Management reserves are not included in the cost or schedule baseline and are established to deal with unforeseen work. While management reserves are part of the project budget or duration, they are excluded from the baselines. Contingency reserves differ in that they are estimated for identified risks and can be allocated at the activity level. The document provides a sample exam question and answer regarding the distinction between management reserves and contingency reserves in project management.