2. PROJECT INFORMATION
2
• Partnership between the Florida Department of
Transportation (FDOT) and the Miami-Dade
Expressway Authority (MDX)
• Construction Cost: $802 million
o FDOT: $616 million
o MDX: $186 million
• Contract Time: Four Years*
*Contract time does not reflect days added to the contract for
holidays, weather days or special events.
3. SR 836 IMPROVEMENTS I-95 CONCRETE PAVEMENT RECONSTRUCTION I-395 RECONSTRUCTION ENHANCEMENTS
N
PROJECT MAP
3
Consists of three major projects to be constructed
concurrently to minimize impacts to the public;
• I-395 from I-95 to MacArthur Causeway Bridge
• SR 836 from West of NW 17 Ave to Midtown Interchange
• I-95 Pavement Reconstruction from NW 8 St to NW 29 St
4. 4
SR 836 ENHANCEMENTS/DOUBLE-DECKING
N
I-395 Mainline
• Limits: West of NW 17 Avenue to the SR 836/I-95/I-395 Midtown Interchange
• Add capacity to SR 836 and improve flow of traffic
• Double-decked SR 836 section provides a direct connection to/from I-395, PortMiami Tunnel and Miami Beach that bypasses
traffic entering and exiting local roads and I-95
NW17Ave
SR 836 Mainline SR 836 Local/I-95 Access
5. 5
• Reconstructing I-395 from the Midtown Interchange to the MacArthur Causeway Bridge
• Improving capacity and safety by separating local and I-95 ramps from through traffic
• Building a new Signature Bridge over NE 2 Avenue and Biscayne Boulevard
I-395 ENHANCEMENTS
NE 13 St
N
I-395 Mainline
Signature Bridge
7. Existing condition - NE 1 Avenue looking west.
7
Increased vertical clearance
will allow more light into the
areas under the bridge
I-395 ENHANCEMENTS/PROPOSED FEATURES UNDER I-395
2
24
4 6
6
1
1
3
3
5
5
8. 8
Under-deck and other light fixtures
will provide ample lighting.
I-395 ENHANCEMENTS/PROPOSED FEATURES UNDER I-395
TURNING NIGHT INTO DAY
9. 9
I-95 ENHANCEMENTS
N
NW17St
NW29St
• Limits: NW 8 Street to NW 29 Street
• Pavement replacement will enhance rideability
• Extension of auxiliary lane from NW 17 Street to NW 29 Street will improve the flow of traffic on the widened eastbound SR 836
and westbound I-395 ramps to northbound I-95
10. * This schedule does not reflect days added to the contract for
holidays, weather days or special events
CONSTRUCTION
Project is a Design-Build – Plans design underway
Preliminary construction activities are expected to begin in October/November
2018 with major construction anticipated to begin in February/March of 2019
Construction will be done in phases to minimize construction impacts to the public
10
11. UPCOMING ACTIVITIES - SIX MONTH LOOK - AHEAD
11
• Utility relocations
• Surveying and Geotechnical Exploration-Test piles
• Continue to develop roadway and bridge plans
• Construction along I-95 in the median and begin concrete replacement
• Widening SR 836 in preparation for double-decking
• Construction of the I-395 bridge foundations
12. MAINTENANCE OF TRAFFIC (MOT)/HOURS
I-395 SPECIFIC
Mainline Nightly Closures
• 10:00 pm to 5:30 am Sunday thru Thursday
• 1:00 am to 7:00 am Saturday and Sunday
SR 836 SPECIFIC
Mainline Nightly Closures
• 8:00 pm to 5:30 am Sunday thru Thursday
• 8:30 pm to 9:00 am Friday
• 8:30 pm to 11:00 am Saturday
I-95 SPECIFIC
Mainline Nightly Closures
• 9:00 pm to 5:30 am Sunday thru Thursday
RAMPS
• 10:00 pm to 6:30 am Sunday thru Thursday
• 11:00 pm to 7:00 am Friday and Saturday
SPECIAL NOTES:
• Special events will be taken into account when scheduling closures
• Hours noted above are for single lane closures, multi-lane closure will occur later
• Weekend lane closures will be permitted on I-95 from 11 p.m. on Friday to 5:30 a.m. on Monday
• The contract documents allows for weekend closures on certain ramps
13. • Provide drivers with real-time
travel information;
• Encourage motorists to take
alternate routes;
• Clear incidents more quickly,
thereby reducing secondary
incidents; and
• Make work zones safer for
highway workers and motorists.
Smart Work Zone Management
System (SWZMS) - The project will
implement a SWZMS that will utilize
Intelligent Transportation System
(ITS) Devices such as traffic
cameras, data collection devices
and portable message signs to:
TRAFFIC MANAGEMENT SYSTEM
14. 14
COMMUNITY OUTREACH
PROJECT WEBSITE
• www.i-395miami.com
• Sign-up for project alerts/updates
Lane Closure information
Upcoming construction activities
• Calendar of events
OUTREACH OFFICE IN THE OVERTOWN COMMUNITY
• 1035 NW 3 Avenue, Miami, Florida 33136
STAKEHOLDER UPDATE MONTHLY MEETINGS
• Monday, October 15, 2018 at MDX Headquarters
UPCOMING PRESENTATIONS/EVENTS
• Miami-Dade TPO TARC Committee – October 3
• Traffic Incident Management Team – October 3
• Folk Life Friday Event Participation – October 5
• Miami-Dade TPO CTAC Committee – October 10
• City of Miami Commission – October 11
• Miami-Dade TPO FTAC Committee – November 14
• Miami-Dade TPO BPAC Committee – December 11
PUBLIC OUTREACH MEETINGS
• Public open house meetings to be scheduled prior to
major construction beginning in February/March 2019
• Individual stakeholder meetings