquiries or orders, contact us at ☎ 9928909666. Experience luxury at unbeatable prices.
High-Quality IPTV Monthly Subscription for $15advik4387
Experience high-quality entertainment with our IPTV monthly subscription for just $15. Access a vast array of live TV channels, movies, and on-demand shows with crystal-clear streaming. Our reliable service ensures smooth, uninterrupted viewing at an unbeatable price. Perfect for those seeking premium content without breaking the bank. Start streaming today!
https://rb.gy/f409dk
SATTA MATKA DPBOSS KALYAN MATKA RESULTS KALYAN MATKA MATKA RESULT KALYAN MATKA TIPS SATTA MATKA MATKA COM MATKA PANA JODI TODAY BATTA SATKA MATKA PATTI JODI NUMBER MATKA RESULTS MATKA CHART MATKA JODI SATTA COM INDIA SATTA MATKA MATKA TIPS MATKA WAPKA ALL MATKA RESULT LIVE ONLINE MATKA RESULT KALYAN MATKA RESULT DPBOSS MATKA 143 MAIN MATKA KALYAN MATKA RESULTS KALYAN CHART KALYAN CHART
Efficient PHP Development Solutions for Dynamic Web ApplicationsHarwinder Singh
Unlock the full potential of your web projects with our expert PHP development solutions. From robust backend systems to dynamic front-end interfaces, we deliver scalable, secure, and high-performance applications tailored to your needs. Trust our skilled team to transform your ideas into reality with custom PHP programming, ensuring seamless functionality and a superior user experience.
2. Açu Shipyard – Licensing
• Term of Reference
• EIA filling
• Public Hearing
• Preliminary License
• Installation License
• Beginning of Construction (July)
1
3. Açu Shipyard – Industrial District
A new cluster for Heavy Industry
2
4. Açu Shipyard – Setup
Platform Platform construction
assembly area area
Modules
Drydock and construction area
effluent station
treatment
Green curtain
Water treatment station
FPSO Industrial unit Administrative
buildings
Quay
Administrative buildings with
Electric Substation 345 kV – 13.8 kV LEED Certification
(US Green Building Council)
3
5. Açu Shipyard – Advantages
1. Welding economies: 18m steel plate results in 56% less welding
• US$ 3.5 million savings and 28 days reduction in construction / FPSO
• US$ 1.9 million savings and 24 days reduction in construction / WHP
Regular Size Açu
COMPARATIVO DE FABRICAÇÃO DE BLOCOS PARA DOIS TIPOS DE CHAPAS: (18m X 4m X 19,5mm) & (9m X 2,44m X 19,5mm)
20M 20M
1 2 3 4 5 6 7 8 9 9M
18M 18M
1 2 3 4 5
9M
2.4M 2.4M 2.4M 2.4M 2.4M 2.4M 2.4M 2.4M 4M 4M 4M 4M 4M
WELDING LENGTH: (18M 8point) + 20m 20M = 182 M
Welding length: (18m x * 9POINT) + = 164m WELDING LENGTH: 18M4point) =72m 72M
Welding lenght: (18m x * 4POINT =
2. Energy Savings: 30% reduction and US$ 4 million in annual savings
4
6. Açu Shipyard – Advantages
3. Optimal Weather conditions: Less than 30% of rainy days per year
4. Better soil: Sandy soil requires lighter foundations
5. Integration Slots: Up to 3,525m of quay allowing
simultaneous integration of 9 FPSOs and the construction of
8 WHPs. (6 FPSOs and 2,400m at 1st phase)
6. Proximity to Campos Basin: ( ≈ 150Km)
FPSO / WHP travels to Campos Basin in half a day
Savings of US$ 4,0 million as compared to a site in Singapore
5
7. Açu Shipyard – Capex
Preliminary Budget – US$ (MM) Total LLX OSX
Common Infrastructure 448 219 229
Investigation and Engineering 31 15 16
Civil Works 416 204 212
Offshore Dredging (854k m3) 111 55 56
Onshore Dredging (13,000k m3) 41 20 21
Break Water (2,300k m3) 264 129 135
Pre eng. costs + environmental 74 - 74
Civil works 447 - 447
Onshore Dredging (10,500k m3) 90 - 90
Quay (2,270 m) 262 - 262
Back area embankment (6,000k m3) 21 - 21
Site camp facility and management 74 - 74
Shipyard structure 544 - 544
Buildings 265 - 265
Dry Dock 133 - 133
Roads and Paving 146 - 146
Equipment and others 420 - 420
Total 1,933 219 1,714
Merchant Marine Fund ≈ 80%
6
12. FPSO OSX-1 – Project Progress
• FPSO
– MECHANICAL COMPLETION AND COMISSIONING: 30TH OF JULY
• TURRET
– INSTAND-BY AT INDONESIA.
• COMPONENTS OF THE MOORING SYSTEM
– STORED IN BRAZIL.
11
14. FPSO OSX-1 – Hire of Personnel On-Track
Percentage of Workers Hired
100%
90%
80%
70%
60%
50%
40%
30%
20%
10%
0%
% Planned % Actual
No. of employees MAR/11 APR/11 MAY/11 JUN/11
PLANNED 58 79 79 86
ACTUAL 61 73 74 77
13
15. FPSO OSX-1 – Personnel Experience
Age Experience Time
4%
14% 20 to 30 years 19%
Less than 20 years
30 to 40 years
28%
49% 20 to 30 years
40 to 50 years
26%
Greater than or equal to
50 to 60 years 30 years
32%
Greater than or equal to
60 years
28%
14
18. OSX-2 / WHP-1 System
OSX 2 WHP 1
Expected Timeline Status Expected Timeline Status
GTD GTD
RFP RFP
Delivery at shipyard* 2Q13 Delivery at shipyard* 1Q13
* ex-installation * ex-installation
Construction Contract Construction Contract
• EPCIC (Engineering, Procurement, • EPCIC (Engineering, Procurement,
Construction, Installation and Construction, Installation and
Commissioning) contract executed with Commissioning) contract executed with
SBM Offshore Techint
Long term debt commitment Drilling Package
• Proposals with 100% underwriting • Ongoing tender
• Mandated and with negotiated term sheet • Initial proposals received on
• Debt/Equity Structure – 80/20 December 8th, 2010 from AKER,
NOV, TTS and SEAWELL 17
21. OSX-3 / WHP-2 System
OSX 3 WHP 2
Expected Timeline Status Expected Timeline Status
GTD GTD
RFP RFP
Delivery at shipyard* 3Q13 Delivery at shipyard* 2Q13
* ex-installation * ex-installation
Construction Contract Contrato de Construção
• EPCIC (Engineering, Procurement, • EPCIC (Engineering, Procurement,
Construction, Installation and Construction, Installation and
Commissioning) contract executed with Commissioning) contract executed with
Modec Techint
Drilling Package
• Ongoing tender
• Initial proposals received on
December 8th, 2010 from AKER,
NOV, TTS and SEAWELL 20
23. FPSOs OSX-4 and OSX-5
Gemini Star Suhail Star
• Two sister VLCC´s (Very Large Crude Oil Carriers) purchased in
November 2010
• Purchase price: US$ 27 MM each
• VLCC Gemini Star received on January 13th, 2011 and VLCC
Suhail Star received on February 22nd, 2011
• Purchased from Vela International Marine Limited (subsidiary of
Saudi Aramco)
• Engineering for conversion and integration under bidding
process
• Delivery ex-installation scheduled for 2Q14 and 4Q14,
respectively 22