SlideShare a Scribd company logo
1 of 8
Download to read offline
†jmccall@lindsey-usa.com
Determining Crossing Conductor Clearance Using Line-Mounted LiDAR
J. C. MCCALL†, P. SPILLANE, K. LINDSEY
Lindsey Manufacturing
USA
SUMMARY
Maintaining proper transmission line clearance is required by the North American Electric Reliability
Corporation (NERC). Locations where two lines cross or are co-located along a common right-of-way
pose a difficult monitoring challenge: determining the clearance between the crossing lines. While the
National Electric Safety Code details what these clearances should be and how they should be
estimated based on a variety of criteria, these calculations do not provide confirmation of actual
clearance or of the clearance itself. This becomes particularly important when the loading
characteristics of the crossing lines vary significantly, or if future system changes may result in
unpredictable clearances. In this case the sag characteristics of each line cannot be assumed to result in
a consistent clearance value, as each line may be loaded differently as they are often on different
circuits. The spatial difference of the lines can also result in different wind levels and a difference in
the rate of cooling of the conductors.
ENMAX, a utility located in the Province of Alberta in Canada, faced this situation where a 138kV
transmission line with Curlew conductor is located above a 25 kV distribution circuit using Hawk
conductor for a distance of approximately 9.3 km. The pending energization of a new local 800MW
generation source made knowledge of the clearance between the two circuits more critical as the
additional generation will change power flows and result in very different load profiles on the 138kV
transmission circuit.
ENMAX installed four transmission line conductor monitors containing built-in downward-looking
LiDAR units to provide the line-to-ground clearance of each line. The difference in the line’s
clearances-to-ground provided clearance between the two circuits. The paper discusses ENMAX’s
situation, the operational characteristics of the monitors, their installation, the communication method
used to collect the measurement information and pass it back to EMS, an algorithm used to filter out
bad data caused by motor vehicles passing under the lines, and operational experience to date.
KEYWORDS
Clearance, LiDAR, conductor monitor, line crossing, conductor crossing, line clearance, dynamic line
rating
21, rue d’Artois, F-75008 PARIS CIGRE US National Committee
http : //www.cigre.org 2015 Grid of the Future Symposium
Lindsey Publication Number 11T-001 CROSSING CONDUCTOR TLM • October 2015
2
1. INTRODUCTION
Maintaining proper clearance-to-ground for transmission lines is a requirement of utilities by the North
American Electric Reliability Corporation (NERC). While transmission line profiles are kept and
maintained by utility engineering departments, and validated by periodic LiDAR measurements from
helicopter or ground based measuring devices, these methods capture only point-in-time snapshots of
clearance. One situation which is peculiarly problematic is when two lines cross or are co-located along
a common right-of-way. In this case it is important to not only measure the clearance-to-ground of the
lowest line, but also the clearance between the closest adjacent conductors of the two lines.
ENMAX, a utility located in the Province of Alberta in Canada, faced this situation where a 138kV
transmission line is located above a 25 kV distribution circuit for a distance of approximately 9.3 km.
The need to know, in real-time, the clearance between the two circuits was to become more critical when
later in 2015 ENMAX’s Shepard Energy Centre comes on line, bringing 800MW of additional power
generation to the area[1].
2. CROSSING LINES; THE ISSUE OF CLEARANCE
The required clearances between crossing transmission lines of various voltages are well documented.
In North America, Sections 233 and 235 of the National Electric Safety Code (NESC) [2] details the
clearance requirements for crossing lines mounted on different supporting structures and the same
supporting structures respectively. Examination of these sections highlights various issues that
underscore the complexity of determining clearance:
 Conductor characteristics
 Ambient temperature and wind assumptions (for conductor movement)
 Insulator and structure deflection
 Sag, which itself is a function of conductor temperature, wind speed (for cooling), solar
radiation, ice loading, etc.
 Application of various safety factors and configuration factors
Most if not all of these issues are also common to determining conductor thermal behavior as
documented in the IEEE 738 [3] standard and the CIGRE 207 [4] brochure. Dynamic line rating (DLR)
applications all depend on being able to accurately determine conductor clearance to what is below,
whether in real-time or forecasted.
For both dynamic line rating and crossing conductors, “clearance-to-something” is the real issue. Both
of the dynamic line rating standards and the NESC depend upon essentially a double estimation; the
computation of conductor sag and the subsequent use of that parameter to estimate clearance. Sag is a
value that is distinctly different than clearance. Sag is essentially the droop of a conductor below the
straight line drawn between its two endpoints. Variables that affect sag:
 Conductor temperature and all that affects it; current, solar radiation, cooling associated with
wind, the thermal insulating effects of ice and snow, etc.
 The location of the endpoints; insulator swing and tower movement from wind and conductor
expansion/contraction, the weight effects of ice and snow loading, etc.
And yet sag does not give clearance, which also depends on the location of what it beneath; ground,
snow cover, vegetation growth, and human activity (construction of buildings or vehicles).
The difficulties associated with accurately determining and designing for proper clearance between
conductors is underscored in one widely distributed report that for one utility, fully 60% of all
documented transmission clearance issues were the result of distribution crossings [5].
Here, the problem facing ENMAX was particularly challenging:
 The transmission and distribution lines had very different loading profiles.
Lindsey Publication Number 11T-001 CROSSING CONDUCTOR TLM • October 2015
3
 After the Shepard Energy Centre is on-line, the 800MW of additional power generation in the
area would change power flows and result in very different load profiles on the 138kV
transmission circuit than before.
 Again, after the Shepard Energy Centre is on-line, identified system contingencies could result
in greatly increased conductor sag.
Since clearance is what ultimately matters, ENMAX chose to approach the potential problem with the
co-located 138kV and 25kV lines by actually measuring the clearance between the lines in real-time.
3. CONDUCTOR MOUNTED LiDAR
To accomplish the required real-time direct conductor clearance, ENMAX chose to use a novel
conductor mounted monitor called the TLM® conductor monitor. This device provides a complete
picture of conductor behavior including actual conductor clearance-to-ground, conductor temperature,
line current, and vibration. The TLM monitor directly provides accurate, actionable, clearance-to-
ground distance. See Figure 1.
Figure 1: TLM Conductor Monitor Figure 2: Location of LiDAR measurement
taken from installed conductor monitor
The distance of the nearest object to the conductor is measured using an on-board LiDAR (i.e., Light
Detection And Ranging) sensor providing a highly accurate (+/-0.3% at 40m) line clearance
measurement regardless of tower or insulator motion, varying span lengths, or other line conditions [6].
See Figure 2.
The particular application need facing ENMAX required knowledge of the clearance between the co-
located138kV and 25kV lines along line for a length of 9.3km. The sensor’s LiDAR unit performs a
measurement sweep perpendicular to the conductor as part of its method to correct for conductor rotation
due to heating, conductor swing, and to adapt to under build and undergrowth. However, this sweep
does not allow for the accurate measurement from the 138kV line directly to the 25kV line below; the
25kV conductor presents too small of a target. To address this situation, it was decided to mount a sensor
in the lowest phase of the 138kV line and the nearest phase of the 25kV circuit. See Figures 3 and 4.
Measurements would then be taken from each conductor to ground, with the difference between the two
measurements being the clearance between the conductors.
Figure3 (left): Photo of parallel 138kV
and 25kV lines
Figure 4 (right): End view perspective
Lindsey Publication Number 11T-001 CROSSING CONDUCTOR TLM • October 2015
4
4. INSTALLATION AND COMMISSIONING
The initial project involved the installation of two TLM
monitors each in two locations, for a total of four TLM
monitors. Being pilot installations, the locations were
chosen by ENMAX based on ease of access and proximity
to the substation in which the communication gateway was
installed, eliminating the need for any repeaters. Both spans
were along the same straight right-of-way, so both spans
were exposed to similar conditions. The spans were 115m
and 107m in length. Even though the two sites were
physically close, the presence of a small body of water
resulted in a 5km drive between the installation sites. The
monitors were installed using bare hand, live line
installation methods. See Figure 5. The total elapsed time
from arrival on site of the contractor crew to their departure was four hours. Figure 6 shows one set of
the TLM conductor monitors immediately after installation.
The monitors are self-powered from the
magnetic field associated with the line’s
current. Closing the clamp-style
monitor body energizes the power
supply charging circuit. This allowed
the monitors to immediately begin
communicating via built-in 915 MHz
mesh radios to each other, and
ultimately to a rack-mounted
communication gateway that had been
previously installed in a nearby
substation. The communication gateway
was set up to communicate to
ENMAX’s SCADA system via DNP 3.0
protocol. The mesh radios allow direct
communication from one TLM monitor
to the next at distances up to 2km,
depending upon terrain. Because of the
proximity of the four monitors, only one
communication gateway was required to collect the data and interface with ENMAX’s SCADA system.
Note that up to 100 TLM monitors could be used with one communication gateway.
5. TRAFFIC ISSUE AND RESOLUTION
A site survey was completed before the installation. Figure 7 shows the environment around the line and
where the conductor monitors would be installed. The lines are adjacent to a fairly busy light industrial
commercial area with a fair amount of vehicle traffic. Although the sensors at each site are located
roughly vertical from each other, it was identified that passing vehicular traffic may result in a sudden
change in the reported distance to ground of the conductors, and during the vehicle’s transit, possibly
even a step change in the reported conductor-to-conductor clearance. See Figure 8.
The TLM conductor monitors pass along their raw data to the communication gateway which collects
the raw data and processes it to fit the application. In this case the gateway was programmed with an
algorithm that looks for step changes of 1m or greater in either the line-to-ground clearance reported by
a given conductor monitor, or in the difference between monitor sets, which represents the line crossing
clearance. If such a step difference is seen, the gateway reports the measurement through SCADA but
also reports via a separate SCADA point that the data is suspect, allowing ENMAX’s SCADA system
to disregard that measurement.
Figure 5: Live line installation of sensor
Figure 6: Installation of two line-mounted LiDAR measuring
units on co-located transmission and distribution circuits
Lindsey Publication Number 11T-001 CROSSING CONDUCTOR TLM • October 2015
5
6. EXPERIENCE
The system as described is now
operational and is providing
continuous, real-time clearance data
between the 138kV and 25kV
distribution lines. At the time of this
paper, ENMAX is only monitoring
the data and no operational actions
are being taken.
Figure 9 shows the measured
clearance between the two lines at
one of the TLM monitor locations
for a one day period, June 8, 2015.
The dashed line is the nominal
NESC required clearance per Table
233-1. The actual clearance ranges
from 3.7m to 6.0m during the
course of the day, or a 2.3m change
between the two lines. As would be expected, examination of the underlying data shows most of the
change is due to the 138kV line; only 0.3m of clearance difference was due to the 25kV distribution
line. While there were moderate winds present in the afternoon that could result in some blowout, for
the conductor used, this would account for approximately 0.5m of this difference. The current on the
138kV line ranged from 111A to 319A over the day. This change would not result in appreciable sag
for the size of the conductor used. Therefore this change in clearance over the course of the day seemed
much greater than expected.
Figure 9: Measured clearance on June 8, 2015 between the 138kV and 25kV lines at Span A based on
one conductor mounted LiDAR-based monitor pair
As mentioned previously, two sets of spans were monitored. As the 25kV line clearance to ground varied
little, the focus was brought to the 138kV spans. Figure 10 shows the clearance to ground over the course
of the day of each of these two spans, marked Span A and Span B. Recall that both spans are roughly
equal length at 115m and 107m (Span A and B respectively). Note that Span A is the span for which the
conductor-to-conductor clearance is shown in Figure 9.
Figure 7: Commercial / Industrial Figure 8: Possible step
environment conductor clearance distance reporting error
monitor installation due to vehicular traffic
Lindsey Publication Number 11T-001 CROSSING CONDUCTOR TLM • October 2015
6
Figure 10: Distance to ground of 138kV lines for monitored Spans A and B
Figure 11: Plan profiles of monitored Spans A and B
Here we can see that the behaviour of Span A is quite different than that of Span B. To explain this, it is
useful to examine the plan profiles of both spans as shown in Figures 11.
 Figure 10 shows the clearance to ground of Span B varies little over the course of the day (0.5m).
However, as expected, in the afternoon as the conductor heats due to ambient temperature
(approaching 32C from 3-5pm) and the modest current increase, the sag is greatest (lowest
clearance). Note that the spans adjacent to Span B are at essentially the same elevation; all the
spans will behave similarly.
 The clearance to ground of Span A has much more variation (1.8m). In addition, the variation
is opposite that of Span B; that is, in the warm afternoon, the clearance to ground increases,
meaning sag is decreasing.
 This behaviour is explained by examination of the plan profile in Figure 11. The spans on either
side of Span A are at greater elevation; the span on the right in particular. As those elevated
spans heat up (similar to Span B), those spans will sag more, exerting a pulling force on the
flexible polymer brace post insulators on either side of Span A, lifting the conductor. As a point
of reference, depending on initial tension an outward deflection of the brace post insulators on
Span A by 0.1m each will result in approximately a 1.5m increase in the conductor height.
6.1. Geometry Aspects
Two sets of geometrical issues need be addressed. The first concerns the angle at which the LiDAR
sensor is looking. The second is related to any lateral movement of the conductor. The latter is
highlighted as a result of the observed wind.
Lindsey Publication Number 11T-001 CROSSING CONDUCTOR TLM • October 2015
7
6.1.1.LiDAR Angle Correction
The LiDAR units in the conductor monitors are fixed. Therefore the LiDAR measurement is initially
based on the direction the monitor is facing. To ensure the measurements are always made in reference
to the downward facing direction the monitors contain tilt and roll sensors. The reported distance to
ground is corrected for theses measured angles. See Figure 12.
Figure 12: Tilt and Roll Correction Figure 13: Lateral Conductor Movement Geometry
6.1.2.Lateral Conductor Movement Error
Recall that the overall concern is in measuring to ensure conductor clearances are not violated. The
most critical case is when there is no, or very little, wind. This, with high current flow, will cause the
most critical minimum clearance condition and the difference between the two LiDAR measurements
will give the true conductor clearance. This is indicated by Line A in Figure 13.
The second geometric issue arises from conductor movement due to wind. Conductors in wind are not
stationary; they will swing back and forth as the wind blows and gusts and the conductor will follow
their own swing paths as shown in Figure 12. Therefore it is possible that the 138kV and 25kV
conductors will not be in the same plane at the time of any given measurement. Recall that the algorithm
used simply subtracts the tilt/roll corrected 138kv line distance-to-ground from the equivalent 25kV line
distance-to-ground. This is shown as Line C in the Figure.
As it is possible for the LiDAR units to take their measurements at any time, it is possible an
instantaneous error in measured clearance will occur, as Line C is shorter than Line B. However this
error will be in a conservative direction, effectively under-reporting clearance. This direction of error
is favorable considering the goal is to verify conductor clearances are not violated. However, it is most
important to note that as the 138kV and 25kV conductors are not linked, their swinging in relation to
each other is random. As such, this random motion causes them to occasionally cross underneath each
other. At this point they again lay in the same plane and their vertical separation will be a minimum,
equal to Line A, which is again derived by simple subtraction of the two line-to-ground distance
measurements. Therefore even when wind is present, the method will return either the actual conductor-
to-conductor clearance, or some value slightly smaller than actual. In no case will the system be reporting
greater clearance than is occurring.
Based on the above, it was determined that there was no need to compensate for any such measurement
error due to lateral conductor movement.
6.1.3.Miscellaneous Observations
 During windy conditions, significant conductor cooling will result, which will tend to increase
clearance compared to the critical case. Therefore even in the case of notable lateral conductor
movement, the clearance of concern will not become critical.
 Both line designs are such that there is effectively no insulator movement contribution; the 25kV
circuit is on rigid pin insulators, and the 138kV line uses a brace post design.
Lindsey Publication Number 11T-001 CROSSING CONDUCTOR TLM • October 2015
8
7. FUTURE PLANS
For the future, ENMAX intends on installing additional monitor pairs along the path where the lines are
co-located. Because the conductor monitors also provide (+/-1%) line current measurements, conductor
temperature, ground temperature and conductor vibration measurements, ENMAX is considering plans
to take advantage of this data and implement a pilot dynamic line rating system based on their output.
BIBLIOGRAPHY
[1] McCall, J., Spillane, P, Chappell, M., “Real-Time Monitoring Of Crossing Conductor Clearance
Using Line-Mounted LiDAR,” CIGRÉ Canada Conference, Winnipeg, Manitoba, September
2015
[2] “National Electric Safety Code”, 2007 Edition, Accredited Standards Committee C2-2007,
Institute of Electrical and Electronics Engineers, New York City, NY, 2006
[3] IEEE 738-2006, IEEE Standard for Calculating the Current-Temperature of Bare Overhead
Conductors, IEEE Power Engineering Society
[4] CIGRE TB 207, Thermal Behavior of Overhead Conductors, August 2002
[5] “Facility Ratings Assurance Best Practices – White Paper”, P. Shah, North American Reliability
Corporation, Atlanta, Georgia, March 2014, p5.
[6] U.S. Patents 7,786,894 and 8,738,318. Other U.S. and foreign patents pending.
Lindsey Publication Number 11T-001 CROSSING CONDUCTOR TLM • October 2015

More Related Content

What's hot

Simulation and analysis of HVDC on MATLAB and PSCAD
Simulation and analysis of HVDC on MATLAB and PSCADSimulation and analysis of HVDC on MATLAB and PSCAD
Simulation and analysis of HVDC on MATLAB and PSCADVishal Bhimani
 
GENERATING OF HIGH ALTERNATING VOLTAGE
GENERATING OF HIGH ALTERNATING VOLTAGEGENERATING OF HIGH ALTERNATING VOLTAGE
GENERATING OF HIGH ALTERNATING VOLTAGEJamil Abdullah
 
High voltage transmission
High voltage transmissionHigh voltage transmission
High voltage transmissionSHIVLAL MOHAL
 
Concept of energy transmission & distribution
Concept of energy transmission & distribution Concept of energy transmission & distribution
Concept of energy transmission & distribution ZunAib Ali
 
Hvdc transmission
Hvdc transmissionHvdc transmission
Hvdc transmissionsipr
 
hvdc transimission line
hvdc transimission linehvdc transimission line
hvdc transimission lineMohd Sohail
 
315564438 hvdc-transmission-ppt
315564438 hvdc-transmission-ppt315564438 hvdc-transmission-ppt
315564438 hvdc-transmission-pptLaveen Raghunam
 
TESTING AND COMMISSIONING OF VSC HVDC SYSTEMS
TESTING AND COMMISSIONING OF VSC HVDC SYSTEMSTESTING AND COMMISSIONING OF VSC HVDC SYSTEMS
TESTING AND COMMISSIONING OF VSC HVDC SYSTEMSPower System Operation
 
Basis principles of hvdc
Basis principles of hvdcBasis principles of hvdc
Basis principles of hvdcrakesh_rath
 
Construction EHV Transmission Line
Construction EHV Transmission LineConstruction EHV Transmission Line
Construction EHV Transmission LineSURESH GOPAL
 
Theory of HVDC transmission
Theory of HVDC transmission Theory of HVDC transmission
Theory of HVDC transmission SAURAV DAYAL SING
 
Lightning Characteristics and Impulse Voltage.
Lightning Characteristics and Impulse Voltage.Lightning Characteristics and Impulse Voltage.
Lightning Characteristics and Impulse Voltage.Milton Sarker
 
Multi-terminal HVDC systems and ancillary services
Multi-terminal HVDC systems and ancillary servicesMulti-terminal HVDC systems and ancillary services
Multi-terminal HVDC systems and ancillary servicesUniversité de Liège (ULg)
 
Grounding pad mounted transformers
Grounding   pad mounted transformersGrounding   pad mounted transformers
Grounding pad mounted transformersJimmy Chaparro
 

What's hot (20)

Hvdc transmission
Hvdc transmissionHvdc transmission
Hvdc transmission
 
Simulation and analysis of HVDC on MATLAB and PSCAD
Simulation and analysis of HVDC on MATLAB and PSCADSimulation and analysis of HVDC on MATLAB and PSCAD
Simulation and analysis of HVDC on MATLAB and PSCAD
 
HVDC & FACTS
HVDC & FACTSHVDC & FACTS
HVDC & FACTS
 
GENERATING OF HIGH ALTERNATING VOLTAGE
GENERATING OF HIGH ALTERNATING VOLTAGEGENERATING OF HIGH ALTERNATING VOLTAGE
GENERATING OF HIGH ALTERNATING VOLTAGE
 
Transmission line Project
Transmission line ProjectTransmission line Project
Transmission line Project
 
High voltage transmission
High voltage transmissionHigh voltage transmission
High voltage transmission
 
Basics of hvdc
Basics of hvdc Basics of hvdc
Basics of hvdc
 
Concept of energy transmission & distribution
Concept of energy transmission & distribution Concept of energy transmission & distribution
Concept of energy transmission & distribution
 
Hvdc transmission
Hvdc transmissionHvdc transmission
Hvdc transmission
 
hvdc transimission line
hvdc transimission linehvdc transimission line
hvdc transimission line
 
315564438 hvdc-transmission-ppt
315564438 hvdc-transmission-ppt315564438 hvdc-transmission-ppt
315564438 hvdc-transmission-ppt
 
“HOT LINE CLEANING ROBOT USED IN TRANSMISSION LINE AND SUBSTATION”
“HOT LINE CLEANING ROBOT USED IN TRANSMISSION LINE AND SUBSTATION”“HOT LINE CLEANING ROBOT USED IN TRANSMISSION LINE AND SUBSTATION”
“HOT LINE CLEANING ROBOT USED IN TRANSMISSION LINE AND SUBSTATION”
 
TESTING AND COMMISSIONING OF VSC HVDC SYSTEMS
TESTING AND COMMISSIONING OF VSC HVDC SYSTEMSTESTING AND COMMISSIONING OF VSC HVDC SYSTEMS
TESTING AND COMMISSIONING OF VSC HVDC SYSTEMS
 
Basis principles of hvdc
Basis principles of hvdcBasis principles of hvdc
Basis principles of hvdc
 
Construction EHV Transmission Line
Construction EHV Transmission LineConstruction EHV Transmission Line
Construction EHV Transmission Line
 
Theory of HVDC transmission
Theory of HVDC transmission Theory of HVDC transmission
Theory of HVDC transmission
 
Lightning Characteristics and Impulse Voltage.
Lightning Characteristics and Impulse Voltage.Lightning Characteristics and Impulse Voltage.
Lightning Characteristics and Impulse Voltage.
 
EHV AC
EHV ACEHV AC
EHV AC
 
Multi-terminal HVDC systems and ancillary services
Multi-terminal HVDC systems and ancillary servicesMulti-terminal HVDC systems and ancillary services
Multi-terminal HVDC systems and ancillary services
 
Grounding pad mounted transformers
Grounding   pad mounted transformersGrounding   pad mounted transformers
Grounding pad mounted transformers
 

Similar to Determining Crossing Conductor Clearance Using Line-Mounted LiDAR

Optimal Placement of Distributed Generation on Radial Distribution System for...
Optimal Placement of Distributed Generation on Radial Distribution System for...Optimal Placement of Distributed Generation on Radial Distribution System for...
Optimal Placement of Distributed Generation on Radial Distribution System for...IJMER
 
01-120917022737-phpapp02.pdf
01-120917022737-phpapp02.pdf01-120917022737-phpapp02.pdf
01-120917022737-phpapp02.pdfThien Phan Bản
 
Analysis of Fault Detection and its Location using Microcontroller for Underg...
Analysis of Fault Detection and its Location using Microcontroller for Underg...Analysis of Fault Detection and its Location using Microcontroller for Underg...
Analysis of Fault Detection and its Location using Microcontroller for Underg...IRJET Journal
 
Design aspects of high voltage transmission line
Design aspects of high voltage transmission lineDesign aspects of high voltage transmission line
Design aspects of high voltage transmission linejournalBEEI
 
NTDC 220kV Transmission gird station Internship report
NTDC 220kV Transmission gird station Internship reportNTDC 220kV Transmission gird station Internship report
NTDC 220kV Transmission gird station Internship reportAneel-k Suthar
 
Chapter 2 transmission line parameters
Chapter 2  transmission line parametersChapter 2  transmission line parameters
Chapter 2 transmission line parametersfiraoltemesgen1
 
Arc Fault and Flash Signal Analysis and Detection in DC Distribution Systems ...
Arc Fault and Flash Signal Analysis and Detection in DC Distribution Systems ...Arc Fault and Flash Signal Analysis and Detection in DC Distribution Systems ...
Arc Fault and Flash Signal Analysis and Detection in DC Distribution Systems ...IRJET Journal
 
System design-engineering-j jicable11-0279_final-evolution-in-method-performa...
System design-engineering-j jicable11-0279_final-evolution-in-method-performa...System design-engineering-j jicable11-0279_final-evolution-in-method-performa...
System design-engineering-j jicable11-0279_final-evolution-in-method-performa...nak maneth
 
Performance of quadrilateral relay on EHV transmission line protection during...
Performance of quadrilateral relay on EHV transmission line protection during...Performance of quadrilateral relay on EHV transmission line protection during...
Performance of quadrilateral relay on EHV transmission line protection during...IDES Editor
 
UNDERGROUND CABLE FAULT DISTANCE LOCATOR
UNDERGROUND CABLE FAULT DISTANCE LOCATORUNDERGROUND CABLE FAULT DISTANCE LOCATOR
UNDERGROUND CABLE FAULT DISTANCE LOCATORijiert bestjournal
 
A COMPREHENSIVE REVIEW OF DC MICROGRID PROTECTION TECHNIQUES
A COMPREHENSIVE REVIEW OF DC MICROGRID PROTECTION TECHNIQUESA COMPREHENSIVE REVIEW OF DC MICROGRID PROTECTION TECHNIQUES
A COMPREHENSIVE REVIEW OF DC MICROGRID PROTECTION TECHNIQUESIRJET Journal
 
Algorithem Algorithem and Programme for Computation of Forces Acting on line ...
Algorithem Algorithem and Programme for Computation of Forces Acting on line ...Algorithem Algorithem and Programme for Computation of Forces Acting on line ...
Algorithem Algorithem and Programme for Computation of Forces Acting on line ...CSCJournals
 
Voltage Profile Improvement using Switched Capacitors: Case of Single Wire Ea...
Voltage Profile Improvement using Switched Capacitors: Case of Single Wire Ea...Voltage Profile Improvement using Switched Capacitors: Case of Single Wire Ea...
Voltage Profile Improvement using Switched Capacitors: Case of Single Wire Ea...IJMERJOURNAL
 
Detection of Underground Cable Fault using Arduino
Detection of Underground Cable Fault using ArduinoDetection of Underground Cable Fault using Arduino
Detection of Underground Cable Fault using ArduinoIRJET Journal
 
Coautor en Revista JCR, International Transactions on Electrical Energy Syste...
Coautor en Revista JCR, International Transactions on Electrical Energy Syste...Coautor en Revista JCR, International Transactions on Electrical Energy Syste...
Coautor en Revista JCR, International Transactions on Electrical Energy Syste...Grupo Termoeléctrico La Pereda-Hunosa
 
HIGH VOLTAGE DIRECT CURRENT TRANSMISSION.pdf
HIGH VOLTAGE DIRECT CURRENT TRANSMISSION.pdfHIGH VOLTAGE DIRECT CURRENT TRANSMISSION.pdf
HIGH VOLTAGE DIRECT CURRENT TRANSMISSION.pdfEMERSON EDUARDO RODRIGUES
 
Abhishek scada ppt
Abhishek scada pptAbhishek scada ppt
Abhishek scada pptanilakib
 
Abhishek scada ppt
Abhishek scada pptAbhishek scada ppt
Abhishek scada pptanilakib
 
Techno economic study of series current limiting reactor and its impact in th...
Techno economic study of series current limiting reactor and its impact in th...Techno economic study of series current limiting reactor and its impact in th...
Techno economic study of series current limiting reactor and its impact in th...Alexander Decker
 

Similar to Determining Crossing Conductor Clearance Using Line-Mounted LiDAR (20)

Optimal Placement of Distributed Generation on Radial Distribution System for...
Optimal Placement of Distributed Generation on Radial Distribution System for...Optimal Placement of Distributed Generation on Radial Distribution System for...
Optimal Placement of Distributed Generation on Radial Distribution System for...
 
01-120917022737-phpapp02.pdf
01-120917022737-phpapp02.pdf01-120917022737-phpapp02.pdf
01-120917022737-phpapp02.pdf
 
Analysis of Fault Detection and its Location using Microcontroller for Underg...
Analysis of Fault Detection and its Location using Microcontroller for Underg...Analysis of Fault Detection and its Location using Microcontroller for Underg...
Analysis of Fault Detection and its Location using Microcontroller for Underg...
 
Design aspects of high voltage transmission line
Design aspects of high voltage transmission lineDesign aspects of high voltage transmission line
Design aspects of high voltage transmission line
 
NTDC 220kV Transmission gird station Internship report
NTDC 220kV Transmission gird station Internship reportNTDC 220kV Transmission gird station Internship report
NTDC 220kV Transmission gird station Internship report
 
Chapter 2 transmission line parameters
Chapter 2  transmission line parametersChapter 2  transmission line parameters
Chapter 2 transmission line parameters
 
B1102030610
B1102030610B1102030610
B1102030610
 
Arc Fault and Flash Signal Analysis and Detection in DC Distribution Systems ...
Arc Fault and Flash Signal Analysis and Detection in DC Distribution Systems ...Arc Fault and Flash Signal Analysis and Detection in DC Distribution Systems ...
Arc Fault and Flash Signal Analysis and Detection in DC Distribution Systems ...
 
System design-engineering-j jicable11-0279_final-evolution-in-method-performa...
System design-engineering-j jicable11-0279_final-evolution-in-method-performa...System design-engineering-j jicable11-0279_final-evolution-in-method-performa...
System design-engineering-j jicable11-0279_final-evolution-in-method-performa...
 
Performance of quadrilateral relay on EHV transmission line protection during...
Performance of quadrilateral relay on EHV transmission line protection during...Performance of quadrilateral relay on EHV transmission line protection during...
Performance of quadrilateral relay on EHV transmission line protection during...
 
UNDERGROUND CABLE FAULT DISTANCE LOCATOR
UNDERGROUND CABLE FAULT DISTANCE LOCATORUNDERGROUND CABLE FAULT DISTANCE LOCATOR
UNDERGROUND CABLE FAULT DISTANCE LOCATOR
 
A COMPREHENSIVE REVIEW OF DC MICROGRID PROTECTION TECHNIQUES
A COMPREHENSIVE REVIEW OF DC MICROGRID PROTECTION TECHNIQUESA COMPREHENSIVE REVIEW OF DC MICROGRID PROTECTION TECHNIQUES
A COMPREHENSIVE REVIEW OF DC MICROGRID PROTECTION TECHNIQUES
 
Algorithem Algorithem and Programme for Computation of Forces Acting on line ...
Algorithem Algorithem and Programme for Computation of Forces Acting on line ...Algorithem Algorithem and Programme for Computation of Forces Acting on line ...
Algorithem Algorithem and Programme for Computation of Forces Acting on line ...
 
Voltage Profile Improvement using Switched Capacitors: Case of Single Wire Ea...
Voltage Profile Improvement using Switched Capacitors: Case of Single Wire Ea...Voltage Profile Improvement using Switched Capacitors: Case of Single Wire Ea...
Voltage Profile Improvement using Switched Capacitors: Case of Single Wire Ea...
 
Detection of Underground Cable Fault using Arduino
Detection of Underground Cable Fault using ArduinoDetection of Underground Cable Fault using Arduino
Detection of Underground Cable Fault using Arduino
 
Coautor en Revista JCR, International Transactions on Electrical Energy Syste...
Coautor en Revista JCR, International Transactions on Electrical Energy Syste...Coautor en Revista JCR, International Transactions on Electrical Energy Syste...
Coautor en Revista JCR, International Transactions on Electrical Energy Syste...
 
HIGH VOLTAGE DIRECT CURRENT TRANSMISSION.pdf
HIGH VOLTAGE DIRECT CURRENT TRANSMISSION.pdfHIGH VOLTAGE DIRECT CURRENT TRANSMISSION.pdf
HIGH VOLTAGE DIRECT CURRENT TRANSMISSION.pdf
 
Abhishek scada ppt
Abhishek scada pptAbhishek scada ppt
Abhishek scada ppt
 
Abhishek scada ppt
Abhishek scada pptAbhishek scada ppt
Abhishek scada ppt
 
Techno economic study of series current limiting reactor and its impact in th...
Techno economic study of series current limiting reactor and its impact in th...Techno economic study of series current limiting reactor and its impact in th...
Techno economic study of series current limiting reactor and its impact in th...
 

More from Lindsey-USA Transmission and Manufacturing Co.

More from Lindsey-USA Transmission and Manufacturing Co. (16)

Distribution Rollers Multi Conductor
Distribution Rollers Multi ConductorDistribution Rollers Multi Conductor
Distribution Rollers Multi Conductor
 
Distribution Specialty Stringing Rollers
Distribution Specialty Stringing Rollers Distribution Specialty Stringing Rollers
Distribution Specialty Stringing Rollers
 
Distributed horizontal Dumping Roller
Distributed horizontal Dumping RollerDistributed horizontal Dumping Roller
Distributed horizontal Dumping Roller
 
Lindsey ERS Questionnaire
Lindsey ERS QuestionnaireLindsey ERS Questionnaire
Lindsey ERS Questionnaire
 
Ferc1000 march
Ferc1000 marchFerc1000 march
Ferc1000 march
 
Ers ladwp
Ers ladwpErs ladwp
Ers ladwp
 
Ers public-power
Ers public-powerErs public-power
Ers public-power
 
Pole Line Hardware Fail Safe Bases
Pole Line Hardware Fail Safe BasesPole Line Hardware Fail Safe Bases
Pole Line Hardware Fail Safe Bases
 
Pole Line Hardware Dead End Adapter
Pole Line Hardware Dead End AdapterPole Line Hardware Dead End Adapter
Pole Line Hardware Dead End Adapter
 
Pole Line Hardware
Pole Line HardwarePole Line Hardware
Pole Line Hardware
 
Tie top-vertical-clamps-10-2015
Tie top-vertical-clamps-10-2015Tie top-vertical-clamps-10-2015
Tie top-vertical-clamps-10-2015
 
Dynamic line rating as a means to enhance transmission grid resilience
Dynamic line rating as a means to enhance transmission grid resilienceDynamic line rating as a means to enhance transmission grid resilience
Dynamic line rating as a means to enhance transmission grid resilience
 
Canductors clamps
Canductors clampsCanductors clamps
Canductors clamps
 
07 t 005-ers-public-power
07 t 005-ers-public-power07 t 005-ers-public-power
07 t 005-ers-public-power
 
07 t 002-control-risk
07 t 002-control-risk07 t 002-control-risk
07 t 002-control-risk
 
Dynamic line rating as a means to enhance transmission grid resilience
Dynamic line rating as a means to enhance transmission grid resilienceDynamic line rating as a means to enhance transmission grid resilience
Dynamic line rating as a means to enhance transmission grid resilience
 

Recently uploaded

College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Glass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesGlass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesPrabhanshu Chaturvedi
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGSIVASHANKAR N
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...Call Girls in Nagpur High Profile
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdfKamal Acharya
 

Recently uploaded (20)

College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Glass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesGlass Ceramics: Processing and Properties
Glass Ceramics: Processing and Properties
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 

Determining Crossing Conductor Clearance Using Line-Mounted LiDAR

  • 1. †jmccall@lindsey-usa.com Determining Crossing Conductor Clearance Using Line-Mounted LiDAR J. C. MCCALL†, P. SPILLANE, K. LINDSEY Lindsey Manufacturing USA SUMMARY Maintaining proper transmission line clearance is required by the North American Electric Reliability Corporation (NERC). Locations where two lines cross or are co-located along a common right-of-way pose a difficult monitoring challenge: determining the clearance between the crossing lines. While the National Electric Safety Code details what these clearances should be and how they should be estimated based on a variety of criteria, these calculations do not provide confirmation of actual clearance or of the clearance itself. This becomes particularly important when the loading characteristics of the crossing lines vary significantly, or if future system changes may result in unpredictable clearances. In this case the sag characteristics of each line cannot be assumed to result in a consistent clearance value, as each line may be loaded differently as they are often on different circuits. The spatial difference of the lines can also result in different wind levels and a difference in the rate of cooling of the conductors. ENMAX, a utility located in the Province of Alberta in Canada, faced this situation where a 138kV transmission line with Curlew conductor is located above a 25 kV distribution circuit using Hawk conductor for a distance of approximately 9.3 km. The pending energization of a new local 800MW generation source made knowledge of the clearance between the two circuits more critical as the additional generation will change power flows and result in very different load profiles on the 138kV transmission circuit. ENMAX installed four transmission line conductor monitors containing built-in downward-looking LiDAR units to provide the line-to-ground clearance of each line. The difference in the line’s clearances-to-ground provided clearance between the two circuits. The paper discusses ENMAX’s situation, the operational characteristics of the monitors, their installation, the communication method used to collect the measurement information and pass it back to EMS, an algorithm used to filter out bad data caused by motor vehicles passing under the lines, and operational experience to date. KEYWORDS Clearance, LiDAR, conductor monitor, line crossing, conductor crossing, line clearance, dynamic line rating 21, rue d’Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2015 Grid of the Future Symposium Lindsey Publication Number 11T-001 CROSSING CONDUCTOR TLM • October 2015
  • 2. 2 1. INTRODUCTION Maintaining proper clearance-to-ground for transmission lines is a requirement of utilities by the North American Electric Reliability Corporation (NERC). While transmission line profiles are kept and maintained by utility engineering departments, and validated by periodic LiDAR measurements from helicopter or ground based measuring devices, these methods capture only point-in-time snapshots of clearance. One situation which is peculiarly problematic is when two lines cross or are co-located along a common right-of-way. In this case it is important to not only measure the clearance-to-ground of the lowest line, but also the clearance between the closest adjacent conductors of the two lines. ENMAX, a utility located in the Province of Alberta in Canada, faced this situation where a 138kV transmission line is located above a 25 kV distribution circuit for a distance of approximately 9.3 km. The need to know, in real-time, the clearance between the two circuits was to become more critical when later in 2015 ENMAX’s Shepard Energy Centre comes on line, bringing 800MW of additional power generation to the area[1]. 2. CROSSING LINES; THE ISSUE OF CLEARANCE The required clearances between crossing transmission lines of various voltages are well documented. In North America, Sections 233 and 235 of the National Electric Safety Code (NESC) [2] details the clearance requirements for crossing lines mounted on different supporting structures and the same supporting structures respectively. Examination of these sections highlights various issues that underscore the complexity of determining clearance:  Conductor characteristics  Ambient temperature and wind assumptions (for conductor movement)  Insulator and structure deflection  Sag, which itself is a function of conductor temperature, wind speed (for cooling), solar radiation, ice loading, etc.  Application of various safety factors and configuration factors Most if not all of these issues are also common to determining conductor thermal behavior as documented in the IEEE 738 [3] standard and the CIGRE 207 [4] brochure. Dynamic line rating (DLR) applications all depend on being able to accurately determine conductor clearance to what is below, whether in real-time or forecasted. For both dynamic line rating and crossing conductors, “clearance-to-something” is the real issue. Both of the dynamic line rating standards and the NESC depend upon essentially a double estimation; the computation of conductor sag and the subsequent use of that parameter to estimate clearance. Sag is a value that is distinctly different than clearance. Sag is essentially the droop of a conductor below the straight line drawn between its two endpoints. Variables that affect sag:  Conductor temperature and all that affects it; current, solar radiation, cooling associated with wind, the thermal insulating effects of ice and snow, etc.  The location of the endpoints; insulator swing and tower movement from wind and conductor expansion/contraction, the weight effects of ice and snow loading, etc. And yet sag does not give clearance, which also depends on the location of what it beneath; ground, snow cover, vegetation growth, and human activity (construction of buildings or vehicles). The difficulties associated with accurately determining and designing for proper clearance between conductors is underscored in one widely distributed report that for one utility, fully 60% of all documented transmission clearance issues were the result of distribution crossings [5]. Here, the problem facing ENMAX was particularly challenging:  The transmission and distribution lines had very different loading profiles. Lindsey Publication Number 11T-001 CROSSING CONDUCTOR TLM • October 2015
  • 3. 3  After the Shepard Energy Centre is on-line, the 800MW of additional power generation in the area would change power flows and result in very different load profiles on the 138kV transmission circuit than before.  Again, after the Shepard Energy Centre is on-line, identified system contingencies could result in greatly increased conductor sag. Since clearance is what ultimately matters, ENMAX chose to approach the potential problem with the co-located 138kV and 25kV lines by actually measuring the clearance between the lines in real-time. 3. CONDUCTOR MOUNTED LiDAR To accomplish the required real-time direct conductor clearance, ENMAX chose to use a novel conductor mounted monitor called the TLM® conductor monitor. This device provides a complete picture of conductor behavior including actual conductor clearance-to-ground, conductor temperature, line current, and vibration. The TLM monitor directly provides accurate, actionable, clearance-to- ground distance. See Figure 1. Figure 1: TLM Conductor Monitor Figure 2: Location of LiDAR measurement taken from installed conductor monitor The distance of the nearest object to the conductor is measured using an on-board LiDAR (i.e., Light Detection And Ranging) sensor providing a highly accurate (+/-0.3% at 40m) line clearance measurement regardless of tower or insulator motion, varying span lengths, or other line conditions [6]. See Figure 2. The particular application need facing ENMAX required knowledge of the clearance between the co- located138kV and 25kV lines along line for a length of 9.3km. The sensor’s LiDAR unit performs a measurement sweep perpendicular to the conductor as part of its method to correct for conductor rotation due to heating, conductor swing, and to adapt to under build and undergrowth. However, this sweep does not allow for the accurate measurement from the 138kV line directly to the 25kV line below; the 25kV conductor presents too small of a target. To address this situation, it was decided to mount a sensor in the lowest phase of the 138kV line and the nearest phase of the 25kV circuit. See Figures 3 and 4. Measurements would then be taken from each conductor to ground, with the difference between the two measurements being the clearance between the conductors. Figure3 (left): Photo of parallel 138kV and 25kV lines Figure 4 (right): End view perspective Lindsey Publication Number 11T-001 CROSSING CONDUCTOR TLM • October 2015
  • 4. 4 4. INSTALLATION AND COMMISSIONING The initial project involved the installation of two TLM monitors each in two locations, for a total of four TLM monitors. Being pilot installations, the locations were chosen by ENMAX based on ease of access and proximity to the substation in which the communication gateway was installed, eliminating the need for any repeaters. Both spans were along the same straight right-of-way, so both spans were exposed to similar conditions. The spans were 115m and 107m in length. Even though the two sites were physically close, the presence of a small body of water resulted in a 5km drive between the installation sites. The monitors were installed using bare hand, live line installation methods. See Figure 5. The total elapsed time from arrival on site of the contractor crew to their departure was four hours. Figure 6 shows one set of the TLM conductor monitors immediately after installation. The monitors are self-powered from the magnetic field associated with the line’s current. Closing the clamp-style monitor body energizes the power supply charging circuit. This allowed the monitors to immediately begin communicating via built-in 915 MHz mesh radios to each other, and ultimately to a rack-mounted communication gateway that had been previously installed in a nearby substation. The communication gateway was set up to communicate to ENMAX’s SCADA system via DNP 3.0 protocol. The mesh radios allow direct communication from one TLM monitor to the next at distances up to 2km, depending upon terrain. Because of the proximity of the four monitors, only one communication gateway was required to collect the data and interface with ENMAX’s SCADA system. Note that up to 100 TLM monitors could be used with one communication gateway. 5. TRAFFIC ISSUE AND RESOLUTION A site survey was completed before the installation. Figure 7 shows the environment around the line and where the conductor monitors would be installed. The lines are adjacent to a fairly busy light industrial commercial area with a fair amount of vehicle traffic. Although the sensors at each site are located roughly vertical from each other, it was identified that passing vehicular traffic may result in a sudden change in the reported distance to ground of the conductors, and during the vehicle’s transit, possibly even a step change in the reported conductor-to-conductor clearance. See Figure 8. The TLM conductor monitors pass along their raw data to the communication gateway which collects the raw data and processes it to fit the application. In this case the gateway was programmed with an algorithm that looks for step changes of 1m or greater in either the line-to-ground clearance reported by a given conductor monitor, or in the difference between monitor sets, which represents the line crossing clearance. If such a step difference is seen, the gateway reports the measurement through SCADA but also reports via a separate SCADA point that the data is suspect, allowing ENMAX’s SCADA system to disregard that measurement. Figure 5: Live line installation of sensor Figure 6: Installation of two line-mounted LiDAR measuring units on co-located transmission and distribution circuits Lindsey Publication Number 11T-001 CROSSING CONDUCTOR TLM • October 2015
  • 5. 5 6. EXPERIENCE The system as described is now operational and is providing continuous, real-time clearance data between the 138kV and 25kV distribution lines. At the time of this paper, ENMAX is only monitoring the data and no operational actions are being taken. Figure 9 shows the measured clearance between the two lines at one of the TLM monitor locations for a one day period, June 8, 2015. The dashed line is the nominal NESC required clearance per Table 233-1. The actual clearance ranges from 3.7m to 6.0m during the course of the day, or a 2.3m change between the two lines. As would be expected, examination of the underlying data shows most of the change is due to the 138kV line; only 0.3m of clearance difference was due to the 25kV distribution line. While there were moderate winds present in the afternoon that could result in some blowout, for the conductor used, this would account for approximately 0.5m of this difference. The current on the 138kV line ranged from 111A to 319A over the day. This change would not result in appreciable sag for the size of the conductor used. Therefore this change in clearance over the course of the day seemed much greater than expected. Figure 9: Measured clearance on June 8, 2015 between the 138kV and 25kV lines at Span A based on one conductor mounted LiDAR-based monitor pair As mentioned previously, two sets of spans were monitored. As the 25kV line clearance to ground varied little, the focus was brought to the 138kV spans. Figure 10 shows the clearance to ground over the course of the day of each of these two spans, marked Span A and Span B. Recall that both spans are roughly equal length at 115m and 107m (Span A and B respectively). Note that Span A is the span for which the conductor-to-conductor clearance is shown in Figure 9. Figure 7: Commercial / Industrial Figure 8: Possible step environment conductor clearance distance reporting error monitor installation due to vehicular traffic Lindsey Publication Number 11T-001 CROSSING CONDUCTOR TLM • October 2015
  • 6. 6 Figure 10: Distance to ground of 138kV lines for monitored Spans A and B Figure 11: Plan profiles of monitored Spans A and B Here we can see that the behaviour of Span A is quite different than that of Span B. To explain this, it is useful to examine the plan profiles of both spans as shown in Figures 11.  Figure 10 shows the clearance to ground of Span B varies little over the course of the day (0.5m). However, as expected, in the afternoon as the conductor heats due to ambient temperature (approaching 32C from 3-5pm) and the modest current increase, the sag is greatest (lowest clearance). Note that the spans adjacent to Span B are at essentially the same elevation; all the spans will behave similarly.  The clearance to ground of Span A has much more variation (1.8m). In addition, the variation is opposite that of Span B; that is, in the warm afternoon, the clearance to ground increases, meaning sag is decreasing.  This behaviour is explained by examination of the plan profile in Figure 11. The spans on either side of Span A are at greater elevation; the span on the right in particular. As those elevated spans heat up (similar to Span B), those spans will sag more, exerting a pulling force on the flexible polymer brace post insulators on either side of Span A, lifting the conductor. As a point of reference, depending on initial tension an outward deflection of the brace post insulators on Span A by 0.1m each will result in approximately a 1.5m increase in the conductor height. 6.1. Geometry Aspects Two sets of geometrical issues need be addressed. The first concerns the angle at which the LiDAR sensor is looking. The second is related to any lateral movement of the conductor. The latter is highlighted as a result of the observed wind. Lindsey Publication Number 11T-001 CROSSING CONDUCTOR TLM • October 2015
  • 7. 7 6.1.1.LiDAR Angle Correction The LiDAR units in the conductor monitors are fixed. Therefore the LiDAR measurement is initially based on the direction the monitor is facing. To ensure the measurements are always made in reference to the downward facing direction the monitors contain tilt and roll sensors. The reported distance to ground is corrected for theses measured angles. See Figure 12. Figure 12: Tilt and Roll Correction Figure 13: Lateral Conductor Movement Geometry 6.1.2.Lateral Conductor Movement Error Recall that the overall concern is in measuring to ensure conductor clearances are not violated. The most critical case is when there is no, or very little, wind. This, with high current flow, will cause the most critical minimum clearance condition and the difference between the two LiDAR measurements will give the true conductor clearance. This is indicated by Line A in Figure 13. The second geometric issue arises from conductor movement due to wind. Conductors in wind are not stationary; they will swing back and forth as the wind blows and gusts and the conductor will follow their own swing paths as shown in Figure 12. Therefore it is possible that the 138kV and 25kV conductors will not be in the same plane at the time of any given measurement. Recall that the algorithm used simply subtracts the tilt/roll corrected 138kv line distance-to-ground from the equivalent 25kV line distance-to-ground. This is shown as Line C in the Figure. As it is possible for the LiDAR units to take their measurements at any time, it is possible an instantaneous error in measured clearance will occur, as Line C is shorter than Line B. However this error will be in a conservative direction, effectively under-reporting clearance. This direction of error is favorable considering the goal is to verify conductor clearances are not violated. However, it is most important to note that as the 138kV and 25kV conductors are not linked, their swinging in relation to each other is random. As such, this random motion causes them to occasionally cross underneath each other. At this point they again lay in the same plane and their vertical separation will be a minimum, equal to Line A, which is again derived by simple subtraction of the two line-to-ground distance measurements. Therefore even when wind is present, the method will return either the actual conductor- to-conductor clearance, or some value slightly smaller than actual. In no case will the system be reporting greater clearance than is occurring. Based on the above, it was determined that there was no need to compensate for any such measurement error due to lateral conductor movement. 6.1.3.Miscellaneous Observations  During windy conditions, significant conductor cooling will result, which will tend to increase clearance compared to the critical case. Therefore even in the case of notable lateral conductor movement, the clearance of concern will not become critical.  Both line designs are such that there is effectively no insulator movement contribution; the 25kV circuit is on rigid pin insulators, and the 138kV line uses a brace post design. Lindsey Publication Number 11T-001 CROSSING CONDUCTOR TLM • October 2015
  • 8. 8 7. FUTURE PLANS For the future, ENMAX intends on installing additional monitor pairs along the path where the lines are co-located. Because the conductor monitors also provide (+/-1%) line current measurements, conductor temperature, ground temperature and conductor vibration measurements, ENMAX is considering plans to take advantage of this data and implement a pilot dynamic line rating system based on their output. BIBLIOGRAPHY [1] McCall, J., Spillane, P, Chappell, M., “Real-Time Monitoring Of Crossing Conductor Clearance Using Line-Mounted LiDAR,” CIGRÉ Canada Conference, Winnipeg, Manitoba, September 2015 [2] “National Electric Safety Code”, 2007 Edition, Accredited Standards Committee C2-2007, Institute of Electrical and Electronics Engineers, New York City, NY, 2006 [3] IEEE 738-2006, IEEE Standard for Calculating the Current-Temperature of Bare Overhead Conductors, IEEE Power Engineering Society [4] CIGRE TB 207, Thermal Behavior of Overhead Conductors, August 2002 [5] “Facility Ratings Assurance Best Practices – White Paper”, P. Shah, North American Reliability Corporation, Atlanta, Georgia, March 2014, p5. [6] U.S. Patents 7,786,894 and 8,738,318. Other U.S. and foreign patents pending. Lindsey Publication Number 11T-001 CROSSING CONDUCTOR TLM • October 2015