ELEMENTAL COST ANALYSIS - Form 3 8 - Residential Buildings
A - 24 - 16439
BRIEF SPECIFICATION
Gross Floor Area : 16,422 M2 Tender date : 9th June 2011
ELEMENT SPECIFICATION
1 Substructure
1A Piling separate contract.
1B Work Below Lowest Floor Finishes separate building.
2 Superstructure
2A Frame
2B Upper Floor In-situ reinforced concret suspended slabs.
2C Roof
2D Stairs
2E External Walls
2F Windows & External Doors Proprietary fire doors
2G Internal Walls & Partitions 150mm thick common clay brickwall.
2H Internals Doors
3 Finishes
3A Internal Wall Finishes
3B Internal Floor Finishes
3C Internal Ceiling Finishes
3D External Finishes
4 Fittings and Furnishings
5 Services
5A Sanitary appliances
5B Plumbing Installation
5C Refuse Disposal Nil
5D
5E Electrical Installation
5F Fire Protection Installation
5G Lift & Conveyor Installation Lift installation (Prime Cost Sum of RM 257,796.00)
5H Communication Installation SMATV system (Prime Cost Sum of RM 39,157.65)
5J Special Installation
5K Builder's Profit & Attendance on
Services
5L Builder's Work in Connection
with Services
6 External Works
6A Site Works
6B Drainage
6C External Services Water storage and reticulation system
6D Ancillary Buildings TNB substation and guard house.
6E Recreational Facilities
Cold water, sanitary and hot water plumbing installation to relevant Malaysian and British standards.
In-situ reinforced concrete isolated columns, walls, lift walls, shear walls, floor beams and roof beams.
In-situ reinforced concrete flat roof slab with waterproofing; roof drainage, rainwater downpipe, siphonic roof outlet,
anti-backflow fittings, and UPVC pressure pipes.
In-situ reinforced concrete staircase with cement and sand pavings and ceramic nosing tiles; cement skim coat to
other parts of stairs; mild steel handrail and balustrades.
150mm and 200mm thick common clay brickwall for walls and panels; in-situ reinforced concrete parapet walls;
curtain walling, aluminium and glazing works (PC Sum of RM 2,962,688.53 which includes aluminium and glazing
for windows element)
Generally cement skim coat and cement and sand plaster to walls and columns. Polished homogeneous tiles,
porcelain tiles and painting to internal wall.
Air-Conditioning & Ventilation
System
Electrical and telephone distribution system (Prime Cost Sum of RM 1,674,067.50 which includes the cost from the
communication installation element)
Fire protection services (Prime Cost Sum of RM 381,937), Alarm and CMS system (Prime Cost Sum of RM 139,860)
Cement and sand pavings, pebble washed flooring, block, parquet and strip flooring, porcelain and homogeneous
tiles,and carpet.
Generally cement skim coat and painting and fibrous plaster boards to internal ceiling.
Cement skim coat, cement and sand plaster and painting works (PC Sum of RM3852200.00) to external walls,
columns, ceilings and floor finish
Reinforced in-situ concrete and marble counter tops to wash basin and silvered float glass mirrors; Signage (PC
Sum of RM42665.18) and Indoor Facilities of (PC Sum of RM146164.73)
WC, accessories comprising of floor traps, PVC bottle traps, stopcock, , vanity basin, wash basin, kitchen sink, taps,
shower fittings, bidet, tub, soap holder and toilet roll holder.
Swimming Pool Equipment (Prime Cost Sum of RM 128,157.75). Tennis court (Provisional sum of RM21,262.50).
Sandy Beach (Provisional sum of RM 171.360)
Generally honeycomb flush door; fire-rated doors.
Electronic keycard system (Prime Cost Sum of RM 58,297.05) , CCTV system (Prime Cost Sum of RM 26,375),
Intercom (Prime Cost Sum of RM 32,224.50)
Builder's profit and allowance of 3% to all Prime Cost Sums of RM 83,515.75)
Builder's works in connection with mechanical and electrical services (Prime Cost Sum of RM 102,847.50)
Excavate, fillings, kerbs, road signages, external painting and guard rails. Hard landscaping works (PC Sum of RM
606,559). Soft landscaping works (PC Sum of RM 346,837.05). Anti-termite treatment (PC Sum of 20,440.35).
Security gate and fencing (Provisional Sum of RM 43,627.50). External concrete features (Provisional Sum of
RM179,550). Cribwall landscaping works (Provisional Sum of RM 47,250)
Primary stormwater drainage system, sewerage system and primary soil drainage system
Air-conditioning and mechanical ventilation installation (PC Sum of RM 1,052,100)