SlideShare a Scribd company logo
1 of 62
Download to read offline
The Webinar video is available here:
https://register.gotowebinar.com/recording/4525984979424798721
Protection and local control of HVDC grids
Kees Koreman chairman JWG B4/B5.59
Webinar 15 November 2018
Introduction and positioning of the work
Main components and rationale for meshed HVDC grids
Functional requirements on protection
Short circuit phenomena
Short circuit limiting techniques
Protection system components
Protection system overview
Conclusions
Table of contents
2
Introduction and
positioning of the work
Protection and local control of HVDC grids
Webinar Cigre 15 November 2018
3
Introduction
Development of DC systems in the late 19th century
AC solutions came somewhat later
But AC systems (50 or 60 Hz) became the standard in the world
Simple transformation between different Voltage levels
Short circuit current interruption
Limited interest for DC in the second half of the 20th century
Increased interest in the last years
Renewable energy sources
Offshore solutions
4
5
Positioning of the work
Cigre B4 gained interest and started a WG B4.52
who finished their work in 2013 (TB 533)
A new WG was formed together with SC A3
JWG A3/B4.34 on DC switching equipment (TB 683)
Five areas of further work were defined
WG B4.56 on connection agreements (TB 657)
WG B4.57 on simulation models (TB 604)
WB B4.58 on load flow control (TB 699)
WG B4.60 on reliability design (TB 713)
JWG B4/B5.59 on protection (TB 739) this work
6
Main components and
rationale for meshed DC
grids
Protection and local control of HVDC grids
Webinar Cigre 15 November 2018
7
Some definitions for meshed grids and protection
Meshed system (IEV reference 131-13-16)
A set of branches forming a loop and containing only one link of
a given co-tree
Loop (IEV reference 131-13-12)
A closed path passing only once through every node in the path
Protection system (IEV reference 448-11-04)
An arrangement of one or more protection equipments, and other
devices intended to perform one or more specified protection
functions
8
Considered HVDC system designs
Consisting of two poles of opposite polarity with the same
voltage amplitude
Symmetrical monopolar system
Full bipolar system with or without metallic return
(Asymmetrical monopoles possible)
9
Converter topologies
Multi modular half-bridge converter
Cascaded two level converter
Module output voltage 0 or Vcap
In case of a DC pole to pole fault
Uncontrolled current path possible
Diode parallel to IGBT T2
Fault current cannot be blocked
AC circuit breaker needs to operate
Non fault current blocking converters
10
Converter topologies
Full-bridge converters less used
Module output voltage 0, Vcap or - Vcap
Uncontrolled current path possible
Allways incorporates the module
capacitor
Fault current blocked by converter
operation
AC circuit breaker operation not required
Fault current blocking converters
11
Developing grids
Full scale HVDC meshed grid will not emerge directly
Development through connection of individual point-to-point
connections
Adding converters and lines/cables
Develop multi terminal systems
Developing into a fully meshed grid
Possibly by using DC-DC Converters
12
Kees Koreman| October 2018
13
Functional requirements
on protection
Protection and local control of HVDC grids
Webinar Cigre 15 November 2018
14
Objectives and Requirements for Protection
Large similarity with protection in AC grids
Ensure Human safety
Fast fault clearance
Minimise impact on the system
Minimise stress on components
Protection philosophy requirements
Reliability
Speed
Sensitivity
Selectivity
15
HVDC equipment constraints
Semiconductors and power electronics
Low overcurrent widthstand capabilities
Fast temperature rise
Breakdown leads to permanent damage
Transformers and connections
Similar to HVAC systems
Overcurrents 5 – 10 times rated current
Widthstand time hundreds of ms
Prevent permanent damage
16
HVDC grid constraints
Full description derived by WG B4.56
Worst case unbalance
Sectionalised HVDC grid
Voltage profiles apply on non-faulted sections
Balanced pole voltages
Overvoltage profiles to be developed
Faulted sections need to be isolated
Tripping time considered
Brochure 657 gives 10 – 15 ms
Recent developments 3 – 6 ms
Maximum allowable Voltage profile
17
18
DC grid protection philosophies
The entire HVDC grid is seen as a single protection zone
The entire zone is switched off
By the AC breakers in all converter bays
By current control in full bridge converters
By HVDC circuit breakers in the converter connection points
The faulted section is identified and disconnected after fault
clearance with mechanical or high speed switches
Non-selective fault clearing strategy
19
DC grid protection philosophies
The entire HVDC grid is divided into several protection zones
The faulted zone is isolated from the other zones
By HVDC circuit breakers in the connection points
By DC-DC converters between the zones
By current limiters (SFCL) between the zones
The faulted section is identified and disconnected after fault
clearance with mechanical or high speed switches
Partial selective fault clearing strategy
20
DC grid protection philosophies
Each branch in the HVDC grid is a separate protection zone
The faulted branch is isolated from the other zones
By HVDC circuit breakers in the faulted branch
The faulted branch is immediately identified
Full selective fault clearing strategy
21
Kees Koreman| October 2018
Non-selective fault clearing strategy
22
Kees Koreman| October 2018
Partial selective fault clearing strategy
23
Kees Koreman| October 2018
Full selective fault clearing strategy
24
Short circuit phenomena
Protection and local control of HVDC grids
Webinar Cigre 15 November 2018
25
Fault current development
Open circuit faults can be detected by:
Redistribution of load currents
Power flow no longer matches the scheduled power flow
Focus of the brochure is on short circuit faults
Current development is highly dependent on the earthing
concept
High impedance earthing
Low impedance earthing
Earthing concept less dominant when pole-to-pole faults occur
26
Fault current development
Fault example with low impedance earthing
27
Fault current development
28
Fault current increase
General rules cannot be given
Factors to consider:
Transmission line type
Fault resistance
DC side inductance
DC side capacitance
Interruption instant
AC system strength
Converter topology
Detailed simulations are required
29
Short circuit limiting
techniques
Protection and local control of HVDC grids
Webinar Cigre 15 November 2018
30
Introduction
Invisible to the grid during normal
conditions
Act instantaneously after a fault
Significant impedance during faults
Out of action after clearance
Capability to act multiple times
31
Characteristics of current limiters
Limiting the rate-of-rise of fault currents
Currently HVDC circuit breakers have moderate interrupting
capability
Current interruption level 10 – 20 kA
Operating time 3 – 5 ms
Limiting the rate-of-rise of current will help
DC reactors
Superconducting fault current limiters
Time to reach the maximum current will increase
32
Limiting the overcurrent magnitude
The HVAC grid is the source delivering the current
Impedance between the fault and the AC sources is
determining
Transformer impedance (0,1 - 0,2 pu)
Converter impedance (< 0,1 pu)
Additional measures are required
AC resistance
DC resistance
DC – DC converters
HVDC circuit breakers
33
DC system earthing
High impedance earthing low impedance earthing
34
DC system earthing
35
DC system earthing
Conclusions
Both principles can be used in a HVDC meshed grid
High impedance earthing reduces the fault current but increases
the over-voltages on the non-faulted pole
Monopolar systems can be attached in both principles
The recommendation is to implement the low impedance
earthing given the anticipated size of the meshed HVDC grid
36
Protection system
components
Protection and local control of HVDC grids
Webinar Cigre 15 November 2018
37
Protection system algorithms
Many HVAC based algorithms are also applicable for
HVDC applications (with minor modifications)
DC overcurrent protection
Distance and differential protection
Under Voltage and Voltage unbalance protection
Specific DC algorithms to increase selectivity and
speed
Travelling wave protection
Voltage and/or current derivative protection (ROCOV
and/or ROCOC)
Simulation in the HVDC grid prepared by WG B4.57
38
Fault current distribution
This example shows the pole to earth steady
state fault current distribution in the reference
grid during a fault in the HVDC cable
between bus 1 and bus 3
DC overcurrent protection will not lead to a
fully selective operation
Alternative algorithms are needed
39
Rate-of-Change of Voltage (ROCOV)
Derivative of the voltage is determined directly from the
measured voltages
Selectivity is improved with the addition of series reactors
between the station and the measuring point
Additional advantage is the reduction of the rate of rise of the
fault current
40
Rate-of-Change of Voltage (ROCOV)
Effect of series reactor
41
Rate-of-Change of Voltage (ROCOV)
Calculation of
ROCOV in the connection point
ROCOC in the connections
Sign of ROCOV and ROCOC
Different indicates the faulted
section
Equal indicates fault outside
zone
Selective detection improved
combining ROCOV and ROCOC
42
Preliminary conclusions
regarding algorithms [1]
Best performance is obtained by rate of
change protection algorithms
Voltage change is the best indicator
Current change can assist to increase
selectivity
Other algorithms are not selective enough
but can be used to protect equipment by
offering delayed protection functions
43
Preliminary conclusions
regarding algorithms [2]
Utilisation of ROCOV only relies on local
measurements
Telecommunication between stations is not
required. Communication delay has not effect
on tripping time
Telecommunication can be supporting for
back-up protection functions. Delayed
tripping in case of a breaker failure
44
Measuring equipment
Large bandwidth is required
High pass characteristic sufficient
Current measurement
Direct shunt
Zero flux
Optical
Rogowski coil
Voltage measurement
Resistive divider
RC divider
Essential for correct operation of ROCOV and ROCOC
45
Acting equipment
Impressive development DC circuit-breakers
Various principles
Semiconductor breaker
Hybrid circuit-breaker
Resonant circuit-breaker
Mechanical with active current injection
Excellent overview is given in TB 683
Upscaling to 500 +kV possible
46
Operating principle hybrid CB
Commutation
Branch
Energy Absorption
Branch
Low
Voltage
Switch
Primary Branch
Source
Voltage
Current
Contact
Voltage
47
Operating principle hybrid CB
Commutation
Branch
Energy Absorption
Branch
Low
Voltage
Switch
Primary Branch
Source
Voltage
Current
Contact
Voltage
Low Voltage
Switch Open;
Commutation
Branch Closed
Fault
Detection
48
Operating principle hybrid CB
Energy Absorption
Branch
Low
Voltage
Switch
Primary Branch
Commutation
Branch
Source
Voltage
Current
Contact
Voltage
Commutation
Branch
Conduction
Low Voltage
Switch Open;
Commutation
Branch Closed
Fault
Detection
49
Operating principle hybrid CB
Commutation
Branch
Energy Absorption
Branch
Low
Voltage
Switch
Primary Branch
Source
Voltage
Current
Contact
Voltage
Commutation
Branch
Conduction
Low Voltage
Switch Open;
Commutation
Branch Closed
Fault
Detection
Mechanical
Switch Open
50
Operating principle hybrid CB
Commutation
Branch
Energy Absorption
Branch
Low
Voltage
Switch
Primary Branch
Source
Voltage
Current
Contact
Voltage
Commutation
Branch
Conduction
Low Voltage
Switch Open;
Commutation
Branch Closed
Fault
Detection
Mechanical
Switch Open
Energy
Absorption
Commutation
Branch OFF
51
Fault localisation
Fast fault localisation is needed to avoid long outage times
With underground cables
With submarine cables
(overhead lines)
Accuracy in the localisation limits the required amount of spare
cable
Repair strategies need to be in place
52
Basics for localisation
Offline measurements
TDR
Murray bridge
Direct analysis of fault voltages and
currents
Cigre WG B1.52 gives further analysis
53
Protection system
overview
Protection and local control of HVDC grids
Webinar Cigre 15 November 2018
54
Point – to – point protection overview
55
Connection point protection overview
56
Conclusions
Protection and local control of HVDC grids
Webinar Cigre 15 November 2018
57
Conclusions [1]
Technology has moved fast in the last years
Measuring techniques are available
Specific algorithms are tested and available
HVDC circuit breakers are available
ROCOV and ROCOC algorithms improve selectivity
No use of telecommunication between the stations
A series reactor further improves selective operation
50 or 100 mH in each pole is sufficient
Regarding the technology
58
Conclusions [2]
Three strategies are available
Non selective fault clearing
Partial selective fault clearing
Full selective fault clearing
An advise cannot be given at this stage
Depending on the size of the HVDC grid
Economical analysis needed
Detailed simulation studies are essential
Regarding the application of DC grids
59
Conclusions [3]
The technology for HVDC grids is available: ready for use!
Lines and cables
Converters and stations
DC – DC converters
DC current interruption facilities
Protection and control algorithms
It allows for the development of a meshed DC grid
Link to promotion movie: https://youtu.be/lBnWEK9IUn4
60
Copyright © 2018
This tutorial has been prepared based upon
the work of CIGRE and its Working Groups.
If it is used in total or in part, proper
reference and credit should be given to
CIGRE.
Disclaimer notice
“CIGRE gives no warranty or assurance
about the contents of this publication, nor
does it accept any responsibility, as to the
accuracy or exhaustiveness of the
information. All implied warranties and
conditions are excluded to the maximum
extent permitted by law”.
Copyright &
Disclaimer notice
61

More Related Content

What's hot

What's hot (20)

MTDC SYSTEMS
MTDC SYSTEMSMTDC SYSTEMS
MTDC SYSTEMS
 
Status of hvdc links
Status of hvdc linksStatus of hvdc links
Status of hvdc links
 
DC SIDE HARMONICS & FILTERING IN HVDC TRANSMISSION SYSTEMS
DC SIDE HARMONICS & FILTERING IN HVDC TRANSMISSION SYSTEMS DC SIDE HARMONICS & FILTERING IN HVDC TRANSMISSION SYSTEMS
DC SIDE HARMONICS & FILTERING IN HVDC TRANSMISSION SYSTEMS
 
Unit 3 FACTS Technology
Unit 3 FACTS TechnologyUnit 3 FACTS Technology
Unit 3 FACTS Technology
 
Reactive power compensation
Reactive power compensationReactive power compensation
Reactive power compensation
 
Electrostatic fields and field stress control
Electrostatic fields and field stress controlElectrostatic fields and field stress control
Electrostatic fields and field stress control
 
Unified Power Flow Controller(upfc)1
Unified Power Flow Controller(upfc)1Unified Power Flow Controller(upfc)1
Unified Power Flow Controller(upfc)1
 
Load dispatch center
Load dispatch centerLoad dispatch center
Load dispatch center
 
FAULT ANALYSIS IN HVDC & HVAC TRANSMISSION LINE
FAULT ANALYSIS IN HVDC & HVAC TRANSMISSION LINEFAULT ANALYSIS IN HVDC & HVAC TRANSMISSION LINE
FAULT ANALYSIS IN HVDC & HVAC TRANSMISSION LINE
 
Power system security
Power system security Power system security
Power system security
 
HVDC
HVDC HVDC
HVDC
 
Gcsc gto thyristor controlled series capacitor
Gcsc   gto thyristor controlled series capacitorGcsc   gto thyristor controlled series capacitor
Gcsc gto thyristor controlled series capacitor
 
Grid integration issues and solutions
Grid integration issues and solutionsGrid integration issues and solutions
Grid integration issues and solutions
 
Static var compensator
Static var compensatorStatic var compensator
Static var compensator
 
Facts
FactsFacts
Facts
 
High Voltage Direct Current Transmission System
High Voltage Direct Current Transmission SystemHigh Voltage Direct Current Transmission System
High Voltage Direct Current Transmission System
 
Voltage sag
Voltage sagVoltage sag
Voltage sag
 
Electrical substations: 132 KV
Electrical substations: 132 KV Electrical substations: 132 KV
Electrical substations: 132 KV
 
3 reactive power and voltage control
3 reactive power and voltage control3 reactive power and voltage control
3 reactive power and voltage control
 
Hvdc
HvdcHvdc
Hvdc
 

Similar to Protection and local control of HVDC grids

Group 8 hvdc
Group  8 hvdcGroup  8 hvdc
Group 8 hvdcMahesh B
 
Group 8 hvdc
Group  8 hvdcGroup  8 hvdc
Group 8 hvdcMahesh B
 
Applying Digital Isolators in Motor Control
Applying Digital Isolators in Motor ControlApplying Digital Isolators in Motor Control
Applying Digital Isolators in Motor ControlAnalog Devices, Inc.
 
HIGH VOLTAGE DIRECT CURRENT TRANSMISSION.pdf
HIGH VOLTAGE DIRECT CURRENT TRANSMISSION.pdfHIGH VOLTAGE DIRECT CURRENT TRANSMISSION.pdf
HIGH VOLTAGE DIRECT CURRENT TRANSMISSION.pdfEMERSON EDUARDO RODRIGUES
 
Power factor corrector
Power factor correctorPower factor corrector
Power factor correctorJoeChueng
 
Industry outlook_ ABB.pdf
Industry outlook_ ABB.pdfIndustry outlook_ ABB.pdf
Industry outlook_ ABB.pdfssuser8073a0
 
Faculty of Engineering and Technology.pptx
Faculty of Engineering and Technology.pptxFaculty of Engineering and Technology.pptx
Faculty of Engineering and Technology.pptxanshumaansingh310
 
Fault Detection and Isolation in Low-Voltage DC-Bus Microgrid System
Fault Detection and Isolation in Low-Voltage DC-Bus Microgrid SystemFault Detection and Isolation in Low-Voltage DC-Bus Microgrid System
Fault Detection and Isolation in Low-Voltage DC-Bus Microgrid SystemSuraj Shrestha
 
A review on hvdc circuit breakers
A review on hvdc circuit breakersA review on hvdc circuit breakers
A review on hvdc circuit breakersJuly Carranza
 
IRJET- Protection of VSC Controlled HVDCPlus System using PWM Technique
IRJET- Protection of VSC Controlled HVDCPlus System using PWM TechniqueIRJET- Protection of VSC Controlled HVDCPlus System using PWM Technique
IRJET- Protection of VSC Controlled HVDCPlus System using PWM TechniqueIRJET Journal
 
IRJET- Literature Review on Uncertainty Management in Construction Sites
IRJET- Literature Review on Uncertainty Management in Construction SitesIRJET- Literature Review on Uncertainty Management in Construction Sites
IRJET- Literature Review on Uncertainty Management in Construction SitesIRJET Journal
 
Schneider electric tc indoor
Schneider electric tc indoorSchneider electric tc indoor
Schneider electric tc indoorRosmer Ocando
 
Crouzet Aerospace - Electrical Protection & Distribution
Crouzet Aerospace - Electrical Protection & DistributionCrouzet Aerospace - Electrical Protection & Distribution
Crouzet Aerospace - Electrical Protection & DistributionCrouzet
 
High Voltage Direct Current Transmission Systems 2Mark Materials
High Voltage Direct Current Transmission Systems 2Mark MaterialsHigh Voltage Direct Current Transmission Systems 2Mark Materials
High Voltage Direct Current Transmission Systems 2Mark MaterialsSanthosh Kumar
 
Weg automation-drives-and-controls-usa804-brochure-english
Weg automation-drives-and-controls-usa804-brochure-englishWeg automation-drives-and-controls-usa804-brochure-english
Weg automation-drives-and-controls-usa804-brochure-englishDaniel García
 
HVDC System a Need for Future Power Transmission
HVDC System a Need for Future Power TransmissionHVDC System a Need for Future Power Transmission
HVDC System a Need for Future Power Transmissionijtsrd
 
Universal Four Leg v4
Universal Four Leg v4Universal Four Leg v4
Universal Four Leg v4AxelDijksman
 

Similar to Protection and local control of HVDC grids (20)

Group 8 hvdc
Group  8 hvdcGroup  8 hvdc
Group 8 hvdc
 
Group 8 hvdc
Group  8 hvdcGroup  8 hvdc
Group 8 hvdc
 
Power factor correction
Power factor correctionPower factor correction
Power factor correction
 
Applying Digital Isolators in Motor Control
Applying Digital Isolators in Motor ControlApplying Digital Isolators in Motor Control
Applying Digital Isolators in Motor Control
 
HIGH VOLTAGE DIRECT CURRENT TRANSMISSION.pdf
HIGH VOLTAGE DIRECT CURRENT TRANSMISSION.pdfHIGH VOLTAGE DIRECT CURRENT TRANSMISSION.pdf
HIGH VOLTAGE DIRECT CURRENT TRANSMISSION.pdf
 
Power factor corrector
Power factor correctorPower factor corrector
Power factor corrector
 
Industry outlook_ ABB.pdf
Industry outlook_ ABB.pdfIndustry outlook_ ABB.pdf
Industry outlook_ ABB.pdf
 
Faculty of Engineering and Technology.pptx
Faculty of Engineering and Technology.pptxFaculty of Engineering and Technology.pptx
Faculty of Engineering and Technology.pptx
 
Fault Detection and Isolation in Low-Voltage DC-Bus Microgrid System
Fault Detection and Isolation in Low-Voltage DC-Bus Microgrid SystemFault Detection and Isolation in Low-Voltage DC-Bus Microgrid System
Fault Detection and Isolation in Low-Voltage DC-Bus Microgrid System
 
circuit breakers
circuit breakerscircuit breakers
circuit breakers
 
A review on hvdc circuit breakers
A review on hvdc circuit breakersA review on hvdc circuit breakers
A review on hvdc circuit breakers
 
Hvdc system.pptx
Hvdc system.pptxHvdc system.pptx
Hvdc system.pptx
 
IRJET- Protection of VSC Controlled HVDCPlus System using PWM Technique
IRJET- Protection of VSC Controlled HVDCPlus System using PWM TechniqueIRJET- Protection of VSC Controlled HVDCPlus System using PWM Technique
IRJET- Protection of VSC Controlled HVDCPlus System using PWM Technique
 
IRJET- Literature Review on Uncertainty Management in Construction Sites
IRJET- Literature Review on Uncertainty Management in Construction SitesIRJET- Literature Review on Uncertainty Management in Construction Sites
IRJET- Literature Review on Uncertainty Management in Construction Sites
 
Schneider electric tc indoor
Schneider electric tc indoorSchneider electric tc indoor
Schneider electric tc indoor
 
Crouzet Aerospace - Electrical Protection & Distribution
Crouzet Aerospace - Electrical Protection & DistributionCrouzet Aerospace - Electrical Protection & Distribution
Crouzet Aerospace - Electrical Protection & Distribution
 
High Voltage Direct Current Transmission Systems 2Mark Materials
High Voltage Direct Current Transmission Systems 2Mark MaterialsHigh Voltage Direct Current Transmission Systems 2Mark Materials
High Voltage Direct Current Transmission Systems 2Mark Materials
 
Weg automation-drives-and-controls-usa804-brochure-english
Weg automation-drives-and-controls-usa804-brochure-englishWeg automation-drives-and-controls-usa804-brochure-english
Weg automation-drives-and-controls-usa804-brochure-english
 
HVDC System a Need for Future Power Transmission
HVDC System a Need for Future Power TransmissionHVDC System a Need for Future Power Transmission
HVDC System a Need for Future Power Transmission
 
Universal Four Leg v4
Universal Four Leg v4Universal Four Leg v4
Universal Four Leg v4
 

More from Power System Operation

Thermography test of electrical panels
Thermography test of electrical panelsThermography test of electrical panels
Thermography test of electrical panelsPower System Operation
 
Big Data Analytics for Power Grid Operations
Big Data Analytics for Power Grid OperationsBig Data Analytics for Power Grid Operations
Big Data Analytics for Power Grid OperationsPower System Operation
 
SPS to RAS Special Protection Scheme Remedial Action Scheme
SPS to RAS Special Protection Scheme  Remedial Action SchemeSPS to RAS Special Protection Scheme  Remedial Action Scheme
SPS to RAS Special Protection Scheme Remedial Action SchemePower System Operation
 
SVC PLUS Frequency Stabilizer Frequency and voltage support for dynamic grid...
SVC PLUS Frequency Stabilizer Frequency and voltage support for  dynamic grid...SVC PLUS Frequency Stabilizer Frequency and voltage support for  dynamic grid...
SVC PLUS Frequency Stabilizer Frequency and voltage support for dynamic grid...Power System Operation
 
Principles & Testing Methods Of Earth Ground Resistance
Principles & Testing Methods Of Earth Ground ResistancePrinciples & Testing Methods Of Earth Ground Resistance
Principles & Testing Methods Of Earth Ground ResistancePower System Operation
 
Gas Insulated Switchgear? Gas-Insulated High-Voltage Switchgear (GIS)
Gas Insulated Switchgear?  Gas-Insulated High-Voltage Switchgear (GIS)Gas Insulated Switchgear?  Gas-Insulated High-Voltage Switchgear (GIS)
Gas Insulated Switchgear? Gas-Insulated High-Voltage Switchgear (GIS)Power System Operation
 
Electrical Transmission Tower Types - Design & Parts
Electrical Transmission Tower  Types - Design & PartsElectrical Transmission Tower  Types - Design & Parts
Electrical Transmission Tower Types - Design & PartsPower System Operation
 
The Need for Enhanced Power System Modelling Techniques & Simulation Tools
The Need for Enhanced  Power System  Modelling Techniques  &  Simulation Tools The Need for Enhanced  Power System  Modelling Techniques  &  Simulation Tools
The Need for Enhanced Power System Modelling Techniques & Simulation Tools Power System Operation
 
Power Quality Trends in the Transition to Carbon-Free Electrical Energy System
Power Quality  Trends in the Transition to  Carbon-Free Electrical Energy SystemPower Quality  Trends in the Transition to  Carbon-Free Electrical Energy System
Power Quality Trends in the Transition to Carbon-Free Electrical Energy SystemPower System Operation
 

More from Power System Operation (20)

ENERGY TRANSITION OUTLOOK 2021
ENERGY TRANSITION OUTLOOK  2021ENERGY TRANSITION OUTLOOK  2021
ENERGY TRANSITION OUTLOOK 2021
 
Thermography test of electrical panels
Thermography test of electrical panelsThermography test of electrical panels
Thermography test of electrical panels
 
What does peak shaving mean
What does peak shaving meanWhat does peak shaving mean
What does peak shaving mean
 
What's short circuit level
What's short circuit levelWhat's short circuit level
What's short circuit level
 
Power System Restoration Guide
Power System Restoration Guide  Power System Restoration Guide
Power System Restoration Guide
 
Big Data Analytics for Power Grid Operations
Big Data Analytics for Power Grid OperationsBig Data Analytics for Power Grid Operations
Big Data Analytics for Power Grid Operations
 
SPS to RAS Special Protection Scheme Remedial Action Scheme
SPS to RAS Special Protection Scheme  Remedial Action SchemeSPS to RAS Special Protection Scheme  Remedial Action Scheme
SPS to RAS Special Protection Scheme Remedial Action Scheme
 
Substation Neutral Earthing
Substation Neutral EarthingSubstation Neutral Earthing
Substation Neutral Earthing
 
SVC PLUS Frequency Stabilizer Frequency and voltage support for dynamic grid...
SVC PLUS Frequency Stabilizer Frequency and voltage support for  dynamic grid...SVC PLUS Frequency Stabilizer Frequency and voltage support for  dynamic grid...
SVC PLUS Frequency Stabilizer Frequency and voltage support for dynamic grid...
 
Principles & Testing Methods Of Earth Ground Resistance
Principles & Testing Methods Of Earth Ground ResistancePrinciples & Testing Methods Of Earth Ground Resistance
Principles & Testing Methods Of Earth Ground Resistance
 
Gas Insulated Switchgear? Gas-Insulated High-Voltage Switchgear (GIS)
Gas Insulated Switchgear?  Gas-Insulated High-Voltage Switchgear (GIS)Gas Insulated Switchgear?  Gas-Insulated High-Voltage Switchgear (GIS)
Gas Insulated Switchgear? Gas-Insulated High-Voltage Switchgear (GIS)
 
Electrical Transmission Tower Types - Design & Parts
Electrical Transmission Tower  Types - Design & PartsElectrical Transmission Tower  Types - Design & Parts
Electrical Transmission Tower Types - Design & Parts
 
What is load management
What is load managementWhat is load management
What is load management
 
What does merit order mean
What does merit order meanWhat does merit order mean
What does merit order mean
 
What are Balancing Services ?
What are  Balancing Services ?What are  Balancing Services ?
What are Balancing Services ?
 
The Need for Enhanced Power System Modelling Techniques & Simulation Tools
The Need for Enhanced  Power System  Modelling Techniques  &  Simulation Tools The Need for Enhanced  Power System  Modelling Techniques  &  Simulation Tools
The Need for Enhanced Power System Modelling Techniques & Simulation Tools
 
Power Quality Trends in the Transition to Carbon-Free Electrical Energy System
Power Quality  Trends in the Transition to  Carbon-Free Electrical Energy SystemPower Quality  Trends in the Transition to  Carbon-Free Electrical Energy System
Power Quality Trends in the Transition to Carbon-Free Electrical Energy System
 
Power Purchase Agreement PPA
Power Purchase Agreement PPA Power Purchase Agreement PPA
Power Purchase Agreement PPA
 
Harmonic study and analysis
Harmonic study and analysisHarmonic study and analysis
Harmonic study and analysis
 
What is leakage current testing
What is leakage current testingWhat is leakage current testing
What is leakage current testing
 

Recently uploaded

HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxSCMS School of Architecture
 
Verification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptxVerification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptxchumtiyababu
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxSCMS School of Architecture
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXssuser89054b
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayEpec Engineered Technologies
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueBhangaleSonal
 
Moment Distribution Method For Btech Civil
Moment Distribution Method For Btech CivilMoment Distribution Method For Btech Civil
Moment Distribution Method For Btech CivilVinayVitekari
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startQuintin Balsdon
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdfKamal Acharya
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Call Girls Mumbai
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapRishantSharmaFr
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdfKamal Acharya
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdfKamal Acharya
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptxJIT KUMAR GUPTA
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptNANDHAKUMARA10
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdfKamal Acharya
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsvanyagupta248
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationBhangaleSonal
 

Recently uploaded (20)

HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
 
Verification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptxVerification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptx
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
Moment Distribution Method For Btech Civil
Moment Distribution Method For Btech CivilMoment Distribution Method For Btech Civil
Moment Distribution Method For Btech Civil
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdf
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.ppt
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdf
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech students
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 

Protection and local control of HVDC grids

  • 1. The Webinar video is available here: https://register.gotowebinar.com/recording/4525984979424798721
  • 2. Protection and local control of HVDC grids Kees Koreman chairman JWG B4/B5.59 Webinar 15 November 2018
  • 3. Introduction and positioning of the work Main components and rationale for meshed HVDC grids Functional requirements on protection Short circuit phenomena Short circuit limiting techniques Protection system components Protection system overview Conclusions Table of contents 2
  • 4. Introduction and positioning of the work Protection and local control of HVDC grids Webinar Cigre 15 November 2018 3
  • 5. Introduction Development of DC systems in the late 19th century AC solutions came somewhat later But AC systems (50 or 60 Hz) became the standard in the world Simple transformation between different Voltage levels Short circuit current interruption Limited interest for DC in the second half of the 20th century Increased interest in the last years Renewable energy sources Offshore solutions 4
  • 6. 5
  • 7. Positioning of the work Cigre B4 gained interest and started a WG B4.52 who finished their work in 2013 (TB 533) A new WG was formed together with SC A3 JWG A3/B4.34 on DC switching equipment (TB 683) Five areas of further work were defined WG B4.56 on connection agreements (TB 657) WG B4.57 on simulation models (TB 604) WB B4.58 on load flow control (TB 699) WG B4.60 on reliability design (TB 713) JWG B4/B5.59 on protection (TB 739) this work 6
  • 8. Main components and rationale for meshed DC grids Protection and local control of HVDC grids Webinar Cigre 15 November 2018 7
  • 9. Some definitions for meshed grids and protection Meshed system (IEV reference 131-13-16) A set of branches forming a loop and containing only one link of a given co-tree Loop (IEV reference 131-13-12) A closed path passing only once through every node in the path Protection system (IEV reference 448-11-04) An arrangement of one or more protection equipments, and other devices intended to perform one or more specified protection functions 8
  • 10. Considered HVDC system designs Consisting of two poles of opposite polarity with the same voltage amplitude Symmetrical monopolar system Full bipolar system with or without metallic return (Asymmetrical monopoles possible) 9
  • 11. Converter topologies Multi modular half-bridge converter Cascaded two level converter Module output voltage 0 or Vcap In case of a DC pole to pole fault Uncontrolled current path possible Diode parallel to IGBT T2 Fault current cannot be blocked AC circuit breaker needs to operate Non fault current blocking converters 10
  • 12. Converter topologies Full-bridge converters less used Module output voltage 0, Vcap or - Vcap Uncontrolled current path possible Allways incorporates the module capacitor Fault current blocked by converter operation AC circuit breaker operation not required Fault current blocking converters 11
  • 13. Developing grids Full scale HVDC meshed grid will not emerge directly Development through connection of individual point-to-point connections Adding converters and lines/cables Develop multi terminal systems Developing into a fully meshed grid Possibly by using DC-DC Converters 12
  • 15. Functional requirements on protection Protection and local control of HVDC grids Webinar Cigre 15 November 2018 14
  • 16. Objectives and Requirements for Protection Large similarity with protection in AC grids Ensure Human safety Fast fault clearance Minimise impact on the system Minimise stress on components Protection philosophy requirements Reliability Speed Sensitivity Selectivity 15
  • 17. HVDC equipment constraints Semiconductors and power electronics Low overcurrent widthstand capabilities Fast temperature rise Breakdown leads to permanent damage Transformers and connections Similar to HVAC systems Overcurrents 5 – 10 times rated current Widthstand time hundreds of ms Prevent permanent damage 16
  • 18. HVDC grid constraints Full description derived by WG B4.56 Worst case unbalance Sectionalised HVDC grid Voltage profiles apply on non-faulted sections Balanced pole voltages Overvoltage profiles to be developed Faulted sections need to be isolated Tripping time considered Brochure 657 gives 10 – 15 ms Recent developments 3 – 6 ms Maximum allowable Voltage profile 17
  • 19. 18
  • 20. DC grid protection philosophies The entire HVDC grid is seen as a single protection zone The entire zone is switched off By the AC breakers in all converter bays By current control in full bridge converters By HVDC circuit breakers in the converter connection points The faulted section is identified and disconnected after fault clearance with mechanical or high speed switches Non-selective fault clearing strategy 19
  • 21. DC grid protection philosophies The entire HVDC grid is divided into several protection zones The faulted zone is isolated from the other zones By HVDC circuit breakers in the connection points By DC-DC converters between the zones By current limiters (SFCL) between the zones The faulted section is identified and disconnected after fault clearance with mechanical or high speed switches Partial selective fault clearing strategy 20
  • 22. DC grid protection philosophies Each branch in the HVDC grid is a separate protection zone The faulted branch is isolated from the other zones By HVDC circuit breakers in the faulted branch The faulted branch is immediately identified Full selective fault clearing strategy 21
  • 23. Kees Koreman| October 2018 Non-selective fault clearing strategy 22
  • 24. Kees Koreman| October 2018 Partial selective fault clearing strategy 23
  • 25. Kees Koreman| October 2018 Full selective fault clearing strategy 24
  • 26. Short circuit phenomena Protection and local control of HVDC grids Webinar Cigre 15 November 2018 25
  • 27. Fault current development Open circuit faults can be detected by: Redistribution of load currents Power flow no longer matches the scheduled power flow Focus of the brochure is on short circuit faults Current development is highly dependent on the earthing concept High impedance earthing Low impedance earthing Earthing concept less dominant when pole-to-pole faults occur 26
  • 28. Fault current development Fault example with low impedance earthing 27
  • 30. Fault current increase General rules cannot be given Factors to consider: Transmission line type Fault resistance DC side inductance DC side capacitance Interruption instant AC system strength Converter topology Detailed simulations are required 29
  • 31. Short circuit limiting techniques Protection and local control of HVDC grids Webinar Cigre 15 November 2018 30
  • 32. Introduction Invisible to the grid during normal conditions Act instantaneously after a fault Significant impedance during faults Out of action after clearance Capability to act multiple times 31 Characteristics of current limiters
  • 33. Limiting the rate-of-rise of fault currents Currently HVDC circuit breakers have moderate interrupting capability Current interruption level 10 – 20 kA Operating time 3 – 5 ms Limiting the rate-of-rise of current will help DC reactors Superconducting fault current limiters Time to reach the maximum current will increase 32
  • 34. Limiting the overcurrent magnitude The HVAC grid is the source delivering the current Impedance between the fault and the AC sources is determining Transformer impedance (0,1 - 0,2 pu) Converter impedance (< 0,1 pu) Additional measures are required AC resistance DC resistance DC – DC converters HVDC circuit breakers 33
  • 35. DC system earthing High impedance earthing low impedance earthing 34
  • 37. DC system earthing Conclusions Both principles can be used in a HVDC meshed grid High impedance earthing reduces the fault current but increases the over-voltages on the non-faulted pole Monopolar systems can be attached in both principles The recommendation is to implement the low impedance earthing given the anticipated size of the meshed HVDC grid 36
  • 38. Protection system components Protection and local control of HVDC grids Webinar Cigre 15 November 2018 37
  • 39. Protection system algorithms Many HVAC based algorithms are also applicable for HVDC applications (with minor modifications) DC overcurrent protection Distance and differential protection Under Voltage and Voltage unbalance protection Specific DC algorithms to increase selectivity and speed Travelling wave protection Voltage and/or current derivative protection (ROCOV and/or ROCOC) Simulation in the HVDC grid prepared by WG B4.57 38
  • 40. Fault current distribution This example shows the pole to earth steady state fault current distribution in the reference grid during a fault in the HVDC cable between bus 1 and bus 3 DC overcurrent protection will not lead to a fully selective operation Alternative algorithms are needed 39
  • 41. Rate-of-Change of Voltage (ROCOV) Derivative of the voltage is determined directly from the measured voltages Selectivity is improved with the addition of series reactors between the station and the measuring point Additional advantage is the reduction of the rate of rise of the fault current 40
  • 42. Rate-of-Change of Voltage (ROCOV) Effect of series reactor 41
  • 43. Rate-of-Change of Voltage (ROCOV) Calculation of ROCOV in the connection point ROCOC in the connections Sign of ROCOV and ROCOC Different indicates the faulted section Equal indicates fault outside zone Selective detection improved combining ROCOV and ROCOC 42
  • 44. Preliminary conclusions regarding algorithms [1] Best performance is obtained by rate of change protection algorithms Voltage change is the best indicator Current change can assist to increase selectivity Other algorithms are not selective enough but can be used to protect equipment by offering delayed protection functions 43
  • 45. Preliminary conclusions regarding algorithms [2] Utilisation of ROCOV only relies on local measurements Telecommunication between stations is not required. Communication delay has not effect on tripping time Telecommunication can be supporting for back-up protection functions. Delayed tripping in case of a breaker failure 44
  • 46. Measuring equipment Large bandwidth is required High pass characteristic sufficient Current measurement Direct shunt Zero flux Optical Rogowski coil Voltage measurement Resistive divider RC divider Essential for correct operation of ROCOV and ROCOC 45
  • 47. Acting equipment Impressive development DC circuit-breakers Various principles Semiconductor breaker Hybrid circuit-breaker Resonant circuit-breaker Mechanical with active current injection Excellent overview is given in TB 683 Upscaling to 500 +kV possible 46
  • 48. Operating principle hybrid CB Commutation Branch Energy Absorption Branch Low Voltage Switch Primary Branch Source Voltage Current Contact Voltage 47
  • 49. Operating principle hybrid CB Commutation Branch Energy Absorption Branch Low Voltage Switch Primary Branch Source Voltage Current Contact Voltage Low Voltage Switch Open; Commutation Branch Closed Fault Detection 48
  • 50. Operating principle hybrid CB Energy Absorption Branch Low Voltage Switch Primary Branch Commutation Branch Source Voltage Current Contact Voltage Commutation Branch Conduction Low Voltage Switch Open; Commutation Branch Closed Fault Detection 49
  • 51. Operating principle hybrid CB Commutation Branch Energy Absorption Branch Low Voltage Switch Primary Branch Source Voltage Current Contact Voltage Commutation Branch Conduction Low Voltage Switch Open; Commutation Branch Closed Fault Detection Mechanical Switch Open 50
  • 52. Operating principle hybrid CB Commutation Branch Energy Absorption Branch Low Voltage Switch Primary Branch Source Voltage Current Contact Voltage Commutation Branch Conduction Low Voltage Switch Open; Commutation Branch Closed Fault Detection Mechanical Switch Open Energy Absorption Commutation Branch OFF 51
  • 53. Fault localisation Fast fault localisation is needed to avoid long outage times With underground cables With submarine cables (overhead lines) Accuracy in the localisation limits the required amount of spare cable Repair strategies need to be in place 52
  • 54. Basics for localisation Offline measurements TDR Murray bridge Direct analysis of fault voltages and currents Cigre WG B1.52 gives further analysis 53
  • 55. Protection system overview Protection and local control of HVDC grids Webinar Cigre 15 November 2018 54
  • 56. Point – to – point protection overview 55
  • 58. Conclusions Protection and local control of HVDC grids Webinar Cigre 15 November 2018 57
  • 59. Conclusions [1] Technology has moved fast in the last years Measuring techniques are available Specific algorithms are tested and available HVDC circuit breakers are available ROCOV and ROCOC algorithms improve selectivity No use of telecommunication between the stations A series reactor further improves selective operation 50 or 100 mH in each pole is sufficient Regarding the technology 58
  • 60. Conclusions [2] Three strategies are available Non selective fault clearing Partial selective fault clearing Full selective fault clearing An advise cannot be given at this stage Depending on the size of the HVDC grid Economical analysis needed Detailed simulation studies are essential Regarding the application of DC grids 59
  • 61. Conclusions [3] The technology for HVDC grids is available: ready for use! Lines and cables Converters and stations DC – DC converters DC current interruption facilities Protection and control algorithms It allows for the development of a meshed DC grid Link to promotion movie: https://youtu.be/lBnWEK9IUn4 60
  • 62. Copyright © 2018 This tutorial has been prepared based upon the work of CIGRE and its Working Groups. If it is used in total or in part, proper reference and credit should be given to CIGRE. Disclaimer notice “CIGRE gives no warranty or assurance about the contents of this publication, nor does it accept any responsibility, as to the accuracy or exhaustiveness of the information. All implied warranties and conditions are excluded to the maximum extent permitted by law”. Copyright & Disclaimer notice 61