SlideShare a Scribd company logo
Basement Car Park
KEY PLAN
N
Scale
LECTURER
Drawn by
Date
Project number
Institute of Technology Carlow
BSc. in Architectural Technology
Year 3 2016-2017
1 : 1000
15/11/201713:30:10
building section 3D
3
Carlow Leisure Centre
28/02/2017
TEJ RAJ UPRETI
NOEL DUNNE/ DAN
O'SULLIVAN/MARK DUFFY
Sheet No- A106
leisure centre 3D
4
A
B
Precast concrete floor slab
Spec: 200mm thickness. With edge thickening and
steel reinforced. All Gaps filled with lean mix concrete
before insulation install
Structural Concrete Screed
Spec: 100mm Thickness. All columns wrapped in
compressible insulation layer to meet screed height.
Movement joints also to be accommodated. With
edge thickening and steel reinforced To Comply
with Engineers Details, Specs and Design.
Fixing: Poured on top of insulation.
Plasterboard and Plaster Finish
Spec: 12.5mm thickness and 2.5mm Plaster Skim.
Moisture Resistance plasterboard.
Fixing: Secured to steel structure behind.
Finish: 2.5mm White plaster skimcoat
APA curtain walling systm
Spec: APA curtain walling systm box
150x70mm fitted with pressure plate with 24mm
double glazing curtain wall with U-value 1.00W/m2 k
and fixed with structural column,
Fixing :fixed to circular steel hollow section
Aluminium slidding door
Torch on membrane finish flat roof
intensive Green roof
North clad Aluminium cladding
APA curtain walling systm
Spec: APA curtain walling systm box
150x70mm fitted with pressure plate with 24mm
double glazing curtain wall with U-value 1.00W/m2 k
and fixed with structural column,
STONE LITE RAINSCREEN PANEL
Spec: 8 mm stone vineer + backing 20 mm
honeycomb structure
3D Building Section
1
Building Long Section 3D
2
GSKY green wall panel
Spec: green wall planting will be native
to ireland or Irish weather .
Fixing :propriety hidden fix bracket
to horizantal rail.
Steel Perimeter Columns
Spec: Serial Size - 356mm x 171mm. Kg/m - 67.
Fixing: Concrete Wall Below with holding down
bolts cast in to secure steel columns.
To Comply with Engineers Details, Specs and
Design.
Existing Bridge
River Barrow
Basement Car Park
Main Swimming Pool
sports hall
plant room
Gym
Changing room
Leisure Pool
intensive Green roof
plant room
Basement Car Park
Changing room
Gym
Gym
Changing room
3D prespective view of Leisure Swimming Pool
3D prespective view of Rear Entrance
3D prespective view North Elevation3D prespective view of West Elevation
3D prespective view of Section C-C3D prespective view of `Section A-A
A
B
Ambulant disabled Stair
Cafe Area
plant room
plant room
Atrium
Atrium
Atrium
1400x2200mm Fire Escape Door
Torch on membrane finish flat roof
Torch on membrane finish flat roof
intensive Green roof
North
Entrance
River Barrow
Existing Bridge
Existing Apartment
Existing Town hall
Cox's Lane
BarrowTrack
Carlow Town park
Rainwater harvesting tank
HH
H
H
MH1
MH2
MH3
MH5
fire assembly point
fire assembly point
KEY PLAN
N
GFL
47000
FFL
51500
Sport hall Roof level
56020
Roof
59760
Atrium Level
58997
Green Roof Level
54597
Inverter
Battery pack
Scale
LECTURER
Drawn by
Date
Project number
Institute of Technology Carlow
BSc. in Architectural Technology
Year 3 2016-2017
As indicated
16/11/201713:17:27
Building Services
3
Carlow Leisure Centre
28/02/2017
TEJ RAJ UPRETI
NOEL DUNNE/ DAN
O'SULLIVAN/MARK DUFFY
Sheet No- A124
PHOTOVOLTIC PANEL
Pv Technology produces electricity directly from electrons
freed by the interaction of sunlight with a solar panel made of
semiconductor material. The power provided is direct current
(DC) electricity. The basic building block is known as solar
cell. Many cells puts together are known as a module and
many modules assembled together from an array. A PV
system will consist of an array of modules generating DC
electricity.an inverter and can be stored in battery storage
banks
Advantages
PV panels provide clean – green energy. During electricity
generation with PV panels there is no harmful greenhouse
gas emissions thus solar PV is environmentally friendly.
Solar energy is energy supplied by nature – it is thus free and
abundant!
Solar energy can be made available almost anywhere there is
sunlight
PV panels have no mechanically moving parts, except in
cases of –sun-tracking mechanical bases; consequently they
have far less breakages or require less maintenance than
other renewable energy systems (e.g. wind turbines)
PV panels are totally silent, producing no noise at all;
consequently, they are a perfect solution for urban areas and
for residential applications (see solar panels for home)
Economical with little to no running cost.
Disadvantages
As in all renewable energy sources, solar energy has
intermittency issues; not shining at night but also during
daytime there may be cloudy or rainy weather.
Consequently, intermittency and unpredictability of solar
energy makes solar energy panels less reliable a solution.
Solar energy panels require additional equipment (inverters)
to convert direct electricity (DC) to alternating electricity (AC)
in order to be used on the power network.
For a continuous supply of electric power, especially for on-
grid connections, Photovoltaic panels require not only
Inverters but also storage batteries; thus increasing the
investment cost for PV panels considerably
In case of land-mounted PV panel installations, they require
relatively large areas for deployment; usually the land space is
committed for this purpose for a period of 15-20 years – or
even longer.
safeguard a PV investment.
How its integrated?
I’m using a grid system photovoltics panel on my roof .these
are connected to utility grid and feed power. Many cells puts
together are known as a module and many modules
assembled together from an array. A PV system will consist
of an array of modules generating DC electricity.an inverter
and can be stored in battery storage banks.the power
produced by the PV sysem can either suppy electrical loads in
to the building or be fed back into the grid when the PV
systems output is greater than the load demand .i have
include my calculation with my report.
solar PV System Diagram
1 : 500
Site Plan (Services )
1
Mains Water Supply line
Gas supply
MH Manhole
ESB Supply Line
Site Boundry Line
H Water hydrant location
Fire Assembly Point
legend
Roof Slope
General Design Notes:
All works to comply with all current, building regulations
and codes of Practice.
Design Guidance is taken from Sports England
Documents and also
The Metric Handbook, TGD'L',TGD 'k,' TGD'B', TGD'M',
BS:9999.
All works to be passed by building Control officer
inspections.
Cast in-situ concrete to comply with BS 8004.
Steel reinforcement & structural steel Frame to engineer’s
details &design.
architect's Office for clarification.
SUNSINE AND SOLAR RADIATION
Ireland normally gets between 1100-1600 hours of sunshine each year
the sunniest months may-June. During these months, sunshine duration
averages between 5-6.5 hours per day most part of the country. The
southeast of Ireland gets the most sunshine average over 7 hours a day
in the early summer. December is the dullest month, with an average
sunshine from about 1 hour in north and 2 hour in the south east
The orientation of the building
The orientation of building that I have chosen
to propose is directly north east as it optimise
the use passive heating and co0lling techniques
among with renewable technology. There is
more glazing area on the south east elevation
which will allow natural light and heat from the
sun. The buildings south elevation side has
an existing apartment so it needs to be
1 hour fire rated wall but south east side
I have put high performance triple glazed
curtain walling .
Wind Direction in Ireland
Average Temperature in Carlow
Average Rainfall in Carlow
mono-crystaline PV panel
autometic wall mounted
light control devices will be Every
6M on the room like (Bathroom, Corridor etc)
mono-crystaline PV panel
OVERSHADING FACTOR
None or very little = 1
1 module = 1.65 M2 = .235 kpeak
258 module = 1.65 x 258 = 425 M2
calculate the total peak power of all panels
= 425 x 0.235 kpeak
= 100 kwp
calculate the total peak power of south
oriantation panel
Total panel on south side = 258panel
= 258 x 0.235
= 60kwp
The Annual output would be
output (kwp) = 0.8 x 60 x 1072 x 1
=51456 kwh
1 : 100
Section E-E
2
AC isolator
Mains AC isolator
Distribution board
Load
45
RAIN WATER HARVESTING SYSTEM
PV PANEL
LED LIGHT
All existing light need to be replaced with new LED
light on the building .which will get the immersion
powered by Pv panel .
All light is connected with autometic wall mounted
light control devices on every 10 Metre
range.
There would be mono-crystaline PV panel on the
roof.The panel will be S/W and N/W oriantation
with 15 degrees slope.there would be Mono -cristaling
(kingspan) 258 panel ,size will be 1.65m2 module
100 wpeak.
There would be 100,000 ltr Stainless Steel tank on the site
( see site plan) which would be conneted with another
tank on the roof level which water will be use for toilet
flushing.
the moter will get the immersion powered by PV panel.
Eco flush toilet
All Toilet will have Eco tank Flush Tank. there
will be use Rain water From
Rain water harvesting tank will be use for toilet flushing.
All Tap Will be Contemporary Sensor Tap Automatic
Touchless Bathroom Sink Tap Mixer
Basement Car Park
KEY PLAN
N
Scale
LECTURER
Drawn by
Date
Project number
Institute of Technology Carlow
BSc. in Architectural Technology
Year 3 2016-2017
1 : 1000
15/11/201713:30:10
building section 3D
3
Carlow Leisure Centre
28/02/2017
TEJ RAJ UPRETI
NOEL DUNNE/ DAN
O'SULLIVAN/MARK DUFFY
Sheet No- A106
leisure centre 3D
4
A
B
Precast concrete floor slab
Spec: 200mm thickness. With edge thickening and
steel reinforced. All Gaps filled with lean mix concrete
before insulation install
Structural Concrete Screed
Spec: 100mm Thickness. All columns wrapped in
compressible insulation layer to meet screed height.
Movement joints also to be accommodated. With
edge thickening and steel reinforced To Comply
with Engineers Details, Specs and Design.
Fixing: Poured on top of insulation.
Plasterboard and Plaster Finish
Spec: 12.5mm thickness and 2.5mm Plaster Skim.
Moisture Resistance plasterboard.
Fixing: Secured to steel structure behind.
Finish: 2.5mm White plaster skimcoat
APA curtain walling systm
Spec: APA curtain walling systm box
150x70mm fitted with pressure plate with 24mm
double glazing curtain wall with U-value 1.00W/m2 k
and fixed with structural column,
Fixing :fixed to circular steel hollow section
Aluminium slidding door
Torch on membrane finish flat roof
intensive Green roof
North clad Aluminium cladding
APA curtain walling systm
Spec: APA curtain walling systm box
150x70mm fitted with pressure plate with 24mm
double glazing curtain wall with U-value 1.00W/m2 k
and fixed with structural column,
STONE LITE RAINSCREEN PANEL
Spec: 8 mm stone vineer + backing 20 mm
honeycomb structure
3D Building Section
1
Building Long Section 3D
2
GSKY green wall panel
Spec: green wall planting will be native
to ireland or Irish weather .
Fixing :propriety hidden fix bracket
to horizantal rail.
Steel Perimeter Columns
Spec: Serial Size - 356mm x 171mm. Kg/m - 67.
Fixing: Concrete Wall Below with holding down
bolts cast in to secure steel columns.
To Comply with Engineers Details, Specs and
Design.
Existing Bridge
River Barrow
Basement Car Park
Main Swimming Pool
sports hall
plant room
Gym
Changing room
Leisure Pool
intensive Green roof
plant room
Basement Car Park
Changing room
Gym
Gym
Changing room
3D prespective view of Leisure Swimming Pool
3D prespective view of Rear Entrance
3D prespective view North Elevation3D prespective view of West Elevation
3D prespective view of Section C-C3D prespective view of `Section A-A
A
B
Ambulant disabled Stair
Cafe Area
plant room
plant room
Atrium
Atrium
Atrium
1400x2200mm Fire Escape Door
Torch on membrane finish flat roof
Torch on membrane finish flat roof
intensive Green roof
BSc in Architectural Technology
Year 3: 2016 - 2017
Scale
LECTURER
Drawn by
Date
Project number
16/11/201713:22:23
3D Building
3
28/02/2017
TEJ RAJ UPRETI
NOEL DUNNE/ DAN
O'SULLIVAN/MARK DUFFY
Sheet No- A127
South West 3d View
1
North west 3D View
2
North East 3D View
3
South West 3D View
4
APA curtain walling systm
Spec: APA curtain walling systm box
150x70mm fitted with pressure plate with 24mm
double glazing curtain wall with U-value 1.00W/m2 k
and fixed with structural column,
Fixing :fixed to circular steel hollow section
Aluminium slidding door
Torch on membrane finish flat roof
APA curtain walling systm
Spec: APA curtain walling systm box
150x70mm fitted with pressure plate with 24mm
double glazing curtain wall with U-value 1.00W/m2 k
and fixed with structural column,
Fixing :fixed to circular steel hollow section
STONE LITE RAINSCREEN PANEL
Spec: 8 mm stone vineer + backing 20 mm
honeycomb structure
Fixing :propriety hidden fix bracket to horizantal rail
APA curtain walling systm
Spec: APA curtain walling systm box
150x70mm fitted with pressure plate with 24mm
double glazing curtain wall with U-value 1.00W/m2 k
and fixed with structural column,
Fixing :fixed to circular steel hollow section
GSKY green wall panel
Spec: green wall planting will be native
to ireland or Irish weather .
Fixing :propriety hidden fix bracket
to horizantal rail.
APA curtain walling systm
Spec: APA curtain walling systm box
150x70mm fitted with pressure plate with 24mm
double glazing curtain wall with U-value 1.00W/m2 k
and fixed with structural column,
Fixing :fixed to circular steel hollow section
APA curtain walling systm
Spec: APA curtain walling systm box
150x70mm fitted with pressure plate with 24mm
double glazing curtain wall with U-value 1.00W/m2 k
and fixed with structural column,
Fixing :fixed to circular steel hollow section
GSKY green wall panel
Spec: green wall planting will be native
to ireland or Irish weather .
Fixing :propriety hidden fix bracket
to horizantal rail.
STONE LITE RAINSCREEN PANEL
Spec: 8 mm stone vineer + backing 20 mm
honeycomb structure
Fixing :propriety hidden fix bracket to horizantal rail
STONE LITE RAINSCREEN PANEL
Spec: 8 mm stone vineer + backing 20 mm
honeycomb structure
Fixing :propriety hidden fix bracket to horizantal rail
Aluminium Cladding
Fixing: Proprietary Hidden Fix System
Cement plaster board through PIR
Insulation via Z-Girt Bracket.
Finish: ALUMINIUM CLADDING WITH
BLUE COLOUR FINISH.
Zinc roof
STONE LITE RAINSCREEN PANEL
Spec: 8 mm stone vineer + backing 20 mm
honeycomb structure
Fixing :propriety hidden fix bracket to horizantal rail
Aluminium slidding door
Roof Light
Intensive Green roof
intensive Green roof
Aluminium Cladding
Fixing: Proprietary Hidden Fix System
Cement plaster board through PIR
Insulation via Z-Girt Bracket.
Finish: ALUMINIUM CLADDING WITH
BLUE COLOUR FINISH.
Aluminium Cladding
Fixing: Proprietary Hidden Fix System
Cement plaster board through PIR
Insulation via Z-Girt Bracket.
Finish: ALUMINIUM CLADDING WITH
BLUE COLOUR FINISH.
Curtain Walling At North
Ambulant Disabled Concrete
Stairwell
Full Length of Curtain walling
at East Stairwell
350 mm Cast in place
concrete Raft Foundation
intensive Green roof
intensive Green roof
Torch on membrane finish flat roof
Zinc roof
6500mmx3000mm opening to
Enter and Exit Car Park
1400x2200mm Fire Escape Door
1400x2200mm Fire Escape Door
North
Entrance
River Barrow
Existing Bridge
Existing Apartment
Existing Town hall
Cox's Lane
BarrowTrack
Carlow Town park
Rainwater harvesting tank
HH
H
H
MH1
MH2
MH3
MH5
fire assembly point
fire assembly point
KEY PLAN
N
98151200
598
Scale
LECTURER
Drawn by
Date
Project number
Institute of Technology Carlow
BSc. in Architectural Technology
Year 3 2016-2017
As indicated
16/11/201713:16:26
Sustainable Service Strategy
3
Carlow Leisure Centre
28/02/2017
TEJ RAJ UPRETI
NOEL DUNNE/ DAN
O'SULLIVAN/MARK DUFFY
Sheet No- A123
SUNSINE AND SOLAR RADIATION
Ireland normally gets between 1100-1600 hours of sunshine each year
the sunniest months may-June. During these months, sunshine duration
averages between 5-6.5 hours per day most part of the country. The
southeast of Ireland gets the most sunshine average over 7 hours a day
in the early summer. December is the dullest month, with an average
sunshine from about 1 hour in north and 2 hour in the south east
The orientation of the building
The orientation of building that I have chosen
to propose is directly north east as it optimise
the use passive heating and co0lling techniques
among with renewable technology. There is
more glazing area on the south east elevation
which will allow natural light and heat from the
sun. The buildings south elevation side has
an existing apartment so it needs to be
1 hour fire rated wall but south east side
I have put high performance triple glazed
curtain walling .
Rainwater harvesting system
In this building have a large amount of clear roof space
collecting it and recycling water will be no problem. Water
collected from the roof will be filtered with and stored in a
40000 m3 tank located in the building site. This filtered
clean water will be pumped to much smaller tank on the
roof so this water will be use as flushing toilet and urinals
on the building .while outdoor water can be feed directly
from the outdoor tank
This system will be very useful for my building .I have
include my calculation for rainwater harvesting system
you can see
Wood pellet boiler
Biomass is a form of renewable energy that can reduce our
reliance on fossil fuels. Instead of burning fossil fuels for
energy, biomass uses organic materials. These organic
materials are derived from a variety of sources. Wood
sources such as trees are commonly used, but energy
crops, food waste or industrial waste can also be exploited
as fuel in biomass heating.
The fuel is burned in boilers and stoves and the energy
generated heats water and space. Stoves generally are only
useful to heat one room, whereas boilers are able to heat
whole properties.
Rather than burning expensive oil or gas the boiler burns
wood pellets instead
The boiler will have 3 main parts the boiler, the hopper and
the store. The wood pallets are kept in the store. And the
hopper automatically adds them to the boiler, to minimise the
amount of work.
The wood pallet is fuel, just like gas or oil. Only this is more
environmentally friendly and renewable energy. And cheaper
to burn .
Advantages
Biomass is considered a carbon neutral form of energy
because the carbon dioxide released when it is burned is
only that which was absorbed by the plant during its
life. Therefore there is no gain or loss of carbon dioxide.
It is high efficient system
The pallets are produced from west material
Another financial benefit of using biomass boilers for heating
is that there is less exposure to the fluctuations of the energy
market
Disadvantage
Installing a biomass boiler or stove is not cheap
Requires a lot of storage space.
Need regular cleaning and maintenance
How its integrated:
The wood pellet boiler will be stored in the basement level in
the plant room .i have done the calculation include my report.
All of the sizes are worked out making it the
Deciding factor in which I chose this system in the leisure
centre.
Suppose total energy required is =805000kwh
Step 2: Calculate quantity of pellets required to meet the
above energy demand for the
building.
Use thumb rule: Energy content of 1 kg pellet= approx. 5
kWh
So for 805000 kwh ,?kg pellet ,=805000/5 =161000 kgs.or
161 tonnes
Step 3: Calculate the total cost for using pellets
Use thumb rule: €230 per tonne (Bulk Pellets) and€299 per
tonne (Bagged Pellets)
Ie,230 x161 =37030 euros.
Step4: Calculate the total volume of pellets used
Use thumb rule:1 m³ pellets = 650 kg
So for 161000 kg of pellets total volume= 161000/650=
247.5m3.
Step 5: Calculate total volume required for pellet store
=Total volume of pellet used * 3/2……if total storage =x then
2/3 *x = 248 or
ie, x = 248*3/2= 372 m3
Step 6: Calculate Total heat demand
Use Thumb rule:Per 1 kW heat demand = 0.9 m³ of the
space (incl. empty space)
So for 372 m3 of pellets it is 372/ 0.9 = 413KW
Ventilation
Stack ventilation uses temperature differences to move air.
Hot air rises because it is lower pressure. Cool air is sucked
in through low intent openings and hotter exhaust air escape
through outlet openings. The ventilation rate is proportional to
the area of openings. Placing opening at the bottom and top
of an open space will encourage natural ventilation through a
stack ventilation.
Advantages
This system will improved air quality in a building.
It will improved ventilation in a building
Economical with little running cost.
Energy saving as there is no need for HAVC system to cool
the building.
Environmentally friendly.
Limitations
The air on the outside must be cooler then the air inside for
the stack ventilation to work
Risk of cold bridging (need to be insulated)
How I integrated:
The stack ventilation will be placed at the top of the atrium in
the leisure centre building which will allow the hot air pass
through to the outside
Therefore bringing in new fresh air keeping the building
ventilated. Where there is atrium in a building stack
ventilation is the best strategy to use as they have a large
difference in height between air inlets and outlets.so stack will
be start from basement to atrium level.
3D Building with Glazing Unit
3 Proposed curtain walling to allow
natural light into the space, with
proposed passivent aircool ventilators
to allow natural ventiltion into the
GYM.
Proposed curtain walling to allow
natural light into the space, with
proposed passivent aircool ventilators
to allow natural ventiltion into the
Pool.
Rainwater Harvesting System Diagram
Stack Ventilation system
1 : 500
Site Plan For Services
1
Mains Water Supply line
Gas supply
MH Manhole
ESB Supply Line
Site Boundry Line
H Water hydrant location
Fire Assembly Point
legend
Roof Slope
Wind Direction in Ireland
Average Temperature in Carlow
Average Rainfall in Carlow
RAIN WATER HARVESTING SYSTEM
average rainfal in carlow =1200 l/m2
Roof Area =600m2
correction factor=0.9
Annual rainwater yield
= 1200x600x0.9
= 648000 L/year
Annual rain water demand .
for 50 person
flush toilet per person = 11800x200 = 2360000
cleaning per person = 800x200 = 160000
Total =2520000
= 91133.24
Tank size will be 100000 L
2360000+648000 x21 days
Tank size =
2x365
General Design Notes:
All works to comply with all current, building regulations
and codes of Practice.
Design Guidance is taken from Sports England
Documents and also
The Metric Handbook, TGD'L',TGD 'k,' TGD'B', TGD'M',
BS:9999.
All works to be passed by building Control officer
inspections.
Cast in-situ concrete to comply with BS 8004.
Steel reinforcement & structural steel Frame to engineer’s
details &design.
architect's Office for clarification.
1 : 20
aluminium cladding with Ventilation on Basement
4
ventilation Grill
Prefabricated Steel vent Grate
fitted to wall but not Fixed
(removable for maintanence Purpose
Paving Stone kerb 100x160mm
Paving Stone 40x200mm layed to fall of
1:50, sand Brushed between stone to
allow water Penetration
Geotextile Membrane
A
B
C
D
E
F
G
H
I
J
1 2 3 4 5 6 7 8
9
10
K
M
60006000
6000 6000 6000 6000 6000 8000 11330 22245 580
60006000600060006000225032506000
600060006000
2591
404 m²
4351.6 SF
Sports Hall
12 m²
125.0 SF
Store Hall Store
18 m²
197.2 SF
Male Changing
19 m²
200.8 SF
Female Changing
24 m²
258.9 SF
Female changing
26 m²
282.8 SF
Male Changing
wc wc
Cafe
Reception
area
23903
17087
1907
892892
17081692
3376
4786
2734
2499
2457
5875
11514
7838
5830
6842
5621
3827
26802635
30972
16697
19787
2185
1730
1730
5230
4633
4546
5013
2185
1430
1430
1275
1690
840
1730
1730
2008
940
1430 1430
940
940
940
933
840
1763
2410
1730 1730 1730
1536
1422
2850
8536
1999
1999
1999
1730
1830
1339
900
1780
835
1430
1900
1241
24690
13785
1038
940928
67 m²
721.2 SF
Squash Court
67 m²
721.2 SF
Squash Court
68 m²
729.3 SF
Squash Court
14 m²
153.0 SF
First Aid
6 m²
66.4 SF
Store Room
13 m²
140.0 SF
Office
307 m²
3309.2 SF
Leisure Pool
340 m²
3663.5 SF
Main Pool
38 m²
406.2 SF
Pool Store
10 m²
104.3 SF
Sauna Room
10 m²
106.1 SF
Steam Room
45 m²
483.3 SF
Plant Room
57 m²
617.6 SF
Changing Village
23 m²
247.5 SF
Female Toilts
22 m²
236.3 SF
Male Toilets
1200
36
34
7 10911
17
16
14
5 6
35
12
13
2 3 4
15
KEY PLAN
N
10080150
10280150
13 13
Plasterboard and Plaster Finish
Spec: 12.5mm thickness and 2.5mm Plaster Skim.
Moisture and Fire Resistance plasterboard.
Fixing: Secured to steel stud via proprietary Clip.
Finish: 2.5mm White plaster skimcoat
Steel Perimeter Columns
Spec: Serial Size - 356mm x 171mm. Kg/m - 67.
Fixing: Concrete Wall Below with holding down
bolts cast in to secure steel columns.
Finish: Lined with Moisture and Fire Registrant plasterboard
and Plaster.
To Comply with Engineers Details, Specs and
Design
Scale
LECTURER
Drawn by
Date
Project number
Institute of Technology Carlow
BSc. in Architectural Technology
Year 3 2016-2017
As indicated
16/11/201713:14:25
FSC Ground Floor
3
Carlow Leisure Centre
28/02/2017
TEJ RAJ UPRETI
NOEL DUNNE/ DAN
O'SULLIVAN/MARK DUFFY
Sheet No- A120
1 : 200
GFL Building Regulation part 'B'
1
EMERGENCY ESCAPE LIGHTING
there shall be light on all escape routes to
comply with BS 5266-1 and BS 5266-7
30 MIN FIRE RESISTANCE DOOR SET
In Accordance with TGD 'B' table B1 fitted
with intrumescent strips and smoke seal door
set to be fitted with autometic self closing
devicewhich can be capable of closing the
door from any angle against any latch fitted to
comply with TGD'B'.
In this building at least 30 minute fire rated
door lon the corridor and the lobby area.
60 MIN FIRE RESISTANCE DOOR SET
In Accordance with TGD 'B' table B1 fitted
with intrumescent strips and smoke seal door
set to be fitted with autometic self closing
devicewhich can be capable of closing the
door from any angle against any latch fitted to
comply with TGD'B'.
In this building at least 60 minute fire rated
door on the corridor,plant room ,store and
stairs.
60 min fire resistant doorset in Accordance with BS476PAd 22 fitted
with intrumescent strip and smoke seals.door set will fitted with autometic
selfclosing devicewhich will be capable of closing the door from any angle
and aginst any latch fitted to this door.
30 min fire resistant doorset in Accordance with BS476PAd 22 fitted
with intrumescent strip and smoke seals.door set will fitted with autometic
selfclosing devicewhich will be capable of closing the door from any angle
and aginst any latch fitted to this door.
Disable refuge Area (1400x900mm )provide with two way communication to the
internal Refuge area.
Emergency Escape lighting to be comply with TGD'B' table 8.installed and certified in
accordance with 2013
1800mmx18mm clear space for wheelchair turning circle
60 min Protected stairwell in accordance with section TGD
part 'B'A2 ie top story served not more than 5m above ground
level.
Traval distances
one Direction D1
Two Direction D2
Stair 3D
2
1 : 10
internal Partition wall
3
100 mm self leveling Structural Screed
150 mm Precast concrete hollowcore
floor slab has a span of 9 M
corebord to fix Steel Channel to
100 mm cold rolled Ceiling chanel to
support the Vertical Chanel
Fastener Strap
Double Slabbed standard 2x12.5 mm fire rated
plaster board.60 min fire rated.
Double Slabbed standard 2x12.5 mm fire rated
plaster board.
100 mm steel vertical studpartition for
service zone.
Gypsum active air suspended ceiling tile 600x600
suspended with Aluminium Tracks and hanging
with Steel wire suspended from Steel Beam
Double Slabbed standard 2x12.5 mm fire rated
plaster board.60 min fire rated.
150 mm Precast concrete hollowcore
floor slab has a span of 9 M
100 mm self leveling Structural Screed
80 mm rigid insulation on the floor for sound
80 mm rigid insulation on the floor for sound
4mm Marmoleum floor finish
Double Slabbed standard 2x12.5 mm fire rated
plaster board.60 min fire rated.
Structural Steel Beam Encasment
Structural Steel column encasment
30min Protected stairwell in accordance with section TGD
part 'B'A2 ie top story served not more than 5m above ground
level.
60 min Fire resistance Door Set
All Doors Leading from stairwell
will be 60 min fire reted
Stairwell is Constructed with
350mm wall with 2x12.5 mm
gypsum pasterbord 60min fire
rated
Lobby To Stairwell constructed with
60 min fire rated with 60 min partition
fited with 60 min fire door
Autometic Opening vent at the
top of Each stair well opens when alram is
triggered
Ambulant disabled Stair Notes
The clear width (between enclosing ,
string or upstand ) wiil be 1200mm.
the landing will be level and have an
unobstructed length (Clear of any Door
swing)of at least 1200mm .
Section 1: Means of Escape in case of Fire
All Area of the building and Occupancy of the Building calculated with the methological
approach of the building with comply with TGD'B' Clauses 1.0.10
SECTION B5
External fire Main
The Hydraint are Designed and maintained in accordance
with BS5306 Part 1.
Vehicle access
Vehicle Access roure including manhole or other covers
accordance with TGD part 'B'
Overhead obstruction such as cables that would be set with
ladders.
Provision of switches
A fire fighter Emergency switch will be Provide at beside
plant Room .
Escape stairways 1,2&3 will have autometic opening vent
it is indicate in site plan.
All autometic opening vents will be automatically activate if
smoke detectors in the stairway enclosure are activate .
Section B4-External Fire Spread
external wall construction
The main walls are Constructed of steel with Cold Rolled
Multichanel Beam (secondary Structure ) Between those chanel
there will be mineral Quilt Insulation with PIR rigid insulation .
there will be Rockwool insulation on intermediate Floor level .
Sprinkler Systems
The intensity of radiation from a fire in the compartment which is
fitted throughout with a sprinkler systm will be accordance with
TGD part 'B' 4.2.8.2 the sprincal system will meet the BS 5306
part 2 1990.
Section B2 -Internal Fire Spread(linings)
walls
The surfae of the wall in in a room ,bathroom Changing room etc will
be lower but it will comply with class D-s3,d2(european)
windows
external windows to room glazed with thermoplastic metterials.the
internal glazing will in accorance with TGD'B' paragraph 2.1.
Roof Lights
All roof light to rooms , circulation space can be construction with thermo
plastic material comply with TGD'B' paragrapf A15 and Appendix A.
Section B3 -Internal Fire Spread
Forms of Compartmentation
This building is Assembly and Recration purpose group
5.on the Ground Floor has more than the requirement minimium of Apx
1900 m2 in Area.therefore it will be three Compartment Area shown on
Drawing Above.
Construction of Compartment Floors and walls
there will be complete fire barrier to between the compartments they
will separate the construction in accordance with the TGD'B'3.2.5.1 to
3.2.5.11 .
Separating walls
All separating walls will comply with the TGD'B' 3.2.5.7.
Openings between compartments
All Door opening in compartment walls will be protechted by means of fire
door in accordance with Appendix B and table B1of the TGD 'B'
the passage of pipes ,ventilation Ductsor more Services will be construct
in accordance with TGD'B'3.4.
construction of Protechted shaft
it will have have the Appropriate Fire resistance in Accordance with
TGD'B' Appendix A table A1.
all compartments wall will be comply with TGD'B; section 3.2.7.3
There will be three zone in the building
Zone 1 :swimming pool area and its facilities
Zone 2:the middle part of building including changing room ,wc reception area, cafe
squash court gym etc
Zone 3: sport hall also include storage which is only accessible from sport hall
this zone has its own direct escape to the outside .
Escape Stairways
All escape stairways will be comply with TGD'B' 1.3.6.2. to 1.3.6.6.
Fire Door Assemblies
All fire Door need to be cirtified before Fitting in accordance with BS476part 8.
Automatilc Door
the main Automatic slidding door will be comply with BS7036
Floor Surface of Escape Route
All stairs , rams and landing will be comply with TGD'K'and 'M'.also the escape route
surface nedd to be sleep resistant finish.
Ventilation
there will be ventilation on all Stairways which will open Autometicly .the vent will be
opens when alram is triggered.
the ventilation will be comply with BS 5925and BS5720.
Fire Safety Signs
all sign will accordance with BS ISO 7010.2011
Fire Detection and Alram System
Fire Alarm and detection system will be design in accordance with I.S3218
there will be Portable Fire Extinguisher provide in Accordance with helth and
safety.
DN
DN
DN
DN
A
B
C
D
E
F
G
H
I
J
1 2 3 4 5 6 7 8
9
10
K
M
wc
wc
MCR
office
FAR
GYM
AREA
GYM
STORE
PLANT ROOM
SQUASH COURT
VOID OVER
VOID OVER
SPORTS HALL
VOID OVER
LEISURE POOL
ROOF
VOID OVER
SWIMMING POOL
6000 6000 6000 6000 6000
8000 11330
10000 12245 580
3250600060006000225060006000600060006000
5946
12647
1443
1470
3893
1430
7361
7932
2515
5874
1278
1730
1730
900
840 840
2926
1425
940840
1489
1430
2528
North
1
2
34
8
9
10
11
12
D1=17.16
D2=22.60
KEY PLAN
N
A
B
C
D
E
F
G
H
I
J
1 2 3 4 5 6 7 8
9
10
K
M
wc
wc
MCR
office
FAR
GYM
AREA
GYM
STORE
PLANT ROOM
VOID OVER
SQUASH COURT
VOID OVER
SPORTS HALL
VOID OVER
LEISURE POOL
ROOF
VOID OVER
SWIMMING POOL
6000 6000 6000 6000 6000 8000 11330
10000 12245
580
3250600060006000225060006000
600060006000
5946
12647
1443
1470
3893
1430
7361
7932
2515
5874
1278
1730
1730
900
840 840
2926
1425
940840
1489
1430
2528
North
Plasterboard and Plaster Finish
Spec: 12.5mm thickness and 2.5mm Plaster Skim.
Moisture and Fire Resistance plasterboard.
Fixing: Secured to steel stud via proprietary Clip.
Finish: 2.5mm White plaster skimcoat
Steel Perimeter Columns
Spec: Serial Size - 356mm x 171mm. Kg/m - 67.
Fixing: Concrete Wall Below with holding down
bolts cast in to secure steel columns.
Finish: Lined with Moisture and Fire Registrant
plasterboard and Plaster.
To Comply with Engineers Details, Specs and
Design
Plasterboard and Plaster
Finish
Spec: 12.5mm thickness and
2.5mm Plaster Skim.
Moisture and Fire Resistance
plasterboard.
Steel Perimeter Columns
Spec: Serial Size - 356mm x 171mm.
Kg/m - 67.
Fixing: Concrete Wall Below with holding
down
bolts cast in to secure steel columns.
Structural Screed
Scale
LECTURER
Drawn by
Date
Project number
Institute of Technology Carlow
BSc. in Architectural Technology
Year 3 2016-2017
As indicated
16/11/201713:11:44
DAC & FAC for First Floor
3
Carlow Leisure Centre
28/02/2017
TEJ RAJ UPRETI
NOEL DUNNE/ DAN
O'SULLIVAN/MARK DUFFY
Sheet No- A118
1 : 200
FFP Building REgulation Part 'B'
1
1 : 200
FFL Building Regulation Part 'M'
2
EMERGENCY ESCAPE LIGHTING
there shall be light on all escape routes to
comply with BS 5266-1 and BS 5266-7
30 MIN FIRE RESISTANCE DOOR SET
In Accordance with TGD 'B' table B1 fitted
with intrumescent strips and smoke seal door
set to be fitted with autometic self closing
devicewhich can be capable of closing the
door from any angle against any latch fitted to
comply with TGD'B'.
In this building at least 30 minute fire rated
door lon the corridor and the lobby area.
60 MIN FIRE RESISTANCE DOOR SET
In Accordance with TGD 'B' table B1 fitted
with intrumescent strips and smoke seal door
set to be fitted with autometic self closing
devicewhich can be capable of closing the
door from any angle against any latch fitted to
comply with TGD'B'.
In this building at least 60 minute fire rated
door on the corridor,plant room ,store and
stairs.
HANDRAILS
The Vertical Height To The Top Of The Upper Handrail
From The Pitch Line Of The Surface Of A Flight Should
Be Between 900mm and 1000mm.
This Is In Accordance With Building Regulations Part M,
Section 1.1.3.6 - (Handrails)
There Should Be A Clearance Of At Least 50mm To 60 mm
Between The Handrail And Any Adjacent Wall.
This Is In Accordance With Building Regulations Part M,
Section 1.1.3.6 - (Handrails)
HANDRAILS
The Profile Should Be Either Circular With Diameter Of
Between 40mm To 50mm Or Oval With A Width Of 50mm.
This Is In Accordance With Building Regulations Part M,
Section 1.1.3.6 - (Handrails)
CORRIDORS AND PASSAGEWAYS
This Is In Accordance With Building Regulations Part M,
Section 1.3.3.3 .
Passing Places Should Be Provided Where The
Unobstructed Width Of The Corridor Is Less Than 1800 mm.
Passing Places Should Have A Total Unobstructed Width Of
Corridor Of 1800mm Wide Over An 1800mm Length.
This Is In Accordance With Building Regulations Part M,
Section 1.3.3.3 - (Corridors and passageways)
All Floor Surface Finishes Should Be Slip Resistant. Refer To
Annex E Of BS 8300:2009.
This Is In Accordance With Building Regulations Part M,
Section 1.3.3.3 - (Corridors and passageways)
Passing Places In This Building will Have An Unobstructed Width
Of 2000mm which is Comply with TGD part 'M'.
This Is In Accordance With Building Regulations Part
ACCESS ROUTES
The Minimum Headroom Provided Should Be 2100 mm To
The Underside Of Stairs, Ramps Or Similar Features.
This Is In Accordance With Building Regulations Part M,
1.1.3 - (Access routes)
THE WIDTHS DOOR MUST BE
The Fire Escape Doors Are 1060x2100mm(Clear Width)
The Main Entrance Door Is 1670x2100mm (Clear Width)
the WC must be changed
to comply with TGD M- 1.4Access
& use
accessible WC (1800mmx1800mm
turning space ,comply with TGD 'M'1.4
Effective clear width door 900 mm
comply with TGD 'M' 1.2
The all WC must slip resistant marmoleum or vinyl
floor finish
All switches and shoket-outlets need to be between
900mm-1200mm comply with TGD Part 'M' section 1.5
60 min fire resistant doorset in Accordance with BS476PAd 22 fitted
with intrumescent strip and smoke seals.door set will fitted with autometic
selfclosing devicewhich will be capable of closing the door from any angle
and aginst any latch fitted to this door.
30 min fire resistant doorset in Accordance with BS476PAd 22 fitted
with intrumescent strip and smoke seals.door set will fitted with autometic
selfclosing devicewhich will be capable of closing the door from any angle
and aginst any latch fitted to this door.
Disable refuge Area (1400x900mm )provide with two way communication to the
internal Refuge area.
Emergency Escape lighting to be comply with TGD'B' table 8.installed and certified in
accordance with 2013
1800mmx18mm clear space for wheelchair turning circle
1800mmx18mm clear space for wheelchair turning circle
60 min Protected stairwell in accordance with section TGD
part 'B'A2 ie top story served not more than 5m above ground
level.
Ambulent accessible stair (see note and Detail)
Traval distances
one Direction D1
Two Direction D2
Ambulant disabled Stair Notes
The clear width (between enclosing , string or upstand ) wiil be
1200mm.
the landing will be level and have an unobstructed length (Clear of
any Door swing)of at least 1200mm .
The rise of a fight between landing should not exceed 1800mm.
All steps noisings will be incorporate a permanently contrasting
continuous meterial on the tread.the reminder of the tread a
continuous handrail on each side of flights and landings in
accordance with TGD part 'M' table no.1.1,3.6.
Proposed sanitary facilities provided in accordance with the TGD part 'M'
section 1.4.4.and 1.4.5
30 min Protected Corridors accordance with section TGD
part 'B'A2 ie top story served not more than 5m above ground
level.
Provision of Accessible Sanitary Conveniences
First Floor
one
Unisex Wheelchair Accessible WC Cubicle will be Provided for the Whole
First Floor
60 min Fire resistance Door Set
Use of Facilities within a building
All stories of the building Will Allow for independent Circulation By
People With Disabilities and Independent Access to the Range of
Services and Facilities Provided on that Story .level Access Suitable
For People With Disabilities Will be Provided throughout all storys
of the Building.All internal Circulation Routes Within Each Story Will
be
Free From Steps or slopes.there are all space will be Accessible on
the building.
Aids Of Communication
Suitable aids to Communication will be Available For people with an
impairment hearing or sight in Accordance with TGD 'M' 2010
Paragraph
0.3
Signs
Adequate Signage Will be provided to ensure that people with
Disabilities , including those with an impairment of hearing or vision
can
safely and independently access and use the building and its
fasilities.
Lighting
There will be natural and artificial light on the building , where
artifificial lighting
is Provided is.
• Give Good Colour rendering to all Surface and not Crate
Glare or strong
shadow.
UP
UP
A
B
C
D
E
F
G
H
I
2 3 4 5 6 7 8
9
10M
600060006000
6000
6000
225060006000
1730
900
1430 1430
580
12245
10000
11330
80006000600060006000
6100
1
2
3
4
5
6
7
8
9
10
11
12
13
14 15 16 17 18 19
20
22
23
24
25
26
27 28 29 30
2400
43 m²
459.2 SF
wood pellet boiler store37 m²
398.5 SF
Pool Store
22 m²
241.5 SF
Stair 2
1200 m²
12917.8 SF
Bacemet CAr park
1430
6405
5780 6440
41575
48485
32887
24531
29595
41758
North
35
56 58
67
75
33
D
1=18m
,D
2=21.5m
A
B
C
D
E
F
G
H
I
2 3 4 5 6 7 8
9
10M
600060006000
6000
6000
225060006000
1730
900
1430 1430
580
1224510000
11330
80006000600060006000
6100
1
2
3
4
5
6
7
8
9
10
11
12
13
14 15 16 17 18 19
20
22
23
24
25
26
27 28 29 30
2400
43 m²
459.2 SF
wood pellet boiler store37 m²
398.5 SF
Pool Store
22 m²
241.5 SF
Stair 2
1200 m²
12917.8 SF
Bacemet CAr park
1430
6405
5780 6440
41575
48485
32887
24531
29595
41758
North
1730
4780
1430
KEY PLAN
N
Plasterboard and Plaster Finish
Spec: 12.5mm thickness and 2.5mm Plaster Skim.
Moisture and Fire Resistance plasterboard.
Fixing: Secured to steel stud via proprietary Clip.
Finish: 2.5mm White plaster skimcoat
Steel Perimeter Columns
Spec: Serial Size - 356mm x 171mm. Kg/m - 67.
Fixing: Concrete Wall Below with holding down
bolts cast in to secure steel columns.
Finish: Lined with Moisture and Fire Registrant plasterboard
and Plaster.
To Comply with Engineers Details, Specs and
Design
18mm gyprock fireline plasster bord
steel frame for partition wall
40 mm 60 mint fire door
hinges and screws
50 mm dryline screw
Scale
LECTURER
Drawn by
Date
Project number
Institute of Technology Carlow
BSc. in Architectural Technology
Year 3 2016-2017
As indicated
16/11/201713:12:54
DAC & FSC Bacement
3
Carlow Leisure Centre
28/02/2017
TEJ RAJ UPRETI
NOEL DUNNE/ DAN
O'SULLIVAN/MARK DUFFY
Sheet No- A119
1 : 200
Basement Plan Building Regulation 'B'
1
1 : 200
Basement Plan Building Regulation Part 'm'
2
EMERGENCY ESCAPE LIGHTING
there shall be light on all escape routes to
comply with BS 5266-1 and BS 5266-7
30 MIN FIRE RESISTANCE DOOR SET
In Accordance with TGD 'B' table B1 fitted
with intrumescent strips and smoke seal door
set to be fitted with autometic self closing
devicewhich can be capable of closing the
door from any angle against any latch fitted to
comply with TGD'B'.
In this building at least 30 minute fire rated
door lon the corridor and the lobby area.
60 MIN FIRE RESISTANCE DOOR SET
In Accordance with TGD 'B' table B1 fitted
with intrumescent strips and smoke seal door
set to be fitted with autometic self closing
devicewhich can be capable of closing the
door from any angle against any latch fitted to
comply with TGD'B'.
In this building at least 60 minute fire rated
door on the corridor,plant room ,store and
stairs.
THE WIDTHS DOOR MUST BE
The Fire Escape Doors Are 14300x2100mm(Clear Width)
The Main Entrance Door Is 1700x2100mm (Clear Width)
HANDRAILS
The Vertical Height To The Top Of The Upper Handrail
From The Pitch Line Of The Surface Of A Flight Should
Be Between 900mm and 1000mm.
This Is In Accordance With Building Regulations Part M,
Section 1.1.3.6 - (Handrails)
There Should Be A Clearance Of At Least 50mm To 60 mm
Between The Handrail And Any Adjacent Wall.
This Is In Accordance With Building Regulations Part M,
Section 1.1.3.6 - (Handrails)
HANDRAILS
The Profile Should Be Either Circular With Diameter Of
Between 40mm To 50mm Or Oval With A Width Of 50mm.
This Is In Accordance With Building Regulations Part M,
Section 1.1.3.6 - (Handrails)
CORRIDORS AND PASSAGEWAYS
This Is In Accordance With Building Regulations Part M,
Section 1.3.3.3 .
Passing Places Should Be Provided Where The
Unobstructed Width Of The Corridor Is Less Than 1800 mm.
Passing Places Should Have A Total Unobstructed Width Of
Corridor Of 1800mm Wide Over An 1800mm Length.
This Is In Accordance With Building Regulations Part M,
Section 1.3.3.3 - (Corridors and passageways)
All Floor Surface Finishes Should Be Slip Resistant. Refer To
Annex E Of BS 8300:2009.
This Is In Accordance With Building Regulations Part M,
Section 1.3.3.3 - (Corridors and passageways)
Passing Places In This Building will Have An Unobstructed Width
Of 2000mm which is Comply with TGD part 'M'.
This Is In Accordance With Building Regulations Part
60 min fire resistant doorset in Accordance with BS476PAd 22 fitted
with intrumescent strip and smoke seals.door set will fitted with autometic
selfclosing devicewhich will be capable of closing the door from any angle
and aginst any latch fitted to this door.
30 min fire resistant doorset in Accordance with BS476PAd 22 fitted
with intrumescent strip and smoke seals.door set will fitted with autometic
selfclosing devicewhich will be capable of closing the door from any angle
and aginst any latch fitted to this door.
Disable refuge Area (1400x900mm )provide with two way communication to the
internal Refuge area.
Emergency Escape lighting to be comply with TGD'B' table 8.installed and certified in
accordance with 2013
1800mmx18mm clear space for wheelchair turning circle
1800mmx18mm clear space for wheelchair turning circle
60 min Protected stairwell in accordance with section TGD
part 'B'A2 ie top story served not more than 5m above ground
level.
Ambulent accessible stair (see note and Detail)
Traval distances
one Direction D1
Two Direction D2
Steel columns Beams And Portal frames used in Support load bearig
elements of structure to be Protected to give minimum 90 min fir resistance.
Ambulant disabled Stair Notes
The clear width (between enclosing , string or upstand ) wiil be
1200mm.
the landing will be level and have an unobstructed length (Clear
of any Door swing)of at least 1200mm .
The rise of a fight between landing should not exceed
1800mm.
All steps noisings will be incorporate a permanently contrasting
continuous meterial on the tread.the reminder of the tread a
continuous handrail on each side of flights and landings in
accordance with TGD part 'M' table no.1.1,3.6.
60 min Fire resistance Door Set
1 : 5
60 min Fire Door
5
KEY PLAN
N
GFL
47000
FFL
51500
Sport hall Roof level
56020
Roof
59760
Atrium Level
58997
Green Roof Level
54597
GFL
47000
FFL
51500
4500
Sport hall Roof level
56020
4520
Roof
59760
3740
Atrium Level
58997
Green Roof Level
54597
Scale
LECTURER
Drawn by
Date
Project number
Institute of Technology Carlow
BSc. in Architectural Technology
Year 3 2016-2017
As indicated
16/11/201713:04:22
Elevation
3
Carlow Leisure Centre
28/02/2017
TEJ RAJ UPRETI
NOEL DUNNE/ DAN
O'SULLIVAN/MARK DUFFY
Sheet No- A115
1 : 100
East ELevation
1
1 : 100
South ELevation
2
STONE LITE RAINSCREEN PANEL
Spec: 8 mm stone vineer + backing 20 mm
honeycomb structure
Fixing :propriety hidden fix bracket to horizantal rail.
APA curtain walling systm
Spec: APA curtain walling systm box
150x70mm fitted with pressure plate with 24mm
double glazing curtain wall with U-value 1.00W/m2 k
and fixed with structural column,
Fixing :fixed to circular steel hollow section
GSKY green wall panel
Spec: green wall planting will be native to ireland or
Irish weather .
Fixing :propriety hidden fix bracket to horizantal rail.
NORTH CLAD ALUMINIUM RAINSCREEN
PANEL
Spec:3mm Aluminium composite panels 400mm
X600mm Or 400mmx800mm lightweight cladding
panels ideal for external facades
Fixing :propriety hidden fix bracket to horizantal rail.
fire exit door stonelite cladding
green wall cladding
aluminium cladding (blue)
APA curtain walling systm
kalzip zinc roof
Kalzip zinc roof
Aluminium curtain windows
Stone lite cladding
Northclad Aluminium cladding (Blue)
APA Curtain walling systm
Basement level
Bacement level
GFL
47000
FFL
51500
Sport hall Roof level
56020
Roof
59760
Atrium Level
58997
Green Roof Level
54597
GFL
47000
FFL
51500
Sport hall Roof level
56020
Roof
59760
Atrium Level
58997
Green Roof Level
54597
KEY PLAN
N
Scale
LECTURER
Drawn by
Date
Project number
Institute of Technology Carlow
BSc. in Architectural Technology
Year 3 2016-2017
As indicated
16/11/201713:46:06
ELevation
3
Carlow Leisure Centre
28/02/2017
TEJ RAJ UPRETI
NOEL DUNNE/ DAN
O'SULLIVAN/MARK DUFFY
Sheet No- A116
1 : 100
West ELevation
2
1 : 100
North ELevation
4
STONE LITE RAINSCREEN PANEL
Spec: 8 mm stone vineer + backing 20 mm
honeycomb structure
Fixing :propriety hidden fix bracket to horizantal rail.
APA curtain walling systm
Spec: APA curtain walling systm box
150x70mm fitted with pressure plate with 24mm
double glazing curtain wall with U-value 1.00W/m2 k
and fixed with structural column,
Fixing :fixed to circular steel hollow section
GSKY green wall panel
Spec: green wall planting will be native to ireland or
Irish weather .
Fixing :propriety hidden fix bracket to horizantal rail.
NORTH CLAD ALUMINIUM RAINSCREEN
PANEL
Spec:3mm Aluminium composite panels 400mm
X600mm Or 400mmx800mm lightweight cladding
panels ideal for external facades
Fixing :propriety hidden fix bracket to horizantal rail.
fire exit door
stonelite cladding
green wall cladding
aluminium cladding (blue)
APA curtain walling systm
kalzip zinc roof
Kalzip zinc roof
Aluminium curtain windows
Stone lite cladding
Bacement level
Basement level
APA Curtain walling systm
Basement Level

More Related Content

What's hot

24th Street Passive House Projects
24th Street Passive House Projects24th Street Passive House Projects
24th Street Passive House Projects
TE Studio
 
Solar systems in hestroic building
Solar systems in hestroic buildingSolar systems in hestroic building
Solar systems in hestroic building
Arcreham
 
Commercial Passive House Case Studies
Commercial Passive House Case StudiesCommercial Passive House Case Studies
Commercial Passive House Case Studies
TE Studio
 
Rho-Orion Investments: Our Story
Rho-Orion Investments: Our StoryRho-Orion Investments: Our Story
Rho-Orion Investments: Our Story
Don White
 
David snape solarsense community energy technology installation 300715
David snape solarsense community energy technology installation 300715David snape solarsense community energy technology installation 300715
David snape solarsense community energy technology installation 300715
The Future Economy Network
 
EGing projects references
EGing projects referencesEGing projects references
EGing projects references
Leo Lu
 
Building Enclosures of the Future - Building Tomorrow's Buildings Today
Building Enclosures of the Future - Building Tomorrow's Buildings TodayBuilding Enclosures of the Future - Building Tomorrow's Buildings Today
Building Enclosures of the Future - Building Tomorrow's Buildings Today
RDH Building Science
 
Tall Wood Building Enclosures - A Race To the Top
Tall Wood Building Enclosures - A Race To the TopTall Wood Building Enclosures - A Race To the Top
Tall Wood Building Enclosures - A Race To the Top
RDH Building Science
 
Energy Assignments
Energy AssignmentsEnergy Assignments
Energy AssignmentsEamon Healy
 
Minneapolis Passive House and Zero Energy Ready Home Report Presentation
Minneapolis Passive House and Zero Energy Ready Home Report PresentationMinneapolis Passive House and Zero Energy Ready Home Report Presentation
Minneapolis Passive House and Zero Energy Ready Home Report Presentation
TE Studio
 
2013 University of Minnesota Passive House Lecture
2013 University of Minnesota Passive House Lecture2013 University of Minnesota Passive House Lecture
2013 University of Minnesota Passive House Lecture
TE Studio
 
Canadian Victory Garden: Overview of an Off Grid Solution
Canadian Victory Garden: Overview of an Off Grid SolutionCanadian Victory Garden: Overview of an Off Grid Solution
Canadian Victory Garden: Overview of an Off Grid Solution
Internet Society
 
Karpiak Mulhall Passive House
Karpiak Mulhall Passive HouseKarpiak Mulhall Passive House
Karpiak Mulhall Passive House
Richard Pedranti Architect
 
First Passive House Retrofit in a Cold Climate: The MinnePHit House
First Passive House Retrofit in a Cold Climate: The MinnePHit HouseFirst Passive House Retrofit in a Cold Climate: The MinnePHit House
First Passive House Retrofit in a Cold Climate: The MinnePHit House
TE Studio
 
Intep: 24th St Passive House (Student Workshop #1)
Intep: 24th St Passive House (Student Workshop #1)Intep: 24th St Passive House (Student Workshop #1)
Intep: 24th St Passive House (Student Workshop #1)
TE Studio
 
Domestic solar water heater
Domestic solar water heaterDomestic solar water heater
Domestic solar water heater
venkatesh
 
Good Energy Haus
Good Energy HausGood Energy Haus
Good Energy Haus
TE Studio
 
MinnePHit House Case Study
MinnePHit House Case StudyMinnePHit House Case Study
MinnePHit House Case Study
TE Studio
 
Powertech1
Powertech1Powertech1
Powertech1
powertechshare
 

What's hot (20)

24th Street Passive House Projects
24th Street Passive House Projects24th Street Passive House Projects
24th Street Passive House Projects
 
Solar systems in hestroic building
Solar systems in hestroic buildingSolar systems in hestroic building
Solar systems in hestroic building
 
Commercial Passive House Case Studies
Commercial Passive House Case StudiesCommercial Passive House Case Studies
Commercial Passive House Case Studies
 
Solar water heaters
Solar water heatersSolar water heaters
Solar water heaters
 
Rho-Orion Investments: Our Story
Rho-Orion Investments: Our StoryRho-Orion Investments: Our Story
Rho-Orion Investments: Our Story
 
David snape solarsense community energy technology installation 300715
David snape solarsense community energy technology installation 300715David snape solarsense community energy technology installation 300715
David snape solarsense community energy technology installation 300715
 
EGing projects references
EGing projects referencesEGing projects references
EGing projects references
 
Building Enclosures of the Future - Building Tomorrow's Buildings Today
Building Enclosures of the Future - Building Tomorrow's Buildings TodayBuilding Enclosures of the Future - Building Tomorrow's Buildings Today
Building Enclosures of the Future - Building Tomorrow's Buildings Today
 
Tall Wood Building Enclosures - A Race To the Top
Tall Wood Building Enclosures - A Race To the TopTall Wood Building Enclosures - A Race To the Top
Tall Wood Building Enclosures - A Race To the Top
 
Energy Assignments
Energy AssignmentsEnergy Assignments
Energy Assignments
 
Minneapolis Passive House and Zero Energy Ready Home Report Presentation
Minneapolis Passive House and Zero Energy Ready Home Report PresentationMinneapolis Passive House and Zero Energy Ready Home Report Presentation
Minneapolis Passive House and Zero Energy Ready Home Report Presentation
 
2013 University of Minnesota Passive House Lecture
2013 University of Minnesota Passive House Lecture2013 University of Minnesota Passive House Lecture
2013 University of Minnesota Passive House Lecture
 
Canadian Victory Garden: Overview of an Off Grid Solution
Canadian Victory Garden: Overview of an Off Grid SolutionCanadian Victory Garden: Overview of an Off Grid Solution
Canadian Victory Garden: Overview of an Off Grid Solution
 
Karpiak Mulhall Passive House
Karpiak Mulhall Passive HouseKarpiak Mulhall Passive House
Karpiak Mulhall Passive House
 
First Passive House Retrofit in a Cold Climate: The MinnePHit House
First Passive House Retrofit in a Cold Climate: The MinnePHit HouseFirst Passive House Retrofit in a Cold Climate: The MinnePHit House
First Passive House Retrofit in a Cold Climate: The MinnePHit House
 
Intep: 24th St Passive House (Student Workshop #1)
Intep: 24th St Passive House (Student Workshop #1)Intep: 24th St Passive House (Student Workshop #1)
Intep: 24th St Passive House (Student Workshop #1)
 
Domestic solar water heater
Domestic solar water heaterDomestic solar water heater
Domestic solar water heater
 
Good Energy Haus
Good Energy HausGood Energy Haus
Good Energy Haus
 
MinnePHit House Case Study
MinnePHit House Case StudyMinnePHit House Case Study
MinnePHit House Case Study
 
Powertech1
Powertech1Powertech1
Powertech1
 

Similar to Leisure Center. Part 2

The Eddlington Centre, Eddlington, Doncaster
The Eddlington Centre, Eddlington, DoncasterThe Eddlington Centre, Eddlington, Doncaster
The Eddlington Centre, Eddlington, DoncasterMartyn Watkinson
 
Km34 thermal power generator and solar and wind (wecompress)
Km34 thermal power generator and solar and wind (wecompress)Km34 thermal power generator and solar and wind (wecompress)
Km34 thermal power generator and solar and wind (wecompress)
1000kv technologies
 
Lobel Solar Latetst Specification
Lobel Solar Latetst SpecificationLobel Solar Latetst Specification
Lobel Solar Latetst Specification
L'Obel Solar Power System
 
Building-Integrated PhotovoltaicDesigns.pptx
Building-Integrated PhotovoltaicDesigns.pptxBuilding-Integrated PhotovoltaicDesigns.pptx
Building-Integrated PhotovoltaicDesigns.pptx
DaisyChami1
 
Supply of technology by l'obel solar power system
Supply of technology by l'obel solar power systemSupply of technology by l'obel solar power system
Supply of technology by l'obel solar power system
Chintan Gandhi
 
Bergh 42.585 KW Planset - Final
Bergh 42.585 KW Planset - FinalBergh 42.585 KW Planset - Final
Bergh 42.585 KW Planset - FinalDavid Hults
 
Selleck, Matthew NEDF Built Environment Project
Selleck, Matthew NEDF Built Environment Project Selleck, Matthew NEDF Built Environment Project
Selleck, Matthew NEDF Built Environment Project
MatthewSelleck1
 
Km21 solar powered grass cutting machine (wecompress)
Km21 solar powered grass cutting machine (wecompress)Km21 solar powered grass cutting machine (wecompress)
Km21 solar powered grass cutting machine (wecompress)
1000kv technologies
 
Km67 solar grass dual cutter (wecompress)
Km67 solar grass dual cutter (wecompress)Km67 solar grass dual cutter (wecompress)
Km67 solar grass dual cutter (wecompress)
1000kv technologies
 
Mike's presentation
Mike's presentationMike's presentation
Mike's presentation
Michael Larkin
 
Supply of technology by l'obel solar power system
Supply of technology by l'obel solar power systemSupply of technology by l'obel solar power system
Supply of technology by l'obel solar power system
L'Obel Solar Power System
 
Solar power pv presentation by jmv lps ltd (2)
Solar power pv presentation by jmv lps ltd (2)Solar power pv presentation by jmv lps ltd (2)
Solar power pv presentation by jmv lps ltd (2)
Mahesh Chandra Manav
 
Available Solar Technologies - Susannah Wood (Solarcentury)
Available Solar Technologies - Susannah Wood (Solarcentury)Available Solar Technologies - Susannah Wood (Solarcentury)
Available Solar Technologies - Susannah Wood (Solarcentury)
Farming Futures
 
Hybrid battery +solar pv grid tie power project presentation by jmv lps
Hybrid battery +solar pv grid tie power project presentation by jmv lpsHybrid battery +solar pv grid tie power project presentation by jmv lps
Hybrid battery +solar pv grid tie power project presentation by jmv lps
Mahesh Chandra Manav
 
Appropriate technology part 2
Appropriate technology   part 2Appropriate technology   part 2
Appropriate technology part 2
Shirish Avrani
 
Leisure Centre
Leisure CentreLeisure Centre
Leisure CentreEdel Fox
 
AIA Chicago Presentation
AIA Chicago PresentationAIA Chicago Presentation
AIA Chicago Presentation
Christian Cianfrone
 
Presentation lightning protection system by jmv lps
Presentation lightning protection system by jmv lpsPresentation lightning protection system by jmv lps
Presentation lightning protection system by jmv lps
Mahesh Chandra Manav
 
Worldwide Lightning called as Disaster not as Guest(SACHET)
Worldwide Lightning called as Disaster not as Guest(SACHET)Worldwide Lightning called as Disaster not as Guest(SACHET)
Worldwide Lightning called as Disaster not as Guest(SACHET)
Mahesh Chandra Manav
 

Similar to Leisure Center. Part 2 (20)

The Eddlington Centre, Eddlington, Doncaster
The Eddlington Centre, Eddlington, DoncasterThe Eddlington Centre, Eddlington, Doncaster
The Eddlington Centre, Eddlington, Doncaster
 
Km34 thermal power generator and solar and wind (wecompress)
Km34 thermal power generator and solar and wind (wecompress)Km34 thermal power generator and solar and wind (wecompress)
Km34 thermal power generator and solar and wind (wecompress)
 
Lobel Solar Latetst Specification
Lobel Solar Latetst SpecificationLobel Solar Latetst Specification
Lobel Solar Latetst Specification
 
Building-Integrated PhotovoltaicDesigns.pptx
Building-Integrated PhotovoltaicDesigns.pptxBuilding-Integrated PhotovoltaicDesigns.pptx
Building-Integrated PhotovoltaicDesigns.pptx
 
Supply of technology by l'obel solar power system
Supply of technology by l'obel solar power systemSupply of technology by l'obel solar power system
Supply of technology by l'obel solar power system
 
Bergh 42.585 KW Planset - Final
Bergh 42.585 KW Planset - FinalBergh 42.585 KW Planset - Final
Bergh 42.585 KW Planset - Final
 
Selleck, Matthew NEDF Built Environment Project
Selleck, Matthew NEDF Built Environment Project Selleck, Matthew NEDF Built Environment Project
Selleck, Matthew NEDF Built Environment Project
 
Km21 solar powered grass cutting machine (wecompress)
Km21 solar powered grass cutting machine (wecompress)Km21 solar powered grass cutting machine (wecompress)
Km21 solar powered grass cutting machine (wecompress)
 
Km67 solar grass dual cutter (wecompress)
Km67 solar grass dual cutter (wecompress)Km67 solar grass dual cutter (wecompress)
Km67 solar grass dual cutter (wecompress)
 
Mike's presentation
Mike's presentationMike's presentation
Mike's presentation
 
Supply of technology by l'obel solar power system
Supply of technology by l'obel solar power systemSupply of technology by l'obel solar power system
Supply of technology by l'obel solar power system
 
Solar power pv presentation by jmv lps ltd (2)
Solar power pv presentation by jmv lps ltd (2)Solar power pv presentation by jmv lps ltd (2)
Solar power pv presentation by jmv lps ltd (2)
 
PORTFOLIO-Model
PORTFOLIO-ModelPORTFOLIO-Model
PORTFOLIO-Model
 
Available Solar Technologies - Susannah Wood (Solarcentury)
Available Solar Technologies - Susannah Wood (Solarcentury)Available Solar Technologies - Susannah Wood (Solarcentury)
Available Solar Technologies - Susannah Wood (Solarcentury)
 
Hybrid battery +solar pv grid tie power project presentation by jmv lps
Hybrid battery +solar pv grid tie power project presentation by jmv lpsHybrid battery +solar pv grid tie power project presentation by jmv lps
Hybrid battery +solar pv grid tie power project presentation by jmv lps
 
Appropriate technology part 2
Appropriate technology   part 2Appropriate technology   part 2
Appropriate technology part 2
 
Leisure Centre
Leisure CentreLeisure Centre
Leisure Centre
 
AIA Chicago Presentation
AIA Chicago PresentationAIA Chicago Presentation
AIA Chicago Presentation
 
Presentation lightning protection system by jmv lps
Presentation lightning protection system by jmv lpsPresentation lightning protection system by jmv lps
Presentation lightning protection system by jmv lps
 
Worldwide Lightning called as Disaster not as Guest(SACHET)
Worldwide Lightning called as Disaster not as Guest(SACHET)Worldwide Lightning called as Disaster not as Guest(SACHET)
Worldwide Lightning called as Disaster not as Guest(SACHET)
 

Recently uploaded

Thesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.pptThesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.ppt
EverAndrsGuerraGuerr
 
Palestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptxPalestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptx
RaedMohamed3
 
Introduction to Quality Improvement Essentials
Introduction to Quality Improvement EssentialsIntroduction to Quality Improvement Essentials
Introduction to Quality Improvement Essentials
Excellence Foundation for South Sudan
 
Basic phrases for greeting and assisting costumers
Basic phrases for greeting and assisting costumersBasic phrases for greeting and assisting costumers
Basic phrases for greeting and assisting costumers
PedroFerreira53928
 
Operation Blue Star - Saka Neela Tara
Operation Blue Star   -  Saka Neela TaraOperation Blue Star   -  Saka Neela Tara
Operation Blue Star - Saka Neela Tara
Balvir Singh
 
How to Break the cycle of negative Thoughts
How to Break the cycle of negative ThoughtsHow to Break the cycle of negative Thoughts
How to Break the cycle of negative Thoughts
Col Mukteshwar Prasad
 
The French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free downloadThe French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free download
Vivekanand Anglo Vedic Academy
 
Language Across the Curriculm LAC B.Ed.
Language Across the  Curriculm LAC B.Ed.Language Across the  Curriculm LAC B.Ed.
Language Across the Curriculm LAC B.Ed.
Atul Kumar Singh
 
How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...
Jisc
 
The Art Pastor's Guide to Sabbath | Steve Thomason
The Art Pastor's Guide to Sabbath | Steve ThomasonThe Art Pastor's Guide to Sabbath | Steve Thomason
The Art Pastor's Guide to Sabbath | Steve Thomason
Steve Thomason
 
Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
Celine George
 
PART A. Introduction to Costumer Service
PART A. Introduction to Costumer ServicePART A. Introduction to Costumer Service
PART A. Introduction to Costumer Service
PedroFerreira53928
 
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
MysoreMuleSoftMeetup
 
The geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideasThe geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideas
GeoBlogs
 
Polish students' mobility in the Czech Republic
Polish students' mobility in the Czech RepublicPolish students' mobility in the Czech Republic
Polish students' mobility in the Czech Republic
Anna Sz.
 
Synthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptxSynthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptx
Pavel ( NSTU)
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
siemaillard
 
Sectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdfSectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdf
Vivekanand Anglo Vedic Academy
 
GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...
GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...
GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...
Nguyen Thanh Tu Collection
 
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
EugeneSaldivar
 

Recently uploaded (20)

Thesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.pptThesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.ppt
 
Palestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptxPalestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptx
 
Introduction to Quality Improvement Essentials
Introduction to Quality Improvement EssentialsIntroduction to Quality Improvement Essentials
Introduction to Quality Improvement Essentials
 
Basic phrases for greeting and assisting costumers
Basic phrases for greeting and assisting costumersBasic phrases for greeting and assisting costumers
Basic phrases for greeting and assisting costumers
 
Operation Blue Star - Saka Neela Tara
Operation Blue Star   -  Saka Neela TaraOperation Blue Star   -  Saka Neela Tara
Operation Blue Star - Saka Neela Tara
 
How to Break the cycle of negative Thoughts
How to Break the cycle of negative ThoughtsHow to Break the cycle of negative Thoughts
How to Break the cycle of negative Thoughts
 
The French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free downloadThe French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free download
 
Language Across the Curriculm LAC B.Ed.
Language Across the  Curriculm LAC B.Ed.Language Across the  Curriculm LAC B.Ed.
Language Across the Curriculm LAC B.Ed.
 
How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...
 
The Art Pastor's Guide to Sabbath | Steve Thomason
The Art Pastor's Guide to Sabbath | Steve ThomasonThe Art Pastor's Guide to Sabbath | Steve Thomason
The Art Pastor's Guide to Sabbath | Steve Thomason
 
Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
 
PART A. Introduction to Costumer Service
PART A. Introduction to Costumer ServicePART A. Introduction to Costumer Service
PART A. Introduction to Costumer Service
 
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
 
The geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideasThe geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideas
 
Polish students' mobility in the Czech Republic
Polish students' mobility in the Czech RepublicPolish students' mobility in the Czech Republic
Polish students' mobility in the Czech Republic
 
Synthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptxSynthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptx
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
 
Sectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdfSectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdf
 
GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...
GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...
GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...
 
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
 

Leisure Center. Part 2

  • 1. Basement Car Park KEY PLAN N Scale LECTURER Drawn by Date Project number Institute of Technology Carlow BSc. in Architectural Technology Year 3 2016-2017 1 : 1000 15/11/201713:30:10 building section 3D 3 Carlow Leisure Centre 28/02/2017 TEJ RAJ UPRETI NOEL DUNNE/ DAN O'SULLIVAN/MARK DUFFY Sheet No- A106 leisure centre 3D 4 A B Precast concrete floor slab Spec: 200mm thickness. With edge thickening and steel reinforced. All Gaps filled with lean mix concrete before insulation install Structural Concrete Screed Spec: 100mm Thickness. All columns wrapped in compressible insulation layer to meet screed height. Movement joints also to be accommodated. With edge thickening and steel reinforced To Comply with Engineers Details, Specs and Design. Fixing: Poured on top of insulation. Plasterboard and Plaster Finish Spec: 12.5mm thickness and 2.5mm Plaster Skim. Moisture Resistance plasterboard. Fixing: Secured to steel structure behind. Finish: 2.5mm White plaster skimcoat APA curtain walling systm Spec: APA curtain walling systm box 150x70mm fitted with pressure plate with 24mm double glazing curtain wall with U-value 1.00W/m2 k and fixed with structural column, Fixing :fixed to circular steel hollow section Aluminium slidding door Torch on membrane finish flat roof intensive Green roof North clad Aluminium cladding APA curtain walling systm Spec: APA curtain walling systm box 150x70mm fitted with pressure plate with 24mm double glazing curtain wall with U-value 1.00W/m2 k and fixed with structural column, STONE LITE RAINSCREEN PANEL Spec: 8 mm stone vineer + backing 20 mm honeycomb structure 3D Building Section 1 Building Long Section 3D 2 GSKY green wall panel Spec: green wall planting will be native to ireland or Irish weather . Fixing :propriety hidden fix bracket to horizantal rail. Steel Perimeter Columns Spec: Serial Size - 356mm x 171mm. Kg/m - 67. Fixing: Concrete Wall Below with holding down bolts cast in to secure steel columns. To Comply with Engineers Details, Specs and Design. Existing Bridge River Barrow Basement Car Park Main Swimming Pool sports hall plant room Gym Changing room Leisure Pool intensive Green roof plant room Basement Car Park Changing room Gym Gym Changing room 3D prespective view of Leisure Swimming Pool 3D prespective view of Rear Entrance 3D prespective view North Elevation3D prespective view of West Elevation 3D prespective view of Section C-C3D prespective view of `Section A-A A B Ambulant disabled Stair Cafe Area plant room plant room Atrium Atrium Atrium 1400x2200mm Fire Escape Door Torch on membrane finish flat roof Torch on membrane finish flat roof intensive Green roof
  • 2. North Entrance River Barrow Existing Bridge Existing Apartment Existing Town hall Cox's Lane BarrowTrack Carlow Town park Rainwater harvesting tank HH H H MH1 MH2 MH3 MH5 fire assembly point fire assembly point KEY PLAN N GFL 47000 FFL 51500 Sport hall Roof level 56020 Roof 59760 Atrium Level 58997 Green Roof Level 54597 Inverter Battery pack Scale LECTURER Drawn by Date Project number Institute of Technology Carlow BSc. in Architectural Technology Year 3 2016-2017 As indicated 16/11/201713:17:27 Building Services 3 Carlow Leisure Centre 28/02/2017 TEJ RAJ UPRETI NOEL DUNNE/ DAN O'SULLIVAN/MARK DUFFY Sheet No- A124 PHOTOVOLTIC PANEL Pv Technology produces electricity directly from electrons freed by the interaction of sunlight with a solar panel made of semiconductor material. The power provided is direct current (DC) electricity. The basic building block is known as solar cell. Many cells puts together are known as a module and many modules assembled together from an array. A PV system will consist of an array of modules generating DC electricity.an inverter and can be stored in battery storage banks Advantages PV panels provide clean – green energy. During electricity generation with PV panels there is no harmful greenhouse gas emissions thus solar PV is environmentally friendly. Solar energy is energy supplied by nature – it is thus free and abundant! Solar energy can be made available almost anywhere there is sunlight PV panels have no mechanically moving parts, except in cases of –sun-tracking mechanical bases; consequently they have far less breakages or require less maintenance than other renewable energy systems (e.g. wind turbines) PV panels are totally silent, producing no noise at all; consequently, they are a perfect solution for urban areas and for residential applications (see solar panels for home) Economical with little to no running cost. Disadvantages As in all renewable energy sources, solar energy has intermittency issues; not shining at night but also during daytime there may be cloudy or rainy weather. Consequently, intermittency and unpredictability of solar energy makes solar energy panels less reliable a solution. Solar energy panels require additional equipment (inverters) to convert direct electricity (DC) to alternating electricity (AC) in order to be used on the power network. For a continuous supply of electric power, especially for on- grid connections, Photovoltaic panels require not only Inverters but also storage batteries; thus increasing the investment cost for PV panels considerably In case of land-mounted PV panel installations, they require relatively large areas for deployment; usually the land space is committed for this purpose for a period of 15-20 years – or even longer. safeguard a PV investment. How its integrated? I’m using a grid system photovoltics panel on my roof .these are connected to utility grid and feed power. Many cells puts together are known as a module and many modules assembled together from an array. A PV system will consist of an array of modules generating DC electricity.an inverter and can be stored in battery storage banks.the power produced by the PV sysem can either suppy electrical loads in to the building or be fed back into the grid when the PV systems output is greater than the load demand .i have include my calculation with my report. solar PV System Diagram 1 : 500 Site Plan (Services ) 1 Mains Water Supply line Gas supply MH Manhole ESB Supply Line Site Boundry Line H Water hydrant location Fire Assembly Point legend Roof Slope General Design Notes: All works to comply with all current, building regulations and codes of Practice. Design Guidance is taken from Sports England Documents and also The Metric Handbook, TGD'L',TGD 'k,' TGD'B', TGD'M', BS:9999. All works to be passed by building Control officer inspections. Cast in-situ concrete to comply with BS 8004. Steel reinforcement & structural steel Frame to engineer’s details &design. architect's Office for clarification. SUNSINE AND SOLAR RADIATION Ireland normally gets between 1100-1600 hours of sunshine each year the sunniest months may-June. During these months, sunshine duration averages between 5-6.5 hours per day most part of the country. The southeast of Ireland gets the most sunshine average over 7 hours a day in the early summer. December is the dullest month, with an average sunshine from about 1 hour in north and 2 hour in the south east The orientation of the building The orientation of building that I have chosen to propose is directly north east as it optimise the use passive heating and co0lling techniques among with renewable technology. There is more glazing area on the south east elevation which will allow natural light and heat from the sun. The buildings south elevation side has an existing apartment so it needs to be 1 hour fire rated wall but south east side I have put high performance triple glazed curtain walling . Wind Direction in Ireland Average Temperature in Carlow Average Rainfall in Carlow mono-crystaline PV panel autometic wall mounted light control devices will be Every 6M on the room like (Bathroom, Corridor etc) mono-crystaline PV panel OVERSHADING FACTOR None or very little = 1 1 module = 1.65 M2 = .235 kpeak 258 module = 1.65 x 258 = 425 M2 calculate the total peak power of all panels = 425 x 0.235 kpeak = 100 kwp calculate the total peak power of south oriantation panel Total panel on south side = 258panel = 258 x 0.235 = 60kwp The Annual output would be output (kwp) = 0.8 x 60 x 1072 x 1 =51456 kwh 1 : 100 Section E-E 2 AC isolator Mains AC isolator Distribution board Load 45 RAIN WATER HARVESTING SYSTEM PV PANEL LED LIGHT All existing light need to be replaced with new LED light on the building .which will get the immersion powered by Pv panel . All light is connected with autometic wall mounted light control devices on every 10 Metre range. There would be mono-crystaline PV panel on the roof.The panel will be S/W and N/W oriantation with 15 degrees slope.there would be Mono -cristaling (kingspan) 258 panel ,size will be 1.65m2 module 100 wpeak. There would be 100,000 ltr Stainless Steel tank on the site ( see site plan) which would be conneted with another tank on the roof level which water will be use for toilet flushing. the moter will get the immersion powered by PV panel. Eco flush toilet All Toilet will have Eco tank Flush Tank. there will be use Rain water From Rain water harvesting tank will be use for toilet flushing. All Tap Will be Contemporary Sensor Tap Automatic Touchless Bathroom Sink Tap Mixer
  • 3. Basement Car Park KEY PLAN N Scale LECTURER Drawn by Date Project number Institute of Technology Carlow BSc. in Architectural Technology Year 3 2016-2017 1 : 1000 15/11/201713:30:10 building section 3D 3 Carlow Leisure Centre 28/02/2017 TEJ RAJ UPRETI NOEL DUNNE/ DAN O'SULLIVAN/MARK DUFFY Sheet No- A106 leisure centre 3D 4 A B Precast concrete floor slab Spec: 200mm thickness. With edge thickening and steel reinforced. All Gaps filled with lean mix concrete before insulation install Structural Concrete Screed Spec: 100mm Thickness. All columns wrapped in compressible insulation layer to meet screed height. Movement joints also to be accommodated. With edge thickening and steel reinforced To Comply with Engineers Details, Specs and Design. Fixing: Poured on top of insulation. Plasterboard and Plaster Finish Spec: 12.5mm thickness and 2.5mm Plaster Skim. Moisture Resistance plasterboard. Fixing: Secured to steel structure behind. Finish: 2.5mm White plaster skimcoat APA curtain walling systm Spec: APA curtain walling systm box 150x70mm fitted with pressure plate with 24mm double glazing curtain wall with U-value 1.00W/m2 k and fixed with structural column, Fixing :fixed to circular steel hollow section Aluminium slidding door Torch on membrane finish flat roof intensive Green roof North clad Aluminium cladding APA curtain walling systm Spec: APA curtain walling systm box 150x70mm fitted with pressure plate with 24mm double glazing curtain wall with U-value 1.00W/m2 k and fixed with structural column, STONE LITE RAINSCREEN PANEL Spec: 8 mm stone vineer + backing 20 mm honeycomb structure 3D Building Section 1 Building Long Section 3D 2 GSKY green wall panel Spec: green wall planting will be native to ireland or Irish weather . Fixing :propriety hidden fix bracket to horizantal rail. Steel Perimeter Columns Spec: Serial Size - 356mm x 171mm. Kg/m - 67. Fixing: Concrete Wall Below with holding down bolts cast in to secure steel columns. To Comply with Engineers Details, Specs and Design. Existing Bridge River Barrow Basement Car Park Main Swimming Pool sports hall plant room Gym Changing room Leisure Pool intensive Green roof plant room Basement Car Park Changing room Gym Gym Changing room 3D prespective view of Leisure Swimming Pool 3D prespective view of Rear Entrance 3D prespective view North Elevation3D prespective view of West Elevation 3D prespective view of Section C-C3D prespective view of `Section A-A A B Ambulant disabled Stair Cafe Area plant room plant room Atrium Atrium Atrium 1400x2200mm Fire Escape Door Torch on membrane finish flat roof Torch on membrane finish flat roof intensive Green roof
  • 4. BSc in Architectural Technology Year 3: 2016 - 2017 Scale LECTURER Drawn by Date Project number 16/11/201713:22:23 3D Building 3 28/02/2017 TEJ RAJ UPRETI NOEL DUNNE/ DAN O'SULLIVAN/MARK DUFFY Sheet No- A127 South West 3d View 1 North west 3D View 2 North East 3D View 3 South West 3D View 4 APA curtain walling systm Spec: APA curtain walling systm box 150x70mm fitted with pressure plate with 24mm double glazing curtain wall with U-value 1.00W/m2 k and fixed with structural column, Fixing :fixed to circular steel hollow section Aluminium slidding door Torch on membrane finish flat roof APA curtain walling systm Spec: APA curtain walling systm box 150x70mm fitted with pressure plate with 24mm double glazing curtain wall with U-value 1.00W/m2 k and fixed with structural column, Fixing :fixed to circular steel hollow section STONE LITE RAINSCREEN PANEL Spec: 8 mm stone vineer + backing 20 mm honeycomb structure Fixing :propriety hidden fix bracket to horizantal rail APA curtain walling systm Spec: APA curtain walling systm box 150x70mm fitted with pressure plate with 24mm double glazing curtain wall with U-value 1.00W/m2 k and fixed with structural column, Fixing :fixed to circular steel hollow section GSKY green wall panel Spec: green wall planting will be native to ireland or Irish weather . Fixing :propriety hidden fix bracket to horizantal rail. APA curtain walling systm Spec: APA curtain walling systm box 150x70mm fitted with pressure plate with 24mm double glazing curtain wall with U-value 1.00W/m2 k and fixed with structural column, Fixing :fixed to circular steel hollow section APA curtain walling systm Spec: APA curtain walling systm box 150x70mm fitted with pressure plate with 24mm double glazing curtain wall with U-value 1.00W/m2 k and fixed with structural column, Fixing :fixed to circular steel hollow section GSKY green wall panel Spec: green wall planting will be native to ireland or Irish weather . Fixing :propriety hidden fix bracket to horizantal rail. STONE LITE RAINSCREEN PANEL Spec: 8 mm stone vineer + backing 20 mm honeycomb structure Fixing :propriety hidden fix bracket to horizantal rail STONE LITE RAINSCREEN PANEL Spec: 8 mm stone vineer + backing 20 mm honeycomb structure Fixing :propriety hidden fix bracket to horizantal rail Aluminium Cladding Fixing: Proprietary Hidden Fix System Cement plaster board through PIR Insulation via Z-Girt Bracket. Finish: ALUMINIUM CLADDING WITH BLUE COLOUR FINISH. Zinc roof STONE LITE RAINSCREEN PANEL Spec: 8 mm stone vineer + backing 20 mm honeycomb structure Fixing :propriety hidden fix bracket to horizantal rail Aluminium slidding door Roof Light Intensive Green roof intensive Green roof Aluminium Cladding Fixing: Proprietary Hidden Fix System Cement plaster board through PIR Insulation via Z-Girt Bracket. Finish: ALUMINIUM CLADDING WITH BLUE COLOUR FINISH. Aluminium Cladding Fixing: Proprietary Hidden Fix System Cement plaster board through PIR Insulation via Z-Girt Bracket. Finish: ALUMINIUM CLADDING WITH BLUE COLOUR FINISH. Curtain Walling At North Ambulant Disabled Concrete Stairwell Full Length of Curtain walling at East Stairwell 350 mm Cast in place concrete Raft Foundation intensive Green roof intensive Green roof Torch on membrane finish flat roof Zinc roof 6500mmx3000mm opening to Enter and Exit Car Park 1400x2200mm Fire Escape Door 1400x2200mm Fire Escape Door
  • 5. North Entrance River Barrow Existing Bridge Existing Apartment Existing Town hall Cox's Lane BarrowTrack Carlow Town park Rainwater harvesting tank HH H H MH1 MH2 MH3 MH5 fire assembly point fire assembly point KEY PLAN N 98151200 598 Scale LECTURER Drawn by Date Project number Institute of Technology Carlow BSc. in Architectural Technology Year 3 2016-2017 As indicated 16/11/201713:16:26 Sustainable Service Strategy 3 Carlow Leisure Centre 28/02/2017 TEJ RAJ UPRETI NOEL DUNNE/ DAN O'SULLIVAN/MARK DUFFY Sheet No- A123 SUNSINE AND SOLAR RADIATION Ireland normally gets between 1100-1600 hours of sunshine each year the sunniest months may-June. During these months, sunshine duration averages between 5-6.5 hours per day most part of the country. The southeast of Ireland gets the most sunshine average over 7 hours a day in the early summer. December is the dullest month, with an average sunshine from about 1 hour in north and 2 hour in the south east The orientation of the building The orientation of building that I have chosen to propose is directly north east as it optimise the use passive heating and co0lling techniques among with renewable technology. There is more glazing area on the south east elevation which will allow natural light and heat from the sun. The buildings south elevation side has an existing apartment so it needs to be 1 hour fire rated wall but south east side I have put high performance triple glazed curtain walling . Rainwater harvesting system In this building have a large amount of clear roof space collecting it and recycling water will be no problem. Water collected from the roof will be filtered with and stored in a 40000 m3 tank located in the building site. This filtered clean water will be pumped to much smaller tank on the roof so this water will be use as flushing toilet and urinals on the building .while outdoor water can be feed directly from the outdoor tank This system will be very useful for my building .I have include my calculation for rainwater harvesting system you can see Wood pellet boiler Biomass is a form of renewable energy that can reduce our reliance on fossil fuels. Instead of burning fossil fuels for energy, biomass uses organic materials. These organic materials are derived from a variety of sources. Wood sources such as trees are commonly used, but energy crops, food waste or industrial waste can also be exploited as fuel in biomass heating. The fuel is burned in boilers and stoves and the energy generated heats water and space. Stoves generally are only useful to heat one room, whereas boilers are able to heat whole properties. Rather than burning expensive oil or gas the boiler burns wood pellets instead The boiler will have 3 main parts the boiler, the hopper and the store. The wood pallets are kept in the store. And the hopper automatically adds them to the boiler, to minimise the amount of work. The wood pallet is fuel, just like gas or oil. Only this is more environmentally friendly and renewable energy. And cheaper to burn . Advantages Biomass is considered a carbon neutral form of energy because the carbon dioxide released when it is burned is only that which was absorbed by the plant during its life. Therefore there is no gain or loss of carbon dioxide. It is high efficient system The pallets are produced from west material Another financial benefit of using biomass boilers for heating is that there is less exposure to the fluctuations of the energy market Disadvantage Installing a biomass boiler or stove is not cheap Requires a lot of storage space. Need regular cleaning and maintenance How its integrated: The wood pellet boiler will be stored in the basement level in the plant room .i have done the calculation include my report. All of the sizes are worked out making it the Deciding factor in which I chose this system in the leisure centre. Suppose total energy required is =805000kwh Step 2: Calculate quantity of pellets required to meet the above energy demand for the building. Use thumb rule: Energy content of 1 kg pellet= approx. 5 kWh So for 805000 kwh ,?kg pellet ,=805000/5 =161000 kgs.or 161 tonnes Step 3: Calculate the total cost for using pellets Use thumb rule: €230 per tonne (Bulk Pellets) and€299 per tonne (Bagged Pellets) Ie,230 x161 =37030 euros. Step4: Calculate the total volume of pellets used Use thumb rule:1 m³ pellets = 650 kg So for 161000 kg of pellets total volume= 161000/650= 247.5m3. Step 5: Calculate total volume required for pellet store =Total volume of pellet used * 3/2……if total storage =x then 2/3 *x = 248 or ie, x = 248*3/2= 372 m3 Step 6: Calculate Total heat demand Use Thumb rule:Per 1 kW heat demand = 0.9 m³ of the space (incl. empty space) So for 372 m3 of pellets it is 372/ 0.9 = 413KW Ventilation Stack ventilation uses temperature differences to move air. Hot air rises because it is lower pressure. Cool air is sucked in through low intent openings and hotter exhaust air escape through outlet openings. The ventilation rate is proportional to the area of openings. Placing opening at the bottom and top of an open space will encourage natural ventilation through a stack ventilation. Advantages This system will improved air quality in a building. It will improved ventilation in a building Economical with little running cost. Energy saving as there is no need for HAVC system to cool the building. Environmentally friendly. Limitations The air on the outside must be cooler then the air inside for the stack ventilation to work Risk of cold bridging (need to be insulated) How I integrated: The stack ventilation will be placed at the top of the atrium in the leisure centre building which will allow the hot air pass through to the outside Therefore bringing in new fresh air keeping the building ventilated. Where there is atrium in a building stack ventilation is the best strategy to use as they have a large difference in height between air inlets and outlets.so stack will be start from basement to atrium level. 3D Building with Glazing Unit 3 Proposed curtain walling to allow natural light into the space, with proposed passivent aircool ventilators to allow natural ventiltion into the GYM. Proposed curtain walling to allow natural light into the space, with proposed passivent aircool ventilators to allow natural ventiltion into the Pool. Rainwater Harvesting System Diagram Stack Ventilation system 1 : 500 Site Plan For Services 1 Mains Water Supply line Gas supply MH Manhole ESB Supply Line Site Boundry Line H Water hydrant location Fire Assembly Point legend Roof Slope Wind Direction in Ireland Average Temperature in Carlow Average Rainfall in Carlow RAIN WATER HARVESTING SYSTEM average rainfal in carlow =1200 l/m2 Roof Area =600m2 correction factor=0.9 Annual rainwater yield = 1200x600x0.9 = 648000 L/year Annual rain water demand . for 50 person flush toilet per person = 11800x200 = 2360000 cleaning per person = 800x200 = 160000 Total =2520000 = 91133.24 Tank size will be 100000 L 2360000+648000 x21 days Tank size = 2x365 General Design Notes: All works to comply with all current, building regulations and codes of Practice. Design Guidance is taken from Sports England Documents and also The Metric Handbook, TGD'L',TGD 'k,' TGD'B', TGD'M', BS:9999. All works to be passed by building Control officer inspections. Cast in-situ concrete to comply with BS 8004. Steel reinforcement & structural steel Frame to engineer’s details &design. architect's Office for clarification. 1 : 20 aluminium cladding with Ventilation on Basement 4 ventilation Grill Prefabricated Steel vent Grate fitted to wall but not Fixed (removable for maintanence Purpose Paving Stone kerb 100x160mm Paving Stone 40x200mm layed to fall of 1:50, sand Brushed between stone to allow water Penetration Geotextile Membrane
  • 6. A B C D E F G H I J 1 2 3 4 5 6 7 8 9 10 K M 60006000 6000 6000 6000 6000 6000 8000 11330 22245 580 60006000600060006000225032506000 600060006000 2591 404 m² 4351.6 SF Sports Hall 12 m² 125.0 SF Store Hall Store 18 m² 197.2 SF Male Changing 19 m² 200.8 SF Female Changing 24 m² 258.9 SF Female changing 26 m² 282.8 SF Male Changing wc wc Cafe Reception area 23903 17087 1907 892892 17081692 3376 4786 2734 2499 2457 5875 11514 7838 5830 6842 5621 3827 26802635 30972 16697 19787 2185 1730 1730 5230 4633 4546 5013 2185 1430 1430 1275 1690 840 1730 1730 2008 940 1430 1430 940 940 940 933 840 1763 2410 1730 1730 1730 1536 1422 2850 8536 1999 1999 1999 1730 1830 1339 900 1780 835 1430 1900 1241 24690 13785 1038 940928 67 m² 721.2 SF Squash Court 67 m² 721.2 SF Squash Court 68 m² 729.3 SF Squash Court 14 m² 153.0 SF First Aid 6 m² 66.4 SF Store Room 13 m² 140.0 SF Office 307 m² 3309.2 SF Leisure Pool 340 m² 3663.5 SF Main Pool 38 m² 406.2 SF Pool Store 10 m² 104.3 SF Sauna Room 10 m² 106.1 SF Steam Room 45 m² 483.3 SF Plant Room 57 m² 617.6 SF Changing Village 23 m² 247.5 SF Female Toilts 22 m² 236.3 SF Male Toilets 1200 36 34 7 10911 17 16 14 5 6 35 12 13 2 3 4 15 KEY PLAN N 10080150 10280150 13 13 Plasterboard and Plaster Finish Spec: 12.5mm thickness and 2.5mm Plaster Skim. Moisture and Fire Resistance plasterboard. Fixing: Secured to steel stud via proprietary Clip. Finish: 2.5mm White plaster skimcoat Steel Perimeter Columns Spec: Serial Size - 356mm x 171mm. Kg/m - 67. Fixing: Concrete Wall Below with holding down bolts cast in to secure steel columns. Finish: Lined with Moisture and Fire Registrant plasterboard and Plaster. To Comply with Engineers Details, Specs and Design Scale LECTURER Drawn by Date Project number Institute of Technology Carlow BSc. in Architectural Technology Year 3 2016-2017 As indicated 16/11/201713:14:25 FSC Ground Floor 3 Carlow Leisure Centre 28/02/2017 TEJ RAJ UPRETI NOEL DUNNE/ DAN O'SULLIVAN/MARK DUFFY Sheet No- A120 1 : 200 GFL Building Regulation part 'B' 1 EMERGENCY ESCAPE LIGHTING there shall be light on all escape routes to comply with BS 5266-1 and BS 5266-7 30 MIN FIRE RESISTANCE DOOR SET In Accordance with TGD 'B' table B1 fitted with intrumescent strips and smoke seal door set to be fitted with autometic self closing devicewhich can be capable of closing the door from any angle against any latch fitted to comply with TGD'B'. In this building at least 30 minute fire rated door lon the corridor and the lobby area. 60 MIN FIRE RESISTANCE DOOR SET In Accordance with TGD 'B' table B1 fitted with intrumescent strips and smoke seal door set to be fitted with autometic self closing devicewhich can be capable of closing the door from any angle against any latch fitted to comply with TGD'B'. In this building at least 60 minute fire rated door on the corridor,plant room ,store and stairs. 60 min fire resistant doorset in Accordance with BS476PAd 22 fitted with intrumescent strip and smoke seals.door set will fitted with autometic selfclosing devicewhich will be capable of closing the door from any angle and aginst any latch fitted to this door. 30 min fire resistant doorset in Accordance with BS476PAd 22 fitted with intrumescent strip and smoke seals.door set will fitted with autometic selfclosing devicewhich will be capable of closing the door from any angle and aginst any latch fitted to this door. Disable refuge Area (1400x900mm )provide with two way communication to the internal Refuge area. Emergency Escape lighting to be comply with TGD'B' table 8.installed and certified in accordance with 2013 1800mmx18mm clear space for wheelchair turning circle 60 min Protected stairwell in accordance with section TGD part 'B'A2 ie top story served not more than 5m above ground level. Traval distances one Direction D1 Two Direction D2 Stair 3D 2 1 : 10 internal Partition wall 3 100 mm self leveling Structural Screed 150 mm Precast concrete hollowcore floor slab has a span of 9 M corebord to fix Steel Channel to 100 mm cold rolled Ceiling chanel to support the Vertical Chanel Fastener Strap Double Slabbed standard 2x12.5 mm fire rated plaster board.60 min fire rated. Double Slabbed standard 2x12.5 mm fire rated plaster board. 100 mm steel vertical studpartition for service zone. Gypsum active air suspended ceiling tile 600x600 suspended with Aluminium Tracks and hanging with Steel wire suspended from Steel Beam Double Slabbed standard 2x12.5 mm fire rated plaster board.60 min fire rated. 150 mm Precast concrete hollowcore floor slab has a span of 9 M 100 mm self leveling Structural Screed 80 mm rigid insulation on the floor for sound 80 mm rigid insulation on the floor for sound 4mm Marmoleum floor finish Double Slabbed standard 2x12.5 mm fire rated plaster board.60 min fire rated. Structural Steel Beam Encasment Structural Steel column encasment 30min Protected stairwell in accordance with section TGD part 'B'A2 ie top story served not more than 5m above ground level. 60 min Fire resistance Door Set All Doors Leading from stairwell will be 60 min fire reted Stairwell is Constructed with 350mm wall with 2x12.5 mm gypsum pasterbord 60min fire rated Lobby To Stairwell constructed with 60 min fire rated with 60 min partition fited with 60 min fire door Autometic Opening vent at the top of Each stair well opens when alram is triggered Ambulant disabled Stair Notes The clear width (between enclosing , string or upstand ) wiil be 1200mm. the landing will be level and have an unobstructed length (Clear of any Door swing)of at least 1200mm . Section 1: Means of Escape in case of Fire All Area of the building and Occupancy of the Building calculated with the methological approach of the building with comply with TGD'B' Clauses 1.0.10 SECTION B5 External fire Main The Hydraint are Designed and maintained in accordance with BS5306 Part 1. Vehicle access Vehicle Access roure including manhole or other covers accordance with TGD part 'B' Overhead obstruction such as cables that would be set with ladders. Provision of switches A fire fighter Emergency switch will be Provide at beside plant Room . Escape stairways 1,2&3 will have autometic opening vent it is indicate in site plan. All autometic opening vents will be automatically activate if smoke detectors in the stairway enclosure are activate . Section B4-External Fire Spread external wall construction The main walls are Constructed of steel with Cold Rolled Multichanel Beam (secondary Structure ) Between those chanel there will be mineral Quilt Insulation with PIR rigid insulation . there will be Rockwool insulation on intermediate Floor level . Sprinkler Systems The intensity of radiation from a fire in the compartment which is fitted throughout with a sprinkler systm will be accordance with TGD part 'B' 4.2.8.2 the sprincal system will meet the BS 5306 part 2 1990. Section B2 -Internal Fire Spread(linings) walls The surfae of the wall in in a room ,bathroom Changing room etc will be lower but it will comply with class D-s3,d2(european) windows external windows to room glazed with thermoplastic metterials.the internal glazing will in accorance with TGD'B' paragraph 2.1. Roof Lights All roof light to rooms , circulation space can be construction with thermo plastic material comply with TGD'B' paragrapf A15 and Appendix A. Section B3 -Internal Fire Spread Forms of Compartmentation This building is Assembly and Recration purpose group 5.on the Ground Floor has more than the requirement minimium of Apx 1900 m2 in Area.therefore it will be three Compartment Area shown on Drawing Above. Construction of Compartment Floors and walls there will be complete fire barrier to between the compartments they will separate the construction in accordance with the TGD'B'3.2.5.1 to 3.2.5.11 . Separating walls All separating walls will comply with the TGD'B' 3.2.5.7. Openings between compartments All Door opening in compartment walls will be protechted by means of fire door in accordance with Appendix B and table B1of the TGD 'B' the passage of pipes ,ventilation Ductsor more Services will be construct in accordance with TGD'B'3.4. construction of Protechted shaft it will have have the Appropriate Fire resistance in Accordance with TGD'B' Appendix A table A1. all compartments wall will be comply with TGD'B; section 3.2.7.3 There will be three zone in the building Zone 1 :swimming pool area and its facilities Zone 2:the middle part of building including changing room ,wc reception area, cafe squash court gym etc Zone 3: sport hall also include storage which is only accessible from sport hall this zone has its own direct escape to the outside . Escape Stairways All escape stairways will be comply with TGD'B' 1.3.6.2. to 1.3.6.6. Fire Door Assemblies All fire Door need to be cirtified before Fitting in accordance with BS476part 8. Automatilc Door the main Automatic slidding door will be comply with BS7036 Floor Surface of Escape Route All stairs , rams and landing will be comply with TGD'K'and 'M'.also the escape route surface nedd to be sleep resistant finish. Ventilation there will be ventilation on all Stairways which will open Autometicly .the vent will be opens when alram is triggered. the ventilation will be comply with BS 5925and BS5720. Fire Safety Signs all sign will accordance with BS ISO 7010.2011 Fire Detection and Alram System Fire Alarm and detection system will be design in accordance with I.S3218 there will be Portable Fire Extinguisher provide in Accordance with helth and safety.
  • 7. DN DN DN DN A B C D E F G H I J 1 2 3 4 5 6 7 8 9 10 K M wc wc MCR office FAR GYM AREA GYM STORE PLANT ROOM SQUASH COURT VOID OVER VOID OVER SPORTS HALL VOID OVER LEISURE POOL ROOF VOID OVER SWIMMING POOL 6000 6000 6000 6000 6000 8000 11330 10000 12245 580 3250600060006000225060006000600060006000 5946 12647 1443 1470 3893 1430 7361 7932 2515 5874 1278 1730 1730 900 840 840 2926 1425 940840 1489 1430 2528 North 1 2 34 8 9 10 11 12 D1=17.16 D2=22.60 KEY PLAN N A B C D E F G H I J 1 2 3 4 5 6 7 8 9 10 K M wc wc MCR office FAR GYM AREA GYM STORE PLANT ROOM VOID OVER SQUASH COURT VOID OVER SPORTS HALL VOID OVER LEISURE POOL ROOF VOID OVER SWIMMING POOL 6000 6000 6000 6000 6000 8000 11330 10000 12245 580 3250600060006000225060006000 600060006000 5946 12647 1443 1470 3893 1430 7361 7932 2515 5874 1278 1730 1730 900 840 840 2926 1425 940840 1489 1430 2528 North Plasterboard and Plaster Finish Spec: 12.5mm thickness and 2.5mm Plaster Skim. Moisture and Fire Resistance plasterboard. Fixing: Secured to steel stud via proprietary Clip. Finish: 2.5mm White plaster skimcoat Steel Perimeter Columns Spec: Serial Size - 356mm x 171mm. Kg/m - 67. Fixing: Concrete Wall Below with holding down bolts cast in to secure steel columns. Finish: Lined with Moisture and Fire Registrant plasterboard and Plaster. To Comply with Engineers Details, Specs and Design Plasterboard and Plaster Finish Spec: 12.5mm thickness and 2.5mm Plaster Skim. Moisture and Fire Resistance plasterboard. Steel Perimeter Columns Spec: Serial Size - 356mm x 171mm. Kg/m - 67. Fixing: Concrete Wall Below with holding down bolts cast in to secure steel columns. Structural Screed Scale LECTURER Drawn by Date Project number Institute of Technology Carlow BSc. in Architectural Technology Year 3 2016-2017 As indicated 16/11/201713:11:44 DAC & FAC for First Floor 3 Carlow Leisure Centre 28/02/2017 TEJ RAJ UPRETI NOEL DUNNE/ DAN O'SULLIVAN/MARK DUFFY Sheet No- A118 1 : 200 FFP Building REgulation Part 'B' 1 1 : 200 FFL Building Regulation Part 'M' 2 EMERGENCY ESCAPE LIGHTING there shall be light on all escape routes to comply with BS 5266-1 and BS 5266-7 30 MIN FIRE RESISTANCE DOOR SET In Accordance with TGD 'B' table B1 fitted with intrumescent strips and smoke seal door set to be fitted with autometic self closing devicewhich can be capable of closing the door from any angle against any latch fitted to comply with TGD'B'. In this building at least 30 minute fire rated door lon the corridor and the lobby area. 60 MIN FIRE RESISTANCE DOOR SET In Accordance with TGD 'B' table B1 fitted with intrumescent strips and smoke seal door set to be fitted with autometic self closing devicewhich can be capable of closing the door from any angle against any latch fitted to comply with TGD'B'. In this building at least 60 minute fire rated door on the corridor,plant room ,store and stairs. HANDRAILS The Vertical Height To The Top Of The Upper Handrail From The Pitch Line Of The Surface Of A Flight Should Be Between 900mm and 1000mm. This Is In Accordance With Building Regulations Part M, Section 1.1.3.6 - (Handrails) There Should Be A Clearance Of At Least 50mm To 60 mm Between The Handrail And Any Adjacent Wall. This Is In Accordance With Building Regulations Part M, Section 1.1.3.6 - (Handrails) HANDRAILS The Profile Should Be Either Circular With Diameter Of Between 40mm To 50mm Or Oval With A Width Of 50mm. This Is In Accordance With Building Regulations Part M, Section 1.1.3.6 - (Handrails) CORRIDORS AND PASSAGEWAYS This Is In Accordance With Building Regulations Part M, Section 1.3.3.3 . Passing Places Should Be Provided Where The Unobstructed Width Of The Corridor Is Less Than 1800 mm. Passing Places Should Have A Total Unobstructed Width Of Corridor Of 1800mm Wide Over An 1800mm Length. This Is In Accordance With Building Regulations Part M, Section 1.3.3.3 - (Corridors and passageways) All Floor Surface Finishes Should Be Slip Resistant. Refer To Annex E Of BS 8300:2009. This Is In Accordance With Building Regulations Part M, Section 1.3.3.3 - (Corridors and passageways) Passing Places In This Building will Have An Unobstructed Width Of 2000mm which is Comply with TGD part 'M'. This Is In Accordance With Building Regulations Part ACCESS ROUTES The Minimum Headroom Provided Should Be 2100 mm To The Underside Of Stairs, Ramps Or Similar Features. This Is In Accordance With Building Regulations Part M, 1.1.3 - (Access routes) THE WIDTHS DOOR MUST BE The Fire Escape Doors Are 1060x2100mm(Clear Width) The Main Entrance Door Is 1670x2100mm (Clear Width) the WC must be changed to comply with TGD M- 1.4Access & use accessible WC (1800mmx1800mm turning space ,comply with TGD 'M'1.4 Effective clear width door 900 mm comply with TGD 'M' 1.2 The all WC must slip resistant marmoleum or vinyl floor finish All switches and shoket-outlets need to be between 900mm-1200mm comply with TGD Part 'M' section 1.5 60 min fire resistant doorset in Accordance with BS476PAd 22 fitted with intrumescent strip and smoke seals.door set will fitted with autometic selfclosing devicewhich will be capable of closing the door from any angle and aginst any latch fitted to this door. 30 min fire resistant doorset in Accordance with BS476PAd 22 fitted with intrumescent strip and smoke seals.door set will fitted with autometic selfclosing devicewhich will be capable of closing the door from any angle and aginst any latch fitted to this door. Disable refuge Area (1400x900mm )provide with two way communication to the internal Refuge area. Emergency Escape lighting to be comply with TGD'B' table 8.installed and certified in accordance with 2013 1800mmx18mm clear space for wheelchair turning circle 1800mmx18mm clear space for wheelchair turning circle 60 min Protected stairwell in accordance with section TGD part 'B'A2 ie top story served not more than 5m above ground level. Ambulent accessible stair (see note and Detail) Traval distances one Direction D1 Two Direction D2 Ambulant disabled Stair Notes The clear width (between enclosing , string or upstand ) wiil be 1200mm. the landing will be level and have an unobstructed length (Clear of any Door swing)of at least 1200mm . The rise of a fight between landing should not exceed 1800mm. All steps noisings will be incorporate a permanently contrasting continuous meterial on the tread.the reminder of the tread a continuous handrail on each side of flights and landings in accordance with TGD part 'M' table no.1.1,3.6. Proposed sanitary facilities provided in accordance with the TGD part 'M' section 1.4.4.and 1.4.5 30 min Protected Corridors accordance with section TGD part 'B'A2 ie top story served not more than 5m above ground level. Provision of Accessible Sanitary Conveniences First Floor one Unisex Wheelchair Accessible WC Cubicle will be Provided for the Whole First Floor 60 min Fire resistance Door Set Use of Facilities within a building All stories of the building Will Allow for independent Circulation By People With Disabilities and Independent Access to the Range of Services and Facilities Provided on that Story .level Access Suitable For People With Disabilities Will be Provided throughout all storys of the Building.All internal Circulation Routes Within Each Story Will be Free From Steps or slopes.there are all space will be Accessible on the building. Aids Of Communication Suitable aids to Communication will be Available For people with an impairment hearing or sight in Accordance with TGD 'M' 2010 Paragraph 0.3 Signs Adequate Signage Will be provided to ensure that people with Disabilities , including those with an impairment of hearing or vision can safely and independently access and use the building and its fasilities. Lighting There will be natural and artificial light on the building , where artifificial lighting is Provided is. • Give Good Colour rendering to all Surface and not Crate Glare or strong shadow.
  • 8. UP UP A B C D E F G H I 2 3 4 5 6 7 8 9 10M 600060006000 6000 6000 225060006000 1730 900 1430 1430 580 12245 10000 11330 80006000600060006000 6100 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 22 23 24 25 26 27 28 29 30 2400 43 m² 459.2 SF wood pellet boiler store37 m² 398.5 SF Pool Store 22 m² 241.5 SF Stair 2 1200 m² 12917.8 SF Bacemet CAr park 1430 6405 5780 6440 41575 48485 32887 24531 29595 41758 North 35 56 58 67 75 33 D 1=18m ,D 2=21.5m A B C D E F G H I 2 3 4 5 6 7 8 9 10M 600060006000 6000 6000 225060006000 1730 900 1430 1430 580 1224510000 11330 80006000600060006000 6100 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 22 23 24 25 26 27 28 29 30 2400 43 m² 459.2 SF wood pellet boiler store37 m² 398.5 SF Pool Store 22 m² 241.5 SF Stair 2 1200 m² 12917.8 SF Bacemet CAr park 1430 6405 5780 6440 41575 48485 32887 24531 29595 41758 North 1730 4780 1430 KEY PLAN N Plasterboard and Plaster Finish Spec: 12.5mm thickness and 2.5mm Plaster Skim. Moisture and Fire Resistance plasterboard. Fixing: Secured to steel stud via proprietary Clip. Finish: 2.5mm White plaster skimcoat Steel Perimeter Columns Spec: Serial Size - 356mm x 171mm. Kg/m - 67. Fixing: Concrete Wall Below with holding down bolts cast in to secure steel columns. Finish: Lined with Moisture and Fire Registrant plasterboard and Plaster. To Comply with Engineers Details, Specs and Design 18mm gyprock fireline plasster bord steel frame for partition wall 40 mm 60 mint fire door hinges and screws 50 mm dryline screw Scale LECTURER Drawn by Date Project number Institute of Technology Carlow BSc. in Architectural Technology Year 3 2016-2017 As indicated 16/11/201713:12:54 DAC & FSC Bacement 3 Carlow Leisure Centre 28/02/2017 TEJ RAJ UPRETI NOEL DUNNE/ DAN O'SULLIVAN/MARK DUFFY Sheet No- A119 1 : 200 Basement Plan Building Regulation 'B' 1 1 : 200 Basement Plan Building Regulation Part 'm' 2 EMERGENCY ESCAPE LIGHTING there shall be light on all escape routes to comply with BS 5266-1 and BS 5266-7 30 MIN FIRE RESISTANCE DOOR SET In Accordance with TGD 'B' table B1 fitted with intrumescent strips and smoke seal door set to be fitted with autometic self closing devicewhich can be capable of closing the door from any angle against any latch fitted to comply with TGD'B'. In this building at least 30 minute fire rated door lon the corridor and the lobby area. 60 MIN FIRE RESISTANCE DOOR SET In Accordance with TGD 'B' table B1 fitted with intrumescent strips and smoke seal door set to be fitted with autometic self closing devicewhich can be capable of closing the door from any angle against any latch fitted to comply with TGD'B'. In this building at least 60 minute fire rated door on the corridor,plant room ,store and stairs. THE WIDTHS DOOR MUST BE The Fire Escape Doors Are 14300x2100mm(Clear Width) The Main Entrance Door Is 1700x2100mm (Clear Width) HANDRAILS The Vertical Height To The Top Of The Upper Handrail From The Pitch Line Of The Surface Of A Flight Should Be Between 900mm and 1000mm. This Is In Accordance With Building Regulations Part M, Section 1.1.3.6 - (Handrails) There Should Be A Clearance Of At Least 50mm To 60 mm Between The Handrail And Any Adjacent Wall. This Is In Accordance With Building Regulations Part M, Section 1.1.3.6 - (Handrails) HANDRAILS The Profile Should Be Either Circular With Diameter Of Between 40mm To 50mm Or Oval With A Width Of 50mm. This Is In Accordance With Building Regulations Part M, Section 1.1.3.6 - (Handrails) CORRIDORS AND PASSAGEWAYS This Is In Accordance With Building Regulations Part M, Section 1.3.3.3 . Passing Places Should Be Provided Where The Unobstructed Width Of The Corridor Is Less Than 1800 mm. Passing Places Should Have A Total Unobstructed Width Of Corridor Of 1800mm Wide Over An 1800mm Length. This Is In Accordance With Building Regulations Part M, Section 1.3.3.3 - (Corridors and passageways) All Floor Surface Finishes Should Be Slip Resistant. Refer To Annex E Of BS 8300:2009. This Is In Accordance With Building Regulations Part M, Section 1.3.3.3 - (Corridors and passageways) Passing Places In This Building will Have An Unobstructed Width Of 2000mm which is Comply with TGD part 'M'. This Is In Accordance With Building Regulations Part 60 min fire resistant doorset in Accordance with BS476PAd 22 fitted with intrumescent strip and smoke seals.door set will fitted with autometic selfclosing devicewhich will be capable of closing the door from any angle and aginst any latch fitted to this door. 30 min fire resistant doorset in Accordance with BS476PAd 22 fitted with intrumescent strip and smoke seals.door set will fitted with autometic selfclosing devicewhich will be capable of closing the door from any angle and aginst any latch fitted to this door. Disable refuge Area (1400x900mm )provide with two way communication to the internal Refuge area. Emergency Escape lighting to be comply with TGD'B' table 8.installed and certified in accordance with 2013 1800mmx18mm clear space for wheelchair turning circle 1800mmx18mm clear space for wheelchair turning circle 60 min Protected stairwell in accordance with section TGD part 'B'A2 ie top story served not more than 5m above ground level. Ambulent accessible stair (see note and Detail) Traval distances one Direction D1 Two Direction D2 Steel columns Beams And Portal frames used in Support load bearig elements of structure to be Protected to give minimum 90 min fir resistance. Ambulant disabled Stair Notes The clear width (between enclosing , string or upstand ) wiil be 1200mm. the landing will be level and have an unobstructed length (Clear of any Door swing)of at least 1200mm . The rise of a fight between landing should not exceed 1800mm. All steps noisings will be incorporate a permanently contrasting continuous meterial on the tread.the reminder of the tread a continuous handrail on each side of flights and landings in accordance with TGD part 'M' table no.1.1,3.6. 60 min Fire resistance Door Set 1 : 5 60 min Fire Door 5
  • 9. KEY PLAN N GFL 47000 FFL 51500 Sport hall Roof level 56020 Roof 59760 Atrium Level 58997 Green Roof Level 54597 GFL 47000 FFL 51500 4500 Sport hall Roof level 56020 4520 Roof 59760 3740 Atrium Level 58997 Green Roof Level 54597 Scale LECTURER Drawn by Date Project number Institute of Technology Carlow BSc. in Architectural Technology Year 3 2016-2017 As indicated 16/11/201713:04:22 Elevation 3 Carlow Leisure Centre 28/02/2017 TEJ RAJ UPRETI NOEL DUNNE/ DAN O'SULLIVAN/MARK DUFFY Sheet No- A115 1 : 100 East ELevation 1 1 : 100 South ELevation 2 STONE LITE RAINSCREEN PANEL Spec: 8 mm stone vineer + backing 20 mm honeycomb structure Fixing :propriety hidden fix bracket to horizantal rail. APA curtain walling systm Spec: APA curtain walling systm box 150x70mm fitted with pressure plate with 24mm double glazing curtain wall with U-value 1.00W/m2 k and fixed with structural column, Fixing :fixed to circular steel hollow section GSKY green wall panel Spec: green wall planting will be native to ireland or Irish weather . Fixing :propriety hidden fix bracket to horizantal rail. NORTH CLAD ALUMINIUM RAINSCREEN PANEL Spec:3mm Aluminium composite panels 400mm X600mm Or 400mmx800mm lightweight cladding panels ideal for external facades Fixing :propriety hidden fix bracket to horizantal rail. fire exit door stonelite cladding green wall cladding aluminium cladding (blue) APA curtain walling systm kalzip zinc roof Kalzip zinc roof Aluminium curtain windows Stone lite cladding Northclad Aluminium cladding (Blue) APA Curtain walling systm Basement level Bacement level
  • 10. GFL 47000 FFL 51500 Sport hall Roof level 56020 Roof 59760 Atrium Level 58997 Green Roof Level 54597 GFL 47000 FFL 51500 Sport hall Roof level 56020 Roof 59760 Atrium Level 58997 Green Roof Level 54597 KEY PLAN N Scale LECTURER Drawn by Date Project number Institute of Technology Carlow BSc. in Architectural Technology Year 3 2016-2017 As indicated 16/11/201713:46:06 ELevation 3 Carlow Leisure Centre 28/02/2017 TEJ RAJ UPRETI NOEL DUNNE/ DAN O'SULLIVAN/MARK DUFFY Sheet No- A116 1 : 100 West ELevation 2 1 : 100 North ELevation 4 STONE LITE RAINSCREEN PANEL Spec: 8 mm stone vineer + backing 20 mm honeycomb structure Fixing :propriety hidden fix bracket to horizantal rail. APA curtain walling systm Spec: APA curtain walling systm box 150x70mm fitted with pressure plate with 24mm double glazing curtain wall with U-value 1.00W/m2 k and fixed with structural column, Fixing :fixed to circular steel hollow section GSKY green wall panel Spec: green wall planting will be native to ireland or Irish weather . Fixing :propriety hidden fix bracket to horizantal rail. NORTH CLAD ALUMINIUM RAINSCREEN PANEL Spec:3mm Aluminium composite panels 400mm X600mm Or 400mmx800mm lightweight cladding panels ideal for external facades Fixing :propriety hidden fix bracket to horizantal rail. fire exit door stonelite cladding green wall cladding aluminium cladding (blue) APA curtain walling systm kalzip zinc roof Kalzip zinc roof Aluminium curtain windows Stone lite cladding Bacement level Basement level APA Curtain walling systm Basement Level