Construction Methodology for the
Infrastructure Project
RUWAIS HOUSING COMPLEX EXPANSION PHASE IV
INFRASTRUCTURE WORKS PROJECT 7010C9
Content :
1. Scope of Work
2. Project Milestones
3. Organization Chart
4. Building Site Phases
5. Villa Site Phases
6. Project WBS
7. Execution Plan for infrastructure network
8. Execution Plan for Structure
9. Company Equipment
10.Company Manpower
Scope
Infrastructure Network for
Accommodation (Building
site ) and Villas site
Building site
Villas site
STP by Other
P6020
DCP by Other
P7010C12
Electrical
Substation by
Other
P7010C8
SLS 3
SLS1A
EP 1
SNG
Water
tanks
Guest House
by Other
Storm water & Drainage Network
Waste Water Network
Water Supply Network with Fire Hydrants
Irrigation Network
Telecom Network
Chilled Water Network
SNG Distribution Network
Low Voltage (LV) Network
11Kv Network (MV Cable)
Street Lighting Network
Soft and Hard Landscape
Roads
Force Main line from SLS3 to STP
Force Main line from SLS1A to STP
Discharge Line between Evaporated
Ponds
Chilled Water Line from exciting DCP to
new Gust House
Force
Main from
SLS1A to
STP
Force
Main from
SLS3 to
STP
Plant and Structure
SNG Plant
Sewer Pump Station SLS3
Sewer Pump Station SLS1A
Water Reservoirs and Pump Station
Electrical Substation 11/.4 kv
Evaporation Pond No. 1
Evaporation Pond No. 2
Evaporation Pond No. 3
Improve existing Evaporation Pond
Guard House 1
Guard House 2
Building site
Villas site
STP by Other
P6020
DCP by Other
P7010C12
Electrical
Substation by
Other
P7010C8
SLS 3
SLS1A
EP 1
SNG
Water
tanks
Guest
House
Project Milestones
Ghantoot Milestones
El Gaber Milestones
El Dabey Milestones
Organization Chart
Phasing for building Site G+5
Phase 1 from building no .
20 to building no. 36 (total
no. is 17)
Finish Millstone is 78 w
Sewer Line up to from
MH 1-1 to MH1-1.12 and
from MH 1-5 to MH 1-1
including line to SLS3
Phase 1 for building site
17 Nos Building (G+5)
Water Line from
water tank up to
isolated valve in
the corner
Storm Water Line from
MH1-3 to MH1-1 and from
MH 1-1 to MH 1-1.12 and
line to EP1
Phase 2 - Remaining building site network
Finish Milstone is 90w
Phase 2 for building site
23 Nos Building (G+5)
Phasing for Villas
Phase 1 for Villas site
350 villas (4 BR)+27 villas(5 BR)
To SLS A1
& EP3
To SLS 2 & EP2
27 Villas 5BR +
245 Villas 4BR
109 4BR Villas
Total =
354 villas 4BR +27 Villas 5BR
North Hill not including in Phase 1
Water Line connecting with water
tank feed phase 1 area
Sewer and
Storm lines in
this road to be
included in
phase 1
(road length ≈450m)
Sewer and Storm lines in this road
to be included in phase 1
(road length ≈475m)
Phase 2 for Villas site
214 villas (4 BR)+72 villas(5 BR)
211 4BR Villas
72 VIP Villas 5BR
North and south Hills including in
Phase 2
Phase 1 & 2 Villas site and related
utilities
Project work breakdown
structure
Project Wide
Package 1 Package 2 (building)Site) Package 3 (Villa Site)
UTILIY Compound
MM(EF after 58w)
(Eng. & Con & test)
Phase 1 (17 no.
(G+5) building )
KM(EF after
78w)
(Eng. & Con &
test)
Phase 2 (23 no.
(G+5) building )
MM(EF after 90w)
(Eng. & Con & test)
Phase 1 (377
villas)
KM(EF after 78w)
(Eng. & Con &
test)
Phase 2 (286
villas)
KM(EF after
88w)
(Eng. & Con &
test)
Project Start Earth work
Project Finish
milestones
SNG Plant Chilled water Net
Work
Chilled Water Net
Work
Mobilization Water Reservoirs and
pump station
Sewer Net work Sewer Net work Sewer Net work Sewer Net work
Material submittal &
approval
11/.4kv elec. substation
for water pump station
Storm Water Net
work
Storm Water Net work
and EP 1
Storm Water Net
work and EP 2
Storm Water Net
work & EP 3
Procurement (order &
deliver material)
Sewerage pumping
station 03
Potable Water Net
work
Potable Water Net
work
Potable Water Net
work
Potable Water
Net work
Authority NOC.s Sewerage pumping
station 1-A
Irrigation Net work Irrigation Net work Irrigation Net work Irrigation Net work
Demobilization Infrastructure within
utility yard
Telecom Network Telecom Network Telecom Network Telecom Network
Chain Link Fence
around utility
compound
Chilled water line from
exciting DCP to new
temporary Guest House
Street Lighting Net
work
Street Lighting Net
work
Street Lighting Net
work
Street Lighting
Net work
Forced sewer line from
temp. Guest House to
Sewer pump station 1A
11 KV Net Work 11 KV Net Work 11 KV Net Work 11 KV Net Work
Guard House 1 & 2 Gas Net Work Gas Net Work Gas Net Work Gas Net Work
TSE line from STP to
irrigation tie in point
Roads Roads Roads Roads
Improve the Existing
Evaporation Pond
Landscape Landscape Landscape Landscape
include hills
Execution plan for
Infrastructure Network
Execution of Infrastructure
network
Start
End
phase 1
on 78 W
End
phase 2
on 92 W
Order & delivery
Electrical cables and
street Lighting materials
Submit & Approval Utilities Shop
DrawingSubmit & Approval Utilities
material (pipes ,fitting ,….
Order & delivery Utilities
material (pipes ,fitting
,….
Install dewatering system
if required
Excavation ,install utilities pipes
and backfilling in sequence
according to the depth &
disposition
Excavation ,install LV
,MV & ST found.
Submit & Approval
electrical LV,MV & ST
shop Drawing
Excavation ,install
Telecom system.
Submit & Approval
prequalification of
Etisalat subcontractor
Submit & Approval
Telecom shop
Drawing
Submit & approve
Telecom Materials
Submit & approval
Electrical cables and
street Lighting materials
Order & delivery
Telecom Materials
Submit & Approval
Roads ,irrigation ,Hard
& soft landscape shop
drawing
Submit & Approval
Roads ,irrigation ,Hard
& soft landscape
material
Order & delivery Roads
,irrigation ,Hard & soft
landscape material
Install sec. Irrigation , Roads ,hard
&soft landscape and street lighting
poles.
Submit & Approval
prequalification of
Gas third party
consultant
Submit & Approval
Gas stress analysis
Report
Site survey
•Final testing ,commissioning ,snagging
and handover
Sewer Network Storm Network Water Network
HDPE Pipe=6920m
Upvc Pipe=15270m
GRP Pipe=18020m
Upvc Pipe=17990m
HDPE Pipe =6420m for EP
HDPE Pipe=24500m
DI Pipe=730 m
Fire Hydrant= 172 no.
Irrigation Network Gas Network Chilled Water Network
HDPE Pipe=88200m
Upvc Pipe=100m
PE Pipe =44190m HDPE Pipe=9192m
Electrical Network Street Lighting Telecom & ELV Network
MV Cable=51000m
Upvc Ducts=58332m
Light Poles=3365 no. Upvc ducts=45880 m
12 SM F.O cables=52000m
CCTV System
SMATV System
Roads Structural Works Landscape
Asphalt Roads=174174 m2
Tiles = 346416 m2
Reinforced Concrete=6926m3
Steel Reinforced = 439 ton
Trees=5288 no.
Palm Trees=219 no.
Shrubs = 60135 no.
Major Material for Infrastructure
Network
Execution plan for Structure
Utilities Compound Structure
Execution plan for
SNG Plant
•Submit subcontractor
prequalification
•ADNOC approval for subcontractor
•Submit and approve
Material (include long
lead items)
•Submit and approve
Civil and MEP shop
drawing
•Construct Civil
Structure
•Order and deliver
Civil and MEP
material
•Install MEP material
•Testing and Pre-commissioning
•Final testing ,commissioning ,snagging
and handover
W52
W58
Start
•Submit Design Consultant
prequalification
•ADNOC approval for Consultant
•Verification SNG gas network
Design
Major Material for SNG Plant
No. Material Description Unit Qty.
1 LPG storage tanks no 3
2 LPG filter no 3
3 SNG accumulator tank no 2
4 Compressed air receiver tank no 1
5 LPG compressor no 2
6 Air compressor no 4
8 Vaporiser feed pump, rotary type no 4
9 LPG vaporiser, indirect fired no 4
10 LPG-Air blender no 1
11 Flare stack no 1
12 Methanol injection skid no 1
13 Valves ,strainer (different type)
14 5 Tons Overhead Crane, FPS-OHTC-
01
no 1
15 Steel Pipe for Fire Suppression m 1055
16 Steel Pipe schedule 80 HVAC m 413
Utilities Compound Structure
Execution plan for
Water Tank Reservoirs , Water Pump Station
•Order and deliver
Civil material
•Submit and
approve Civil and
MEP shop drawing
for pump station
•Install MEP material
•Testing and Pre-commissioning
•Final testing ,commissioning ,snagging
and handover
W52
W58
•Submit and approve MEP
Material AND civil (include
long lead items)
•Construct Civil
Structure for pump
station
•Order and deliver
MEP material
•Construct water
tanks reservoirs
•Submit and approve
Civil shop drawing for
water tanks
•Submit subcontractor prequalification
•ADNOC approval for subcontractor
Start
No. Material Description Unit Qty.
1 Vertical Turbine Double Case Pump 106 L/S no 4
2 Vertical Booster Pump 2L/S no 2
3 Vertical Turbine Double Case Jockey Pump 32
L/S
no 1
4 Monorail crane - 5 Tons , WPS-MC-1 no 1
5 Pressure Tanks 20000 L no 2
6 Valves ( B.F.V,G.V, Check,etc.) no
7 D.I Pipes & Fittings m
8 Dismantling Joints no
9 Motor Control Center (MCC) no 1
10 Diesel Generator 640KVA no 1
11 Bulk Fuel Tank 9500 Liters no 1
12 Fire Fighting & Fire Alarm System no 1
13 Chlorination System no 1
14 UPS System 3KVA no 1
15 SCADA System and Instrumentation no 1
Major Material for Water pump Station
Utilities Compound Structure
Execution plan for
11/.4kv Electrical substation
•Order and deliver
Civil material
•Construct Civil
Structure for
electrical substation
•Install MEP material
•Testing and Pre-commissioning
•Final testing ,commissioning ,snagging
and handover
W52
W58
•Submit and approve MEP
Material AND civil (include
long lead items)
•Submit and
approve Civil and
MEP shop drawing
for Electrical
substation
•Order and deliver
MEP material
•Submit subcontractor prequalification
•ADNOC approval for subcontractor
Start
No. Material Description Unit Qty.
1 Capacitor Bank 200KVAR no 2
2 UPS System 3KVA no 1
3 SCADA System and Instrumentation no 1
4 11kV switchgear, indoor type no 1
5 Oil immersed type distribution
transformer(s) ,three phase, 50Hz,
1500 kVA (AN) rating, 11/0.4 kV
no 1
Major Material for 11/.4kv Electrical substation
Execution plan for
Sewerage Lifting Station SLS 3
•Install MEP material
•Testing and Pre-commissioning
•Final testing ,commissioning ,snagging
and handover
W52
W58
•Submit and approve
Material (include long
lead items)
•Submit and
approve Civil and
MEP shop drawing
for lifting station
•Construct Civil
Structure for lifting
station
•Order and deliver
Civil and MEP
material
•Submit subcontractor prequalification
•ADNOC approval for subcontractor
Start
Execution plan for
Sewerage Lifting Station SLS -1A & Force
main line from SLS-1A to STP &
From Guest House to STP
•Submit Design consultant prequalification for
design of force main lines
•ADNOC approval for design consultant
•Install MEP material
•Testing and Pre-commissioning
•Final testing ,commissioning ,snagging
and handover
W52
W58
•Submit and approve
Material (include long
lead items)
•Submit and
approve Civil and
MEP shop drawing
for lifting station &
force main line
•Construct Civil
Structure for lifting
station
•Order and deliver
Civil and MEP
material •Execution of force
main line (including
install dewatering
system )
•Submit subcontractor prequalification for SLS -1A
•ADNOC approval for subcontractor
•Submit &approval design drawing FORCE MAIN
LINES
Start
No. Material Description Unit Qty.
1 Submersible Sewage Pump 46 L/S no 3
2 Odor Control Unit 620 L/s no 1
3
Macerator 94 L/S
no
2
4 Motorized Penstock no 1
5 Overhead Travelling Crane 1.5 T no 1
6 Valves ( G.V, Check,etc.) no
7 D.I Pipes & Fittings m
8 Dismantling & Flexible Coupling no
9 Motor Control Center (MCC) no 1
10 SCADA System & Instrumintations no 1
11 HVAC no 1
12 Diesel Generator 315 KVA no 1
13 Fire Fighting And Fire Alarm System no 1
14 UPS System no 1
15 Power & Control Cable M
16 Surge Vessel 3000L no 2
17 Sump Pumps 5 L/S no 2
Major Material for
SLS3
No. Material Description Unit Qty.
1 Submersible Sewage Pump 160 L/S no 4
2 Odor Control Unit no 1
3
Macerator 210 L/S no 2
4 Motorized Penstock no 1
5 Overhead Travelling Crane 5 T no 1
6 Valves ( G.V, Check,etc.) no
7 D.I Pipes & Fittings m
8 Dismantling & Flexible Coupling no
9 Motor Control Center (MCC) no 1
10 SCADA System & Instrumentations no 1
11 HVAC no 1
12 Diesel Generator 315 KVA no 1
13 UPS System no 1
14 Surge Vessel no 2
SLS-1A
Execution plan for
New Evaporation Pond 1 ,2 & 3
•Install MEP material
•Testing and Pre-commissioning
•Final testing ,commissioning ,snagging
and handover
•Submit and approve
Material (include long
lead items)
•Submit and approve
Civil and MEP shop
drawing for new
Evaporation Pond 1,2,3
•Construct Civil
Structure for
Evaporation Pond
•Order and deliver
Civil and MEP
material
Improve of Existing Evaporation Pond
•Submit Design consultant prequalification
•ADNOC approval for design consultant
•Submit &approval design drawing for sump pit ,
pump station & overflow line from exiting EP to
EP2 and overflow line from EP 1 to EP2 and overflow
line from EP2 to EP3 and overflow line from exiting EP3
to Sabkha area
•Submit and approve
Civil and MEP shop
drawing for EP &
overflow lines
•Submit and approve
Material (include long
lead items)
•Order and deliver
Civil and MEP
material
Lining of existing EP
construction of a sump pit &
pump station for existing EP
Construct overflow line from
EP1 to EP2
Construct overflow line from
EP2 to EP3
Construct overflow line from
EP3 to Sabkha Area
Construct overflow line from
existing EP to EP2
Start
No. Material Description Unit Qty.
1 Submersible Pump 75 L/s no 2
2 Swing Check Valve no 2
3 Gate Valves no 2
4 Dismantling Coupling no 2
5 Di Pipes & Fittings no
6 ARV & Vacuum Breaker Valve no 1
EP1
No. Material Description Unit Qty.
1 Submersible Pump 83 L/s no 2
2 Swing Check Valve no 2
3 Gate Valves no
2
4 Dismantling Coupling no 2
5 Di Pipes & Fittings no
6 ARV & Vacuum Breaker Valve no 1
EP2
No. Material Description Unit Qty.
1 Submersible Pump 85 L/s no 2
2 Swing Check Valve no 2
3 Gate Valves no
2
4 Dismantling Coupling no 2
5 Di Pipes & Fittings no
6 ARV & Vacuum Breaker Valve no 1
EP3
Major Material for
Execution plan for
Chilled water Line from DCP to new Guest house and Additional Forced Sewer
Lines from New Guest House to STP and TSE line from STP to irrigation tie in
point
•Submit Design consultant prequalification
•ADNOC approval for design consultant
•Submit &approval design drawing for chilled water
line and additional forced sewer lines & TSE line
•Submit and approve
shop drawing for
chilled water line
&Force main & TSE line
•Submit and approve
Material (include long
lead items)
•Order and deliver
Civil and MEP
material
Install dewatering if required ,
excavation , laying pipe line
,…., testing and backfilling
•Testing and Pre-commissioning
•Final testing ,commissioning ,snagging
and handover
W52
W56
Start
DESCRIPTION, CAPACITY, MAKE & MODEL
NUMBER OF
ITEMS
YEAR OF
MANUFACTURE
PRESENT
LOCATION
Excavator 320 D/PC-300 30 2008 - 2012 Abu Dhabi
Excavator/ Road Breaker JCBJW17 45 2009 - 2013 Abu Dhabi
Crane 20 Tons LW250-2 15 2008 - 2010 Abu Dhabi
Crane 50 Tons QY50B 16 2008 - 2011 Abu Dhabi
Crane 70 Tons GR-700EX 9 2009 - 2010 Abu Dhabi
Concrete Batching Plant 100 C.M./Hr 2 2010 Abu Dhabi
Grader GD 705A-4, 18 2009 - 2013 Abu Dhabi
Backhoe Loader OPERATING WEIGHT: 9800 kg; ZAV
90, OPERATING WEIGHT: 20000 kg
28 2007 - 2012 Abu Dhabi
Wheel Loader CAT 966D, OPERATING WEIGHT: 22010
kg
20 2007 - 2011 Abu Dhabi
Small Wheel Loader 906H, OPERATING WEIGHT: 5.630
ton
10 2008 - 2012 Abu Dhabi
Trailor 38m³ 135 2006 - 2013 Abu Dhabi
Tipper Trucks 18m³ 104 2006 - 2013 Abu Dhabi
Double Drum Roller HD75, OPERATING WEIGHT:
7680kg
14 2007 - 2011 Abu Dhabi
Single Drum Roller OPERATING WEIGHT: 4290 kg. SD
100DC
23 2008 - 2012 Abu Dhabi
Hand Roller BWR650 6 2006 - 2010 Abu Dhabi
Asphalt Baby Roller RD 16-90, OPERATING WEIGHT:
1485 kg.
6 2007 - 2011 Abu Dhabi
Generator 3 - 20 Kva 5 2008 - 2011 Abu Dhabi
Generator 101 - 1300 Kva 7 2007 - 2011 Abu Dhabi
Asphalt Paver ABG 7820 + VB88/ SUPER 1800-2 5 2007 - 2012 Abu Dhabi
Asphalt Plant 200 Ton/Hr 2 2009 Abu Dhabi
Prime Coat/Tack Coat Sprayer 4000 Ltr 3 2010 Abu Dhabi
Pneumatic Tyre Roller GRW18 9 2010 - 2012 Abu Dhabi
Milling Machine W1900, OPERATING WEIGHT: 20000kg 1 2008 Abu Dhabi
Asphalt Plate Compactor IB20-7 1 2008 Abu Dhabi
Bobcat Skid Loader 410, OPERATING WEIGHT: 2490kg 20 2007 - 2013 Abu Dhabi
Dozer D8R, OPERATING WEIGHT: 41 ton 66 2008 - 2012 Abu Dhabi
Shovel 966H 34 2009 - 2013 Abu Dhabi
Mobile Service Workshop Upto 75mm Shaft 4 2011 Abu Dhabi
Concrete Vibrator 120 Ton 14 2007 - 2013 Abu Dhabi
Weigh Bridge - Electronic 210 Ton 1 2009 Abu Dhabi
Pick Up 48 2008 - 2013 Abu Dhabi
Diesel Tanker 6000 Ltr 5 2008 - 2011 Abu Dhabi
LIST OF AVAILABLE EQUIPMENT
Chairman 1
Managing Director 1
General Managers 8 8
Group Finance Manager 1 1
Roads, Bridges & Infrastructure 18 12 6 2
Electrical Works 8 1 1 1
Marine & Earth Works 5 4 1
Building and Structural Works 7 5 2 1
Others 15 12 3
Project Engineers 25 17 8 4
Site Engineers 70 49 21 12
Material Engineers 22 18 4 2
Office & Design Engineers 18 14 4 2
Planning Engineers 11 8 3 1
Estimation Engineers 6 4 2 1
Safety Engineers 36 25 11 8
Structural Engineers 6 4 2 1
Production Engineers 7 5 2
Plant Engineers 6 5 1
QC Engineers 28 18 10 4
Quantity Surveyors 26 20 6 2
Safety Officers 70 46 24 18
Construction Superintendent 26 20 6 2
Lab Technicians 33 26 7 2
Draftsmen 60 48 12 8
Chief Surveyors 32 19 13 2
Land Surveyors 74 59 15 5
General Foreman 32 21 11 6
Foremen 88 52 36 14
Others (Asst. Foreman, Asst. Surveyors, Asst. QS,
etc
285 228 57 16
Finance Managers 5 5 0
Chief Accountant 6 5 1
Admin Officer 28 19 9 4
Accountant 28 23 5 1
Costing Clerk 30 25 5 1
Document Controller 32 21 11 2
Secretary 38 30 8 4
Typist 41 26 15
Receptionist 16 12 4 1
Time Keeper 49 32 17 3
Camp Supervisor 52 34 18 6
Others (PRO,Guards, Office Boys, etc) 60 39 21 18
1
2
3
4
5
Proposed for
this Project
Top Management
Project
Management
Engineering
Technical
Department
No.
Total Available in
Company
Administration &
Accounts
Balance
Available
Current
Assignment
Staff Designation
Company Indirect
Manpower
Heavy Equipment Operators 725 435 290 60
Light Equipments Operators 316 207 109 52
Heavy Duty Dvrs 1,021 713 308 112
Light Duty Dvrs 725 472 253 96
Work Shop General Foreman 18 14 4 1
Foreman 55 36 19 12
Plant Operator 12 7 5 2
Plant Foreman 12 7 5 2
Plant Mechanic 12 7 5 2
Plant Electrician 12 7 5 2
Rake man 39 25 14 10
Screw man (Gauge man) 45 24 21 10
Helpers 114 79 35 30
Asset Controller 5 5 0
Store Controller 8 6 2 39
Store Keeper 41 26 15 5
Purchaser 21 16 5 2
Asst Store Keeper 71 50 21 1
Mason 647 422 225 90
Carpenter 589 390 199 90
Steel Fixer 568 397 171 46
Pipe Fitter 105 69 36 30
Electrician 114 69 45 40
Mechanic 144 86 58 49
Asst Mechanic 156 101 55 50
Tyreman 48 32 16 10
Welder 52 31 21 11
Denter 13 8 5 2
Chainmen 202 136 66 54
Painter 32 19 13 8
10
Un Skilled Workers Ordinary Labor 3,374 2365 1009 300
7
8
9
6
Proposed for
this Project
No.
Total Available in
Company
Transport
Department
Plant & Production
Department
Stores & Purchase
Department
Skilled Workers
Balance
Available
Current
Assignment
Staff Designation
Company direct
Manpower

More Related Content

Viewers also liked

Project Execution Plan for Bridge Construction
Project Execution Plan for Bridge ConstructionProject Execution Plan for Bridge Construction
Project Execution Plan for Bridge Construction
David H Moloney
 
final report last.pdf
final report last.pdffinal report last.pdf
final report last.pdfwzhen77
 
Roadhouse e Mediamond: storia di una campagna digitale
Roadhouse e Mediamond: storia di una campagna digitaleRoadhouse e Mediamond: storia di una campagna digitale
Roadhouse e Mediamond: storia di una campagna digitale
Mediamond
 
Ladybug Srls
Ladybug SrlsLadybug Srls
Ladybug Srls
Mattia Salvi
 
Escanear0049
Escanear0049Escanear0049
Evaluation question 2
Evaluation question 2Evaluation question 2
Evaluation question 2
sam hill
 
SEWER REHABILITATION / REPLACEMENT FOR RCC PIPES WITH INTERNAL LINING
SEWER REHABILITATION / REPLACEMENT FOR RCC PIPES WITH INTERNAL LININGSEWER REHABILITATION / REPLACEMENT FOR RCC PIPES WITH INTERNAL LINING
SEWER REHABILITATION / REPLACEMENT FOR RCC PIPES WITH INTERNAL LININGDEEPAK MALLICK
 
eval 5
eval 5eval 5
eval 5
sam hill
 
Mediamond Digital Talks - Moda
Mediamond Digital Talks - ModaMediamond Digital Talks - Moda
Mediamond Digital Talks - Moda
Mediamond
 
ProjectExperience_BJU.pdf
ProjectExperience_BJU.pdfProjectExperience_BJU.pdf
ProjectExperience_BJU.pdf
humblelarry
 
Plásticos termoestables. (1)
Plásticos termoestables. (1)Plásticos termoestables. (1)
Plásticos termoestables. (1)
Eva_Tecno
 
assignment 2 2
assignment 2 2assignment 2 2
assignment 2 2
CoombeMedia1
 
Metro Tunnels Programme 3D Visualisation
Metro Tunnels Programme 3D VisualisationMetro Tunnels Programme 3D Visualisation
Metro Tunnels Programme 3D Visualisation
David H Moloney
 
Route 2020 Metro Dubai Construction Details
Route 2020 Metro Dubai   Construction DetailsRoute 2020 Metro Dubai   Construction Details
Route 2020 Metro Dubai Construction Details
David H Moloney
 
Motorway Construction, Project Execution Plan
Motorway Construction, Project Execution PlanMotorway Construction, Project Execution Plan
Motorway Construction, Project Execution Plan
David H Moloney
 
Достопримечательности Сеула
Достопримечательности СеулаДостопримечательности Сеула
Достопримечательности Сеула
anchicha2408
 
Pre tecn
Pre tecnPre tecn
Pre tecn
AnaHerr14
 
Expocsicion hitoria
Expocsicion hitoriaExpocsicion hitoria
Expocsicion hitoria
Ruben Salgado
 

Viewers also liked (20)

Project Execution Plan for Bridge Construction
Project Execution Plan for Bridge ConstructionProject Execution Plan for Bridge Construction
Project Execution Plan for Bridge Construction
 
resume c.v. new updated.
resume c.v. new updated.resume c.v. new updated.
resume c.v. new updated.
 
final report last.pdf
final report last.pdffinal report last.pdf
final report last.pdf
 
Roadhouse e Mediamond: storia di una campagna digitale
Roadhouse e Mediamond: storia di una campagna digitaleRoadhouse e Mediamond: storia di una campagna digitale
Roadhouse e Mediamond: storia di una campagna digitale
 
Ladybug Srls
Ladybug SrlsLadybug Srls
Ladybug Srls
 
Escanear0049
Escanear0049Escanear0049
Escanear0049
 
HOUSE OF TECHNOLOGY
HOUSE OF TECHNOLOGYHOUSE OF TECHNOLOGY
HOUSE OF TECHNOLOGY
 
Evaluation question 2
Evaluation question 2Evaluation question 2
Evaluation question 2
 
SEWER REHABILITATION / REPLACEMENT FOR RCC PIPES WITH INTERNAL LINING
SEWER REHABILITATION / REPLACEMENT FOR RCC PIPES WITH INTERNAL LININGSEWER REHABILITATION / REPLACEMENT FOR RCC PIPES WITH INTERNAL LINING
SEWER REHABILITATION / REPLACEMENT FOR RCC PIPES WITH INTERNAL LINING
 
eval 5
eval 5eval 5
eval 5
 
Mediamond Digital Talks - Moda
Mediamond Digital Talks - ModaMediamond Digital Talks - Moda
Mediamond Digital Talks - Moda
 
ProjectExperience_BJU.pdf
ProjectExperience_BJU.pdfProjectExperience_BJU.pdf
ProjectExperience_BJU.pdf
 
Plásticos termoestables. (1)
Plásticos termoestables. (1)Plásticos termoestables. (1)
Plásticos termoestables. (1)
 
assignment 2 2
assignment 2 2assignment 2 2
assignment 2 2
 
Metro Tunnels Programme 3D Visualisation
Metro Tunnels Programme 3D VisualisationMetro Tunnels Programme 3D Visualisation
Metro Tunnels Programme 3D Visualisation
 
Route 2020 Metro Dubai Construction Details
Route 2020 Metro Dubai   Construction DetailsRoute 2020 Metro Dubai   Construction Details
Route 2020 Metro Dubai Construction Details
 
Motorway Construction, Project Execution Plan
Motorway Construction, Project Execution PlanMotorway Construction, Project Execution Plan
Motorway Construction, Project Execution Plan
 
Достопримечательности Сеула
Достопримечательности СеулаДостопримечательности Сеула
Достопримечательности Сеула
 
Pre tecn
Pre tecnPre tecn
Pre tecn
 
Expocsicion hitoria
Expocsicion hitoriaExpocsicion hitoria
Expocsicion hitoria
 

Similar to New Persentation

Colt Hayes Planning Approach v1 220121.pptx
Colt Hayes Planning Approach v1 220121.pptxColt Hayes Planning Approach v1 220121.pptx
Colt Hayes Planning Approach v1 220121.pptx
IrfanAwan25
 
Colt Hayes Planning Approach v1 220121.pptx
Colt Hayes Planning Approach v1 220121.pptxColt Hayes Planning Approach v1 220121.pptx
Colt Hayes Planning Approach v1 220121.pptx
IrfanAwan25
 
MES Case Study - Carlton Park Substation
MES Case Study - Carlton Park SubstationMES Case Study - Carlton Park Substation
MES Case Study - Carlton Park SubstationSteve Sadler
 
odunlami prese_033552.pptx
odunlami prese_033552.pptxodunlami prese_033552.pptx
odunlami prese_033552.pptx
AgohaChinonso
 
Colt Hayes Planning Approach v2 220121.pptx
Colt Hayes Planning Approach v2 220121.pptxColt Hayes Planning Approach v2 220121.pptx
Colt Hayes Planning Approach v2 220121.pptx
IrfanAwan25
 
20150209111021 tech spn dtd 29.jan 2015
20150209111021 tech spn dtd 29.jan 201520150209111021 tech spn dtd 29.jan 2015
20150209111021 tech spn dtd 29.jan 2015
JOTHIMANIKKAM SOMASUNDARAM
 
Resume -Abdul Alim Dewan -2017
Resume -Abdul Alim Dewan -2017Resume -Abdul Alim Dewan -2017
Resume -Abdul Alim Dewan -2017Abdul Alim Dewan
 
Eme slide gioi thieu version tieng anh_2-01-2014
Eme  slide gioi thieu version tieng anh_2-01-2014Eme  slide gioi thieu version tieng anh_2-01-2014
Eme slide gioi thieu version tieng anh_2-01-2014
xncd
 
Eme slide gioi thieu version tieng anh_02-01-2014
Eme  slide gioi thieu version tieng anh_02-01-2014Eme  slide gioi thieu version tieng anh_02-01-2014
Eme slide gioi thieu version tieng anh_02-01-2014xncd
 
odunlami prese_033552.pptx
odunlami prese_033552.pptxodunlami prese_033552.pptx
odunlami prese_033552.pptx
AgohaChinonso
 
Harish aggarwal
Harish aggarwalHarish aggarwal
Harish aggarwal
Harish Agarwal
 
Engineering Drawings required for Solar Projects
Engineering Drawings required for Solar Projects Engineering Drawings required for Solar Projects
Engineering Drawings required for Solar Projects
Gensol Engineering Limited
 
Watkins-M-and-E-Main-Brochure-WEB version.pptx
Watkins-M-and-E-Main-Brochure-WEB version.pptxWatkins-M-and-E-Main-Brochure-WEB version.pptx
Watkins-M-and-E-Main-Brochure-WEB version.pptx
TanveerAziz7
 
Presentation CS_update
Presentation CS_updatePresentation CS_update
Presentation CS_updateBoris Markov
 
Uhde Shedden Project Undertaken
Uhde Shedden Project UndertakenUhde Shedden Project Undertaken
Uhde Shedden Project UndertakenMichael Macek
 
ELECTRICITYWIRING REGULATION for safety of
ELECTRICITYWIRING REGULATION for safety ofELECTRICITYWIRING REGULATION for safety of
ELECTRICITYWIRING REGULATION for safety of
abdirahman gure
 
Hossam salah-cv
Hossam salah-cvHossam salah-cv
Hossam salah-cv
Hosam Salah
 

Similar to New Persentation (20)

Colt Hayes Planning Approach v1 220121.pptx
Colt Hayes Planning Approach v1 220121.pptxColt Hayes Planning Approach v1 220121.pptx
Colt Hayes Planning Approach v1 220121.pptx
 
Colt Hayes Planning Approach v1 220121.pptx
Colt Hayes Planning Approach v1 220121.pptxColt Hayes Planning Approach v1 220121.pptx
Colt Hayes Planning Approach v1 220121.pptx
 
MES Case Study - Carlton Park Substation
MES Case Study - Carlton Park SubstationMES Case Study - Carlton Park Substation
MES Case Study - Carlton Park Substation
 
odunlami prese_033552.pptx
odunlami prese_033552.pptxodunlami prese_033552.pptx
odunlami prese_033552.pptx
 
Colt Hayes Planning Approach v2 220121.pptx
Colt Hayes Planning Approach v2 220121.pptxColt Hayes Planning Approach v2 220121.pptx
Colt Hayes Planning Approach v2 220121.pptx
 
20150209111021 tech spn dtd 29.jan 2015
20150209111021 tech spn dtd 29.jan 201520150209111021 tech spn dtd 29.jan 2015
20150209111021 tech spn dtd 29.jan 2015
 
COBRA PRESENTATION
COBRA  PRESENTATIONCOBRA  PRESENTATION
COBRA PRESENTATION
 
Resume -Abdul Alim Dewan -2017
Resume -Abdul Alim Dewan -2017Resume -Abdul Alim Dewan -2017
Resume -Abdul Alim Dewan -2017
 
hendrik cv 3
hendrik cv 3hendrik cv 3
hendrik cv 3
 
Eme slide gioi thieu version tieng anh_2-01-2014
Eme  slide gioi thieu version tieng anh_2-01-2014Eme  slide gioi thieu version tieng anh_2-01-2014
Eme slide gioi thieu version tieng anh_2-01-2014
 
Eme slide gioi thieu version tieng anh_02-01-2014
Eme  slide gioi thieu version tieng anh_02-01-2014Eme  slide gioi thieu version tieng anh_02-01-2014
Eme slide gioi thieu version tieng anh_02-01-2014
 
odunlami prese_033552.pptx
odunlami prese_033552.pptxodunlami prese_033552.pptx
odunlami prese_033552.pptx
 
Harish aggarwal
Harish aggarwalHarish aggarwal
Harish aggarwal
 
Engineering Drawings required for Solar Projects
Engineering Drawings required for Solar Projects Engineering Drawings required for Solar Projects
Engineering Drawings required for Solar Projects
 
Keepintouch2008_v3
Keepintouch2008_v3Keepintouch2008_v3
Keepintouch2008_v3
 
Watkins-M-and-E-Main-Brochure-WEB version.pptx
Watkins-M-and-E-Main-Brochure-WEB version.pptxWatkins-M-and-E-Main-Brochure-WEB version.pptx
Watkins-M-and-E-Main-Brochure-WEB version.pptx
 
Presentation CS_update
Presentation CS_updatePresentation CS_update
Presentation CS_update
 
Uhde Shedden Project Undertaken
Uhde Shedden Project UndertakenUhde Shedden Project Undertaken
Uhde Shedden Project Undertaken
 
ELECTRICITYWIRING REGULATION for safety of
ELECTRICITYWIRING REGULATION for safety ofELECTRICITYWIRING REGULATION for safety of
ELECTRICITYWIRING REGULATION for safety of
 
Hossam salah-cv
Hossam salah-cvHossam salah-cv
Hossam salah-cv
 

New Persentation

  • 1. Construction Methodology for the Infrastructure Project RUWAIS HOUSING COMPLEX EXPANSION PHASE IV INFRASTRUCTURE WORKS PROJECT 7010C9
  • 2. Content : 1. Scope of Work 2. Project Milestones 3. Organization Chart 4. Building Site Phases 5. Villa Site Phases 6. Project WBS 7. Execution Plan for infrastructure network 8. Execution Plan for Structure 9. Company Equipment 10.Company Manpower
  • 4. Infrastructure Network for Accommodation (Building site ) and Villas site Building site Villas site STP by Other P6020 DCP by Other P7010C12 Electrical Substation by Other P7010C8 SLS 3 SLS1A EP 1 SNG Water tanks Guest House by Other Storm water & Drainage Network Waste Water Network Water Supply Network with Fire Hydrants Irrigation Network Telecom Network Chilled Water Network SNG Distribution Network Low Voltage (LV) Network 11Kv Network (MV Cable) Street Lighting Network Soft and Hard Landscape Roads Force Main line from SLS3 to STP Force Main line from SLS1A to STP Discharge Line between Evaporated Ponds Chilled Water Line from exciting DCP to new Gust House Force Main from SLS1A to STP Force Main from SLS3 to STP
  • 5. Plant and Structure SNG Plant Sewer Pump Station SLS3 Sewer Pump Station SLS1A Water Reservoirs and Pump Station Electrical Substation 11/.4 kv Evaporation Pond No. 1 Evaporation Pond No. 2 Evaporation Pond No. 3 Improve existing Evaporation Pond Guard House 1 Guard House 2 Building site Villas site STP by Other P6020 DCP by Other P7010C12 Electrical Substation by Other P7010C8 SLS 3 SLS1A EP 1 SNG Water tanks Guest House
  • 8. El Gaber Milestones El Dabey Milestones
  • 10.
  • 12. Phase 1 from building no . 20 to building no. 36 (total no. is 17) Finish Millstone is 78 w Sewer Line up to from MH 1-1 to MH1-1.12 and from MH 1-5 to MH 1-1 including line to SLS3 Phase 1 for building site 17 Nos Building (G+5) Water Line from water tank up to isolated valve in the corner Storm Water Line from MH1-3 to MH1-1 and from MH 1-1 to MH 1-1.12 and line to EP1
  • 13. Phase 2 - Remaining building site network Finish Milstone is 90w Phase 2 for building site 23 Nos Building (G+5)
  • 15. Phase 1 for Villas site 350 villas (4 BR)+27 villas(5 BR) To SLS A1 & EP3 To SLS 2 & EP2 27 Villas 5BR + 245 Villas 4BR 109 4BR Villas Total = 354 villas 4BR +27 Villas 5BR North Hill not including in Phase 1 Water Line connecting with water tank feed phase 1 area Sewer and Storm lines in this road to be included in phase 1 (road length ≈450m) Sewer and Storm lines in this road to be included in phase 1 (road length ≈475m)
  • 16.
  • 17.
  • 18. Phase 2 for Villas site 214 villas (4 BR)+72 villas(5 BR) 211 4BR Villas 72 VIP Villas 5BR North and south Hills including in Phase 2
  • 19. Phase 1 & 2 Villas site and related utilities
  • 21. Project Wide Package 1 Package 2 (building)Site) Package 3 (Villa Site) UTILIY Compound MM(EF after 58w) (Eng. & Con & test) Phase 1 (17 no. (G+5) building ) KM(EF after 78w) (Eng. & Con & test) Phase 2 (23 no. (G+5) building ) MM(EF after 90w) (Eng. & Con & test) Phase 1 (377 villas) KM(EF after 78w) (Eng. & Con & test) Phase 2 (286 villas) KM(EF after 88w) (Eng. & Con & test) Project Start Earth work Project Finish milestones SNG Plant Chilled water Net Work Chilled Water Net Work Mobilization Water Reservoirs and pump station Sewer Net work Sewer Net work Sewer Net work Sewer Net work Material submittal & approval 11/.4kv elec. substation for water pump station Storm Water Net work Storm Water Net work and EP 1 Storm Water Net work and EP 2 Storm Water Net work & EP 3 Procurement (order & deliver material) Sewerage pumping station 03 Potable Water Net work Potable Water Net work Potable Water Net work Potable Water Net work Authority NOC.s Sewerage pumping station 1-A Irrigation Net work Irrigation Net work Irrigation Net work Irrigation Net work Demobilization Infrastructure within utility yard Telecom Network Telecom Network Telecom Network Telecom Network Chain Link Fence around utility compound Chilled water line from exciting DCP to new temporary Guest House Street Lighting Net work Street Lighting Net work Street Lighting Net work Street Lighting Net work Forced sewer line from temp. Guest House to Sewer pump station 1A 11 KV Net Work 11 KV Net Work 11 KV Net Work 11 KV Net Work Guard House 1 & 2 Gas Net Work Gas Net Work Gas Net Work Gas Net Work TSE line from STP to irrigation tie in point Roads Roads Roads Roads Improve the Existing Evaporation Pond Landscape Landscape Landscape Landscape include hills
  • 23. Execution of Infrastructure network Start End phase 1 on 78 W End phase 2 on 92 W Order & delivery Electrical cables and street Lighting materials Submit & Approval Utilities Shop DrawingSubmit & Approval Utilities material (pipes ,fitting ,…. Order & delivery Utilities material (pipes ,fitting ,…. Install dewatering system if required Excavation ,install utilities pipes and backfilling in sequence according to the depth & disposition Excavation ,install LV ,MV & ST found. Submit & Approval electrical LV,MV & ST shop Drawing Excavation ,install Telecom system. Submit & Approval prequalification of Etisalat subcontractor Submit & Approval Telecom shop Drawing Submit & approve Telecom Materials Submit & approval Electrical cables and street Lighting materials Order & delivery Telecom Materials Submit & Approval Roads ,irrigation ,Hard & soft landscape shop drawing Submit & Approval Roads ,irrigation ,Hard & soft landscape material Order & delivery Roads ,irrigation ,Hard & soft landscape material Install sec. Irrigation , Roads ,hard &soft landscape and street lighting poles. Submit & Approval prequalification of Gas third party consultant Submit & Approval Gas stress analysis Report Site survey •Final testing ,commissioning ,snagging and handover
  • 24. Sewer Network Storm Network Water Network HDPE Pipe=6920m Upvc Pipe=15270m GRP Pipe=18020m Upvc Pipe=17990m HDPE Pipe =6420m for EP HDPE Pipe=24500m DI Pipe=730 m Fire Hydrant= 172 no. Irrigation Network Gas Network Chilled Water Network HDPE Pipe=88200m Upvc Pipe=100m PE Pipe =44190m HDPE Pipe=9192m Electrical Network Street Lighting Telecom & ELV Network MV Cable=51000m Upvc Ducts=58332m Light Poles=3365 no. Upvc ducts=45880 m 12 SM F.O cables=52000m CCTV System SMATV System Roads Structural Works Landscape Asphalt Roads=174174 m2 Tiles = 346416 m2 Reinforced Concrete=6926m3 Steel Reinforced = 439 ton Trees=5288 no. Palm Trees=219 no. Shrubs = 60135 no. Major Material for Infrastructure Network
  • 25. Execution plan for Structure
  • 26. Utilities Compound Structure Execution plan for SNG Plant •Submit subcontractor prequalification •ADNOC approval for subcontractor •Submit and approve Material (include long lead items) •Submit and approve Civil and MEP shop drawing •Construct Civil Structure •Order and deliver Civil and MEP material •Install MEP material •Testing and Pre-commissioning •Final testing ,commissioning ,snagging and handover W52 W58 Start •Submit Design Consultant prequalification •ADNOC approval for Consultant •Verification SNG gas network Design
  • 27. Major Material for SNG Plant No. Material Description Unit Qty. 1 LPG storage tanks no 3 2 LPG filter no 3 3 SNG accumulator tank no 2 4 Compressed air receiver tank no 1 5 LPG compressor no 2 6 Air compressor no 4 8 Vaporiser feed pump, rotary type no 4 9 LPG vaporiser, indirect fired no 4 10 LPG-Air blender no 1 11 Flare stack no 1 12 Methanol injection skid no 1 13 Valves ,strainer (different type) 14 5 Tons Overhead Crane, FPS-OHTC- 01 no 1 15 Steel Pipe for Fire Suppression m 1055 16 Steel Pipe schedule 80 HVAC m 413
  • 28. Utilities Compound Structure Execution plan for Water Tank Reservoirs , Water Pump Station •Order and deliver Civil material •Submit and approve Civil and MEP shop drawing for pump station •Install MEP material •Testing and Pre-commissioning •Final testing ,commissioning ,snagging and handover W52 W58 •Submit and approve MEP Material AND civil (include long lead items) •Construct Civil Structure for pump station •Order and deliver MEP material •Construct water tanks reservoirs •Submit and approve Civil shop drawing for water tanks •Submit subcontractor prequalification •ADNOC approval for subcontractor Start
  • 29. No. Material Description Unit Qty. 1 Vertical Turbine Double Case Pump 106 L/S no 4 2 Vertical Booster Pump 2L/S no 2 3 Vertical Turbine Double Case Jockey Pump 32 L/S no 1 4 Monorail crane - 5 Tons , WPS-MC-1 no 1 5 Pressure Tanks 20000 L no 2 6 Valves ( B.F.V,G.V, Check,etc.) no 7 D.I Pipes & Fittings m 8 Dismantling Joints no 9 Motor Control Center (MCC) no 1 10 Diesel Generator 640KVA no 1 11 Bulk Fuel Tank 9500 Liters no 1 12 Fire Fighting & Fire Alarm System no 1 13 Chlorination System no 1 14 UPS System 3KVA no 1 15 SCADA System and Instrumentation no 1 Major Material for Water pump Station
  • 30. Utilities Compound Structure Execution plan for 11/.4kv Electrical substation •Order and deliver Civil material •Construct Civil Structure for electrical substation •Install MEP material •Testing and Pre-commissioning •Final testing ,commissioning ,snagging and handover W52 W58 •Submit and approve MEP Material AND civil (include long lead items) •Submit and approve Civil and MEP shop drawing for Electrical substation •Order and deliver MEP material •Submit subcontractor prequalification •ADNOC approval for subcontractor Start
  • 31. No. Material Description Unit Qty. 1 Capacitor Bank 200KVAR no 2 2 UPS System 3KVA no 1 3 SCADA System and Instrumentation no 1 4 11kV switchgear, indoor type no 1 5 Oil immersed type distribution transformer(s) ,three phase, 50Hz, 1500 kVA (AN) rating, 11/0.4 kV no 1 Major Material for 11/.4kv Electrical substation
  • 32. Execution plan for Sewerage Lifting Station SLS 3 •Install MEP material •Testing and Pre-commissioning •Final testing ,commissioning ,snagging and handover W52 W58 •Submit and approve Material (include long lead items) •Submit and approve Civil and MEP shop drawing for lifting station •Construct Civil Structure for lifting station •Order and deliver Civil and MEP material •Submit subcontractor prequalification •ADNOC approval for subcontractor Start
  • 33. Execution plan for Sewerage Lifting Station SLS -1A & Force main line from SLS-1A to STP & From Guest House to STP •Submit Design consultant prequalification for design of force main lines •ADNOC approval for design consultant •Install MEP material •Testing and Pre-commissioning •Final testing ,commissioning ,snagging and handover W52 W58 •Submit and approve Material (include long lead items) •Submit and approve Civil and MEP shop drawing for lifting station & force main line •Construct Civil Structure for lifting station •Order and deliver Civil and MEP material •Execution of force main line (including install dewatering system ) •Submit subcontractor prequalification for SLS -1A •ADNOC approval for subcontractor •Submit &approval design drawing FORCE MAIN LINES Start
  • 34. No. Material Description Unit Qty. 1 Submersible Sewage Pump 46 L/S no 3 2 Odor Control Unit 620 L/s no 1 3 Macerator 94 L/S no 2 4 Motorized Penstock no 1 5 Overhead Travelling Crane 1.5 T no 1 6 Valves ( G.V, Check,etc.) no 7 D.I Pipes & Fittings m 8 Dismantling & Flexible Coupling no 9 Motor Control Center (MCC) no 1 10 SCADA System & Instrumintations no 1 11 HVAC no 1 12 Diesel Generator 315 KVA no 1 13 Fire Fighting And Fire Alarm System no 1 14 UPS System no 1 15 Power & Control Cable M 16 Surge Vessel 3000L no 2 17 Sump Pumps 5 L/S no 2 Major Material for SLS3 No. Material Description Unit Qty. 1 Submersible Sewage Pump 160 L/S no 4 2 Odor Control Unit no 1 3 Macerator 210 L/S no 2 4 Motorized Penstock no 1 5 Overhead Travelling Crane 5 T no 1 6 Valves ( G.V, Check,etc.) no 7 D.I Pipes & Fittings m 8 Dismantling & Flexible Coupling no 9 Motor Control Center (MCC) no 1 10 SCADA System & Instrumentations no 1 11 HVAC no 1 12 Diesel Generator 315 KVA no 1 13 UPS System no 1 14 Surge Vessel no 2 SLS-1A
  • 35. Execution plan for New Evaporation Pond 1 ,2 & 3 •Install MEP material •Testing and Pre-commissioning •Final testing ,commissioning ,snagging and handover •Submit and approve Material (include long lead items) •Submit and approve Civil and MEP shop drawing for new Evaporation Pond 1,2,3 •Construct Civil Structure for Evaporation Pond •Order and deliver Civil and MEP material Improve of Existing Evaporation Pond •Submit Design consultant prequalification •ADNOC approval for design consultant •Submit &approval design drawing for sump pit , pump station & overflow line from exiting EP to EP2 and overflow line from EP 1 to EP2 and overflow line from EP2 to EP3 and overflow line from exiting EP3 to Sabkha area •Submit and approve Civil and MEP shop drawing for EP & overflow lines •Submit and approve Material (include long lead items) •Order and deliver Civil and MEP material Lining of existing EP construction of a sump pit & pump station for existing EP Construct overflow line from EP1 to EP2 Construct overflow line from EP2 to EP3 Construct overflow line from EP3 to Sabkha Area Construct overflow line from existing EP to EP2 Start
  • 36. No. Material Description Unit Qty. 1 Submersible Pump 75 L/s no 2 2 Swing Check Valve no 2 3 Gate Valves no 2 4 Dismantling Coupling no 2 5 Di Pipes & Fittings no 6 ARV & Vacuum Breaker Valve no 1 EP1 No. Material Description Unit Qty. 1 Submersible Pump 83 L/s no 2 2 Swing Check Valve no 2 3 Gate Valves no 2 4 Dismantling Coupling no 2 5 Di Pipes & Fittings no 6 ARV & Vacuum Breaker Valve no 1 EP2 No. Material Description Unit Qty. 1 Submersible Pump 85 L/s no 2 2 Swing Check Valve no 2 3 Gate Valves no 2 4 Dismantling Coupling no 2 5 Di Pipes & Fittings no 6 ARV & Vacuum Breaker Valve no 1 EP3 Major Material for
  • 37. Execution plan for Chilled water Line from DCP to new Guest house and Additional Forced Sewer Lines from New Guest House to STP and TSE line from STP to irrigation tie in point •Submit Design consultant prequalification •ADNOC approval for design consultant •Submit &approval design drawing for chilled water line and additional forced sewer lines & TSE line •Submit and approve shop drawing for chilled water line &Force main & TSE line •Submit and approve Material (include long lead items) •Order and deliver Civil and MEP material Install dewatering if required , excavation , laying pipe line ,…., testing and backfilling •Testing and Pre-commissioning •Final testing ,commissioning ,snagging and handover W52 W56 Start
  • 38. DESCRIPTION, CAPACITY, MAKE & MODEL NUMBER OF ITEMS YEAR OF MANUFACTURE PRESENT LOCATION Excavator 320 D/PC-300 30 2008 - 2012 Abu Dhabi Excavator/ Road Breaker JCBJW17 45 2009 - 2013 Abu Dhabi Crane 20 Tons LW250-2 15 2008 - 2010 Abu Dhabi Crane 50 Tons QY50B 16 2008 - 2011 Abu Dhabi Crane 70 Tons GR-700EX 9 2009 - 2010 Abu Dhabi Concrete Batching Plant 100 C.M./Hr 2 2010 Abu Dhabi Grader GD 705A-4, 18 2009 - 2013 Abu Dhabi Backhoe Loader OPERATING WEIGHT: 9800 kg; ZAV 90, OPERATING WEIGHT: 20000 kg 28 2007 - 2012 Abu Dhabi Wheel Loader CAT 966D, OPERATING WEIGHT: 22010 kg 20 2007 - 2011 Abu Dhabi Small Wheel Loader 906H, OPERATING WEIGHT: 5.630 ton 10 2008 - 2012 Abu Dhabi Trailor 38m³ 135 2006 - 2013 Abu Dhabi Tipper Trucks 18m³ 104 2006 - 2013 Abu Dhabi Double Drum Roller HD75, OPERATING WEIGHT: 7680kg 14 2007 - 2011 Abu Dhabi Single Drum Roller OPERATING WEIGHT: 4290 kg. SD 100DC 23 2008 - 2012 Abu Dhabi Hand Roller BWR650 6 2006 - 2010 Abu Dhabi Asphalt Baby Roller RD 16-90, OPERATING WEIGHT: 1485 kg. 6 2007 - 2011 Abu Dhabi Generator 3 - 20 Kva 5 2008 - 2011 Abu Dhabi Generator 101 - 1300 Kva 7 2007 - 2011 Abu Dhabi Asphalt Paver ABG 7820 + VB88/ SUPER 1800-2 5 2007 - 2012 Abu Dhabi Asphalt Plant 200 Ton/Hr 2 2009 Abu Dhabi Prime Coat/Tack Coat Sprayer 4000 Ltr 3 2010 Abu Dhabi Pneumatic Tyre Roller GRW18 9 2010 - 2012 Abu Dhabi Milling Machine W1900, OPERATING WEIGHT: 20000kg 1 2008 Abu Dhabi Asphalt Plate Compactor IB20-7 1 2008 Abu Dhabi Bobcat Skid Loader 410, OPERATING WEIGHT: 2490kg 20 2007 - 2013 Abu Dhabi Dozer D8R, OPERATING WEIGHT: 41 ton 66 2008 - 2012 Abu Dhabi Shovel 966H 34 2009 - 2013 Abu Dhabi Mobile Service Workshop Upto 75mm Shaft 4 2011 Abu Dhabi Concrete Vibrator 120 Ton 14 2007 - 2013 Abu Dhabi Weigh Bridge - Electronic 210 Ton 1 2009 Abu Dhabi Pick Up 48 2008 - 2013 Abu Dhabi Diesel Tanker 6000 Ltr 5 2008 - 2011 Abu Dhabi LIST OF AVAILABLE EQUIPMENT
  • 39. Chairman 1 Managing Director 1 General Managers 8 8 Group Finance Manager 1 1 Roads, Bridges & Infrastructure 18 12 6 2 Electrical Works 8 1 1 1 Marine & Earth Works 5 4 1 Building and Structural Works 7 5 2 1 Others 15 12 3 Project Engineers 25 17 8 4 Site Engineers 70 49 21 12 Material Engineers 22 18 4 2 Office & Design Engineers 18 14 4 2 Planning Engineers 11 8 3 1 Estimation Engineers 6 4 2 1 Safety Engineers 36 25 11 8 Structural Engineers 6 4 2 1 Production Engineers 7 5 2 Plant Engineers 6 5 1 QC Engineers 28 18 10 4 Quantity Surveyors 26 20 6 2 Safety Officers 70 46 24 18 Construction Superintendent 26 20 6 2 Lab Technicians 33 26 7 2 Draftsmen 60 48 12 8 Chief Surveyors 32 19 13 2 Land Surveyors 74 59 15 5 General Foreman 32 21 11 6 Foremen 88 52 36 14 Others (Asst. Foreman, Asst. Surveyors, Asst. QS, etc 285 228 57 16 Finance Managers 5 5 0 Chief Accountant 6 5 1 Admin Officer 28 19 9 4 Accountant 28 23 5 1 Costing Clerk 30 25 5 1 Document Controller 32 21 11 2 Secretary 38 30 8 4 Typist 41 26 15 Receptionist 16 12 4 1 Time Keeper 49 32 17 3 Camp Supervisor 52 34 18 6 Others (PRO,Guards, Office Boys, etc) 60 39 21 18 1 2 3 4 5 Proposed for this Project Top Management Project Management Engineering Technical Department No. Total Available in Company Administration & Accounts Balance Available Current Assignment Staff Designation Company Indirect Manpower
  • 40. Heavy Equipment Operators 725 435 290 60 Light Equipments Operators 316 207 109 52 Heavy Duty Dvrs 1,021 713 308 112 Light Duty Dvrs 725 472 253 96 Work Shop General Foreman 18 14 4 1 Foreman 55 36 19 12 Plant Operator 12 7 5 2 Plant Foreman 12 7 5 2 Plant Mechanic 12 7 5 2 Plant Electrician 12 7 5 2 Rake man 39 25 14 10 Screw man (Gauge man) 45 24 21 10 Helpers 114 79 35 30 Asset Controller 5 5 0 Store Controller 8 6 2 39 Store Keeper 41 26 15 5 Purchaser 21 16 5 2 Asst Store Keeper 71 50 21 1 Mason 647 422 225 90 Carpenter 589 390 199 90 Steel Fixer 568 397 171 46 Pipe Fitter 105 69 36 30 Electrician 114 69 45 40 Mechanic 144 86 58 49 Asst Mechanic 156 101 55 50 Tyreman 48 32 16 10 Welder 52 31 21 11 Denter 13 8 5 2 Chainmen 202 136 66 54 Painter 32 19 13 8 10 Un Skilled Workers Ordinary Labor 3,374 2365 1009 300 7 8 9 6 Proposed for this Project No. Total Available in Company Transport Department Plant & Production Department Stores & Purchase Department Skilled Workers Balance Available Current Assignment Staff Designation Company direct Manpower