SlideShare a Scribd company logo
of the PrīmXComposite
system that make it the best
application in 80% of all
concrete structures
Five
Values
✓ 50% Stronger Material
✓ 30% Faster Construction
✓ 40% CO2 Emission Saving
✓ Water-tight
✓ Jointless
Concrete Rafts,
Walls, Floors…
• No time-consuming, expensive and dangerous tying of reinforcement
mesh and bars for workers
• Time savings on the installation of waterproofing membranes
The well-established PrīmXComposite system uses a high dosage rate (1.2
kilometres of steel per cubic metre of very strong - 3 times stronger than traditional
rebars - steel fibres, blended into concrete using the PrīmX Fibre blower. It ensures
the precisely dosed and homogeneous integration of fibres.
Below you will find a speed comparison of the PrīmXComposite and traditional (steel
bar reinforced) concrete system installing raft (mat) foundation. The comparison is
made based on data from a successful raft foundation installation at one of our
completed projects in Norway. The current project was built with the
PrīmXComposite method and the data comes from the real life application.
3 major steps in the raft foundation construction process:
1. Waterproofing membrane installation;
2. Steel bar/mesh installation; and
3. Concrete casting.
•Raft/mat foundation
•Building site is located only
ten metres from a channel
•High groundwater level
Case Study
5 story building
Norway, Storgata 5,
Fredrikstad
30% Faster
Construction
Steps
Traditional Method
(steel bar reinforced)
PrīmXComposite
Waterproofing membrane
installation
7 days
4 workers
28 man-days
1 day
4 workers
4 man-days
Steel bar/mesh installation
15 days
10 workers
150 man-days
5 days
5 workers
25 man-days
Concrete casting
1 day
5 workers
5 man-days
1 day
8 workers
8 man-days
Total:
23 days
183 man days
7 days
37 man days
System Comparison
Additionally, for a traditional system:
• For the traditional method, expensive waterproofing membranes are
needed. In the case of PrīmXComposite, membranes are not placed
as PrīmXComposite concrete is waterproof.
• Membrane installation is dependent on weather conditions and there
is risk of damage during steel bar/mesh installation. In most cases, it
is very difficult to fix if damage occurs.
• Using the traditional method, there are crane rental costs for
unloading steel bars and dangerous conditions for for workers
(unloading, work with steel bar cutters etc.).
• Steel bar delivery and storage requires additional space.
Savings using the
PrīmXComposite system
in the current project:
16 168
Days
saved that can be
used for further
build-up
Man-days
saved due to absence of
steel bar installation and
waterproofing works
3
1 3 5 7 9 11 13 15 17 19 21 23
Duration in Days
1 3 5 7 9 11 13 15 17 19 21 23
Traditional Concrete
7 Days
Waterproofing,
measurements, and mould
placement
15 Days
Steel Bar & Mesh Installation
1 Day
Concrete
Casting
1 Day
Measurements and mould placement
5 Days
Starters & Rebar near pile heads
Implementation Time Comparison:
Traditional Concrete to PrīmXComposite
1 Day
Concrete Casting
Time Savings: 16 Days
Labor Savings: 146 Days
Much
faster
Perfect in
limited building
space
Safe for
workers
Watertight
5
In the concrete industry, all professionals
are familiar with the traditional (steel
bar/steel mesh) reinforced concrete
solutions. Integrated in traditional
concrete, steel bars/meshes solve various
structural tasks. However, this system has
challenges:
- installation is time consuming and
therefore a costly process;
- used in watertight solutions, the
traditional system is very expensive and
inefficient from the perspective of
materials used (steel and concrete);
- material is not homogenous; there are
often challenges regarding flexural and
impact resistance;
- amount of steel needed in a traditional
reinforcement solution is often high, so this
type of reinforcement is costly;
- a dedicated zone is required onsite for
unloading;
- installation work (rebar cutters, work
with angle grinder, stumbling possibilities
on mesh etc.) is often dangerous for
workers.
Steel fiber reinforced ultra
performance system
In a steel fibre system, reinforcement is
formed from a high concentration of steel
fibres homogenously distributed into a
concrete matrix.
By adding steel fibres into concrete, the
flexural strength of the composite can be
increased significantly - even 100% or
more - depending on the concrete’s
strength, dosage, amount and strength of
fibres. Steel fibre reinforcement
transforms concrete from a brittle
material with very low flexural strength
into a ductile, spatially reinforced
structure with much higher flexural
strength, better control of cracking,
higher resistance to spalling, improved
fatigue strength and much higher wear
resistance.
NB! 80 kg/m3 12mm steel bars OR
35 kg/m3 steel fibers. Interface
surface: 4m2 vs 23.5 m2
140 meters of
reinforcement bars / 1m3
550 N/mm2 steel
reinforcement bars
10 000 meters of steel
fiber reinforcement /
1m3
1 200 to 1 800 N/mm2
steel fibers
50% Stronger
Material
6
PrīmXComposite system uses steel fibre reinforcement and special anti-
shrinkage additives to ensure non-shrinking, ductile concrete that can be used in
many structures.
Due to special anti-shrinkage additives in the drying process, a chemical pre-
stress is formed that puts fibres in permanent tension. Therefore, fibres act
against the crack formation process and cracking is absolutely minimised.
Cracks are taken into consideration as weakening points for the structure when
making structural calculations. In the case of PrīmXComposite there is no
weakening due to crack formation, or the risk is highly reduced.
In the PrīmXComposite system, we use high-quality steel fibres only. We have
investigated the performance of fibres of different shapes and lengths with our
system, conducting many tests in our own and partner laboratories. In our own
laboratory, we perform more than 300 tests yearly for concrete and fibres.
One of the key benefits when comparing steel bar and steel fibre reinforced
structures is homogenous material properties obtained with steel fibre
technology. To ensure perfect reinforcement distribution, we use special steel
fibre dosing equipment, the PrīmX Fibre blower. View the video to see how we
ensure homogenous fibre distribution:
WATCH HERE
7
Strength
Development
Shrinkage
Stress
crack
shrinkage stress
PrīmXComposite
Concrete
Model on the left schematically shows the
relation between concrete material strength
development and tensile stress development, which
is induced by the restrained drying shrinkage.
Traditional concrete shrinks right after it has been
poured and at a certain point the shrinkage stress
induced exceeds the resistance of the concrete,
which causes the material to crack.
PrīmXComposite concrete works towards reducing
the negative effects of shrinkage stress. The
special, patented formula of additives causes
material expansion and delays the onset of
shrinkage and significantly reduces the amount of
shrinkage of the concrete, therefore drying
shrinkage is practically eliminated.
A high quality end result is obtained through a
careful process of mix design preparation,
controlled addition of PrīmXComposite
shrinkage reducing additives, concrete batch plant
control and onsite concrete control in the form of
fresh concrete testing to ensure mix design
parameters are met.
Model on the right shows loads applied vs. deflection.
You can see, and it is shown in many scientific papers,
that the SFR (Steel Fibre Reinforced) concrete enjoys a
phenomenon called material hardening. This is the SFR
concrete being able to continue to resist loads far
higher than that which cracked the specimen.
Traditional concrete cracks at a lower load and simply
fails with no residual load bearing capacity.
Saying this, it is important to ensure that you use a
quality steel fibre. A force Ʈ (image below) is applied to
pull out the fibre, and this is resisted by the
development of the bond / friction within the concrete -
to the extent of the surface area and length of
embedment.
1st crack
kN
Deflection
Trad. Concrete
SFR Concrete
Material Hardening
Material Hardening Phenomenon
Our design approach is based on full-scale structural testing of round
indeterminate plate tests. These tests result in high plastic tensile strength with
controlled integration of the PrīmXComposite system’s anti shrinkage additives.
Mix design preparation considers the quality of the base materials, the trial mix
testing (slump, density, compressive strength cubes 3, 7 and 28 days) and the
eventual quality control over the execution and casting on site, where fresh
concrete testing is of the utmost importance and is in accordance with ASTM
and CEN guidelines.
8
Tensile force
T
d
1.
L
𝜏
L/2
2.
3.
Matrix
3 Possible Types of Failure
Thousands of tests have been carried out with fibres of different strength class and
shape, to have reliable results upon which to build optimal designs.
Along with tests made with different types of fibres (various tensile strengths, diameters, shape
length) to determine optimal solutions, Primekss has carried out tests to determine the pull-out
force differences between standard SFRC (steel fibre reinforced) and own HPSFRC (High
Performance Steel Fibre Reinforced Concrete) technology – PrīmXComposite. The tests
performed indicate that there is on average a 12% increase in pull-out force using
PrīmXComposite concrete. Due to special anti-shrinkage chemical additives being added
during curing of the material, expansion occurs. The expansion is restrained by the
fibres and surrounding concrete, thus there is increased compressive force working on
each fibre, leading to higher pull-out force.
Main benefits due to the increased strength of concrete with the PrīmXComposite system:
• possibility to optimise design and reduce slab thickness resulting in material and cost
economies
• high impact resistance due to spatially integrated reinforcement and absolutely minimised
cracking
• greater fatigue endurance
• reduced maintenance costs as steel fibre reinforced concrete becomes more impact resistant
• longer useful working life.
1. Tension. Embedment in concrete is very strong but the fibre ruptures.
2. Interface bond. The bond between fibre and concrete is not sufficient and the fibre is
pulled out from the concrete.
3. Concrete. Fibre is strong, the bond is strong and when the fibre is pulled out, the
concrete along the fibre is pulled out in a cone.
9
With improved environmental awareness, there is an ever-growing interest in
reducing carbon emissions related to concrete. The Cement industry is
responsible for 6% of the world’s overall CO2 emissions, and this is twice the
amount of CO2 emissions generated by all of the world’s airplanes combined.
Due to the inclusion of steel fibre reinforcement and special anti-shrinkage
additives, the PrīmXComposite system ensures a possibility to cast a strong,
stiff, and jointless concrete slab with significantly reduced slab thickness
compared to traditionally reinforced floors, still exceeding the defined load
bearing capacity. The slab thickness reduction and use of steel fibre
reinforcement in the PrīmXComposite system reduces the consumption of
our limited resources and reduces CO2 emissions during construction. On
average, the PrīmXCoposite system saves 40% of CO2 emissions
compared to traditional steel bar reinforced concrete construction.
40% CO2
Emission
Saving
ECO-friendly construction
10
Design solution
Concrete Steel
CO₂ emission (kg
CO₂/m² of floor) from
m3 kg/m2 Concrete Steel Net
Traditional design (50,000 m2, 150 mm) 7,500 11.7 36.7 11.7 48.4
PrīmXComposite design – Total (50,000 m²) 6,300* 5.0 30.8 5.0 35.9
PrīmXComposite design (40,000 m2, 130 mm) 5,200 5.2 31.8 5.2 37.0
PrīmXComposite design (10,000 m2, 110 mm) 1,100 4.4 26.9 4.4 31.3
* Reduced volume of concrete results in an
estimated 120 fewer trucks on the job site,
assuming a 10 m³ volume drum
Material savings due to PrīmXComposite application:
CO2 calculation based on methodology covered in detail in the scientific paper: “REDUCING
CO2 EMISSIONS OF CONCRETE SLAB CONSTRUCTIONS WITH THE PRIME COMPOSITE
SLAB SYSTEM”, Brad J. PEASE, PhD Concrete and Structural Engineer, PrimekssLabs;
Xavier DESTRÉE, Structural Engineer, La Hulpe, Belgium.
CO2 savings calculation:
CO2 savings on concrete: 5.9 kg CO₂ per m² of floor
CO2 savings on steel: 6.7 kg CO₂ per m² of floor
Total CO2 saved on this project: 626,280 kg
Scientific paper covering
methodology and
calculations
DOWNLOAD HERE
Traditional Concrete
reinforced with steel mesh
150mm
all 50,000 m2
PrimXComposite Design
130mm
40,000 m2 110mm
10,000 m2
Cross Dock Area
Example: warehouse with 50,000m2 total area
Selected PrimXComposite over Traditional Concrete
FloorThickness
Warehouse Floor
11
Reduced more than 18 285 525 kg of CO2
emissions in 2017 by customers choosing
PrīmXComposite, the Primekss 20th
Anniversary campaign.
Reducing CO2 emissions lets your Company go GREEN and gain LEED
certification. Projects pursuing LEED certification earn points across several
categories. Based on the number of points achieved, a project then earns one of
four LEED rating levels: Certified, Silver, Gold or Platinum.
Presented with CO2 saver certificate
Ensuring environmentally-friendly construction is one of Primekss’ priorities. To
celebrate Primekss’ 20th anniversary in 2017, a very important charity campaign
was introduced. The campaign intended to give a donation in the amount equal
to the saved CO2 emissions that were achieved by utilising our PrīmXComposite
technology during 2017.
Primekss’ goal for the year 2017 was to install 1,000,000 m2 of PrīmXComposite
structures. During 2017, 812,690 m2 of PrīmXComposite floors and other
concrete structures was installed. It resulted in saving 18,285,525 kg of CO2.
In comparison, a passenger vehicle emits 94 gr/km on average. The distance
around the globe is about 40,000 km. So it is possible to go around the world
5,984 times by car, emitting the same amount of CO2 that we will save with
our unique technology.
allows saving tons of
Carbon Dioxide
12
Edges of cracks deteriorate and, in many cases, debris separated from the
concrete becomes a grinding agent and further supports the floor abrasion
process. The floor is no longer resistant to liquid penetration and is more prone to
further damage: concrete deterioration, possible steel reinforcement corrosion,
joint chipping etc.
Curling is caused by the different drying speed of various material layers. It is a
huge problem for material handling units driving in logistics premises. Curled
edges near the joints/saw cuts slow down the speed, damage the equipment and
are harmful for operators’ health due to vibrations caused by crossing the
damaged and uplifted joints.
To solve problems caused by shrinkage, traditional concrete floor systems use
saw-cut shrinkage control joints every 6 metres and a slip sheet underneath the
slab, but they do not eliminate the problems.
Some more advanced systems without steel
reinforcement have solutions where joints are
extended to 30-50 metres.
However, this is not a solution but an ongoing fight with a problem
that still remains. Even in these systems, dominant joints develop
with a large joint opening and curling still occurs, adding to the cost
of maintenance and repair. It should also be remembered that
curled joint repairs are not long lasting. The process of curling
never stops and repairs will be needed again.
The PrimXComposite system addresses the cause of the problem
instead of fighting the symptoms. In the case of this system, the
shrinkage process is controlled with special anti-shrinkage
additives. The additives in PrīmXComposite bind H2O molecules
and form a micro-scale composite structure, including crystals, that
expand and compress the internal concrete matrix. In this way
cracking is absolutely minimised and curling does not occur.
Jointless
Traditional concrete shrinks during the curing process. As a result, it forms cracks
and curls at the slab edges. Both phenomena raise meaningful problems for
further slab application. Cracking progresses with time due to ongoing shrinkage,
wheel impacts and other factors.
Unlimited size
Jointless slabs
13
The solving of shrinkage-induced issues allows the use of
PrīmXComposite for a practically unlimited size field
casting, without the need for saw cutting or placing joints.
The PrīmXComposite system uses steel fibre reinforcement that allows us to
create ductile, seamless concrete that is so strong it does not need traditional
steel bar reinforcement as a primary reinforcement.
Due to the properties of the material we can optimise traditional floor designs
significantly reducing the slab thickness. Combined with the increased speed of
construction, predictable, high-quality end result (flat, precise structures that stay
flat), the ability to ensure efficient gas and watertight solutions and environment-
friendly construction (saved CO2 emissions), makes PrīmXComposite the best
solution for industrial concrete floors and many other concrete structures.
WATCH HERE
Jointless concrete slabs on ground (full product description on website)
Jointless concrete slabs on piles (full product description on website)
14
Traditional concrete shrinks due to the drying process and forms cracks. Due to
uncontrolled cracking, concrete is not waterproof. Water penetrates the concrete
structure, resulting in different problems including erosion, reinforcement
corrosion etc.
To prevent the penetration of water indoors for foundations and other structures
exposed to water, waterproofing membranes are often used. Membranes work
as a barrier between the water and concrete structure. The traditional concrete
system solves the problem rather than addressing the cause.
The PrimXComposite system addresses
the cause rather than solving the
problem. In the case of this system, the
shrinkage process is controlled with
special anti-shrinkage additives. The
additives in PrīmXComposite bind H2O
molecules and form a micro-scale
composite structure, including crystals
that expand and compress the internal
concrete matrix. This expansion puts the
steel fibres in tension, creating permanent
pre-stress that results in compression of
the concrete.
Steel fibre integration ensures
homogenous reinforcement throughout
and has a significant impact on the
reduction of crack width as they hold
together cracks from the very start of their
development.
Water-tight
From the beginning, the PrīmXComposite system has been designed to address
a major drawback with traditional concrete– shrinkage and the problems it
causes: slab edge curling, cracking etc.
Effective water-
tight solutions
In this way, the concrete structure is much more homogenous and the
absence of cracks allows the material to be used in watertight concrete
structures.
A watertight concrete structure in turn means huge savings on waterproofing
membranes, its installation time and associated costs, including costly
groundwater pumping.
See the animation where watertight PrīmXComposite concrete is used to install
the watertight foundation plate (PrīmXComposite Raft foundation).
WATCH HERE

More Related Content

What's hot

FIBER REINFORCED CONCRETE
FIBER REINFORCED CONCRETEFIBER REINFORCED CONCRETE
FIBER REINFORCED CONCRETE
manish jashnani
 
Experimental Performance, Mathematical Modelling and Development of Stress Bl...
Experimental Performance, Mathematical Modelling and Development of Stress Bl...Experimental Performance, Mathematical Modelling and Development of Stress Bl...
Experimental Performance, Mathematical Modelling and Development of Stress Bl...
IRJET Journal
 
IRJET- Experimental Investigation of Steel Fiber Reinforced Concrete with Par...
IRJET- Experimental Investigation of Steel Fiber Reinforced Concrete with Par...IRJET- Experimental Investigation of Steel Fiber Reinforced Concrete with Par...
IRJET- Experimental Investigation of Steel Fiber Reinforced Concrete with Par...
IRJET Journal
 
Amjad ppt copy
Amjad ppt   copyAmjad ppt   copy
Amjad ppt copy
Amjad Ansari
 
Fibre Reinforced Concrete
Fibre Reinforced ConcreteFibre Reinforced Concrete
Fibre Reinforced Concrete
Harish1256
 
IRJET - Study on Workability and Compressive Strength of Concrete Blended...
IRJET -  	  Study on Workability and Compressive Strength of Concrete Blended...IRJET -  	  Study on Workability and Compressive Strength of Concrete Blended...
IRJET - Study on Workability and Compressive Strength of Concrete Blended...
IRJET Journal
 
Compressive and Split Tensile Strength of Chopped Basalt Fiber Concrete
Compressive and Split Tensile Strength of Chopped Basalt Fiber ConcreteCompressive and Split Tensile Strength of Chopped Basalt Fiber Concrete
Compressive and Split Tensile Strength of Chopped Basalt Fiber Concrete
IRJET Journal
 
Reactive powder concrete
Reactive powder concreteReactive powder concrete
Reactive powder concrete
Vignesh Nandha
 
IRJET- Durability Study on OPC and Slag based Cement Reinforced with Steel Fi...
IRJET- Durability Study on OPC and Slag based Cement Reinforced with Steel Fi...IRJET- Durability Study on OPC and Slag based Cement Reinforced with Steel Fi...
IRJET- Durability Study on OPC and Slag based Cement Reinforced with Steel Fi...
IRJET Journal
 
IRJET- Study on Mechanical Properties of Steel Fibre Reinforced Concrete
IRJET-  	  Study on Mechanical Properties of Steel Fibre Reinforced ConcreteIRJET-  	  Study on Mechanical Properties of Steel Fibre Reinforced Concrete
IRJET- Study on Mechanical Properties of Steel Fibre Reinforced Concrete
IRJET Journal
 
AN INVESTIGATION ON GLASS FIBRE REINFORCED CONCRETE USING ECO SAND
AN INVESTIGATION ON GLASS FIBRE REINFORCED CONCRETE USING ECO SANDAN INVESTIGATION ON GLASS FIBRE REINFORCED CONCRETE USING ECO SAND
AN INVESTIGATION ON GLASS FIBRE REINFORCED CONCRETE USING ECO SAND
Vikaas Balaji
 
Frc in industrial flooring
Frc in industrial flooringFrc in industrial flooring
Frc in industrial flooring
AMAL THANKACHAN
 
Self compacting concrete
Self compacting concreteSelf compacting concrete
Self compacting concrete
SonaSaravanan2
 
fibre reinforced concrete
fibre reinforced concretefibre reinforced concrete
fibre reinforced concrete
Venkatesh Ca
 
IRJET- Utilization of Rice Husk Ash and Foundry Sand as Partial Replaceme...
IRJET-  	  Utilization of Rice Husk Ash and Foundry Sand as Partial Replaceme...IRJET-  	  Utilization of Rice Husk Ash and Foundry Sand as Partial Replaceme...
IRJET- Utilization of Rice Husk Ash and Foundry Sand as Partial Replaceme...
IRJET Journal
 
journel clubs in prosthodontics
journel clubs in prosthodonticsjournel clubs in prosthodontics
journel clubs in prosthodontics
dellasain
 
J48077280
J48077280J48077280
J48077280
IJERA Editor
 
Quality control of concrete
Quality control of concreteQuality control of concrete
Quality control of concrete
Gaurang Kakadiya
 
REPAIRS AND REHABILITATION OF STRUCTURES
REPAIRS AND REHABILITATION OF STRUCTURESREPAIRS AND REHABILITATION OF STRUCTURES
REPAIRS AND REHABILITATION OF STRUCTURES
brijlata sharma
 
fiber reinforced concrete
fiber reinforced concretefiber reinforced concrete
fiber reinforced concrete
gopichand's
 

What's hot (20)

FIBER REINFORCED CONCRETE
FIBER REINFORCED CONCRETEFIBER REINFORCED CONCRETE
FIBER REINFORCED CONCRETE
 
Experimental Performance, Mathematical Modelling and Development of Stress Bl...
Experimental Performance, Mathematical Modelling and Development of Stress Bl...Experimental Performance, Mathematical Modelling and Development of Stress Bl...
Experimental Performance, Mathematical Modelling and Development of Stress Bl...
 
IRJET- Experimental Investigation of Steel Fiber Reinforced Concrete with Par...
IRJET- Experimental Investigation of Steel Fiber Reinforced Concrete with Par...IRJET- Experimental Investigation of Steel Fiber Reinforced Concrete with Par...
IRJET- Experimental Investigation of Steel Fiber Reinforced Concrete with Par...
 
Amjad ppt copy
Amjad ppt   copyAmjad ppt   copy
Amjad ppt copy
 
Fibre Reinforced Concrete
Fibre Reinforced ConcreteFibre Reinforced Concrete
Fibre Reinforced Concrete
 
IRJET - Study on Workability and Compressive Strength of Concrete Blended...
IRJET -  	  Study on Workability and Compressive Strength of Concrete Blended...IRJET -  	  Study on Workability and Compressive Strength of Concrete Blended...
IRJET - Study on Workability and Compressive Strength of Concrete Blended...
 
Compressive and Split Tensile Strength of Chopped Basalt Fiber Concrete
Compressive and Split Tensile Strength of Chopped Basalt Fiber ConcreteCompressive and Split Tensile Strength of Chopped Basalt Fiber Concrete
Compressive and Split Tensile Strength of Chopped Basalt Fiber Concrete
 
Reactive powder concrete
Reactive powder concreteReactive powder concrete
Reactive powder concrete
 
IRJET- Durability Study on OPC and Slag based Cement Reinforced with Steel Fi...
IRJET- Durability Study on OPC and Slag based Cement Reinforced with Steel Fi...IRJET- Durability Study on OPC and Slag based Cement Reinforced with Steel Fi...
IRJET- Durability Study on OPC and Slag based Cement Reinforced with Steel Fi...
 
IRJET- Study on Mechanical Properties of Steel Fibre Reinforced Concrete
IRJET-  	  Study on Mechanical Properties of Steel Fibre Reinforced ConcreteIRJET-  	  Study on Mechanical Properties of Steel Fibre Reinforced Concrete
IRJET- Study on Mechanical Properties of Steel Fibre Reinforced Concrete
 
AN INVESTIGATION ON GLASS FIBRE REINFORCED CONCRETE USING ECO SAND
AN INVESTIGATION ON GLASS FIBRE REINFORCED CONCRETE USING ECO SANDAN INVESTIGATION ON GLASS FIBRE REINFORCED CONCRETE USING ECO SAND
AN INVESTIGATION ON GLASS FIBRE REINFORCED CONCRETE USING ECO SAND
 
Frc in industrial flooring
Frc in industrial flooringFrc in industrial flooring
Frc in industrial flooring
 
Self compacting concrete
Self compacting concreteSelf compacting concrete
Self compacting concrete
 
fibre reinforced concrete
fibre reinforced concretefibre reinforced concrete
fibre reinforced concrete
 
IRJET- Utilization of Rice Husk Ash and Foundry Sand as Partial Replaceme...
IRJET-  	  Utilization of Rice Husk Ash and Foundry Sand as Partial Replaceme...IRJET-  	  Utilization of Rice Husk Ash and Foundry Sand as Partial Replaceme...
IRJET- Utilization of Rice Husk Ash and Foundry Sand as Partial Replaceme...
 
journel clubs in prosthodontics
journel clubs in prosthodonticsjournel clubs in prosthodontics
journel clubs in prosthodontics
 
J48077280
J48077280J48077280
J48077280
 
Quality control of concrete
Quality control of concreteQuality control of concrete
Quality control of concrete
 
REPAIRS AND REHABILITATION OF STRUCTURES
REPAIRS AND REHABILITATION OF STRUCTURESREPAIRS AND REHABILITATION OF STRUCTURES
REPAIRS AND REHABILITATION OF STRUCTURES
 
fiber reinforced concrete
fiber reinforced concretefiber reinforced concrete
fiber reinforced concrete
 

Similar to 2018 primekss e book-five-values-of-pxc-1910-2018

Precast compound wall
Precast compound wallPrecast compound wall
Precast compound wall
Harsh Bothra
 
Post tensioned (PT) slabs
Post tensioned (PT) slabsPost tensioned (PT) slabs
Post tensioned (PT) slabs
FOYSOLMAHMUD1
 
Experimental study of concrete using corrugated steel fibre
Experimental study of concrete using corrugated steel fibreExperimental study of concrete using corrugated steel fibre
Experimental study of concrete using corrugated steel fibre
AbishaY1
 
IRJET- Performance Evaluation of Ferro Cement Sandwich Wall Panels with D...
IRJET-  	  Performance Evaluation of Ferro Cement Sandwich Wall Panels with D...IRJET-  	  Performance Evaluation of Ferro Cement Sandwich Wall Panels with D...
IRJET- Performance Evaluation of Ferro Cement Sandwich Wall Panels with D...
IRJET Journal
 
Use of Human Hair as Natural Fibre for Reinforced Concrete .
Use of Human Hair as Natural Fibre for Reinforced Concrete .Use of Human Hair as Natural Fibre for Reinforced Concrete .
Use of Human Hair as Natural Fibre for Reinforced Concrete .
SHASHANK SHEKHAR
 
Acm assignment
Acm assignmentAcm assignment
Acm assignment
Aaqib Iqbal
 
How to Guarantee Design-Life of Concrete Structures-MasterBuilder-July 2016
How to Guarantee Design-Life of Concrete Structures-MasterBuilder-July 2016How to Guarantee Design-Life of Concrete Structures-MasterBuilder-July 2016
How to Guarantee Design-Life of Concrete Structures-MasterBuilder-July 2016
Dr.Subramanian Narayanan
 
Post tensioning in building structures
Post tensioning in building structuresPost tensioning in building structures
Post tensioning in building structures
Luan Truong Van
 
Iaetsd experimental investigation on self compacting fiber reinforced concret...
Iaetsd experimental investigation on self compacting fiber reinforced concret...Iaetsd experimental investigation on self compacting fiber reinforced concret...
Iaetsd experimental investigation on self compacting fiber reinforced concret...
Iaetsd Iaetsd
 
Iirdem experimental investigation on self compacting fiber reinforced concret...
Iirdem experimental investigation on self compacting fiber reinforced concret...Iirdem experimental investigation on self compacting fiber reinforced concret...
Iirdem experimental investigation on self compacting fiber reinforced concret...
Iaetsd Iaetsd
 
Case Study on Glass Fibre Reinforced Concrete
Case Study on Glass Fibre Reinforced ConcreteCase Study on Glass Fibre Reinforced Concrete
Case Study on Glass Fibre Reinforced Concrete
IRJET Journal
 
Steel fibers vs steel mesh in concrete reinforcement
Steel fibers vs steel mesh in concrete reinforcementSteel fibers vs steel mesh in concrete reinforcement
Steel fibers vs steel mesh in concrete reinforcement
Bekaert
 
Experimental Investigation on Steel Concrete Composite Floor Slab
Experimental Investigation on Steel Concrete Composite Floor SlabExperimental Investigation on Steel Concrete Composite Floor Slab
Experimental Investigation on Steel Concrete Composite Floor Slab
IRJET Journal
 
Self-Compacting-Fiber-Reinforced-Concrete.pptx
Self-Compacting-Fiber-Reinforced-Concrete.pptxSelf-Compacting-Fiber-Reinforced-Concrete.pptx
Self-Compacting-Fiber-Reinforced-Concrete.pptx
BasineniUdaykumar
 
Comparison of Performance of Non Metallic Fibre Reinforced Concrete and Plain...
Comparison of Performance of Non Metallic Fibre Reinforced Concrete and Plain...Comparison of Performance of Non Metallic Fibre Reinforced Concrete and Plain...
Comparison of Performance of Non Metallic Fibre Reinforced Concrete and Plain...
IRJET Journal
 
Self-Compacting-Fiber-Reinforced-Concrete.pptx
Self-Compacting-Fiber-Reinforced-Concrete.pptxSelf-Compacting-Fiber-Reinforced-Concrete.pptx
Self-Compacting-Fiber-Reinforced-Concrete.pptx
Pranay Reddy
 
Experimental Study on Strength of Concrete with Addition of Chopped Glass Fiber
Experimental Study on Strength of Concrete with Addition of Chopped Glass FiberExperimental Study on Strength of Concrete with Addition of Chopped Glass Fiber
Experimental Study on Strength of Concrete with Addition of Chopped Glass Fiber
IRJET Journal
 
Light weight concrete
Light weight concreteLight weight concrete
Light weight concrete
chandrakanthkadadas
 
Precast Concrete is the most prominent structure
Precast Concrete is the most prominent structurePrecast Concrete is the most prominent structure
Precast Concrete is the most prominent structure
NisshantSinghSaud
 
Speedy construction
Speedy constructionSpeedy construction
Speedy construction
somitra bhardwaj
 

Similar to 2018 primekss e book-five-values-of-pxc-1910-2018 (20)

Precast compound wall
Precast compound wallPrecast compound wall
Precast compound wall
 
Post tensioned (PT) slabs
Post tensioned (PT) slabsPost tensioned (PT) slabs
Post tensioned (PT) slabs
 
Experimental study of concrete using corrugated steel fibre
Experimental study of concrete using corrugated steel fibreExperimental study of concrete using corrugated steel fibre
Experimental study of concrete using corrugated steel fibre
 
IRJET- Performance Evaluation of Ferro Cement Sandwich Wall Panels with D...
IRJET-  	  Performance Evaluation of Ferro Cement Sandwich Wall Panels with D...IRJET-  	  Performance Evaluation of Ferro Cement Sandwich Wall Panels with D...
IRJET- Performance Evaluation of Ferro Cement Sandwich Wall Panels with D...
 
Use of Human Hair as Natural Fibre for Reinforced Concrete .
Use of Human Hair as Natural Fibre for Reinforced Concrete .Use of Human Hair as Natural Fibre for Reinforced Concrete .
Use of Human Hair as Natural Fibre for Reinforced Concrete .
 
Acm assignment
Acm assignmentAcm assignment
Acm assignment
 
How to Guarantee Design-Life of Concrete Structures-MasterBuilder-July 2016
How to Guarantee Design-Life of Concrete Structures-MasterBuilder-July 2016How to Guarantee Design-Life of Concrete Structures-MasterBuilder-July 2016
How to Guarantee Design-Life of Concrete Structures-MasterBuilder-July 2016
 
Post tensioning in building structures
Post tensioning in building structuresPost tensioning in building structures
Post tensioning in building structures
 
Iaetsd experimental investigation on self compacting fiber reinforced concret...
Iaetsd experimental investigation on self compacting fiber reinforced concret...Iaetsd experimental investigation on self compacting fiber reinforced concret...
Iaetsd experimental investigation on self compacting fiber reinforced concret...
 
Iirdem experimental investigation on self compacting fiber reinforced concret...
Iirdem experimental investigation on self compacting fiber reinforced concret...Iirdem experimental investigation on self compacting fiber reinforced concret...
Iirdem experimental investigation on self compacting fiber reinforced concret...
 
Case Study on Glass Fibre Reinforced Concrete
Case Study on Glass Fibre Reinforced ConcreteCase Study on Glass Fibre Reinforced Concrete
Case Study on Glass Fibre Reinforced Concrete
 
Steel fibers vs steel mesh in concrete reinforcement
Steel fibers vs steel mesh in concrete reinforcementSteel fibers vs steel mesh in concrete reinforcement
Steel fibers vs steel mesh in concrete reinforcement
 
Experimental Investigation on Steel Concrete Composite Floor Slab
Experimental Investigation on Steel Concrete Composite Floor SlabExperimental Investigation on Steel Concrete Composite Floor Slab
Experimental Investigation on Steel Concrete Composite Floor Slab
 
Self-Compacting-Fiber-Reinforced-Concrete.pptx
Self-Compacting-Fiber-Reinforced-Concrete.pptxSelf-Compacting-Fiber-Reinforced-Concrete.pptx
Self-Compacting-Fiber-Reinforced-Concrete.pptx
 
Comparison of Performance of Non Metallic Fibre Reinforced Concrete and Plain...
Comparison of Performance of Non Metallic Fibre Reinforced Concrete and Plain...Comparison of Performance of Non Metallic Fibre Reinforced Concrete and Plain...
Comparison of Performance of Non Metallic Fibre Reinforced Concrete and Plain...
 
Self-Compacting-Fiber-Reinforced-Concrete.pptx
Self-Compacting-Fiber-Reinforced-Concrete.pptxSelf-Compacting-Fiber-Reinforced-Concrete.pptx
Self-Compacting-Fiber-Reinforced-Concrete.pptx
 
Experimental Study on Strength of Concrete with Addition of Chopped Glass Fiber
Experimental Study on Strength of Concrete with Addition of Chopped Glass FiberExperimental Study on Strength of Concrete with Addition of Chopped Glass Fiber
Experimental Study on Strength of Concrete with Addition of Chopped Glass Fiber
 
Light weight concrete
Light weight concreteLight weight concrete
Light weight concrete
 
Precast Concrete is the most prominent structure
Precast Concrete is the most prominent structurePrecast Concrete is the most prominent structure
Precast Concrete is the most prominent structure
 
Speedy construction
Speedy constructionSpeedy construction
Speedy construction
 

Recently uploaded

みなさんこんにちはこれ何文字まで入るの?40文字以下不可とか本当に意味わからないけどこれ限界文字数書いてないからマジでやばい文字数いけるんじゃないの?えこ...
みなさんこんにちはこれ何文字まで入るの?40文字以下不可とか本当に意味わからないけどこれ限界文字数書いてないからマジでやばい文字数いけるんじゃないの?えこ...みなさんこんにちはこれ何文字まで入るの?40文字以下不可とか本当に意味わからないけどこれ限界文字数書いてないからマジでやばい文字数いけるんじゃないの?えこ...
みなさんこんにちはこれ何文字まで入るの?40文字以下不可とか本当に意味わからないけどこれ限界文字数書いてないからマジでやばい文字数いけるんじゃないの?えこ...
名前 です男
 
20240609 QFM020 Irresponsible AI Reading List May 2024
20240609 QFM020 Irresponsible AI Reading List May 202420240609 QFM020 Irresponsible AI Reading List May 2024
20240609 QFM020 Irresponsible AI Reading List May 2024
Matthew Sinclair
 
GraphSummit Singapore | Graphing Success: Revolutionising Organisational Stru...
GraphSummit Singapore | Graphing Success: Revolutionising Organisational Stru...GraphSummit Singapore | Graphing Success: Revolutionising Organisational Stru...
GraphSummit Singapore | Graphing Success: Revolutionising Organisational Stru...
Neo4j
 
Pushing the limits of ePRTC: 100ns holdover for 100 days
Pushing the limits of ePRTC: 100ns holdover for 100 daysPushing the limits of ePRTC: 100ns holdover for 100 days
Pushing the limits of ePRTC: 100ns holdover for 100 days
Adtran
 
Unlock the Future of Search with MongoDB Atlas_ Vector Search Unleashed.pdf
Unlock the Future of Search with MongoDB Atlas_ Vector Search Unleashed.pdfUnlock the Future of Search with MongoDB Atlas_ Vector Search Unleashed.pdf
Unlock the Future of Search with MongoDB Atlas_ Vector Search Unleashed.pdf
Malak Abu Hammad
 
GraphSummit Singapore | The Future of Agility: Supercharging Digital Transfor...
GraphSummit Singapore | The Future of Agility: Supercharging Digital Transfor...GraphSummit Singapore | The Future of Agility: Supercharging Digital Transfor...
GraphSummit Singapore | The Future of Agility: Supercharging Digital Transfor...
Neo4j
 
RESUME BUILDER APPLICATION Project for students
RESUME BUILDER APPLICATION Project for studentsRESUME BUILDER APPLICATION Project for students
RESUME BUILDER APPLICATION Project for students
KAMESHS29
 
Introducing Milvus Lite: Easy-to-Install, Easy-to-Use vector database for you...
Introducing Milvus Lite: Easy-to-Install, Easy-to-Use vector database for you...Introducing Milvus Lite: Easy-to-Install, Easy-to-Use vector database for you...
Introducing Milvus Lite: Easy-to-Install, Easy-to-Use vector database for you...
Zilliz
 
Climate Impact of Software Testing at Nordic Testing Days
Climate Impact of Software Testing at Nordic Testing DaysClimate Impact of Software Testing at Nordic Testing Days
Climate Impact of Software Testing at Nordic Testing Days
Kari Kakkonen
 
Presentation of the OECD Artificial Intelligence Review of Germany
Presentation of the OECD Artificial Intelligence Review of GermanyPresentation of the OECD Artificial Intelligence Review of Germany
Presentation of the OECD Artificial Intelligence Review of Germany
innovationoecd
 
Why You Should Replace Windows 11 with Nitrux Linux 3.5.0 for enhanced perfor...
Why You Should Replace Windows 11 with Nitrux Linux 3.5.0 for enhanced perfor...Why You Should Replace Windows 11 with Nitrux Linux 3.5.0 for enhanced perfor...
Why You Should Replace Windows 11 with Nitrux Linux 3.5.0 for enhanced perfor...
SOFTTECHHUB
 
Microsoft - Power Platform_G.Aspiotis.pdf
Microsoft - Power Platform_G.Aspiotis.pdfMicrosoft - Power Platform_G.Aspiotis.pdf
Microsoft - Power Platform_G.Aspiotis.pdf
Uni Systems S.M.S.A.
 
Let's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with Slack
Let's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with SlackLet's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with Slack
Let's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with Slack
shyamraj55
 
Generative AI Deep Dive: Advancing from Proof of Concept to Production
Generative AI Deep Dive: Advancing from Proof of Concept to ProductionGenerative AI Deep Dive: Advancing from Proof of Concept to Production
Generative AI Deep Dive: Advancing from Proof of Concept to Production
Aggregage
 
TrustArc Webinar - 2024 Global Privacy Survey
TrustArc Webinar - 2024 Global Privacy SurveyTrustArc Webinar - 2024 Global Privacy Survey
TrustArc Webinar - 2024 Global Privacy Survey
TrustArc
 
National Security Agency - NSA mobile device best practices
National Security Agency - NSA mobile device best practicesNational Security Agency - NSA mobile device best practices
National Security Agency - NSA mobile device best practices
Quotidiano Piemontese
 
20 Comprehensive Checklist of Designing and Developing a Website
20 Comprehensive Checklist of Designing and Developing a Website20 Comprehensive Checklist of Designing and Developing a Website
20 Comprehensive Checklist of Designing and Developing a Website
Pixlogix Infotech
 
Data structures and Algorithms in Python.pdf
Data structures and Algorithms in Python.pdfData structures and Algorithms in Python.pdf
Data structures and Algorithms in Python.pdf
TIPNGVN2
 
20240605 QFM017 Machine Intelligence Reading List May 2024
20240605 QFM017 Machine Intelligence Reading List May 202420240605 QFM017 Machine Intelligence Reading List May 2024
20240605 QFM017 Machine Intelligence Reading List May 2024
Matthew Sinclair
 
How to Get CNIC Information System with Paksim Ga.pptx
How to Get CNIC Information System with Paksim Ga.pptxHow to Get CNIC Information System with Paksim Ga.pptx
How to Get CNIC Information System with Paksim Ga.pptx
danishmna97
 

Recently uploaded (20)

みなさんこんにちはこれ何文字まで入るの?40文字以下不可とか本当に意味わからないけどこれ限界文字数書いてないからマジでやばい文字数いけるんじゃないの?えこ...
みなさんこんにちはこれ何文字まで入るの?40文字以下不可とか本当に意味わからないけどこれ限界文字数書いてないからマジでやばい文字数いけるんじゃないの?えこ...みなさんこんにちはこれ何文字まで入るの?40文字以下不可とか本当に意味わからないけどこれ限界文字数書いてないからマジでやばい文字数いけるんじゃないの?えこ...
みなさんこんにちはこれ何文字まで入るの?40文字以下不可とか本当に意味わからないけどこれ限界文字数書いてないからマジでやばい文字数いけるんじゃないの?えこ...
 
20240609 QFM020 Irresponsible AI Reading List May 2024
20240609 QFM020 Irresponsible AI Reading List May 202420240609 QFM020 Irresponsible AI Reading List May 2024
20240609 QFM020 Irresponsible AI Reading List May 2024
 
GraphSummit Singapore | Graphing Success: Revolutionising Organisational Stru...
GraphSummit Singapore | Graphing Success: Revolutionising Organisational Stru...GraphSummit Singapore | Graphing Success: Revolutionising Organisational Stru...
GraphSummit Singapore | Graphing Success: Revolutionising Organisational Stru...
 
Pushing the limits of ePRTC: 100ns holdover for 100 days
Pushing the limits of ePRTC: 100ns holdover for 100 daysPushing the limits of ePRTC: 100ns holdover for 100 days
Pushing the limits of ePRTC: 100ns holdover for 100 days
 
Unlock the Future of Search with MongoDB Atlas_ Vector Search Unleashed.pdf
Unlock the Future of Search with MongoDB Atlas_ Vector Search Unleashed.pdfUnlock the Future of Search with MongoDB Atlas_ Vector Search Unleashed.pdf
Unlock the Future of Search with MongoDB Atlas_ Vector Search Unleashed.pdf
 
GraphSummit Singapore | The Future of Agility: Supercharging Digital Transfor...
GraphSummit Singapore | The Future of Agility: Supercharging Digital Transfor...GraphSummit Singapore | The Future of Agility: Supercharging Digital Transfor...
GraphSummit Singapore | The Future of Agility: Supercharging Digital Transfor...
 
RESUME BUILDER APPLICATION Project for students
RESUME BUILDER APPLICATION Project for studentsRESUME BUILDER APPLICATION Project for students
RESUME BUILDER APPLICATION Project for students
 
Introducing Milvus Lite: Easy-to-Install, Easy-to-Use vector database for you...
Introducing Milvus Lite: Easy-to-Install, Easy-to-Use vector database for you...Introducing Milvus Lite: Easy-to-Install, Easy-to-Use vector database for you...
Introducing Milvus Lite: Easy-to-Install, Easy-to-Use vector database for you...
 
Climate Impact of Software Testing at Nordic Testing Days
Climate Impact of Software Testing at Nordic Testing DaysClimate Impact of Software Testing at Nordic Testing Days
Climate Impact of Software Testing at Nordic Testing Days
 
Presentation of the OECD Artificial Intelligence Review of Germany
Presentation of the OECD Artificial Intelligence Review of GermanyPresentation of the OECD Artificial Intelligence Review of Germany
Presentation of the OECD Artificial Intelligence Review of Germany
 
Why You Should Replace Windows 11 with Nitrux Linux 3.5.0 for enhanced perfor...
Why You Should Replace Windows 11 with Nitrux Linux 3.5.0 for enhanced perfor...Why You Should Replace Windows 11 with Nitrux Linux 3.5.0 for enhanced perfor...
Why You Should Replace Windows 11 with Nitrux Linux 3.5.0 for enhanced perfor...
 
Microsoft - Power Platform_G.Aspiotis.pdf
Microsoft - Power Platform_G.Aspiotis.pdfMicrosoft - Power Platform_G.Aspiotis.pdf
Microsoft - Power Platform_G.Aspiotis.pdf
 
Let's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with Slack
Let's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with SlackLet's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with Slack
Let's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with Slack
 
Generative AI Deep Dive: Advancing from Proof of Concept to Production
Generative AI Deep Dive: Advancing from Proof of Concept to ProductionGenerative AI Deep Dive: Advancing from Proof of Concept to Production
Generative AI Deep Dive: Advancing from Proof of Concept to Production
 
TrustArc Webinar - 2024 Global Privacy Survey
TrustArc Webinar - 2024 Global Privacy SurveyTrustArc Webinar - 2024 Global Privacy Survey
TrustArc Webinar - 2024 Global Privacy Survey
 
National Security Agency - NSA mobile device best practices
National Security Agency - NSA mobile device best practicesNational Security Agency - NSA mobile device best practices
National Security Agency - NSA mobile device best practices
 
20 Comprehensive Checklist of Designing and Developing a Website
20 Comprehensive Checklist of Designing and Developing a Website20 Comprehensive Checklist of Designing and Developing a Website
20 Comprehensive Checklist of Designing and Developing a Website
 
Data structures and Algorithms in Python.pdf
Data structures and Algorithms in Python.pdfData structures and Algorithms in Python.pdf
Data structures and Algorithms in Python.pdf
 
20240605 QFM017 Machine Intelligence Reading List May 2024
20240605 QFM017 Machine Intelligence Reading List May 202420240605 QFM017 Machine Intelligence Reading List May 2024
20240605 QFM017 Machine Intelligence Reading List May 2024
 
How to Get CNIC Information System with Paksim Ga.pptx
How to Get CNIC Information System with Paksim Ga.pptxHow to Get CNIC Information System with Paksim Ga.pptx
How to Get CNIC Information System with Paksim Ga.pptx
 

2018 primekss e book-five-values-of-pxc-1910-2018

  • 1. of the PrīmXComposite system that make it the best application in 80% of all concrete structures Five Values ✓ 50% Stronger Material ✓ 30% Faster Construction ✓ 40% CO2 Emission Saving ✓ Water-tight ✓ Jointless
  • 2. Concrete Rafts, Walls, Floors… • No time-consuming, expensive and dangerous tying of reinforcement mesh and bars for workers • Time savings on the installation of waterproofing membranes The well-established PrīmXComposite system uses a high dosage rate (1.2 kilometres of steel per cubic metre of very strong - 3 times stronger than traditional rebars - steel fibres, blended into concrete using the PrīmX Fibre blower. It ensures the precisely dosed and homogeneous integration of fibres. Below you will find a speed comparison of the PrīmXComposite and traditional (steel bar reinforced) concrete system installing raft (mat) foundation. The comparison is made based on data from a successful raft foundation installation at one of our completed projects in Norway. The current project was built with the PrīmXComposite method and the data comes from the real life application. 3 major steps in the raft foundation construction process: 1. Waterproofing membrane installation; 2. Steel bar/mesh installation; and 3. Concrete casting. •Raft/mat foundation •Building site is located only ten metres from a channel •High groundwater level Case Study 5 story building Norway, Storgata 5, Fredrikstad 30% Faster Construction
  • 3. Steps Traditional Method (steel bar reinforced) PrīmXComposite Waterproofing membrane installation 7 days 4 workers 28 man-days 1 day 4 workers 4 man-days Steel bar/mesh installation 15 days 10 workers 150 man-days 5 days 5 workers 25 man-days Concrete casting 1 day 5 workers 5 man-days 1 day 8 workers 8 man-days Total: 23 days 183 man days 7 days 37 man days System Comparison Additionally, for a traditional system: • For the traditional method, expensive waterproofing membranes are needed. In the case of PrīmXComposite, membranes are not placed as PrīmXComposite concrete is waterproof. • Membrane installation is dependent on weather conditions and there is risk of damage during steel bar/mesh installation. In most cases, it is very difficult to fix if damage occurs. • Using the traditional method, there are crane rental costs for unloading steel bars and dangerous conditions for for workers (unloading, work with steel bar cutters etc.). • Steel bar delivery and storage requires additional space. Savings using the PrīmXComposite system in the current project: 16 168 Days saved that can be used for further build-up Man-days saved due to absence of steel bar installation and waterproofing works 3
  • 4. 1 3 5 7 9 11 13 15 17 19 21 23 Duration in Days 1 3 5 7 9 11 13 15 17 19 21 23 Traditional Concrete 7 Days Waterproofing, measurements, and mould placement 15 Days Steel Bar & Mesh Installation 1 Day Concrete Casting 1 Day Measurements and mould placement 5 Days Starters & Rebar near pile heads Implementation Time Comparison: Traditional Concrete to PrīmXComposite 1 Day Concrete Casting Time Savings: 16 Days Labor Savings: 146 Days Much faster Perfect in limited building space Safe for workers Watertight
  • 5. 5 In the concrete industry, all professionals are familiar with the traditional (steel bar/steel mesh) reinforced concrete solutions. Integrated in traditional concrete, steel bars/meshes solve various structural tasks. However, this system has challenges: - installation is time consuming and therefore a costly process; - used in watertight solutions, the traditional system is very expensive and inefficient from the perspective of materials used (steel and concrete); - material is not homogenous; there are often challenges regarding flexural and impact resistance; - amount of steel needed in a traditional reinforcement solution is often high, so this type of reinforcement is costly; - a dedicated zone is required onsite for unloading; - installation work (rebar cutters, work with angle grinder, stumbling possibilities on mesh etc.) is often dangerous for workers. Steel fiber reinforced ultra performance system In a steel fibre system, reinforcement is formed from a high concentration of steel fibres homogenously distributed into a concrete matrix. By adding steel fibres into concrete, the flexural strength of the composite can be increased significantly - even 100% or more - depending on the concrete’s strength, dosage, amount and strength of fibres. Steel fibre reinforcement transforms concrete from a brittle material with very low flexural strength into a ductile, spatially reinforced structure with much higher flexural strength, better control of cracking, higher resistance to spalling, improved fatigue strength and much higher wear resistance. NB! 80 kg/m3 12mm steel bars OR 35 kg/m3 steel fibers. Interface surface: 4m2 vs 23.5 m2 140 meters of reinforcement bars / 1m3 550 N/mm2 steel reinforcement bars 10 000 meters of steel fiber reinforcement / 1m3 1 200 to 1 800 N/mm2 steel fibers 50% Stronger Material
  • 6. 6 PrīmXComposite system uses steel fibre reinforcement and special anti- shrinkage additives to ensure non-shrinking, ductile concrete that can be used in many structures. Due to special anti-shrinkage additives in the drying process, a chemical pre- stress is formed that puts fibres in permanent tension. Therefore, fibres act against the crack formation process and cracking is absolutely minimised. Cracks are taken into consideration as weakening points for the structure when making structural calculations. In the case of PrīmXComposite there is no weakening due to crack formation, or the risk is highly reduced. In the PrīmXComposite system, we use high-quality steel fibres only. We have investigated the performance of fibres of different shapes and lengths with our system, conducting many tests in our own and partner laboratories. In our own laboratory, we perform more than 300 tests yearly for concrete and fibres. One of the key benefits when comparing steel bar and steel fibre reinforced structures is homogenous material properties obtained with steel fibre technology. To ensure perfect reinforcement distribution, we use special steel fibre dosing equipment, the PrīmX Fibre blower. View the video to see how we ensure homogenous fibre distribution: WATCH HERE
  • 7. 7 Strength Development Shrinkage Stress crack shrinkage stress PrīmXComposite Concrete Model on the left schematically shows the relation between concrete material strength development and tensile stress development, which is induced by the restrained drying shrinkage. Traditional concrete shrinks right after it has been poured and at a certain point the shrinkage stress induced exceeds the resistance of the concrete, which causes the material to crack. PrīmXComposite concrete works towards reducing the negative effects of shrinkage stress. The special, patented formula of additives causes material expansion and delays the onset of shrinkage and significantly reduces the amount of shrinkage of the concrete, therefore drying shrinkage is practically eliminated. A high quality end result is obtained through a careful process of mix design preparation, controlled addition of PrīmXComposite shrinkage reducing additives, concrete batch plant control and onsite concrete control in the form of fresh concrete testing to ensure mix design parameters are met. Model on the right shows loads applied vs. deflection. You can see, and it is shown in many scientific papers, that the SFR (Steel Fibre Reinforced) concrete enjoys a phenomenon called material hardening. This is the SFR concrete being able to continue to resist loads far higher than that which cracked the specimen. Traditional concrete cracks at a lower load and simply fails with no residual load bearing capacity. Saying this, it is important to ensure that you use a quality steel fibre. A force Ʈ (image below) is applied to pull out the fibre, and this is resisted by the development of the bond / friction within the concrete - to the extent of the surface area and length of embedment. 1st crack kN Deflection Trad. Concrete SFR Concrete Material Hardening Material Hardening Phenomenon Our design approach is based on full-scale structural testing of round indeterminate plate tests. These tests result in high plastic tensile strength with controlled integration of the PrīmXComposite system’s anti shrinkage additives. Mix design preparation considers the quality of the base materials, the trial mix testing (slump, density, compressive strength cubes 3, 7 and 28 days) and the eventual quality control over the execution and casting on site, where fresh concrete testing is of the utmost importance and is in accordance with ASTM and CEN guidelines.
  • 8. 8 Tensile force T d 1. L 𝜏 L/2 2. 3. Matrix 3 Possible Types of Failure Thousands of tests have been carried out with fibres of different strength class and shape, to have reliable results upon which to build optimal designs. Along with tests made with different types of fibres (various tensile strengths, diameters, shape length) to determine optimal solutions, Primekss has carried out tests to determine the pull-out force differences between standard SFRC (steel fibre reinforced) and own HPSFRC (High Performance Steel Fibre Reinforced Concrete) technology – PrīmXComposite. The tests performed indicate that there is on average a 12% increase in pull-out force using PrīmXComposite concrete. Due to special anti-shrinkage chemical additives being added during curing of the material, expansion occurs. The expansion is restrained by the fibres and surrounding concrete, thus there is increased compressive force working on each fibre, leading to higher pull-out force. Main benefits due to the increased strength of concrete with the PrīmXComposite system: • possibility to optimise design and reduce slab thickness resulting in material and cost economies • high impact resistance due to spatially integrated reinforcement and absolutely minimised cracking • greater fatigue endurance • reduced maintenance costs as steel fibre reinforced concrete becomes more impact resistant • longer useful working life. 1. Tension. Embedment in concrete is very strong but the fibre ruptures. 2. Interface bond. The bond between fibre and concrete is not sufficient and the fibre is pulled out from the concrete. 3. Concrete. Fibre is strong, the bond is strong and when the fibre is pulled out, the concrete along the fibre is pulled out in a cone.
  • 9. 9 With improved environmental awareness, there is an ever-growing interest in reducing carbon emissions related to concrete. The Cement industry is responsible for 6% of the world’s overall CO2 emissions, and this is twice the amount of CO2 emissions generated by all of the world’s airplanes combined. Due to the inclusion of steel fibre reinforcement and special anti-shrinkage additives, the PrīmXComposite system ensures a possibility to cast a strong, stiff, and jointless concrete slab with significantly reduced slab thickness compared to traditionally reinforced floors, still exceeding the defined load bearing capacity. The slab thickness reduction and use of steel fibre reinforcement in the PrīmXComposite system reduces the consumption of our limited resources and reduces CO2 emissions during construction. On average, the PrīmXCoposite system saves 40% of CO2 emissions compared to traditional steel bar reinforced concrete construction. 40% CO2 Emission Saving ECO-friendly construction
  • 10. 10 Design solution Concrete Steel CO₂ emission (kg CO₂/m² of floor) from m3 kg/m2 Concrete Steel Net Traditional design (50,000 m2, 150 mm) 7,500 11.7 36.7 11.7 48.4 PrīmXComposite design – Total (50,000 m²) 6,300* 5.0 30.8 5.0 35.9 PrīmXComposite design (40,000 m2, 130 mm) 5,200 5.2 31.8 5.2 37.0 PrīmXComposite design (10,000 m2, 110 mm) 1,100 4.4 26.9 4.4 31.3 * Reduced volume of concrete results in an estimated 120 fewer trucks on the job site, assuming a 10 m³ volume drum Material savings due to PrīmXComposite application: CO2 calculation based on methodology covered in detail in the scientific paper: “REDUCING CO2 EMISSIONS OF CONCRETE SLAB CONSTRUCTIONS WITH THE PRIME COMPOSITE SLAB SYSTEM”, Brad J. PEASE, PhD Concrete and Structural Engineer, PrimekssLabs; Xavier DESTRÉE, Structural Engineer, La Hulpe, Belgium. CO2 savings calculation: CO2 savings on concrete: 5.9 kg CO₂ per m² of floor CO2 savings on steel: 6.7 kg CO₂ per m² of floor Total CO2 saved on this project: 626,280 kg Scientific paper covering methodology and calculations DOWNLOAD HERE Traditional Concrete reinforced with steel mesh 150mm all 50,000 m2 PrimXComposite Design 130mm 40,000 m2 110mm 10,000 m2 Cross Dock Area Example: warehouse with 50,000m2 total area Selected PrimXComposite over Traditional Concrete FloorThickness Warehouse Floor
  • 11. 11 Reduced more than 18 285 525 kg of CO2 emissions in 2017 by customers choosing PrīmXComposite, the Primekss 20th Anniversary campaign. Reducing CO2 emissions lets your Company go GREEN and gain LEED certification. Projects pursuing LEED certification earn points across several categories. Based on the number of points achieved, a project then earns one of four LEED rating levels: Certified, Silver, Gold or Platinum. Presented with CO2 saver certificate Ensuring environmentally-friendly construction is one of Primekss’ priorities. To celebrate Primekss’ 20th anniversary in 2017, a very important charity campaign was introduced. The campaign intended to give a donation in the amount equal to the saved CO2 emissions that were achieved by utilising our PrīmXComposite technology during 2017. Primekss’ goal for the year 2017 was to install 1,000,000 m2 of PrīmXComposite structures. During 2017, 812,690 m2 of PrīmXComposite floors and other concrete structures was installed. It resulted in saving 18,285,525 kg of CO2. In comparison, a passenger vehicle emits 94 gr/km on average. The distance around the globe is about 40,000 km. So it is possible to go around the world 5,984 times by car, emitting the same amount of CO2 that we will save with our unique technology. allows saving tons of Carbon Dioxide
  • 12. 12 Edges of cracks deteriorate and, in many cases, debris separated from the concrete becomes a grinding agent and further supports the floor abrasion process. The floor is no longer resistant to liquid penetration and is more prone to further damage: concrete deterioration, possible steel reinforcement corrosion, joint chipping etc. Curling is caused by the different drying speed of various material layers. It is a huge problem for material handling units driving in logistics premises. Curled edges near the joints/saw cuts slow down the speed, damage the equipment and are harmful for operators’ health due to vibrations caused by crossing the damaged and uplifted joints. To solve problems caused by shrinkage, traditional concrete floor systems use saw-cut shrinkage control joints every 6 metres and a slip sheet underneath the slab, but they do not eliminate the problems. Some more advanced systems without steel reinforcement have solutions where joints are extended to 30-50 metres. However, this is not a solution but an ongoing fight with a problem that still remains. Even in these systems, dominant joints develop with a large joint opening and curling still occurs, adding to the cost of maintenance and repair. It should also be remembered that curled joint repairs are not long lasting. The process of curling never stops and repairs will be needed again. The PrimXComposite system addresses the cause of the problem instead of fighting the symptoms. In the case of this system, the shrinkage process is controlled with special anti-shrinkage additives. The additives in PrīmXComposite bind H2O molecules and form a micro-scale composite structure, including crystals, that expand and compress the internal concrete matrix. In this way cracking is absolutely minimised and curling does not occur. Jointless Traditional concrete shrinks during the curing process. As a result, it forms cracks and curls at the slab edges. Both phenomena raise meaningful problems for further slab application. Cracking progresses with time due to ongoing shrinkage, wheel impacts and other factors. Unlimited size Jointless slabs
  • 13. 13 The solving of shrinkage-induced issues allows the use of PrīmXComposite for a practically unlimited size field casting, without the need for saw cutting or placing joints. The PrīmXComposite system uses steel fibre reinforcement that allows us to create ductile, seamless concrete that is so strong it does not need traditional steel bar reinforcement as a primary reinforcement. Due to the properties of the material we can optimise traditional floor designs significantly reducing the slab thickness. Combined with the increased speed of construction, predictable, high-quality end result (flat, precise structures that stay flat), the ability to ensure efficient gas and watertight solutions and environment- friendly construction (saved CO2 emissions), makes PrīmXComposite the best solution for industrial concrete floors and many other concrete structures. WATCH HERE Jointless concrete slabs on ground (full product description on website) Jointless concrete slabs on piles (full product description on website)
  • 14. 14 Traditional concrete shrinks due to the drying process and forms cracks. Due to uncontrolled cracking, concrete is not waterproof. Water penetrates the concrete structure, resulting in different problems including erosion, reinforcement corrosion etc. To prevent the penetration of water indoors for foundations and other structures exposed to water, waterproofing membranes are often used. Membranes work as a barrier between the water and concrete structure. The traditional concrete system solves the problem rather than addressing the cause. The PrimXComposite system addresses the cause rather than solving the problem. In the case of this system, the shrinkage process is controlled with special anti-shrinkage additives. The additives in PrīmXComposite bind H2O molecules and form a micro-scale composite structure, including crystals that expand and compress the internal concrete matrix. This expansion puts the steel fibres in tension, creating permanent pre-stress that results in compression of the concrete. Steel fibre integration ensures homogenous reinforcement throughout and has a significant impact on the reduction of crack width as they hold together cracks from the very start of their development. Water-tight From the beginning, the PrīmXComposite system has been designed to address a major drawback with traditional concrete– shrinkage and the problems it causes: slab edge curling, cracking etc. Effective water- tight solutions
  • 15. In this way, the concrete structure is much more homogenous and the absence of cracks allows the material to be used in watertight concrete structures. A watertight concrete structure in turn means huge savings on waterproofing membranes, its installation time and associated costs, including costly groundwater pumping. See the animation where watertight PrīmXComposite concrete is used to install the watertight foundation plate (PrīmXComposite Raft foundation). WATCH HERE