2. A.L.D.
PROJECT MANAGER
ISSAM M. AL FAQIR
2
1. LIAISING WITH DIFFERENT GOVERNMENT AUTHORITIES FOR
VARIOUS MATTERS SUCH AS PROJECT INSURANCE POLICIES,
BUILDING PERMITS, NOCS, DEMARCATIONS, FINAL SURVEY
CERTIFICATES, APPROVALS ETC.
2. DEALING WITH ALL SECURITY MATTERS OF THE DIVISION,
ARRANGING/DEALING/CONTROLLING ACCOMMODATION AND
TRANSPORTATION ISSUES AND MATTERS
3. RECRUITING/HIRING STAFF/MANPOWER AS PER THE
PROJECTS REQUIREMENT IN COORDINATION WITH HEAD
OFFICE.
3. 3
4. PROJECT-WISE DAILY/WEEKLY AND MONTHLY
RECORDING/UPDATING OF TOTAL MANPOWER AND
CALCULATION OF TOTAL MAN-HOURS/TOTAL WAGES/TOTAL
OVERTIME AND KEEPING PERCENTAGEWISE RECORDS OF THE
SAME FOR THE COST CONTROL PURPOSE.
5. OVERALL CONTROL OF ADMINISTRATION AND HR MATTERS
OF THE ALD1 PROJECTS/DEPARTMENT AND OFFICES AND
WELLBEING OF STAFF AND LABOURS
6. ARRANGING WORK PERMIT CARDS/EMIRATES ID CARDS/
INSURANCE CARDS/VISA RENEWALS/VISA MEDICALS FOR ALL
THE EMPLOYEES IN COORDINATION WITH HEAD OFFICE.
4. QA/QC OFFICE
4. INSPECTION & TESTING OF MATERIALS AS
PER ITP
2. PREPARATION OF METHOD STATEMENT & ITP
SCHEDULE
3. METHOD STATEMENT & ITP PREPARATION AS
PER SCHEDULE
PROJECT LEVEL QA/QC PROGRAMME
1. PREPARATION OF PROJECT SPECIFIC QUALITY
PLAN
4
5. 8. ISSUE SITE OBSERVATION REPORT/ NON-
CONFORMANCE REPORT FOR NON-COMPLIANCE
OF WORK DURING EXECUTION (IF ANY)
9. PERIODIC INTERNAL AUDIT AS PER
INTERGATED MANAGEMENT SYSTEM
6. QA/QC VERIFICATION OF WORKS AS PER
QUALITY CONTROL CHECKLIST
7. SITE INSPECTION REQUEST SUBMISSION TO
CONSULTANT FOR INSPECTION & APPROVAL
PROJECT LEVEL QA/QC PROGRAMME
5. WORK START NOTIFICATION PRIOR TO
COMMENCEMENT OF EACH ACTIVITY
5
6. 13. HANDING OVER
12. PREPARE & SUBMIT THE CLOSE-OUT
DOCUMENTS
11. CARRY OUT THE SNAGGING & DE-SNAGGING
PROCESS
PROJECT LEVEL QA/QC PROGRAMME
10. CARRY OUT THE TESTING &
COMMISSIONING OF ALL INSTALLED ITEMS
6
7. VILLAS CONSTRUCTION SEQUENCE SUMMERY
(TUNNEL FORM WORKS )
7
First Stage Second Stage Third Stage
Substructure Superstructure Finishing
1
Excavation & Earth
Works
Including leveling and
compaction
1
RCC Columns & Walls Kickers
Kicker: like the column necks
to facilitate tunnel form
installation
1
First Fix for MEP Works
All embedded conduits
and pipes to be installed
in block walls
2
Anti-termite (chemical
spray)
2
Tunnels Forms Installation
Using mobile cranes cranes
2
Wooden Doors Subframes
12mm plywood
3
PCC & Blinding
50mm plain concrete
below foundation
3
RCC Works for Columns,
Walls & Slab (GF, FF, etc.)
3
Plaster Works
Plaster preparation
including rush coat, fiber
mesh, angle beads ..etc.
Then filling by cement
sand plaster
4
RCC Foundation
Reinforced Strip
Foundation
4
Roof Parapet, Staircase &
Miscellaneous RCC Works as
per architectural shop
drawings
4
Roof Waterproofing Works
Getting the slope by foam
concrete then using
membrane system and
polystyrene for heat
insulation and finally
protected by natural
gravel and concrete tiles
8. 8
First Stage Second Stage Third Stage
Substructure Superstructure Finishing
5
Stub Walls
All around the center
line of the strip
foundation to suit the
tunnel design
5
Block Works (Insulation)
50 mm polystyrene is used
between two block walls
(100mm & 200mm)
Total wall thickness is 350
mm
5
Tile & Marble Works
Including floor and wet
area walls and staircase
step and vanities and
kitchen tops
6
Damp Proofing
Bitumen Paint
6
Second Fix MEP (A/C
System, High level
Drainage) especially
above false ceiling
survices
7
Backfilling
(Compaction on
Layers)
Including underground
drainage and MEP
services
7
External Works:
Precast, Boundary Walls,
External Drainage, Paving
& landscaping.
8 Anti-termite 8
False Ceiling Works
Suspension & Gypsum
board installation.
9. 9
First Stage Second Stage Third Stage
Substructure Superstructure Finishing
9
Slab on grade
100mm reinforced
concrete
9
Painting Works
Internal & External
1
0
UPVC & Aluminum Works
Including doors, windows
and railings and other
decorative items
1
1
Doors & Joinery Works
Including wardrobes and
kitchen cabinets, wooden
handrail and pergolas
1
2
MEP Final Fix (Electrical
Accessories, Light
Fittings, Sanitary Wares
…etc.
1
3
Testing & Commissioning
1
4
Snagging & Handing over
Special team for clearance
and preparing the villas
for final handing over to
the end user.