1. PMP® Sample
Questions
PMI, PMP, CAPM, PgMP, PMI-ACP, PMI-SP, PMI-RMP and PMBOK are trademarks of the Project Management Institute, Inc. PMI has not endorsed and did not participate in the
development of this publication. PMI does not sponsor this publication and makes no warranty, guarantee or representation, expressed or implied as to the accuracy or content. Every
attempt has been made by OSP International LLC to ensure that the information presented in this publication is accurate and can serve as preparation for the PMP certification exam.
However, OSP International LLC accepts no legal responsibility for the content herein. This document should be used only as a reference and not as a replacement for officially
published material. Using the information from this document does not guarantee that the reader will pass the PMP certification exam. No such guarantees or warranties are implied or
expressed by OSP International LLC.
2. This presentation will showcase free sample
PMP® questions that will help and guide
you in studying for your PMP® exam
Find more free sample questions when you visit
www.free-pm-exam-questions.com and
free.pm-exam-simulator.com
3. 1. You are considering using WBS templates to create your project's WBS.
Where would you most likely find these templates?
A. Enterprise Environmental Factors
B. Requirements Documentation
C. Project Management Plan
D. Organizational Process Assets
Hint: Get your mind out of the PMBOK Guide and think freely for this question.
Sample PMP® Exam Question
4. The correct answer is D
Explanation:This question isn't asking about "inputs"
to the CreateWBS process.The question is simply
asking:Where could you find templates to help you
build aWBS? Organizational Process Assets contain
WBS templates.
Answer and Explanation
5. 2. You are managing a water supply network deployment project. During project
planning you are considering two approaches to lay the pipe network. Approach A will
most likely cost $50,000 (+/-5%). Approach B will most likely cost $25,000 (+/-
40%). Which approach will you select if your project stakeholders' risk tolerances are
low and if you want to select the less risky approach?
A. Neither approach since they are not definitive estimates
B. Approach B since it ranges from $15,000 to $35,000
C. Approach A since it ranges from $47,500 to $52,500
D. A combination of approach A and B
Hint:Estimates are never definitive.
Sample PMP® Exam Question
6. The correct answer is C
Explanation: Please note that the question doesn't ask for
the approach that is more financially feasible. Instead, the
question asks you to identify the approach that has the
lower risk.The larger the range of an estimate, the larger
the risk. Since approach B is a wide range estimate, it is
more risky.Approach C has a narrow estimate, which
makes this approach less risky.
Answer and Explanation
7. 3. An element of a Work Breakdown Structure that can be viewed at the lowest level
of each branch is referred to as which of the following?
A. ControlAccount
B. Work Breakdown Structure Component"
C. Work Package
D. Task
Hint: A work package is at the lowest level of aWBS.
Sample PMP® Exam Question
8. The correct answer is C
Explanation:A control account is a management control
point where scope, budget, resources, actual cost and
schedule are integrated and compared to earned value
for performance measurement. Control accounts are
placed at selected management points (specific
components at selected levels) of theWork Breakdown
Structure.A work package is a deliverable or project
work component at the lowest level of each branch of
theWork Breakdown Structure.Tasks are the results of
further decomposition of work packages.
Answer and Explanation
9. 4. Sensitivity analysis has strong similarities to which of the following?
A. Probability Distributions
B. Risk Identification
C. Tornado Diagram
D. Statistical Sampling
Hint: Sensitivity analysis is a risk analysis technique,not a risk identification technique.
Sample PMP® Exam Question
10. The correct answer is C
Explanation: Sensitivity analysis is a risk analysis technique,
not a risk identification technique. It is not a sampling
technique or a distribution. In Sensitivity analysis one looks
at the effect of varying the inputs of a mathematical model on
the output of the model itself.TheTornado Diagram is an
example for sensitivity analysis.
Answer and Explanation
11. 5. You are managing a nationwide telecom network deployment project. You learned
that you are unable to start any civil works before obtaining a government agency's
permit, which could take months. The project deadlines are aggressive and you might
face penalties if you don't meet them. Obtaining the government agency's permit
prior to civil works on any site is an example of which of the following?
A. Mandatory Dependency
B. External Dependency
C. Project Constraint
D. Project Requirement
Hint:All of the choices are correct in a way but considering the relationship of the permit to the
civil work will yield only one correct choice.
Sample PMP® Exam Question
12. The correct answer is B
Explanation:The question asked you about the relationship
between civil works and the government agency permit to
perform these works.When we are talking about relationships
between activities we are talking about dependencies between
the tasks. Obtaining the permits will definitely be in your
project's scope of work and will also be a part of your contract.
Therefore, it is considered a mandatory dependency. Similarly,
as you have to fulfil this requirement it is both a project
constraint and a project requirement. Most importantly, as
obtaining the permit and the lead time to do so is beyond your
control, it is an external dependency, which is the best answer
to this question given the scenario.
Answer and Explanation