SlideShare a Scribd company logo
1 of 45
Canals
INTRODUCTION
A canal is defined as an artificial channel
constructed on the ground to carry water from a
river or another canal or a reservoir to the fields.
Types of Canals
TYPES OF CANALS
(Based on Source of Supply)
• Continuous source of water
supply.
• Also called perennial canals
Permanent
Canal
• Draws its supplies from a
river only during the high
stages of the river.
Inundation
Canal
TYPES OF CANALS
(Based on Function)
• Carries water from its source to
agricultural fields.
Irrigation
Canal
• Used for transport of goods.
Navigation
Canal
• Used to carry water for
generation of hydroelectricity.
Power Canal
• Feeds two or more canals.
Feeder Canal
Note, a canal can serve more than one purpose.
TYPES OF CANALS
(Based on Alignment)
Watershed Canal or
Ridge Canal
Contour Canal
Side Slope Canal
Watershed canal or Ridge canal
The canal which is aligned along any natural
watershed (ridge line) is called a watershed canal,
or a ridge canal.
Watershed canal or Ridge canal (Contd.)
Aligning a canal (main canal or branch canal or
distributary) on the ridge ensures gravity irrigation on both
sides of the canal.
 Since the drainage flows away from the ridge, no
drainage can cross a canal aligned on the ridge.
Thus, a canal aligned on the watershed saves the cost of
construction of cross-drainage works.
Watershed canal or Ridge canal (Contd.)
Pranamesh Chakraborty
Contour Canal
Watershed canal along the ridge line are not
found economical in hill areas. In hills, the river
flows in the valley well below the watershed.
In fact, the ridge line (watershed) may be
hundred of meters above the river. It therefore
becomes virtually impossible to take the canal on
top of such a higher ridge line. In such conditions,
contour canals are usually constructed.
A contour canal irrigates only on one side
because the area on the other side is higher.
Contour Canal (Contd.)
Side Slope Canal
A side slope canal is that which is aligned at
right angles to the contours; i.e. along the side
slopes.
Since such a canal runs parallel to the natural
drainage flow, it usually does not intercept
drainage channels, thus avoiding the construction
of cross-drainage structures.
It is a canal which is aligned roughly at right
angle to contours of the country but not on
watershed or valley.
Side Slope Canal (Contd.)
Types of Canals
(BASED ON DISCHARGE)
Main Canal
Branch Canal
Major Distributary
Minor Distributary
Water Course
MAIN CANAL
Main Canal takes off directly from the upstream
side of weir head works or dam.
Usually no direct cultivation is proposed
BRANCH CANAL
All offtakes from main canal with head discharge of
14-15 cumecs and above are termed as branch canals.
Acts as feeder channel for major distributaries
MAJOR DISTRIBUTARY
 All offtakes from main canal or branch canal with head
discharge from 0.25 to 15 cumecs are termed as major distributa
MINOR DISTRIBUTARY
 All offtakes taking off from a major distributary
carrying discharge less than 0.25 cumec are termed as
minor distributaries
WATER COURSE
 Small channels which carry water from the outlets of
a major or minor distributary or a branch canal to the
fields to be irrigated.
Types of Canals
(Based on lining provided or not)
• Bed and banks made up of natural soil.
• Water velocities higher than 0.7 m/s
are not tolerable.
• High seepage and conveyance water
losses.
• Profuse growth of aquatic weeds
retards the flow .
Unlined
Canal
• Lining of impervious material on its bed
and banks to prevent the seepage of
water.
• Different types of lining used e.g.
concrete, brick or burnt clay tile,
boulder, etc.
Lined
Canal
A PICTURE OF A UNLINED CANAL
A PICTURE OF A LINED CANAL
Canal Alignment
General consideration for alignment:-
1. It should be aligned in such a way that maximum area is
served with the least length. And its cost including CD- work
is minimum.
2. A shorter length of canal has less loss of head due to friction
and smaller loss of water due to seepage and evaporation, so
that additional area can be brought under cultivation.
3. The alignment should be kept straight as far as possible, it
will result in minimum losses.
4. It should have minimum CD work.
Canal Alignment
General consideration for alignment:-
5. It should not passes through the village, town, forest or
costly lands, otherwise heavily compensation shall have
to given.
6. It should be such that heavy cutting and filling
(embankment) are avoided.
7. It should through passes the ridge so that both side of
canal can be irrigated.
8. The alignment should be such that as far as possible a
balanced depth of cutting and filling is achieved.
9. The alignment should not be made in rocky, brackish or
cracked strata.
Cross-Section of Irrigation
Canal
A canal is generally taken in such a way that its
section is partly in cutting and partly in filling in
order to approach close to balancing depth. Many
times however the canal has to be carried through
deep cutting or filling.
A canal structure may, therefore, either :
1. In Cutting
2. In Filling
3. In Partial Cutting and Filling.
Cross-section of canal
Cross-section of canal:-
Cross-section of canal:-
Cross-section of canal:-
A canal section will be economical when earth
work involved at a particular section has an equal
amount of cut and fill. Usually a canal section has
a part in cutting and part in filling as shown in fig.
If the amount of cut is equal to the amount of fill,
it has to be paid for once only.
Definition:-
For a given C/S there is always only one depth of
cutting for which the cutting and filling will be
equal. The depth is known as balancing depth.
Balancing Depth
Balancing Depth:-
If :-
h = vertical height of top of bank from the
bed of canal.
b = bed width of the channel.
t = top width of the canal bank.
n:1 = side slope of bank in filling.
z:1 = side slope of canal in cutting.
d = full supply depth of canal.
y = depth of cutting.
Balancing Depth:-
Area of the cut = by + zy2
= y(b + zy)
Area of fill = 2[(h – y)t + n(h-y)2 ]
Equating the area of cut and fill:
y(b + z y) = 2[(h – y)t + n(h-y)2 ]
b y+ zy2 = 2th + 2nh2 – 2nhy – 2ty – 2nhy + 2ny2
y2 (2n – z) – (b + 4nh + 2t)y + 2h(t + nh) =0
From this equation the balancing depth of the canal may be
determined.
Balancing Depth
A canal is usually constructed with side slope of 1:1 in cutting and
a slope 1.5:1 in filling.
Putting n = 1.5 and z =1 in above equation.
We get;
y2 – (b/2 + 3h + t)y + h (t + 3/2 h)=0
Balancing Depth
Components of Cross- Section
 Side slope
 Berm
 Freeboard
 Bank
 Service road
 Back Berm or Counter Berm
 Spoil Bank
 Borrow Pit
Side Slope
The side slopes should be such that they are stable,
depending upon the type of the soil.
A comparatively steeper slope can be provided in
cutting rather than in filling, as the soil in the former
case shall be more stable.
Berm
Berm is the horizontal distance left at ground level
between the toe of the bank and the top edge of
cutting.
Berm (contd.)
Purposes of Berms:
 They give additional strength to the banks and
provide protection against erosion and breaches.
 They protect the banks from erosion due to wave
action.
 They provide a scope for future widening of the
canal.
Freeboard
The margin between FSL and bank level is known as
freeboard. The amount of freeboard depends upon the
discharge of the channel.
Bank
The primary purpose of banks in to retain water.
This can be used as means of communication and
as inspection paths.
Service Road
Service roads are provided on canals for inspection
purposes, and may simultaneously serve as the means
of communication in remote areas.
Dowla: As a measure of safety in driving, dowlas
with side slopes of 1.5: 1 to 2:1, are provided along
the banks.
Back Berm or Counter Berm
Even after providing sufficient section for bank
embankment, the saturation gradient line may cut the
downstream end of the bank. In such a case, the saturation
line can be kept covered at least by 0.5 m with the help of
counter berms as shown in figure below.
Spoil Bank
When the earthwork in excavation exceeds earthworks
in filling, the extra earth has to be disposed of
economically.
Economical mode of its disposal may be collecting
this soil on the edge of the bank embankment itself.
Borrow Pit
When earthwork in filling exceeds the earthwork in
excavation, the earth has to be brought from
somewhere.
The pits, which are dug for bringing earth, are
known as borrow pits.
If such pits are excavated outside the channel, they
are known as external borrow pits, and if they are
excavated somewhere within the channel, they are
known as internal borrow pits.
Internal borrow pits are more preferred than
external one.
Borrow Pit (Contd.)
The inside borrow pit may be located at the centre
of canal. The idea behind this is that the borrow pits
will act as water pockets where the silt will be
deposited and ultimately the canal bed will get
levelled up.

More Related Content

What's hot (20)

River training method
River training methodRiver training method
River training method
 
A presentation on irrigation engineering
A presentation on irrigation engineeringA presentation on irrigation engineering
A presentation on irrigation engineering
 
Cross section of the canal, balancing depth and canal fsl
Cross section of the canal, balancing depth  and canal fslCross section of the canal, balancing depth  and canal fsl
Cross section of the canal, balancing depth and canal fsl
 
1. reservoirs unit !
1. reservoirs   unit !1. reservoirs   unit !
1. reservoirs unit !
 
Reservoir Planning
Reservoir PlanningReservoir Planning
Reservoir Planning
 
Dams
DamsDams
Dams
 
Water requirements of crops
Water requirements of cropsWater requirements of crops
Water requirements of crops
 
Canal alignment
Canal alignmentCanal alignment
Canal alignment
 
Canal lining
Canal liningCanal lining
Canal lining
 
S curve hydrograph
S curve hydrographS curve hydrograph
S curve hydrograph
 
Diversion head works
Diversion head worksDiversion head works
Diversion head works
 
Spillways
SpillwaysSpillways
Spillways
 
Canal
CanalCanal
Canal
 
Highway Drainage (Highway Engineering)
Highway Drainage (Highway Engineering)Highway Drainage (Highway Engineering)
Highway Drainage (Highway Engineering)
 
Canal of design
Canal of designCanal of design
Canal of design
 
Storage head works
Storage head worksStorage head works
Storage head works
 
Methos of irrigation
Methos  of  irrigationMethos  of  irrigation
Methos of irrigation
 
Synthetic unit hydrograph
Synthetic unit hydrographSynthetic unit hydrograph
Synthetic unit hydrograph
 
Duty And Delta
Duty And DeltaDuty And Delta
Duty And Delta
 
Canal & canal types with design of channels by dj sir covered kennedy lacey t...
Canal & canal types with design of channels by dj sir covered kennedy lacey t...Canal & canal types with design of channels by dj sir covered kennedy lacey t...
Canal & canal types with design of channels by dj sir covered kennedy lacey t...
 

Similar to Unit 4-canal

08. Classification of Canals.pdf
08. Classification of Canals.pdf08. Classification of Canals.pdf
08. Classification of Canals.pdfMuhammadAjmal326519
 
Canal irrigation
Canal irrigationCanal irrigation
Canal irrigationSAGAR RAUT
 
WREII Canals Head Works and Distribution system
WREII Canals Head Works and Distribution systemWREII Canals Head Works and Distribution system
WREII Canals Head Works and Distribution systemMitaliShelke
 
Canal irrigation (Mr. Kiran B. Mane)
Canal irrigation (Mr. Kiran B. Mane)Canal irrigation (Mr. Kiran B. Mane)
Canal irrigation (Mr. Kiran B. Mane)Kiran Mane
 
Irrigation Engg Lec 03.pptx
Irrigation Engg Lec 03.pptxIrrigation Engg Lec 03.pptx
Irrigation Engg Lec 03.pptxAliFurqan6
 
• Sediment Transport • The Earthen Canal Section • Lined Canals & Its Advantages
• Sediment Transport • The Earthen Canal Section • Lined Canals & Its Advantages• Sediment Transport • The Earthen Canal Section • Lined Canals & Its Advantages
• Sediment Transport • The Earthen Canal Section • Lined Canals & Its Advantagesabdqadeer
 
CIV_604_IHS-6th_CIVIL-Chapter-3_Notes.pdf
CIV_604_IHS-6th_CIVIL-Chapter-3_Notes.pdfCIV_604_IHS-6th_CIVIL-Chapter-3_Notes.pdf
CIV_604_IHS-6th_CIVIL-Chapter-3_Notes.pdfRamenRoyAEKHSD2PWRD
 
Module 03 Distribution Works.pptx
Module 03 Distribution Works.pptxModule 03 Distribution Works.pptx
Module 03 Distribution Works.pptxSilasChaudhari
 
presentation of industrial training irrigation (2).pptx
presentation of industrial training irrigation (2).pptxpresentation of industrial training irrigation (2).pptx
presentation of industrial training irrigation (2).pptxMaloth3
 
Canal Regulation & Canal Types
Canal Regulation & Canal TypesCanal Regulation & Canal Types
Canal Regulation & Canal TypesAbbasZafar3
 

Similar to Unit 4-canal (20)

08. Classification of Canals.pdf
08. Classification of Canals.pdf08. Classification of Canals.pdf
08. Classification of Canals.pdf
 
Canal Irrigation
Canal IrrigationCanal Irrigation
Canal Irrigation
 
Canal irrigation
Canal irrigationCanal irrigation
Canal irrigation
 
WREII Canals Head Works and Distribution system
WREII Canals Head Works and Distribution systemWREII Canals Head Works and Distribution system
WREII Canals Head Works and Distribution system
 
Canal irrigation (Mr. Kiran B. Mane)
Canal irrigation (Mr. Kiran B. Mane)Canal irrigation (Mr. Kiran B. Mane)
Canal irrigation (Mr. Kiran B. Mane)
 
Irrigation canals
Irrigation canalsIrrigation canals
Irrigation canals
 
Irrigation Channels
Irrigation ChannelsIrrigation Channels
Irrigation Channels
 
Canals
CanalsCanals
Canals
 
Irrigation Engg Lec 03.pptx
Irrigation Engg Lec 03.pptxIrrigation Engg Lec 03.pptx
Irrigation Engg Lec 03.pptx
 
Canal
CanalCanal
Canal
 
Canal irrigation
Canal irrigationCanal irrigation
Canal irrigation
 
Geotech alignment of canal
Geotech alignment of canalGeotech alignment of canal
Geotech alignment of canal
 
Gt ppt
Gt pptGt ppt
Gt ppt
 
• Sediment Transport • The Earthen Canal Section • Lined Canals & Its Advantages
• Sediment Transport • The Earthen Canal Section • Lined Canals & Its Advantages• Sediment Transport • The Earthen Canal Section • Lined Canals & Its Advantages
• Sediment Transport • The Earthen Canal Section • Lined Canals & Its Advantages
 
CIV_604_IHS-6th_CIVIL-Chapter-3_Notes.pdf
CIV_604_IHS-6th_CIVIL-Chapter-3_Notes.pdfCIV_604_IHS-6th_CIVIL-Chapter-3_Notes.pdf
CIV_604_IHS-6th_CIVIL-Chapter-3_Notes.pdf
 
Module-5.pptx
Module-5.pptxModule-5.pptx
Module-5.pptx
 
Module 03 Distribution Works.pptx
Module 03 Distribution Works.pptxModule 03 Distribution Works.pptx
Module 03 Distribution Works.pptx
 
presentation of industrial training irrigation (2).pptx
presentation of industrial training irrigation (2).pptxpresentation of industrial training irrigation (2).pptx
presentation of industrial training irrigation (2).pptx
 
Canal irrigation
Canal irrigationCanal irrigation
Canal irrigation
 
Canal Regulation & Canal Types
Canal Regulation & Canal TypesCanal Regulation & Canal Types
Canal Regulation & Canal Types
 

More from saibabu48

Design of-steel-structures bhavakkati- by easy engineering.net
Design of-steel-structures bhavakkati- by easy engineering.netDesign of-steel-structures bhavakkati- by easy engineering.net
Design of-steel-structures bhavakkati- by easy engineering.netsaibabu48
 
Sr bolted and welded conviction
Sr bolted and welded convictionSr bolted and welded conviction
Sr bolted and welded convictionsaibabu48
 
Iii design-of-steel-structures-unit-1
Iii design-of-steel-structures-unit-1Iii design-of-steel-structures-unit-1
Iii design-of-steel-structures-unit-1saibabu48
 
Iii design-of-steel-structures-unit-2
Iii design-of-steel-structures-unit-2Iii design-of-steel-structures-unit-2
Iii design-of-steel-structures-unit-2saibabu48
 
Ce 6603-dss-qb
Ce 6603-dss-qbCe 6603-dss-qb
Ce 6603-dss-qbsaibabu48
 
Ce6603 design of steel structures qb
Ce6603 design of steel structures qbCe6603 design of steel structures qb
Ce6603 design of steel structures qbsaibabu48
 
Dss notebook pdf someones
Dss notebook pdf someonesDss notebook pdf someones
Dss notebook pdf someonessaibabu48
 
29 30-31-spillway gatespp20121003
29 30-31-spillway gatespp2012100329 30-31-spillway gatespp20121003
29 30-31-spillway gatespp20121003saibabu48
 
9fc1684e e872-4d1a-b54e-254f07c47009-150123191452-conversion-gate02
9fc1684e e872-4d1a-b54e-254f07c47009-150123191452-conversion-gate029fc1684e e872-4d1a-b54e-254f07c47009-150123191452-conversion-gate02
9fc1684e e872-4d1a-b54e-254f07c47009-150123191452-conversion-gate02saibabu48
 
Wreii unitv-170917082636
Wreii unitv-170917082636Wreii unitv-170917082636
Wreii unitv-170917082636saibabu48
 
Unit 4-canal lining
Unit 4-canal liningUnit 4-canal lining
Unit 4-canal liningsaibabu48
 
Types of spillways
Types of spillwaysTypes of spillways
Types of spillwayssaibabu48
 
Types of forces
Types of forcesTypes of forces
Types of forcessaibabu48
 
Types of earth dams
Types of earth damsTypes of earth dams
Types of earth damssaibabu48
 
Sprinkler irrigation
Sprinkler irrigationSprinkler irrigation
Sprinkler irrigationsaibabu48
 
Retaing wall
Retaing wallRetaing wall
Retaing wallsaibabu48
 

More from saibabu48 (20)

Design of-steel-structures bhavakkati- by easy engineering.net
Design of-steel-structures bhavakkati- by easy engineering.netDesign of-steel-structures bhavakkati- by easy engineering.net
Design of-steel-structures bhavakkati- by easy engineering.net
 
Sr bolted and welded conviction
Sr bolted and welded convictionSr bolted and welded conviction
Sr bolted and welded conviction
 
Iii design-of-steel-structures-unit-1
Iii design-of-steel-structures-unit-1Iii design-of-steel-structures-unit-1
Iii design-of-steel-structures-unit-1
 
Iii design-of-steel-structures-unit-2
Iii design-of-steel-structures-unit-2Iii design-of-steel-structures-unit-2
Iii design-of-steel-structures-unit-2
 
Ce 6603-dss-qb
Ce 6603-dss-qbCe 6603-dss-qb
Ce 6603-dss-qb
 
Ce6603 design of steel structures qb
Ce6603 design of steel structures qbCe6603 design of steel structures qb
Ce6603 design of steel structures qb
 
Dss notebook pdf someones
Dss notebook pdf someonesDss notebook pdf someones
Dss notebook pdf someones
 
29 30-31-spillway gatespp20121003
29 30-31-spillway gatespp2012100329 30-31-spillway gatespp20121003
29 30-31-spillway gatespp20121003
 
9fc1684e e872-4d1a-b54e-254f07c47009-150123191452-conversion-gate02
9fc1684e e872-4d1a-b54e-254f07c47009-150123191452-conversion-gate029fc1684e e872-4d1a-b54e-254f07c47009-150123191452-conversion-gate02
9fc1684e e872-4d1a-b54e-254f07c47009-150123191452-conversion-gate02
 
4 spillways
4 spillways4 spillways
4 spillways
 
Wreii unitv-170917082636
Wreii unitv-170917082636Wreii unitv-170917082636
Wreii unitv-170917082636
 
Unit 4-canal lining
Unit 4-canal liningUnit 4-canal lining
Unit 4-canal lining
 
Types of spillways
Types of spillwaysTypes of spillways
Types of spillways
 
Types of forces
Types of forcesTypes of forces
Types of forces
 
Types of earth dams
Types of earth damsTypes of earth dams
Types of earth dams
 
Sprinkler irrigation
Sprinkler irrigationSprinkler irrigation
Sprinkler irrigation
 
Spillways
SpillwaysSpillways
Spillways
 
Spillways
SpillwaysSpillways
Spillways
 
Spillway
SpillwaySpillway
Spillway
 
Retaing wall
Retaing wallRetaing wall
Retaing wall
 

Recently uploaded

MARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized GroupMARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized GroupJonathanParaisoCruz
 
Pharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdfPharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdfMahmoud M. Sallam
 
भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,Virag Sontakke
 
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfFraming an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfUjwalaBharambe
 
Full Stack Web Development Course for Beginners
Full Stack Web Development Course  for BeginnersFull Stack Web Development Course  for Beginners
Full Stack Web Development Course for BeginnersSabitha Banu
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationnomboosow
 
Types of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxTypes of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxEyham Joco
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTiammrhaywood
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxOH TEIK BIN
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Celine George
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatYousafMalik24
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxRaymartEstabillo3
 
Hierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of managementHierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of managementmkooblal
 
Painted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaPainted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaVirag Sontakke
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxNirmalaLoungPoorunde1
 
History Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptxHistory Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptxsocialsciencegdgrohi
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdfssuser54595a
 

Recently uploaded (20)

MARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized GroupMARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized Group
 
Pharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdfPharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdf
 
भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,
 
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfFraming an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
 
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
Full Stack Web Development Course for Beginners
Full Stack Web Development Course  for BeginnersFull Stack Web Development Course  for Beginners
Full Stack Web Development Course for Beginners
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communication
 
Types of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxTypes of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptx
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptx
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice great
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
 
Hierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of managementHierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of management
 
ESSENTIAL of (CS/IT/IS) class 06 (database)
ESSENTIAL of (CS/IT/IS) class 06 (database)ESSENTIAL of (CS/IT/IS) class 06 (database)
ESSENTIAL of (CS/IT/IS) class 06 (database)
 
Painted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaPainted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of India
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptx
 
History Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptxHistory Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptx
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
 

Unit 4-canal

  • 2. INTRODUCTION A canal is defined as an artificial channel constructed on the ground to carry water from a river or another canal or a reservoir to the fields.
  • 4. TYPES OF CANALS (Based on Source of Supply) • Continuous source of water supply. • Also called perennial canals Permanent Canal • Draws its supplies from a river only during the high stages of the river. Inundation Canal
  • 5. TYPES OF CANALS (Based on Function) • Carries water from its source to agricultural fields. Irrigation Canal • Used for transport of goods. Navigation Canal • Used to carry water for generation of hydroelectricity. Power Canal • Feeds two or more canals. Feeder Canal Note, a canal can serve more than one purpose.
  • 6. TYPES OF CANALS (Based on Alignment) Watershed Canal or Ridge Canal Contour Canal Side Slope Canal
  • 7. Watershed canal or Ridge canal The canal which is aligned along any natural watershed (ridge line) is called a watershed canal, or a ridge canal.
  • 8. Watershed canal or Ridge canal (Contd.) Aligning a canal (main canal or branch canal or distributary) on the ridge ensures gravity irrigation on both sides of the canal.  Since the drainage flows away from the ridge, no drainage can cross a canal aligned on the ridge. Thus, a canal aligned on the watershed saves the cost of construction of cross-drainage works.
  • 9. Watershed canal or Ridge canal (Contd.) Pranamesh Chakraborty
  • 10. Contour Canal Watershed canal along the ridge line are not found economical in hill areas. In hills, the river flows in the valley well below the watershed. In fact, the ridge line (watershed) may be hundred of meters above the river. It therefore becomes virtually impossible to take the canal on top of such a higher ridge line. In such conditions, contour canals are usually constructed. A contour canal irrigates only on one side because the area on the other side is higher.
  • 12. Side Slope Canal A side slope canal is that which is aligned at right angles to the contours; i.e. along the side slopes. Since such a canal runs parallel to the natural drainage flow, it usually does not intercept drainage channels, thus avoiding the construction of cross-drainage structures. It is a canal which is aligned roughly at right angle to contours of the country but not on watershed or valley.
  • 13. Side Slope Canal (Contd.)
  • 14. Types of Canals (BASED ON DISCHARGE) Main Canal Branch Canal Major Distributary Minor Distributary Water Course
  • 15.
  • 16. MAIN CANAL Main Canal takes off directly from the upstream side of weir head works or dam. Usually no direct cultivation is proposed
  • 17. BRANCH CANAL All offtakes from main canal with head discharge of 14-15 cumecs and above are termed as branch canals. Acts as feeder channel for major distributaries
  • 18. MAJOR DISTRIBUTARY  All offtakes from main canal or branch canal with head discharge from 0.25 to 15 cumecs are termed as major distributa MINOR DISTRIBUTARY  All offtakes taking off from a major distributary carrying discharge less than 0.25 cumec are termed as minor distributaries WATER COURSE  Small channels which carry water from the outlets of a major or minor distributary or a branch canal to the fields to be irrigated.
  • 19.
  • 20. Types of Canals (Based on lining provided or not) • Bed and banks made up of natural soil. • Water velocities higher than 0.7 m/s are not tolerable. • High seepage and conveyance water losses. • Profuse growth of aquatic weeds retards the flow . Unlined Canal • Lining of impervious material on its bed and banks to prevent the seepage of water. • Different types of lining used e.g. concrete, brick or burnt clay tile, boulder, etc. Lined Canal
  • 21. A PICTURE OF A UNLINED CANAL
  • 22. A PICTURE OF A LINED CANAL
  • 23. Canal Alignment General consideration for alignment:- 1. It should be aligned in such a way that maximum area is served with the least length. And its cost including CD- work is minimum. 2. A shorter length of canal has less loss of head due to friction and smaller loss of water due to seepage and evaporation, so that additional area can be brought under cultivation. 3. The alignment should be kept straight as far as possible, it will result in minimum losses. 4. It should have minimum CD work.
  • 24. Canal Alignment General consideration for alignment:- 5. It should not passes through the village, town, forest or costly lands, otherwise heavily compensation shall have to given. 6. It should be such that heavy cutting and filling (embankment) are avoided. 7. It should through passes the ridge so that both side of canal can be irrigated. 8. The alignment should be such that as far as possible a balanced depth of cutting and filling is achieved. 9. The alignment should not be made in rocky, brackish or cracked strata.
  • 26. A canal is generally taken in such a way that its section is partly in cutting and partly in filling in order to approach close to balancing depth. Many times however the canal has to be carried through deep cutting or filling. A canal structure may, therefore, either : 1. In Cutting 2. In Filling 3. In Partial Cutting and Filling. Cross-section of canal
  • 30. A canal section will be economical when earth work involved at a particular section has an equal amount of cut and fill. Usually a canal section has a part in cutting and part in filling as shown in fig. If the amount of cut is equal to the amount of fill, it has to be paid for once only. Definition:- For a given C/S there is always only one depth of cutting for which the cutting and filling will be equal. The depth is known as balancing depth. Balancing Depth
  • 32. If :- h = vertical height of top of bank from the bed of canal. b = bed width of the channel. t = top width of the canal bank. n:1 = side slope of bank in filling. z:1 = side slope of canal in cutting. d = full supply depth of canal. y = depth of cutting. Balancing Depth:-
  • 33. Area of the cut = by + zy2 = y(b + zy) Area of fill = 2[(h – y)t + n(h-y)2 ] Equating the area of cut and fill: y(b + z y) = 2[(h – y)t + n(h-y)2 ] b y+ zy2 = 2th + 2nh2 – 2nhy – 2ty – 2nhy + 2ny2 y2 (2n – z) – (b + 4nh + 2t)y + 2h(t + nh) =0 From this equation the balancing depth of the canal may be determined. Balancing Depth
  • 34. A canal is usually constructed with side slope of 1:1 in cutting and a slope 1.5:1 in filling. Putting n = 1.5 and z =1 in above equation. We get; y2 – (b/2 + 3h + t)y + h (t + 3/2 h)=0 Balancing Depth
  • 35. Components of Cross- Section  Side slope  Berm  Freeboard  Bank  Service road  Back Berm or Counter Berm  Spoil Bank  Borrow Pit
  • 36. Side Slope The side slopes should be such that they are stable, depending upon the type of the soil. A comparatively steeper slope can be provided in cutting rather than in filling, as the soil in the former case shall be more stable.
  • 37. Berm Berm is the horizontal distance left at ground level between the toe of the bank and the top edge of cutting.
  • 38. Berm (contd.) Purposes of Berms:  They give additional strength to the banks and provide protection against erosion and breaches.  They protect the banks from erosion due to wave action.  They provide a scope for future widening of the canal.
  • 39. Freeboard The margin between FSL and bank level is known as freeboard. The amount of freeboard depends upon the discharge of the channel.
  • 40. Bank The primary purpose of banks in to retain water. This can be used as means of communication and as inspection paths.
  • 41. Service Road Service roads are provided on canals for inspection purposes, and may simultaneously serve as the means of communication in remote areas. Dowla: As a measure of safety in driving, dowlas with side slopes of 1.5: 1 to 2:1, are provided along the banks.
  • 42. Back Berm or Counter Berm Even after providing sufficient section for bank embankment, the saturation gradient line may cut the downstream end of the bank. In such a case, the saturation line can be kept covered at least by 0.5 m with the help of counter berms as shown in figure below.
  • 43. Spoil Bank When the earthwork in excavation exceeds earthworks in filling, the extra earth has to be disposed of economically. Economical mode of its disposal may be collecting this soil on the edge of the bank embankment itself.
  • 44. Borrow Pit When earthwork in filling exceeds the earthwork in excavation, the earth has to be brought from somewhere. The pits, which are dug for bringing earth, are known as borrow pits. If such pits are excavated outside the channel, they are known as external borrow pits, and if they are excavated somewhere within the channel, they are known as internal borrow pits. Internal borrow pits are more preferred than external one.
  • 45. Borrow Pit (Contd.) The inside borrow pit may be located at the centre of canal. The idea behind this is that the borrow pits will act as water pockets where the silt will be deposited and ultimately the canal bed will get levelled up.