SlideShare a Scribd company logo
1 of 9
Sheet1[Project Name]0Gantt ChartSecurity Network
UpgradeTeam BToday's Date:9/5/16Monday(vertical red line)
Jon: Work Breakdown Structure
Level 1: 1, 2, 3, ...
Level 2: 1.1, 1.2, 1.3, ...
Level 3: 1.1.1, 1.1.2, 1.1.3, …
The WBS is automatically entered, but the formulas are
different for different levels.Project Lead:Team B
Jon: Duration (Calendar Days)
Enter the number of calendar days for the given task. Refer to
the Working Days column or use a calendar to determine the
corresponding working days. The duration is from the beginning
of the Start date to the ending of the End Date.
When the duration is calculated, it is calculated as End Date
minus the Start Date plus 1 day, so that a task starting and
ending on the same day has a duration of 1 day.
Jon: Percent Complete
Update the status of this task by entering the percent complete
(between 0% and 100%).
Jon: Working Days
Counts the number of working days using the
NETWORKDAYS() formula, which excludes weekends. When
planning work based upon the number of working days, adjust
the Duration until the desired # of working days is reached.
Jon: Calendar Days Complete
This column is calculated by multiplying the Duration by the
%Complete and rounding down to the nearest integer.
Jon: Calendar Days Remaining
This column is calculated by subtracting the Days Complete
from the Duration.Start Date:9/5/16Monday[42]First Day of
Week
(Mon=2):212/29/1412/30/1412/31/141/1/151/2/151/3/151/4/151/
5/151/6/151/7/151/8/151/9/151/10/151/11/151/12/151/13/151/14
/151/15/151/16/151/17/151/18/151/19/151/20/151/21/151/22/15
1/23/151/24/151/25/151/26/151/27/151/28/151/29/151/30/151/3
1/152/1/152/2/152/3/152/4/152/5/152/6/152/7/152/8/152/9/152/
10/152/11/152/12/152/13/152/14/152/15/152/16/152/17/152/18/
152/19/152/20/152/21/152/22/152/23/152/24/152/25/152/26/152
/27/152/28/153/1/153/2/153/3/153/4/153/5/153/6/153/7/153/8/1
53/9/153/10/153/11/153/12/153/13/153/14/153/15/153/16/153/1
7/153/18/153/19/153/20/153/21/153/22/153/23/153/24/153/25/1
53/26/153/27/153/28/153/29/153/30/153/31/154/1/154/2/154/3/1
54/4/154/5/154/6/154/7/154/8/154/9/154/10/154/11/154/12/154/
13/154/14/154/15/154/16/154/17/154/18/154/19/154/20/154/21/
154/22/154/23/154/24/154/25/154/26/154/27/154/28/154/29/154
/30/155/1/155/2/155/3/155/4/155/5/155/6/155/7/155/8/155/9/15
5/10/155/11/155/12/155/13/155/14/155/15/155/16/155/17/155/1
8/155/19/155/20/155/21/155/22/155/23/155/24/155/25/155/26/1
55/27/155/28/155/29/155/30/155/31/156/1/156/2/156/3/156/4/15
6/5/156/6/156/7/156/8/156/9/156/10/156/11/156/12/156/13/156/
14/156/15/156/16/156/17/156/18/156/19/156/20/156/21/156/22/
156/23/156/24/156/25/156/26/156/27/156/28/156/29/156/30/157
/1/157/2/157/3/157/4/157/5/157/6/157/7/157/8/157/9/157/10/15
7/11/157/12/157/13/157/14/157/15/157/16/157/17/157/18/157/1
9/157/20/157/21/157/22/157/23/157/24/157/25/157/26/157/27/1
57/28/157/29/157/30/157/31/158/1/158/2/158/3/158/4/158/5/158
/6/158/7/158/8/158/9/158/10/158/11/158/12/158/13/158/14/158/
15/158/16/158/17/158/18/158/19/158/20/158/21/158/22/158/23/
15WBSTasksStartEndDuration (Days)% CompleteWorking
DaysDays CompleteDays Remaining05 - Sep - 1606 - Sep -
1607 - Sep - 1608 - Sep - 1609 - Sep - 1610 - Sep - 1611 - Sep -
1612 - Sep - 1613 - Sep - 1614 - Sep - 1615 - Sep - 1616 - Sep -
1617 - Sep - 16Task Lead1Security Network UpgradeTeam
B9/5/169/17/16130%1301312Meet and Create ScheduleTeam
B9/5/169/6/1620%21132Meet and Create Schedule2.1Office
Managers Meeting for
Discussion9/5/169/5/1610%1112.12.2Create and Submit
Security Upgrade9/6/169/6/1610%1012.22.3Approve
schedule9/6/169/6/1610%1012.33Receive New Security
SoftwareTeam B9/7/169/10/16450%4043Receive New Securty
Software3.1Purchase New
Software9/7/169/7/16150%1013.13.2Ensure Hardware is
sufficient9/7/169/7/16150%1013.23.3Purchase
Accessories9/8/169/8/16150%1013.33.4Prepare for Hardwasre
installation9/9/169/10/1622023.44Back Up DataTeam
B9/11/169/13/1630%3034Back Up Data4.1Back Up shared
Drives & Files9/11/169/11/1610%1014.14.2Back Up User
Data9/12/169/12/1610%1014.24.3Ensure Back Up Was
Successful9/13/169/13/1610%1014.35Install and configureTeam
B9/14/169/17/1640%4045Install and configure5.1Set Up
Security Software9/14/169/14/1610%1015.15.2Set Up
Firewals9/15/169/15/1610%1015.25.3Create Passwords and
Acces Rules9/16/169/16/1610%1015.35.4Individual Security
Settings9/17/169/17/1610%1015.4FinalNetwork Upgrade
ReadyFinal
Running head: PROJECT CHARTER
1
Project Schedule
Learning Team B: Project Schedule
Ali Mbil, Gerald Merten, Jose Murguia, Lilia Nevarez, Ronalyn
Reyes
CMGT/410
September 5, 2016
Seth Chaikin
Project Details
Project Name
Orao Media Technologies
Project Type
Music Industry Production Software
Project Start Date
September 5, 2016
Project End Date
September 27, 2016
Project Sponsor
Media Technologies
Primary Driver
Production
Secondary Driver
Quality Assurance
Division
Music
Project Manager/Dept
Team B
Overview
This document defines the high level requirements for Orao
Media Technologies. It will be used as the basis for the
following activities:
· Creating solution designs, assigning the appropriate software
· Developing test plans, test scripts, and test cases, utilizing
Mojave as an internal secure data line
· Determining project completion refreshing consumer’s server
operating system and hardware.
· Assessing project success
Role
Functionality
Sub Functionality/Budget
NFR/Client-Server Database System
Consumer
Add production cart
With login 30%
Performance / CRM
Consumer
logout
Without login
30%
Usability/ CRM
Consumer
Add production cart
With login
30%
Performance/ CRM
Admin
logout
Without login
40%
Compatability/CRM
Admin
40%
Security/ CRM
Admin
Add production cart
40%
Usability/CRM
consumer
Add production cart
30%
Compatability/CRM
Admin
logout
40%
Performance/CRM
Admin
logout
40%
Security/CRM
Admin
Add production cart
40%
Usability/CRM
Consumer
logout
30%
Performance/CRM
Actor Name
Actor Type
Access Type needed
Comments
Member 1
|_| Stakeholder
|_| Primary Actor
|_| Supporting Actor
|_| Create |_| Print
|_| Read |_| Export
|_| Update |_| Others
|_| Delete
Internal Secure Data Line/Mojave
Member 2
|_| Stakeholder
|_| Primary Actor
|_| Supporting Actor
|_| Create |_| Print
|_| Read |_| Export
|_| Update |_| Others
|_| Delete
Internal Secure Data Line/Mojave
Member 3
|_| Stakeholder
|_| Primary Actor
|_| Supporting Actor
|_| Create |_| Print
|_| Read |_| Export
|_| Update |_| Others
|_| Delete
Internal Secure Data Line/Mojave
Member 4
|_| Stakeholder
|_| Primary Actor
|_| Supporting Actor
|_| Create |_| Print
|_| Read |_| Export
|_| Update |_| Others
|_| Delete
Internal Secure Data Line/Mojave
Project Scope
An analysis of the current network will need to be completed to
further understand the process. The scope of the project is the
design and implementation of the resources necessary for a new
and secured system. The new system will require several
resources for successful implementation. Hence, the current
system and operations must be maintained, while ensuring that
client data is intact.
Phases:
I. Assessment
II. Development
III. Implementation
IV. Maintenance and support
Assumptions
· Funds for the upgrade will be available prior to project
mobilization.
· Personnel will be available to complete assigned tasks
Constraints
· Adjustments or changes to security and data protocols
· Training personnel on new upgrades and policies
· Budget Limitations
· Disruption to business operations
Risks
· Breach of security during data migration from old to new
system network
· There might be project overlap which may impair timeline
· The above bullet points may require outsourcing that may put
the company to security vulnerability since there’s limited
control to their network system

More Related Content

Similar to Sheet1[Project Name]0Gantt ChartSecurity Network UpgradeTeam BToda.docx

Assignment 3 VoIP Part 1 (Work Breakdown Structure)This ass.docx
Assignment 3 VoIP Part 1 (Work Breakdown Structure)This ass.docxAssignment 3 VoIP Part 1 (Work Breakdown Structure)This ass.docx
Assignment 3 VoIP Part 1 (Work Breakdown Structure)This ass.docx
danielfoster65629
 
CIS337– Networking in Business Unit 6 Assignment Final
CIS337– Networking in Business  Unit 6 Assignment FinalCIS337– Networking in Business  Unit 6 Assignment Final
CIS337– Networking in Business Unit 6 Assignment Final
VinaOconner450
 
VoIP Implementation WBSTask NameDurationStart DateEnd DatePredeces.docx
VoIP Implementation WBSTask NameDurationStart DateEnd DatePredeces.docxVoIP Implementation WBSTask NameDurationStart DateEnd DatePredeces.docx
VoIP Implementation WBSTask NameDurationStart DateEnd DatePredeces.docx
jessiehampson
 
Work Breakdown Structure (WBS) TemplateThis Project WB.docx
Work Breakdown Structure (WBS) TemplateThis Project WB.docxWork Breakdown Structure (WBS) TemplateThis Project WB.docx
Work Breakdown Structure (WBS) TemplateThis Project WB.docx
ambersalomon88660
 
Part 3A· After creating the resource pool, copy the screen image.docx
Part 3A· After creating the resource pool, copy the screen image.docxPart 3A· After creating the resource pool, copy the screen image.docx
Part 3A· After creating the resource pool, copy the screen image.docx
herbertwilson5999
 
CPIN 269 Final Documentation
CPIN 269 Final DocumentationCPIN 269 Final Documentation
CPIN 269 Final Documentation
Jennifer Cordes
 
Business RequirementsReference number Document Control
Business RequirementsReference number Document ControlBusiness RequirementsReference number Document Control
Business RequirementsReference number Document Control
TawnaDelatorrejs
 
Resume Manoj Kumar M
Resume Manoj Kumar MResume Manoj Kumar M
Resume Manoj Kumar M
Manoj Kumar
 
Sheet2ScoresMaxActualComments1. Effort Estimate. Estimate the e.docx
Sheet2ScoresMaxActualComments1.  Effort Estimate.   Estimate the e.docxSheet2ScoresMaxActualComments1.  Effort Estimate.   Estimate the e.docx
Sheet2ScoresMaxActualComments1. Effort Estimate. Estimate the e.docx
bjohn46
 
Running Head PROJECT PLAN-BUSINESS REQUIREMENT DOCUMENT .docx
Running Head PROJECT PLAN-BUSINESS REQUIREMENT DOCUMENT      .docxRunning Head PROJECT PLAN-BUSINESS REQUIREMENT DOCUMENT      .docx
Running Head PROJECT PLAN-BUSINESS REQUIREMENT DOCUMENT .docx
jeanettehully
 
System ImplementationGantt Chart0Going Live (Software Installation.docx
System ImplementationGantt Chart0Going Live (Software Installation.docxSystem ImplementationGantt Chart0Going Live (Software Installation.docx
System ImplementationGantt Chart0Going Live (Software Installation.docx
mattinsonjanel
 

Similar to Sheet1[Project Name]0Gantt ChartSecurity Network UpgradeTeam BToda.docx (20)

Assignment 3 VoIP Part 1 (Work Breakdown Structure)This ass.docx
Assignment 3 VoIP Part 1 (Work Breakdown Structure)This ass.docxAssignment 3 VoIP Part 1 (Work Breakdown Structure)This ass.docx
Assignment 3 VoIP Part 1 (Work Breakdown Structure)This ass.docx
 
CIS337– Networking in Business Unit 6 Assignment Final
CIS337– Networking in Business  Unit 6 Assignment FinalCIS337– Networking in Business  Unit 6 Assignment Final
CIS337– Networking in Business Unit 6 Assignment Final
 
Pm 430 develop a quality management/tutorialoutlet
Pm 430 develop a quality management/tutorialoutletPm 430 develop a quality management/tutorialoutlet
Pm 430 develop a quality management/tutorialoutlet
 
VoIP Implementation WBSTask NameDurationStart DateEnd DatePredeces.docx
VoIP Implementation WBSTask NameDurationStart DateEnd DatePredeces.docxVoIP Implementation WBSTask NameDurationStart DateEnd DatePredeces.docx
VoIP Implementation WBSTask NameDurationStart DateEnd DatePredeces.docx
 
Work Breakdown Structure (WBS) TemplateThis Project WB.docx
Work Breakdown Structure (WBS) TemplateThis Project WB.docxWork Breakdown Structure (WBS) TemplateThis Project WB.docx
Work Breakdown Structure (WBS) TemplateThis Project WB.docx
 
Part 3A· After creating the resource pool, copy the screen image.docx
Part 3A· After creating the resource pool, copy the screen image.docxPart 3A· After creating the resource pool, copy the screen image.docx
Part 3A· After creating the resource pool, copy the screen image.docx
 
CS8494 SOFTWARE ENGINEERING Unit-5
CS8494 SOFTWARE ENGINEERING Unit-5CS8494 SOFTWARE ENGINEERING Unit-5
CS8494 SOFTWARE ENGINEERING Unit-5
 
Software Project Proposal- Result Analysis Tool
Software Project Proposal- Result Analysis ToolSoftware Project Proposal- Result Analysis Tool
Software Project Proposal- Result Analysis Tool
 
CPIN 269 Final Documentation
CPIN 269 Final DocumentationCPIN 269 Final Documentation
CPIN 269 Final Documentation
 
Business RequirementsReference number Document Control
Business RequirementsReference number Document ControlBusiness RequirementsReference number Document Control
Business RequirementsReference number Document Control
 
Final project se
Final project seFinal project se
Final project se
 
Resume Manoj Kumar M
Resume Manoj Kumar MResume Manoj Kumar M
Resume Manoj Kumar M
 
The Pennsylvania State University: Modernizing and Standardizing the Penn Sta...
The Pennsylvania State University: Modernizing and Standardizing the Penn Sta...The Pennsylvania State University: Modernizing and Standardizing the Penn Sta...
The Pennsylvania State University: Modernizing and Standardizing the Penn Sta...
 
Sheet2ScoresMaxActualComments1. Effort Estimate. Estimate the e.docx
Sheet2ScoresMaxActualComments1.  Effort Estimate.   Estimate the e.docxSheet2ScoresMaxActualComments1.  Effort Estimate.   Estimate the e.docx
Sheet2ScoresMaxActualComments1. Effort Estimate. Estimate the e.docx
 
Project management case analysis
Project management case analysisProject management case analysis
Project management case analysis
 
Running Head PROJECT PLAN-BUSINESS REQUIREMENT DOCUMENT .docx
Running Head PROJECT PLAN-BUSINESS REQUIREMENT DOCUMENT      .docxRunning Head PROJECT PLAN-BUSINESS REQUIREMENT DOCUMENT      .docx
Running Head PROJECT PLAN-BUSINESS REQUIREMENT DOCUMENT .docx
 
Test plansample
Test plansampleTest plansample
Test plansample
 
Effort estimation( software Engineering)
Effort estimation( software Engineering)Effort estimation( software Engineering)
Effort estimation( software Engineering)
 
System ImplementationGantt Chart0Going Live (Software Installation.docx
System ImplementationGantt Chart0Going Live (Software Installation.docxSystem ImplementationGantt Chart0Going Live (Software Installation.docx
System ImplementationGantt Chart0Going Live (Software Installation.docx
 
PROJECT CHARTER
PROJECT CHARTERPROJECT CHARTER
PROJECT CHARTER
 

More from maoanderton

InstructionsFor this assignment, select one of the following.docx
InstructionsFor this assignment, select one of the following.docxInstructionsFor this assignment, select one of the following.docx
InstructionsFor this assignment, select one of the following.docx
maoanderton
 
InstructionsFind a NEWS article that addresses a recent t.docx
InstructionsFind a NEWS article that addresses a recent t.docxInstructionsFind a NEWS article that addresses a recent t.docx
InstructionsFind a NEWS article that addresses a recent t.docx
maoanderton
 
InstructionsFind a NEWS article that addresses a current .docx
InstructionsFind a NEWS article that addresses a current .docxInstructionsFind a NEWS article that addresses a current .docx
InstructionsFind a NEWS article that addresses a current .docx
maoanderton
 
InstructionsFinancial challenges associated with changes.docx
InstructionsFinancial challenges associated with changes.docxInstructionsFinancial challenges associated with changes.docx
InstructionsFinancial challenges associated with changes.docx
maoanderton
 
InstructionsEach of your responses will be graded not only for .docx
InstructionsEach of your responses will be graded not only for .docxInstructionsEach of your responses will be graded not only for .docx
InstructionsEach of your responses will be graded not only for .docx
maoanderton
 
InstructionsDevelop an iconographic essay. Select a work fro.docx
InstructionsDevelop an iconographic essay. Select a work fro.docxInstructionsDevelop an iconographic essay. Select a work fro.docx
InstructionsDevelop an iconographic essay. Select a work fro.docx
maoanderton
 
InstructionsCookie Creations (Continued)Part INatalie is.docx
InstructionsCookie Creations (Continued)Part INatalie is.docxInstructionsCookie Creations (Continued)Part INatalie is.docx
InstructionsCookie Creations (Continued)Part INatalie is.docx
maoanderton
 
InstructionsCommunities do not exist in a bubble. Often changes .docx
InstructionsCommunities do not exist in a bubble. Often changes .docxInstructionsCommunities do not exist in a bubble. Often changes .docx
InstructionsCommunities do not exist in a bubble. Often changes .docx
maoanderton
 
InstructionsBeginning in the 1770s, an Age of Revolution swep.docx
InstructionsBeginning in the 1770s, an Age of Revolution  swep.docxInstructionsBeginning in the 1770s, an Age of Revolution  swep.docx
InstructionsBeginning in the 1770s, an Age of Revolution swep.docx
maoanderton
 

More from maoanderton (20)

InstructionsFor this assignment, select one of the following.docx
InstructionsFor this assignment, select one of the following.docxInstructionsFor this assignment, select one of the following.docx
InstructionsFor this assignment, select one of the following.docx
 
InstructionsFor this assignment, analyze the space race..docx
InstructionsFor this assignment, analyze the space race..docxInstructionsFor this assignment, analyze the space race..docx
InstructionsFor this assignment, analyze the space race..docx
 
InstructionsFor the initial post, address one of the fol.docx
InstructionsFor the initial post, address one of the fol.docxInstructionsFor the initial post, address one of the fol.docx
InstructionsFor the initial post, address one of the fol.docx
 
InstructionsFollow paper format and Chicago Style to complete t.docx
InstructionsFollow paper format and Chicago Style to complete t.docxInstructionsFollow paper format and Chicago Style to complete t.docx
InstructionsFollow paper format and Chicago Style to complete t.docx
 
InstructionsFind a NEWS article that addresses a recent t.docx
InstructionsFind a NEWS article that addresses a recent t.docxInstructionsFind a NEWS article that addresses a recent t.docx
InstructionsFind a NEWS article that addresses a recent t.docx
 
InstructionsFind a NEWS article that addresses a current .docx
InstructionsFind a NEWS article that addresses a current .docxInstructionsFind a NEWS article that addresses a current .docx
InstructionsFind a NEWS article that addresses a current .docx
 
InstructionsFinancial challenges associated with changes.docx
InstructionsFinancial challenges associated with changes.docxInstructionsFinancial challenges associated with changes.docx
InstructionsFinancial challenges associated with changes.docx
 
InstructionsExplain the role of the U.S. Office of Personnel.docx
InstructionsExplain the role of the U.S. Office of Personnel.docxInstructionsExplain the role of the U.S. Office of Personnel.docx
InstructionsExplain the role of the U.S. Office of Personnel.docx
 
InstructionsEvaluate Personality TestsEvaluation Title.docx
InstructionsEvaluate Personality TestsEvaluation Title.docxInstructionsEvaluate Personality TestsEvaluation Title.docx
InstructionsEvaluate Personality TestsEvaluation Title.docx
 
InstructionsEach of your responses will be graded not only for .docx
InstructionsEach of your responses will be graded not only for .docxInstructionsEach of your responses will be graded not only for .docx
InstructionsEach of your responses will be graded not only for .docx
 
InstructionsEffective communication skills can prevent many si.docx
InstructionsEffective communication skills can prevent many si.docxInstructionsEffective communication skills can prevent many si.docx
InstructionsEffective communication skills can prevent many si.docx
 
InstructionsEcologyTo complete this assignment, complete the.docx
InstructionsEcologyTo complete this assignment, complete the.docxInstructionsEcologyTo complete this assignment, complete the.docx
InstructionsEcologyTo complete this assignment, complete the.docx
 
InstructionsDevelop an iconographic essay. Select a work fro.docx
InstructionsDevelop an iconographic essay. Select a work fro.docxInstructionsDevelop an iconographic essay. Select a work fro.docx
InstructionsDevelop an iconographic essay. Select a work fro.docx
 
InstructionsDEFINITION a brief definition of the key term fo.docx
InstructionsDEFINITION a brief definition of the key term fo.docxInstructionsDEFINITION a brief definition of the key term fo.docx
InstructionsDEFINITION a brief definition of the key term fo.docx
 
InstructionsCreate a PowerPoint presentation of 15 slides (not c.docx
InstructionsCreate a PowerPoint presentation of 15 slides (not c.docxInstructionsCreate a PowerPoint presentation of 15 slides (not c.docx
InstructionsCreate a PowerPoint presentation of 15 slides (not c.docx
 
InstructionsCookie Creations (Continued)Part INatalie is.docx
InstructionsCookie Creations (Continued)Part INatalie is.docxInstructionsCookie Creations (Continued)Part INatalie is.docx
InstructionsCookie Creations (Continued)Part INatalie is.docx
 
InstructionsCommunities do not exist in a bubble. Often changes .docx
InstructionsCommunities do not exist in a bubble. Often changes .docxInstructionsCommunities do not exist in a bubble. Often changes .docx
InstructionsCommunities do not exist in a bubble. Often changes .docx
 
InstructionsChoose only ONE of the following options and wri.docx
InstructionsChoose only ONE of the following options and wri.docxInstructionsChoose only ONE of the following options and wri.docx
InstructionsChoose only ONE of the following options and wri.docx
 
InstructionsChoose only ONE of the following options and.docx
InstructionsChoose only ONE of the following options and.docxInstructionsChoose only ONE of the following options and.docx
InstructionsChoose only ONE of the following options and.docx
 
InstructionsBeginning in the 1770s, an Age of Revolution swep.docx
InstructionsBeginning in the 1770s, an Age of Revolution  swep.docxInstructionsBeginning in the 1770s, an Age of Revolution  swep.docx
InstructionsBeginning in the 1770s, an Age of Revolution swep.docx
 

Recently uploaded

Personalisation of Education by AI and Big Data - Lourdes Guàrdia
Personalisation of Education by AI and Big Data - Lourdes GuàrdiaPersonalisation of Education by AI and Big Data - Lourdes Guàrdia
Personalisation of Education by AI and Big Data - Lourdes Guàrdia
EADTU
 
會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽
會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽
會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽
中 央社
 
SURVEY I created for uni project research
SURVEY I created for uni project researchSURVEY I created for uni project research
SURVEY I created for uni project research
CaitlinCummins3
 

Recently uploaded (20)

OSCM Unit 2_Operations Processes & Systems
OSCM Unit 2_Operations Processes & SystemsOSCM Unit 2_Operations Processes & Systems
OSCM Unit 2_Operations Processes & Systems
 
Mattingly "AI & Prompt Design: Named Entity Recognition"
Mattingly "AI & Prompt Design: Named Entity Recognition"Mattingly "AI & Prompt Design: Named Entity Recognition"
Mattingly "AI & Prompt Design: Named Entity Recognition"
 
An Overview of the Odoo 17 Knowledge App
An Overview of the Odoo 17 Knowledge AppAn Overview of the Odoo 17 Knowledge App
An Overview of the Odoo 17 Knowledge App
 
ĐỀ THAM KHẢO KÌ THI TUYỂN SINH VÀO LỚP 10 MÔN TIẾNG ANH FORM 50 CÂU TRẮC NGHI...
ĐỀ THAM KHẢO KÌ THI TUYỂN SINH VÀO LỚP 10 MÔN TIẾNG ANH FORM 50 CÂU TRẮC NGHI...ĐỀ THAM KHẢO KÌ THI TUYỂN SINH VÀO LỚP 10 MÔN TIẾNG ANH FORM 50 CÂU TRẮC NGHI...
ĐỀ THAM KHẢO KÌ THI TUYỂN SINH VÀO LỚP 10 MÔN TIẾNG ANH FORM 50 CÂU TRẮC NGHI...
 
Supporting Newcomer Multilingual Learners
Supporting Newcomer  Multilingual LearnersSupporting Newcomer  Multilingual Learners
Supporting Newcomer Multilingual Learners
 
OS-operating systems- ch05 (CPU Scheduling) ...
OS-operating systems- ch05 (CPU Scheduling) ...OS-operating systems- ch05 (CPU Scheduling) ...
OS-operating systems- ch05 (CPU Scheduling) ...
 
How to Send Pro Forma Invoice to Your Customers in Odoo 17
How to Send Pro Forma Invoice to Your Customers in Odoo 17How to Send Pro Forma Invoice to Your Customers in Odoo 17
How to Send Pro Forma Invoice to Your Customers in Odoo 17
 
Personalisation of Education by AI and Big Data - Lourdes Guàrdia
Personalisation of Education by AI and Big Data - Lourdes GuàrdiaPersonalisation of Education by AI and Big Data - Lourdes Guàrdia
Personalisation of Education by AI and Big Data - Lourdes Guàrdia
 
diagnosting testing bsc 2nd sem.pptx....
diagnosting testing bsc 2nd sem.pptx....diagnosting testing bsc 2nd sem.pptx....
diagnosting testing bsc 2nd sem.pptx....
 
When Quality Assurance Meets Innovation in Higher Education - Report launch w...
When Quality Assurance Meets Innovation in Higher Education - Report launch w...When Quality Assurance Meets Innovation in Higher Education - Report launch w...
When Quality Assurance Meets Innovation in Higher Education - Report launch w...
 
FICTIONAL SALESMAN/SALESMAN SNSW 2024.pdf
FICTIONAL SALESMAN/SALESMAN SNSW 2024.pdfFICTIONAL SALESMAN/SALESMAN SNSW 2024.pdf
FICTIONAL SALESMAN/SALESMAN SNSW 2024.pdf
 
Sternal Fractures & Dislocations - EMGuidewire Radiology Reading Room
Sternal Fractures & Dislocations - EMGuidewire Radiology Reading RoomSternal Fractures & Dislocations - EMGuidewire Radiology Reading Room
Sternal Fractures & Dislocations - EMGuidewire Radiology Reading Room
 
Book Review of Run For Your Life Powerpoint
Book Review of Run For Your Life PowerpointBook Review of Run For Your Life Powerpoint
Book Review of Run For Your Life Powerpoint
 
會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽
會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽
會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽
 
Observing-Correct-Grammar-in-Making-Definitions.pptx
Observing-Correct-Grammar-in-Making-Definitions.pptxObserving-Correct-Grammar-in-Making-Definitions.pptx
Observing-Correct-Grammar-in-Making-Definitions.pptx
 
SURVEY I created for uni project research
SURVEY I created for uni project researchSURVEY I created for uni project research
SURVEY I created for uni project research
 
Major project report on Tata Motors and its marketing strategies
Major project report on Tata Motors and its marketing strategiesMajor project report on Tata Motors and its marketing strategies
Major project report on Tata Motors and its marketing strategies
 
How to Manage Website in Odoo 17 Studio App.pptx
How to Manage Website in Odoo 17 Studio App.pptxHow to Manage Website in Odoo 17 Studio App.pptx
How to Manage Website in Odoo 17 Studio App.pptx
 
Basic Civil Engineering notes on Transportation Engineering & Modes of Transport
Basic Civil Engineering notes on Transportation Engineering & Modes of TransportBasic Civil Engineering notes on Transportation Engineering & Modes of Transport
Basic Civil Engineering notes on Transportation Engineering & Modes of Transport
 
PSYPACT- Practicing Over State Lines May 2024.pptx
PSYPACT- Practicing Over State Lines May 2024.pptxPSYPACT- Practicing Over State Lines May 2024.pptx
PSYPACT- Practicing Over State Lines May 2024.pptx
 

Sheet1[Project Name]0Gantt ChartSecurity Network UpgradeTeam BToda.docx

  • 1. Sheet1[Project Name]0Gantt ChartSecurity Network UpgradeTeam BToday's Date:9/5/16Monday(vertical red line) Jon: Work Breakdown Structure Level 1: 1, 2, 3, ... Level 2: 1.1, 1.2, 1.3, ... Level 3: 1.1.1, 1.1.2, 1.1.3, … The WBS is automatically entered, but the formulas are different for different levels.Project Lead:Team B Jon: Duration (Calendar Days) Enter the number of calendar days for the given task. Refer to the Working Days column or use a calendar to determine the corresponding working days. The duration is from the beginning of the Start date to the ending of the End Date. When the duration is calculated, it is calculated as End Date minus the Start Date plus 1 day, so that a task starting and ending on the same day has a duration of 1 day. Jon: Percent Complete Update the status of this task by entering the percent complete (between 0% and 100%). Jon: Working Days Counts the number of working days using the NETWORKDAYS() formula, which excludes weekends. When planning work based upon the number of working days, adjust the Duration until the desired # of working days is reached. Jon: Calendar Days Complete This column is calculated by multiplying the Duration by the %Complete and rounding down to the nearest integer.
  • 2. Jon: Calendar Days Remaining This column is calculated by subtracting the Days Complete from the Duration.Start Date:9/5/16Monday[42]First Day of Week (Mon=2):212/29/1412/30/1412/31/141/1/151/2/151/3/151/4/151/ 5/151/6/151/7/151/8/151/9/151/10/151/11/151/12/151/13/151/14 /151/15/151/16/151/17/151/18/151/19/151/20/151/21/151/22/15 1/23/151/24/151/25/151/26/151/27/151/28/151/29/151/30/151/3 1/152/1/152/2/152/3/152/4/152/5/152/6/152/7/152/8/152/9/152/ 10/152/11/152/12/152/13/152/14/152/15/152/16/152/17/152/18/ 152/19/152/20/152/21/152/22/152/23/152/24/152/25/152/26/152 /27/152/28/153/1/153/2/153/3/153/4/153/5/153/6/153/7/153/8/1 53/9/153/10/153/11/153/12/153/13/153/14/153/15/153/16/153/1 7/153/18/153/19/153/20/153/21/153/22/153/23/153/24/153/25/1 53/26/153/27/153/28/153/29/153/30/153/31/154/1/154/2/154/3/1 54/4/154/5/154/6/154/7/154/8/154/9/154/10/154/11/154/12/154/ 13/154/14/154/15/154/16/154/17/154/18/154/19/154/20/154/21/ 154/22/154/23/154/24/154/25/154/26/154/27/154/28/154/29/154 /30/155/1/155/2/155/3/155/4/155/5/155/6/155/7/155/8/155/9/15 5/10/155/11/155/12/155/13/155/14/155/15/155/16/155/17/155/1 8/155/19/155/20/155/21/155/22/155/23/155/24/155/25/155/26/1 55/27/155/28/155/29/155/30/155/31/156/1/156/2/156/3/156/4/15 6/5/156/6/156/7/156/8/156/9/156/10/156/11/156/12/156/13/156/ 14/156/15/156/16/156/17/156/18/156/19/156/20/156/21/156/22/ 156/23/156/24/156/25/156/26/156/27/156/28/156/29/156/30/157 /1/157/2/157/3/157/4/157/5/157/6/157/7/157/8/157/9/157/10/15 7/11/157/12/157/13/157/14/157/15/157/16/157/17/157/18/157/1 9/157/20/157/21/157/22/157/23/157/24/157/25/157/26/157/27/1 57/28/157/29/157/30/157/31/158/1/158/2/158/3/158/4/158/5/158 /6/158/7/158/8/158/9/158/10/158/11/158/12/158/13/158/14/158/ 15/158/16/158/17/158/18/158/19/158/20/158/21/158/22/158/23/ 15WBSTasksStartEndDuration (Days)% CompleteWorking DaysDays CompleteDays Remaining05 - Sep - 1606 - Sep - 1607 - Sep - 1608 - Sep - 1609 - Sep - 1610 - Sep - 1611 - Sep - 1612 - Sep - 1613 - Sep - 1614 - Sep - 1615 - Sep - 1616 - Sep - 1617 - Sep - 16Task Lead1Security Network UpgradeTeam
  • 3. B9/5/169/17/16130%1301312Meet and Create ScheduleTeam B9/5/169/6/1620%21132Meet and Create Schedule2.1Office Managers Meeting for Discussion9/5/169/5/1610%1112.12.2Create and Submit Security Upgrade9/6/169/6/1610%1012.22.3Approve schedule9/6/169/6/1610%1012.33Receive New Security SoftwareTeam B9/7/169/10/16450%4043Receive New Securty Software3.1Purchase New Software9/7/169/7/16150%1013.13.2Ensure Hardware is sufficient9/7/169/7/16150%1013.23.3Purchase Accessories9/8/169/8/16150%1013.33.4Prepare for Hardwasre installation9/9/169/10/1622023.44Back Up DataTeam B9/11/169/13/1630%3034Back Up Data4.1Back Up shared Drives & Files9/11/169/11/1610%1014.14.2Back Up User Data9/12/169/12/1610%1014.24.3Ensure Back Up Was Successful9/13/169/13/1610%1014.35Install and configureTeam B9/14/169/17/1640%4045Install and configure5.1Set Up Security Software9/14/169/14/1610%1015.15.2Set Up Firewals9/15/169/15/1610%1015.25.3Create Passwords and Acces Rules9/16/169/16/1610%1015.35.4Individual Security Settings9/17/169/17/1610%1015.4FinalNetwork Upgrade ReadyFinal Running head: PROJECT CHARTER 1 Project Schedule Learning Team B: Project Schedule Ali Mbil, Gerald Merten, Jose Murguia, Lilia Nevarez, Ronalyn Reyes
  • 4. CMGT/410 September 5, 2016 Seth Chaikin Project Details Project Name Orao Media Technologies Project Type Music Industry Production Software Project Start Date September 5, 2016 Project End Date September 27, 2016 Project Sponsor Media Technologies Primary Driver Production Secondary Driver Quality Assurance Division Music Project Manager/Dept Team B
  • 5. Overview This document defines the high level requirements for Orao Media Technologies. It will be used as the basis for the following activities: · Creating solution designs, assigning the appropriate software · Developing test plans, test scripts, and test cases, utilizing Mojave as an internal secure data line · Determining project completion refreshing consumer’s server operating system and hardware. · Assessing project success Role Functionality Sub Functionality/Budget NFR/Client-Server Database System Consumer Add production cart With login 30% Performance / CRM Consumer logout Without login 30% Usability/ CRM Consumer Add production cart With login 30% Performance/ CRM Admin logout Without login 40% Compatability/CRM
  • 6. Admin 40% Security/ CRM Admin Add production cart 40% Usability/CRM consumer Add production cart 30% Compatability/CRM Admin logout 40% Performance/CRM Admin logout 40% Security/CRM Admin Add production cart 40% Usability/CRM Consumer logout 30% Performance/CRM Actor Name Actor Type Access Type needed
  • 7. Comments Member 1 |_| Stakeholder |_| Primary Actor |_| Supporting Actor |_| Create |_| Print |_| Read |_| Export |_| Update |_| Others |_| Delete Internal Secure Data Line/Mojave Member 2 |_| Stakeholder |_| Primary Actor |_| Supporting Actor |_| Create |_| Print |_| Read |_| Export |_| Update |_| Others |_| Delete Internal Secure Data Line/Mojave Member 3 |_| Stakeholder |_| Primary Actor |_| Supporting Actor |_| Create |_| Print |_| Read |_| Export |_| Update |_| Others |_| Delete Internal Secure Data Line/Mojave Member 4 |_| Stakeholder |_| Primary Actor |_| Supporting Actor |_| Create |_| Print |_| Read |_| Export |_| Update |_| Others |_| Delete
  • 8. Internal Secure Data Line/Mojave Project Scope An analysis of the current network will need to be completed to further understand the process. The scope of the project is the design and implementation of the resources necessary for a new and secured system. The new system will require several resources for successful implementation. Hence, the current system and operations must be maintained, while ensuring that client data is intact. Phases: I. Assessment II. Development III. Implementation IV. Maintenance and support Assumptions · Funds for the upgrade will be available prior to project mobilization. · Personnel will be available to complete assigned tasks Constraints · Adjustments or changes to security and data protocols · Training personnel on new upgrades and policies · Budget Limitations · Disruption to business operations
  • 9. Risks · Breach of security during data migration from old to new system network · There might be project overlap which may impair timeline · The above bullet points may require outsourcing that may put the company to security vulnerability since there’s limited control to their network system