SlideShare a Scribd company logo
1 of 4
Download to read offline
www.systemprotection.in +91-265-2225137
ISO 9001:2015
ISO 45001:2015 (OH & S)
Certified Company
Importance of Relay Coordination in
Process Industries
Case Study
There are certainly quite a few cases of inadvertent tripping in cement plants, steel plants,
fertilizer plants, FMCG and other industries that many Electrical Engineers witness at a certain
point of time. Such scenarios occur in the majority of industries, not for the reason that the
protection plan of these industries is not properly coordinated but because changes in the
electrical system take place on a day-to-day basis. Pinned below is the SLD of a Cement Plant
which failed due to poor Relay Coordination, we will discuss the same in this case study.
www.systemprotection.in +91-265-2225137
During one instance, the Clinker Hammer
Crusher Motor tripped in overload due to
jamming. It was after 30 seconds that the
control room gave the command to start
the crusher again as it was observed in the
past that jamming could be cleared by
heavy starting torque but this time
unexpectedly when the command was
given to crusher motor, the entire plant
tripped. It was unexpected because the
Clinker crusher jamming happens at least 3
to 4 times in a year and the plant was
running for the last 4 years and such co-
ordination problems never occurred. This
issue had arisen for the second time in the
last 3 months and our team was called to
address the issue.
The very first thing that we did was to check
whether the complete electrical system was
properly coordinated or not and it was
found that the system was well coordinated
since the commissioning stage and they
had the records for the same.
Thereafter, we inquired about any
modification done in the distribution team
like replacing the existing motor with less
KW or adding any extra load on that MCC
because of any process requirement. They
told us that a 37 kW old compressor was
removed as it was no longer being used and
one 18- kW compressor was shifted from
another MCC to the present MCC as the
load on that MCC was around 100 %. They
also told us that one more change was
made. A 75 kW high-pressure pump that
was used for breaking jamming in Kiln was
installed as per the requirement of
process/production. Therefore, a total of
around 217 kW was added and the settings
were manually adjusted according to the
MCC incomer and PCC outgoing panel.
www.systemprotection.in +91-265-2225137
It was a 5000 TPD plant and this
breakdown cost the plant around 410 tons
of clinker which is approximately 500 tons
of cement (10000 Bags of cement). It
turned around to be a loss of INR 2.5 to 2.8
millions in just 2 hours (Total of INR 5 – 5.5
million for 2 breakdowns). Besides, the time,
all the efforts put in for the modification to
improve stability and efficiency went waste.
Ideally, the MCC-6 Incomer should have
tripped and not the motor because the
motor started normally with just the extra
load on it.
Knowing all these details, we concluded
that the reason for such a problem was that
there was a clinker lump and the clinker
crusher motor was tripped. Based on the
experience, they took action and restarted it
again after 30 seconds but as the whole
plant was running except clinker crusher,
MCC was already at 80% load and when the
315 kW motor started, the starting current
was around 4 to 5 times of motor FLC. The
total current crossed the threshold of that
relays and they forgot to make changes in
the setting of 6.6 kV Side as mentioned in
SLD. This made the complete PCC bus dead
and the total plant was completely tripped
and it took around 2 hours to start back.
Thus, it was concluded that to avoid such
an issue which incurs heavy losses, each
time any kind of big modification is made
to the electrical distribution system viz.
adding load or adding any source, the
complete relaying and protection should be
coordinated again.
CONTACT INFORMATION
301/2/306, Silverline Complex,Opposite BBC
Tower,Sayajigunj,Vadodara - 390 005,
Gujarat, India.
bdm@systemprotection.in
www.systemprotection.in
+91-265-2225137

More Related Content

What's hot

ETAP - Transient stability
ETAP - Transient stabilityETAP - Transient stability
ETAP - Transient stabilityHimmelstern
 
Transformer Diagnostics | Sweep Frequency Response Analysis
Transformer Diagnostics | Sweep Frequency Response AnalysisTransformer Diagnostics | Sweep Frequency Response Analysis
Transformer Diagnostics | Sweep Frequency Response AnalysisHamedPasha1
 
ETAP - Transformer sizing using etap
ETAP - Transformer sizing using etapETAP - Transformer sizing using etap
ETAP - Transformer sizing using etapHimmelstern
 
Generator Protection By - Er Rahul Sharma
Generator Protection By - Er Rahul Sharma Generator Protection By - Er Rahul Sharma
Generator Protection By - Er Rahul Sharma Rahul Ruddra
 
Case Study - How we saved a Process Plant from break-down
Case Study - How we saved a Process Plant from break-downCase Study - How we saved a Process Plant from break-down
Case Study - How we saved a Process Plant from break-downSystem Protection
 
Lightning impulse test in precise
Lightning impulse test in  preciseLightning impulse test in  precise
Lightning impulse test in preciseMuthar Hussain
 
ETAP - Transformer mva sizing
ETAP - Transformer mva sizingETAP - Transformer mva sizing
ETAP - Transformer mva sizingHimmelstern
 
class on Protection.pptx
class on Protection.pptxclass on Protection.pptx
class on Protection.pptxSubhroSen9
 
Lecture 9 load equalization
Lecture 9 load equalizationLecture 9 load equalization
Lecture 9 load equalizationSwapnil Gadgune
 
ETAP - Coordination and protecion 2
ETAP -  Coordination and protecion 2ETAP -  Coordination and protecion 2
ETAP - Coordination and protecion 2Himmelstern
 
Genrator Relay Protection & Logics
Genrator Relay Protection & LogicsGenrator Relay Protection & Logics
Genrator Relay Protection & LogicsMahadev Kovalli
 
Unit 2 Questions_Nagrath kothari
Unit 2 Questions_Nagrath kothariUnit 2 Questions_Nagrath kothari
Unit 2 Questions_Nagrath kothariAbha Tripathi
 
An introduction to FACTS
An introduction to FACTSAn introduction to FACTS
An introduction to FACTSAyyarao T S L V
 
Power transformer protection
Power transformer protectionPower transformer protection
Power transformer protectionmichaeljmack
 
Transformer failure case study
Transformer failure case studyTransformer failure case study
Transformer failure case studyLeonardo ENERGY
 
ETAP - Short circuit analysis iec standard
ETAP - Short circuit analysis iec standardETAP - Short circuit analysis iec standard
ETAP - Short circuit analysis iec standardHimmelstern
 

What's hot (20)

ETAP - Transient stability
ETAP - Transient stabilityETAP - Transient stability
ETAP - Transient stability
 
Transformer Diagnostics | Sweep Frequency Response Analysis
Transformer Diagnostics | Sweep Frequency Response AnalysisTransformer Diagnostics | Sweep Frequency Response Analysis
Transformer Diagnostics | Sweep Frequency Response Analysis
 
ETAP - Transformer sizing using etap
ETAP - Transformer sizing using etapETAP - Transformer sizing using etap
ETAP - Transformer sizing using etap
 
Generator Protection By - Er Rahul Sharma
Generator Protection By - Er Rahul Sharma Generator Protection By - Er Rahul Sharma
Generator Protection By - Er Rahul Sharma
 
Reactors
ReactorsReactors
Reactors
 
Case Study - How we saved a Process Plant from break-down
Case Study - How we saved a Process Plant from break-downCase Study - How we saved a Process Plant from break-down
Case Study - How we saved a Process Plant from break-down
 
Lightning impulse test in precise
Lightning impulse test in  preciseLightning impulse test in  precise
Lightning impulse test in precise
 
ETAP - Transformer mva sizing
ETAP - Transformer mva sizingETAP - Transformer mva sizing
ETAP - Transformer mva sizing
 
Overcurrent protection
Overcurrent protectionOvercurrent protection
Overcurrent protection
 
class on Protection.pptx
class on Protection.pptxclass on Protection.pptx
class on Protection.pptx
 
Lecture 9 load equalization
Lecture 9 load equalizationLecture 9 load equalization
Lecture 9 load equalization
 
ETAP - Coordination and protecion 2
ETAP -  Coordination and protecion 2ETAP -  Coordination and protecion 2
ETAP - Coordination and protecion 2
 
Motor Protection
Motor ProtectionMotor Protection
Motor Protection
 
Genrator Relay Protection & Logics
Genrator Relay Protection & LogicsGenrator Relay Protection & Logics
Genrator Relay Protection & Logics
 
Unit 2 Questions_Nagrath kothari
Unit 2 Questions_Nagrath kothariUnit 2 Questions_Nagrath kothari
Unit 2 Questions_Nagrath kothari
 
An introduction to FACTS
An introduction to FACTSAn introduction to FACTS
An introduction to FACTS
 
Power transformer protection
Power transformer protectionPower transformer protection
Power transformer protection
 
(7) overfluxing
(7) overfluxing(7) overfluxing
(7) overfluxing
 
Transformer failure case study
Transformer failure case studyTransformer failure case study
Transformer failure case study
 
ETAP - Short circuit analysis iec standard
ETAP - Short circuit analysis iec standardETAP - Short circuit analysis iec standard
ETAP - Short circuit analysis iec standard
 

Similar to Case Study - Importance of Relay Coordination in Process Industries

2 PCCE White_Paper-Rev5
2 PCCE White_Paper-Rev52 PCCE White_Paper-Rev5
2 PCCE White_Paper-Rev5Victor Sauers
 
Rajghat power house ppt
Rajghat power house pptRajghat power house ppt
Rajghat power house pptEr Sagar
 
5T Intemediate Frequency Furnace
5T Intemediate Frequency Furnace5T Intemediate Frequency Furnace
5T Intemediate Frequency FurnaceGuo ke
 
Power System Protection -Plant visiting report
Power System Protection -Plant visiting report Power System Protection -Plant visiting report
Power System Protection -Plant visiting report AB Amit
 
Engineering Practice Report
Engineering Practice ReportEngineering Practice Report
Engineering Practice ReportPaul Soko
 
Shivam Dubey trainees mechanical engineering NTPC ltd.Vindhyachal .pdf
Shivam Dubey trainees mechanical engineering NTPC ltd.Vindhyachal .pdfShivam Dubey trainees mechanical engineering NTPC ltd.Vindhyachal .pdf
Shivam Dubey trainees mechanical engineering NTPC ltd.Vindhyachal .pdfShivam Dubey
 
MEECL Chakresh report UTM Shillong
MEECL Chakresh report UTM ShillongMEECL Chakresh report UTM Shillong
MEECL Chakresh report UTM ShillongChakresh Tiwari
 
Winter Newsletter 1.12.16
Winter Newsletter 1.12.16Winter Newsletter 1.12.16
Winter Newsletter 1.12.16fidge72
 
NTPC faridabad nd badarpur
NTPC faridabad nd badarpurNTPC faridabad nd badarpur
NTPC faridabad nd badarpurShrey Dhasmana
 
Fire Pump Engines Overview
Fire Pump Engines OverviewFire Pump Engines Overview
Fire Pump Engines OverviewJames S Nasby
 
internship report final.DOC
internship report final.DOCinternship report final.DOC
internship report final.DOCqazi faisal
 
Steam_E_RevA_202109_Rev.1_0_Mitsubishi Power.pdf
Steam_E_RevA_202109_Rev.1_0_Mitsubishi Power.pdfSteam_E_RevA_202109_Rev.1_0_Mitsubishi Power.pdf
Steam_E_RevA_202109_Rev.1_0_Mitsubishi Power.pdfHafidz Akbar
 
Study of generator and switchgear Vizag steel plant report
Study of generator and switchgear Vizag steel plant reportStudy of generator and switchgear Vizag steel plant report
Study of generator and switchgear Vizag steel plant reportsushi roy
 
2010 Energy Presentation
2010 Energy Presentation2010 Energy Presentation
2010 Energy PresentationChad Blair
 
ONALAJA OLORUNTIMILEHIN EGBIN PRESENTATION SLIDE.pptx
ONALAJA OLORUNTIMILEHIN EGBIN PRESENTATION SLIDE.pptxONALAJA OLORUNTIMILEHIN EGBIN PRESENTATION SLIDE.pptx
ONALAJA OLORUNTIMILEHIN EGBIN PRESENTATION SLIDE.pptxTimilehinonalaja
 

Similar to Case Study - Importance of Relay Coordination in Process Industries (20)

2 PCCE White_Paper-Rev5
2 PCCE White_Paper-Rev52 PCCE White_Paper-Rev5
2 PCCE White_Paper-Rev5
 
Rajghat power house ppt
Rajghat power house pptRajghat power house ppt
Rajghat power house ppt
 
5T Intemediate Frequency Furnace
5T Intemediate Frequency Furnace5T Intemediate Frequency Furnace
5T Intemediate Frequency Furnace
 
Power System Protection -Plant visiting report
Power System Protection -Plant visiting report Power System Protection -Plant visiting report
Power System Protection -Plant visiting report
 
Engineering Practice Report
Engineering Practice ReportEngineering Practice Report
Engineering Practice Report
 
motor drives report
motor drives reportmotor drives report
motor drives report
 
Shivam Dubey trainees mechanical engineering NTPC ltd.Vindhyachal .pdf
Shivam Dubey trainees mechanical engineering NTPC ltd.Vindhyachal .pdfShivam Dubey trainees mechanical engineering NTPC ltd.Vindhyachal .pdf
Shivam Dubey trainees mechanical engineering NTPC ltd.Vindhyachal .pdf
 
Chakresh meecl report
Chakresh meecl reportChakresh meecl report
Chakresh meecl report
 
MEECL Chakresh report UTM Shillong
MEECL Chakresh report UTM ShillongMEECL Chakresh report UTM Shillong
MEECL Chakresh report UTM Shillong
 
Winter Newsletter 1.12.16
Winter Newsletter 1.12.16Winter Newsletter 1.12.16
Winter Newsletter 1.12.16
 
11-IAGT-202_paper
11-IAGT-202_paper11-IAGT-202_paper
11-IAGT-202_paper
 
Resume Superintendent Head Electrical
Resume Superintendent Head ElectricalResume Superintendent Head Electrical
Resume Superintendent Head Electrical
 
NTPC faridabad nd badarpur
NTPC faridabad nd badarpurNTPC faridabad nd badarpur
NTPC faridabad nd badarpur
 
Fire Pump Engines Overview
Fire Pump Engines OverviewFire Pump Engines Overview
Fire Pump Engines Overview
 
internship report final.DOC
internship report final.DOCinternship report final.DOC
internship report final.DOC
 
Steam_E_RevA_202109_Rev.1_0_Mitsubishi Power.pdf
Steam_E_RevA_202109_Rev.1_0_Mitsubishi Power.pdfSteam_E_RevA_202109_Rev.1_0_Mitsubishi Power.pdf
Steam_E_RevA_202109_Rev.1_0_Mitsubishi Power.pdf
 
My ppt vfd
My ppt vfdMy ppt vfd
My ppt vfd
 
Study of generator and switchgear Vizag steel plant report
Study of generator and switchgear Vizag steel plant reportStudy of generator and switchgear Vizag steel plant report
Study of generator and switchgear Vizag steel plant report
 
2010 Energy Presentation
2010 Energy Presentation2010 Energy Presentation
2010 Energy Presentation
 
ONALAJA OLORUNTIMILEHIN EGBIN PRESENTATION SLIDE.pptx
ONALAJA OLORUNTIMILEHIN EGBIN PRESENTATION SLIDE.pptxONALAJA OLORUNTIMILEHIN EGBIN PRESENTATION SLIDE.pptx
ONALAJA OLORUNTIMILEHIN EGBIN PRESENTATION SLIDE.pptx
 

More from System Protection

Transformer differential protection – SIEMENS Reyrolle 7SR54
Transformer differential protection – SIEMENS Reyrolle 7SR54Transformer differential protection – SIEMENS Reyrolle 7SR54
Transformer differential protection – SIEMENS Reyrolle 7SR54System Protection
 
Mastering Motor Protection with SIEMENS Reyrolle 7SR17: Safeguarding Your Assets
Mastering Motor Protection with SIEMENS Reyrolle 7SR17: Safeguarding Your AssetsMastering Motor Protection with SIEMENS Reyrolle 7SR17: Safeguarding Your Assets
Mastering Motor Protection with SIEMENS Reyrolle 7SR17: Safeguarding Your AssetsSystem Protection
 
AC Digital Clamp Meter KEW 2204R Overview | System Protection
AC Digital Clamp Meter KEW 2204R Overview | System ProtectionAC Digital Clamp Meter KEW 2204R Overview | System Protection
AC Digital Clamp Meter KEW 2204R Overview | System ProtectionSystem Protection
 
Digital Multimeter with AC/DC Clamp Sensor KEWMATE 2012RA | System Protection
Digital Multimeter with AC/DC Clamp Sensor KEWMATE 2012RA | System ProtectionDigital Multimeter with AC/DC Clamp Sensor KEWMATE 2012RA | System Protection
Digital Multimeter with AC/DC Clamp Sensor KEWMATE 2012RA | System ProtectionSystem Protection
 
DIGITAL MULTIMETERS KEW 1052 | System Protection
DIGITAL MULTIMETERS KEW 1052 | System ProtectionDIGITAL MULTIMETERS KEW 1052 | System Protection
DIGITAL MULTIMETERS KEW 1052 | System ProtectionSystem Protection
 
Kyoritsu Voltage Detector KEW 5711
Kyoritsu Voltage Detector KEW 5711Kyoritsu Voltage Detector KEW 5711
Kyoritsu Voltage Detector KEW 5711System Protection
 
Earth Clamp Testing with the KEW 4202 | Ultimate Tool for Earth Clamp Testing
Earth Clamp Testing with the KEW 4202 | Ultimate Tool for Earth Clamp TestingEarth Clamp Testing with the KEW 4202 | Ultimate Tool for Earth Clamp Testing
Earth Clamp Testing with the KEW 4202 | Ultimate Tool for Earth Clamp TestingSystem Protection
 
Kyoritsu Multi-Function Testers | KEW 6016
Kyoritsu Multi-Function Testers | KEW 6016Kyoritsu Multi-Function Testers | KEW 6016
Kyoritsu Multi-Function Testers | KEW 6016System Protection
 
Honeywell | Overcoat | Fabric Composition (Patented)
Honeywell | Overcoat | Fabric Composition (Patented)Honeywell | Overcoat | Fabric Composition (Patented)
Honeywell | Overcoat | Fabric Composition (Patented)System Protection
 
Case Study – How an Unchecked Capacitor can cause loss of revenue
Case Study – How an Unchecked Capacitor can cause loss of revenueCase Study – How an Unchecked Capacitor can cause loss of revenue
Case Study – How an Unchecked Capacitor can cause loss of revenueSystem Protection
 
HONEYWELL - Electrical Safety Mat | HONEYWELL Insulating Rubber Mat
HONEYWELL - Electrical Safety Mat | HONEYWELL Insulating Rubber MatHONEYWELL - Electrical Safety Mat | HONEYWELL Insulating Rubber Mat
HONEYWELL - Electrical Safety Mat | HONEYWELL Insulating Rubber MatSystem Protection
 
Salisbury By Honeywell | 51511 Di – Electric Over Shoes
Salisbury By Honeywell | 51511 Di – Electric Over ShoesSalisbury By Honeywell | 51511 Di – Electric Over Shoes
Salisbury By Honeywell | 51511 Di – Electric Over ShoesSystem Protection
 
Salisbury By Honeywell | 4556 Voltage Detector 240V to 230kV
Salisbury By Honeywell | 4556 Voltage Detector 240V to 230kVSalisbury By Honeywell | 4556 Voltage Detector 240V to 230kV
Salisbury By Honeywell | 4556 Voltage Detector 240V to 230kVSystem Protection
 
LOGGER KEW 5020 | KYORITSU | System Protection
LOGGER KEW 5020 | KYORITSU | System ProtectionLOGGER KEW 5020 | KYORITSU | System Protection
LOGGER KEW 5020 | KYORITSU | System ProtectionSystem Protection
 
PORTABLE APPLIANCE TESTER KEW 6205 | KYORITSU | System Protection
PORTABLE APPLIANCE TESTER KEW 6205 | KYORITSU | System ProtectionPORTABLE APPLIANCE TESTER KEW 6205 | KYORITSU | System Protection
PORTABLE APPLIANCE TESTER KEW 6205 | KYORITSU | System ProtectionSystem Protection
 
RCD TESTER KEW 5410| KYORITSU | System Protection
RCD TESTER KEW 5410| KYORITSU | System ProtectionRCD TESTER KEW 5410| KYORITSU | System Protection
RCD TESTER KEW 5410| KYORITSU | System ProtectionSystem Protection
 
Case Study | How we solved an Earth-fault (mal)Tripping that was causing trip...
Case Study | How we solved an Earth-fault (mal)Tripping that was causing trip...Case Study | How we solved an Earth-fault (mal)Tripping that was causing trip...
Case Study | How we solved an Earth-fault (mal)Tripping that was causing trip...System Protection
 
Case Study | How your Motor Protection should designed when running in parall...
Case Study | How your Motor Protection should designed when running in parall...Case Study | How your Motor Protection should designed when running in parall...
Case Study | How your Motor Protection should designed when running in parall...System Protection
 
Case Study | How we saved a Generator (in fact two), again!
Case Study | How we saved a Generator (in fact two), again!Case Study | How we saved a Generator (in fact two), again!
Case Study | How we saved a Generator (in fact two), again!System Protection
 
AC/DC Digital Clamp Meters | KEW 2010 | Kyoritsu
AC/DC Digital Clamp Meters | KEW 2010 | KyoritsuAC/DC Digital Clamp Meters | KEW 2010 | Kyoritsu
AC/DC Digital Clamp Meters | KEW 2010 | KyoritsuSystem Protection
 

More from System Protection (20)

Transformer differential protection – SIEMENS Reyrolle 7SR54
Transformer differential protection – SIEMENS Reyrolle 7SR54Transformer differential protection – SIEMENS Reyrolle 7SR54
Transformer differential protection – SIEMENS Reyrolle 7SR54
 
Mastering Motor Protection with SIEMENS Reyrolle 7SR17: Safeguarding Your Assets
Mastering Motor Protection with SIEMENS Reyrolle 7SR17: Safeguarding Your AssetsMastering Motor Protection with SIEMENS Reyrolle 7SR17: Safeguarding Your Assets
Mastering Motor Protection with SIEMENS Reyrolle 7SR17: Safeguarding Your Assets
 
AC Digital Clamp Meter KEW 2204R Overview | System Protection
AC Digital Clamp Meter KEW 2204R Overview | System ProtectionAC Digital Clamp Meter KEW 2204R Overview | System Protection
AC Digital Clamp Meter KEW 2204R Overview | System Protection
 
Digital Multimeter with AC/DC Clamp Sensor KEWMATE 2012RA | System Protection
Digital Multimeter with AC/DC Clamp Sensor KEWMATE 2012RA | System ProtectionDigital Multimeter with AC/DC Clamp Sensor KEWMATE 2012RA | System Protection
Digital Multimeter with AC/DC Clamp Sensor KEWMATE 2012RA | System Protection
 
DIGITAL MULTIMETERS KEW 1052 | System Protection
DIGITAL MULTIMETERS KEW 1052 | System ProtectionDIGITAL MULTIMETERS KEW 1052 | System Protection
DIGITAL MULTIMETERS KEW 1052 | System Protection
 
Kyoritsu Voltage Detector KEW 5711
Kyoritsu Voltage Detector KEW 5711Kyoritsu Voltage Detector KEW 5711
Kyoritsu Voltage Detector KEW 5711
 
Earth Clamp Testing with the KEW 4202 | Ultimate Tool for Earth Clamp Testing
Earth Clamp Testing with the KEW 4202 | Ultimate Tool for Earth Clamp TestingEarth Clamp Testing with the KEW 4202 | Ultimate Tool for Earth Clamp Testing
Earth Clamp Testing with the KEW 4202 | Ultimate Tool for Earth Clamp Testing
 
Kyoritsu Multi-Function Testers | KEW 6016
Kyoritsu Multi-Function Testers | KEW 6016Kyoritsu Multi-Function Testers | KEW 6016
Kyoritsu Multi-Function Testers | KEW 6016
 
Honeywell | Overcoat | Fabric Composition (Patented)
Honeywell | Overcoat | Fabric Composition (Patented)Honeywell | Overcoat | Fabric Composition (Patented)
Honeywell | Overcoat | Fabric Composition (Patented)
 
Case Study – How an Unchecked Capacitor can cause loss of revenue
Case Study – How an Unchecked Capacitor can cause loss of revenueCase Study – How an Unchecked Capacitor can cause loss of revenue
Case Study – How an Unchecked Capacitor can cause loss of revenue
 
HONEYWELL - Electrical Safety Mat | HONEYWELL Insulating Rubber Mat
HONEYWELL - Electrical Safety Mat | HONEYWELL Insulating Rubber MatHONEYWELL - Electrical Safety Mat | HONEYWELL Insulating Rubber Mat
HONEYWELL - Electrical Safety Mat | HONEYWELL Insulating Rubber Mat
 
Salisbury By Honeywell | 51511 Di – Electric Over Shoes
Salisbury By Honeywell | 51511 Di – Electric Over ShoesSalisbury By Honeywell | 51511 Di – Electric Over Shoes
Salisbury By Honeywell | 51511 Di – Electric Over Shoes
 
Salisbury By Honeywell | 4556 Voltage Detector 240V to 230kV
Salisbury By Honeywell | 4556 Voltage Detector 240V to 230kVSalisbury By Honeywell | 4556 Voltage Detector 240V to 230kV
Salisbury By Honeywell | 4556 Voltage Detector 240V to 230kV
 
LOGGER KEW 5020 | KYORITSU | System Protection
LOGGER KEW 5020 | KYORITSU | System ProtectionLOGGER KEW 5020 | KYORITSU | System Protection
LOGGER KEW 5020 | KYORITSU | System Protection
 
PORTABLE APPLIANCE TESTER KEW 6205 | KYORITSU | System Protection
PORTABLE APPLIANCE TESTER KEW 6205 | KYORITSU | System ProtectionPORTABLE APPLIANCE TESTER KEW 6205 | KYORITSU | System Protection
PORTABLE APPLIANCE TESTER KEW 6205 | KYORITSU | System Protection
 
RCD TESTER KEW 5410| KYORITSU | System Protection
RCD TESTER KEW 5410| KYORITSU | System ProtectionRCD TESTER KEW 5410| KYORITSU | System Protection
RCD TESTER KEW 5410| KYORITSU | System Protection
 
Case Study | How we solved an Earth-fault (mal)Tripping that was causing trip...
Case Study | How we solved an Earth-fault (mal)Tripping that was causing trip...Case Study | How we solved an Earth-fault (mal)Tripping that was causing trip...
Case Study | How we solved an Earth-fault (mal)Tripping that was causing trip...
 
Case Study | How your Motor Protection should designed when running in parall...
Case Study | How your Motor Protection should designed when running in parall...Case Study | How your Motor Protection should designed when running in parall...
Case Study | How your Motor Protection should designed when running in parall...
 
Case Study | How we saved a Generator (in fact two), again!
Case Study | How we saved a Generator (in fact two), again!Case Study | How we saved a Generator (in fact two), again!
Case Study | How we saved a Generator (in fact two), again!
 
AC/DC Digital Clamp Meters | KEW 2010 | Kyoritsu
AC/DC Digital Clamp Meters | KEW 2010 | KyoritsuAC/DC Digital Clamp Meters | KEW 2010 | Kyoritsu
AC/DC Digital Clamp Meters | KEW 2010 | Kyoritsu
 

Recently uploaded

PHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation FinalPHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation FinalPanhandleOilandGas
 
UAE Bur Dubai Call Girls ☏ 0564401582 Call Girl in Bur Dubai
UAE Bur Dubai Call Girls ☏ 0564401582 Call Girl in Bur DubaiUAE Bur Dubai Call Girls ☏ 0564401582 Call Girl in Bur Dubai
UAE Bur Dubai Call Girls ☏ 0564401582 Call Girl in Bur Dubaijaehdlyzca
 
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...Falcon Invoice Discounting
 
Berhampur CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGBerhampur CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGpr788182
 
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All TimeCall 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Timegargpaaro
 
Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...
Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...
Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...pujan9679
 
Mckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for ViewingMckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for ViewingNauman Safdar
 
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al MizharAl Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizharallensay1
 
GUWAHATI 💋 Call Girl 9827461493 Call Girls in Escort service book now
GUWAHATI 💋 Call Girl 9827461493 Call Girls in  Escort service book nowGUWAHATI 💋 Call Girl 9827461493 Call Girls in  Escort service book now
GUWAHATI 💋 Call Girl 9827461493 Call Girls in Escort service book nowkapoorjyoti4444
 
Falcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business PotentialFalcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business PotentialFalcon investment
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with CultureSeta Wicaksana
 
Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...
Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...
Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...meghakumariji156
 
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAIGetting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAITim Wilson
 
Kalyan Call Girl 98350*37198 Call Girls in Escort service book now
Kalyan Call Girl 98350*37198 Call Girls in Escort service book nowKalyan Call Girl 98350*37198 Call Girls in Escort service book now
Kalyan Call Girl 98350*37198 Call Girls in Escort service book nowranineha57744
 
Cannabis Legalization World Map: 2024 Updated
Cannabis Legalization World Map: 2024 UpdatedCannabis Legalization World Map: 2024 Updated
Cannabis Legalization World Map: 2024 UpdatedCannaBusinessPlans
 
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGParadip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGpr788182
 
Falcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investorsFalcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investorsFalcon Invoice Discounting
 
Pre Engineered Building Manufacturers Hyderabad.pptx
Pre Engineered  Building Manufacturers Hyderabad.pptxPre Engineered  Building Manufacturers Hyderabad.pptx
Pre Engineered Building Manufacturers Hyderabad.pptxRoofing Contractor
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...daisycvs
 

Recently uploaded (20)

PHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation FinalPHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation Final
 
Buy gmail accounts.pdf buy Old Gmail Accounts
Buy gmail accounts.pdf buy Old Gmail AccountsBuy gmail accounts.pdf buy Old Gmail Accounts
Buy gmail accounts.pdf buy Old Gmail Accounts
 
UAE Bur Dubai Call Girls ☏ 0564401582 Call Girl in Bur Dubai
UAE Bur Dubai Call Girls ☏ 0564401582 Call Girl in Bur DubaiUAE Bur Dubai Call Girls ☏ 0564401582 Call Girl in Bur Dubai
UAE Bur Dubai Call Girls ☏ 0564401582 Call Girl in Bur Dubai
 
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
 
Berhampur CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGBerhampur CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
 
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All TimeCall 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
 
Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...
Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...
Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...
 
Mckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for ViewingMckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for Viewing
 
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al MizharAl Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
 
GUWAHATI 💋 Call Girl 9827461493 Call Girls in Escort service book now
GUWAHATI 💋 Call Girl 9827461493 Call Girls in  Escort service book nowGUWAHATI 💋 Call Girl 9827461493 Call Girls in  Escort service book now
GUWAHATI 💋 Call Girl 9827461493 Call Girls in Escort service book now
 
Falcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business PotentialFalcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business Potential
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with Culture
 
Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...
Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...
Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...
 
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAIGetting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
 
Kalyan Call Girl 98350*37198 Call Girls in Escort service book now
Kalyan Call Girl 98350*37198 Call Girls in Escort service book nowKalyan Call Girl 98350*37198 Call Girls in Escort service book now
Kalyan Call Girl 98350*37198 Call Girls in Escort service book now
 
Cannabis Legalization World Map: 2024 Updated
Cannabis Legalization World Map: 2024 UpdatedCannabis Legalization World Map: 2024 Updated
Cannabis Legalization World Map: 2024 Updated
 
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGParadip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
 
Falcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investorsFalcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investors
 
Pre Engineered Building Manufacturers Hyderabad.pptx
Pre Engineered  Building Manufacturers Hyderabad.pptxPre Engineered  Building Manufacturers Hyderabad.pptx
Pre Engineered Building Manufacturers Hyderabad.pptx
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
 

Case Study - Importance of Relay Coordination in Process Industries

  • 1. www.systemprotection.in +91-265-2225137 ISO 9001:2015 ISO 45001:2015 (OH & S) Certified Company Importance of Relay Coordination in Process Industries Case Study
  • 2. There are certainly quite a few cases of inadvertent tripping in cement plants, steel plants, fertilizer plants, FMCG and other industries that many Electrical Engineers witness at a certain point of time. Such scenarios occur in the majority of industries, not for the reason that the protection plan of these industries is not properly coordinated but because changes in the electrical system take place on a day-to-day basis. Pinned below is the SLD of a Cement Plant which failed due to poor Relay Coordination, we will discuss the same in this case study. www.systemprotection.in +91-265-2225137 During one instance, the Clinker Hammer Crusher Motor tripped in overload due to jamming. It was after 30 seconds that the control room gave the command to start the crusher again as it was observed in the past that jamming could be cleared by heavy starting torque but this time unexpectedly when the command was given to crusher motor, the entire plant tripped. It was unexpected because the Clinker crusher jamming happens at least 3 to 4 times in a year and the plant was running for the last 4 years and such co- ordination problems never occurred. This issue had arisen for the second time in the last 3 months and our team was called to address the issue. The very first thing that we did was to check whether the complete electrical system was properly coordinated or not and it was found that the system was well coordinated since the commissioning stage and they had the records for the same.
  • 3. Thereafter, we inquired about any modification done in the distribution team like replacing the existing motor with less KW or adding any extra load on that MCC because of any process requirement. They told us that a 37 kW old compressor was removed as it was no longer being used and one 18- kW compressor was shifted from another MCC to the present MCC as the load on that MCC was around 100 %. They also told us that one more change was made. A 75 kW high-pressure pump that was used for breaking jamming in Kiln was installed as per the requirement of process/production. Therefore, a total of around 217 kW was added and the settings were manually adjusted according to the MCC incomer and PCC outgoing panel. www.systemprotection.in +91-265-2225137 It was a 5000 TPD plant and this breakdown cost the plant around 410 tons of clinker which is approximately 500 tons of cement (10000 Bags of cement). It turned around to be a loss of INR 2.5 to 2.8 millions in just 2 hours (Total of INR 5 – 5.5 million for 2 breakdowns). Besides, the time, all the efforts put in for the modification to improve stability and efficiency went waste. Ideally, the MCC-6 Incomer should have tripped and not the motor because the motor started normally with just the extra load on it. Knowing all these details, we concluded that the reason for such a problem was that there was a clinker lump and the clinker crusher motor was tripped. Based on the experience, they took action and restarted it again after 30 seconds but as the whole plant was running except clinker crusher, MCC was already at 80% load and when the 315 kW motor started, the starting current was around 4 to 5 times of motor FLC. The total current crossed the threshold of that relays and they forgot to make changes in the setting of 6.6 kV Side as mentioned in SLD. This made the complete PCC bus dead and the total plant was completely tripped and it took around 2 hours to start back. Thus, it was concluded that to avoid such an issue which incurs heavy losses, each time any kind of big modification is made to the electrical distribution system viz. adding load or adding any source, the complete relaying and protection should be coordinated again.
  • 4. CONTACT INFORMATION 301/2/306, Silverline Complex,Opposite BBC Tower,Sayajigunj,Vadodara - 390 005, Gujarat, India. bdm@systemprotection.in www.systemprotection.in +91-265-2225137