SlideShare a Scribd company logo
1 of 6
Download to read offline
B.10.4 8th International Conference on Insulated Power Cables B.10.4
Jicable’11 – 19 – 23 June 2011, Versailles - France
EVOLUTION IN METHOD AND PERFORMANCE FOR BONDING THE
METAL SCREEN OF UG HV POWER CABLE
David DUBOIS (1), Pierre MIREBEAU (1), Pascal STREIT (1), Didier LIEMANS (1), Mohamed MAMMERI (2),
Franck MICHON(3), Minh NGUYEN TUAN (4), Aude BARRALON(5)
1 – Nexans, david.dubois@nexans.com, pierre.mirebeau@nexans.com, pascal.streit@nexans.com
didier.liemans@nexans.com
2 – Sileccable mohamed.mammeri@sileccable.com
3 – Prysmian franck.michon@prysmian.com
4 – EDF minh-2.nguyen-tuan@edf.fr
5 – RTE aude.barralon@rte-france.com
ABSTRACT
The paper presents the economical reasons for
expanding the cable shipping length, the different
technical obstacles that have to be overcome and the
resulting evolution of the performances required by the
increase in potential stresses applied to the secondary
insulation.
Different novelties in bonding diagram such as “direct
cross bonding” are explained, highlighting their benefit as
well as their prerequisites and drawbacks.
The use of longer shipping lengths as well as of “direct
cross-bonding” method supposes that an accurate and
thorough study of the electrical stress applied to joint
shield break is carried out as part of the basic design of
the link.
New concept of the electrical components around the
cable joint is presented and its benefits on classic design
are explained.
PRESENT AND FUTURE
Economy is leading the world. For many years the
standard shipping length for UG HV and EHV cable was
in the range of 500m, sometimes less.
This value was due to different limitations such as:
• Production equipment like impregnating tanks, take-
up units, etc.
• Testing equipment like maximum current of test
transformers or maximal capacitance of the test
object
• Transport in term of drum size and weight
• Last but not least regulation restriction on the
maximum standing voltages along the metal
sheath/screen.
By having longer lengths per shipping drum the hardware
cost, the labour cost and the civil work cost are reduced.
Costs of maintenance are also linked to the number of
accessories along a UG power line.
• Civil work cost
It is including the cost of joint bays and associated pits
that house the cross-bonding boxes.
• Labour cost
Mounting joint can represent 25 percent of the total
installation cost.
• Hardware cost
Hardware encompasses the joints with their possible
monitoring system as well as the bonding leads and
cabinets with or without SVL’s.
In fact the limitation on maximum sheath standing
voltages put a brake to an increase of the unitary shipping
length. Some countries were limiting the maximum
standing to values as low as 65V. Some are still. The
graph in Fig.1 shows that keeping such limit prevents any
kind of change in the maximum allowed distance between
joints. However the demand for UG transmission line
tends toward larger transmission capacity then the
problem of standing voltages has become more and more
penalising.
In France the maximum allowed standing voltage for line
where public access is prohibited is 400V. That particular
feature of the French regulation makes possible the
extension of shipping lengths up to 2000m and more.
Fig.1 induced voltage versus the ratio of cable spacing
over metal screen diameter
When the obstacle of maximum standing voltage is
removed there is still to address the problem of induced
voltage under short-circuit condition.
Combining longer lengths and short-circuit current that
can reach 63kA and even more makes necessary to take
care of the rating of the SVL that are protecting the screen
interruption of joints.
Another direction to reduce the cost of UG cable power
line is to decrease the amount of protections put on the
different joints along the route, irrespective of the section
length between them. This second track has been called
“direct cross-bonding”. .
B.10.4 8th International Conference on Insulated Power Cables B.10.4
Jicable’11 – 19 – 23 June 2011, Versailles - France
Both directions towards more economical UG power lines
have the following prerequisites:
• A very good and reliable knowledge of the network
(overhead lines and their design, resistance of earth
grids, short-circuit current and duration, etc…),
• Data on impact of thunder lightnings and their effects
(magnitude, frequency, seasonal and local variation) .
CROSS-BONDING DESIGNS
Generalities
Cross bonding consists essentially in sectionalizing the
cable sheaths along the route into elementary sections
and cross connecting them so as to approximately
neutralize the total induced voltage in three consecutive
sections.
Lightning strokes cause the propagation of surge waves in
underground links they are connected with.
The magnitude of the overvoltages that stress the screen
interruptions at cross-bonding locations decreases with
the distance to the end.
As a consequence, the overvoltages in the middle
sections are likely to be lower than the withstand level of
the screen interruption in shield break joints [1] [2] even if
not protected by SVL.
Evolution of the Cross-bonding design in
France
Sectionalised cross-bonding is used [3]. Cables are
transposed to limit induced voltages in neighbouring
networks. The screen interruptions are protected by surge
arresters connected to the shield break joints through
coaxial bonding leads, maximum 10 m in length. These
arresters are star connected, and the neutral point is
grounded. They are located in a manhole, designed to
contain the effect of an internal arcing.
Up to now, the nominal voltage was limited to 6 kV.
In order to increase shipping lengths, a study has been
lead.
The results confirm:
- The possibility to use a 12 kV arrester instead of the
6 kV ;
- The need to test equipments according to the withstand
levels specified in the French standard C-33-254 [4]
given in Table 1.
For impulse levels, international recommendations from
CIGRE and IEC are given in brackets, if they are different.
In addition, a.c. withstand levels are also required, and
a.c. tests are carried out as type tests
.
Nominal voltage of the link (kV) 36/63 (72,5) 52/90 (100) 130/225 (245) 230/400 (420)
Lightning impulse voltage for main insulation (kVc) 325 450 1050 1425
Screen to ground impulse withstand level (kVc) 50 (30) 50 (37,5) 50 (47,5) 62,5
Impulse withstand level for screen interruption (kVc) 80 (60) 80 (75) 100 (95) 125
Screen to ground a.c. withstand level (kV) (15min.) 20 20 20 20
a.c. withstand level for screen interruption (kV 15min.) 25 25 25 35
Table 1 : Withstand levels specified in French standard C-33-254
Direct cross-bonding
In the case of the so called “direct cross bonding”, the
reliability of the system is totally dependent on the
integrity of the insulating shield interruption. The dielectric
strengths, and the ac, impulse, and switching surge
withstand levels of the interruptions have to be
established and coordinated with the calculated
magnitudes of ac and transient voltages for the circuit.
INSULATION COORDINATION STUDIES
To compare the overvoltages likely to occur in the grid
with the withstand level of shield break joints; studies
were carried out, using EMTP-RV software. Main features
and results are presented below.
Description of the configuration
A single-circuit siphon is considered (see Fig.2).
Overhead
Line
Overhead
Line
Span length = 400m
Network
Fig. 2: studied configuration
B.10.4 8th International Conference on Insulated Power Cables B.10.4
Jicable’11 – 19 – 23 June 2011, Versailles - France
The overhead line is protected by 2 sky wires with a D.C.
resistance 0.24Ω/km. The towers height is 20m, the
grounding impedance is 10Ω. The withstand voltage of
their insulator strings is 900kV for 225kV grid.
1600mm² Cu XLPE cables are laid in ducts in trefoil
formation (0.2m spacing)
The soil resistivity is 100Ω.m.
The main insulation of the cable is protected by surge
arresters installed at both terminals, connected by a 3m
long lead to the grounding electrode of the first tower.
The screen interruptions are protected by 12kV surge
arresters.
Modelling
The modelling follows IEC 60071.4 [5] recommendations.
Representation of the sections of the underground cable
The sections of the underground cable were represented
using the FDQ model [6] [7].
Overhead line
Spans in the vicinity of the siphon were represented using
the FDLINE model. Corona effect has not been taken into
account. Spans far from the siphon have been
represented by single long line avoiding unrealistic
reflections.
Towers were represented as loss-less lines. The
characteristic impedance is 150Ω; the wave velocity has
been taken equal to the velocity of light in vacuum.
The grounding electrodes of the towers were represented
as a constant resistance, except for those just before the
underground cable, which has been represented taking
into account soil ionisation [2].
Air gap
They were represented as an ideal switch closing when
the voltage between its terminals reaches the withstand
voltage of the air gap.
Connections between the overhead line and the
underground cable
They were represented as lumped inductances (1 μH/m).
Surge arresters
Surge arresters were modelled as a non-linear element
with U(I) 8/20μs characteristic of the arresters. An
inductance added to the connection account for the
change of characteristic when steeper fronts are
considered.
Surge arrester leads
Lumped inductances were used.
Lightning stroke
The CIGRE Concave [8] model was used.
Results
The upper curves show the phase to remote earth voltage
at cross-bonding locations and the lower curves display
the voltage stressing the screen interruptions.
In the first case, SVL are installed only at the 2 ending
major sections; in the second case, SVL are installed
within the 3 sections. The magnitude of the overvoltages
is roughly the same.
The sheath overvoltages within the second major section
exceed 62.5kV only for lightning strokes with high
magnitude. One has to keep in mind that the computed
overvoltages refer to the remote earth, so that
overvoltages applied to the sheath are significantly lower.
The screen interruption overvoltages are lower than
100kV, with or without surge arresters.
Results of same study for 225kV lines were published in
CIGRE Technical Brochure 283 [2]
It is worthy to remind that the median lightning current
magnitude is about 30 kA and the probability of a current
higher than is 150 kA is about 0.05 %.
Fig 3: Study for a 400kV siphon – 3 major sections.
B.10.4 8th International Conference on Insulated Power Cables B.10.4
4
Jicable’11 – 19 – 23 June 2011, Versailles - France
POWER FREQUENCY ISSUES
Basic features
For trefoil cables, the voltage of each screen to earth
during a 3-phase symmetrical fault (external to the cables)
is given by the well-known formula Electra 28 [9] or 128
[10]:
I
L
d
S
Ln
E .
.
.
2
.
.
2
.






=
π
μ
ω
where ω is the circular frequency, μ is the magnetic
permeability of vacuum, d is the screen mean diameter, S
is the spacing between cables, L is the length of minor
sections and I is the short-circuit current.
Voltages between screens which stress joints screen
interruptions are equal and are given by √3 times the
voltage of each screen to earth E.
In case of phase to phase fault, the theoretical maximum
voltage between screens is 2 times E [9], but, in practical
situations screen currents flow in the screens and reduce
the screen voltages below this level [10].
During a single phase earth fault, external to cables,
screen to earth voltages depend strongly on the earthing
resistances at the ends of the circuit which determine the
return current path, but voltages between screens may be
easily derived since the return current through the screens
divides between the 3 screens in parallel. In that case the
maximum voltage is simply E.
Electra 128 states that, in case of single phase to earth
fault, internal to cables, the maximum voltages between
screens do not exceed those due to external fault.
This is more or less in line with the CIGRE Brochure 347
[11] which states that the maximum voltage may be larger
than the voltage occurring in three -phase faults if:
• The screen resistance is “high”.
• The fault is fed mainly by one side.
• The magnitudes of the 3-phase and the phase to earth
short-circuit currents are similar.
So, for design purpose, the highest power frequency
voltage between screens can generally be taken as √3.E.
Earth Potential Rises
As already mentioned, the calculation of the screen to
earth voltages which stress joints coverings and SVL is
easy only in case of 3-phase faults.
Electra 128 and CIGRE Brochure 347 point out some
configurations where earth potential rises may lead to
excessive screen to earth voltage with respect to the
withstand level of SVL if they are star connected with the
star point earthed.
Power-frequency over-voltages likely to occur during
single-phase to earth faults in the French HV and EHV
networks were determined with the Complex Impedance
Matrices method, as presented in CIGRE Brochure 347.
The following conclusions were drawn:
• In 63 and 90 kV links, as the single-phase short-circuit
current is smaller than the three-phase short-circuit
current, EPR caused by the fault current flowing
through the earthings do not lead to excessive
overvoltages at the cross-bonding points of cross-
bonded links.
• In 225 and 400kV links between two substations, EPR
are not excessive provided that earth resistances in
the substations are low and similar (typically less than
4Ω).
• In 225 and 400kV systems involving an underground
link connected to a substation and an overhead line, or
a siphon, excessive overvoltages are likely to occur at
the faulted underground link to overhead line
transition, if the fault current is close to the nominal
value.
In this latter case, the installation of an earth continuity
conductor is an efficient solution to limit overvoltages that
can appear on sheath SVL.
However, in 400kV links, EPR at underground link to
overhead line transitions lead to overvoltages on cable
oversheath and joint covering exceeding their rating, if the
fault current flowing through the overhead line is higher
than about 30kA. It is then possible to limit the metal
sheath potential rises by reducing significantly the length
of minor sections.
The above conclusions do not apply to underground links
connected to an overhead line without skywire. In such a
configuration, excessive overvoltages may occur even if
earth resistances are low.
NOVELTIES IN BONDING DIAGRAM
Cross-bonding design is usually made by concentric
bonding leads with each conductor connected to each
cable screen in screen interruption HV joints and
connected to a cross-bonding link box.
The link boxes can be either installed underground
(directly buried or inside a dedicated manhole) or on a
frame above the ground (which is not recommended).
Each of these link boxes is equipped with surge arresters
which are here to limit over voltage either on outer sheath
or on joint screen interruption.
Fig. 4. Standard cross-bonding connection with concentric
bonding leads
B.10.4 8th International Conference on Insulated Power Cables B.10.4
5
Jicable’11 – 19 – 23 June 2011, Versailles - France
Advantages:
• Short lengths of cable outer sheath can be tested
separately (between each shield break joint)
• Easy fault localization (by screen disconnection inside
link boxes)
Disadvantages:
• Requires SVL maintenance
• Above ground link boxes can be easily damaged
• Risks in case of link box internal arcing
As described in the previous section this design needs to
remain on first major section on each end of long
underground cable links.
But studies have shown that such cross link boxes can be
avoided between the 2 extreme major sections by doing a
so called "direct cross-bonding".
This design consists to use single core bonding leads to
make joint screen cross-bonding directly from one joint to
the others inside the joint-bay.
Fig. 5 Direct cross-bonding connections
One positive feature of the standard cross-bonding
system is that owing the different link boxes it is easy to
locate sheath fault. A fully direct cross-bonding system
would not provide easy fault location because:
• Outer sheath tests cannot be segmented.
• Fault localization is more difficult as a test made on
outer sheath integrity change from one phase to
another phase at each shield break joint.
To avoid this drawback the following departures are
applied
• For very long links, in order to divide the link in shorter
segments some earthed joints with screen interruption
have to be used. The 6 single-core bonding leads
(concentric cables can be used as well) are connected
to earth via an earthing box.
Fig. 6 Bonding to earth through earthing box using
concentric leads with possible disconnection
Practical experience with direct cross bonding has been
achieved on 2000mm² Alu XLPE 150kV links as shown in
figure 7. The shield break joint has been successfully
tested according IEC 60 840 tests of outer protection
(Annex H) where the sheath sectionalizing insulation has
been submitted to 150kVp impulses level instead to
75kVp.
Fig 7. Earthing System using Direct Cross Bonding
B.10.4 8th International Conference on Insulated Power Cables B.10.4
6
Jicable’11 – 19 – 23 June 2011, Versailles - France
NEW CONCEPT FOR ACCESSORIES
The use of the direct cross-bonding system makes
necessary new types of accessory as shown on the
following schematic diagram
Shield
break
joint
Shield
break
joint
Shield
break
joint
Shield
break
joint
Shield
break
joint
Shield
break
joint
Earthing
joint
Earthing
joint
Crossbonding
cabinet
Cross
bonding
cabinet
Cross
bonding
cabinet
UnitsectionrepeatedNtimes
Earthing
cabinet
Earthing
cabinet
Fig. .8. Schematic diagram of a UG power cable line featuring some direct cross-bonding sections [12]
Sections between A to D and G to J are with a standard
cross-bonding system. Sections between D and G use the
direct cross-bonding system. Three different types of
joints and their associated hardware are represented:
• Joints with direct connection to earth
• Joints with cross-bonding connections : the screen
interruption is protected with SVL’s
• Joints with direct cross-bonding connections : the
screen interruption is not protected against
overvoltages.
Different technological solutions can be applied to
address the functional requirements listed above. Three
different specifications for bonding leads are identified:
• Single core bonding lead directly connected to earth
• Single core bonding lead to connect two joints
• Coaxial bonding lead for classic cross-bonding
connection between joint and cross-bonding box.
These three types have a different technical specification
based on their functional requirements.
In principle they have to feature the same performances
as the different components which they are bonded to.
CONCLUSION
To achieve more economical long HV UG lines on the
French network the design rules have been studied to
cover longer cable length between accessories and less
protection hardware for the screen interruptions.
Meanwhile the performances of the material has been
improved and so the tests to check them. Namely a.c.
voltage is now part of the test program.
To verify that the incurred increase of potential stresses
on the joints remains acceptable thorough studies of the
induced voltages under surges conditions were
necessary.
RTE is currently studying their optimisation to the French
power transmission system.
GLOSSARY
UG: Underground
HV-EHV: High Voltage, Extra High Voltage
SVL: Surge Voltage Limiter or surge arrester.
EPR: Earth Potential Rise
REFERENCES
[1] A.Gille et al “Double 150 kV link, 32km long, in
Belgium : design and construction” - 2004 – CIGRE
report B1-305
[2] CIGRE Technical Brochure 283 Special Bonding of
High Voltage Cable Oct. 2005
[3] CIGRE 2000 Dorison et al - 400 kV underground links
for bulk power transmission. New developments in
the field of XLPE insulated cables
[4] French standard NFC 33.254 Insulated cables and
their accessories for power systems
[5] IEC 60071.4 – “Computational Guide to Insulation
Co-ordination and Modelling of Electrical Networks”
2004
[6] EMTP-RV online documentation
[7] Hermann Dommel – EMTP Theory Book
[8] CIGRE 63 brochure – Guide to procedures for
estimating the lightning performance of transmission
lines
[9] The design of specially bonded cable systems
against sheath overvoltages – Electra 28 – 1973
[10] Guide to the protection of specially bonded cable
systems against sheath overvoltage – Electra 128–
1990
[11] CIGRE Technical Brochure 347 Earth Potential Rises
in specially bonded systems - June 2008
[12] French dispositions for bonding the metal screen of
UG HV power cable – RST part 7 – October 2010

More Related Content

What's hot

Simulation and detection of transients on a 150kV HV Cable-paper
Simulation and detection of transients on a 150kV HV Cable-paperSimulation and detection of transients on a 150kV HV Cable-paper
Simulation and detection of transients on a 150kV HV Cable-paperThomas Mathew
 
Analysis of Co-Axial Cable Response to 700m Long Digital Data Transmission.
Analysis of Co-Axial Cable Response to 700m Long Digital Data Transmission.Analysis of Co-Axial Cable Response to 700m Long Digital Data Transmission.
Analysis of Co-Axial Cable Response to 700m Long Digital Data Transmission.iosrjce
 
Underground cables
Underground cablesUnderground cables
Underground cablesAnu71
 
Power cable technology in cesc ltd
Power cable technology in cesc ltdPower cable technology in cesc ltd
Power cable technology in cesc ltdAritra Sarkar
 
Power Cables Operation, Maintenance, Location and Fault Detection
Power Cables Operation, Maintenance, Location and Fault DetectionPower Cables Operation, Maintenance, Location and Fault Detection
Power Cables Operation, Maintenance, Location and Fault DetectionLiving Online
 
Factors considered for High Voltage Cable Joint design
Factors considered for High Voltage Cable Joint design Factors considered for High Voltage Cable Joint design
Factors considered for High Voltage Cable Joint design Shahab Khan
 
Edf R&D Xemard Coupling Between Transmission Underground Cables And Pipelines
Edf R&D Xemard Coupling Between Transmission Underground Cables And PipelinesEdf R&D Xemard Coupling Between Transmission Underground Cables And Pipelines
Edf R&D Xemard Coupling Between Transmission Underground Cables And Pipelinescorinne rocherieux
 
1.8 overhead vs underground system
1.8 overhead vs underground system1.8 overhead vs underground system
1.8 overhead vs underground systemW3Edify
 
Under ground cables presention
Under ground cables presentionUnder ground cables presention
Under ground cables presentionRazu Khan
 
Comparison of overhead and underground transmission lines
Comparison of overhead and underground transmission linesComparison of overhead and underground transmission lines
Comparison of overhead and underground transmission linesahmed usama
 
Design of 230 kV Twin Bundle Double Circuit Overhead Transmission Line
Design of 230 kV Twin Bundle Double Circuit Overhead Transmission LineDesign of 230 kV Twin Bundle Double Circuit Overhead Transmission Line
Design of 230 kV Twin Bundle Double Circuit Overhead Transmission Lineijtsrd
 
Swartley b santinia_maled_jaccinob-destructive-arcong-of-insulated-joints-in-...
Swartley b santinia_maled_jaccinob-destructive-arcong-of-insulated-joints-in-...Swartley b santinia_maled_jaccinob-destructive-arcong-of-insulated-joints-in-...
Swartley b santinia_maled_jaccinob-destructive-arcong-of-insulated-joints-in-...Gilberto Mejía
 
Power cables
Power cablesPower cables
Power cablescollege
 
Power cable - Installation methods
Power cable - Installation methodsPower cable - Installation methods
Power cable - Installation methodsLeonardo ENERGY
 
Influence choice of the injection nodes of energy source on on-line losses of...
Influence choice of the injection nodes of energy source on on-line losses of...Influence choice of the injection nodes of energy source on on-line losses of...
Influence choice of the injection nodes of energy source on on-line losses of...IJMER
 
Coaxial Cable
Coaxial CableCoaxial Cable
Coaxial CableMissAnam
 
Reducing Induced Voltages on Parallel Facilities in Shared Transmission Corri...
Reducing Induced Voltages on Parallel Facilities in Shared Transmission Corri...Reducing Induced Voltages on Parallel Facilities in Shared Transmission Corri...
Reducing Induced Voltages on Parallel Facilities in Shared Transmission Corri...Power System Operation
 

What's hot (20)

Simulation and detection of transients on a 150kV HV Cable-paper
Simulation and detection of transients on a 150kV HV Cable-paperSimulation and detection of transients on a 150kV HV Cable-paper
Simulation and detection of transients on a 150kV HV Cable-paper
 
Analysis of Co-Axial Cable Response to 700m Long Digital Data Transmission.
Analysis of Co-Axial Cable Response to 700m Long Digital Data Transmission.Analysis of Co-Axial Cable Response to 700m Long Digital Data Transmission.
Analysis of Co-Axial Cable Response to 700m Long Digital Data Transmission.
 
Underground cables
Underground cablesUnderground cables
Underground cables
 
Power cable technology in cesc ltd
Power cable technology in cesc ltdPower cable technology in cesc ltd
Power cable technology in cesc ltd
 
Power Cables Operation, Maintenance, Location and Fault Detection
Power Cables Operation, Maintenance, Location and Fault DetectionPower Cables Operation, Maintenance, Location and Fault Detection
Power Cables Operation, Maintenance, Location and Fault Detection
 
Factors considered for High Voltage Cable Joint design
Factors considered for High Voltage Cable Joint design Factors considered for High Voltage Cable Joint design
Factors considered for High Voltage Cable Joint design
 
Edf R&D Xemard Coupling Between Transmission Underground Cables And Pipelines
Edf R&D Xemard Coupling Between Transmission Underground Cables And PipelinesEdf R&D Xemard Coupling Between Transmission Underground Cables And Pipelines
Edf R&D Xemard Coupling Between Transmission Underground Cables And Pipelines
 
1.8 overhead vs underground system
1.8 overhead vs underground system1.8 overhead vs underground system
1.8 overhead vs underground system
 
Under ground cables presention
Under ground cables presentionUnder ground cables presention
Under ground cables presention
 
Ug cables
Ug cablesUg cables
Ug cables
 
Comparison of overhead and underground transmission lines
Comparison of overhead and underground transmission linesComparison of overhead and underground transmission lines
Comparison of overhead and underground transmission lines
 
Design of 230 kV Twin Bundle Double Circuit Overhead Transmission Line
Design of 230 kV Twin Bundle Double Circuit Overhead Transmission LineDesign of 230 kV Twin Bundle Double Circuit Overhead Transmission Line
Design of 230 kV Twin Bundle Double Circuit Overhead Transmission Line
 
Swartley b santinia_maled_jaccinob-destructive-arcong-of-insulated-joints-in-...
Swartley b santinia_maled_jaccinob-destructive-arcong-of-insulated-joints-in-...Swartley b santinia_maled_jaccinob-destructive-arcong-of-insulated-joints-in-...
Swartley b santinia_maled_jaccinob-destructive-arcong-of-insulated-joints-in-...
 
Power cables
Power cablesPower cables
Power cables
 
Power cable - Installation methods
Power cable - Installation methodsPower cable - Installation methods
Power cable - Installation methods
 
Influence choice of the injection nodes of energy source on on-line losses of...
Influence choice of the injection nodes of energy source on on-line losses of...Influence choice of the injection nodes of energy source on on-line losses of...
Influence choice of the injection nodes of energy source on on-line losses of...
 
Coaxial Cable
Coaxial CableCoaxial Cable
Coaxial Cable
 
Reducing Induced Voltages on Parallel Facilities in Shared Transmission Corri...
Reducing Induced Voltages on Parallel Facilities in Shared Transmission Corri...Reducing Induced Voltages on Parallel Facilities in Shared Transmission Corri...
Reducing Induced Voltages on Parallel Facilities in Shared Transmission Corri...
 
cables
cablescables
cables
 
Cable
CableCable
Cable
 

Similar to Evolution of Bonding Methods for UG Power Cables

Design and construction of underground cable transmission line
Design and construction of underground cable transmission lineDesign and construction of underground cable transmission line
Design and construction of underground cable transmission lineFazlur Rahman
 
Undergrounding high voltage_electricity_transmission_lines_the_technical_issu...
Undergrounding high voltage_electricity_transmission_lines_the_technical_issu...Undergrounding high voltage_electricity_transmission_lines_the_technical_issu...
Undergrounding high voltage_electricity_transmission_lines_the_technical_issu...Ivan Rojas Soliz
 
ARDUINO MICROCONTROLLER BASED UNDERGROUND CABLE FAULT DISTANCE LOCATOR
ARDUINO MICROCONTROLLER BASED UNDERGROUND CABLE FAULT DISTANCE LOCATORARDUINO MICROCONTROLLER BASED UNDERGROUND CABLE FAULT DISTANCE LOCATOR
ARDUINO MICROCONTROLLER BASED UNDERGROUND CABLE FAULT DISTANCE LOCATORIAEME Publication
 
IRJET-Sensitivity Analysis of Maximum Overvoltage on Cables with Considering ...
IRJET-Sensitivity Analysis of Maximum Overvoltage on Cables with Considering ...IRJET-Sensitivity Analysis of Maximum Overvoltage on Cables with Considering ...
IRJET-Sensitivity Analysis of Maximum Overvoltage on Cables with Considering ...IRJET Journal
 
A Training Report Of Saltlake 132/33kv Substation
A Training Report Of Saltlake 132/33kv SubstationA Training Report Of Saltlake 132/33kv Substation
A Training Report Of Saltlake 132/33kv SubstationSubhrajit Ghosh
 
The_insulation_of_HVDC_extruded_cable_sy.pdf
The_insulation_of_HVDC_extruded_cable_sy.pdfThe_insulation_of_HVDC_extruded_cable_sy.pdf
The_insulation_of_HVDC_extruded_cable_sy.pdfAhmed Refai ,M. Sc.,Ph. D
 
Power capacity of transmission lines
Power capacity of transmission linesPower capacity of transmission lines
Power capacity of transmission linesAlexander Decker
 
Electric Field Analysis and Impact Study with Shrubbery on the 11 kV Distribu...
Electric Field Analysis and Impact Study with Shrubbery on the 11 kV Distribu...Electric Field Analysis and Impact Study with Shrubbery on the 11 kV Distribu...
Electric Field Analysis and Impact Study with Shrubbery on the 11 kV Distribu...IRJET Journal
 
Jmv presentation smart power transmission projects cea
Jmv  presentation  smart power transmission projects  ceaJmv  presentation  smart power transmission projects  cea
Jmv presentation smart power transmission projects ceaMahesh Chandra Manav
 
ppt-of-ehv-ac-transmission-pdf.pptx
ppt-of-ehv-ac-transmission-pdf.pptxppt-of-ehv-ac-transmission-pdf.pptx
ppt-of-ehv-ac-transmission-pdf.pptxNagen87
 
Analysis of Electric Field and Current Density on XLPE Insulator
Analysis of Electric Field and Current Density on XLPE Insulator Analysis of Electric Field and Current Density on XLPE Insulator
Analysis of Electric Field and Current Density on XLPE Insulator IJECEIAES
 
COMPENSATION OF FAULT RESISTANCE IN DISTANCE RELAY FOR LONG TRANSMISSION LINE
COMPENSATION OF FAULT RESISTANCE IN DISTANCE RELAY FOR LONG TRANSMISSION LINECOMPENSATION OF FAULT RESISTANCE IN DISTANCE RELAY FOR LONG TRANSMISSION LINE
COMPENSATION OF FAULT RESISTANCE IN DISTANCE RELAY FOR LONG TRANSMISSION LINEIRJET Journal
 
Power transmission and distribution along with power qualty presentation by j...
Power transmission and distribution along with power qualty presentation by j...Power transmission and distribution along with power qualty presentation by j...
Power transmission and distribution along with power qualty presentation by j...Mahesh Chandra Manav
 

Similar to Evolution of Bonding Methods for UG Power Cables (20)

Design and construction of underground cable transmission line
Design and construction of underground cable transmission lineDesign and construction of underground cable transmission line
Design and construction of underground cable transmission line
 
Undergrounding high voltage_electricity_transmission_lines_the_technical_issu...
Undergrounding high voltage_electricity_transmission_lines_the_technical_issu...Undergrounding high voltage_electricity_transmission_lines_the_technical_issu...
Undergrounding high voltage_electricity_transmission_lines_the_technical_issu...
 
B011120723
B011120723B011120723
B011120723
 
ARDUINO MICROCONTROLLER BASED UNDERGROUND CABLE FAULT DISTANCE LOCATOR
ARDUINO MICROCONTROLLER BASED UNDERGROUND CABLE FAULT DISTANCE LOCATORARDUINO MICROCONTROLLER BASED UNDERGROUND CABLE FAULT DISTANCE LOCATOR
ARDUINO MICROCONTROLLER BASED UNDERGROUND CABLE FAULT DISTANCE LOCATOR
 
IRJET-Sensitivity Analysis of Maximum Overvoltage on Cables with Considering ...
IRJET-Sensitivity Analysis of Maximum Overvoltage on Cables with Considering ...IRJET-Sensitivity Analysis of Maximum Overvoltage on Cables with Considering ...
IRJET-Sensitivity Analysis of Maximum Overvoltage on Cables with Considering ...
 
A Training Report Of Saltlake 132/33kv Substation
A Training Report Of Saltlake 132/33kv SubstationA Training Report Of Saltlake 132/33kv Substation
A Training Report Of Saltlake 132/33kv Substation
 
A modified bridge-type nonsuperconducting fault current limiter for distribut...
A modified bridge-type nonsuperconducting fault current limiter for distribut...A modified bridge-type nonsuperconducting fault current limiter for distribut...
A modified bridge-type nonsuperconducting fault current limiter for distribut...
 
H010625867
H010625867H010625867
H010625867
 
The_insulation_of_HVDC_extruded_cable_sy.pdf
The_insulation_of_HVDC_extruded_cable_sy.pdfThe_insulation_of_HVDC_extruded_cable_sy.pdf
The_insulation_of_HVDC_extruded_cable_sy.pdf
 
H046044147
H046044147H046044147
H046044147
 
EMC for Networks - Peter Thomas, Control Specialists and Jos Knockaert, UGent
EMC for Networks - Peter Thomas, Control Specialists and Jos Knockaert, UGentEMC for Networks - Peter Thomas, Control Specialists and Jos Knockaert, UGent
EMC for Networks - Peter Thomas, Control Specialists and Jos Knockaert, UGent
 
113
113113
113
 
EMC and HFPQ for industrial networks - Jos Knockaert, UGent and Peter Thomas...
EMC and HFPQ for industrial networks -  Jos Knockaert, UGent and Peter Thomas...EMC and HFPQ for industrial networks -  Jos Knockaert, UGent and Peter Thomas...
EMC and HFPQ for industrial networks - Jos Knockaert, UGent and Peter Thomas...
 
Power capacity of transmission lines
Power capacity of transmission linesPower capacity of transmission lines
Power capacity of transmission lines
 
Electric Field Analysis and Impact Study with Shrubbery on the 11 kV Distribu...
Electric Field Analysis and Impact Study with Shrubbery on the 11 kV Distribu...Electric Field Analysis and Impact Study with Shrubbery on the 11 kV Distribu...
Electric Field Analysis and Impact Study with Shrubbery on the 11 kV Distribu...
 
Jmv presentation smart power transmission projects cea
Jmv  presentation  smart power transmission projects  ceaJmv  presentation  smart power transmission projects  cea
Jmv presentation smart power transmission projects cea
 
ppt-of-ehv-ac-transmission-pdf.pptx
ppt-of-ehv-ac-transmission-pdf.pptxppt-of-ehv-ac-transmission-pdf.pptx
ppt-of-ehv-ac-transmission-pdf.pptx
 
Analysis of Electric Field and Current Density on XLPE Insulator
Analysis of Electric Field and Current Density on XLPE Insulator Analysis of Electric Field and Current Density on XLPE Insulator
Analysis of Electric Field and Current Density on XLPE Insulator
 
COMPENSATION OF FAULT RESISTANCE IN DISTANCE RELAY FOR LONG TRANSMISSION LINE
COMPENSATION OF FAULT RESISTANCE IN DISTANCE RELAY FOR LONG TRANSMISSION LINECOMPENSATION OF FAULT RESISTANCE IN DISTANCE RELAY FOR LONG TRANSMISSION LINE
COMPENSATION OF FAULT RESISTANCE IN DISTANCE RELAY FOR LONG TRANSMISSION LINE
 
Power transmission and distribution along with power qualty presentation by j...
Power transmission and distribution along with power qualty presentation by j...Power transmission and distribution along with power qualty presentation by j...
Power transmission and distribution along with power qualty presentation by j...
 

Recently uploaded

HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...ranjana rawat
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 

Recently uploaded (20)

HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 

Evolution of Bonding Methods for UG Power Cables

  • 1. B.10.4 8th International Conference on Insulated Power Cables B.10.4 Jicable’11 – 19 – 23 June 2011, Versailles - France EVOLUTION IN METHOD AND PERFORMANCE FOR BONDING THE METAL SCREEN OF UG HV POWER CABLE David DUBOIS (1), Pierre MIREBEAU (1), Pascal STREIT (1), Didier LIEMANS (1), Mohamed MAMMERI (2), Franck MICHON(3), Minh NGUYEN TUAN (4), Aude BARRALON(5) 1 – Nexans, david.dubois@nexans.com, pierre.mirebeau@nexans.com, pascal.streit@nexans.com didier.liemans@nexans.com 2 – Sileccable mohamed.mammeri@sileccable.com 3 – Prysmian franck.michon@prysmian.com 4 – EDF minh-2.nguyen-tuan@edf.fr 5 – RTE aude.barralon@rte-france.com ABSTRACT The paper presents the economical reasons for expanding the cable shipping length, the different technical obstacles that have to be overcome and the resulting evolution of the performances required by the increase in potential stresses applied to the secondary insulation. Different novelties in bonding diagram such as “direct cross bonding” are explained, highlighting their benefit as well as their prerequisites and drawbacks. The use of longer shipping lengths as well as of “direct cross-bonding” method supposes that an accurate and thorough study of the electrical stress applied to joint shield break is carried out as part of the basic design of the link. New concept of the electrical components around the cable joint is presented and its benefits on classic design are explained. PRESENT AND FUTURE Economy is leading the world. For many years the standard shipping length for UG HV and EHV cable was in the range of 500m, sometimes less. This value was due to different limitations such as: • Production equipment like impregnating tanks, take- up units, etc. • Testing equipment like maximum current of test transformers or maximal capacitance of the test object • Transport in term of drum size and weight • Last but not least regulation restriction on the maximum standing voltages along the metal sheath/screen. By having longer lengths per shipping drum the hardware cost, the labour cost and the civil work cost are reduced. Costs of maintenance are also linked to the number of accessories along a UG power line. • Civil work cost It is including the cost of joint bays and associated pits that house the cross-bonding boxes. • Labour cost Mounting joint can represent 25 percent of the total installation cost. • Hardware cost Hardware encompasses the joints with their possible monitoring system as well as the bonding leads and cabinets with or without SVL’s. In fact the limitation on maximum sheath standing voltages put a brake to an increase of the unitary shipping length. Some countries were limiting the maximum standing to values as low as 65V. Some are still. The graph in Fig.1 shows that keeping such limit prevents any kind of change in the maximum allowed distance between joints. However the demand for UG transmission line tends toward larger transmission capacity then the problem of standing voltages has become more and more penalising. In France the maximum allowed standing voltage for line where public access is prohibited is 400V. That particular feature of the French regulation makes possible the extension of shipping lengths up to 2000m and more. Fig.1 induced voltage versus the ratio of cable spacing over metal screen diameter When the obstacle of maximum standing voltage is removed there is still to address the problem of induced voltage under short-circuit condition. Combining longer lengths and short-circuit current that can reach 63kA and even more makes necessary to take care of the rating of the SVL that are protecting the screen interruption of joints. Another direction to reduce the cost of UG cable power line is to decrease the amount of protections put on the different joints along the route, irrespective of the section length between them. This second track has been called “direct cross-bonding”. .
  • 2. B.10.4 8th International Conference on Insulated Power Cables B.10.4 Jicable’11 – 19 – 23 June 2011, Versailles - France Both directions towards more economical UG power lines have the following prerequisites: • A very good and reliable knowledge of the network (overhead lines and their design, resistance of earth grids, short-circuit current and duration, etc…), • Data on impact of thunder lightnings and their effects (magnitude, frequency, seasonal and local variation) . CROSS-BONDING DESIGNS Generalities Cross bonding consists essentially in sectionalizing the cable sheaths along the route into elementary sections and cross connecting them so as to approximately neutralize the total induced voltage in three consecutive sections. Lightning strokes cause the propagation of surge waves in underground links they are connected with. The magnitude of the overvoltages that stress the screen interruptions at cross-bonding locations decreases with the distance to the end. As a consequence, the overvoltages in the middle sections are likely to be lower than the withstand level of the screen interruption in shield break joints [1] [2] even if not protected by SVL. Evolution of the Cross-bonding design in France Sectionalised cross-bonding is used [3]. Cables are transposed to limit induced voltages in neighbouring networks. The screen interruptions are protected by surge arresters connected to the shield break joints through coaxial bonding leads, maximum 10 m in length. These arresters are star connected, and the neutral point is grounded. They are located in a manhole, designed to contain the effect of an internal arcing. Up to now, the nominal voltage was limited to 6 kV. In order to increase shipping lengths, a study has been lead. The results confirm: - The possibility to use a 12 kV arrester instead of the 6 kV ; - The need to test equipments according to the withstand levels specified in the French standard C-33-254 [4] given in Table 1. For impulse levels, international recommendations from CIGRE and IEC are given in brackets, if they are different. In addition, a.c. withstand levels are also required, and a.c. tests are carried out as type tests . Nominal voltage of the link (kV) 36/63 (72,5) 52/90 (100) 130/225 (245) 230/400 (420) Lightning impulse voltage for main insulation (kVc) 325 450 1050 1425 Screen to ground impulse withstand level (kVc) 50 (30) 50 (37,5) 50 (47,5) 62,5 Impulse withstand level for screen interruption (kVc) 80 (60) 80 (75) 100 (95) 125 Screen to ground a.c. withstand level (kV) (15min.) 20 20 20 20 a.c. withstand level for screen interruption (kV 15min.) 25 25 25 35 Table 1 : Withstand levels specified in French standard C-33-254 Direct cross-bonding In the case of the so called “direct cross bonding”, the reliability of the system is totally dependent on the integrity of the insulating shield interruption. The dielectric strengths, and the ac, impulse, and switching surge withstand levels of the interruptions have to be established and coordinated with the calculated magnitudes of ac and transient voltages for the circuit. INSULATION COORDINATION STUDIES To compare the overvoltages likely to occur in the grid with the withstand level of shield break joints; studies were carried out, using EMTP-RV software. Main features and results are presented below. Description of the configuration A single-circuit siphon is considered (see Fig.2). Overhead Line Overhead Line Span length = 400m Network Fig. 2: studied configuration
  • 3. B.10.4 8th International Conference on Insulated Power Cables B.10.4 Jicable’11 – 19 – 23 June 2011, Versailles - France The overhead line is protected by 2 sky wires with a D.C. resistance 0.24Ω/km. The towers height is 20m, the grounding impedance is 10Ω. The withstand voltage of their insulator strings is 900kV for 225kV grid. 1600mm² Cu XLPE cables are laid in ducts in trefoil formation (0.2m spacing) The soil resistivity is 100Ω.m. The main insulation of the cable is protected by surge arresters installed at both terminals, connected by a 3m long lead to the grounding electrode of the first tower. The screen interruptions are protected by 12kV surge arresters. Modelling The modelling follows IEC 60071.4 [5] recommendations. Representation of the sections of the underground cable The sections of the underground cable were represented using the FDQ model [6] [7]. Overhead line Spans in the vicinity of the siphon were represented using the FDLINE model. Corona effect has not been taken into account. Spans far from the siphon have been represented by single long line avoiding unrealistic reflections. Towers were represented as loss-less lines. The characteristic impedance is 150Ω; the wave velocity has been taken equal to the velocity of light in vacuum. The grounding electrodes of the towers were represented as a constant resistance, except for those just before the underground cable, which has been represented taking into account soil ionisation [2]. Air gap They were represented as an ideal switch closing when the voltage between its terminals reaches the withstand voltage of the air gap. Connections between the overhead line and the underground cable They were represented as lumped inductances (1 μH/m). Surge arresters Surge arresters were modelled as a non-linear element with U(I) 8/20μs characteristic of the arresters. An inductance added to the connection account for the change of characteristic when steeper fronts are considered. Surge arrester leads Lumped inductances were used. Lightning stroke The CIGRE Concave [8] model was used. Results The upper curves show the phase to remote earth voltage at cross-bonding locations and the lower curves display the voltage stressing the screen interruptions. In the first case, SVL are installed only at the 2 ending major sections; in the second case, SVL are installed within the 3 sections. The magnitude of the overvoltages is roughly the same. The sheath overvoltages within the second major section exceed 62.5kV only for lightning strokes with high magnitude. One has to keep in mind that the computed overvoltages refer to the remote earth, so that overvoltages applied to the sheath are significantly lower. The screen interruption overvoltages are lower than 100kV, with or without surge arresters. Results of same study for 225kV lines were published in CIGRE Technical Brochure 283 [2] It is worthy to remind that the median lightning current magnitude is about 30 kA and the probability of a current higher than is 150 kA is about 0.05 %. Fig 3: Study for a 400kV siphon – 3 major sections.
  • 4. B.10.4 8th International Conference on Insulated Power Cables B.10.4 4 Jicable’11 – 19 – 23 June 2011, Versailles - France POWER FREQUENCY ISSUES Basic features For trefoil cables, the voltage of each screen to earth during a 3-phase symmetrical fault (external to the cables) is given by the well-known formula Electra 28 [9] or 128 [10]: I L d S Ln E . . . 2 . . 2 .       = π μ ω where ω is the circular frequency, μ is the magnetic permeability of vacuum, d is the screen mean diameter, S is the spacing between cables, L is the length of minor sections and I is the short-circuit current. Voltages between screens which stress joints screen interruptions are equal and are given by √3 times the voltage of each screen to earth E. In case of phase to phase fault, the theoretical maximum voltage between screens is 2 times E [9], but, in practical situations screen currents flow in the screens and reduce the screen voltages below this level [10]. During a single phase earth fault, external to cables, screen to earth voltages depend strongly on the earthing resistances at the ends of the circuit which determine the return current path, but voltages between screens may be easily derived since the return current through the screens divides between the 3 screens in parallel. In that case the maximum voltage is simply E. Electra 128 states that, in case of single phase to earth fault, internal to cables, the maximum voltages between screens do not exceed those due to external fault. This is more or less in line with the CIGRE Brochure 347 [11] which states that the maximum voltage may be larger than the voltage occurring in three -phase faults if: • The screen resistance is “high”. • The fault is fed mainly by one side. • The magnitudes of the 3-phase and the phase to earth short-circuit currents are similar. So, for design purpose, the highest power frequency voltage between screens can generally be taken as √3.E. Earth Potential Rises As already mentioned, the calculation of the screen to earth voltages which stress joints coverings and SVL is easy only in case of 3-phase faults. Electra 128 and CIGRE Brochure 347 point out some configurations where earth potential rises may lead to excessive screen to earth voltage with respect to the withstand level of SVL if they are star connected with the star point earthed. Power-frequency over-voltages likely to occur during single-phase to earth faults in the French HV and EHV networks were determined with the Complex Impedance Matrices method, as presented in CIGRE Brochure 347. The following conclusions were drawn: • In 63 and 90 kV links, as the single-phase short-circuit current is smaller than the three-phase short-circuit current, EPR caused by the fault current flowing through the earthings do not lead to excessive overvoltages at the cross-bonding points of cross- bonded links. • In 225 and 400kV links between two substations, EPR are not excessive provided that earth resistances in the substations are low and similar (typically less than 4Ω). • In 225 and 400kV systems involving an underground link connected to a substation and an overhead line, or a siphon, excessive overvoltages are likely to occur at the faulted underground link to overhead line transition, if the fault current is close to the nominal value. In this latter case, the installation of an earth continuity conductor is an efficient solution to limit overvoltages that can appear on sheath SVL. However, in 400kV links, EPR at underground link to overhead line transitions lead to overvoltages on cable oversheath and joint covering exceeding their rating, if the fault current flowing through the overhead line is higher than about 30kA. It is then possible to limit the metal sheath potential rises by reducing significantly the length of minor sections. The above conclusions do not apply to underground links connected to an overhead line without skywire. In such a configuration, excessive overvoltages may occur even if earth resistances are low. NOVELTIES IN BONDING DIAGRAM Cross-bonding design is usually made by concentric bonding leads with each conductor connected to each cable screen in screen interruption HV joints and connected to a cross-bonding link box. The link boxes can be either installed underground (directly buried or inside a dedicated manhole) or on a frame above the ground (which is not recommended). Each of these link boxes is equipped with surge arresters which are here to limit over voltage either on outer sheath or on joint screen interruption. Fig. 4. Standard cross-bonding connection with concentric bonding leads
  • 5. B.10.4 8th International Conference on Insulated Power Cables B.10.4 5 Jicable’11 – 19 – 23 June 2011, Versailles - France Advantages: • Short lengths of cable outer sheath can be tested separately (between each shield break joint) • Easy fault localization (by screen disconnection inside link boxes) Disadvantages: • Requires SVL maintenance • Above ground link boxes can be easily damaged • Risks in case of link box internal arcing As described in the previous section this design needs to remain on first major section on each end of long underground cable links. But studies have shown that such cross link boxes can be avoided between the 2 extreme major sections by doing a so called "direct cross-bonding". This design consists to use single core bonding leads to make joint screen cross-bonding directly from one joint to the others inside the joint-bay. Fig. 5 Direct cross-bonding connections One positive feature of the standard cross-bonding system is that owing the different link boxes it is easy to locate sheath fault. A fully direct cross-bonding system would not provide easy fault location because: • Outer sheath tests cannot be segmented. • Fault localization is more difficult as a test made on outer sheath integrity change from one phase to another phase at each shield break joint. To avoid this drawback the following departures are applied • For very long links, in order to divide the link in shorter segments some earthed joints with screen interruption have to be used. The 6 single-core bonding leads (concentric cables can be used as well) are connected to earth via an earthing box. Fig. 6 Bonding to earth through earthing box using concentric leads with possible disconnection Practical experience with direct cross bonding has been achieved on 2000mm² Alu XLPE 150kV links as shown in figure 7. The shield break joint has been successfully tested according IEC 60 840 tests of outer protection (Annex H) where the sheath sectionalizing insulation has been submitted to 150kVp impulses level instead to 75kVp. Fig 7. Earthing System using Direct Cross Bonding
  • 6. B.10.4 8th International Conference on Insulated Power Cables B.10.4 6 Jicable’11 – 19 – 23 June 2011, Versailles - France NEW CONCEPT FOR ACCESSORIES The use of the direct cross-bonding system makes necessary new types of accessory as shown on the following schematic diagram Shield break joint Shield break joint Shield break joint Shield break joint Shield break joint Shield break joint Earthing joint Earthing joint Crossbonding cabinet Cross bonding cabinet Cross bonding cabinet UnitsectionrepeatedNtimes Earthing cabinet Earthing cabinet Fig. .8. Schematic diagram of a UG power cable line featuring some direct cross-bonding sections [12] Sections between A to D and G to J are with a standard cross-bonding system. Sections between D and G use the direct cross-bonding system. Three different types of joints and their associated hardware are represented: • Joints with direct connection to earth • Joints with cross-bonding connections : the screen interruption is protected with SVL’s • Joints with direct cross-bonding connections : the screen interruption is not protected against overvoltages. Different technological solutions can be applied to address the functional requirements listed above. Three different specifications for bonding leads are identified: • Single core bonding lead directly connected to earth • Single core bonding lead to connect two joints • Coaxial bonding lead for classic cross-bonding connection between joint and cross-bonding box. These three types have a different technical specification based on their functional requirements. In principle they have to feature the same performances as the different components which they are bonded to. CONCLUSION To achieve more economical long HV UG lines on the French network the design rules have been studied to cover longer cable length between accessories and less protection hardware for the screen interruptions. Meanwhile the performances of the material has been improved and so the tests to check them. Namely a.c. voltage is now part of the test program. To verify that the incurred increase of potential stresses on the joints remains acceptable thorough studies of the induced voltages under surges conditions were necessary. RTE is currently studying their optimisation to the French power transmission system. GLOSSARY UG: Underground HV-EHV: High Voltage, Extra High Voltage SVL: Surge Voltage Limiter or surge arrester. EPR: Earth Potential Rise REFERENCES [1] A.Gille et al “Double 150 kV link, 32km long, in Belgium : design and construction” - 2004 – CIGRE report B1-305 [2] CIGRE Technical Brochure 283 Special Bonding of High Voltage Cable Oct. 2005 [3] CIGRE 2000 Dorison et al - 400 kV underground links for bulk power transmission. New developments in the field of XLPE insulated cables [4] French standard NFC 33.254 Insulated cables and their accessories for power systems [5] IEC 60071.4 – “Computational Guide to Insulation Co-ordination and Modelling of Electrical Networks” 2004 [6] EMTP-RV online documentation [7] Hermann Dommel – EMTP Theory Book [8] CIGRE 63 brochure – Guide to procedures for estimating the lightning performance of transmission lines [9] The design of specially bonded cable systems against sheath overvoltages – Electra 28 – 1973 [10] Guide to the protection of specially bonded cable systems against sheath overvoltage – Electra 128– 1990 [11] CIGRE Technical Brochure 347 Earth Potential Rises in specially bonded systems - June 2008 [12] French dispositions for bonding the metal screen of UG HV power cable – RST part 7 – October 2010