Description
The Aires Corporation is highly desirous of implementing a new time tracking system to help automate their project control system, accounting and account receivables. The time tracking system is designed to allow employees and subcontractors to charge hours against project control accounts and to help prevent mischarging. The system is called Chronos and it is written in a modern database management system, which is the preferred database platform by Aires. The project is to integrate the time card system to project management, accounting and accounts receivable/payables. The Director of Information Technology (IT) has assigned an integration project to you as project manager; in addition, the director assigned a senior systems engineer to be the project's technical lead.
The Software Engineer has a team of five (5) developers that will work on the project; the Director has asked for a project management plan to be briefed to the IT senior leadership team, which is in a few days. Your mission is to construct a Microsoft Project proposal to help prepare for the briefing. You are also to construct a quick Total Project Cost (TPC) cross reference work sheet to verify the accuracy of the MS Project effort.
Organizing
As project manager, you meet with your development team and determine that the interface will be composed of input screens, interface processes, and verification reports for the integration of the time tracking system to the other legacy financial systems. The Developers have indicated that they would like to receive training on the Chronos system to help them with the database structures to facilitate the integration. The training would have to occur before any other activity could evolve. The team is highly adept to the other systems being used and the integration risk is mainly centered on Chronos Time Tracking system since it is new to the organization. The team has decided that the plan should be oriented on Design, Programming, Quality Assurance, Rework, Documentation, User Training, and Production. Lastly, the team recommended support from the Chronos vendor to address technical questions they might have during development of the interface. As project manager, you note that there are special stakeholders and decide to involve support from Finance and Project Management to address process and procedure questions that might arise during the design, development and testing of the interface. The outcome of the planning meeting with the entire project team is represented in the list under scope and schedule.
Scope and Schedule
The following preliminary WBS was developed as a result of your meeting:
WBS Description Scope Units Duration Relationships
1. Chronos Interface 1 Interface Summary
1.1. Design 1 Spec Summary
1.1.1. Screens 5 Screens 8 1.1.1->1.1.3
1.1.2. Interfaces 3 Process Algorithms 10 1.1.2->1.1.3
1.1.3. Reports 6 Reports 5 1.1.3->1.1.4, 1.1.3->1.1.7
1.1.4. Eng.
DescriptionThe Aires Corporation is highly desirous of implementi.docx
1. Description
The Aires Corporation is highly desirous of implementing a
new time tracking system to help automate their project control
system, accounting and account receivables. The time tracking
system is designed to allow employees and subcontractors to
charge hours against project control accounts and to help
prevent mischarging. The system is called Chronos and it is
written in a modern database management system, which is the
preferred database platform by Aires. The project is to integrate
the time card system to project management, accounting and
accounts receivable/payables. The Director of Information
Technology (IT) has assigned an integration project to you as
project manager; in addition, the director assigned a senior
systems engineer to be the project's technical lead.
The Software Engineer has a team of five (5) developers that
will work on the project; the Director has asked for a project
management plan to be briefed to the IT senior leadership team,
which is in a few days. Your mission is to construct a Microsoft
Project proposal to help prepare for the briefing. You are also to
construct a quick Total Project Cost (TPC) cross reference work
sheet to verify the accuracy of the MS Project effort.
Organizing
As project manager, you meet with your development team and
determine that the interface will be composed of input screens,
interface processes, and verification reports for the integration
of the time tracking system to the other legacy financial
systems. The Developers have indicated that they would like to
receive training on the Chronos system to help them with the
database structures to facilitate the integration. The training
would have to occur before any other activity could evolve. The
team is highly adept to the other systems being used and the
2. integration risk is mainly centered on Chronos Time Tracking
system since it is new to the organization. The team has decided
that the plan should be oriented on Design, Programming,
Quality Assurance, Rework, Documentation, User Training, and
Production. Lastly, the team recommended support from the
Chronos vendor to address technical questions they might have
during development of the interface. As project manager, you
note that there are special stakeholders and decide to involve
support from Finance and Project Management to address
process and procedure questions that might arise during the
design, development and testing of the interface. The outcome
of the planning meeting with the entire project team is
represented in the list under scope and schedule.
Scope and Schedule
The following preliminary WBS was developed as a result of
your meeting:
WBSDescription Scope Units
Duration Relationships
1. Chronos Interface 1 Interface
Summary
1.1. Design 1 Spec Summary
1.1.1. Screens 5 Screens 8
1.1.1->1.1.3
1.1.2. Interfaces 3 Process Algorithms
10 1.1.2->1.1.3
1.1.3. Reports 6 Reports 5
1.1.3->1.1.4, 1.1.3->1.1.7
4. 1.5.1. Reference Guide 1 Manual
10 1.5.1->1.5.2
1.5.2. Training manuals 1 Manual
10 1.5.2->1.5.3
1.5.3. Manuals Done
Milestone 1.5.3->1.6
1.6. User Training 1 Class 5
1.6->1.7
1.7. Production 1 Interface
Milestone
Resources & Cost
After a discussion, the team decided that the project had
sufficient detail in terms of scope and schedule. Resources
would be loaded against the top summary level activity only for
the entire duration of the project. So the resource and cost
estimate would be estimated at the, "1 Chronos Interface" level.
The following resources will be applied in terms of labor across
the project:
Heads Resource Name Resource Description
Direct Rate
1.00 L1PRJM Project Manager $75/hr
1.00 L2SWE Software Engineer $60/hr
5.00 L3DEVL Software Developers $40/hr
5. 0.50 L4CONS Chronos Consultant $200/hr
0.25 L5FCON Finance Support Staff $85/hr
0.25 L5PRJM Project Management Support $85/hr
The finance department provided the labor codes above and the
burden rates below. Finance provided guidance that the Chronos
Consultant is a subcontractor an only the G&A rate applies. All
other rates associated to labor are to be fully burdened with the
following rate:
Burden Description Rate
Direct Labor Overhead (DLO) 80%
General & Administrative 20%
Since this is a capital project, there is no profit or fee inclusion
in the burden rate. Capital projects are financially sponsored by
the host organization so the total rate is discounted by both
profit and fee; the company will only pay expense rates.
usually, all burden rates come from Finance and are derived
from the financial statements. What is the multiplier and what
are the final rates for each category? You will need to know the
final rates before entering them into MS Project.
Other Project Costs
The director has notified you that the IT Department has
procured a special server for this project to allow for the
development and testing to occur in a non-production
environment. The server is equipment and is to be included as
an investment on the project. The full amount of the service
through installation is $29,234. The server cost is not allocated
6. against the activities, but is to be included in the total project
cost.
Project Start & Calendar
You are to assume a project start date of 1/1/2011. The project
has not started yet, and the calendar is a five (5) day work
week.
Management Reserve
The director has stipulated a Management Reserve to be
imposed on the total project budget of 10%.
How to do the assignment:
1. Enter MS Project and change all time scales to Quarter for
Second Tear, and Monthly for bottom tier. Change all views
including resource views to quarterly and monthly timescale.
Why?
2. Set the project start date to the project start set herein.
Also, put in the status date as none or to 12/31/10. Why?
3. Go to Gantt View and insert the following custom fields:
Scope, Actual, Units. Scope and Actual fields will be numeric
and will require a text field. The Unit field will also have to be
a text field and will be a text format. We inserted fields for the
Week 2 assignment. Also include the WBS number or Outline
Number and make sure they align to the task list above in terms
of numbering. What is a summary activity? What is a
milestone? How many milestones does an activity have when
there is a duration greater than zero?
4. You will need the top level summary task to enter in
resources and you will need to get the duration to create a quick
7. Total Project Cost in the work book provided. You will load
resources only against that one task; however, you need to
create the schedule correctly to derive the overall summary
activity duration. This can only be done by correctly entering in
the project activities correctly with the proper summary levels.
Enter in the activities, make sure every activity is appropriately
identified as a milestone and summary task. Enter in the scope
for each activity and then enter the relationships. When
entering relationships, how does MS Project differ from the list
above?
5. Set all activities to Fixed Duration and turn off the Effort
Driven on the Activity Detail screen on the Advanced tab.
6. Insert the early start and finish, late start and finish, free
slack, and total slack fields on the Gantt View; then format the
Gantt view to show the critical path. How can you identify
critical path activities?
7. You should now know the durations of all summary tasks
and you can begin to calculate the TPC. Before showing the
TPC, you will have to calculate the fully burdened rates for all
resources. use the workbook to calculate the final rates for all
resources.
8. Once the fully burdened rates are know, enter the task
name and all resources into the TPC spreadsheet in the
Workbook. Enter the appropriate rates; enter the head count and
the spreadsheet should calculate the hours as all resources will
be loaded across the entire duration of the project, which is
given to you by the top-level summary cost. You will use the
spreadsheet as a cross reference in what you input into MS
Project.
9. Don't forget the project server that was procured; this cost
represents the other project costs the IT department did outside
8. the project.
10. Enter resources into the Resource Screen in MS Project.
All labor resources are represented as work resources. Ensure
that the right rates are applied. The Other Charges and
Management Reserve (MR) are depicted as costs and will
transpire respectively at the start and end of the summary level.
11. Load resources against the top-level activity. The numbers
should match exactly to the workbook. What is the purpose of
MR and Other Charges?