SlideShare a Scribd company logo
1 of 60
Download to read offline
ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL
42
Project Number: ____________________________________________________________________________________
Project Name: ______________________________________________________________________________________
Location: ___________________________________________________________________________________________
Estimator: __________________________________________________________________________________________
Project Manager: ____________________________________________________________________________________
PRE-CONSTRUCTION PLANNING CHECKLIST
COMPLETION ACTIVITY ACT.
DATE CATEGORY NO.
ACTIVITY
II 1
Finalize selection of project manager, field supervisor
and other key team members.
II 2
Hold turnover meeting between estimator and project
separate manager (when applicable).
II 3
Hold separate turnover meeting between project
manager and field supervisor.
II 4
Hold pre-job (planning) kickoff meeting with internal
team members to assign responsibilities.
II 5
Review contract for unfavorable or high risk clauses
(recommended).
II 6
Project manager reviews plans, specifications, and
schedule.
II 7
Field supervisor reviews plans, specifications, and
schedule.
II 8
Create a list of issues that need to be resolved and
begin the request for information (RFI) process.
II 9 Conduct site visit (recommended).
II 10
Compare estimated (bid) work activities and materials
to planned performance.
II 11
Identify value engineering and refabrication
opportunities and how to simplify the work.
II 12 Prepare construction takeoff.
II 13 Set up project files and create contact list.
II 14
Set up computerized tracking and control system
(forms, database, schedule, tracking).
II 15 Initiate a change management system.
II 16
Initiate a request for information (RFI) tracking and
processing system.
II 17 Initiate a submittal tracking and processing system.
II 18
Develop a “Labor Requirements/Expectations” letter
(for background check, etc.) (recommended).
Table 4.1: Checklist of Pre-Construction Planning Activities (page 15)
Team
Selection and
Turnover
Scope and
Contract
Review
Administrative
Setup
PRE-CONSTRUCTION PLANNING ACTIVITIES
43
Project Number: ____________________________________________________________________________________
Table 4.1: Checklist of Pre-Construction Planning Activities (continued)
PRE-CONSTRUCTION PLANNING CHECKLIST
COMPLETION ACTIVITY ACT.
DATE CATEGORY NO.
ACTIVITY
II 19
Price and/or review subcontractor/supplier/vendor
prices and qualifications.
II 20
Negotiate pricing and contract conditions, and select
separate subcontractors/suppliers/vendors.
II 21
Develop and issue purchase orders and contracts for
materials and equipment.
II 22 Order long-lead-time materials and equipment.
II 23 Request submittals, cut sheets and shop drawings.
II 24
Develop and process log and book of submittals, cut
sheets and shop drawings.
II 25 Develop material delivery and handling plan.
II 26 Develop material storage and staging plan.
II 27 Develop, review or expand cost code scheme.
II 28
Develop budget by breaking down labor, material,
overhead and profit costs.
II 29 Develop schedule of values.
II 30 Develop installation sequence and layout drawings.
II 31
Develop field instructions, including panel, pull or
conduit schedules.
II 32
Develop prefabrication drawings for field use (when
applicable).
II 33 Review customer’s schedule and timeline.
II 34 Identify work that impacts electrical activities.
II 35
Review the work sequence and long-lead-time
material/equipment delivery dates.
II 36 Coordinate electrical schedule with customer schedule
(recommended).
II 37 Create a bar chart schedule (recommended).
Customize the computerized tracking and control
II 38 system (database/schedule/etc.) for the current
project.
II 39 Develop labor and materials tracking report.
Buyout
Process
Material
Handling Plan
Budget
Preparation
Layout and
Sequencing
Plan
Schedule
Development
Tracking and
Control
ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL
44
Project Number: ____________________________________________________________________________________
PRE-CONSTRUCTION PLANNING CHECKLIST
COMPLETION ACTIVITY ACT.
DATE CATEGORY NO.
ACTIVITY
II 40 Review meeting schedule.
II 41 Review request for information (RFI) process.
II 42
Review change order process and field change
management process.
II 43 Review submittal processing procedure.
II 44 Review billing and invoicing procedures.
II 45
Review project and field reporting and tracking
procedures.
II 46 Review electrical and customer schedules.
Construction
Execution
Kickoff
Meeting
Table 4.1: Checklist of Pre-Construction Planning Activities (continued)
PRE-CONSTRUCTION PLANNING ACTIVITIES
45
Project Number: _____________________________________________________________________________________
Project Name: _______________________________________________________________________________________
Location:____________________________________________________________________________________________
Estimator:___________________________________________________________________________________________
Project Manager:_____________________________________________________________________________________
TEAM SELECTION AND TURNOVER CHECKLIST FOR PRE-CONSTRUCTION PLANNING
ACT.
COMPLETION ITEM
DATE NO.
SUB-ACTIVITIES
1. Finalize selection of project manager, field supervisor and other key team members.
II 1
Assemble a list of project managers and review their current work-
load and special skills.
II 2
Determine whether an ideal match can be made between the project
manager and the job, and then select the project manager.
II 3
Assemble a list of field supervisors and review their current work-
load and special skills.
II 4
Determine whether an ideal match can be made between the field
supervisor and the job, and then select the project manager.
II 5
Work with the project manager, field supervisor, and/or the director
of operations to select key foreman when appropriate.
2. Hold turnover meeting between estimator and project manager (when applicable).
II 1
Arrange a meeting time and location and ensure enough time has
been allocated to transfer knowledge between the estimator and
project manager.
II 2
Follow and complete a checklist that describes the information that
should be transferred (See Table 4.3).
3. Hold separate turnover meeting between project manager and field supervisor.
II Arrange a meeting time and location and ensure enough time has
1 been allocated to transfer knowledge between the project manager
and field supervisor.
II 2
Follow and complete a checklist that describes the information that
must be transferred (see Table 4.3).
4. Hold pre-job (planning) kickoff meeting with internal team members to assign responsibilities.
II 1
Arrange a meeting time and location and ensure enough time has
been allocated to assign planning responsibilities.
II Invite internal team members that will be involved during the
2 construction execution process, such as project manager, field
supervisor, accounting, purchasing, and director of field operations.
II 3
Complete a checklist that describes the planning activities that must
be completed and who is responsible for completion (see Table 4.4).
Table 4.2: Team Selection and Turnover Checklist (page 16)
ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL
46
TURNOVER MEETING AGENDA
Review Items:
1. Project overview
a. Project name
b. Location
c. Type of work
d. Estimated cost and estimated work hours
e. Profit goal
f. General scope of work
g. Identify potential opportunities and challenges of the project
2. Review the plans and specifications.
a. Go page by page through the plans to discuss the quantities and costs.
b. Review each section of the specifications.
c. Discuss how the estimator assumed the work would be performed (materials and methods).
d. Review others’ work performance.
e. Identify discrepancies and ambiguities in the bid documents.
f. Identify design discrepancies or issues.
g. Identify potential errors in the bid documents.
h. Discuss information collected during a site visit.
i. Discuss information collected during a pre-bid meeting.
j. Identify potential cost savings from changes to materials and methods.
k. Identify potential prefabrication or internal value engineering opportunities.
l. Discuss alternative routing of conduits.
m. Identify any temporary power and lighting requirements.
3. Review the cost estimate and bid price.
a. Review each bid line item and its cost.
b. Review overhead, profit and contingency funds.
c. Discuss wage rates.
d. Review the bid submission letter with clarifications and qualifications.
4. Review subcontractor/vendor pricing and qualifications.
a. Review subcontractors and suppliers scope of work and qualifications.
b. Identify all pre-contract commitments and promises.
c. Verify minority business requirements.
Project Number: _____________________________________________________________________________________
Project Name: _______________________________________________________________________________________
Location:____________________________________________________________________________________________
Estimator:___________________________________________________________________________________________
Project Manager:_____________________________________________________________________________________
Table 4.3: Turnover Meeting Agenda (page 16)
PRE-CONSTRUCTION PLANNING ACTIVITIES
47
Review Items:
5. Review the schedule and milestones.
a. Review the owner-furnished schedule.
b. Review any preliminary schedule submitted with the bid.
c. Review work by others that will impact the electrical work.
d. Identify important material and equipment delivery dates.
e. Discuss holidays, vacations and potential weather events.
6. Review manpower requirements and labor rates.
a. Review the manpower loading chart (if available).
b. Identify the estimated crew mix.
c. Identify any wage increases.
d. Review the potential for overtime.
7. Review other items specific to this project:
____________________________________________________________________________________________________
____________________________________________________________________________________________________
____________________________________________________________________________________________________
____________________________________________________________________________________________________
____________________________________________________________________________________________________
____________________________________________________________________________________________________
____________________________________________________________________________________________________
____________________________________________________________________________________________________
____________________________________________________________________________________________________
____________________________________________________________________________________________________
____________________________________________________________________________________________________
Project Number: ____________________________________________________________________________________
Table 4.3: Turnover Meeting Agenda (continued)
ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL
48
PRE-JOB PLANNING KICKOFF MEETING AGENDA
Agenda Items:
1. Project overview
a. Project name
b. Location
c. Type of work
d. Contract cost
e. General scope of work
f. Identify potential opportunities and challenges of the project
2. Introduce internal team members.
a. Project manager
b. Field supervisor/foreman
c. Estimator
d. Accounting representative
e. Other internal team members (i.e., CAD operator, purchasing agent, etc.)
3. Identify external team members.
a. Owner/customer
b. Architect/engineer
c. General contractor/construction manager
d. Other specialty subcontractors
e. Vendors/suppliers
4. Review the general scope of work.
a. Provide an overview of the project scope of work and the electrical scope.
b. Review major work performed by others.
5. Review the contract cost.
a. Review direct costs and the contract cost.
b. Review overhead, profit and contingency funds.
6. Review purchasing of materials, equipment and services from subcontractors/vendors.
a. Review subcontractors and suppliers scope of work and qualifications.
b. Identify all pre-contract commitments and promises.
c. Verify minority business requirements.
Project Number: _____________________________________________________________________________________
Project Name: _______________________________________________________________________________________
Location:____________________________________________________________________________________________
Estimator:___________________________________________________________________________________________
Project Manager:_____________________________________________________________________________________
Table 4.4: Pre-Job Planning Kickoff Meeting Agenda (page 17)
PRE-CONSTRUCTION PLANNING ACTIVITIES
49
Agenda Items:
7. Review the schedule and milestones.
a. Review the owner-furnished schedule.
b. Review any preliminary schedule submitted with the bid or construction schedule.
c. Review work by others that will impact the electrical work.
d. Identify important material and equipment delivery dates.
8. Review manpower requirements and labor rates.
a. Review the manpower loading chart (if available).
b. Identify the estimated crew mix.
c. Identify any wage increases.
9. Review the contract—identify any special clauses that require careful consideration.
10. Review administrative procedures.
a. Administrative setup
b. Request for Information (RFI) procedures and setup
c. Submittal process and setting up the submittal tracking system
d. Change order procedures and setting up the change management system
e. Field reporting requirements
f. Budget preparation and billing procedures
g. Cost control and setting up the tracking system
11. Review special safety issues.
12. Review site logistics and material storage and staging.
a. Site access
b. Parking
c. Material delivery and movement procedures
d. Material storage locations
e. Trailer locations (if applicable)
f. Site cleanup requirements
g. Temporary power and lighting requirements
13. Review bond, permit and certificate of insurance requirements
14. Review other items specific to this project:
______________________________________________________________________________________________
______________________________________________________________________________________________
______________________________________________________________________________________________
Project Number: ____________________________________________________________________________________
Table 4.4: Pre-Job Planning Kickoff Meeting Agenda (continued)
ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL
50
Project Number: _____________________________________________________________________________________
Project Name: _______________________________________________________________________________________
Location:____________________________________________________________________________________________
Estimator:___________________________________________________________________________________________
Bid Due Date: _______________________________________________________________________________________
SCOPE AND CONTRACT REVIEW CHECKLIST FOR PRE-CONSTRUCTION PLANNING
ACT.
COMPLETION ITEM
DATE NO.
SUB-ACTIVITIES
5. Review contract for unfavorable or high risk clauses (performance recommended).
II 1 Complete the Contract Review Checklist (Table 4.6).
II 2 Identify all required bonds, permits and certificates.
II 3 Review contractual billing requirements.
II 4 Review and understand procedures for requesting change orders.
II 5
Identify whether disputes must be resolved through alternative
dispute resolution, such as mediation or arbitration.
6. Project manager reviews plans, specifications and schedule.
II 1 Order extra sets of plans and specifications if necessary.
II 2 Complete the Scope and Schedule Review checklist (Table 4.7).
II 3
Compare the scope identified in the contract to the scope from the
bid submission to verify that they match.
II 4 Compare the plans to the specifications to identify any discrepancies.
II 5
Review the customer-furnished schedule to determine whether the
electrical work can be completed within the contractual timeframe.
7. Field supervisor reviews plans, specifications and schedule.
II 1 Complete the Scope and Schedule Review checklist (Table 4.7).
II 2 Review best field practices or lessons learned.
II 3
Identify value engineering and prefabrication opportunities (see
Activity 23).
II 4 Identify labor requirements and begin selecting foremen.
II 5 Identify special tools that will need to be purchased or assembled.
8. Create a list of issues that need to be resolved and begin the request for information (RFI) process.
II 1
Establish a request for information (RFI) process (see Activity 16)
and create a list of questions that require clarification.
II 2
Formalize the RFIs by assigning them a trackable number and
submitting them to the owner/CM/GC.
Table 4.5: Scope and Contract Review Checklist (page 17)
PRE-CONSTRUCTION PLANNING ACTIVITIES
51
9. Conduct a site visit (performance recommended).
II 1 Complete the Site Visit Checklist (Table 4.8).
II 2
Examine site access and layout, including parking, material delivery
points and material lay-down and storage.
II 3
Identify locations and availability of matieral and personnel lifts,
elevators, cranes, scaffolding and forklifts.
II 4 Create a plan for installing temporary power (when applicable).
II 5
Verify existing conditions and compare them to the conditions shown
on the plans and described in the specifications.
10. Compare estimated (bid) work activities and materials to planned performance.
II 1
Compare the estimator’s concept of how to perform the work to
typical field operations and document differences.
II 2 Discuss unclear methods or discrepancies with the estimator.
II 3
Determine the cost difference between the as-bid and planned
performance of the work.
11. Identify value engineering and prefabrication opportunities and how to simplify the work.
Review value engineering (VE) or prefabrication opportunities that
II 1 were identified in the turnover meeting between the estimator and
project manager.
II 2
Review procedures for formally requesting VE consideration if
required.
II 3 Search for and identify additional VE and prefabrication items.
II 4 Identify additional ways to simplify the work.
II 5 Price out the cost difference between the as-bid and VE options.
10. Compare estimated (bid) work activities and materials to planned performance.
II 1
Take off the materials, equipment and systems in the order they will
be constructed.
Code each plan sheet as you take it off so that you can return to it
II 2 later and immediately identify the quantity of various materials
shown on the sheet.
II 3
The final quantities should be identified by the units in which they
will be purchased.
II 4 All assumptions should be noted on the quantity takeoff sheets.
II 5 Be sure the quantities that are estimated include a waste factor.
II 6
Compare the construction takeoff to the bid takeoff to identify
significant differences or discrepancies.
Project Number: ____________________________________________________________________________________
Table 4.5: Scope and Contract Review Checklist (continued)
ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL
52
Project Number: _____________________________________________________________________________________
Project Name: _______________________________________________________________________________________
Location:____________________________________________________________________________________________
Project Manager:_____________________________________________________________________________________
Completed Date Completed ITEM
II Check for ambiguous clauses and seek clarification.
II Check for one-sided clauses that favor the other party.
II Cross-reference clauses to understand the whole meaning of clauses.
II Identify discrepancies and conflicting clauses and seek clarification.
II Check for agreement between plans and specifications, and seek clarification
if there is any discrepancy.
II Identify any “killer clauses” that assign full responsibility for everything to
the electrical contractor.
II Determine whether the contract clearly favors the other party (owner/CM/
GC), and seek more equitable contract terms.
II Review the Indemnification Clause, and ensure your insurance converage can
sufficiently cover the risk.
II Evaluate the Coordination Clause to determine each party’s responsibility to
coordinate the work.
II Determine your rights and responsibilities if the sequence of work is
changed or if out-of-sequence work impacts the project.
II Carefully review all time-sensitive clauses that cover commencement,
completion, milestones, accelerations, delays and progress.
II Review and understand your rights to receive damages if the schedule is
accelerated or delayed by other parties.
II Determine whether there is a no-damages-for-delay clause, and review your
rights and responsibilities.
II Review and understand the clause that describes waivers.
II Review the concealed conditions clause, and identify the circumstances
that will entitle you to compensation.
II Review the Force Majeure clause, and identify the circumstances that will
entitle you to a time extension.
II Evaluate clauses that identify procedures for seeking change orders.
II Evaluate clauses that identify the compensation for extra work.
II Identify payment provisions, especially a “pay when paid” clause and a
“pay if paid” clause.
Table 4.6: Contract Review Items1
(page 17)
1
Detailed contract review guidelines can be found in ELECTRI International (2000) Fundamentals of Contract Risk Management for
Electrical Contractors.
PRE-CONSTRUCTION PLANNING ACTIVITIES
53
SCOPE AND SCHEDULE REVIEW ITEMS
Completed Completed By Date Completed Item
II Contract
II Plans
II Specifications
II Cost estimate and bid breakdown
II Referenced/applicable codes or regulations
II Quality requirements
II Safety requirements
II Special conditions
II Addendums
II Temporary power and lighting requirements
II Owner/CM/GC-furnished materials
II Vendor pricing and qualifications
II Owner/CM/GC schedule
II Internal schedule submitted with bid
II Work sequence and work by others
II Required coordination with other trades
II Material and equipment deliveries
II Anticipated weather problems or holidays
II Required labor
II Labor rates and potential increases
II Crew mix
II Administrative procedures (submittals/RFIs/changes)
II Other:
II Other:
II Other:
Project Number: _____________________________________________________________________________________
Project Name: _______________________________________________________________________________________
Location:____________________________________________________________________________________________
Estimator:___________________________________________________________________________________________
Project Manager:_____________________________________________________________________________________
Table 4.7: Scope and Schedule Review Items (pages 18, 39)
ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL
54
Project Number: ____________________________________________________________________________________
Table 4.7: Scope and Schedule Review Items (continued)
SCOPE AND SCHEDULE REVIEW ITEMS
Completed Who furnishes? Who installs? What to review in the Plans and Specifications
II Access doors
II Asbestos abatement
II Carpentry (miscellaneous)
II Clean up
II Conduit (sizes and quantities)
II Crane
II Cutting and patching
II Demolition and removal
II Electric motors
II Electric starters
II Excavation and backfill
II Fire alarm wiring
II Fire alarm devices
II Hand dryers
II Hoists for personnel
II Hoists for materials
II Interior layout
II Painting
II Panels
II Scaffolding
II Site access
II Site surveying
II Temporary power
II Underground utilities
II Wire (and/or pipe and wire)
II Other:
II Other:
II Other:
PRE-CONSTRUCTION PLANNING ACTIVITIES
55
SITE VISIT REVIEW ITEMS
Completed Item to Review Notes
II Access into and out of the site
II Circulation throughout the site
II Material and equipment delivery routes
II Material storage and staging locations
II Office trailer or office space
II Temporary power and lighting locations
II Existing underground utilities location
II Existing above ground utility locations
II Location of existing interior systems
II Progress of the demolition
II Progress of the site work
II Progress of the site layout/surveying
II Asbestos abatement has been completed
II Work completed to date
II Presence/location of the crane
II Presence/location of the personnel lift
II Presence/location of the materials lift
II Potential coordination with others
II Anticipated weather problems
II Housekeeping conditions
II Special site considerations
II Safety issues or concerns
II Other:
II Other:
II Other:
Project Number: _____________________________________________________________________________________
Project Name: _______________________________________________________________________________________
Location:____________________________________________________________________________________________
Project Manager:_____________________________________________________________________________________
Scope Review Completion Date: _______________________________________________________________________
Table 4.8: Site Visit Checklist (page 19)
ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL
56
Project Number: _____________________________________________________________________________________
Project Name: _______________________________________________________________________________________
Location:____________________________________________________________________________________________
Project Manager:_____________________________________________________________________________________
Start Date: __________________________________________________________________________________________
ADMINISTRATIVE SETUP CHECKLIST FOR PRE-CONSTRUCTION PLANNING
ACT.
COMPLETION ITEM
DATE NO.
SUB-ACTIVITIES
13. Set up project files and create contact list.
II 1 Use the File System Checklist (Table 4.11) to creat paper files.
II 2
Create a contact sheet that lists all team members and their
company contact information.
14. Set up computerized tracking and control system (forms, database, schedule and tracking).
II 1
Verify the accounting department has assigned a project number and
entered intial information in the cost control center.
II 2 Use the File System Checklist (Table 4.11) to creat computer files.
II 3
If a separate project management software system is used, set up
the project in the system.
II 4
If a separate project management software system is used, set up
the project in the system.
15. Initiate a change management system.
II 1
Review the contract to identify required change order, field change,
and time-and-materials procedures.
II 2
Review your company’s standard procedures for initiating,
requesting, and processing change orders and field changes.
Develop a log with sequential numbering to track all changes,
II 3 including change orders, field changes and time-and-materials
requests (Table 4.12).
16. Initiate a request for information (RFI) tracking and processing system.
II 1
Develop a log with sequential numbering to track all requests for
information (RFIs) (Table 4.13).
II 2
Determine whether RFIs will be submitted by e-mail, fax or postal
mail.
II 3
Review your company’s standard procedures for processing RFIs, and
use a company standard form for submitting RFIs.
II 4 Ensure each RFI also identifies a proposed solution.
Table 4.9: Administrative Setup Checklist (page 21)
PRE-CONSTRUCTION PLANNING ACTIVITIES
57
17. Initiate a submittal tracking and processing system.
II 1
Develop a log with sequential numbering to track all submittals,
including those of vendors and subcontractors (Table 4.14).
II 2
Review your company’s standard procedures for processing
submittals, and use a company standard form for submissions.
Verify that each submittal processing form identifies a respond-no-
II 3 later-than date, which is associated with timely ordering and delivery
of materials and equipment.
18. Develop a “Labor Requirements/Expectation” letter (for background check, etc.) (performance
recommended)
II For projects that have special requirements such as drug testing,
1
background check or special safety training, develop an
“expectations” letter that must be reviewed and signed by crew
members (see Figure 4.8).
For projects that will require hiring workers from the union hall,
II 2 develop an “expectations” letter that must be reviewed and signed
by crew members.
Project Number: ____________________________________________________________________________________
Table 4.9: Administrative Setup Checklist (continued)
ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL
58
Project Number: _____________________________________________________________________________________
Project Name: _______________________________________________________________________________________
Location:____________________________________________________________________________________________
Project Manager:_____________________________________________________________________________________
Table 4.10: File System Checklist (page 21)
SCOPE AND SCHEDULE REVIEW ITEMS
Completed File Number File Description
II Project Information and Contacts
II Cost Estimate and Bid Submission
II Contract Agreement
II Contract Documents
II Budget and Pay Requests
II Purchase Orders
II Subcontracts
II Materials Folder (Fixtures, Switchgear, Fire Alarm, Low Voltage)
II Requests for Information
II Submittals
II Change Orders—Pending
II Change Orders—Approved
II Correspondence
II Meeting Minutes
II Daily/Weekly Field Report
II Progress Reports
II Other:
II Other:
II Other:
PRE-CONSTRUCTION PLANNING ACTIVITIES
59
COMPANY NAME
COMPANY ADDRESS
CHANGE ORDER PROPOSAL
PROJECT NUMBER: ______________________________
PROJECT NAME: ____________________________________________________________________________________
DATE: ___________________________
TO:_____________________________________________ FROM: ___________________________________________
________________________________________________ _________________________________________________
________________________________________________ _________________________________________________
________________________________________________ _________________________________________________
DESCRIPTION OF CHANGED WORK:
COST OF THE CHANGED WORK:
Description Labor Materials Equipment Other Subcontracts Total
____________________________________________________________________________________________________
____________________________________________________________________________________________________
____________________________________________________________________________________________________
____________________________________________________________________________________________________
Labor Burden ___________%
Bond Premium __________%
Liability Insurance ________%
Subtotal ___________________________________________
Overhead ________________
Profit ____________________
TOTAL _____________________________________________
TIME EXTENSION ______________ calendar days
APPROVED BY: _________________________________________________________DATE: ________________________
Figure 4.2: Change Order Proposal (pages 22, 39)
ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL
60
PROJECT NUMBER: _____________________________________________________________________________________________
PROJECT NAME: _______________________________________________________________________________________________
FIELD SUPERVISOR: ____________________________________________________________________________________________
WORK PERFORMED BY (EMPLOYEE NAME): _____________________________________________________________________
DATE: _________________________________________________________________________________________________________
WORK AUTHORIZED BY: _______________________________________________________________________________________
TITLE: _________________________________________________________________________________________________________
FIELD CHANGE FORM
SCOPE OF WORK:
LABOR: EQUIPMENT/TOOLS:
EMPLOYEE
HOURS WAGE
TOTAL EQUIPMENT/TOOL TYPE COST
REG OT DT RATE
SUBTOTAL SUBTOTAL
_______ % MARKUP _______ % MARKUP
TOTAL TOTAL
MATERIALS: SUBCONTRACTORS:
MATERIAL TYPE UNITS QTY
UNIT
TOTAL COMPANY NAME COST
COST
SUBTOTAL
_______ % MARKUP
TOTAL
SUMMARY OF COSTS:
TOTAL LABOR
TOTAL MATERIALS
SUBTOTAL TOTAL EQUIPMENT/TOOLS
______ % MARKUP TOTAL SUBCONTRACTS
TOTAL TOTAL COST
Figure 4.3: Field Change Form (page 22)
PRE-CONSTRUCTION PLANNING ACTIVITIES
61
Table 4.11: Change Order Log (page 22)
ProjectNumber:___________________________________________________________________________________________________________________
ProjectName:____________________________________________________________________________________________________________________
Location:__________________________________________________________________________________________________________________________
ProjectManager:__________________________________________________________________________________________________________________
CHANGEORDERLOG
C.O.DATEWHOWHOASSOCIATEDC.O.
NUMBERSUBMITTED
DESCRIPTIONOFCHANGE
INITIATEDAUTHORIZEDRFINUMBERAMOUNT
STATUS
ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL
62
Table 4.12: Request for Information Log (pages 22, 41)
ProjectNumber:___________________________________________________________________________________________________________________
ProjectName:____________________________________________________________________________________________________________________
Location:__________________________________________________________________________________________________________________________
ProjectManager:__________________________________________________________________________________________________________________
REQUESTFORINFORMATIONLOG
RFIDATESUBMITTEDDATEOFWHO
NUMBERSUBMITTED
DESCRIPTIONOFINFORMATIONNEEDED
TORESPONSEINITIATED
STATUS
PRE-CONSTRUCTION PLANNING ACTIVITIES
63
COMPANY NAME
COMPANY ADDRESS
REQUEST FOR INFORMATION
PROJECT NUMBER: PROJECT NAME: DATE:
RFI NUMBER:
TO: FROM:
METHOD SENT: II FAX II MAIL II E-MAIL
DESCRIPTION OF REQUEST:
ADDITIONAL SUPPORT DOCUMENTS: II ARE II ARE NOT ATTACHED.
DATE REQUIRED:
DATE RESPONSE RECEIVED:
RESPONSE FROM:
RESPONSE:
Figure 4.5: Request for Information Form (pages 22, 38)
PRE-CONSTRUCTION PLANNING ACTIVITIES
64
Table 4.13: Submittal Log (pages 24, 28, 38, 39)
ProjectNumber:___________________________________________________________________________________________________________________
ProjectName:____________________________________________________________________________________________________________________
Location:__________________________________________________________________________________________________________________________
ProjectManager:__________________________________________________________________________________________________________________
SUBMITTALLOG
CSIDATEREVISIONDATETODATEDATETOORDERDELIVERY
SECTIONSUBMITTEDNUMBER
SUBMITTEDITEMSUPPLIER
ARCH/ENGAPPROVEDSUPPLIERDATEDATE
PRE-CONSTRUCTION PLANNING ACTIVITIES
65
COMPANY NAME
COMPANY ADDRESS
SUBMITTAL TRANSMITTAL FORM
PROJECT NUMBER: ______________________________ DATE:___________________________________________
PROJECT NAME: ____________________________________________________________________________________
CSI SECTION: ___________________________
TO: FROM:
FOR FOR FOR
SUBMITTAL YOUR FOR YOUR YOUR INFORMATION DATE
QTY DESCRIPTION REVIEW APPROVAL FILES ONLY REQ’D
Please return __________ copies.
Additional Comments:________________________________________________________________________________
____________________________________________________________________________________________________
____________________________________________________________________________________________________
____________________________________________________________________________________________________
Signature: ______________________________________________________________Date: _________________________
Figure 4.7: Submittal Transmittal Form (pages 25, 39)
ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL
66
COMPANY NAME
COMPANY ADDRESS
COMPANY PHONE NUMBER
NAME OF NEW EMPLOYEE: __________________________________________________________________________
PROJECT NUMBER: _________________________________________________________________________________
PROJECT NAME: ____________________________________________________________________________________
DATE OF EMPLOYMENT: ____________________________________________________________________________
TODAY’S DATE: _____________________________________________________________________________________
SUBJECT: Requirements and Expectations of Personnel Employed on Project Number _______________________
The purpose of this letter is to notify you of special requirements and expectations of all personnel who will
work on Project Number ____________________, entitled __________________________________. The following
requirements and expectations must be met as a necessary condition of employment:
1. This project requires weekly random drug testing, which will be conducted by a private company employed by
the customer. Any employee who fails a drug test or refuses to submit to a random drug test will be immediate-
ly dismissed from employment.
2. This project requires a complete background check and the use of a security badge at all times. Employees
who fail to exhibit their security badge or who arrive at the jobsite without their badge will be removed from the
premises immediately.
3. Entry into certain parts of the facility will require an escort appointed by the customer. Requests for escorts
must be submitted 24 hours in advance.
4. The work hours for this project are Monday through Friday from 7:00 AM to 3:00 PM.
5. No privately owned vehicles or company vehicles will be permitted into the secure work area. All employees
must arrive at the security gate each morning no later than 6:45 AM to board a bus that will take employees to
the secure work area. All employees must be at the pickup point each afternoon at 3:15 PM to board the bus and
be escorted out of the secure area. Late employees will not be permitted into the secure area.
6. Employees may be monitored by closed-circuit television throughout the day.
7. Smoking will not be permitted inside the secure work area.
Please acknowledge your acceptance of the requirements and expectations of this project by signing and dating
below.
I understand and accept the above terms of employment.
______________________________________________________________________ __________________________
NAME DATE
______________________________________________________________________ __________________________
WITNESS DATE
Figure 4.8: Requirements and Expectations Letter (page 25)
PRE-CONSTRUCTION PLANNING ACTIVITIES
67
Project Number: _____________________________________________________________________________________
Project Name: _______________________________________________________________________________________
Location:____________________________________________________________________________________________
Project Manager:_____________________________________________________________________________________
Start Date: __________________________________________________________________________________________
BUYOUT PROCESS CHECKLIST FOR PRE-CONSTRUCTION PLANNING
ACT.
COMPLETION ITEM
DATE NO.
SUB-ACTIVITIES
19. Request and/or review subcontractor/supplier/vendor prices and qualifications.
II 1
Request subcontractor/supplier/vendor pricing if it was not
requested or received during the bidding stage.
II 2
Compare actual subcontractor/supplier/vendor scope of work with the
scope identified in the subcontractor/supplier/vendor bid submission.
II 3 Evaluate the subcontractor/supplier/vendor qualifications.
II 4
Compare priding and qualifications among the subcontractors/
suppliers/vendors.
20. Negotiate pricing and contract conditions and select subcontractors/suppliers/vendors.
II 1
Discuss potential cost savings with potential subcontractors/
suppliers/vendors.
II 2
Review the contract or purchase order terms and conditions with
potential subcontractors/suppliers/vendors prior to award.
II 3
Select all successful subcontractors/suppliers/vendors, and issue a
letter of intent (if necessary).
21. Develop and issue purchase orders and contracts for materials and equipment.
II 1
Develop the purchase orders or contracts for subcontractors/
suppliers/vendors.
II 2 Process and issue the purchase orders or subcontracts.
22. Order long-lead-time materials and equipment.
II 1
Compare the sequence, schedule and materials/equipment to
identify long-lead-time items.
Negotiate and issue purchase orders and subcontracts for long-lead
II 2 time items before negotiating standard purchase orders and
subcontracts.
II 3
Issue a letter of intent or purchase order immediately to release
long-lead-time items for order and delivery.
Table 4.14: Buyout Process Checklist (page 26)
ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL
68
Project Number: ____________________________________________________________________________________
Table 4.14: Buyout Process Checklist (continued)
23. Request submittals, cut sheets and shop drawings.
Upon issuing the contract document, the subcontractor/supplier/
II 1 vendor should be requested to assemble and submit samples, cut
sheets or shop drawings.
II 2
Identify a deadline by which the submittals, cut sheets, and shop
drawings must be submitted to the electrical contractor.
24. Develop and process log and book of submittals, cut sheets and shop drawings.
Develop a log, with sequential numbering, to track all submittals,
II 1 including those of vendors and subcontractors (see also Activity 17
and Table 4.13).
II 2 Assemble two or more binders of all draft and approved submittals.
II 3 Submit and track required submittal items.
PRE-CONSTRUCTION PLANNING ACTIVITIES
69
Table 4.15: Subcontractor/Supplier/Vendor Comparison Spreadsheet (page 26)
ProjectNumber:___________________________________________________________________________________________________________________
ProjectName:____________________________________________________________________________________________________________________
Location:__________________________________________________________________________________________________________________________
ProjectManager:__________________________________________________________________________________________________________________
SUBCONTRACTOR/SUPPLIER/VENDORBIDANALYSIS
ITEMTYPE___________________________________________VENDORS
REVIEWITEMS:BUDGETVENDORAVENDORBVENDORCVENDORD
Wastheitembidperplansandspecs?[Yes/No]
Wastheitembidperthescopeofwork?[Yes/No]
Aretheworkersunionornon-union?
Howlongwillittaketoorderanddelivertheitem?
Listanyexclusions.
Wastaxincludedinthebidprice?[Yes/No]
Didthevendoracknowledgealladdenda?[Yes/No]
Basebidprice
Listanyalternatepricingprovided.
Listadjustedbidpriceifalternatesaccepted.
ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL
70
COMPANY NAME
COMPANY ADDRESS
COMPANY PHONE NUMBER
Subcontractor Representative
Subcontractor Company Name
Subcontractor Company Address
Subcontractor Phone Number
DATE: December 1, 2005
SUBJECT: Letter of Intent to Award a Contract
Dear Subcontractor Representative:
You have been selected as the successful bidder on Project Number _______________________, entitled
_________________________________________________________. Per our telephone conversation, we are in the
process of developing a contract for the scope of work identified in your bid submission. The contract amount
will be $1,000,000.
This purpose of this letter is to notify you of our intent to award a contract. You can expect to receive the con-
tract no later than _____________, 20____. You are authorized to proceed with the work identified in your bid
submission.
Please feel free to contact me at (222) 110-0000.
Sincerely,
Electrical Contractor Company Officer
Title
Figure 4.9: Letter of Intent (page 27)
PRE-CONSTRUCTION PLANNING ACTIVITIES
71
COMPANY NAME
COMPANY ADDRESS
PURCHASE ORDER FORM
DATE:
P.O. NUMBER:
PROJECT NUMBER:
PROJECT NAME:
TO:
SHIP TO: (Home office or jobsite address) SHIP VIA (jobsite) F.O.B.
REQUIRED SHIP DATE:
QUANTITY DESCRIPTION OF ITEM(S) COST
NOTE: MATERIAL SAFETY DATA SHEETS ARE REQUIRED WITH ALL SHIPMENTS
SHIPPING INSTRUCTIONS:
ADDITIONAL REQUIREMENTS:
1. Submit _____ copies of shop drawings/details/performance data for review/approval
2. Submit _____ copies of OandM manuals or _____ copies of wiring diagrams for review/approval
NAME: _________________________________________ NAME:____________________________________________
SIGNATURE: ____________________________________ SIGNATURE: _______________________________________
DATE: __________________________________________ DATE:_____________________________________________
Figure 4.10: Purchase Order Form (page 27)
ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL
72
Project Number: _____________________________________________________________________________________
Project Name: _______________________________________________________________________________________
Location:____________________________________________________________________________________________
Project Manager:_____________________________________________________________________________________
Start Date: __________________________________________________________________________________________
MATERIAL HANDLING PROCESS CHECKLIST FOR PRE-CONSTRUCTION PLANNING
ACT.
COMPLETION ITEM
DATE NO.
SUB-ACTIVITIES
25. Develop material delivery and handling plan.
II 1
Review the “Material Delivery/Storage and Site Logistics Best
Practices” (see Table 4.18).
II 2 Establish and maintain a file of delivery receipts and packing slips.
II 3 Establish a material and equipment delivery and storage log
II 4 Create a material and equipment delivery schedule.
II 5
Establish standard procedures for receiving, handling and storage of
materials and equipment.
26. Develop material storage and staging plan.
II 1 Complete the site logistics review checklist (Table 4.20).
II 2
Review the “Material Delivery/Storage and Site Logistics Best
Practices” (see Table 4.18).
II 3
Develop a storage site layout that identifies where the materials and
equipment are stored.
Table 4.16: Material Handling Planning Process Checklist (page 29)
PRE-CONSTRUCTION PLANNING ACTIVITIES
73
Project Number: _____________________________________________________________________________________
Project Name: _______________________________________________________________________________________
Location:____________________________________________________________________________________________
Project Manager:_____________________________________________________________________________________
Table 4.17: Material Delivery/Storage and Site Logistics Best Practices (page 29)
MATERIAL DELIVERY/STORAGE AND SITE LOGISTICS BEST PRACTICES
Best Practice
BEST PRACTICE DESCRIPTION
Number
1 Assign one person the responsibility of managing material and equipment delivery, handling
storage and staging.
2 Establish a standard unloading crew that consists of laborers or apprentices.
3 Establish standard procedures for receiving, handling and storing materials, and strictly enforce
the standard.
4 Develop a storage site layout that identifies where the materials and equipment are stored, and
annotate the location on the material and equipment delivery and storage log.
5 Develop a storage site identification system that provides a method to document and track the
location of all materials that have been delivered to the jobsite.
6 Establish storage space for each major material item or group (pipe, wire, boxes, etc.).
7 Sort and store the materials as soon as it is delivered to the site.
8 Allow storage space for waste or excess materials, and remove them as soon as possible.
9 Ensure the material and equipment is adequately secured and protected from the elements.
10 Make sure the materials manager is notified of pending deliveries.
11 Return all damaged, excess or incorrect materials to the vendor immediately in order to keep
the site free from clutter.
12 Arrange to have materials delivered just before you need them so that storage and handling is
kept to a minimum.
13 If materials are ordered in bulk, ask the vendor to store the materials at their office until you
need them on the jobsite (also consider paying extra for this option).
14 Consider using a material consignment trailer, where the vendor inventories the trailer each
week, restocks it and only charges you for the materials you use.
15 Try to place materials/equipment at the location where they will be used to improve access to
the materials/equipment and minimize handling.
16 Arrange to have materials packaged for efficient unloading, handling and installation.
17 Determine ahead of time what equipment will be needed to unload and handle material
deliveries.
18 Evaluate the capacity of material lifts, freight elevators and cranes to ensure they can safely
move the materials and equipment.
19 Locate your toilet facilities as close to the work areas as possible.
20 Locate your break facilities and trash containers as close to the work areas as possible.
21 Develop a map of facility locations, and distribute it to workers and suppliers/vendors.
ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL
74
Table 4.18: Material and Equipment Delivery and Storage Log (page 25)
ProjectNumber:___________________________________________________________________________________________________________________
ProjectName:____________________________________________________________________________________________________________________
Location:__________________________________________________________________________________________________________________________
ProjectManager:__________________________________________________________________________________________________________________
MATERIALANDEQUIPMENTDELIVERYANDSTORAGELOG
DATEP.O.RECEIVEDSTORAGEDAMAGED
RECEIVEDNUMBER
DESCRIPTIONOFITEMRECEIVEDQUANTITY
BYLOCATIONITEMS
NOTES
PRE-CONSTRUCTION PLANNING ACTIVITIES
75
Project Number: _____________________________________________________________________________________
Project Name: _______________________________________________________________________________________
Location:____________________________________________________________________________________________
Project Manager:_____________________________________________________________________________________
Table 4.19: Site Logistics Review Items (page 29)
SITE LOGISTICS REVIEW CHECKLIST
Completed Date Completed ITEM
II Review the site layout, and identify placement of materials and facilities
to maximize productivity.
II Identify site entry and exit points, and plan possible vehicle circulation.
II Identify procedures for receiving materials and authorized personnel.
II Identify material storage locations.
II Determine and document equipment that will be needed to unload and
move materials (cranes, fork lift, pallet jacks, etc.).
II Evaluate material lifts, freight elevators and cranes to determine whether
they can support the size and weight of the material items.
II Determine and order special tools associated with material handling
(box cutters, bar code readers, computers, etc.).
II Establish a “receiving crew” that consists of laborers or apprentices who
will unload trucks and move materials.
II Select a worker to be in charge of material handling, including inspection
and inventory of delivered items.
II Establish standard procedures for receiving, logging, handling and stor-
ing materials and equipment on the jobsite or at an offsite location.
II Establish delivery dates for all materials and develop a schedule of
deliveries.
II Evaluate purchasing options to ensure materials are ordered to promote
efficient unloading, storage and installation.
II Evaluate the benefits and pitfalls of prefabrication in terms of delivery,
storage, handling and installation.
II Review the material delivery, handling, storage and staging best prac-
tices (see Table 4.18).
ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL
76
Project Number: _____________________________________________________________________________________
Project Name: _______________________________________________________________________________________
Location:____________________________________________________________________________________________
Project Manager:_____________________________________________________________________________________
Start Date: __________________________________________________________________________________________
BUDGET PREPARATION CHECKLIST FOR PRE-CONSTRUCTION PLANNING
ACT.
COMPLETION ITEM
DATE NO.
SUB-ACTIVITIES
27. Develop, review or expand the cost code scheme.
II 1
Decide whether to use a cost code scheme based upon 16
specifications divisions or 48 specifications divisions.
II 2
Review the cost estimate to identify the existing cost code
breakdown, and decide whether additional breakdown is necessary.
Review the company standard list of cost codes (or use Table 4.21),
II 3 and decide which codes will be needed for breaking down the work
for tracking and billing.
II 4 Add new codes for work items that are not on the standard list.
II 5
Assign additional codes to specify the costs associated with material,
equipment, labor, subcontractors and other miscellaneous costs.
28. Develop budget by breaking down labor, material, overhead and profit costs.
II 1
Create the budget in concert with the labor and materials tracking
report.
Establish a budget with sufficient line items to identify potential
II 2 problems yet enough simplicity to avoid complex, time-consuming
data entry.
II 3
Verify that labor and materials can and will be reported according to
the budget line items.
29. Develop schedule of values
II 1
Review the contract to identify the contractual format and process
for developing a schedule of values.
II 2 Create the schedule of values in concert with the billing process.
II 3
Consider “rolling up” the budget so that the schedule of values has
the same summary line items but fewer sub-line items.
Table 4.20: Budget Preparation Checklist (page 30)
PRE-CONSTRUCTION PLANNING ACTIVITIES
DIVISION DESCRIPTION
01000 General Requirements/Conditions
01500 Temporary Facilities and Controls
01510 Temporary Utilities
01700 Execution and Closeout Requirements
01710 Mobilization
01730 Cutting and Patching
01740 Cleaning and Waste Management
01780 Closeout Submittals
02200 Site Preparation
02220 Demolition
02500 Utility Services
02580 Electrical and Communications Structures
03400 Precast Concrete
03480 Precast Concrete Specialties
05400 Cold-Formed Metal Framing
05450 Electrical Support Assemblies
10400 Identification Devices
10440 Illuminated Interior Signage
11060 Theater and Stage Equipment
11060 Stage Lighting and Controls
11060 Controls for Theater & Stage Equipment
11130 Audio-Visual Equipment
13100 Lightning Protection Conductors
13110 Cathodic Protection Conductors
13700 Security Access and Surveillance
13800 Building Automation and Control
13850 Detection and Alarms
15900 HVAC Instrumentation and Control
16050 Basic Electrical Materials and Methods
16060 Grounding and Bonding
16070 Hangers and Supports
16075 Electrical Identification
16080 Electrical Testing
16090 Restoration and Repair
16100 Wiring Methods
16120 Conductors and Cables
16130 Raceway and Boxes
16140 Wiring Devices
16150 Wiring Connections
16200 Electrical Power
16210 Electrical Utility Services
16220 Motors and Generators
16230 Generator Assemblies
16240 Battery Equipment
16260 Static Power Converters
16270 Transformers
16280 Power Filters and Conditioners
DIVISION DESCRIPTION
16300 Transmission And Distribution
16310 Transmission and Distribution
Accessories
16320 High-Voltage Switching and Protection
16330 Medium-Voltage Switching and Protection
16340 Medium-Voltage Switching and
Protection Assemblies
16360 Unit Substations
16400 Low-Voltage Distribution
16410 Enclosed Switches and Circuit Breakers
16420 Enclosed Controllers
16430 Low-Voltage Switchgear
16440 Switchboards, Panelboards, and
Control Centers
16450 Enclosed Bus Assemblies
16460 Low-Voltage Transformers
16470 Power Distribution Units
16490 Components and Accessories
16500 Lighting
16510 Interior Luminaires
16520 Exterior Luminaires
16530 Emergency Lighting
16540 Classified Location Lighting
16550 Special-Purpose Lighting
16560 Signal Lighting
16570 Dimming Control
16580 Lighting Accessories
16590 Lighting Restoration and Repair
16700 Communications
16710 Communications Circuits
16720 Telephone and Intercommunication
Equipment
16740 Communication and Data Processing
Equipment
16770 Cable Transmission and Reception
Equipment
16780 Broadcast Transmission and Reception
Equipment
16790 Microwave Transmission and Reception
Equipment
16800 Sound and Video
16810 Sound and Video Circuits
16820 Sound Reinforcement
16830 Broadcast Studio Audio Equipment
16840 Broadcast Studio Video Equipment
16850 Television Equipment
16880 Multimedia Equipment
77
Table 4.21: Cost Code Scheme Based on Masterformat™
1995 (16 Divisions) (page 30)
ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL
78
ProjectNumber:___________________________________________________________________________________________________________________
ProjectName:____________________________________________________________________________________________________________________
Location:__________________________________________________________________________________________________________________________
ProjectManager:__________________________________________________________________________________________________________________
CHANGEORDERLOG
CSIOH&P
DIVISION
DESCRIPTIONLABORMATERIALSEQUIPMENTSUBCONTRACTS
(15%)
TOTAL
Table 4.22: Budget Breakdown and Tracking Spreadsheet (pages 30, 36, 40)
PRE-CONSTRUCTION PLANNING ACTIVITIES
79
ProjectNumber:___________________________________________________________________________________________________________________
ProjectName:____________________________________________________________________________________________________________________
Location:__________________________________________________________________________________________________________________________
ProjectManager:__________________________________________________________________________________________________________________
SCHEDULEOFVALUES
(A)(C)(D)(E)(F)=(D+E)(G)=(F/C)(H)=(C-F)
LINE
(B)
CONTRACTPREVIOUSLYCOMPLETEDCOMPLETED%BALANCE
(I)
ITEM
DESCRIPTION
VALUECOMPLETEDTHISPERIODTODATECOMPLETETOFINISH
RETAINAGE
Table 4.23: Company Schedule of Values (pages 31, 40)
ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL
80
Project Number: _____________________________________________________________________________________
Project Name: _______________________________________________________________________________________
Location:____________________________________________________________________________________________
Project Manager:_____________________________________________________________________________________
Start Date: __________________________________________________________________________________________
LAYOUT AND SEQUENCING CHECKLIST FOR PRE-CONSTRUCTION PLANNING
ACT.
COMPLETION ITEM
DATE NO.
SUB-ACTIVITIES
30. Develop installation sequence and layout drawings.
II 1 Organize the project by areas, floors or systems
II 2
Allocate sufficient time to mentally think through the sequencing of all
work processes from start through completion.
II 3
Determine whether to create sequence and layout drawings by hand
(marked-up drawings) or by creating new CAD drawings.
Create daily installation drawings at least one day prior to the date
II 4 when the work needs to be performed so that the drawings can be
distributed each morning to foremen and field crews.
II 5
Review the sequence daily or weekly to ensure the project is
progressing as expected.
31. Develop field instructions, including panel, pull or conduit schedules.
Review the sequence and installation process to identify any
II 1 additional information that might minimize questions and improve
productivity.
Create the panel, pull or conduit schedules in conjunction with the
II 2 installation drawings so that they can be distributed as a package to
the foremen or field crews.
II 3
When repetitive work is scheduled on a project, develop field
instructions and drawings
32. Develop prefabrication drawings for field use (when applicable).
For systems that are partially or completely prefabricated in a
II 1 prefabrication shop, develop drawings that show how the
prefabricated parts should be assembled and installed in the field.
For systems prefabricated in a shop, ensure the prefabricated parts
II 2 are clearly labeled and that these labels correspond to an assembly
and installation scheme identified on the drawings.
If on-site prefabrication is scheduled, the drawings should identify
II 3 the step-by-step process of how each piece is assembled into the
prefabricated system.
II 4
If on-site prefabrication is scheduled, separate drawings should also
be created to identify how the prefabricated parts should be installed.
II 5
Distribute the prefabrication drawings to the foremen or field crews
that will perform the work.
Table 4.24: Layout and Sequencing Planning Checklist (page 32)
PRE-CONSTRUCTION PLANNING ACTIVITIES
81
Project Number: _____________________________________________________________________________________
Project Name: _______________________________________________________________________________________
Location:____________________________________________________________________________________________
Project Manager:_____________________________________________________________________________________
Start Date: __________________________________________________________________________________________
SCHEDULE DEVELOPMENT CHECKLIST FOR PRE-CONSTRUCTION PLANNING
ACT.
COMPLETION ITEM
DATE NO.
SUB-ACTIVITIES
33. Review customer’s (general contractor’s) schedule and timeline.
II 1
Complete the “Customer’s Schedule Review Items” checklist (see
Table 4.26)
II 2
Initiate or attend a customer schedule review meeting to identify any
special requirements and clarify any questions.
34. Identify work that impacts electrical activities.
II 1
While reviewing the overall construction schedule, annotate work
that must be coordinated with other trades.
II 2
While reviewing the overall construction schedule, annotate potential
conflicts that will require coordination.
II 3
Develop and submit RFIs to resolve open questions about equipment
wiring or conflicts among systems.
Request an initial (and a recurring) coordination meeting to identify
II 4 and resolve schedule questions and conflicts before installation
begins..
35. Review the work sequence and long-lead-time material/equipment delivery dates.
II 1
Develop a rough draft of the electrical schedule from the sequence
and installation plan.
II 2
Verify the ordering and delivery dates of long-lead-time materials
and equipment.
Perform a three-way coordination between the sequencing/
II 3 installation plan, material/equipment delivery plan and the draft
draft electrical schedule.
II 4
Modify the draft schedule and sequencing/installation plan to
accommodate long-lead-time deliveries.
Table 4.25: Schedule Development Planning Checklist (page 34)
ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL
82
Project Number: ____________________________________________________________________________________
Table 4.25: Schedule Development Planning Checklist (continued)
36. Coordinate electrical schedule with the customer’s schedule.
After coordinating the sequencing/installation plan, material/equip-
II 1 ment delivery plan and the draft electrical schedule, coordinate the
draft schedule with the customer’s schedule and adjust as necessary.
Review the final electrical schedule with the customer, general
II 2 contractor, other trade contractors and suppliers to resolve any final
conflicts.
II 3
Seek approval of the schedule from the customer and general
contractor.
II 4
Seek integration of the electrical schedule into the customer/general
contractor’s overall project schedule.
24. Develop and process log and book of submittals, cut sheets and shop drawings.
In addition to the integration of the electrical schedule into the overall
II 1 schedule, format the final electrical schedule into an independent bar
chart for tracking and control.
II 2 Select the type of bar chart to develop and track.
II 3
Save the original approved schedule as the baseline so that progress
can be tracked and delays can be documented.
II 4
Distribute the electrical bar chart schedule to the customer, general
contractor, various subcontractors and suppliers.
PRE-CONSTRUCTION PLANNING ACTIVITIES
83
Project Number: _____________________________________________________________________________________
Project Name: _______________________________________________________________________________________
Location:____________________________________________________________________________________________
Project Manager:_____________________________________________________________________________________
Table 4.26: Customer’s Schedule Review Items (pages 34, 41)
CUSTOMER’S SCHEDULE REVIEW CHECKLIST
Completed Item to Review Annotations
II Identify the overall project start date:
II Identify the electrical work start date:
II Identify the overall project completion date:
II Identify the electrical work completion date:
II List any interim milestones:
II Is the project divided into phases? II Yes II No
II Identify the start and completion dates for each phase (if applicable):
II Does the contract include a liquidated damages clause? II Yes II No
II Does the contract include an incentive for early completion? II Yes II No
II Can the electrical work be completed in the timeframe identified in
the contract documents? II Yes II No
II If the schedule must be compressed, create a plan for compressing
the schedule and completing the work by the contractual completion date.
II Identify unusual scheduling requirements (such as night work, second
shift work, after-school work hours, escort required, etc.):
II Will the owner furnish any items, such as materials or equipment? II Yes II No
II Identify the “deliver no later than” dates that owner-furnished items
must be delivered to the jobsite.
II Will any portion of the work be installed by the owner’s own workforce
or a separate contract? (example: automated shelving systems) II Yes II No
II Identify the “install no later than” dates that owner-installed items
must be completed.
II Identify techniques that will speed up the completion of the work.
ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL
84
Project Number: _____________________________________________________________________________________
Table 4.26: Customer’s Schedule Review Items (continued)
CUSTOMER’S SCHEDULE REVIEW CHECKLIST
Completed Item to Review Annotations
II Review the sequencing/installation plan to determine how the
electrical work fits into the overall project schedule.
II Identify work that has already been completed:
II Identify work in progress and percent complete:
II Identify non-electrical activities that must be completed before the
electrical portion of the work can begin.
II Are you aware of any pending changes to the overall project or
electrical work? II Yes II No
II If yes, describe the pending changes:
II Do you anticipate crowded site conditions? II Yes II No
II If yes, consider scheduling some of the electrical work during a second
shift to improve productivity.
PRE-CONSTRUCTION PLANNING ACTIVITIES
85
Project Number: _____________________________________________________________________________________
Project Name: _______________________________________________________________________________________
Location:____________________________________________________________________________________________
Project Manager:_____________________________________________________________________________________
Table 4.27: Schedule Development Best Practices and Rules-of-Thumb (page 35)
SCHEDULE DEVELOPMENT BEST PRACTICES AND RULES-OF-THUMB
Best Practice
BEST PRACTICE/RULE-OF-THUMB DESCRIPTION
Number
1 Seek scheduling input from the field superintendent and foremen. They often understand how
the work will be accomplished and how the installation method corresponds to the crew size
and duration.
2 Develop the first draft schedule using actual durations to determine whether the electrical work
can be completed by the contractual completion date. If the schedule must be compressed,
build the compression into the second draft schedule.
3 Consider developing a resource-loaded schedule so that the expenditures from the schedule
can be compared to the expenditures from the cost report.
4 Compare the estimated work hours for an activity (or work process) to the scheduled duration
of that activity (or work process). Then, either adjust the duration based on estimated work
hours and expected crew size, or adjust the crew size based on the estimated work hours and
allowable duration.
5 Be sure the schedule takes into account the time of year when the work item will be performed
and the possible weather that can be expected. Excessive heat, cold, humidity, rain or wind can
significantly impact the progress of the work.
6 Understand when major materials and equipment items will be delivered to the jobsite. The
schedule may need to be adjusted to accommodate the delivery of those items.
7 Be sure the schedule clearly documents the date when owner-furnished materials and equip-
ment must be received. Also, make sure the owner knows when these items are required, and
seek their acknowledgement in writing.
8 Review the schedule of other specialty contractors to identify work that will impact the electri-
cal schedule. For example, if the air conditioning unit will require a power connection, comple-
tion of the connection must occur after the unit has been delivered and installed. Hence, the
electrical work must be coordinated with the mechanical work.
9 The electrical schedule should incorporate the work of any electrical subcontractors, such as
the fire alarm installer and tester. Review and incorporate your subcontractors’ work into your
own schedule and be sure to provide updates if the schedule changes.
10 If crowded conditions or overmanning is expected on a jobsite (due to a small site or an accel-
eration of the work), consider scheduling some of the electrical work during a second shift to
improve workflow and increase productivity.
11 Once the electrical schedule has been reviewed and approved by the customer/general contrac-
tor, document delays and changes to the sequence caused by others. Good documentation can
improve your chances of receiving a time extension and financial compensation.
ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL
86
Project Number: _____________________________________________________________________________________
Table 4.27: Schedule Development Best Practices and Rules-of-Thumb (continued)
SCHEDULE DEVELOPMENT BEST PRACTICES AND RULES-OF-THUMB
Best Practice
BEST PRACTICE/RULE-OF-THUMB DESCRIPTION
Number
12 When developing work activities or elements for the schedule, review the budget, cost codes
and installation sequence plan. Create work elements that comprise no more than 5% of the
scope of work so that inaccuracy in tracking progress will not have a significant impact on the
percent complete.
13 Consider creating a computerized bar chart schedule. Tracking and control will be greatly sim-
plified if the updates can be made in a computer system.
14 Consider dividing the schedule into areas or systems, such as first floor, second floor, etc. This
will simplify tracking and control, especially on larger projects.
15 If some of the work is repetitive (such as conduit and wire on the first floor, second floor, etc.),
consider creating these activities in your computer scheduling software and simply cutting and
pasting as many times as the work occurs. The dates and durations can then be modified for
each area of work.
PRE-CONSTRUCTION PLANNING ACTIVITIES
87
Project Number: _____________________________________________________________________________________
Project Name: _______________________________________________________________________________________
Location:____________________________________________________________________________________________
Project Manager:_____________________________________________________________________________________
Start Date: __________________________________________________________________________________________
TRACKING AND CONTROL CHECKLIST FOR PRE-CONSTRUCTION PLANNING
ACT.
COMPLETION ITEM
DATE NO.
SUB-ACTIVITIES
38. Customize the computerized tracking and control system (database/ schedule/etc.) for the current project.
II 1 Review the tracking and control best practices (Table 4.31).
II 2 Complete the tracking and control tools checklist (Table 4.32).
II 3
Select appropriate computerized tracking and control tools for the
project.
II 4 Modify the tracking and control tools for the project.
39. Develop labor and materials tracking report.
II 1
Review the cost estimate and associated budget and cost code
scheme.
II 2
Match the cost estimate/budget work items to crew assignments so
that labor and materials can be tracked easily.
II 3 Select the reports to be created and used for monitoring progress.
II 4
Develop the selected reports by inputting project data into the
reporting system (database or accounting system).
Table 4.28: Tracking and Control Planning Checklist (page 36)
ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL
88
Project Number: _____________________________________________________________________________________
Project Name: _______________________________________________________________________________________
Location:____________________________________________________________________________________________
Project Manager:_____________________________________________________________________________________
Table 4.29: Tracking and Control Best Practices (page 36)
TRACKING AND CONTROL BEST PRACTICES
Best Practice
BEST PRACTICE/RULE-OF-THUMB DESCRIPTION
Number
1 Remember that tracking and control involves a time-cost tradeoff. The more detailed the track-
ing and control system is, the more time must be spent on entering data and the greater the
overhead costs will be. You must balance detail with simplicity.
2 Be sure to take into account the financial information needs of banks and bonding companies
when setting up your control system.
3 If your company keeps track of historic costs, be sure the tracking and control system captures
the right data in the proper format so that it can be added to the historic cost database.
4 Match budget/cost control line items with field work items so that labor hours can be easily
reported and tracked.
5 Review the daily labor reporting procedures with the field supervisor and foremen. Be sure they
understand how to code timecards so that the work performed can be directly associated with
line items in the budget and tracking reports.
6 Deviations between actual and estimated costs and work hours should be discussed with the
field supervisor each week to identify and correct problems immediately.
7 Seek feedback from the crew members about the causes of poor productivity and cost/labor
hours overruns.
8 Work together with crews to improve productivity. Often, management actions or inactions
contribute to productivity outcomes. For example, poor instructions can hinder productive work,
while speedy responses to questions can help increase productivity.
9 If the crew members complete the work in fewer hours than estimated, provide a reward to
thank them for their hard work, such as free lunch or special recognition.
10 Try using incentives regularly to improve productivity.
11 Make sure your data entries are as accurate as possible. Remember that cost reports should
provide the project manager with a realistic financial overview of the project.
12 A negative variance between estimated and actual cost and work hours should be addressed
through corrective action. One of the main benefits of monthly cost reporting is to identify
problems early enough to take corrective action.
PRE-CONSTRUCTION PLANNING ACTIVITIES
89
Project Number: _____________________________________________________________________________________
Project Name: _______________________________________________________________________________________
Location:____________________________________________________________________________________________
Project Manager:_____________________________________________________________________________________
Table 4.30: Tracking and Control Tools Checklist (page 36)
TRACKING AND CONTROL TOOLS CHECKLIST
Completed Date Completed ITEM
II Identify the goals of your tracking and control system. Do you want to:
a. Monitor profitability?
b. Identify variations in costs and work hours?
c. Track productivity of the workforce?
d. Contribute to your historical costs database?
e. Document costs that are beyond the initial scope of work?
f. Track changes in cost and work hours?
g. Create contractually-mandated cost reports for the customer?
h. Evaluate the effectiveness of your management team?
i. Conduct risk analyses on future projects of a similar type?
II
Create a project schedule, and format it so that you can update the
progress of all schedule line items (see Activity 37). Match schedule line
items to budget line items to facilitate effective tracking.
II As an alternative, create a resource-loaded schedule that will permit you
to track cost and labor hours as you track schedule progress.
II
Create a manpower loading chart that identifies your crew size and com-
position for each week of the project (see Figure 4.13).
II
Customize the computerized project management program so that you
can use it as a tool to track RFIs, submittals, purchase orders, deliveries
and change orders.
II
Create a progress report to track variances in costs and labor hours. Your
progress report should track budgeted line items.
II
Create a labor productivity report to compare estimated to actual pro-
ductivity and identify solutions to problems. Daily time sheets should be
coded to match budget line items.
II
Other:
II
Other:
ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL
90
PROJECT NUMBER: _____________________________________________________________________________________________
PROJECT NAME: _______________________________________________________________________________________________
FIELD SUPERVISOR: ____________________________________________________________________________________________
EMPLOYEE NAME:______________________________________________________________________________________________
PAY PERIOD: FROM __________________________________________ TO: ______________________________________________
Figure 4.31: Daily Labor Time Report (pages 36, 40)
DAILY TIME SHEET
DAY WORK DESCRIPTION COST CODE
HOURS
REGULAR OVERTIME DOUBLE TIME
MON
TOTAL HOURS
DAY WORK DESCRIPTION COST CODE
HOURS
REGULAR OVERTIME DOUBLE TIME
TUE
TOTAL HOURS
DAY WORK DESCRIPTION COST CODE
HOURS
REGULAR OVERTIME DOUBLE TIME
WED
TOTAL HOURS
DAY WORK DESCRIPTION COST CODE
HOURS
REGULAR OVERTIME DOUBLE TIME
THU
TOTAL HOURS
PRE-CONSTRUCTION PLANNING ACTIVITIES
91
Figure 4.31: Daily Labor Time Report (continued)
DAY WORK DESCRIPTION COST CODE
HOURS
REGULAR OVERTIME DOUBLE TIME
FRI
TOTAL HOURS
DAY WORK DESCRIPTION COST CODE
HOURS
REGULAR OVERTIME DOUBLE TIME
SAT
TOTAL HOURS
DAY WORK DESCRIPTION COST CODE
HOURS
REGULAR OVERTIME DOUBLE TIME
SUN
TOTAL HOURS
ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL
92
ProjectNumber:___________________________________________________________________________________________________________________
ProjectName:____________________________________________________________________________________________________________________
Location:__________________________________________________________________________________________________________________________
ProjectManager:__________________________________________________________________________________________________________________
LABORPRODUCTIVITYTRACKING
ESTIMATEDACTUAL
CSI
DESCRIPTIONUNITSQTYOF
HOURS
HOURS/TOTALQTYOF
HOURS
HOURS/TOTALDIVISION
UNITSUNITSCOSTUNITSUNITSCOST
Table 4.32: Labor Productivity Report (pages 36, 40)
PRE-CONSTRUCTION PLANNING ACTIVITIES
93
CONSTRUCTION EXECUTION KICKOFF MEETING AGENDA
Agenda Items:
1. Project overview
a. Project name
b. Location
c. Type of work
d. Contract cost
e. General scope of work
2. Introduce internal team members and any changes in team members since planning meeting.
a. Project Manager
b. Field Supervisor
c. Foremen
d. Estimator
e. Accounting representative
f. Purchasing Agent
g. Director of Operations
h. Other internal team members
3. Identify external team members and any changes in team members since planning meeting.
a. Owner/Customer
b. Architect/Engineer
c. General Contractor/Construction Manager
d. Other Specialty Subcontractors
e. Vendors/Suppliers
4. Review the general scope of work.
a. Provide an overview of the project scope of work and the electrical scope
b. Review major work performed by others
5. Review the meetings schedule.
a. Internal office and jobsite progress meetings
b. Jobsite safety and coordination meetings
c. Project progress and coordination meetings
d. Other meetings
6. Review the Request for Information (RFI) Process.
a. Standard company RFI procedure
b. Contractual language regarding RFIs and the RFI process
c. Current outstanding RFIs
Project Number: _____________________________________________________________________________________
Project Name: _______________________________________________________________________________________
Meeting Date and Location: ___________________________________________________________________________
Estimator:___________________________________________________________________________________________
Project Manager:_____________________________________________________________________________________
Table 4.33: Construction Execution Kickoff Meeting Agenda (page 38)
ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL
94
Agenda Items:
7. Review the change order process.
a. Contract language regarding changes and the change order process
b. Standard company change order and field change processes
c. Documentation of changes, delays, disruptions and disputed work
8. Review the submittal process.
a. Contract language regarding submittals and the submittal process
b. Standard company submittal processes
c. Following up on late submissions and approvals
9. Review the billing process.
a. Contract language regarding billing and the payment process
b. Standard company billing processes
c. Subcontractor/supplier/vendor invoicing and payment
d. Following up on late payments or open accounts receivable
10. Review the tracking and control process.
a. Labor reporting
b. Progress reporting and percent complete
c. The progress update timeline
d. Standard company progress update procedures
11. Review the schedule and milestones.
a. Customer-furnished schedule
b. Electrical bar chart schedule
c. Work by others that will impact the electrical work
d. Important material and equipment delivery dates
e. Schedule updating to reflect percent complete
12. Review site logistics and material storage and staging.
a. Site access
b. Parking
c. Material delivery procedures
d. Material storage locations
e. Trailer locations (if applicable)
f. Site cleanup requirements
g. Temporary power and lighting requirements
13. Review special safety issues.
14. Review other items specific to this project:
______________________________________________________________________________________________
______________________________________________________________________________________________
______________________________________________________________________________________________
Project Number: ____________________________________________________________________________________
Table 4.33: Construction Execution Kickoff Meeting Agenda (continued)
PRE-CONSTRUCTION PLANNING ACTIVITIES
95
Project Number: _____________________________________________________________________________________
Project Name: _______________________________________________________________________________________
Location:____________________________________________________________________________________________
Project Manager:_____________________________________________________________________________________
Start Date: __________________________________________________________________________________________
CONSTRUCTION EXECUTION KICKOFF CHECKLIST FOR PRE-CONSTRUCTION PLANNING
ACT.
COMPLETION ITEM
DATE NO.
SUB-ACTIVITIES
40. Review meeting schedule.
II 1
Review the schedule of weekly internal meetings associated with the
project.
II 2
Review the schedule of weekly project meetings conducted by the
customer or general contractor.
II 3
Identify the internal team members that will be responsible for
attending the internal and external meetings.
41. Review request for information (RFI) process.
II 1
Review the contract for a customer-mandated request for information
(RFI) process.
II 2
Review the company standard procedure for developing, processing,
tracking and closing out a request for information.
II 3
Modify the company standard RFI procedure, as necessary, to
conform to the contractually-mandated process.
42. Develop prefabrication drawings for field use (when applicable).
II 1
Review the contract for a customer-mandated change order (CO)
process and field change request process.
II 2
Review the company standard change order procedure and field
change request/management process.
II 3
Discuss the process for documenting changes, delays and
disruptions in the work flow and sequence.
II 4
Discuss the process for tracking and following up on change order
requests and payment for field change directives.
43. Review submittal processing procedures.
II 1
Review the contract documents for a customer-mandated submittal
processing procedures.
II 2
Review the company standard procedure for developing, processing,
tracking and receiving approval for project submittals.
II 3
Modify the company standard submittal procedure, as necessary, to
conform to the contractually-mandated process.
Table 4.34: Construction Execution Kickoff Meeting Checklist (page 38)
ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL
96
Project Number: ____________________________________________________________________________________
Table 4.34: Construction Execution Kickoff Meeting Checklist (continued)
44. Review billing and invoicing procedures
II 1
Review the customer/general contractor’s process and timeline for
invoicing, lien waivers and payment.
II 2
Review the internal billing cycle established by the accounting
department.
II 3
If necessary, adjust the internal billing cycle to conform to the
customer/general contractor’s invoicing cycle.
II 4
Discuss the process for following up with the customer/general
contractor on late unpaid invoices.
45. Review project and field reporting and tracking procedures.
II 1
Discuss the process for reporting labor hours and submitting
timecards to the accounting office.
II 2 Discuss the process for reporting progress and percent complete.
II 3
Discuss the process for tracking material and equipment costs and
purchase orders.
II 4
Review and discuss the tracking tools that will be used to monitor
progress.
II 5 Review the monthly update process.
46. Review electrical and customer schedules.
II 1 Review the electrical bar chart schedule.
II 2 Review the customer/general contractor’s schedule and/or timeline.
II 3 Discuss the process for updating the schedule.
5.1 Introduction to the Planning
Assessment Process
Chapter 4 of this manual discusses, in detail,
the model electrical pre-construction planning
process. This research discovered that projects that
implemented a planning process similar to the
model process tended to perform more successfully.
Furthermore, there appeared to be 16 activities that
had an especially strong influence on perform-
ance—and many of these activities were often over-
looked during the planning process.
5.2 Purpose of the Planning
Assessment Process
Chapter 4 presents a series of instructions and
easy-to-use checklists to guide electrical contractors
through the pre-construction planning process. The
purpose of this chapter is to present a scorecard
that can be used to evaluate the effectiveness of the
planning that was completed on a project that is
about to be executed.
The chapter will begin by identifying the 16
activities that had an especially strong influence on
performance in order to explain why these activities
are weighted more heavily on the planning score-
card. Then, the planning effectiveness scorecard will
be introduced, which includes all of the activities
from the model planning process, and instructions
will be provided on how to score the effectiveness
of planning on a new project. Finally, a section on
“score analysis” will present some rules-of-thumb
and benchmark score values for projects that have
various characteristics, such as large projects versus
small projects, complex projects versus simple proj-
ects, and so on.
5.3 Important and Influential
Planning Activities
It is essential to note that each of the 46 pre-
construction planning activities in the Model
Electrical Pre-Construction Planning Process is an
important part of the planning process. It is also
worth noting that not every activity will require a
great deal of time to complete. Indeed, many of the
activities can be completed in a matter of a few
minutes, particularly on smaller projects. The proj-
ect manager will need to exercise skill and judg-
ment when determining how much time to devote
to each activity.
Many of the activities are clearly critical to an
effective planning process. Such obvious activities
as reviewing the plans and specifications, adminis-
tratively setting up the project, and issuing purchase
orders can directly impact the smooth execution of
a project. Overall, 16 “influential activities” were
identified through careful research, and these activi-
ties are identified in the next section. It is critical
that the project manager understand the following:
However, 16 of those activities have a particu-
larly strong influence on the outcome of a project.
5.3.1 The 16 Influential Planning Activities
Sixteen of the pre-construction planning activi-
ties were identified as having an especially strong
97
Section 3: Planning Assessment and Best Practices
5. The Planning Assessment Process
All of the 46 pre-construction planning
activities are important to project success.
ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL
correlation to a successful project outcome. These
activities include the following:
I Team Selection and Turnover
Activity 2: Hold turnover meeting between
estimator and project manager (when
applicable).
Activity 3: Hold separate turnover meeting
between project manager and field supervi-
sor.
I Scope and Contract Review
Activity 7: Field supervisor reviews plans,
specifications and schedule.
Activity 10: Compare estimated (bid) work
activities and materials to planned per-
formance.
Activity 11: Identify value engineering and pre-
fabrication opportunities and how to sim-
plify the work.
I Administrative Setup
Activity 16: Initiate a request for information
(RFI) tracking and processing system.
Activity 17: Initiate a submittal tracking and
processing system.
I Buyout Process
Activity 23: Request submittals, cut sheets and
shop drawings.
I Material Handling Plan
Activity 25: Develop material delivery and han-
dling plan.
Activity 26: Develop material storage and stag-
ing plan.
I Layout and Sequencing Plan
Activity 30: Develop installation sequence and
layout drawings.
Activity 31: Develop field instructions, includ-
ing panel, pull or conduit schedules.
Activity 32: Develop prefabrication drawings
for field use (when applicable).
I Schedule Development
Activity 36: Coordinate electrical schedule with
the customer's schedule.
I Construction Execution Kickoff Meeting
Activity 43: Review submittal processing pro-
cedure.
Activity 44: Review billing and invoicing pro-
cedures.
When performing pre-construction planning,
extra care should be taken to include these activi-
ties in the planning process. Although it is recom-
mended that all of the 46 activities be completed,
under extraordinary circumstances, when the plan-
ning process must be abbreviated, these 16 activi-
ties should be among those that get completed.
5.4 Planning Assessment Process
The planning assessment process provides a sim-
ple method for evaluating whether each of the 46
pre-construction planning activities has been com-
pleted and whether an activity was completed before
or after a project was executed. Under ideal circum-
stances, all of the planning activities will be complet-
ed prior to executing the work. However, ideal cir-
cumstances are rare in the construction industry, and
often, some of the planning activities must be com-
pleted after the project has been executed.
The purpose of this section is to introduce the
planning effectiveness scorecard and to provide
instructions on how to use the scorecard to evaluate
the planning that has occurred on a new project.
5.4.1 The Planning Effectiveness Scorecard
The planning effectiveness scorecard was devel-
oped as a tool to evaluate how closely a project’s
actual planning process matches the Model
Electrical Pre-Construction Planning Process. The
scorecard, which is presented as Table 5.1 (pages
100-101), lists each of the 46 model pre-construc-
tion planning activities (Column C). Space is pro-
vided in Column D for contractors to identify
98
THE PLANNING ASSESSMENT PROCESS
whether or not the activity was performed and to
assign a “performance score.”
The performance score is assigned based on
whether an activity was performed or not per-
formed and whether it was completed before or
after execution using the following scale:
Using this scale, a higher summed performance
score indicates that more of the pre-construction
planning activities were completed before executing
the work, which correlates strongly to better project
performance.
Column E represents the weight assigned to
each activity. As mentioned in the previous section,
16 of the activities have a stronger influence on
performance, and as a result, these activities are
assigned larger weights. To calculate a final score
(Column F) for each activity, Column D
(Performance Score) is multiplied by Column E
(Weight). The planning effectiveness score is the
sum of all of the total scores.
5.4.2 Score Analysis
Projects that were investigated as part of the
research had various character-istics. In particular,
four characteristics were analyzed, including proj-
ect size, initial uncertainty, bid accuracy and type
of construction.
5.4.2.1 Project Size
Project Size is generally determined by three
values: contract cost at award, original estimated
total work hours and estimated peak number of
electricians. Furthermore, estimated project dura-
tion is also strongly related to a project’s size.
5.4.2.2 Initial Uncertainty of the Project
Initial uncertainty of the project is generally
determined by three values: perceived level of
uncertainty (high, medium or low), percentage of
the total design completed at bid and perceived
level of complexity (high, medium or low).
5.4.2.3 Bid Accuracy
Bid Accuracy is generally determined by two
concepts: a perceived accurate cost estimate and
perceived accurate estimated work hours.
5.4.2.4 Type of Construction
Type of Construction is generally determined
by classifying projects as: commercial, industrial,
institutional and other.
99
PERFORMANCE SCORE (Column D)
2 = Activity was completed before executing
the work
1 = Activity was completed after executing
the work
0 = Activity was not completed
The trend seems to indicate that larger proj-
ects will require a higher planning effective-
ness score to have a greater chance for suc-
cessful performance.
The trend indicates that projects with high
levels of initial uncertainty will require a
higher planning effectiveness score to have a
greater chance for successful performance.
The trend indicates that projects with an
inaccurate bid will require a higher planning
effectiveness score to have a greater chance
for successful performance.
The trend indicates that industrial and insti-
tutional projects require a higher planning
effectiveness score to have a greater chance
for successful performance.
Pdfslide.net electrical pre-construction-planning-planningformsawadelectrical-pre-construction
Pdfslide.net electrical pre-construction-planning-planningformsawadelectrical-pre-construction

More Related Content

What's hot

Commissioning and Operations
Commissioning and OperationsCommissioning and Operations
Commissioning and Operations
Achal Gupta
 
Final report piyush
Final report piyushFinal report piyush
Final report piyush
hiren09
 
Summer Training report at TATA CMC
Summer Training report at TATA CMCSummer Training report at TATA CMC
Summer Training report at TATA CMC
Pallavi Srivastava
 
Industrial Training PRESENTATION
Industrial Training PRESENTATIONIndustrial Training PRESENTATION
Industrial Training PRESENTATION
Muaz Sadini
 

What's hot (20)

industrial training report
industrial training reportindustrial training report
industrial training report
 
Scope of work
Scope of workScope of work
Scope of work
 
PetroSync - Pre-Commissioning, Commissioning and Start-Up
PetroSync - Pre-Commissioning, Commissioning and Start-UpPetroSync - Pre-Commissioning, Commissioning and Start-Up
PetroSync - Pre-Commissioning, Commissioning and Start-Up
 
Commissioning and Operations
Commissioning and OperationsCommissioning and Operations
Commissioning and Operations
 
Site Possession
Site PossessionSite Possession
Site Possession
 
TRANING REPORT ON PLC SCADA and AUTOMATION
TRANING REPORT ON PLC SCADA and AUTOMATIONTRANING REPORT ON PLC SCADA and AUTOMATION
TRANING REPORT ON PLC SCADA and AUTOMATION
 
Plc on cnc
Plc on cncPlc on cnc
Plc on cnc
 
Benefits of Upgrading the Overhead Line of a DC Railway Line in the Netherlands
Benefits of Upgrading the Overhead Line of a DC Railway Line in the NetherlandsBenefits of Upgrading the Overhead Line of a DC Railway Line in the Netherlands
Benefits of Upgrading the Overhead Line of a DC Railway Line in the Netherlands
 
In-Plant Training Report
In-Plant Training ReportIn-Plant Training Report
In-Plant Training Report
 
Final report piyush
Final report piyushFinal report piyush
Final report piyush
 
Electro-Pneumatics
Electro-PneumaticsElectro-Pneumatics
Electro-Pneumatics
 
Automatic drain cleaning system
Automatic drain cleaning systemAutomatic drain cleaning system
Automatic drain cleaning system
 
Safety Audit as per IS 14489.ppt
Safety Audit as per IS 14489.pptSafety Audit as per IS 14489.ppt
Safety Audit as per IS 14489.ppt
 
Commissioning of Industrial Projects - Cost Estimating Considerations
Commissioning of Industrial Projects - Cost Estimating ConsiderationsCommissioning of Industrial Projects - Cost Estimating Considerations
Commissioning of Industrial Projects - Cost Estimating Considerations
 
What is Mechatronics?
What is Mechatronics?What is Mechatronics?
What is Mechatronics?
 
Automation presentation
Automation presentationAutomation presentation
Automation presentation
 
Weekly air compressor check list
Weekly air compressor check listWeekly air compressor check list
Weekly air compressor check list
 
Automation and Robotics Week 01 Theory Notes 20ME51I.pdf
Automation and Robotics Week 01 Theory Notes 20ME51I.pdfAutomation and Robotics Week 01 Theory Notes 20ME51I.pdf
Automation and Robotics Week 01 Theory Notes 20ME51I.pdf
 
Summer Training report at TATA CMC
Summer Training report at TATA CMCSummer Training report at TATA CMC
Summer Training report at TATA CMC
 
Industrial Training PRESENTATION
Industrial Training PRESENTATIONIndustrial Training PRESENTATION
Industrial Training PRESENTATION
 

Similar to Pdfslide.net electrical pre-construction-planning-planningformsawadelectrical-pre-construction

Sheet1Work Breakdown StructureProject NameDistrict 4 Warehouse Mo.docx
Sheet1Work Breakdown StructureProject NameDistrict 4 Warehouse Mo.docxSheet1Work Breakdown StructureProject NameDistrict 4 Warehouse Mo.docx
Sheet1Work Breakdown StructureProject NameDistrict 4 Warehouse Mo.docx
lesleyryder69361
 
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.pptCONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
pisal3
 
10 me667 chap2 project management
10 me667 chap2 project management10 me667 chap2 project management
10 me667 chap2 project management
Pavan Kumar
 
Construction process
Construction processConstruction process
Construction process
Mazen Al-Qadi
 

Similar to Pdfslide.net electrical pre-construction-planning-planningformsawadelectrical-pre-construction (20)

construction-project-management-ppt-india-ppt.pptx
construction-project-management-ppt-india-ppt.pptxconstruction-project-management-ppt-india-ppt.pptx
construction-project-management-ppt-india-ppt.pptx
 
Sheet1Work Breakdown StructureProject NameDistrict 4 Warehouse Mo.docx
Sheet1Work Breakdown StructureProject NameDistrict 4 Warehouse Mo.docxSheet1Work Breakdown StructureProject NameDistrict 4 Warehouse Mo.docx
Sheet1Work Breakdown StructureProject NameDistrict 4 Warehouse Mo.docx
 
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.pptCONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
 
3 pma salehuddin - resource and project management
3   pma salehuddin - resource and project management3   pma salehuddin - resource and project management
3 pma salehuddin - resource and project management
 
NCIT civil Syllabus 2013-2014
NCIT civil Syllabus 2013-2014NCIT civil Syllabus 2013-2014
NCIT civil Syllabus 2013-2014
 
Farm structures ppt.editeddddddddd
Farm structures ppt.editedddddddddFarm structures ppt.editeddddddddd
Farm structures ppt.editeddddddddd
 
Textile plant design.pptx
Textile plant design.pptxTextile plant design.pptx
Textile plant design.pptx
 
Project Planning and Scheduling
Project Planning and SchedulingProject Planning and Scheduling
Project Planning and Scheduling
 
012 bussiness planning process
012 bussiness planning process012 bussiness planning process
012 bussiness planning process
 
7.resource allocation
7.resource allocation7.resource allocation
7.resource allocation
 
Cost Control Process for Construction
Cost Control Process for ConstructionCost Control Process for Construction
Cost Control Process for Construction
 
10 me667 chap2 project management
10 me667 chap2 project management10 me667 chap2 project management
10 me667 chap2 project management
 
Introduction to construction project.pptx
Introduction to construction project.pptxIntroduction to construction project.pptx
Introduction to construction project.pptx
 
Project management-project life cycle-pdf
Project management-project life cycle-pdfProject management-project life cycle-pdf
Project management-project life cycle-pdf
 
PPT4 RIBA Plan of Work 2013 Power point slide
PPT4 RIBA Plan of Work 2013 Power point slidePPT4 RIBA Plan of Work 2013 Power point slide
PPT4 RIBA Plan of Work 2013 Power point slide
 
4 defining scope, quality, responsibility, and activity sequence
4 defining scope, quality, responsibility, and activity sequence4 defining scope, quality, responsibility, and activity sequence
4 defining scope, quality, responsibility, and activity sequence
 
Construction process
Construction processConstruction process
Construction process
 
C. Site managment chapter 5.pptx
C. Site managment chapter 5.pptxC. Site managment chapter 5.pptx
C. Site managment chapter 5.pptx
 
1.Cost Estimation of Civil Structures Orientation.pptx
1.Cost Estimation of Civil Structures Orientation.pptx1.Cost Estimation of Civil Structures Orientation.pptx
1.Cost Estimation of Civil Structures Orientation.pptx
 
Lecture 3 Project Management.ppt
Lecture 3 Project Management.pptLecture 3 Project Management.ppt
Lecture 3 Project Management.ppt
 

Recently uploaded

Personalisation of Education by AI and Big Data - Lourdes Guàrdia
Personalisation of Education by AI and Big Data - Lourdes GuàrdiaPersonalisation of Education by AI and Big Data - Lourdes Guàrdia
Personalisation of Education by AI and Big Data - Lourdes Guàrdia
EADTU
 
SURVEY I created for uni project research
SURVEY I created for uni project researchSURVEY I created for uni project research
SURVEY I created for uni project research
CaitlinCummins3
 
Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...
Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...
Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...
EADTU
 
Spellings Wk 4 and Wk 5 for Grade 4 at CAPS
Spellings Wk 4 and Wk 5 for Grade 4 at CAPSSpellings Wk 4 and Wk 5 for Grade 4 at CAPS
Spellings Wk 4 and Wk 5 for Grade 4 at CAPS
AnaAcapella
 
會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽
會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽
會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽
中 央社
 

Recently uploaded (20)

How to Manage Website in Odoo 17 Studio App.pptx
How to Manage Website in Odoo 17 Studio App.pptxHow to Manage Website in Odoo 17 Studio App.pptx
How to Manage Website in Odoo 17 Studio App.pptx
 
VAMOS CUIDAR DO NOSSO PLANETA! .
VAMOS CUIDAR DO NOSSO PLANETA!                    .VAMOS CUIDAR DO NOSSO PLANETA!                    .
VAMOS CUIDAR DO NOSSO PLANETA! .
 
Sternal Fractures & Dislocations - EMGuidewire Radiology Reading Room
Sternal Fractures & Dislocations - EMGuidewire Radiology Reading RoomSternal Fractures & Dislocations - EMGuidewire Radiology Reading Room
Sternal Fractures & Dislocations - EMGuidewire Radiology Reading Room
 
diagnosting testing bsc 2nd sem.pptx....
diagnosting testing bsc 2nd sem.pptx....diagnosting testing bsc 2nd sem.pptx....
diagnosting testing bsc 2nd sem.pptx....
 
Basic Civil Engineering notes on Transportation Engineering & Modes of Transport
Basic Civil Engineering notes on Transportation Engineering & Modes of TransportBasic Civil Engineering notes on Transportation Engineering & Modes of Transport
Basic Civil Engineering notes on Transportation Engineering & Modes of Transport
 
Personalisation of Education by AI and Big Data - Lourdes Guàrdia
Personalisation of Education by AI and Big Data - Lourdes GuàrdiaPersonalisation of Education by AI and Big Data - Lourdes Guàrdia
Personalisation of Education by AI and Big Data - Lourdes Guàrdia
 
Including Mental Health Support in Project Delivery, 14 May.pdf
Including Mental Health Support in Project Delivery, 14 May.pdfIncluding Mental Health Support in Project Delivery, 14 May.pdf
Including Mental Health Support in Project Delivery, 14 May.pdf
 
Supporting Newcomer Multilingual Learners
Supporting Newcomer  Multilingual LearnersSupporting Newcomer  Multilingual Learners
Supporting Newcomer Multilingual Learners
 
Mattingly "AI and Prompt Design: LLMs with NER"
Mattingly "AI and Prompt Design: LLMs with NER"Mattingly "AI and Prompt Design: LLMs with NER"
Mattingly "AI and Prompt Design: LLMs with NER"
 
SURVEY I created for uni project research
SURVEY I created for uni project researchSURVEY I created for uni project research
SURVEY I created for uni project research
 
Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...
Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...
Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...
 
Improved Approval Flow in Odoo 17 Studio App
Improved Approval Flow in Odoo 17 Studio AppImproved Approval Flow in Odoo 17 Studio App
Improved Approval Flow in Odoo 17 Studio App
 
AIM of Education-Teachers Training-2024.ppt
AIM of Education-Teachers Training-2024.pptAIM of Education-Teachers Training-2024.ppt
AIM of Education-Teachers Training-2024.ppt
 
PSYPACT- Practicing Over State Lines May 2024.pptx
PSYPACT- Practicing Over State Lines May 2024.pptxPSYPACT- Practicing Over State Lines May 2024.pptx
PSYPACT- Practicing Over State Lines May 2024.pptx
 
Observing-Correct-Grammar-in-Making-Definitions.pptx
Observing-Correct-Grammar-in-Making-Definitions.pptxObserving-Correct-Grammar-in-Making-Definitions.pptx
Observing-Correct-Grammar-in-Making-Definitions.pptx
 
Spellings Wk 4 and Wk 5 for Grade 4 at CAPS
Spellings Wk 4 and Wk 5 for Grade 4 at CAPSSpellings Wk 4 and Wk 5 for Grade 4 at CAPS
Spellings Wk 4 and Wk 5 for Grade 4 at CAPS
 
會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽
會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽
會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽
 
Stl Algorithms in C++ jjjjjjjjjjjjjjjjjj
Stl Algorithms in C++ jjjjjjjjjjjjjjjjjjStl Algorithms in C++ jjjjjjjjjjjjjjjjjj
Stl Algorithms in C++ jjjjjjjjjjjjjjjjjj
 
TỔNG HỢP HƠN 100 ĐỀ THI THỬ TỐT NGHIỆP THPT TOÁN 2024 - TỪ CÁC TRƯỜNG, TRƯỜNG...
TỔNG HỢP HƠN 100 ĐỀ THI THỬ TỐT NGHIỆP THPT TOÁN 2024 - TỪ CÁC TRƯỜNG, TRƯỜNG...TỔNG HỢP HƠN 100 ĐỀ THI THỬ TỐT NGHIỆP THPT TOÁN 2024 - TỪ CÁC TRƯỜNG, TRƯỜNG...
TỔNG HỢP HƠN 100 ĐỀ THI THỬ TỐT NGHIỆP THPT TOÁN 2024 - TỪ CÁC TRƯỜNG, TRƯỜNG...
 
Spring gala 2024 photo slideshow - Celebrating School-Community Partnerships
Spring gala 2024 photo slideshow - Celebrating School-Community PartnershipsSpring gala 2024 photo slideshow - Celebrating School-Community Partnerships
Spring gala 2024 photo slideshow - Celebrating School-Community Partnerships
 

Pdfslide.net electrical pre-construction-planning-planningformsawadelectrical-pre-construction

  • 1. ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL 42 Project Number: ____________________________________________________________________________________ Project Name: ______________________________________________________________________________________ Location: ___________________________________________________________________________________________ Estimator: __________________________________________________________________________________________ Project Manager: ____________________________________________________________________________________ PRE-CONSTRUCTION PLANNING CHECKLIST COMPLETION ACTIVITY ACT. DATE CATEGORY NO. ACTIVITY II 1 Finalize selection of project manager, field supervisor and other key team members. II 2 Hold turnover meeting between estimator and project separate manager (when applicable). II 3 Hold separate turnover meeting between project manager and field supervisor. II 4 Hold pre-job (planning) kickoff meeting with internal team members to assign responsibilities. II 5 Review contract for unfavorable or high risk clauses (recommended). II 6 Project manager reviews plans, specifications, and schedule. II 7 Field supervisor reviews plans, specifications, and schedule. II 8 Create a list of issues that need to be resolved and begin the request for information (RFI) process. II 9 Conduct site visit (recommended). II 10 Compare estimated (bid) work activities and materials to planned performance. II 11 Identify value engineering and refabrication opportunities and how to simplify the work. II 12 Prepare construction takeoff. II 13 Set up project files and create contact list. II 14 Set up computerized tracking and control system (forms, database, schedule, tracking). II 15 Initiate a change management system. II 16 Initiate a request for information (RFI) tracking and processing system. II 17 Initiate a submittal tracking and processing system. II 18 Develop a “Labor Requirements/Expectations” letter (for background check, etc.) (recommended). Table 4.1: Checklist of Pre-Construction Planning Activities (page 15) Team Selection and Turnover Scope and Contract Review Administrative Setup
  • 2. PRE-CONSTRUCTION PLANNING ACTIVITIES 43 Project Number: ____________________________________________________________________________________ Table 4.1: Checklist of Pre-Construction Planning Activities (continued) PRE-CONSTRUCTION PLANNING CHECKLIST COMPLETION ACTIVITY ACT. DATE CATEGORY NO. ACTIVITY II 19 Price and/or review subcontractor/supplier/vendor prices and qualifications. II 20 Negotiate pricing and contract conditions, and select separate subcontractors/suppliers/vendors. II 21 Develop and issue purchase orders and contracts for materials and equipment. II 22 Order long-lead-time materials and equipment. II 23 Request submittals, cut sheets and shop drawings. II 24 Develop and process log and book of submittals, cut sheets and shop drawings. II 25 Develop material delivery and handling plan. II 26 Develop material storage and staging plan. II 27 Develop, review or expand cost code scheme. II 28 Develop budget by breaking down labor, material, overhead and profit costs. II 29 Develop schedule of values. II 30 Develop installation sequence and layout drawings. II 31 Develop field instructions, including panel, pull or conduit schedules. II 32 Develop prefabrication drawings for field use (when applicable). II 33 Review customer’s schedule and timeline. II 34 Identify work that impacts electrical activities. II 35 Review the work sequence and long-lead-time material/equipment delivery dates. II 36 Coordinate electrical schedule with customer schedule (recommended). II 37 Create a bar chart schedule (recommended). Customize the computerized tracking and control II 38 system (database/schedule/etc.) for the current project. II 39 Develop labor and materials tracking report. Buyout Process Material Handling Plan Budget Preparation Layout and Sequencing Plan Schedule Development Tracking and Control
  • 3. ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL 44 Project Number: ____________________________________________________________________________________ PRE-CONSTRUCTION PLANNING CHECKLIST COMPLETION ACTIVITY ACT. DATE CATEGORY NO. ACTIVITY II 40 Review meeting schedule. II 41 Review request for information (RFI) process. II 42 Review change order process and field change management process. II 43 Review submittal processing procedure. II 44 Review billing and invoicing procedures. II 45 Review project and field reporting and tracking procedures. II 46 Review electrical and customer schedules. Construction Execution Kickoff Meeting Table 4.1: Checklist of Pre-Construction Planning Activities (continued)
  • 4. PRE-CONSTRUCTION PLANNING ACTIVITIES 45 Project Number: _____________________________________________________________________________________ Project Name: _______________________________________________________________________________________ Location:____________________________________________________________________________________________ Estimator:___________________________________________________________________________________________ Project Manager:_____________________________________________________________________________________ TEAM SELECTION AND TURNOVER CHECKLIST FOR PRE-CONSTRUCTION PLANNING ACT. COMPLETION ITEM DATE NO. SUB-ACTIVITIES 1. Finalize selection of project manager, field supervisor and other key team members. II 1 Assemble a list of project managers and review their current work- load and special skills. II 2 Determine whether an ideal match can be made between the project manager and the job, and then select the project manager. II 3 Assemble a list of field supervisors and review their current work- load and special skills. II 4 Determine whether an ideal match can be made between the field supervisor and the job, and then select the project manager. II 5 Work with the project manager, field supervisor, and/or the director of operations to select key foreman when appropriate. 2. Hold turnover meeting between estimator and project manager (when applicable). II 1 Arrange a meeting time and location and ensure enough time has been allocated to transfer knowledge between the estimator and project manager. II 2 Follow and complete a checklist that describes the information that should be transferred (See Table 4.3). 3. Hold separate turnover meeting between project manager and field supervisor. II Arrange a meeting time and location and ensure enough time has 1 been allocated to transfer knowledge between the project manager and field supervisor. II 2 Follow and complete a checklist that describes the information that must be transferred (see Table 4.3). 4. Hold pre-job (planning) kickoff meeting with internal team members to assign responsibilities. II 1 Arrange a meeting time and location and ensure enough time has been allocated to assign planning responsibilities. II Invite internal team members that will be involved during the 2 construction execution process, such as project manager, field supervisor, accounting, purchasing, and director of field operations. II 3 Complete a checklist that describes the planning activities that must be completed and who is responsible for completion (see Table 4.4). Table 4.2: Team Selection and Turnover Checklist (page 16)
  • 5. ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL 46 TURNOVER MEETING AGENDA Review Items: 1. Project overview a. Project name b. Location c. Type of work d. Estimated cost and estimated work hours e. Profit goal f. General scope of work g. Identify potential opportunities and challenges of the project 2. Review the plans and specifications. a. Go page by page through the plans to discuss the quantities and costs. b. Review each section of the specifications. c. Discuss how the estimator assumed the work would be performed (materials and methods). d. Review others’ work performance. e. Identify discrepancies and ambiguities in the bid documents. f. Identify design discrepancies or issues. g. Identify potential errors in the bid documents. h. Discuss information collected during a site visit. i. Discuss information collected during a pre-bid meeting. j. Identify potential cost savings from changes to materials and methods. k. Identify potential prefabrication or internal value engineering opportunities. l. Discuss alternative routing of conduits. m. Identify any temporary power and lighting requirements. 3. Review the cost estimate and bid price. a. Review each bid line item and its cost. b. Review overhead, profit and contingency funds. c. Discuss wage rates. d. Review the bid submission letter with clarifications and qualifications. 4. Review subcontractor/vendor pricing and qualifications. a. Review subcontractors and suppliers scope of work and qualifications. b. Identify all pre-contract commitments and promises. c. Verify minority business requirements. Project Number: _____________________________________________________________________________________ Project Name: _______________________________________________________________________________________ Location:____________________________________________________________________________________________ Estimator:___________________________________________________________________________________________ Project Manager:_____________________________________________________________________________________ Table 4.3: Turnover Meeting Agenda (page 16)
  • 6. PRE-CONSTRUCTION PLANNING ACTIVITIES 47 Review Items: 5. Review the schedule and milestones. a. Review the owner-furnished schedule. b. Review any preliminary schedule submitted with the bid. c. Review work by others that will impact the electrical work. d. Identify important material and equipment delivery dates. e. Discuss holidays, vacations and potential weather events. 6. Review manpower requirements and labor rates. a. Review the manpower loading chart (if available). b. Identify the estimated crew mix. c. Identify any wage increases. d. Review the potential for overtime. 7. Review other items specific to this project: ____________________________________________________________________________________________________ ____________________________________________________________________________________________________ ____________________________________________________________________________________________________ ____________________________________________________________________________________________________ ____________________________________________________________________________________________________ ____________________________________________________________________________________________________ ____________________________________________________________________________________________________ ____________________________________________________________________________________________________ ____________________________________________________________________________________________________ ____________________________________________________________________________________________________ ____________________________________________________________________________________________________ Project Number: ____________________________________________________________________________________ Table 4.3: Turnover Meeting Agenda (continued)
  • 7. ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL 48 PRE-JOB PLANNING KICKOFF MEETING AGENDA Agenda Items: 1. Project overview a. Project name b. Location c. Type of work d. Contract cost e. General scope of work f. Identify potential opportunities and challenges of the project 2. Introduce internal team members. a. Project manager b. Field supervisor/foreman c. Estimator d. Accounting representative e. Other internal team members (i.e., CAD operator, purchasing agent, etc.) 3. Identify external team members. a. Owner/customer b. Architect/engineer c. General contractor/construction manager d. Other specialty subcontractors e. Vendors/suppliers 4. Review the general scope of work. a. Provide an overview of the project scope of work and the electrical scope. b. Review major work performed by others. 5. Review the contract cost. a. Review direct costs and the contract cost. b. Review overhead, profit and contingency funds. 6. Review purchasing of materials, equipment and services from subcontractors/vendors. a. Review subcontractors and suppliers scope of work and qualifications. b. Identify all pre-contract commitments and promises. c. Verify minority business requirements. Project Number: _____________________________________________________________________________________ Project Name: _______________________________________________________________________________________ Location:____________________________________________________________________________________________ Estimator:___________________________________________________________________________________________ Project Manager:_____________________________________________________________________________________ Table 4.4: Pre-Job Planning Kickoff Meeting Agenda (page 17)
  • 8. PRE-CONSTRUCTION PLANNING ACTIVITIES 49 Agenda Items: 7. Review the schedule and milestones. a. Review the owner-furnished schedule. b. Review any preliminary schedule submitted with the bid or construction schedule. c. Review work by others that will impact the electrical work. d. Identify important material and equipment delivery dates. 8. Review manpower requirements and labor rates. a. Review the manpower loading chart (if available). b. Identify the estimated crew mix. c. Identify any wage increases. 9. Review the contract—identify any special clauses that require careful consideration. 10. Review administrative procedures. a. Administrative setup b. Request for Information (RFI) procedures and setup c. Submittal process and setting up the submittal tracking system d. Change order procedures and setting up the change management system e. Field reporting requirements f. Budget preparation and billing procedures g. Cost control and setting up the tracking system 11. Review special safety issues. 12. Review site logistics and material storage and staging. a. Site access b. Parking c. Material delivery and movement procedures d. Material storage locations e. Trailer locations (if applicable) f. Site cleanup requirements g. Temporary power and lighting requirements 13. Review bond, permit and certificate of insurance requirements 14. Review other items specific to this project: ______________________________________________________________________________________________ ______________________________________________________________________________________________ ______________________________________________________________________________________________ Project Number: ____________________________________________________________________________________ Table 4.4: Pre-Job Planning Kickoff Meeting Agenda (continued)
  • 9. ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL 50 Project Number: _____________________________________________________________________________________ Project Name: _______________________________________________________________________________________ Location:____________________________________________________________________________________________ Estimator:___________________________________________________________________________________________ Bid Due Date: _______________________________________________________________________________________ SCOPE AND CONTRACT REVIEW CHECKLIST FOR PRE-CONSTRUCTION PLANNING ACT. COMPLETION ITEM DATE NO. SUB-ACTIVITIES 5. Review contract for unfavorable or high risk clauses (performance recommended). II 1 Complete the Contract Review Checklist (Table 4.6). II 2 Identify all required bonds, permits and certificates. II 3 Review contractual billing requirements. II 4 Review and understand procedures for requesting change orders. II 5 Identify whether disputes must be resolved through alternative dispute resolution, such as mediation or arbitration. 6. Project manager reviews plans, specifications and schedule. II 1 Order extra sets of plans and specifications if necessary. II 2 Complete the Scope and Schedule Review checklist (Table 4.7). II 3 Compare the scope identified in the contract to the scope from the bid submission to verify that they match. II 4 Compare the plans to the specifications to identify any discrepancies. II 5 Review the customer-furnished schedule to determine whether the electrical work can be completed within the contractual timeframe. 7. Field supervisor reviews plans, specifications and schedule. II 1 Complete the Scope and Schedule Review checklist (Table 4.7). II 2 Review best field practices or lessons learned. II 3 Identify value engineering and prefabrication opportunities (see Activity 23). II 4 Identify labor requirements and begin selecting foremen. II 5 Identify special tools that will need to be purchased or assembled. 8. Create a list of issues that need to be resolved and begin the request for information (RFI) process. II 1 Establish a request for information (RFI) process (see Activity 16) and create a list of questions that require clarification. II 2 Formalize the RFIs by assigning them a trackable number and submitting them to the owner/CM/GC. Table 4.5: Scope and Contract Review Checklist (page 17)
  • 10. PRE-CONSTRUCTION PLANNING ACTIVITIES 51 9. Conduct a site visit (performance recommended). II 1 Complete the Site Visit Checklist (Table 4.8). II 2 Examine site access and layout, including parking, material delivery points and material lay-down and storage. II 3 Identify locations and availability of matieral and personnel lifts, elevators, cranes, scaffolding and forklifts. II 4 Create a plan for installing temporary power (when applicable). II 5 Verify existing conditions and compare them to the conditions shown on the plans and described in the specifications. 10. Compare estimated (bid) work activities and materials to planned performance. II 1 Compare the estimator’s concept of how to perform the work to typical field operations and document differences. II 2 Discuss unclear methods or discrepancies with the estimator. II 3 Determine the cost difference between the as-bid and planned performance of the work. 11. Identify value engineering and prefabrication opportunities and how to simplify the work. Review value engineering (VE) or prefabrication opportunities that II 1 were identified in the turnover meeting between the estimator and project manager. II 2 Review procedures for formally requesting VE consideration if required. II 3 Search for and identify additional VE and prefabrication items. II 4 Identify additional ways to simplify the work. II 5 Price out the cost difference between the as-bid and VE options. 10. Compare estimated (bid) work activities and materials to planned performance. II 1 Take off the materials, equipment and systems in the order they will be constructed. Code each plan sheet as you take it off so that you can return to it II 2 later and immediately identify the quantity of various materials shown on the sheet. II 3 The final quantities should be identified by the units in which they will be purchased. II 4 All assumptions should be noted on the quantity takeoff sheets. II 5 Be sure the quantities that are estimated include a waste factor. II 6 Compare the construction takeoff to the bid takeoff to identify significant differences or discrepancies. Project Number: ____________________________________________________________________________________ Table 4.5: Scope and Contract Review Checklist (continued)
  • 11. ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL 52 Project Number: _____________________________________________________________________________________ Project Name: _______________________________________________________________________________________ Location:____________________________________________________________________________________________ Project Manager:_____________________________________________________________________________________ Completed Date Completed ITEM II Check for ambiguous clauses and seek clarification. II Check for one-sided clauses that favor the other party. II Cross-reference clauses to understand the whole meaning of clauses. II Identify discrepancies and conflicting clauses and seek clarification. II Check for agreement between plans and specifications, and seek clarification if there is any discrepancy. II Identify any “killer clauses” that assign full responsibility for everything to the electrical contractor. II Determine whether the contract clearly favors the other party (owner/CM/ GC), and seek more equitable contract terms. II Review the Indemnification Clause, and ensure your insurance converage can sufficiently cover the risk. II Evaluate the Coordination Clause to determine each party’s responsibility to coordinate the work. II Determine your rights and responsibilities if the sequence of work is changed or if out-of-sequence work impacts the project. II Carefully review all time-sensitive clauses that cover commencement, completion, milestones, accelerations, delays and progress. II Review and understand your rights to receive damages if the schedule is accelerated or delayed by other parties. II Determine whether there is a no-damages-for-delay clause, and review your rights and responsibilities. II Review and understand the clause that describes waivers. II Review the concealed conditions clause, and identify the circumstances that will entitle you to compensation. II Review the Force Majeure clause, and identify the circumstances that will entitle you to a time extension. II Evaluate clauses that identify procedures for seeking change orders. II Evaluate clauses that identify the compensation for extra work. II Identify payment provisions, especially a “pay when paid” clause and a “pay if paid” clause. Table 4.6: Contract Review Items1 (page 17) 1 Detailed contract review guidelines can be found in ELECTRI International (2000) Fundamentals of Contract Risk Management for Electrical Contractors.
  • 12. PRE-CONSTRUCTION PLANNING ACTIVITIES 53 SCOPE AND SCHEDULE REVIEW ITEMS Completed Completed By Date Completed Item II Contract II Plans II Specifications II Cost estimate and bid breakdown II Referenced/applicable codes or regulations II Quality requirements II Safety requirements II Special conditions II Addendums II Temporary power and lighting requirements II Owner/CM/GC-furnished materials II Vendor pricing and qualifications II Owner/CM/GC schedule II Internal schedule submitted with bid II Work sequence and work by others II Required coordination with other trades II Material and equipment deliveries II Anticipated weather problems or holidays II Required labor II Labor rates and potential increases II Crew mix II Administrative procedures (submittals/RFIs/changes) II Other: II Other: II Other: Project Number: _____________________________________________________________________________________ Project Name: _______________________________________________________________________________________ Location:____________________________________________________________________________________________ Estimator:___________________________________________________________________________________________ Project Manager:_____________________________________________________________________________________ Table 4.7: Scope and Schedule Review Items (pages 18, 39)
  • 13. ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL 54 Project Number: ____________________________________________________________________________________ Table 4.7: Scope and Schedule Review Items (continued) SCOPE AND SCHEDULE REVIEW ITEMS Completed Who furnishes? Who installs? What to review in the Plans and Specifications II Access doors II Asbestos abatement II Carpentry (miscellaneous) II Clean up II Conduit (sizes and quantities) II Crane II Cutting and patching II Demolition and removal II Electric motors II Electric starters II Excavation and backfill II Fire alarm wiring II Fire alarm devices II Hand dryers II Hoists for personnel II Hoists for materials II Interior layout II Painting II Panels II Scaffolding II Site access II Site surveying II Temporary power II Underground utilities II Wire (and/or pipe and wire) II Other: II Other: II Other:
  • 14. PRE-CONSTRUCTION PLANNING ACTIVITIES 55 SITE VISIT REVIEW ITEMS Completed Item to Review Notes II Access into and out of the site II Circulation throughout the site II Material and equipment delivery routes II Material storage and staging locations II Office trailer or office space II Temporary power and lighting locations II Existing underground utilities location II Existing above ground utility locations II Location of existing interior systems II Progress of the demolition II Progress of the site work II Progress of the site layout/surveying II Asbestos abatement has been completed II Work completed to date II Presence/location of the crane II Presence/location of the personnel lift II Presence/location of the materials lift II Potential coordination with others II Anticipated weather problems II Housekeeping conditions II Special site considerations II Safety issues or concerns II Other: II Other: II Other: Project Number: _____________________________________________________________________________________ Project Name: _______________________________________________________________________________________ Location:____________________________________________________________________________________________ Project Manager:_____________________________________________________________________________________ Scope Review Completion Date: _______________________________________________________________________ Table 4.8: Site Visit Checklist (page 19)
  • 15. ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL 56 Project Number: _____________________________________________________________________________________ Project Name: _______________________________________________________________________________________ Location:____________________________________________________________________________________________ Project Manager:_____________________________________________________________________________________ Start Date: __________________________________________________________________________________________ ADMINISTRATIVE SETUP CHECKLIST FOR PRE-CONSTRUCTION PLANNING ACT. COMPLETION ITEM DATE NO. SUB-ACTIVITIES 13. Set up project files and create contact list. II 1 Use the File System Checklist (Table 4.11) to creat paper files. II 2 Create a contact sheet that lists all team members and their company contact information. 14. Set up computerized tracking and control system (forms, database, schedule and tracking). II 1 Verify the accounting department has assigned a project number and entered intial information in the cost control center. II 2 Use the File System Checklist (Table 4.11) to creat computer files. II 3 If a separate project management software system is used, set up the project in the system. II 4 If a separate project management software system is used, set up the project in the system. 15. Initiate a change management system. II 1 Review the contract to identify required change order, field change, and time-and-materials procedures. II 2 Review your company’s standard procedures for initiating, requesting, and processing change orders and field changes. Develop a log with sequential numbering to track all changes, II 3 including change orders, field changes and time-and-materials requests (Table 4.12). 16. Initiate a request for information (RFI) tracking and processing system. II 1 Develop a log with sequential numbering to track all requests for information (RFIs) (Table 4.13). II 2 Determine whether RFIs will be submitted by e-mail, fax or postal mail. II 3 Review your company’s standard procedures for processing RFIs, and use a company standard form for submitting RFIs. II 4 Ensure each RFI also identifies a proposed solution. Table 4.9: Administrative Setup Checklist (page 21)
  • 16. PRE-CONSTRUCTION PLANNING ACTIVITIES 57 17. Initiate a submittal tracking and processing system. II 1 Develop a log with sequential numbering to track all submittals, including those of vendors and subcontractors (Table 4.14). II 2 Review your company’s standard procedures for processing submittals, and use a company standard form for submissions. Verify that each submittal processing form identifies a respond-no- II 3 later-than date, which is associated with timely ordering and delivery of materials and equipment. 18. Develop a “Labor Requirements/Expectation” letter (for background check, etc.) (performance recommended) II For projects that have special requirements such as drug testing, 1 background check or special safety training, develop an “expectations” letter that must be reviewed and signed by crew members (see Figure 4.8). For projects that will require hiring workers from the union hall, II 2 develop an “expectations” letter that must be reviewed and signed by crew members. Project Number: ____________________________________________________________________________________ Table 4.9: Administrative Setup Checklist (continued)
  • 17. ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL 58 Project Number: _____________________________________________________________________________________ Project Name: _______________________________________________________________________________________ Location:____________________________________________________________________________________________ Project Manager:_____________________________________________________________________________________ Table 4.10: File System Checklist (page 21) SCOPE AND SCHEDULE REVIEW ITEMS Completed File Number File Description II Project Information and Contacts II Cost Estimate and Bid Submission II Contract Agreement II Contract Documents II Budget and Pay Requests II Purchase Orders II Subcontracts II Materials Folder (Fixtures, Switchgear, Fire Alarm, Low Voltage) II Requests for Information II Submittals II Change Orders—Pending II Change Orders—Approved II Correspondence II Meeting Minutes II Daily/Weekly Field Report II Progress Reports II Other: II Other: II Other:
  • 18. PRE-CONSTRUCTION PLANNING ACTIVITIES 59 COMPANY NAME COMPANY ADDRESS CHANGE ORDER PROPOSAL PROJECT NUMBER: ______________________________ PROJECT NAME: ____________________________________________________________________________________ DATE: ___________________________ TO:_____________________________________________ FROM: ___________________________________________ ________________________________________________ _________________________________________________ ________________________________________________ _________________________________________________ ________________________________________________ _________________________________________________ DESCRIPTION OF CHANGED WORK: COST OF THE CHANGED WORK: Description Labor Materials Equipment Other Subcontracts Total ____________________________________________________________________________________________________ ____________________________________________________________________________________________________ ____________________________________________________________________________________________________ ____________________________________________________________________________________________________ Labor Burden ___________% Bond Premium __________% Liability Insurance ________% Subtotal ___________________________________________ Overhead ________________ Profit ____________________ TOTAL _____________________________________________ TIME EXTENSION ______________ calendar days APPROVED BY: _________________________________________________________DATE: ________________________ Figure 4.2: Change Order Proposal (pages 22, 39)
  • 19. ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL 60 PROJECT NUMBER: _____________________________________________________________________________________________ PROJECT NAME: _______________________________________________________________________________________________ FIELD SUPERVISOR: ____________________________________________________________________________________________ WORK PERFORMED BY (EMPLOYEE NAME): _____________________________________________________________________ DATE: _________________________________________________________________________________________________________ WORK AUTHORIZED BY: _______________________________________________________________________________________ TITLE: _________________________________________________________________________________________________________ FIELD CHANGE FORM SCOPE OF WORK: LABOR: EQUIPMENT/TOOLS: EMPLOYEE HOURS WAGE TOTAL EQUIPMENT/TOOL TYPE COST REG OT DT RATE SUBTOTAL SUBTOTAL _______ % MARKUP _______ % MARKUP TOTAL TOTAL MATERIALS: SUBCONTRACTORS: MATERIAL TYPE UNITS QTY UNIT TOTAL COMPANY NAME COST COST SUBTOTAL _______ % MARKUP TOTAL SUMMARY OF COSTS: TOTAL LABOR TOTAL MATERIALS SUBTOTAL TOTAL EQUIPMENT/TOOLS ______ % MARKUP TOTAL SUBCONTRACTS TOTAL TOTAL COST Figure 4.3: Field Change Form (page 22)
  • 20. PRE-CONSTRUCTION PLANNING ACTIVITIES 61 Table 4.11: Change Order Log (page 22) ProjectNumber:___________________________________________________________________________________________________________________ ProjectName:____________________________________________________________________________________________________________________ Location:__________________________________________________________________________________________________________________________ ProjectManager:__________________________________________________________________________________________________________________ CHANGEORDERLOG C.O.DATEWHOWHOASSOCIATEDC.O. NUMBERSUBMITTED DESCRIPTIONOFCHANGE INITIATEDAUTHORIZEDRFINUMBERAMOUNT STATUS
  • 21. ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL 62 Table 4.12: Request for Information Log (pages 22, 41) ProjectNumber:___________________________________________________________________________________________________________________ ProjectName:____________________________________________________________________________________________________________________ Location:__________________________________________________________________________________________________________________________ ProjectManager:__________________________________________________________________________________________________________________ REQUESTFORINFORMATIONLOG RFIDATESUBMITTEDDATEOFWHO NUMBERSUBMITTED DESCRIPTIONOFINFORMATIONNEEDED TORESPONSEINITIATED STATUS
  • 22. PRE-CONSTRUCTION PLANNING ACTIVITIES 63 COMPANY NAME COMPANY ADDRESS REQUEST FOR INFORMATION PROJECT NUMBER: PROJECT NAME: DATE: RFI NUMBER: TO: FROM: METHOD SENT: II FAX II MAIL II E-MAIL DESCRIPTION OF REQUEST: ADDITIONAL SUPPORT DOCUMENTS: II ARE II ARE NOT ATTACHED. DATE REQUIRED: DATE RESPONSE RECEIVED: RESPONSE FROM: RESPONSE: Figure 4.5: Request for Information Form (pages 22, 38)
  • 23. PRE-CONSTRUCTION PLANNING ACTIVITIES 64 Table 4.13: Submittal Log (pages 24, 28, 38, 39) ProjectNumber:___________________________________________________________________________________________________________________ ProjectName:____________________________________________________________________________________________________________________ Location:__________________________________________________________________________________________________________________________ ProjectManager:__________________________________________________________________________________________________________________ SUBMITTALLOG CSIDATEREVISIONDATETODATEDATETOORDERDELIVERY SECTIONSUBMITTEDNUMBER SUBMITTEDITEMSUPPLIER ARCH/ENGAPPROVEDSUPPLIERDATEDATE
  • 24. PRE-CONSTRUCTION PLANNING ACTIVITIES 65 COMPANY NAME COMPANY ADDRESS SUBMITTAL TRANSMITTAL FORM PROJECT NUMBER: ______________________________ DATE:___________________________________________ PROJECT NAME: ____________________________________________________________________________________ CSI SECTION: ___________________________ TO: FROM: FOR FOR FOR SUBMITTAL YOUR FOR YOUR YOUR INFORMATION DATE QTY DESCRIPTION REVIEW APPROVAL FILES ONLY REQ’D Please return __________ copies. Additional Comments:________________________________________________________________________________ ____________________________________________________________________________________________________ ____________________________________________________________________________________________________ ____________________________________________________________________________________________________ Signature: ______________________________________________________________Date: _________________________ Figure 4.7: Submittal Transmittal Form (pages 25, 39)
  • 25. ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL 66 COMPANY NAME COMPANY ADDRESS COMPANY PHONE NUMBER NAME OF NEW EMPLOYEE: __________________________________________________________________________ PROJECT NUMBER: _________________________________________________________________________________ PROJECT NAME: ____________________________________________________________________________________ DATE OF EMPLOYMENT: ____________________________________________________________________________ TODAY’S DATE: _____________________________________________________________________________________ SUBJECT: Requirements and Expectations of Personnel Employed on Project Number _______________________ The purpose of this letter is to notify you of special requirements and expectations of all personnel who will work on Project Number ____________________, entitled __________________________________. The following requirements and expectations must be met as a necessary condition of employment: 1. This project requires weekly random drug testing, which will be conducted by a private company employed by the customer. Any employee who fails a drug test or refuses to submit to a random drug test will be immediate- ly dismissed from employment. 2. This project requires a complete background check and the use of a security badge at all times. Employees who fail to exhibit their security badge or who arrive at the jobsite without their badge will be removed from the premises immediately. 3. Entry into certain parts of the facility will require an escort appointed by the customer. Requests for escorts must be submitted 24 hours in advance. 4. The work hours for this project are Monday through Friday from 7:00 AM to 3:00 PM. 5. No privately owned vehicles or company vehicles will be permitted into the secure work area. All employees must arrive at the security gate each morning no later than 6:45 AM to board a bus that will take employees to the secure work area. All employees must be at the pickup point each afternoon at 3:15 PM to board the bus and be escorted out of the secure area. Late employees will not be permitted into the secure area. 6. Employees may be monitored by closed-circuit television throughout the day. 7. Smoking will not be permitted inside the secure work area. Please acknowledge your acceptance of the requirements and expectations of this project by signing and dating below. I understand and accept the above terms of employment. ______________________________________________________________________ __________________________ NAME DATE ______________________________________________________________________ __________________________ WITNESS DATE Figure 4.8: Requirements and Expectations Letter (page 25)
  • 26. PRE-CONSTRUCTION PLANNING ACTIVITIES 67 Project Number: _____________________________________________________________________________________ Project Name: _______________________________________________________________________________________ Location:____________________________________________________________________________________________ Project Manager:_____________________________________________________________________________________ Start Date: __________________________________________________________________________________________ BUYOUT PROCESS CHECKLIST FOR PRE-CONSTRUCTION PLANNING ACT. COMPLETION ITEM DATE NO. SUB-ACTIVITIES 19. Request and/or review subcontractor/supplier/vendor prices and qualifications. II 1 Request subcontractor/supplier/vendor pricing if it was not requested or received during the bidding stage. II 2 Compare actual subcontractor/supplier/vendor scope of work with the scope identified in the subcontractor/supplier/vendor bid submission. II 3 Evaluate the subcontractor/supplier/vendor qualifications. II 4 Compare priding and qualifications among the subcontractors/ suppliers/vendors. 20. Negotiate pricing and contract conditions and select subcontractors/suppliers/vendors. II 1 Discuss potential cost savings with potential subcontractors/ suppliers/vendors. II 2 Review the contract or purchase order terms and conditions with potential subcontractors/suppliers/vendors prior to award. II 3 Select all successful subcontractors/suppliers/vendors, and issue a letter of intent (if necessary). 21. Develop and issue purchase orders and contracts for materials and equipment. II 1 Develop the purchase orders or contracts for subcontractors/ suppliers/vendors. II 2 Process and issue the purchase orders or subcontracts. 22. Order long-lead-time materials and equipment. II 1 Compare the sequence, schedule and materials/equipment to identify long-lead-time items. Negotiate and issue purchase orders and subcontracts for long-lead II 2 time items before negotiating standard purchase orders and subcontracts. II 3 Issue a letter of intent or purchase order immediately to release long-lead-time items for order and delivery. Table 4.14: Buyout Process Checklist (page 26)
  • 27. ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL 68 Project Number: ____________________________________________________________________________________ Table 4.14: Buyout Process Checklist (continued) 23. Request submittals, cut sheets and shop drawings. Upon issuing the contract document, the subcontractor/supplier/ II 1 vendor should be requested to assemble and submit samples, cut sheets or shop drawings. II 2 Identify a deadline by which the submittals, cut sheets, and shop drawings must be submitted to the electrical contractor. 24. Develop and process log and book of submittals, cut sheets and shop drawings. Develop a log, with sequential numbering, to track all submittals, II 1 including those of vendors and subcontractors (see also Activity 17 and Table 4.13). II 2 Assemble two or more binders of all draft and approved submittals. II 3 Submit and track required submittal items.
  • 28. PRE-CONSTRUCTION PLANNING ACTIVITIES 69 Table 4.15: Subcontractor/Supplier/Vendor Comparison Spreadsheet (page 26) ProjectNumber:___________________________________________________________________________________________________________________ ProjectName:____________________________________________________________________________________________________________________ Location:__________________________________________________________________________________________________________________________ ProjectManager:__________________________________________________________________________________________________________________ SUBCONTRACTOR/SUPPLIER/VENDORBIDANALYSIS ITEMTYPE___________________________________________VENDORS REVIEWITEMS:BUDGETVENDORAVENDORBVENDORCVENDORD Wastheitembidperplansandspecs?[Yes/No] Wastheitembidperthescopeofwork?[Yes/No] Aretheworkersunionornon-union? Howlongwillittaketoorderanddelivertheitem? Listanyexclusions. Wastaxincludedinthebidprice?[Yes/No] Didthevendoracknowledgealladdenda?[Yes/No] Basebidprice Listanyalternatepricingprovided. Listadjustedbidpriceifalternatesaccepted.
  • 29. ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL 70 COMPANY NAME COMPANY ADDRESS COMPANY PHONE NUMBER Subcontractor Representative Subcontractor Company Name Subcontractor Company Address Subcontractor Phone Number DATE: December 1, 2005 SUBJECT: Letter of Intent to Award a Contract Dear Subcontractor Representative: You have been selected as the successful bidder on Project Number _______________________, entitled _________________________________________________________. Per our telephone conversation, we are in the process of developing a contract for the scope of work identified in your bid submission. The contract amount will be $1,000,000. This purpose of this letter is to notify you of our intent to award a contract. You can expect to receive the con- tract no later than _____________, 20____. You are authorized to proceed with the work identified in your bid submission. Please feel free to contact me at (222) 110-0000. Sincerely, Electrical Contractor Company Officer Title Figure 4.9: Letter of Intent (page 27)
  • 30. PRE-CONSTRUCTION PLANNING ACTIVITIES 71 COMPANY NAME COMPANY ADDRESS PURCHASE ORDER FORM DATE: P.O. NUMBER: PROJECT NUMBER: PROJECT NAME: TO: SHIP TO: (Home office or jobsite address) SHIP VIA (jobsite) F.O.B. REQUIRED SHIP DATE: QUANTITY DESCRIPTION OF ITEM(S) COST NOTE: MATERIAL SAFETY DATA SHEETS ARE REQUIRED WITH ALL SHIPMENTS SHIPPING INSTRUCTIONS: ADDITIONAL REQUIREMENTS: 1. Submit _____ copies of shop drawings/details/performance data for review/approval 2. Submit _____ copies of OandM manuals or _____ copies of wiring diagrams for review/approval NAME: _________________________________________ NAME:____________________________________________ SIGNATURE: ____________________________________ SIGNATURE: _______________________________________ DATE: __________________________________________ DATE:_____________________________________________ Figure 4.10: Purchase Order Form (page 27)
  • 31. ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL 72 Project Number: _____________________________________________________________________________________ Project Name: _______________________________________________________________________________________ Location:____________________________________________________________________________________________ Project Manager:_____________________________________________________________________________________ Start Date: __________________________________________________________________________________________ MATERIAL HANDLING PROCESS CHECKLIST FOR PRE-CONSTRUCTION PLANNING ACT. COMPLETION ITEM DATE NO. SUB-ACTIVITIES 25. Develop material delivery and handling plan. II 1 Review the “Material Delivery/Storage and Site Logistics Best Practices” (see Table 4.18). II 2 Establish and maintain a file of delivery receipts and packing slips. II 3 Establish a material and equipment delivery and storage log II 4 Create a material and equipment delivery schedule. II 5 Establish standard procedures for receiving, handling and storage of materials and equipment. 26. Develop material storage and staging plan. II 1 Complete the site logistics review checklist (Table 4.20). II 2 Review the “Material Delivery/Storage and Site Logistics Best Practices” (see Table 4.18). II 3 Develop a storage site layout that identifies where the materials and equipment are stored. Table 4.16: Material Handling Planning Process Checklist (page 29)
  • 32. PRE-CONSTRUCTION PLANNING ACTIVITIES 73 Project Number: _____________________________________________________________________________________ Project Name: _______________________________________________________________________________________ Location:____________________________________________________________________________________________ Project Manager:_____________________________________________________________________________________ Table 4.17: Material Delivery/Storage and Site Logistics Best Practices (page 29) MATERIAL DELIVERY/STORAGE AND SITE LOGISTICS BEST PRACTICES Best Practice BEST PRACTICE DESCRIPTION Number 1 Assign one person the responsibility of managing material and equipment delivery, handling storage and staging. 2 Establish a standard unloading crew that consists of laborers or apprentices. 3 Establish standard procedures for receiving, handling and storing materials, and strictly enforce the standard. 4 Develop a storage site layout that identifies where the materials and equipment are stored, and annotate the location on the material and equipment delivery and storage log. 5 Develop a storage site identification system that provides a method to document and track the location of all materials that have been delivered to the jobsite. 6 Establish storage space for each major material item or group (pipe, wire, boxes, etc.). 7 Sort and store the materials as soon as it is delivered to the site. 8 Allow storage space for waste or excess materials, and remove them as soon as possible. 9 Ensure the material and equipment is adequately secured and protected from the elements. 10 Make sure the materials manager is notified of pending deliveries. 11 Return all damaged, excess or incorrect materials to the vendor immediately in order to keep the site free from clutter. 12 Arrange to have materials delivered just before you need them so that storage and handling is kept to a minimum. 13 If materials are ordered in bulk, ask the vendor to store the materials at their office until you need them on the jobsite (also consider paying extra for this option). 14 Consider using a material consignment trailer, where the vendor inventories the trailer each week, restocks it and only charges you for the materials you use. 15 Try to place materials/equipment at the location where they will be used to improve access to the materials/equipment and minimize handling. 16 Arrange to have materials packaged for efficient unloading, handling and installation. 17 Determine ahead of time what equipment will be needed to unload and handle material deliveries. 18 Evaluate the capacity of material lifts, freight elevators and cranes to ensure they can safely move the materials and equipment. 19 Locate your toilet facilities as close to the work areas as possible. 20 Locate your break facilities and trash containers as close to the work areas as possible. 21 Develop a map of facility locations, and distribute it to workers and suppliers/vendors.
  • 33. ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL 74 Table 4.18: Material and Equipment Delivery and Storage Log (page 25) ProjectNumber:___________________________________________________________________________________________________________________ ProjectName:____________________________________________________________________________________________________________________ Location:__________________________________________________________________________________________________________________________ ProjectManager:__________________________________________________________________________________________________________________ MATERIALANDEQUIPMENTDELIVERYANDSTORAGELOG DATEP.O.RECEIVEDSTORAGEDAMAGED RECEIVEDNUMBER DESCRIPTIONOFITEMRECEIVEDQUANTITY BYLOCATIONITEMS NOTES
  • 34. PRE-CONSTRUCTION PLANNING ACTIVITIES 75 Project Number: _____________________________________________________________________________________ Project Name: _______________________________________________________________________________________ Location:____________________________________________________________________________________________ Project Manager:_____________________________________________________________________________________ Table 4.19: Site Logistics Review Items (page 29) SITE LOGISTICS REVIEW CHECKLIST Completed Date Completed ITEM II Review the site layout, and identify placement of materials and facilities to maximize productivity. II Identify site entry and exit points, and plan possible vehicle circulation. II Identify procedures for receiving materials and authorized personnel. II Identify material storage locations. II Determine and document equipment that will be needed to unload and move materials (cranes, fork lift, pallet jacks, etc.). II Evaluate material lifts, freight elevators and cranes to determine whether they can support the size and weight of the material items. II Determine and order special tools associated with material handling (box cutters, bar code readers, computers, etc.). II Establish a “receiving crew” that consists of laborers or apprentices who will unload trucks and move materials. II Select a worker to be in charge of material handling, including inspection and inventory of delivered items. II Establish standard procedures for receiving, logging, handling and stor- ing materials and equipment on the jobsite or at an offsite location. II Establish delivery dates for all materials and develop a schedule of deliveries. II Evaluate purchasing options to ensure materials are ordered to promote efficient unloading, storage and installation. II Evaluate the benefits and pitfalls of prefabrication in terms of delivery, storage, handling and installation. II Review the material delivery, handling, storage and staging best prac- tices (see Table 4.18).
  • 35. ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL 76 Project Number: _____________________________________________________________________________________ Project Name: _______________________________________________________________________________________ Location:____________________________________________________________________________________________ Project Manager:_____________________________________________________________________________________ Start Date: __________________________________________________________________________________________ BUDGET PREPARATION CHECKLIST FOR PRE-CONSTRUCTION PLANNING ACT. COMPLETION ITEM DATE NO. SUB-ACTIVITIES 27. Develop, review or expand the cost code scheme. II 1 Decide whether to use a cost code scheme based upon 16 specifications divisions or 48 specifications divisions. II 2 Review the cost estimate to identify the existing cost code breakdown, and decide whether additional breakdown is necessary. Review the company standard list of cost codes (or use Table 4.21), II 3 and decide which codes will be needed for breaking down the work for tracking and billing. II 4 Add new codes for work items that are not on the standard list. II 5 Assign additional codes to specify the costs associated with material, equipment, labor, subcontractors and other miscellaneous costs. 28. Develop budget by breaking down labor, material, overhead and profit costs. II 1 Create the budget in concert with the labor and materials tracking report. Establish a budget with sufficient line items to identify potential II 2 problems yet enough simplicity to avoid complex, time-consuming data entry. II 3 Verify that labor and materials can and will be reported according to the budget line items. 29. Develop schedule of values II 1 Review the contract to identify the contractual format and process for developing a schedule of values. II 2 Create the schedule of values in concert with the billing process. II 3 Consider “rolling up” the budget so that the schedule of values has the same summary line items but fewer sub-line items. Table 4.20: Budget Preparation Checklist (page 30)
  • 36. PRE-CONSTRUCTION PLANNING ACTIVITIES DIVISION DESCRIPTION 01000 General Requirements/Conditions 01500 Temporary Facilities and Controls 01510 Temporary Utilities 01700 Execution and Closeout Requirements 01710 Mobilization 01730 Cutting and Patching 01740 Cleaning and Waste Management 01780 Closeout Submittals 02200 Site Preparation 02220 Demolition 02500 Utility Services 02580 Electrical and Communications Structures 03400 Precast Concrete 03480 Precast Concrete Specialties 05400 Cold-Formed Metal Framing 05450 Electrical Support Assemblies 10400 Identification Devices 10440 Illuminated Interior Signage 11060 Theater and Stage Equipment 11060 Stage Lighting and Controls 11060 Controls for Theater & Stage Equipment 11130 Audio-Visual Equipment 13100 Lightning Protection Conductors 13110 Cathodic Protection Conductors 13700 Security Access and Surveillance 13800 Building Automation and Control 13850 Detection and Alarms 15900 HVAC Instrumentation and Control 16050 Basic Electrical Materials and Methods 16060 Grounding and Bonding 16070 Hangers and Supports 16075 Electrical Identification 16080 Electrical Testing 16090 Restoration and Repair 16100 Wiring Methods 16120 Conductors and Cables 16130 Raceway and Boxes 16140 Wiring Devices 16150 Wiring Connections 16200 Electrical Power 16210 Electrical Utility Services 16220 Motors and Generators 16230 Generator Assemblies 16240 Battery Equipment 16260 Static Power Converters 16270 Transformers 16280 Power Filters and Conditioners DIVISION DESCRIPTION 16300 Transmission And Distribution 16310 Transmission and Distribution Accessories 16320 High-Voltage Switching and Protection 16330 Medium-Voltage Switching and Protection 16340 Medium-Voltage Switching and Protection Assemblies 16360 Unit Substations 16400 Low-Voltage Distribution 16410 Enclosed Switches and Circuit Breakers 16420 Enclosed Controllers 16430 Low-Voltage Switchgear 16440 Switchboards, Panelboards, and Control Centers 16450 Enclosed Bus Assemblies 16460 Low-Voltage Transformers 16470 Power Distribution Units 16490 Components and Accessories 16500 Lighting 16510 Interior Luminaires 16520 Exterior Luminaires 16530 Emergency Lighting 16540 Classified Location Lighting 16550 Special-Purpose Lighting 16560 Signal Lighting 16570 Dimming Control 16580 Lighting Accessories 16590 Lighting Restoration and Repair 16700 Communications 16710 Communications Circuits 16720 Telephone and Intercommunication Equipment 16740 Communication and Data Processing Equipment 16770 Cable Transmission and Reception Equipment 16780 Broadcast Transmission and Reception Equipment 16790 Microwave Transmission and Reception Equipment 16800 Sound and Video 16810 Sound and Video Circuits 16820 Sound Reinforcement 16830 Broadcast Studio Audio Equipment 16840 Broadcast Studio Video Equipment 16850 Television Equipment 16880 Multimedia Equipment 77 Table 4.21: Cost Code Scheme Based on Masterformat™ 1995 (16 Divisions) (page 30)
  • 37. ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL 78 ProjectNumber:___________________________________________________________________________________________________________________ ProjectName:____________________________________________________________________________________________________________________ Location:__________________________________________________________________________________________________________________________ ProjectManager:__________________________________________________________________________________________________________________ CHANGEORDERLOG CSIOH&P DIVISION DESCRIPTIONLABORMATERIALSEQUIPMENTSUBCONTRACTS (15%) TOTAL Table 4.22: Budget Breakdown and Tracking Spreadsheet (pages 30, 36, 40)
  • 38. PRE-CONSTRUCTION PLANNING ACTIVITIES 79 ProjectNumber:___________________________________________________________________________________________________________________ ProjectName:____________________________________________________________________________________________________________________ Location:__________________________________________________________________________________________________________________________ ProjectManager:__________________________________________________________________________________________________________________ SCHEDULEOFVALUES (A)(C)(D)(E)(F)=(D+E)(G)=(F/C)(H)=(C-F) LINE (B) CONTRACTPREVIOUSLYCOMPLETEDCOMPLETED%BALANCE (I) ITEM DESCRIPTION VALUECOMPLETEDTHISPERIODTODATECOMPLETETOFINISH RETAINAGE Table 4.23: Company Schedule of Values (pages 31, 40)
  • 39. ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL 80 Project Number: _____________________________________________________________________________________ Project Name: _______________________________________________________________________________________ Location:____________________________________________________________________________________________ Project Manager:_____________________________________________________________________________________ Start Date: __________________________________________________________________________________________ LAYOUT AND SEQUENCING CHECKLIST FOR PRE-CONSTRUCTION PLANNING ACT. COMPLETION ITEM DATE NO. SUB-ACTIVITIES 30. Develop installation sequence and layout drawings. II 1 Organize the project by areas, floors or systems II 2 Allocate sufficient time to mentally think through the sequencing of all work processes from start through completion. II 3 Determine whether to create sequence and layout drawings by hand (marked-up drawings) or by creating new CAD drawings. Create daily installation drawings at least one day prior to the date II 4 when the work needs to be performed so that the drawings can be distributed each morning to foremen and field crews. II 5 Review the sequence daily or weekly to ensure the project is progressing as expected. 31. Develop field instructions, including panel, pull or conduit schedules. Review the sequence and installation process to identify any II 1 additional information that might minimize questions and improve productivity. Create the panel, pull or conduit schedules in conjunction with the II 2 installation drawings so that they can be distributed as a package to the foremen or field crews. II 3 When repetitive work is scheduled on a project, develop field instructions and drawings 32. Develop prefabrication drawings for field use (when applicable). For systems that are partially or completely prefabricated in a II 1 prefabrication shop, develop drawings that show how the prefabricated parts should be assembled and installed in the field. For systems prefabricated in a shop, ensure the prefabricated parts II 2 are clearly labeled and that these labels correspond to an assembly and installation scheme identified on the drawings. If on-site prefabrication is scheduled, the drawings should identify II 3 the step-by-step process of how each piece is assembled into the prefabricated system. II 4 If on-site prefabrication is scheduled, separate drawings should also be created to identify how the prefabricated parts should be installed. II 5 Distribute the prefabrication drawings to the foremen or field crews that will perform the work. Table 4.24: Layout and Sequencing Planning Checklist (page 32)
  • 40. PRE-CONSTRUCTION PLANNING ACTIVITIES 81 Project Number: _____________________________________________________________________________________ Project Name: _______________________________________________________________________________________ Location:____________________________________________________________________________________________ Project Manager:_____________________________________________________________________________________ Start Date: __________________________________________________________________________________________ SCHEDULE DEVELOPMENT CHECKLIST FOR PRE-CONSTRUCTION PLANNING ACT. COMPLETION ITEM DATE NO. SUB-ACTIVITIES 33. Review customer’s (general contractor’s) schedule and timeline. II 1 Complete the “Customer’s Schedule Review Items” checklist (see Table 4.26) II 2 Initiate or attend a customer schedule review meeting to identify any special requirements and clarify any questions. 34. Identify work that impacts electrical activities. II 1 While reviewing the overall construction schedule, annotate work that must be coordinated with other trades. II 2 While reviewing the overall construction schedule, annotate potential conflicts that will require coordination. II 3 Develop and submit RFIs to resolve open questions about equipment wiring or conflicts among systems. Request an initial (and a recurring) coordination meeting to identify II 4 and resolve schedule questions and conflicts before installation begins.. 35. Review the work sequence and long-lead-time material/equipment delivery dates. II 1 Develop a rough draft of the electrical schedule from the sequence and installation plan. II 2 Verify the ordering and delivery dates of long-lead-time materials and equipment. Perform a three-way coordination between the sequencing/ II 3 installation plan, material/equipment delivery plan and the draft draft electrical schedule. II 4 Modify the draft schedule and sequencing/installation plan to accommodate long-lead-time deliveries. Table 4.25: Schedule Development Planning Checklist (page 34)
  • 41. ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL 82 Project Number: ____________________________________________________________________________________ Table 4.25: Schedule Development Planning Checklist (continued) 36. Coordinate electrical schedule with the customer’s schedule. After coordinating the sequencing/installation plan, material/equip- II 1 ment delivery plan and the draft electrical schedule, coordinate the draft schedule with the customer’s schedule and adjust as necessary. Review the final electrical schedule with the customer, general II 2 contractor, other trade contractors and suppliers to resolve any final conflicts. II 3 Seek approval of the schedule from the customer and general contractor. II 4 Seek integration of the electrical schedule into the customer/general contractor’s overall project schedule. 24. Develop and process log and book of submittals, cut sheets and shop drawings. In addition to the integration of the electrical schedule into the overall II 1 schedule, format the final electrical schedule into an independent bar chart for tracking and control. II 2 Select the type of bar chart to develop and track. II 3 Save the original approved schedule as the baseline so that progress can be tracked and delays can be documented. II 4 Distribute the electrical bar chart schedule to the customer, general contractor, various subcontractors and suppliers.
  • 42. PRE-CONSTRUCTION PLANNING ACTIVITIES 83 Project Number: _____________________________________________________________________________________ Project Name: _______________________________________________________________________________________ Location:____________________________________________________________________________________________ Project Manager:_____________________________________________________________________________________ Table 4.26: Customer’s Schedule Review Items (pages 34, 41) CUSTOMER’S SCHEDULE REVIEW CHECKLIST Completed Item to Review Annotations II Identify the overall project start date: II Identify the electrical work start date: II Identify the overall project completion date: II Identify the electrical work completion date: II List any interim milestones: II Is the project divided into phases? II Yes II No II Identify the start and completion dates for each phase (if applicable): II Does the contract include a liquidated damages clause? II Yes II No II Does the contract include an incentive for early completion? II Yes II No II Can the electrical work be completed in the timeframe identified in the contract documents? II Yes II No II If the schedule must be compressed, create a plan for compressing the schedule and completing the work by the contractual completion date. II Identify unusual scheduling requirements (such as night work, second shift work, after-school work hours, escort required, etc.): II Will the owner furnish any items, such as materials or equipment? II Yes II No II Identify the “deliver no later than” dates that owner-furnished items must be delivered to the jobsite. II Will any portion of the work be installed by the owner’s own workforce or a separate contract? (example: automated shelving systems) II Yes II No II Identify the “install no later than” dates that owner-installed items must be completed. II Identify techniques that will speed up the completion of the work.
  • 43. ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL 84 Project Number: _____________________________________________________________________________________ Table 4.26: Customer’s Schedule Review Items (continued) CUSTOMER’S SCHEDULE REVIEW CHECKLIST Completed Item to Review Annotations II Review the sequencing/installation plan to determine how the electrical work fits into the overall project schedule. II Identify work that has already been completed: II Identify work in progress and percent complete: II Identify non-electrical activities that must be completed before the electrical portion of the work can begin. II Are you aware of any pending changes to the overall project or electrical work? II Yes II No II If yes, describe the pending changes: II Do you anticipate crowded site conditions? II Yes II No II If yes, consider scheduling some of the electrical work during a second shift to improve productivity.
  • 44. PRE-CONSTRUCTION PLANNING ACTIVITIES 85 Project Number: _____________________________________________________________________________________ Project Name: _______________________________________________________________________________________ Location:____________________________________________________________________________________________ Project Manager:_____________________________________________________________________________________ Table 4.27: Schedule Development Best Practices and Rules-of-Thumb (page 35) SCHEDULE DEVELOPMENT BEST PRACTICES AND RULES-OF-THUMB Best Practice BEST PRACTICE/RULE-OF-THUMB DESCRIPTION Number 1 Seek scheduling input from the field superintendent and foremen. They often understand how the work will be accomplished and how the installation method corresponds to the crew size and duration. 2 Develop the first draft schedule using actual durations to determine whether the electrical work can be completed by the contractual completion date. If the schedule must be compressed, build the compression into the second draft schedule. 3 Consider developing a resource-loaded schedule so that the expenditures from the schedule can be compared to the expenditures from the cost report. 4 Compare the estimated work hours for an activity (or work process) to the scheduled duration of that activity (or work process). Then, either adjust the duration based on estimated work hours and expected crew size, or adjust the crew size based on the estimated work hours and allowable duration. 5 Be sure the schedule takes into account the time of year when the work item will be performed and the possible weather that can be expected. Excessive heat, cold, humidity, rain or wind can significantly impact the progress of the work. 6 Understand when major materials and equipment items will be delivered to the jobsite. The schedule may need to be adjusted to accommodate the delivery of those items. 7 Be sure the schedule clearly documents the date when owner-furnished materials and equip- ment must be received. Also, make sure the owner knows when these items are required, and seek their acknowledgement in writing. 8 Review the schedule of other specialty contractors to identify work that will impact the electri- cal schedule. For example, if the air conditioning unit will require a power connection, comple- tion of the connection must occur after the unit has been delivered and installed. Hence, the electrical work must be coordinated with the mechanical work. 9 The electrical schedule should incorporate the work of any electrical subcontractors, such as the fire alarm installer and tester. Review and incorporate your subcontractors’ work into your own schedule and be sure to provide updates if the schedule changes. 10 If crowded conditions or overmanning is expected on a jobsite (due to a small site or an accel- eration of the work), consider scheduling some of the electrical work during a second shift to improve workflow and increase productivity. 11 Once the electrical schedule has been reviewed and approved by the customer/general contrac- tor, document delays and changes to the sequence caused by others. Good documentation can improve your chances of receiving a time extension and financial compensation.
  • 45. ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL 86 Project Number: _____________________________________________________________________________________ Table 4.27: Schedule Development Best Practices and Rules-of-Thumb (continued) SCHEDULE DEVELOPMENT BEST PRACTICES AND RULES-OF-THUMB Best Practice BEST PRACTICE/RULE-OF-THUMB DESCRIPTION Number 12 When developing work activities or elements for the schedule, review the budget, cost codes and installation sequence plan. Create work elements that comprise no more than 5% of the scope of work so that inaccuracy in tracking progress will not have a significant impact on the percent complete. 13 Consider creating a computerized bar chart schedule. Tracking and control will be greatly sim- plified if the updates can be made in a computer system. 14 Consider dividing the schedule into areas or systems, such as first floor, second floor, etc. This will simplify tracking and control, especially on larger projects. 15 If some of the work is repetitive (such as conduit and wire on the first floor, second floor, etc.), consider creating these activities in your computer scheduling software and simply cutting and pasting as many times as the work occurs. The dates and durations can then be modified for each area of work.
  • 46. PRE-CONSTRUCTION PLANNING ACTIVITIES 87 Project Number: _____________________________________________________________________________________ Project Name: _______________________________________________________________________________________ Location:____________________________________________________________________________________________ Project Manager:_____________________________________________________________________________________ Start Date: __________________________________________________________________________________________ TRACKING AND CONTROL CHECKLIST FOR PRE-CONSTRUCTION PLANNING ACT. COMPLETION ITEM DATE NO. SUB-ACTIVITIES 38. Customize the computerized tracking and control system (database/ schedule/etc.) for the current project. II 1 Review the tracking and control best practices (Table 4.31). II 2 Complete the tracking and control tools checklist (Table 4.32). II 3 Select appropriate computerized tracking and control tools for the project. II 4 Modify the tracking and control tools for the project. 39. Develop labor and materials tracking report. II 1 Review the cost estimate and associated budget and cost code scheme. II 2 Match the cost estimate/budget work items to crew assignments so that labor and materials can be tracked easily. II 3 Select the reports to be created and used for monitoring progress. II 4 Develop the selected reports by inputting project data into the reporting system (database or accounting system). Table 4.28: Tracking and Control Planning Checklist (page 36)
  • 47. ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL 88 Project Number: _____________________________________________________________________________________ Project Name: _______________________________________________________________________________________ Location:____________________________________________________________________________________________ Project Manager:_____________________________________________________________________________________ Table 4.29: Tracking and Control Best Practices (page 36) TRACKING AND CONTROL BEST PRACTICES Best Practice BEST PRACTICE/RULE-OF-THUMB DESCRIPTION Number 1 Remember that tracking and control involves a time-cost tradeoff. The more detailed the track- ing and control system is, the more time must be spent on entering data and the greater the overhead costs will be. You must balance detail with simplicity. 2 Be sure to take into account the financial information needs of banks and bonding companies when setting up your control system. 3 If your company keeps track of historic costs, be sure the tracking and control system captures the right data in the proper format so that it can be added to the historic cost database. 4 Match budget/cost control line items with field work items so that labor hours can be easily reported and tracked. 5 Review the daily labor reporting procedures with the field supervisor and foremen. Be sure they understand how to code timecards so that the work performed can be directly associated with line items in the budget and tracking reports. 6 Deviations between actual and estimated costs and work hours should be discussed with the field supervisor each week to identify and correct problems immediately. 7 Seek feedback from the crew members about the causes of poor productivity and cost/labor hours overruns. 8 Work together with crews to improve productivity. Often, management actions or inactions contribute to productivity outcomes. For example, poor instructions can hinder productive work, while speedy responses to questions can help increase productivity. 9 If the crew members complete the work in fewer hours than estimated, provide a reward to thank them for their hard work, such as free lunch or special recognition. 10 Try using incentives regularly to improve productivity. 11 Make sure your data entries are as accurate as possible. Remember that cost reports should provide the project manager with a realistic financial overview of the project. 12 A negative variance between estimated and actual cost and work hours should be addressed through corrective action. One of the main benefits of monthly cost reporting is to identify problems early enough to take corrective action.
  • 48. PRE-CONSTRUCTION PLANNING ACTIVITIES 89 Project Number: _____________________________________________________________________________________ Project Name: _______________________________________________________________________________________ Location:____________________________________________________________________________________________ Project Manager:_____________________________________________________________________________________ Table 4.30: Tracking and Control Tools Checklist (page 36) TRACKING AND CONTROL TOOLS CHECKLIST Completed Date Completed ITEM II Identify the goals of your tracking and control system. Do you want to: a. Monitor profitability? b. Identify variations in costs and work hours? c. Track productivity of the workforce? d. Contribute to your historical costs database? e. Document costs that are beyond the initial scope of work? f. Track changes in cost and work hours? g. Create contractually-mandated cost reports for the customer? h. Evaluate the effectiveness of your management team? i. Conduct risk analyses on future projects of a similar type? II Create a project schedule, and format it so that you can update the progress of all schedule line items (see Activity 37). Match schedule line items to budget line items to facilitate effective tracking. II As an alternative, create a resource-loaded schedule that will permit you to track cost and labor hours as you track schedule progress. II Create a manpower loading chart that identifies your crew size and com- position for each week of the project (see Figure 4.13). II Customize the computerized project management program so that you can use it as a tool to track RFIs, submittals, purchase orders, deliveries and change orders. II Create a progress report to track variances in costs and labor hours. Your progress report should track budgeted line items. II Create a labor productivity report to compare estimated to actual pro- ductivity and identify solutions to problems. Daily time sheets should be coded to match budget line items. II Other: II Other:
  • 49. ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL 90 PROJECT NUMBER: _____________________________________________________________________________________________ PROJECT NAME: _______________________________________________________________________________________________ FIELD SUPERVISOR: ____________________________________________________________________________________________ EMPLOYEE NAME:______________________________________________________________________________________________ PAY PERIOD: FROM __________________________________________ TO: ______________________________________________ Figure 4.31: Daily Labor Time Report (pages 36, 40) DAILY TIME SHEET DAY WORK DESCRIPTION COST CODE HOURS REGULAR OVERTIME DOUBLE TIME MON TOTAL HOURS DAY WORK DESCRIPTION COST CODE HOURS REGULAR OVERTIME DOUBLE TIME TUE TOTAL HOURS DAY WORK DESCRIPTION COST CODE HOURS REGULAR OVERTIME DOUBLE TIME WED TOTAL HOURS DAY WORK DESCRIPTION COST CODE HOURS REGULAR OVERTIME DOUBLE TIME THU TOTAL HOURS
  • 50. PRE-CONSTRUCTION PLANNING ACTIVITIES 91 Figure 4.31: Daily Labor Time Report (continued) DAY WORK DESCRIPTION COST CODE HOURS REGULAR OVERTIME DOUBLE TIME FRI TOTAL HOURS DAY WORK DESCRIPTION COST CODE HOURS REGULAR OVERTIME DOUBLE TIME SAT TOTAL HOURS DAY WORK DESCRIPTION COST CODE HOURS REGULAR OVERTIME DOUBLE TIME SUN TOTAL HOURS
  • 51. ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL 92 ProjectNumber:___________________________________________________________________________________________________________________ ProjectName:____________________________________________________________________________________________________________________ Location:__________________________________________________________________________________________________________________________ ProjectManager:__________________________________________________________________________________________________________________ LABORPRODUCTIVITYTRACKING ESTIMATEDACTUAL CSI DESCRIPTIONUNITSQTYOF HOURS HOURS/TOTALQTYOF HOURS HOURS/TOTALDIVISION UNITSUNITSCOSTUNITSUNITSCOST Table 4.32: Labor Productivity Report (pages 36, 40)
  • 52. PRE-CONSTRUCTION PLANNING ACTIVITIES 93 CONSTRUCTION EXECUTION KICKOFF MEETING AGENDA Agenda Items: 1. Project overview a. Project name b. Location c. Type of work d. Contract cost e. General scope of work 2. Introduce internal team members and any changes in team members since planning meeting. a. Project Manager b. Field Supervisor c. Foremen d. Estimator e. Accounting representative f. Purchasing Agent g. Director of Operations h. Other internal team members 3. Identify external team members and any changes in team members since planning meeting. a. Owner/Customer b. Architect/Engineer c. General Contractor/Construction Manager d. Other Specialty Subcontractors e. Vendors/Suppliers 4. Review the general scope of work. a. Provide an overview of the project scope of work and the electrical scope b. Review major work performed by others 5. Review the meetings schedule. a. Internal office and jobsite progress meetings b. Jobsite safety and coordination meetings c. Project progress and coordination meetings d. Other meetings 6. Review the Request for Information (RFI) Process. a. Standard company RFI procedure b. Contractual language regarding RFIs and the RFI process c. Current outstanding RFIs Project Number: _____________________________________________________________________________________ Project Name: _______________________________________________________________________________________ Meeting Date and Location: ___________________________________________________________________________ Estimator:___________________________________________________________________________________________ Project Manager:_____________________________________________________________________________________ Table 4.33: Construction Execution Kickoff Meeting Agenda (page 38)
  • 53. ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL 94 Agenda Items: 7. Review the change order process. a. Contract language regarding changes and the change order process b. Standard company change order and field change processes c. Documentation of changes, delays, disruptions and disputed work 8. Review the submittal process. a. Contract language regarding submittals and the submittal process b. Standard company submittal processes c. Following up on late submissions and approvals 9. Review the billing process. a. Contract language regarding billing and the payment process b. Standard company billing processes c. Subcontractor/supplier/vendor invoicing and payment d. Following up on late payments or open accounts receivable 10. Review the tracking and control process. a. Labor reporting b. Progress reporting and percent complete c. The progress update timeline d. Standard company progress update procedures 11. Review the schedule and milestones. a. Customer-furnished schedule b. Electrical bar chart schedule c. Work by others that will impact the electrical work d. Important material and equipment delivery dates e. Schedule updating to reflect percent complete 12. Review site logistics and material storage and staging. a. Site access b. Parking c. Material delivery procedures d. Material storage locations e. Trailer locations (if applicable) f. Site cleanup requirements g. Temporary power and lighting requirements 13. Review special safety issues. 14. Review other items specific to this project: ______________________________________________________________________________________________ ______________________________________________________________________________________________ ______________________________________________________________________________________________ Project Number: ____________________________________________________________________________________ Table 4.33: Construction Execution Kickoff Meeting Agenda (continued)
  • 54. PRE-CONSTRUCTION PLANNING ACTIVITIES 95 Project Number: _____________________________________________________________________________________ Project Name: _______________________________________________________________________________________ Location:____________________________________________________________________________________________ Project Manager:_____________________________________________________________________________________ Start Date: __________________________________________________________________________________________ CONSTRUCTION EXECUTION KICKOFF CHECKLIST FOR PRE-CONSTRUCTION PLANNING ACT. COMPLETION ITEM DATE NO. SUB-ACTIVITIES 40. Review meeting schedule. II 1 Review the schedule of weekly internal meetings associated with the project. II 2 Review the schedule of weekly project meetings conducted by the customer or general contractor. II 3 Identify the internal team members that will be responsible for attending the internal and external meetings. 41. Review request for information (RFI) process. II 1 Review the contract for a customer-mandated request for information (RFI) process. II 2 Review the company standard procedure for developing, processing, tracking and closing out a request for information. II 3 Modify the company standard RFI procedure, as necessary, to conform to the contractually-mandated process. 42. Develop prefabrication drawings for field use (when applicable). II 1 Review the contract for a customer-mandated change order (CO) process and field change request process. II 2 Review the company standard change order procedure and field change request/management process. II 3 Discuss the process for documenting changes, delays and disruptions in the work flow and sequence. II 4 Discuss the process for tracking and following up on change order requests and payment for field change directives. 43. Review submittal processing procedures. II 1 Review the contract documents for a customer-mandated submittal processing procedures. II 2 Review the company standard procedure for developing, processing, tracking and receiving approval for project submittals. II 3 Modify the company standard submittal procedure, as necessary, to conform to the contractually-mandated process. Table 4.34: Construction Execution Kickoff Meeting Checklist (page 38)
  • 55. ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL 96 Project Number: ____________________________________________________________________________________ Table 4.34: Construction Execution Kickoff Meeting Checklist (continued) 44. Review billing and invoicing procedures II 1 Review the customer/general contractor’s process and timeline for invoicing, lien waivers and payment. II 2 Review the internal billing cycle established by the accounting department. II 3 If necessary, adjust the internal billing cycle to conform to the customer/general contractor’s invoicing cycle. II 4 Discuss the process for following up with the customer/general contractor on late unpaid invoices. 45. Review project and field reporting and tracking procedures. II 1 Discuss the process for reporting labor hours and submitting timecards to the accounting office. II 2 Discuss the process for reporting progress and percent complete. II 3 Discuss the process for tracking material and equipment costs and purchase orders. II 4 Review and discuss the tracking tools that will be used to monitor progress. II 5 Review the monthly update process. 46. Review electrical and customer schedules. II 1 Review the electrical bar chart schedule. II 2 Review the customer/general contractor’s schedule and/or timeline. II 3 Discuss the process for updating the schedule.
  • 56. 5.1 Introduction to the Planning Assessment Process Chapter 4 of this manual discusses, in detail, the model electrical pre-construction planning process. This research discovered that projects that implemented a planning process similar to the model process tended to perform more successfully. Furthermore, there appeared to be 16 activities that had an especially strong influence on perform- ance—and many of these activities were often over- looked during the planning process. 5.2 Purpose of the Planning Assessment Process Chapter 4 presents a series of instructions and easy-to-use checklists to guide electrical contractors through the pre-construction planning process. The purpose of this chapter is to present a scorecard that can be used to evaluate the effectiveness of the planning that was completed on a project that is about to be executed. The chapter will begin by identifying the 16 activities that had an especially strong influence on performance in order to explain why these activities are weighted more heavily on the planning score- card. Then, the planning effectiveness scorecard will be introduced, which includes all of the activities from the model planning process, and instructions will be provided on how to score the effectiveness of planning on a new project. Finally, a section on “score analysis” will present some rules-of-thumb and benchmark score values for projects that have various characteristics, such as large projects versus small projects, complex projects versus simple proj- ects, and so on. 5.3 Important and Influential Planning Activities It is essential to note that each of the 46 pre- construction planning activities in the Model Electrical Pre-Construction Planning Process is an important part of the planning process. It is also worth noting that not every activity will require a great deal of time to complete. Indeed, many of the activities can be completed in a matter of a few minutes, particularly on smaller projects. The proj- ect manager will need to exercise skill and judg- ment when determining how much time to devote to each activity. Many of the activities are clearly critical to an effective planning process. Such obvious activities as reviewing the plans and specifications, adminis- tratively setting up the project, and issuing purchase orders can directly impact the smooth execution of a project. Overall, 16 “influential activities” were identified through careful research, and these activi- ties are identified in the next section. It is critical that the project manager understand the following: However, 16 of those activities have a particu- larly strong influence on the outcome of a project. 5.3.1 The 16 Influential Planning Activities Sixteen of the pre-construction planning activi- ties were identified as having an especially strong 97 Section 3: Planning Assessment and Best Practices 5. The Planning Assessment Process All of the 46 pre-construction planning activities are important to project success.
  • 57. ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL correlation to a successful project outcome. These activities include the following: I Team Selection and Turnover Activity 2: Hold turnover meeting between estimator and project manager (when applicable). Activity 3: Hold separate turnover meeting between project manager and field supervi- sor. I Scope and Contract Review Activity 7: Field supervisor reviews plans, specifications and schedule. Activity 10: Compare estimated (bid) work activities and materials to planned per- formance. Activity 11: Identify value engineering and pre- fabrication opportunities and how to sim- plify the work. I Administrative Setup Activity 16: Initiate a request for information (RFI) tracking and processing system. Activity 17: Initiate a submittal tracking and processing system. I Buyout Process Activity 23: Request submittals, cut sheets and shop drawings. I Material Handling Plan Activity 25: Develop material delivery and han- dling plan. Activity 26: Develop material storage and stag- ing plan. I Layout and Sequencing Plan Activity 30: Develop installation sequence and layout drawings. Activity 31: Develop field instructions, includ- ing panel, pull or conduit schedules. Activity 32: Develop prefabrication drawings for field use (when applicable). I Schedule Development Activity 36: Coordinate electrical schedule with the customer's schedule. I Construction Execution Kickoff Meeting Activity 43: Review submittal processing pro- cedure. Activity 44: Review billing and invoicing pro- cedures. When performing pre-construction planning, extra care should be taken to include these activi- ties in the planning process. Although it is recom- mended that all of the 46 activities be completed, under extraordinary circumstances, when the plan- ning process must be abbreviated, these 16 activi- ties should be among those that get completed. 5.4 Planning Assessment Process The planning assessment process provides a sim- ple method for evaluating whether each of the 46 pre-construction planning activities has been com- pleted and whether an activity was completed before or after a project was executed. Under ideal circum- stances, all of the planning activities will be complet- ed prior to executing the work. However, ideal cir- cumstances are rare in the construction industry, and often, some of the planning activities must be com- pleted after the project has been executed. The purpose of this section is to introduce the planning effectiveness scorecard and to provide instructions on how to use the scorecard to evaluate the planning that has occurred on a new project. 5.4.1 The Planning Effectiveness Scorecard The planning effectiveness scorecard was devel- oped as a tool to evaluate how closely a project’s actual planning process matches the Model Electrical Pre-Construction Planning Process. The scorecard, which is presented as Table 5.1 (pages 100-101), lists each of the 46 model pre-construc- tion planning activities (Column C). Space is pro- vided in Column D for contractors to identify 98
  • 58. THE PLANNING ASSESSMENT PROCESS whether or not the activity was performed and to assign a “performance score.” The performance score is assigned based on whether an activity was performed or not per- formed and whether it was completed before or after execution using the following scale: Using this scale, a higher summed performance score indicates that more of the pre-construction planning activities were completed before executing the work, which correlates strongly to better project performance. Column E represents the weight assigned to each activity. As mentioned in the previous section, 16 of the activities have a stronger influence on performance, and as a result, these activities are assigned larger weights. To calculate a final score (Column F) for each activity, Column D (Performance Score) is multiplied by Column E (Weight). The planning effectiveness score is the sum of all of the total scores. 5.4.2 Score Analysis Projects that were investigated as part of the research had various character-istics. In particular, four characteristics were analyzed, including proj- ect size, initial uncertainty, bid accuracy and type of construction. 5.4.2.1 Project Size Project Size is generally determined by three values: contract cost at award, original estimated total work hours and estimated peak number of electricians. Furthermore, estimated project dura- tion is also strongly related to a project’s size. 5.4.2.2 Initial Uncertainty of the Project Initial uncertainty of the project is generally determined by three values: perceived level of uncertainty (high, medium or low), percentage of the total design completed at bid and perceived level of complexity (high, medium or low). 5.4.2.3 Bid Accuracy Bid Accuracy is generally determined by two concepts: a perceived accurate cost estimate and perceived accurate estimated work hours. 5.4.2.4 Type of Construction Type of Construction is generally determined by classifying projects as: commercial, industrial, institutional and other. 99 PERFORMANCE SCORE (Column D) 2 = Activity was completed before executing the work 1 = Activity was completed after executing the work 0 = Activity was not completed The trend seems to indicate that larger proj- ects will require a higher planning effective- ness score to have a greater chance for suc- cessful performance. The trend indicates that projects with high levels of initial uncertainty will require a higher planning effectiveness score to have a greater chance for successful performance. The trend indicates that projects with an inaccurate bid will require a higher planning effectiveness score to have a greater chance for successful performance. The trend indicates that industrial and insti- tutional projects require a higher planning effectiveness score to have a greater chance for successful performance.