SlideShare a Scribd company logo
1 of 12
Download to read offline
Institute de Technologie du Cambodge Construction Métallique II
KUY Limeng Page 1 of 12 Rev 23/06/2023
Table of Contents
I. Report of construction gas station........................................................................................ 2
1. Foundation .......................................................................................................................... 2
2. Concrete testing .................................................................................................................. 4
3. Beam and floor slab............................................................................................................ 5
4. Column ................................................................................................................................ 5
5. Steel beam............................................................................................................................ 7
II. 3D Model ............................................................................................................................. 9
III. BOM (Bill of Material)..................................................................................................... 10
IV. Conclusion......................................................................................................................... 12
Institute de Technologie du Cambodge Construction Métallique II
KUY Limeng Page 2 of 12 Rev 23/06/2023
Project: Gas station
I. Report of construction gas station
The steel structure is suitable for several types of construction, such as stadiums, bridges,
warehouses, factories, garages, and so on. This is the process of construction of gas station which
its beams are made from steel.
1. Foundation
• Site Preparation
Site preparation is the process of cleaning up a construction site. Site preparation provides
the way for other repair or demolition work needed before the construction of the project can start.
Site cleaning includes the removal of trash, equipment, machinery, and undesired things. Some site
preparation tasks might need your permission. The employees must avoid any trees that were
planted for protection at all costs.
• Excavation
After the area has been cleared, excavation can begin. Excavation is the process of
removing earth in order to dig a hole in the ground. Small sites can utilize wheelbarrows, shovels,
and picks to perform manual excavation. However, deep excavations demand the utilization of
heavy equipment machinery.
• Driven piles
First let surveyor point the points which we need to hit piles into the soil. When the piles
come from the factory, we need to check the time which the piles were created to see whether it
has enough strength for construction or not. Mostly the piles which were made in 28 days, have
enough strength.
Figure 1: Date of production Figure 2: Section of pile
Institute de Technologie du Cambodge Construction Métallique II
KUY Limeng Page 3 of 12 Rev 23/06/2023
We can also check strength of concrete by using the tool to test strength of piles (Hammer).
Before we test, we need to polishing the area of piles. This polishing in order to remove the upper
limescale surface is polished until it reaches the concrete surface to make our test good.
After we check the strength, we hit those piles into soil then we dig the soil around the piles
to see the head of those piles are cracked or not. If they are, we need to cut the head part of piles.
• Footing
We have to compact soil to make it strong and to have constancy level then compact rock
until we get thickness 100mm. After we make lean thickness 50mm to avoid water leakage when
pouring concrete.
We put the formwork of footing above the piles to build footing. We prepare the steel for
footing and then put in formwork of footing by left the spacing cover is 50mm after that prepare
the steel for column then pure the concrete into the formwork but before we pour the concrete, we
need to test slum concrete. The steel column we should left it perhaps 40D, D is the diameter of
the steel.
Figure 3: utilization of Hammer
Institute de Technologie du Cambodge Construction Métallique II
KUY Limeng Page 4 of 12 Rev 23/06/2023
2. Concrete testing
• Slum testing
Before pouring the concrete, we must test it to find the slum. The slum test is a test
performed on fresh cement concrete to determine the workability of fresh concrete. Slum
depends on the amount of mixing water used. In general, the higher the slum value, the
higher the workability of fresh concrete. Testing process is as follows:
− A steel slump cone is placed on a solid, impermeable and flat base
− Filled with fresh concrete in cone as three equal layers
− Each layer is raked 25 times while holding the cone, to ensure compaction
− The cone should be lifted carefully, leaving a pile of concrete that settles or sags
slightly and sagging can take several forms.
− For a subsidence to be acceptable, the concrete must simply collapse, while keeping
more or less the shape of the cone.
− We then measure the length of the cone at the end of the concrete.
− The acceptable length h is (12±2.5) cm
Figure 4: Concrete slum test
Institute de Technologie du Cambodge Construction Métallique II
KUY Limeng Page 5 of 12 Rev 23/06/2023
• Compressive test
We test the compression concrete by putting it on a cube and then taking it to the
laboratory.
3. Beam and floor slab
After pouring the concrete, footing and piles. They must fill the soil and let topography put
the slab level. We have to make lean then prepare steel to manufacture belt beams. Fill the soil
at belt beams level and put plastic bags (we use it instead of lean). We prepare steel by
connecting with the steel we have embedded in belt beam and pour concrete to build slab on
the ground. We prepare of the steel slab by take the cross section and spacing of the steel
according to the plan we have. For floor slab we first pour the concrete into beams, then we
pour the concrete into slabs later. But for beams and slabs from the first floor to the top floor,
concrete can be poured together. Then let topography find the perpendicular of the column for
easy to prepare the pole formwork.
4. Column
To build a column, you need to find the length of steel that will be connected to the steel
we embedded. The length of steel to be cut for the column is equal to the level of the upper slab
minus the level of the lower slab plus the length of steel to be embedded for the other floor
(40D is the diameter of the steel).
Then we connect the cut steel with the steel we embedded and we also have steel stirrup.
We put steel stirrup in the pole to avoid tearing the formwork of the column and buckling of
the column, etc. We prepare the formwork of the column and then pour the concrete. Let left
for 1 day before you can remove the formwork from the column because the column has not
been subjected to slab compression (slab not yet built). But for slab, we cannot remove the slab
formwork in 1 day. We leave it 28 days to remove it, because the slab supports its own weight.
Figure 5: Cube for compression test
Institute de Technologie du Cambodge Construction Métallique II
KUY Limeng Page 6 of 12 Rev 23/06/2023
If during construction have problems like the image below occur:
Figure 7 Figure 8
Figure 7 show that the steel in the column is at the edge of the section, so we have to bend
steel in the shape of the neck of the bottle in the section because when we prepare a column
formwork, there will be a gap between the steel and the formwork of column so that sand and
gravel can flow into this space.
Figure 8 show that the column has been enlarged section so we have to bend some of the
steel shaped like the neck of the bottle.
Figure 6: formwork of column sample
Institute de Technologie du Cambodge Construction Métallique II
KUY Limeng Page 7 of 12 Rev 23/06/2023
Another problem that can also occur is when we remove the formwork from the column.
The column may have shrinkage effect as shown below:
Figure 9: The shrinkage of the column Figure 10: Column repair using Sika
If the column has a shrinkage greater than 20%, we have to destroy it and rebuild it. But if it
has a shrinkage of less than 20%, we can use Sika grout instead.
5. Steel beam
• Types of Connections
1. Column to beam connection:
This type of connection is used with anchor bolt at column head and beam joint. Inserting
anchor bolt in concrete before casting the concrete and steel plate in middle to connect with
these two elements.
2. Beam to beam connection or beam splice:
This kind of connection is located in the beam to splice between one beam to another
beam. Combination of two beam steel, one at top and one at bottom and one plate on each
side. We use bolts to connect them together.
3. Main beam to secondary beam connection
When secondary beam connected to the main beam, we are using one side of plate
connect to main beam connect together by bolt and on the other side that connect to
secondary beam is used by welding.
Institute de Technologie du Cambodge Construction Métallique II
KUY Limeng Page 8 of 12 Rev 23/06/2023
When the columns are built, we lift the main steel beam to connect with column by using
joint such as bolt or welds, etc.
After that we connect other beam with the main beam by using bolt or welds
If the length of beam that we need is too long, we can also joint two beams to make one.
The length of beam maximum is 3m to 9m
Figure 12: Connection main beam to beam by using bolt
Figure 11: Connection column to main beam by using bolt
Institute de Technologie du Cambodge Construction Métallique II
KUY Limeng Page 9 of 12 Rev 23/06/2023
II.3D Model
Figure 12: Connection beam to beam by using bolt
Figure 13: 3D Model
Institute de Technologie du Cambodge Construction Métallique II
KUY Limeng Page 10 of 12 Rev 23/06/2023
1 H250x125x6x9 4 174.1287 6000
2 H250x125x6x9 2 348.2574 12000
3 H250x125x6x9 3 203.1502 7000
4 PL 30x250x400 13
5 M24-8.8 20
other
No. Type of material Quantity Mass [kg] Length [mm]
III. BOM (Bill of Material)
We have BOM of Steel and Reinforce Concrete
Figure 15: Bolt and Connection
Figure 14: Footing and Steel Beam
Figure 16: BOM of Steel
Institute de Technologie du Cambodge Construction Métallique II
KUY Limeng Page 11 of 12 Rev 23/06/2023
1
Pile
300x300
6
-2.1
2
P2
DB16@150
(Long
direction)
16
11
1902
20921
1205
-1.6
TOP
REBAR
3
P2
DB16@150
(Short
direction)
16
4
3322
13290
2105
-1.6
TOP
REBAR
4
P2
DB16@150
(Short
direction)
16
11
1799
19792
1140
-1.6
BOTTOM
REBAR
5
P2
DB16@150
(Short
direction)
16
4
3220
12879
2040
-1.6
BOTTOM
REBAR
6
P2
DB16@150
(Long
direction)
16
11
789
8681
500
-1.6
TOP
MAIN
REBAR
7
P2
DB16@150
(Short
direction)
16
4
2210
8839
1400
-1.6
TOP
MAIN
REBAR
8
P2
DB16@150
(Short
direction)
16
11
789
8681
500
-1.6
BOTTOM
MAIN
REBAR
9
P2
DB16@150
(Short
direction)
16
4
2210
8839
1400
-1.6
BOTTOM
MAIN
REBAR
10
P2
DB12@150
(Long
direction)
12
4
1243
4972
1400
-1.6
SIDE
REBAR
11
P2
DB12@150
(Short
direction)
12
4
444
1776
500
-1.6
SIDE
REBAR
12
C(300x500)
14DB16
16
14
10212
142966
6470
-0.5
13
C(300x500)
DB10@150
10
35
916
32045
1485
-0.5
14
B(300x500)
DB16
(TOP
BAR)
16
5
26327
131633
16680
-0.5
15
B(300x500)
DB16
(BOTTOM
BAR)
16
3
26327
78980
16680
-0.5
16
B(300x500)
DB10
(SIDE
BAR)
12
2
14383
28765
16200
-0.5
17
B(300x500)
DB10@200
(STIRRUP)
10
78
191
14908
310
-0.5
18
B(300x500)
DB16
(SUPPORT)
16
2
3733
7466
2365
-0.5
19
B(300x500)
DB16
(MIDSPAN)
16
1
8586
8586
5440
-0.5
20
B(300x500)
DB16
(MIDSPAN)
16
2
9107
18214
5770
-0.5
21
C(300x400)
14DB16
(MAIN
BAR)
16
14
10212
142966
6470
+5.2
22
C(300x400)
DB10@150
16
35
2344
82034
1485
+5.2
23
Formwork
for
footing
18.6
m
2
24
Formwork
for
ground
beam
300x500
25.6
m
2
25
Formwork
for
ground
slab
490.2
m
2
THk.150
26
Formwork
for
beams
25.6
m
2
27
Formwork
for
columns
23.32
m
2
0.165
1.155
0.6228
0.45
No.
Type
of
material
other
Length
[mm]
Mass
[kg]
Location
Level
[m]
Quantity
Concrete
[m
3
]
Diameter
Total
mass
Figure
17:
BOM
of
RC
Institute de Technologie du Cambodge Construction Métallique II
KUY Limeng Page 12 of 12 Rev 23/06/2023
IV. Conclusion
The structural of Gas station is a composite steel. There is section area of steel such as IPE
or IHE steel in the super-structure and pile cap concrete in the sub-structure. The connection is the
most important in design structure.

More Related Content

Similar to KUY Limeng,e20190482(I4GCI-B)_4.pdf

Sem 1 degree ct assignment 1
Sem 1 degree ct assignment 1Sem 1 degree ct assignment 1
Sem 1 degree ct assignment 1Parham Farhadpoor
 
Mat foundation
Mat foundationMat foundation
Mat foundationshuvo293
 
IRJET - Analysis and Design of Steel Box Girder Bridge using Tekla Structures
IRJET - Analysis and Design of Steel Box Girder Bridge using Tekla StructuresIRJET - Analysis and Design of Steel Box Girder Bridge using Tekla Structures
IRJET - Analysis and Design of Steel Box Girder Bridge using Tekla StructuresIRJET Journal
 
Lecture 3-Composites construction (1).pptx
Lecture 3-Composites construction (1).pptxLecture 3-Composites construction (1).pptx
Lecture 3-Composites construction (1).pptxanik7nziza
 
Case study: Widening an existing bridge structure Challenges and solutions
Case study: Widening an existing bridge structure Challenges and solutionsCase study: Widening an existing bridge structure Challenges and solutions
Case study: Widening an existing bridge structure Challenges and solutionsIRJET Journal
 
RCSDD_PPT editing format.pdf
RCSDD_PPT editing format.pdfRCSDD_PPT editing format.pdf
RCSDD_PPT editing format.pdfUMESHVerma100
 
Site report assignment
Site report assignmentSite report assignment
Site report assignmentSze Ting Kuek
 
Details of RCC Building
Details of RCC BuildingDetails of RCC Building
Details of RCC Buildingppt_master
 
INTERNSHIP PPT.pptx
INTERNSHIP PPT.pptxINTERNSHIP PPT.pptx
INTERNSHIP PPT.pptxHumnaTolina
 
Site visit report 2017
Site visit report 2017Site visit report 2017
Site visit report 2017bee_by
 
Prestressed Concrete Bridge.pptx
Prestressed Concrete Bridge.pptxPrestressed Concrete Bridge.pptx
Prestressed Concrete Bridge.pptxRajeshKumar25548
 
Silo at narrow space
Silo at narrow spaceSilo at narrow space
Silo at narrow spacechandra manik
 
Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...
Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...
Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...Hossam Shafiq II
 
Ce1302 design of rc elements
Ce1302 design of rc elementsCe1302 design of rc elements
Ce1302 design of rc elementsPriyabrata Behera
 
Industrialised Building System
Industrialised Building SystemIndustrialised Building System
Industrialised Building Systemjisunfoo
 
IRJET- Study and Buckling Analysis of Concrete Filled Steel Tubes Columns usi...
IRJET- Study and Buckling Analysis of Concrete Filled Steel Tubes Columns usi...IRJET- Study and Buckling Analysis of Concrete Filled Steel Tubes Columns usi...
IRJET- Study and Buckling Analysis of Concrete Filled Steel Tubes Columns usi...IRJET Journal
 

Similar to KUY Limeng,e20190482(I4GCI-B)_4.pdf (20)

Cast in situ Pile
Cast in situ PileCast in situ Pile
Cast in situ Pile
 
Sem 1 degree ct assignment 1
Sem 1 degree ct assignment 1Sem 1 degree ct assignment 1
Sem 1 degree ct assignment 1
 
Mat foundation
Mat foundationMat foundation
Mat foundation
 
kuku.pptx
kuku.pptxkuku.pptx
kuku.pptx
 
IRJET - Analysis and Design of Steel Box Girder Bridge using Tekla Structures
IRJET - Analysis and Design of Steel Box Girder Bridge using Tekla StructuresIRJET - Analysis and Design of Steel Box Girder Bridge using Tekla Structures
IRJET - Analysis and Design of Steel Box Girder Bridge using Tekla Structures
 
Lecture 3-Composites construction (1).pptx
Lecture 3-Composites construction (1).pptxLecture 3-Composites construction (1).pptx
Lecture 3-Composites construction (1).pptx
 
Case study: Widening an existing bridge structure Challenges and solutions
Case study: Widening an existing bridge structure Challenges and solutionsCase study: Widening an existing bridge structure Challenges and solutions
Case study: Widening an existing bridge structure Challenges and solutions
 
Railway over bridge
Railway over bridgeRailway over bridge
Railway over bridge
 
RCSDD_PPT editing format.pdf
RCSDD_PPT editing format.pdfRCSDD_PPT editing format.pdf
RCSDD_PPT editing format.pdf
 
Site report assignment
Site report assignmentSite report assignment
Site report assignment
 
Details of RCC Building
Details of RCC BuildingDetails of RCC Building
Details of RCC Building
 
INTERNSHIP PPT.pptx
INTERNSHIP PPT.pptxINTERNSHIP PPT.pptx
INTERNSHIP PPT.pptx
 
Site visit report 2017
Site visit report 2017Site visit report 2017
Site visit report 2017
 
Prestressed Concrete Bridge.pptx
Prestressed Concrete Bridge.pptxPrestressed Concrete Bridge.pptx
Prestressed Concrete Bridge.pptx
 
Silo at narrow space
Silo at narrow spaceSilo at narrow space
Silo at narrow space
 
Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...
Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...
Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...
 
Ce1302 design of rc elements
Ce1302 design of rc elementsCe1302 design of rc elements
Ce1302 design of rc elements
 
Industrialised Building System
Industrialised Building SystemIndustrialised Building System
Industrialised Building System
 
IRJET- Study and Buckling Analysis of Concrete Filled Steel Tubes Columns usi...
IRJET- Study and Buckling Analysis of Concrete Filled Steel Tubes Columns usi...IRJET- Study and Buckling Analysis of Concrete Filled Steel Tubes Columns usi...
IRJET- Study and Buckling Analysis of Concrete Filled Steel Tubes Columns usi...
 
Microtunel Construction / Secant Pile
Microtunel Construction / Secant PileMicrotunel Construction / Secant Pile
Microtunel Construction / Secant Pile
 

More from Institute of Technology of Cambodia (6)

KUY Limeng,e20190482(I4GCI-B).pdf
KUY Limeng,e20190482(I4GCI-B).pdfKUY Limeng,e20190482(I4GCI-B).pdf
KUY Limeng,e20190482(I4GCI-B).pdf
 
KUY Limeng,e20190482(I4GCI-B).pdf
KUY Limeng,e20190482(I4GCI-B).pdfKUY Limeng,e20190482(I4GCI-B).pdf
KUY Limeng,e20190482(I4GCI-B).pdf
 
Poster v1.pdf
Poster v1.pdfPoster v1.pdf
Poster v1.pdf
 
KUY Limeng(e20190482)_Group B.pptx
KUY Limeng(e20190482)_Group B.pptxKUY Limeng(e20190482)_Group B.pptx
KUY Limeng(e20190482)_Group B.pptx
 
KUY Limeng(e20190482)_Group B.pdf
KUY Limeng(e20190482)_Group B.pdfKUY Limeng(e20190482)_Group B.pdf
KUY Limeng(e20190482)_Group B.pdf
 
Active&Passive Past Simple.pptx
Active&Passive Past Simple.pptxActive&Passive Past Simple.pptx
Active&Passive Past Simple.pptx
 

Recently uploaded

HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacingjaychoudhary37
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 

Recently uploaded (20)

HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacing
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 

KUY Limeng,e20190482(I4GCI-B)_4.pdf

  • 1. Institute de Technologie du Cambodge Construction Métallique II KUY Limeng Page 1 of 12 Rev 23/06/2023 Table of Contents I. Report of construction gas station........................................................................................ 2 1. Foundation .......................................................................................................................... 2 2. Concrete testing .................................................................................................................. 4 3. Beam and floor slab............................................................................................................ 5 4. Column ................................................................................................................................ 5 5. Steel beam............................................................................................................................ 7 II. 3D Model ............................................................................................................................. 9 III. BOM (Bill of Material)..................................................................................................... 10 IV. Conclusion......................................................................................................................... 12
  • 2. Institute de Technologie du Cambodge Construction Métallique II KUY Limeng Page 2 of 12 Rev 23/06/2023 Project: Gas station I. Report of construction gas station The steel structure is suitable for several types of construction, such as stadiums, bridges, warehouses, factories, garages, and so on. This is the process of construction of gas station which its beams are made from steel. 1. Foundation • Site Preparation Site preparation is the process of cleaning up a construction site. Site preparation provides the way for other repair or demolition work needed before the construction of the project can start. Site cleaning includes the removal of trash, equipment, machinery, and undesired things. Some site preparation tasks might need your permission. The employees must avoid any trees that were planted for protection at all costs. • Excavation After the area has been cleared, excavation can begin. Excavation is the process of removing earth in order to dig a hole in the ground. Small sites can utilize wheelbarrows, shovels, and picks to perform manual excavation. However, deep excavations demand the utilization of heavy equipment machinery. • Driven piles First let surveyor point the points which we need to hit piles into the soil. When the piles come from the factory, we need to check the time which the piles were created to see whether it has enough strength for construction or not. Mostly the piles which were made in 28 days, have enough strength. Figure 1: Date of production Figure 2: Section of pile
  • 3. Institute de Technologie du Cambodge Construction Métallique II KUY Limeng Page 3 of 12 Rev 23/06/2023 We can also check strength of concrete by using the tool to test strength of piles (Hammer). Before we test, we need to polishing the area of piles. This polishing in order to remove the upper limescale surface is polished until it reaches the concrete surface to make our test good. After we check the strength, we hit those piles into soil then we dig the soil around the piles to see the head of those piles are cracked or not. If they are, we need to cut the head part of piles. • Footing We have to compact soil to make it strong and to have constancy level then compact rock until we get thickness 100mm. After we make lean thickness 50mm to avoid water leakage when pouring concrete. We put the formwork of footing above the piles to build footing. We prepare the steel for footing and then put in formwork of footing by left the spacing cover is 50mm after that prepare the steel for column then pure the concrete into the formwork but before we pour the concrete, we need to test slum concrete. The steel column we should left it perhaps 40D, D is the diameter of the steel. Figure 3: utilization of Hammer
  • 4. Institute de Technologie du Cambodge Construction Métallique II KUY Limeng Page 4 of 12 Rev 23/06/2023 2. Concrete testing • Slum testing Before pouring the concrete, we must test it to find the slum. The slum test is a test performed on fresh cement concrete to determine the workability of fresh concrete. Slum depends on the amount of mixing water used. In general, the higher the slum value, the higher the workability of fresh concrete. Testing process is as follows: − A steel slump cone is placed on a solid, impermeable and flat base − Filled with fresh concrete in cone as three equal layers − Each layer is raked 25 times while holding the cone, to ensure compaction − The cone should be lifted carefully, leaving a pile of concrete that settles or sags slightly and sagging can take several forms. − For a subsidence to be acceptable, the concrete must simply collapse, while keeping more or less the shape of the cone. − We then measure the length of the cone at the end of the concrete. − The acceptable length h is (12±2.5) cm Figure 4: Concrete slum test
  • 5. Institute de Technologie du Cambodge Construction Métallique II KUY Limeng Page 5 of 12 Rev 23/06/2023 • Compressive test We test the compression concrete by putting it on a cube and then taking it to the laboratory. 3. Beam and floor slab After pouring the concrete, footing and piles. They must fill the soil and let topography put the slab level. We have to make lean then prepare steel to manufacture belt beams. Fill the soil at belt beams level and put plastic bags (we use it instead of lean). We prepare steel by connecting with the steel we have embedded in belt beam and pour concrete to build slab on the ground. We prepare of the steel slab by take the cross section and spacing of the steel according to the plan we have. For floor slab we first pour the concrete into beams, then we pour the concrete into slabs later. But for beams and slabs from the first floor to the top floor, concrete can be poured together. Then let topography find the perpendicular of the column for easy to prepare the pole formwork. 4. Column To build a column, you need to find the length of steel that will be connected to the steel we embedded. The length of steel to be cut for the column is equal to the level of the upper slab minus the level of the lower slab plus the length of steel to be embedded for the other floor (40D is the diameter of the steel). Then we connect the cut steel with the steel we embedded and we also have steel stirrup. We put steel stirrup in the pole to avoid tearing the formwork of the column and buckling of the column, etc. We prepare the formwork of the column and then pour the concrete. Let left for 1 day before you can remove the formwork from the column because the column has not been subjected to slab compression (slab not yet built). But for slab, we cannot remove the slab formwork in 1 day. We leave it 28 days to remove it, because the slab supports its own weight. Figure 5: Cube for compression test
  • 6. Institute de Technologie du Cambodge Construction Métallique II KUY Limeng Page 6 of 12 Rev 23/06/2023 If during construction have problems like the image below occur: Figure 7 Figure 8 Figure 7 show that the steel in the column is at the edge of the section, so we have to bend steel in the shape of the neck of the bottle in the section because when we prepare a column formwork, there will be a gap between the steel and the formwork of column so that sand and gravel can flow into this space. Figure 8 show that the column has been enlarged section so we have to bend some of the steel shaped like the neck of the bottle. Figure 6: formwork of column sample
  • 7. Institute de Technologie du Cambodge Construction Métallique II KUY Limeng Page 7 of 12 Rev 23/06/2023 Another problem that can also occur is when we remove the formwork from the column. The column may have shrinkage effect as shown below: Figure 9: The shrinkage of the column Figure 10: Column repair using Sika If the column has a shrinkage greater than 20%, we have to destroy it and rebuild it. But if it has a shrinkage of less than 20%, we can use Sika grout instead. 5. Steel beam • Types of Connections 1. Column to beam connection: This type of connection is used with anchor bolt at column head and beam joint. Inserting anchor bolt in concrete before casting the concrete and steel plate in middle to connect with these two elements. 2. Beam to beam connection or beam splice: This kind of connection is located in the beam to splice between one beam to another beam. Combination of two beam steel, one at top and one at bottom and one plate on each side. We use bolts to connect them together. 3. Main beam to secondary beam connection When secondary beam connected to the main beam, we are using one side of plate connect to main beam connect together by bolt and on the other side that connect to secondary beam is used by welding.
  • 8. Institute de Technologie du Cambodge Construction Métallique II KUY Limeng Page 8 of 12 Rev 23/06/2023 When the columns are built, we lift the main steel beam to connect with column by using joint such as bolt or welds, etc. After that we connect other beam with the main beam by using bolt or welds If the length of beam that we need is too long, we can also joint two beams to make one. The length of beam maximum is 3m to 9m Figure 12: Connection main beam to beam by using bolt Figure 11: Connection column to main beam by using bolt
  • 9. Institute de Technologie du Cambodge Construction Métallique II KUY Limeng Page 9 of 12 Rev 23/06/2023 II.3D Model Figure 12: Connection beam to beam by using bolt Figure 13: 3D Model
  • 10. Institute de Technologie du Cambodge Construction Métallique II KUY Limeng Page 10 of 12 Rev 23/06/2023 1 H250x125x6x9 4 174.1287 6000 2 H250x125x6x9 2 348.2574 12000 3 H250x125x6x9 3 203.1502 7000 4 PL 30x250x400 13 5 M24-8.8 20 other No. Type of material Quantity Mass [kg] Length [mm] III. BOM (Bill of Material) We have BOM of Steel and Reinforce Concrete Figure 15: Bolt and Connection Figure 14: Footing and Steel Beam Figure 16: BOM of Steel
  • 11. Institute de Technologie du Cambodge Construction Métallique II KUY Limeng Page 11 of 12 Rev 23/06/2023 1 Pile 300x300 6 -2.1 2 P2 DB16@150 (Long direction) 16 11 1902 20921 1205 -1.6 TOP REBAR 3 P2 DB16@150 (Short direction) 16 4 3322 13290 2105 -1.6 TOP REBAR 4 P2 DB16@150 (Short direction) 16 11 1799 19792 1140 -1.6 BOTTOM REBAR 5 P2 DB16@150 (Short direction) 16 4 3220 12879 2040 -1.6 BOTTOM REBAR 6 P2 DB16@150 (Long direction) 16 11 789 8681 500 -1.6 TOP MAIN REBAR 7 P2 DB16@150 (Short direction) 16 4 2210 8839 1400 -1.6 TOP MAIN REBAR 8 P2 DB16@150 (Short direction) 16 11 789 8681 500 -1.6 BOTTOM MAIN REBAR 9 P2 DB16@150 (Short direction) 16 4 2210 8839 1400 -1.6 BOTTOM MAIN REBAR 10 P2 DB12@150 (Long direction) 12 4 1243 4972 1400 -1.6 SIDE REBAR 11 P2 DB12@150 (Short direction) 12 4 444 1776 500 -1.6 SIDE REBAR 12 C(300x500) 14DB16 16 14 10212 142966 6470 -0.5 13 C(300x500) DB10@150 10 35 916 32045 1485 -0.5 14 B(300x500) DB16 (TOP BAR) 16 5 26327 131633 16680 -0.5 15 B(300x500) DB16 (BOTTOM BAR) 16 3 26327 78980 16680 -0.5 16 B(300x500) DB10 (SIDE BAR) 12 2 14383 28765 16200 -0.5 17 B(300x500) DB10@200 (STIRRUP) 10 78 191 14908 310 -0.5 18 B(300x500) DB16 (SUPPORT) 16 2 3733 7466 2365 -0.5 19 B(300x500) DB16 (MIDSPAN) 16 1 8586 8586 5440 -0.5 20 B(300x500) DB16 (MIDSPAN) 16 2 9107 18214 5770 -0.5 21 C(300x400) 14DB16 (MAIN BAR) 16 14 10212 142966 6470 +5.2 22 C(300x400) DB10@150 16 35 2344 82034 1485 +5.2 23 Formwork for footing 18.6 m 2 24 Formwork for ground beam 300x500 25.6 m 2 25 Formwork for ground slab 490.2 m 2 THk.150 26 Formwork for beams 25.6 m 2 27 Formwork for columns 23.32 m 2 0.165 1.155 0.6228 0.45 No. Type of material other Length [mm] Mass [kg] Location Level [m] Quantity Concrete [m 3 ] Diameter Total mass Figure 17: BOM of RC
  • 12. Institute de Technologie du Cambodge Construction Métallique II KUY Limeng Page 12 of 12 Rev 23/06/2023 IV. Conclusion The structural of Gas station is a composite steel. There is section area of steel such as IPE or IHE steel in the super-structure and pile cap concrete in the sub-structure. The connection is the most important in design structure.