PMP® Sample
      Questions

PMI, PMP, CAPM, PgMP, PMI-ACP, PMI-SP, PMI-RMP and PMBOK are trademarks of the Project Management Institute, Inc. PMI has not endorsed and did not participate in
the development of this publication. PMI does not sponsor this publication and makes no warranty, guarantee or representation, expressed or implied as to the accuracy or
content. Every attempt has been made by OSP International LLC to ensure that the information presented in this publication is accurate and can serve as preparation for the
PMP certification exam. However, OSP International LLC accepts no legal responsibility for the content herein. This document should be used only as a reference and not as a
replacement for officially published material. Using the information from this document does not guarantee that the reader will pass the PMP certification exam. No such
guarantees or warranties are implied or expressed by OSP International LLC.
This presentation will showcase free
  sample PMP® questions that will help
    and guide you in studying for your
               PMP® exam

Find more free sample questions when you
 visit www.free-pm-exam-questions.com
    and free.pm-exam-simulator.com
Sample PMP® Exam Question
 In a project, several risk response strategies are used to effectively
 manage project risks. The strategy or mix of strategies should be used
 when planning for risk responses. Which of the following statements
 best describes an 'accept' strategy for negative risks or threats?

    a. Adopting less complex processes is an accept strategy.
    b. Use of insurance is part of an accept strategy.
    c. Using contingency reserve is part of accept strategy.
    d. Extending schedule is part of an accept strategy.

HINT: A risk acceptance strategy is adopted because it is
seldom possible to eliminate all threats from a project. One of
the risk acceptance strategies is performed in the early stages of
planning. Find the option which is performed during planning.
Answer and Explanation

           The correct answer is C

           The most common risk acceptance strategy
           in a project is to establish contingency
           reserves.
Sample PMP® Exam Question
 You developed alternative schedules based on
 the best-case and worst-case scenarios in your
 project. You want to keep these alternative
 schedules stored in your project, in case of
 changes in project resources.
 Where would you store alternative schedules?

   a. Schedule Baseline
   b. Schedule Data
   c. Project documents
   d. Project scope statement

HINT: Alternative schedules are output of develop
schedule process. Look for the outputs of develop
schedule process to see where these schedules are
stored.
Answer and Explanation

           The correct answer is B

           Schedule data contains alternative
           schedules such as best-case or worst-case
           scenario. This is an output of develop
           schedule process.
Sample PMP® Exam Question
            Tim is working on an electronic manufacturing
            project. In his project he wants to establish a
            warranty for some of the precision parts he is
            buying.
            What risk response strategy is he using?

              a. Mitigate
              b. Avoid
              c. Accept
              d. Transfer

            HINT: Tim is shifting the negative impact of the risk.
Answer and Explanation

           The correct answer is D

           Risk transfer requires shifting some or all of
           the negative impact of a threat, along with
           the ownership of the response. Taking out
           insurance or a warranty transfers the risk
           from the owner to the other party.
Sample PMP® Exam Question
           What is risk tolerance?

             a. Risks created by tolerating customer behavior.
             b. Willingness to accept varying degrees of risk.
             c. Risks created by zero tolerance.
             d. Being tolerant if stakeholders are willing to
                accept risks.



           HINT: Look for the “least strange” answer.
Answer and Explanation

           The correct answer is B

           Do you feel that A, C and D are odd?
           Correct, they are and they were included
           intentionally. Sometimes you can expect to
           find some “funny” answer choices.
           Risk tolerance is the stakeholders'
           willingness to accept varying degrees of
           risk. Choice B is the only correct answer to
           this question.
Sample PMP® Exam Question
  You are managing a software development project. You want to create the
  basis that will be used later on for estimating, scheduling, executing,
  monitoring, and controlling the project work.
  Which process performs this activity?

    a. Create WBS
    b. Define Scope
    c. Define Activities
    d. Create Project Management Plan

HINT: Estimating is performed when the activities
are defined and the schedule is prepared.
Answer and Explanation

           The correct answer is C

           Activities form a basis for estimating,
           scheduling, executing, and monitoring and
           controlling the project work. This is
           performed in the Define Activities process.
Sample PMP® Exam Question
  You are considering using WBS templates to
  create your project's WBS.
  Where would you most likely find these
  templates?

    a. PMI's Practice Standard for WBS
    b. Microsoft Project Web Site
    c. Organizational Process Assets
    d. All of the above

HINT: Get your mind out of the PMBOK Guide and
think freely for this question.
Answer and Explanation

           The correct answer is D

           This question isn't asking about "inputs" to
           the Create WBS process. The question is
           simply asking: Where could you find
           templates to help you build a WBS? All of
           the answer choices are possible sources for
           WBS templates.

PMP Exam Sample Questions Set 1

  • 1.
    PMP® Sample Questions PMI, PMP, CAPM, PgMP, PMI-ACP, PMI-SP, PMI-RMP and PMBOK are trademarks of the Project Management Institute, Inc. PMI has not endorsed and did not participate in the development of this publication. PMI does not sponsor this publication and makes no warranty, guarantee or representation, expressed or implied as to the accuracy or content. Every attempt has been made by OSP International LLC to ensure that the information presented in this publication is accurate and can serve as preparation for the PMP certification exam. However, OSP International LLC accepts no legal responsibility for the content herein. This document should be used only as a reference and not as a replacement for officially published material. Using the information from this document does not guarantee that the reader will pass the PMP certification exam. No such guarantees or warranties are implied or expressed by OSP International LLC.
  • 2.
    This presentation willshowcase free sample PMP® questions that will help and guide you in studying for your PMP® exam Find more free sample questions when you visit www.free-pm-exam-questions.com and free.pm-exam-simulator.com
  • 3.
    Sample PMP® ExamQuestion In a project, several risk response strategies are used to effectively manage project risks. The strategy or mix of strategies should be used when planning for risk responses. Which of the following statements best describes an 'accept' strategy for negative risks or threats? a. Adopting less complex processes is an accept strategy. b. Use of insurance is part of an accept strategy. c. Using contingency reserve is part of accept strategy. d. Extending schedule is part of an accept strategy. HINT: A risk acceptance strategy is adopted because it is seldom possible to eliminate all threats from a project. One of the risk acceptance strategies is performed in the early stages of planning. Find the option which is performed during planning.
  • 4.
    Answer and Explanation The correct answer is C The most common risk acceptance strategy in a project is to establish contingency reserves.
  • 5.
    Sample PMP® ExamQuestion You developed alternative schedules based on the best-case and worst-case scenarios in your project. You want to keep these alternative schedules stored in your project, in case of changes in project resources. Where would you store alternative schedules? a. Schedule Baseline b. Schedule Data c. Project documents d. Project scope statement HINT: Alternative schedules are output of develop schedule process. Look for the outputs of develop schedule process to see where these schedules are stored.
  • 6.
    Answer and Explanation The correct answer is B Schedule data contains alternative schedules such as best-case or worst-case scenario. This is an output of develop schedule process.
  • 7.
    Sample PMP® ExamQuestion Tim is working on an electronic manufacturing project. In his project he wants to establish a warranty for some of the precision parts he is buying. What risk response strategy is he using? a. Mitigate b. Avoid c. Accept d. Transfer HINT: Tim is shifting the negative impact of the risk.
  • 8.
    Answer and Explanation The correct answer is D Risk transfer requires shifting some or all of the negative impact of a threat, along with the ownership of the response. Taking out insurance or a warranty transfers the risk from the owner to the other party.
  • 9.
    Sample PMP® ExamQuestion What is risk tolerance? a. Risks created by tolerating customer behavior. b. Willingness to accept varying degrees of risk. c. Risks created by zero tolerance. d. Being tolerant if stakeholders are willing to accept risks. HINT: Look for the “least strange” answer.
  • 10.
    Answer and Explanation The correct answer is B Do you feel that A, C and D are odd? Correct, they are and they were included intentionally. Sometimes you can expect to find some “funny” answer choices. Risk tolerance is the stakeholders' willingness to accept varying degrees of risk. Choice B is the only correct answer to this question.
  • 11.
    Sample PMP® ExamQuestion You are managing a software development project. You want to create the basis that will be used later on for estimating, scheduling, executing, monitoring, and controlling the project work. Which process performs this activity? a. Create WBS b. Define Scope c. Define Activities d. Create Project Management Plan HINT: Estimating is performed when the activities are defined and the schedule is prepared.
  • 12.
    Answer and Explanation The correct answer is C Activities form a basis for estimating, scheduling, executing, and monitoring and controlling the project work. This is performed in the Define Activities process.
  • 13.
    Sample PMP® ExamQuestion You are considering using WBS templates to create your project's WBS. Where would you most likely find these templates? a. PMI's Practice Standard for WBS b. Microsoft Project Web Site c. Organizational Process Assets d. All of the above HINT: Get your mind out of the PMBOK Guide and think freely for this question.
  • 14.
    Answer and Explanation The correct answer is D This question isn't asking about "inputs" to the Create WBS process. The question is simply asking: Where could you find templates to help you build a WBS? All of the answer choices are possible sources for WBS templates.