7. Introduction
7
•
Secondary Crushing Station in foreground
•
2.2km curved overland conveyor in centre of picture
•
Stockpiles, Mills and tails dams in background
9. Our Challenge!
9
•
3 Electric Shocks experienced from LHD’s within 6 months (including 2 in 5 days)
•
Levels of shock received not clearly understood
•
To continue to operate safely without putting our people at risk
10. 10
Incident
Shock Description
Findings
Actions
Cable snapped while operating cable reeler (10/13) (X2)
1.
Similar to electric fence
2.
Cow kicked me in the chest & back
Snapped at previous join
EC tripped
Level of shock received not clear.
Understand level of shock received & determine course of action
Shock received while unplugging cable in workshop (4/14)
Pain in arm and tingling sensation on tongue
Isolator was on. Level of shock received not clear.
Understand level of shock received & determine course of action
11. Our Equipment
11
Sandvik 514E Electric Loader
-
38 T unloaded
-
52T loaded
-
Max Speed > 20 km/h
-
132 kW 1000V Main Drive Motor
-
45kW 1000V main pump motor
-
425m of type 275 trailing cable
-
56 cables repaired over 12 months including 16 splices & 3 cables torn apart
21. Modelling Process
21
•
External consultant (Restech) engaged to model last 3 incidents to determine root cause of shock and likely level of shock received
•
Initial engagement actually made at this seminar last year
•
Panel inspected & sent offsite for testing
•
Traditional pilot EC protection not used in this application
22. EC System
22
•
Traditional pilot EC protection not used in this application
•
US MSHA compliant not compliant with AS4871 (LHD OEM recommendation)
24. Outcomes from modelling & testing (cable breakages)
24
•
7 Cable breakage scenarios modelled
–
Saturation of Arc Trap in EC circuit contributes to increased touch potentials under certain failure conditions as does parallel interaction of arc traps
–
Most likely breakage scenario of the earths breaking followed by all 3 phases breaking would result in a painful electric shock but would be unlikely to cause ventricular fibrillation. (180 V rms, short duration transient voltage)
–
Likely that the voltage would be removed from the cable breaking before the protection operated
–
AS4871 requirements met except for EC
–
C/B on GEB Panel 9 found to be faulty under S/C conditions
25. Preventative Actions (cable breakages)
25
•
Cut off for cable condition raised from 2 to 5 (AS1747)
•
Cable management plan implemented
•
Tested for voltage rise on earth on machine start-up
•
CB’s replaced (cheaper than testing SC trip function)
•
New GEB panels manufactured compliant with AS4871 & AS2081 (using pilot EC protection). Installation Q4 2014
•
Interim control to use voltage rated gloves where cables are under tension
•
Cable repairs inspected & found to be of a high standard to AS1747
•
EC tested & some adjusted
•
10A NER replaced with 5A
28. Outcomes from modelling & testing (cable unplugging)
28
–
Cable was energised when plug was removed
–
As plug removed phases make & break creating a phase imbalance and a transient earth current on reconnection
–
Modelling showed the effect of this imbalance and transient earth current was further impacted by the behaviour of the EC circuit contributing to a greater shock potential
29. Preventative Actions (cable plugging)
29
•
Clearly label isolation points including On / Off
•
Visual indication of a live receptacle
•
Use of pilot earth system
30. Key Take Away’s
•
Don’t assume everything has been commissioned correctly
•
Ensure installations and equipment comply with the relevant Australian Standards.
•
Continue investigations until the root cause is well understood and engage external expertise (OEM’s, Consultants) to help understand the issue.
•
Foster a work culture where reporting of faults is encouraged and supported.
•
Ensure the cookie cutter approach to engineering design & projects is coupled with a design & standards review for new installations.
30