Project Update
  August 2011
Açu Shipyard – Licensing

                      • Term of Reference


                      • EIA filling


                      • Public Hearing


                      • Preliminary License


                      • Installation License


                      • Beginning of Construction (July)




                                                           1
Açu Shipyard – Industrial District




                 A new cluster for Heavy Industry
                                                    2
Açu Shipyard – Setup
                             Platform     Platform construction
                          assembly area           area

                                                                   Modules
        Drydock and                                            construction area
       effluent station
          treatment
                                                              Green curtain



                                                                              Water treatment station

                 FPSO                       Industrial unit                      Administrative
                                                                                   buildings




                    Quay



                                                  Administrative buildings with
  Electric Substation 345 kV – 13.8 kV                LEED Certification
                                                  (US Green Building Council)



                                                                                                        3
Açu Shipyard – Advantages
1. Welding economies: 18m steel plate results in 56% less welding

• US$ 3.5 million savings and 28 days reduction in construction / FPSO
• US$ 1.9 million savings and 24 days reduction in construction / WHP

                      Regular Size                                                     Açu
     COMPARATIVO DE FABRICAÇÃO DE BLOCOS PARA DOIS TIPOS DE CHAPAS: (18m X 4m X 19,5mm) & (9m X 2,44m X 19,5mm)

                                20M                                                     20M




           1      2    3    4      5    6    7    8      9   9M



     18M                                                          18M
                                                                           1       2      3       4      5




                                                             9M




           2.4M   2.4M 2.4M 2.4M   2.4M 2.4M 2.4M 2.4M                     4M     4M      4M     4M      4M


       WELDING LENGTH: (18M 8point) + 20m 20M = 182 M
          Welding length: (18m x * 9POINT) + = 164m                     WELDING LENGTH: 18M4point) =72m 72M
                                                                          Welding lenght: (18m x * 4POINT =




2. Energy Savings: 30% reduction and US$ 4 million in annual savings

                                                                                                                  4
Açu Shipyard – Advantages
3. Optimal Weather conditions: Less than 30% of rainy days per year


4. Better soil: Sandy soil requires lighter foundations


5. Integration Slots: Up to 3,525m of quay allowing
simultaneous integration of 9 FPSOs and the construction of
8 WHPs. (6 FPSOs and 2,400m at 1st phase)




6. Proximity to Campos Basin: ( ≈ 150Km)

FPSO / WHP travels to Campos Basin in half a day

Savings of US$ 4,0 million as compared to a site in Singapore




                                                                      5
Açu Shipyard – Capex
      Preliminary Budget – US$ (MM)          Total      LLX   OSX

      Common Infrastructure                   448       219    229
       Investigation and Engineering           31        15     16
       Civil Works                            416       204    212
         Offshore Dredging (854k m3)          111        55     56
         Onshore Dredging (13,000k m3)         41        20     21
         Break Water (2,300k m3)              264       129    135

      Pre eng. costs + environmental           74         -     74

      Civil works                             447         -    447
       Onshore Dredging (10,500k m3)           90         -     90
       Quay (2,270 m)                         262         -    262
       Back area embankment (6,000k m3)        21         -     21
       Site camp facility and management       74         -     74

      Shipyard structure                      544         -    544
       Buildings                              265         -    265
       Dry Dock                               133         -    133
       Roads and Paving                       146         -    146

      Equipment and others                    420         -    420

      Total                                  1,933      219   1,714

                           Merchant Marine Fund ≈ 80%
                                                                      6
Current Order Book – OGX
                                                   ESTIMATED CAPEX
      EQUIPMENT                     CAPACITY                         DELIVERY*
                                                       (US$ MM)

      FPSO OSX-1                     80K bopd            610          3Q 2011

      FPSO OSX-2                    100K bopd            775          2Q 2013

      FPSO OSX-3                    100K bopd            800          3Q 2013

      FPSO OSX-4                    100K bopd          850-900        2Q 2014

      FPSO OSX-5                    100K bopd          850-900        4Q 2014

           WHP-1                       30 wells        400-450        1Q 2013

           WHP-2                       30 wells        400-450        2Q 2013

                                         Total       4,685 - 4,885
    * delivery at the shipyard (ex installation)


                                                                                 7
FPSO OSX-1



             8
FPSO OSX-1 – Customization

   MODIFICATION WORK

                                    M380 New
   NEW INSTALLATION
                                                                                         M230 New
                                               M350 New
                                                             M320 Mod.
                                                                                              M200 New
                                                                             M260 Mod.

                                                                      M290 Mod.
                                                                                                         N160 Mod.

                                                                                                              N130 Mod.
   Hull / Engine Room Mod.                                                                                                F110 Mod.


   Central Pipe Rack Mod.

                M430 Mod.

                             M400 Mod.
                                          M310 New

                                                          M280 Mod.


                                                                      M250 New    M220 Mod.

                                                                                                    W140 Mod.




                                                                                                                                  9
FPSO OSX-1 – Project Progress




                                10
FPSO OSX-1 – Project Progress




 •   FPSO
      –   MECHANICAL COMPLETION        AND COMISSIONING:   30TH OF JULY
 •   TURRET
      –   INSTAND-BY   AT INDONESIA.

 •   COMPONENTS OF THE MOORING SYSTEM
      –   STORED IN BRAZIL.



                                                                          11
FPSO OSX-1 – Project Progress

                          Delivery Progress & Timeline
                                       FPSO OSX 1
    100%
    95%
    90%
               Purchase
    85%
    80%                                                                        First Oil
    75%
                                                        Delivery in
    70%
                                                        Singapore
    65%
    60%




                             Planned                  Actual




                           MAR/11         APR/11    MAY/11            JUN/11

     PLANNED              84.81%         86.90%     90.38%            95.85%

     ACTUAL               84.47%         86.96%     89.90%            92.43%
                                                                                           12
FPSO OSX-1 – Hire of Personnel On-Track

                             Percentage of Workers Hired
   100%
    90%
    80%
    70%
    60%
    50%
    40%
    30%
    20%
    10%
     0%




                              % Planned              % Actual


          No. of employees       MAR/11    APR/11    MAY/11     JUN/11

           PLANNED                58        79        79         86

            ACTUAL                61        73        74         77

                                                                         13
FPSO OSX-1 – Personnel Experience



                     Age                                           Experience Time

          4%
               14%          20 to 30 years                   19%

                                                                                 Less than 20 years
                            30 to 40 years
  28%
                                                                         49%     20 to 30 years
                            40 to 50 years
                      26%
                                                                                 Greater than or equal to
                            50 to 60 years                                       30 years
                                                       32%
                            Greater than or equal to
                            60 years
        28%




                                                                                                            14
OSX-2 / WHP-1 System



                       15
OSX-2 / WHP-1 System


          WHP 1        OSX 2




                               16
OSX-2 / WHP-1 System
                     OSX 2                                      WHP 1
 Expected Timeline           Status          Expected Timeline          Status

 GTD                                        GTD

 RFP                                        RFP

 Delivery at shipyard*       2Q13           Delivery at shipyard*       1Q13
 * ex-installation                          * ex-installation


 Construction Contract                      Construction Contract
 • EPCIC (Engineering, Procurement,         • EPCIC (Engineering, Procurement,
   Construction, Installation and             Construction, Installation and
   Commissioning) contract executed with      Commissioning) contract executed with
   SBM Offshore                               Techint
Long term debt commitment                   Drilling Package
• Proposals with 100% underwriting          • Ongoing tender
• Mandated and with negotiated term sheet   • Initial proposals received on
• Debt/Equity Structure – 80/20               December 8th, 2010 from AKER,
                                              NOV, TTS and SEAWELL                    17
OSX-3 / WHP-2 System



                       18
OSX-3 / WHP-2 System


          WHP 2        OSX 3




                               19
OSX-3 / WHP-2 System
                     OSX 3                                     WHP 2
 Expected Timeline           Status         Expected Timeline          Status

 GTD                                       GTD

 RFP                                       RFP

 Delivery at shipyard*       3Q13          Delivery at shipyard*       2Q13
 * ex-installation                         * ex-installation


 Construction Contract                     Contrato de Construção
 • EPCIC (Engineering, Procurement,        • EPCIC (Engineering, Procurement,
   Construction, Installation and            Construction, Installation and
   Commissioning) contract executed with     Commissioning) contract executed with
   Modec                                     Techint
                                           Drilling Package
                                           • Ongoing tender
                                           • Initial proposals received on
                                             December 8th, 2010 from AKER,
                                             NOV, TTS and SEAWELL                    20
FPSOs OSX-4
 and OSX-5


              21
FPSOs OSX-4 and OSX-5
                        Gemini Star                                 Suhail Star




• Two sister VLCC´s (Very Large Crude Oil Carriers) purchased in
November 2010
• Purchase price: US$ 27 MM each
• VLCC Gemini Star received on January 13th, 2011 and VLCC
Suhail Star received on February 22nd, 2011
• Purchased from Vela International Marine Limited (subsidiary of
Saudi Aramco)
• Engineering for conversion and integration under bidding
process
• Delivery ex-installation   scheduled   for   2Q14   and   4Q14,
respectively                                                                      22

Osx project update agosto_final_inglês

  • 1.
    Project Update August 2011
  • 2.
    Açu Shipyard –Licensing • Term of Reference • EIA filling • Public Hearing • Preliminary License • Installation License • Beginning of Construction (July) 1
  • 3.
    Açu Shipyard –Industrial District A new cluster for Heavy Industry 2
  • 4.
    Açu Shipyard –Setup Platform Platform construction assembly area area Modules Drydock and construction area effluent station treatment Green curtain Water treatment station FPSO Industrial unit Administrative buildings Quay Administrative buildings with Electric Substation 345 kV – 13.8 kV LEED Certification (US Green Building Council) 3
  • 5.
    Açu Shipyard –Advantages 1. Welding economies: 18m steel plate results in 56% less welding • US$ 3.5 million savings and 28 days reduction in construction / FPSO • US$ 1.9 million savings and 24 days reduction in construction / WHP Regular Size Açu COMPARATIVO DE FABRICAÇÃO DE BLOCOS PARA DOIS TIPOS DE CHAPAS: (18m X 4m X 19,5mm) & (9m X 2,44m X 19,5mm) 20M 20M 1 2 3 4 5 6 7 8 9 9M 18M 18M 1 2 3 4 5 9M 2.4M 2.4M 2.4M 2.4M 2.4M 2.4M 2.4M 2.4M 4M 4M 4M 4M 4M WELDING LENGTH: (18M 8point) + 20m 20M = 182 M Welding length: (18m x * 9POINT) + = 164m WELDING LENGTH: 18M4point) =72m 72M Welding lenght: (18m x * 4POINT = 2. Energy Savings: 30% reduction and US$ 4 million in annual savings 4
  • 6.
    Açu Shipyard –Advantages 3. Optimal Weather conditions: Less than 30% of rainy days per year 4. Better soil: Sandy soil requires lighter foundations 5. Integration Slots: Up to 3,525m of quay allowing simultaneous integration of 9 FPSOs and the construction of 8 WHPs. (6 FPSOs and 2,400m at 1st phase) 6. Proximity to Campos Basin: ( ≈ 150Km) FPSO / WHP travels to Campos Basin in half a day Savings of US$ 4,0 million as compared to a site in Singapore 5
  • 7.
    Açu Shipyard –Capex Preliminary Budget – US$ (MM) Total LLX OSX Common Infrastructure 448 219 229 Investigation and Engineering 31 15 16 Civil Works 416 204 212 Offshore Dredging (854k m3) 111 55 56 Onshore Dredging (13,000k m3) 41 20 21 Break Water (2,300k m3) 264 129 135 Pre eng. costs + environmental 74 - 74 Civil works 447 - 447 Onshore Dredging (10,500k m3) 90 - 90 Quay (2,270 m) 262 - 262 Back area embankment (6,000k m3) 21 - 21 Site camp facility and management 74 - 74 Shipyard structure 544 - 544 Buildings 265 - 265 Dry Dock 133 - 133 Roads and Paving 146 - 146 Equipment and others 420 - 420 Total 1,933 219 1,714 Merchant Marine Fund ≈ 80% 6
  • 8.
    Current Order Book– OGX ESTIMATED CAPEX EQUIPMENT CAPACITY DELIVERY* (US$ MM) FPSO OSX-1 80K bopd 610 3Q 2011 FPSO OSX-2 100K bopd 775 2Q 2013 FPSO OSX-3 100K bopd 800 3Q 2013 FPSO OSX-4 100K bopd 850-900 2Q 2014 FPSO OSX-5 100K bopd 850-900 4Q 2014 WHP-1 30 wells 400-450 1Q 2013 WHP-2 30 wells 400-450 2Q 2013 Total 4,685 - 4,885 * delivery at the shipyard (ex installation) 7
  • 9.
  • 10.
    FPSO OSX-1 –Customization MODIFICATION WORK M380 New NEW INSTALLATION M230 New M350 New M320 Mod. M200 New M260 Mod. M290 Mod. N160 Mod. N130 Mod. Hull / Engine Room Mod. F110 Mod. Central Pipe Rack Mod. M430 Mod. M400 Mod. M310 New M280 Mod. M250 New M220 Mod. W140 Mod. 9
  • 11.
    FPSO OSX-1 –Project Progress 10
  • 12.
    FPSO OSX-1 –Project Progress • FPSO – MECHANICAL COMPLETION AND COMISSIONING: 30TH OF JULY • TURRET – INSTAND-BY AT INDONESIA. • COMPONENTS OF THE MOORING SYSTEM – STORED IN BRAZIL. 11
  • 13.
    FPSO OSX-1 –Project Progress Delivery Progress & Timeline FPSO OSX 1 100% 95% 90% Purchase 85% 80% First Oil 75% Delivery in 70% Singapore 65% 60% Planned Actual MAR/11 APR/11 MAY/11 JUN/11 PLANNED 84.81% 86.90% 90.38% 95.85% ACTUAL 84.47% 86.96% 89.90% 92.43% 12
  • 14.
    FPSO OSX-1 –Hire of Personnel On-Track Percentage of Workers Hired 100% 90% 80% 70% 60% 50% 40% 30% 20% 10% 0% % Planned % Actual No. of employees MAR/11 APR/11 MAY/11 JUN/11 PLANNED 58 79 79 86 ACTUAL 61 73 74 77 13
  • 15.
    FPSO OSX-1 –Personnel Experience Age Experience Time 4% 14% 20 to 30 years 19% Less than 20 years 30 to 40 years 28% 49% 20 to 30 years 40 to 50 years 26% Greater than or equal to 50 to 60 years 30 years 32% Greater than or equal to 60 years 28% 14
  • 16.
    OSX-2 / WHP-1System 15
  • 17.
    OSX-2 / WHP-1System WHP 1 OSX 2 16
  • 18.
    OSX-2 / WHP-1System OSX 2 WHP 1 Expected Timeline Status Expected Timeline Status GTD GTD RFP RFP Delivery at shipyard* 2Q13 Delivery at shipyard* 1Q13 * ex-installation * ex-installation Construction Contract Construction Contract • EPCIC (Engineering, Procurement, • EPCIC (Engineering, Procurement, Construction, Installation and Construction, Installation and Commissioning) contract executed with Commissioning) contract executed with SBM Offshore Techint Long term debt commitment Drilling Package • Proposals with 100% underwriting • Ongoing tender • Mandated and with negotiated term sheet • Initial proposals received on • Debt/Equity Structure – 80/20 December 8th, 2010 from AKER, NOV, TTS and SEAWELL 17
  • 19.
    OSX-3 / WHP-2System 18
  • 20.
    OSX-3 / WHP-2System WHP 2 OSX 3 19
  • 21.
    OSX-3 / WHP-2System OSX 3 WHP 2 Expected Timeline Status Expected Timeline Status GTD GTD RFP RFP Delivery at shipyard* 3Q13 Delivery at shipyard* 2Q13 * ex-installation * ex-installation Construction Contract Contrato de Construção • EPCIC (Engineering, Procurement, • EPCIC (Engineering, Procurement, Construction, Installation and Construction, Installation and Commissioning) contract executed with Commissioning) contract executed with Modec Techint Drilling Package • Ongoing tender • Initial proposals received on December 8th, 2010 from AKER, NOV, TTS and SEAWELL 20
  • 22.
  • 23.
    FPSOs OSX-4 andOSX-5 Gemini Star Suhail Star • Two sister VLCC´s (Very Large Crude Oil Carriers) purchased in November 2010 • Purchase price: US$ 27 MM each • VLCC Gemini Star received on January 13th, 2011 and VLCC Suhail Star received on February 22nd, 2011 • Purchased from Vela International Marine Limited (subsidiary of Saudi Aramco) • Engineering for conversion and integration under bidding process • Delivery ex-installation scheduled for 2Q14 and 4Q14, respectively 22