SlideShare a Scribd company logo
1 of 12
S-CurveHydrograph
Prepared by
Prof. S. G. Taji
Dept. of Civil Engineering
S.R.E.S’s Sanjivani College of Engineering,
Kopargaon
Type-III (B): Derivation of req. T-hr UH from Given
D-hr UH (where T is not multiple integral of D)
 In this type, S-curve approach should be used for calculation.
S-curve or S-Hydrograph
 A ‘S’ hydrograph is nothing but a hydrograph generated by a
continuous effective rainfall occurring at an uniform rate for an
indefinite period.
 It is called ‘S’ hydrograph because the shape of the hydrograph
comes out like alphabet ‘S’ though slightly deformed. Figure
shows a typical ‘S’ hydrograph.
 It can be derived by summation of the ordinates of an infinite
series of unit hydrographs of same .unit duration spaced at the
same unit duration apart and hence the name summation
hydrograph.
 It is a curve which rises continuously in the form or shape of the
letter S, till a constant discharge value i.e. equilibrium is reached.
 The discharge of the S-curve at the time of equilibrium,
A = Area of catchment in hectares
I = Constant rate of effective rainfall in cm/hour
If ‘A’ is taken in Sq. Km., then above eq. becomes
 The ordinates of S-curve can be plotted by using eq.
S(t) = U (t) + S (t-D)
Where, S(t)= req. ordinate of S-curve hydrograph at time
duration t.
U(t) = Ordinate of Given UH at time duration t.
t = required duration (hr)
D= Given duration of UH.
Therefore, S(t-D) = s-curve ordinate of preceding interval
 Q. Derive S-curve ordinates from given UH
 Ordinates of S-curve
 S(t) = U (t) + S (t-D)
 For S (0): At t = 0, U (t) = 0, S(t-D) = 0, Thus, S (0) = 0
(D=4hr i.e. given duration of UH)
 For S (4): At t = 4, U (t) = 10 m3/s, S(t-D) = S(4-4) = S (0) = 0,
 Thus, S (4) = 10 + 0 = 10 m3/s
 For S (8): At t = 8, U (t) = 30, S(t-D) = S(8-4)= S (4) = 10,
 Thus, S (4) = 30 + 10 = 40 m3/s
 For S (12): At t = 12, U (t) = 25, S(t-D) = S(12-4)= S (8) = 40,
 Thus, S (4) = 25 + 40 = 65 m3/s
 ……… continue till the end.
 These calculation can also be perform in table as shown below.
 Q. Determine 12 hr UH from given 4 hr UH by using S-curve
method.
 Soln:
 In this case, D=given duration= 4 hr and T=req. duration = 12hr
 Step-1: Draw two columns next to given UH (i.e. col. 3 and col. 4). These
two columns are filled consequently as follows:
 Initially, mark dash in first rows up to preceding interval of D hr of 3rd
col (i.e. in this case D=4hr, thus mark dash up to t=0 only)
 Step-2.1: Now, make addition col.2 and col. 3 and write it in col. 4.
 Step-2.2:Then, write that result at next row in col. 3 (as shown by
arrow).
 Step-2.3: Again make addition col.2 and col. 3 and write it in col. 4.
 Step-2.4: Then again, write that result at next row in col. 3 (as shown by
arrow).
 For ex. At time 8 hr, drag last ordinate from col.4 in col.
3 (i.e. 20 as shown by arrow), now do addition of 80 +
20 = 100 and write in col. 4.
 Continue this operation till the end of col. 3 and col. 4.
 Step-3: In col. 4, we get S-curve ordinates which are
nothing but the running summation of flow.
 Now, lag these s-curve ordinates by T-hr as shown in
col. 5 (in this case, T=12hr)
 Note: Always be lag your S-curve ordinate by that
duration for which you are going to derive UH (for ex. If
you going to plot 8 hr UH from given 24 hr UH, then in
step-3 lag your S-curve ordinates by 8 hr and vice
versa)
 Step-4: Now deduct that lagged column from S-
curve ordinates (i.e. col. 4 – col. 5 = col. 6)
 This is necessary because we have a summed valued
which should be converted into single flow value.
This will give us DRH of T/D cm ER (i.e. in this case,
T/D = 12/4 = 3cm ER)
 Thus, col. 6 is DRH of T/D = 12/4 = 3 cm ER.
 Step-5: This is the last step, in which divide last
column by ratio of T/D. (i.e. in this case, T/D = 12/4
= 3 cm) for getting req. 12 hr Uh.
Thank You……….

More Related Content

What's hot (20)

Canal regulation works. m4pptx
Canal regulation works. m4pptxCanal regulation works. m4pptx
Canal regulation works. m4pptx
 
Stilling basin
Stilling basinStilling basin
Stilling basin
 
Hydraulic jump
Hydraulic jumpHydraulic jump
Hydraulic jump
 
Embankment lecture 1
Embankment lecture 1Embankment lecture 1
Embankment lecture 1
 
Diversion Headworks
Diversion HeadworksDiversion Headworks
Diversion Headworks
 
Irrigation Engineering
Irrigation EngineeringIrrigation Engineering
Irrigation Engineering
 
Canal Fall
Canal FallCanal Fall
Canal Fall
 
Canal alignment
Canal alignmentCanal alignment
Canal alignment
 
Earthen Dam
Earthen DamEarthen Dam
Earthen Dam
 
Reservoir
ReservoirReservoir
Reservoir
 
Floods
FloodsFloods
Floods
 
Spillway gates
Spillway gatesSpillway gates
Spillway gates
 
Flood estimation
Flood estimation Flood estimation
Flood estimation
 
Introduction to Engineering Hydrology
Introduction to Engineering HydrologyIntroduction to Engineering Hydrology
Introduction to Engineering Hydrology
 
Design of Canal (Kennedy & Lacey Theory) & Diversion Headwork
Design of Canal (Kennedy & Lacey Theory) & Diversion HeadworkDesign of Canal (Kennedy & Lacey Theory) & Diversion Headwork
Design of Canal (Kennedy & Lacey Theory) & Diversion Headwork
 
Diversion headwork
Diversion headwork Diversion headwork
Diversion headwork
 
Lacey Regime Theory - Irrigation Engineering
Lacey Regime Theory - Irrigation EngineeringLacey Regime Theory - Irrigation Engineering
Lacey Regime Theory - Irrigation Engineering
 
Stream Gauging
Stream GaugingStream Gauging
Stream Gauging
 
theory of seepage
theory of seepagetheory of seepage
theory of seepage
 
Khosla theory
Khosla theoryKhosla theory
Khosla theory
 

Similar to Derive 12-Hour Unit Hydrograph from Given 4-Hour Unit Hydrograph Using S-Curve Method

Class lecture on Hydrology by Rabindra Ranjan saha Lecture 13
Class lecture on Hydrology by Rabindra Ranjan saha Lecture 13Class lecture on Hydrology by Rabindra Ranjan saha Lecture 13
Class lecture on Hydrology by Rabindra Ranjan saha Lecture 13World University of Bangladesh
 
Physics F3 (IGCSE) speed, velocity and acceleration
Physics F3 (IGCSE)   speed, velocity and acceleration Physics F3 (IGCSE)   speed, velocity and acceleration
Physics F3 (IGCSE) speed, velocity and acceleration Nurul Fadhilah
 
Speed, velocity and acceleration
Speed, velocity and accelerationSpeed, velocity and acceleration
Speed, velocity and accelerationShagorika Das
 
GRAPHICAL REPRESENTATION OF MOTION💖.pptx
GRAPHICAL REPRESENTATION OF MOTION💖.pptxGRAPHICAL REPRESENTATION OF MOTION💖.pptx
GRAPHICAL REPRESENTATION OF MOTION💖.pptxssusere853b3
 
Chapter 3, Introduction to Graphing” from Elementary Algebra .docx
Chapter 3, Introduction to Graphing” from Elementary Algebra .docxChapter 3, Introduction to Graphing” from Elementary Algebra .docx
Chapter 3, Introduction to Graphing” from Elementary Algebra .docxchristinemaritza
 
Motion graphs
Motion graphsMotion graphs
Motion graphsndward
 
MA101-Lecturenotes(2019-20)-Module 13 (1).pdf
MA101-Lecturenotes(2019-20)-Module 13 (1).pdfMA101-Lecturenotes(2019-20)-Module 13 (1).pdf
MA101-Lecturenotes(2019-20)-Module 13 (1).pdfvasusingh34
 
MA101-Lecturenotes(2019-20)-Module 13 (1).pdf
MA101-Lecturenotes(2019-20)-Module 13 (1).pdfMA101-Lecturenotes(2019-20)-Module 13 (1).pdf
MA101-Lecturenotes(2019-20)-Module 13 (1).pdfvasusingh34
 
Diagramatic Representation.pdf
Diagramatic Representation.pdfDiagramatic Representation.pdf
Diagramatic Representation.pdfgarefed500
 
Scales in Engineering
Scales in EngineeringScales in Engineering
Scales in EngineeringKushal Patel
 
Bar Pendulum experiment ppt.pptx
Bar Pendulum experiment ppt.pptxBar Pendulum experiment ppt.pptx
Bar Pendulum experiment ppt.pptxGaneshGK5
 
presentation_equation_of_motion_1663608809_139366.pptx
presentation_equation_of_motion_1663608809_139366.pptxpresentation_equation_of_motion_1663608809_139366.pptx
presentation_equation_of_motion_1663608809_139366.pptxharveenkaur64
 
presentation_equation_of_motion_1663608809_139366.pptx
presentation_equation_of_motion_1663608809_139366.pptxpresentation_equation_of_motion_1663608809_139366.pptx
presentation_equation_of_motion_1663608809_139366.pptxharveenkaur64
 
presentation_equation_of_motion_1663608809_139366.pptx
presentation_equation_of_motion_1663608809_139366.pptxpresentation_equation_of_motion_1663608809_139366.pptx
presentation_equation_of_motion_1663608809_139366.pptxLokeshT29
 
CP - Graphical Analysis
CP - Graphical AnalysisCP - Graphical Analysis
CP - Graphical Analysisstephm32
 
Supersonic_Ramji_Amit_10241445
Supersonic_Ramji_Amit_10241445Supersonic_Ramji_Amit_10241445
Supersonic_Ramji_Amit_10241445Amit Ramji ✈
 

Similar to Derive 12-Hour Unit Hydrograph from Given 4-Hour Unit Hydrograph Using S-Curve Method (20)

Class lecture on Hydrology by Rabindra Ranjan saha Lecture 13
Class lecture on Hydrology by Rabindra Ranjan saha Lecture 13Class lecture on Hydrology by Rabindra Ranjan saha Lecture 13
Class lecture on Hydrology by Rabindra Ranjan saha Lecture 13
 
Physics F3 (IGCSE) speed, velocity and acceleration
Physics F3 (IGCSE)   speed, velocity and acceleration Physics F3 (IGCSE)   speed, velocity and acceleration
Physics F3 (IGCSE) speed, velocity and acceleration
 
Speed, velocity and acceleration
Speed, velocity and accelerationSpeed, velocity and acceleration
Speed, velocity and acceleration
 
GRAPHICAL REPRESENTATION OF MOTION💖.pptx
GRAPHICAL REPRESENTATION OF MOTION💖.pptxGRAPHICAL REPRESENTATION OF MOTION💖.pptx
GRAPHICAL REPRESENTATION OF MOTION💖.pptx
 
Chapter 3, Introduction to Graphing” from Elementary Algebra .docx
Chapter 3, Introduction to Graphing” from Elementary Algebra .docxChapter 3, Introduction to Graphing” from Elementary Algebra .docx
Chapter 3, Introduction to Graphing” from Elementary Algebra .docx
 
Motion graphs
Motion graphsMotion graphs
Motion graphs
 
MA101-Lecturenotes(2019-20)-Module 13 (1).pdf
MA101-Lecturenotes(2019-20)-Module 13 (1).pdfMA101-Lecturenotes(2019-20)-Module 13 (1).pdf
MA101-Lecturenotes(2019-20)-Module 13 (1).pdf
 
MA101-Lecturenotes(2019-20)-Module 13 (1).pdf
MA101-Lecturenotes(2019-20)-Module 13 (1).pdfMA101-Lecturenotes(2019-20)-Module 13 (1).pdf
MA101-Lecturenotes(2019-20)-Module 13 (1).pdf
 
Diagramatic Representation.pdf
Diagramatic Representation.pdfDiagramatic Representation.pdf
Diagramatic Representation.pdf
 
Pat 2012 paper_pdf_10581
Pat 2012 paper_pdf_10581Pat 2012 paper_pdf_10581
Pat 2012 paper_pdf_10581
 
Tacheometry 1
Tacheometry 1Tacheometry 1
Tacheometry 1
 
StewartCalc7e_01_01.ppt
StewartCalc7e_01_01.pptStewartCalc7e_01_01.ppt
StewartCalc7e_01_01.ppt
 
Scales in Engineering
Scales in EngineeringScales in Engineering
Scales in Engineering
 
Bar Pendulum experiment ppt.pptx
Bar Pendulum experiment ppt.pptxBar Pendulum experiment ppt.pptx
Bar Pendulum experiment ppt.pptx
 
Laboratory manual surveying_ii
Laboratory manual surveying_iiLaboratory manual surveying_ii
Laboratory manual surveying_ii
 
presentation_equation_of_motion_1663608809_139366.pptx
presentation_equation_of_motion_1663608809_139366.pptxpresentation_equation_of_motion_1663608809_139366.pptx
presentation_equation_of_motion_1663608809_139366.pptx
 
presentation_equation_of_motion_1663608809_139366.pptx
presentation_equation_of_motion_1663608809_139366.pptxpresentation_equation_of_motion_1663608809_139366.pptx
presentation_equation_of_motion_1663608809_139366.pptx
 
presentation_equation_of_motion_1663608809_139366.pptx
presentation_equation_of_motion_1663608809_139366.pptxpresentation_equation_of_motion_1663608809_139366.pptx
presentation_equation_of_motion_1663608809_139366.pptx
 
CP - Graphical Analysis
CP - Graphical AnalysisCP - Graphical Analysis
CP - Graphical Analysis
 
Supersonic_Ramji_Amit_10241445
Supersonic_Ramji_Amit_10241445Supersonic_Ramji_Amit_10241445
Supersonic_Ramji_Amit_10241445
 

More from Satish Taji

Draft Tube and Cavitation | Fluid Mechanics
Draft Tube and Cavitation | Fluid MechanicsDraft Tube and Cavitation | Fluid Mechanics
Draft Tube and Cavitation | Fluid MechanicsSatish Taji
 
Selection of Turbine | Fluid Mechanics
Selection of Turbine | Fluid MechanicsSelection of Turbine | Fluid Mechanics
Selection of Turbine | Fluid MechanicsSatish Taji
 
Governing of the Turbine | Fluid Mechanics
Governing of the Turbine | Fluid MechanicsGoverning of the Turbine | Fluid Mechanics
Governing of the Turbine | Fluid MechanicsSatish Taji
 
Unit Quantities of Turbine | Fluid Mechanics
Unit Quantities of Turbine | Fluid MechanicsUnit Quantities of Turbine | Fluid Mechanics
Unit Quantities of Turbine | Fluid MechanicsSatish Taji
 
Specific Speed of Turbine | Fluid Mechanics
Specific Speed of Turbine | Fluid MechanicsSpecific Speed of Turbine | Fluid Mechanics
Specific Speed of Turbine | Fluid MechanicsSatish Taji
 
Kaplan Turbine - Design and Numerical
Kaplan Turbine - Design and NumericalKaplan Turbine - Design and Numerical
Kaplan Turbine - Design and NumericalSatish Taji
 
Pelton Wheel Turbine Part 2
Pelton Wheel Turbine Part 2Pelton Wheel Turbine Part 2
Pelton Wheel Turbine Part 2Satish Taji
 
Classification of Turbines
Classification of TurbinesClassification of Turbines
Classification of TurbinesSatish Taji
 
Basics of Turbine
Basics of TurbineBasics of Turbine
Basics of TurbineSatish Taji
 
Elements of Water Conductor System
Elements of Water Conductor SystemElements of Water Conductor System
Elements of Water Conductor SystemSatish Taji
 
Run of River and Pumped Storage Plants
Run of River and Pumped Storage PlantsRun of River and Pumped Storage Plants
Run of River and Pumped Storage PlantsSatish Taji
 
Component of Hydro Power Plant
Component of Hydro Power PlantComponent of Hydro Power Plant
Component of Hydro Power PlantSatish Taji
 
Hydropower Development in India
Hydropower Development in IndiaHydropower Development in India
Hydropower Development in IndiaSatish Taji
 
Base Load Plants and Peak Load Plant
Base Load Plants and Peak Load PlantBase Load Plants and Peak Load Plant
Base Load Plants and Peak Load PlantSatish Taji
 
Classification of hydro power plant
Classification of hydro power plantClassification of hydro power plant
Classification of hydro power plantSatish Taji
 
Properties of Fluids, Fluid Static, Buoyancy and Dimensional Analysis
Properties of Fluids, Fluid Static, Buoyancy and Dimensional AnalysisProperties of Fluids, Fluid Static, Buoyancy and Dimensional Analysis
Properties of Fluids, Fluid Static, Buoyancy and Dimensional AnalysisSatish Taji
 
Introduction and Application of GIS
Introduction and Application of GISIntroduction and Application of GIS
Introduction and Application of GISSatish Taji
 

More from Satish Taji (18)

Draft Tube and Cavitation | Fluid Mechanics
Draft Tube and Cavitation | Fluid MechanicsDraft Tube and Cavitation | Fluid Mechanics
Draft Tube and Cavitation | Fluid Mechanics
 
Selection of Turbine | Fluid Mechanics
Selection of Turbine | Fluid MechanicsSelection of Turbine | Fluid Mechanics
Selection of Turbine | Fluid Mechanics
 
Governing of the Turbine | Fluid Mechanics
Governing of the Turbine | Fluid MechanicsGoverning of the Turbine | Fluid Mechanics
Governing of the Turbine | Fluid Mechanics
 
Unit Quantities of Turbine | Fluid Mechanics
Unit Quantities of Turbine | Fluid MechanicsUnit Quantities of Turbine | Fluid Mechanics
Unit Quantities of Turbine | Fluid Mechanics
 
Specific Speed of Turbine | Fluid Mechanics
Specific Speed of Turbine | Fluid MechanicsSpecific Speed of Turbine | Fluid Mechanics
Specific Speed of Turbine | Fluid Mechanics
 
Kaplan Turbine - Design and Numerical
Kaplan Turbine - Design and NumericalKaplan Turbine - Design and Numerical
Kaplan Turbine - Design and Numerical
 
Francis Turbine
Francis TurbineFrancis Turbine
Francis Turbine
 
Pelton Wheel Turbine Part 2
Pelton Wheel Turbine Part 2Pelton Wheel Turbine Part 2
Pelton Wheel Turbine Part 2
 
Classification of Turbines
Classification of TurbinesClassification of Turbines
Classification of Turbines
 
Basics of Turbine
Basics of TurbineBasics of Turbine
Basics of Turbine
 
Elements of Water Conductor System
Elements of Water Conductor SystemElements of Water Conductor System
Elements of Water Conductor System
 
Run of River and Pumped Storage Plants
Run of River and Pumped Storage PlantsRun of River and Pumped Storage Plants
Run of River and Pumped Storage Plants
 
Component of Hydro Power Plant
Component of Hydro Power PlantComponent of Hydro Power Plant
Component of Hydro Power Plant
 
Hydropower Development in India
Hydropower Development in IndiaHydropower Development in India
Hydropower Development in India
 
Base Load Plants and Peak Load Plant
Base Load Plants and Peak Load PlantBase Load Plants and Peak Load Plant
Base Load Plants and Peak Load Plant
 
Classification of hydro power plant
Classification of hydro power plantClassification of hydro power plant
Classification of hydro power plant
 
Properties of Fluids, Fluid Static, Buoyancy and Dimensional Analysis
Properties of Fluids, Fluid Static, Buoyancy and Dimensional AnalysisProperties of Fluids, Fluid Static, Buoyancy and Dimensional Analysis
Properties of Fluids, Fluid Static, Buoyancy and Dimensional Analysis
 
Introduction and Application of GIS
Introduction and Application of GISIntroduction and Application of GIS
Introduction and Application of GIS
 

Recently uploaded

Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptSAURABHKUMAR892774
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
DATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage exampleDATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage examplePragyanshuParadkar1
 
pipeline in computer architecture design
pipeline in computer architecture  designpipeline in computer architecture  design
pipeline in computer architecture designssuser87fa0c1
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...Chandu841456
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 

Recently uploaded (20)

Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.ppt
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
DATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage exampleDATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage example
 
pipeline in computer architecture design
pipeline in computer architecture  designpipeline in computer architecture  design
pipeline in computer architecture design
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 

Derive 12-Hour Unit Hydrograph from Given 4-Hour Unit Hydrograph Using S-Curve Method

  • 1. S-CurveHydrograph Prepared by Prof. S. G. Taji Dept. of Civil Engineering S.R.E.S’s Sanjivani College of Engineering, Kopargaon
  • 2. Type-III (B): Derivation of req. T-hr UH from Given D-hr UH (where T is not multiple integral of D)  In this type, S-curve approach should be used for calculation. S-curve or S-Hydrograph  A ‘S’ hydrograph is nothing but a hydrograph generated by a continuous effective rainfall occurring at an uniform rate for an indefinite period.  It is called ‘S’ hydrograph because the shape of the hydrograph comes out like alphabet ‘S’ though slightly deformed. Figure shows a typical ‘S’ hydrograph.  It can be derived by summation of the ordinates of an infinite series of unit hydrographs of same .unit duration spaced at the same unit duration apart and hence the name summation hydrograph.  It is a curve which rises continuously in the form or shape of the letter S, till a constant discharge value i.e. equilibrium is reached.
  • 3.
  • 4.  The discharge of the S-curve at the time of equilibrium, A = Area of catchment in hectares I = Constant rate of effective rainfall in cm/hour If ‘A’ is taken in Sq. Km., then above eq. becomes  The ordinates of S-curve can be plotted by using eq. S(t) = U (t) + S (t-D) Where, S(t)= req. ordinate of S-curve hydrograph at time duration t. U(t) = Ordinate of Given UH at time duration t. t = required duration (hr) D= Given duration of UH. Therefore, S(t-D) = s-curve ordinate of preceding interval
  • 5.  Q. Derive S-curve ordinates from given UH
  • 6.  Ordinates of S-curve  S(t) = U (t) + S (t-D)  For S (0): At t = 0, U (t) = 0, S(t-D) = 0, Thus, S (0) = 0 (D=4hr i.e. given duration of UH)  For S (4): At t = 4, U (t) = 10 m3/s, S(t-D) = S(4-4) = S (0) = 0,  Thus, S (4) = 10 + 0 = 10 m3/s  For S (8): At t = 8, U (t) = 30, S(t-D) = S(8-4)= S (4) = 10,  Thus, S (4) = 30 + 10 = 40 m3/s  For S (12): At t = 12, U (t) = 25, S(t-D) = S(12-4)= S (8) = 40,  Thus, S (4) = 25 + 40 = 65 m3/s  ……… continue till the end.  These calculation can also be perform in table as shown below.
  • 7.
  • 8.  Q. Determine 12 hr UH from given 4 hr UH by using S-curve method.  Soln:  In this case, D=given duration= 4 hr and T=req. duration = 12hr  Step-1: Draw two columns next to given UH (i.e. col. 3 and col. 4). These two columns are filled consequently as follows:  Initially, mark dash in first rows up to preceding interval of D hr of 3rd col (i.e. in this case D=4hr, thus mark dash up to t=0 only)  Step-2.1: Now, make addition col.2 and col. 3 and write it in col. 4.  Step-2.2:Then, write that result at next row in col. 3 (as shown by arrow).  Step-2.3: Again make addition col.2 and col. 3 and write it in col. 4.  Step-2.4: Then again, write that result at next row in col. 3 (as shown by arrow).
  • 9.  For ex. At time 8 hr, drag last ordinate from col.4 in col. 3 (i.e. 20 as shown by arrow), now do addition of 80 + 20 = 100 and write in col. 4.  Continue this operation till the end of col. 3 and col. 4.  Step-3: In col. 4, we get S-curve ordinates which are nothing but the running summation of flow.  Now, lag these s-curve ordinates by T-hr as shown in col. 5 (in this case, T=12hr)  Note: Always be lag your S-curve ordinate by that duration for which you are going to derive UH (for ex. If you going to plot 8 hr UH from given 24 hr UH, then in step-3 lag your S-curve ordinates by 8 hr and vice versa)
  • 10.  Step-4: Now deduct that lagged column from S- curve ordinates (i.e. col. 4 – col. 5 = col. 6)  This is necessary because we have a summed valued which should be converted into single flow value. This will give us DRH of T/D cm ER (i.e. in this case, T/D = 12/4 = 3cm ER)  Thus, col. 6 is DRH of T/D = 12/4 = 3 cm ER.  Step-5: This is the last step, in which divide last column by ratio of T/D. (i.e. in this case, T/D = 12/4 = 3 cm) for getting req. 12 hr Uh.
  • 11.