1. PROPOSED ROAD IMPROVEMENTS TO
Proposed Road
GAUTENG FREEWAY NETWORK
• In general, freeways will be upgraded to 4 lanes per direction
• Some sections, up to 6 lanes per direction
• Interchanges are improved:
►7 Systems Interchanges (additional lanes, directional ramps)
►21Access Interchanges (Additional bridges, single points, ramp
Additions, lane additions)
• Auxiliary lanes at on- and off-ramps
• Cross road improvements
• Median lighting is provided
9. Project financing
PROJECT FINANCING & IMPLEMENTATION
• User pay principle will be used to finance project
• Open gantry tolling
• Provides a mechanism for accelerated financing of infrastructure
10. TOLL PRINCIPLES
Toll Strategy
• Road user charging implemented worldwide to manage congestion and
promote other modes of transport (public transport)
►Travel demand management measure
►Provides a mechanism for accelerated financing of infrastructure
►Alternative funding mechanisms essential to provide infrastructure
and to stimulate economic growth
►Sanral mandated to implement tolling as mechanism to raise funds
12. Open Road Tolling
OPEN ROAD TOLLING
Electronic Toll Collection = no physical plazas = no delay
13. PROJECT PROGRAMME
• Award of construction contracts: May 2008
• Construction for 2010 phase commences
(2,5 year construction period): May 2008
• Construction substantially completed: May 2010
• Construction completion date: October 2010
• Commencement of toll operations: October 2010
14. IMPLEMENTATION CHALLENGES
N1: WILLIAM NICOL
• Availability of skills
• Availability of materials
• Risks associated with traffic
• Risks regarding labour actions
• Impact of the above on construction
costs
• Impact of high construction costs on
future implementation