2. Slide 2California ISO Confidential. Do not release outside the California ISO.
AgendaâNovember 13, 2008
Jim PricePartial Loop Network Configuration2:20 â 2:50
Jami LongStructure and Plans for Cutover Plan
Walkthrough
ī§ Detailed Walkthrough Scheduled for
November 20, 2008
2:00 â 2:20
Jason IacobucciContinued Discussion of IMS Plans1:00 â 2:00
Lunch12:00 â 1:00
Jason IacobucciMRTU Business Implementation
ī§ Business Implementation Schedule
ī§ Parallel Operations Testing
10:00 â 12:00
PresenterTopicTime
4. Slide 4California ISO Confidential. Do not release outside the California ISO.
Background
ī§ Major remaining tasks:
ī§ Completion of Update 2
ī§ Commencement of Pre-Production phase of Program
ī§ Objectives
ī§ Complete functional phases of Market Simulation
ī§ Build ISO and Market Participant confidence in cutover activities
and MRTU production business processes
ī§ Prepare for Go-Live
5. Slide 5California ISO Confidential. Do not release outside the California ISO.
Definitions
ī§ For the purposes of this presentation, the following terms
are used:
ī§ Pre-Production
ī§ Testing phase focuses on preparing people, process, and technology for
MRTU market launch. Includes elements of Parallel Operations, Cutover
/Reversion testing, and ultimately cutover and Go-Live
ī§ Parallel Operations
ī§ Activities comprised of defined test cycles where some aspect of the MRTU
simulation parallels Production Business and/ or Technical processes (e.g.
RT Operational Support, following Production Load Forecast, etc.)
ī§ Cutover / Reversion
ī§ Testing and execution activities intended to prepare CAISO and Market
Participants for MRTU Go-Live, including a series of Open-Loop tests
6. Slide 6California ISO Confidential. Do not release outside the California ISO.
MRTU Business Implementation Schedule
Sep 2008 Oct 2008 Nov 2008 Dec 2008 Jan 2009
MRTUProgramSchedule
Target U2 Exit
Criteria Met
âĸScenario Testing Priority1
âĸ9/8-9/26
Go-Live
2/1/09
FERC 60 Day
Certification Filing
Production
Environment and
Network Model
Upgrades
`
MRTU Release Management
10/1 â Go-live
Desktop Cutover/
Reversion Plan
Walkthrough with
MPs
Market Participant Testing Pre-Production/ Cutover
âĸScenario Testing
Priority2
âĸ10/6-10/17
Downtime
10/18-10/25
Market Participant Testing
Downtime
12/20-12/27
`Cutover/ Reversion Planning
` CRR Allocation
LECG Final Report
9/26 Tier 1
Results
MP Final Readiness
Assessments
FERC 30 Day
Readiness
Filing
10/13 Tier 2
Results
10/28 Long-
term Results
11/11 Tier 3
Results
12/2 Annual
Auction
Results
`CRR Auction
MP Readiness
Assessment
âĸ11/
3-
11/
7
7. Slide 7California ISO Confidential. Do not release outside the California ISO.
MRTU Business Implementation Schedule
Sep 2008 Oct 2008 Nov 2008 Dec 2008 Jan 2009
MRTUProgramSchedule
Go-Live
2/1/09
9/14
2 Week Master File Publishing
Schedule
Weekly Master File Publishing
Schedule
Daily Master File Publishing
Schedule
9/28 10/12 11/2 11/9
Downtime
10/18-10/25
Downtime
12/20-12/27
10/26
12/28
Network Model
Update
Network Model
Update â Go Live
DB23 DB32 DB 32++DB32+
9. Slide 9California ISO Confidential. Do not release outside the California ISO.
Agenda
ī§ Introduction
ī§ Objectives
ī§ Proposed Test Cycles
ī§ Open Loop Test 1 (OL-1)
ī§ Simulated Closed Loop Test 2 (SCL-2)
ī§ Open Loop Tests 3 (OL-3) and 4 (OL-4)
ī§ Proposed Schedule
10. Slide 10California ISO Confidential. Do not release outside the California ISO.
Parallel Ops Test
Objectives
ī§ Establish confidence in the operational processes and systems
associated with the MRTU implementation
ī§ Demonstrate the infrastructure required for the California ISO to
support MRTU Pre-Production functions
ī§ Demonstrate the infrastructure required for the California ISO to
support the Cutover/Reversion Plan
ī§ Provide Market Participants with mock/test versions of the Pre-
Production and Cutover phases
11. Slide 11California ISO Confidential. Do not release outside the California ISO.
Proposed Test Cycles
ī§ CAISO proposes four test cycles during Parallel Ops, reflecting two
general categories:
ī§ Open Loop testing, where pre-MRTU Production EMS communicates
directly with market systems in the MRTU environment
ī§ Simulated Closed Loop testing, involving a simulated EMS State
Estimator solution and telemetry
Test Cycle
ID
Description Duration Test Circuit-
Resource
Feedback Loop
SE Solution Load Forecast Outages
(SLIC)
Intertie
Schedules
(OATI)
Bidsets
(SIBR)
Dispatch
Instructions
(ADS)
OL-1 Open loop testing with a single SC for a single resource.
Production EMS will feed MRTU Market Simulation
environment only.
30 minutes Open EMS Production MRTU MRTU MRTU Production
SCL-2 Simulation of all MRTU business processes and systems with
24x7 inputs from Market Participants. Current Production
Load Forecast is fed into MRTU ALFS in order to more
accurately simulate transition between operating days. ISO
provides 24x7 Grid Operations support.
60 days Simulated Closed GOTS 1. Summer week
(pre-DB37)
2. Production (post-
DB37)
MRTU
(Open)
MRTU
(Open)
MRTU
(Follow
Production
Load
Forecast)
MRTU
OL-3 Open loop test, where the MRTU environment shadows
Production as closely as possible but units do not adhere to
MRTU dispatches (therefore EMS feeds back in do not mirror
MRTU results). Network model descprepencies will be
handled on a case-by-case basis
30 minutes Open EMS Production MRTU
(Shadow
Production)
MRTU
(Shadow
Production)
MRTU
(Shadow
Production)
Production
OL-4 Synchronize network model with Production 60 minutes Open EMS Production MRTU
(Shadow
Production)
MRTU
(Shadow
Production)
MRTU
(Shadow
Production)
Production
12. Slide 12California ISO Confidential. Do not release outside the California ISO.
Proposed Test Cycles
Open Loop Test 1
ī§ Description
ī§ Open loop testing with a single SC for a single resource
ī§ Production EMS will feed MRTU Market Simulation environment
only
ī§ Objective
ī§ Test the integration of Production EMS with the MRTU market
systems
ī§ Expected result
ī§ Integration successful: communication established between
Production EMS for one unit with MRTU market systems
13. Slide 13California ISO Confidential. Do not release outside the California ISO.
Proposed Test Cycles
Open Loop Test 1
ī§ MRTU Data Feeds
ī§ SE Solution/Telemetry: Production EMS
ī§ Load Forecast: Production
ī§ Outages: MRTU (Not mirroring Production)
ī§ Intertie Schedules: MRTU (Not mirroring Production)
ī§ Bidsets: MRTU (Not mirroring Production)
ī§ Dispatch Instructions: MRTU (No dispatches to real units)
14. Slide 14California ISO Confidential. Do not release outside the California ISO.
Proposed Test Cycles
Simulated Closed Loop Test 2
ī§ Description
ī§ Simulation of all MRTU business processes and systems with 24x7
inputs from Market Participants
ī§ Current Production Load Forecast is fed into MRTU ALFS in order to
more accurately simulate transition between operating days
ī§ ISO provides 24x7 Grid Operations support
ī§ Objectives
ī§ Provide Market Participants with as close to Production-like Business
Processes as possible.
ī§ Specifically, during this test CAISO will rely on Market Participants to
provide all of the same inputs â from bids and schedules through
dispatch acceptance and meter data â that they would in MRTU
Production
15. Slide 15California ISO Confidential. Do not release outside the California ISO.
Proposed Test Cycles
Simulated Closed Loop Test 2
ī§ MRTU Data Feeds
ī§ SE Solution/Telemetry: GOTS (Simulated EMS)
ī§ Load Forecast: Summer week (pre-DB37)
Production (after DB37 deployed)
ī§ Outages: MRTU (Open)
ī§ Intertie Schedules: MRTU (Open)
ī§ Bidsets: MRTU (Follow Production Load
Forecast)
ī§ Dispatch Instructions: MRTU (No dispatches to real units)
16. Slide 16California ISO Confidential. Do not release outside the California ISO.
Proposed Test Cycles
Open Loop Tests 3 and 4
ī§ Description
ī§ Prepare both the ISO and Market Participants for the short
overlap time during Go-Live where current Production must
mirror MRTU
ī§ OL-4 provides a longer duration than OL-3
ī§ Objectives
ī§ Simulate the cutover period by having Market Participants mirror
Production as closely as possible, including matching bidding to
balanced schedules
ī§ Production outages and intertie schedules are reflected in RTM
results, do not cause major issues with RTM solutions
17. Slide 17California ISO Confidential. Do not release outside the California ISO.
Proposed Test Cycles
Open Loop Tests 3 and 4
ī§ Data Feeds
ī§ SE Solution/Telemetry: EMS
ī§ Load Forecast: Production
ī§ Outages: MRTU (Shadow Production*)
ī§ Intertie Schedules: MRTU (Shadow Production)
ī§ Bidsets: MRTU (Shadow Production)
ī§ Dispatch Instructions: MRTU (No dispatches to real units)
* CAISO will facilitate shadowing production by providing a matrix to map pre-MRTU Production inputs
to MRTU inputs
18. Slide 18California ISO Confidential. Do not release outside the California ISO.
Parallel Ops Test
Proposed Schedule
ī§ In the proposed schedule below:
ī§ SCL-2 will be supported by Grid Operations on an ongoing, 24x7
basis over a long duration
ī§ Multiple iterations of OL-1, OL-2, and OL-3 may be run on single
dates throughout the testing period
19. Slide 19California ISO Confidential. Do not release outside the California ISO.
Parallel Ops Test
Proposed Schedule
ī§ Grid Operations Ramp-Up
ī§ Grid Operations support will be phased in over the final two weeks of
November:
ī§ 11/17 â 11/21
6AM to 6PM daily support of SLIC Outages and ADS dispatches; ADS auto-approve
script is disabled
ī§ 11/24 â 11/26
6AM to 6PM daily support of SLIC Outages, ADS dispatches, and CAS eTags (intertie
schedules); ADS auto-accept script is disabled, CAS schedule-creation script is
disabled
ī§ 12/1 â 12/20
24x7 support for SLIC Outages, ADS dispatches, and CAS eTags
ī§ SCL-2 will be supported by Grid Operations on an ongoing, 24x7 basis
over a long duration
ī§ RT Operations contact numbers will be provided by end of week
20. Slide 20California ISO Confidential. Do not release outside the California ISO.
Questions / Feedback
21. CAISO MRTU Cutover & Reversion
C&R Planning Overview
November 13, 2008
Jami Long, Manager, Operations Information
Technology
22. Slide 22California ISO Confidential. Do not release outside the California ISO.
Agenda
ī§ Phases & Deliverables
ī§ Planning Phase - Internal
ī§ Planning Phase â External
ī§ Preparation
ī§ Transition
ī§ Closure
ī§ Review Approach
ī§ System Access Approach
23. Slide 23California ISO Confidential. Do not release outside the California ISO.
C&R Planning Phase - Internal
ī§ Planning Phase includes all artifacts required to execute
Preparation and Transition phases
ī§ Internal Deliverables Include:
ī§ Communication Plan
ī§ Detailed Application C&R Plans
ī§ Detailed Cutover Schedule
ī§ Detailed Reversion Schedule
ī§ Support Plan
24. Slide 24California ISO Confidential. Do not release outside the California ISO.
Cutover Planning Phase - External
ī§ External deliverables include:
ī§ C&R External Overview
ī§ Cutover Timeline
ī§ Detailed External Cutover Schedule
ī§ Detailed External Reversion Schedule
ī§ C&R Plan Validation will occur during Parallel
Operations
25. Slide 25California ISO Confidential. Do not release outside the California ISO.
Cutover Preparation Phase
ī§ Preparation includes system readiness activities that will
occur throughout the Parallel Operation and Pre-
Production windows
ī§ Data Migration
ī§ Data Purging Preparation
ī§ System Access Validation
ī§ Finalize Support Plan
26. Slide 26California ISO Confidential. Do not release outside the California ISO.
Cutover Transition Phase
ī§ Transition is the execution of tasks to prepare data and
begin using systems for production purposes
ī§ Data Migration True-up
ī§ Data Purge
ī§ Cutover Scripts/Tasks
ī§ Transition begins TD-15
27. Slide 27California ISO Confidential. Do not release outside the California ISO.
Cutover Closure Phase
ī§ Closure is the phase following the reversion window.
This phase includes:
ī§ Legacy System Plan Execution
ī§ Lessons Learned
28. Slide 28California ISO Confidential. Do not release outside the California ISO.
Cutover & Reversion Review Approach
ī§ 11/20
ī§ Review Cutover External Overview Updates
ī§ Walkthrough Detailed Cutover Schedule
ī§ Communications and Support Plan Overview
ī§ 12/04
ī§ Review Reversion External Overview Updates
ī§ Walkthrough Detailed Reversion Schedule
ī§ 12/18
ī§ Walkthrough Final Changes
ī§ Follow Up on Open Items
29. Slide 29California ISO Confidential. Do not release outside the California ISO.
System Access
ī§ MRTU Production Access Requests Form (ARF) allows submission
of all users for an application or set of applications on a single form.
ī§ 11/15 â Production access requests are due back from POCs.
ī§ 12/1 â All production user access permissions are configured in both
market simulation and Folsom production.
ī§ 12/14 â All external non-production access will be removed from
Folsom production. This will allow us to identify any âmissedâ
people or systems.
ī§ New production users without market simulation access must submit
an MRTU production ARF.
30. Slide 30California ISO Confidential. Do not release outside the California ISO.
System Access
ī§ Existing market simulation users that require production access:
ī§ Must submit a production ARF for SIBR, CMRI, BAPI and CRN
ī§ Must submit production ARF for legacy systems (ADS, SLIC, PIRP, and
OMAR) IF you do not have production access today. If you already have
production access, you do not need to request access.
ī§ New certificates are not required as production certificates are currently
in use.
ī§ Existing market simulation users that require test/market simulation
access only will no longer have access to MRTU Folsom production
effective 12/14. Access/certificates will be carried over to the new
market simulation environment when Folsom production access is
eliminated.
31. Implementation of âPartial Loopâ Intertie
Network Configuration
Jim Price
Lead Engineering Specialist
Market & Product Development
MRTU Implementation Workshop
November 13, 2008
32. Slide 32California ISO Confidential. Do not release outside the California ISO.
Topics of Discussion
Extension of MRTU modeling of external areas other than
Integrated Balancing Authority Areas, for more accurate
congestion management and LMPs:
ī§ Market simulation results have showed needs for
expanding the Full Network Model outside the ISO. ISO is
adding external lines in DB37 model.
Presentation:
ī§ Background of previous modeling of âNew PTOâ and
âpartial loopâ networks
ī§ Addition of transmission lines outside California, as âpartial
loopâ model
ī§ Plans for further improvement in modeling of external
transmission systems
33. Slide 33California ISO Confidential. Do not release outside the California ISO.
The âNew PTOâ network consists of âConverted Rightsâ on
transmission outside the CAISO area. The âNew PTOâ area in
Southern California, Nevada, and Arizona is documented in the
Full Network Model BPM (section 4.2.4.3), and in a 8/25/2006
white paper at http://www.caiso.com/185d/185db75028b00.pdf.
Operating Procedure S-326 will provide further detail.
MRTU Transmission Model Includes âNew PTOâ
Network
34. Slide 34California ISO Confidential. Do not release outside the California ISO.
âNew PTOâ Modeling Introduced External Loops of
500 kV Lines in Original MRTU Market FNM
MOENKOPI
WESTWING
PALO VERDE
MEAD
McCULLOUGH
MIDWAY
ADELANTO
VALLEY
DEVERS
SERRANO
LUGO
MIRA LOMA
ELDORADO
MARKETPLAC
E
VINCENT
HASSAYAMPA
TO FOUR
CORNERS
MIGUEL IMPERIAL
VALLEY
NORTH
GILA
MOHAVEVICTORVILLE
West
of
River East of
River
500 kV line
C
alifornia
N
evada
N evada
Arizona
Arizona
California
Original MRTU Market FNM consisted of ISO Controlled Grid and âopen loopâ
interties, New PTO network, embedded and adjacent control area concepts, and
external branch group connections.
35. Slide 35California ISO Confidential. Do not release outside the California ISO.
Early Testing Experience Showed Problems with
âOpen Loopâ Intertie Model
ī§ Simulations in LMP Studies and CRR Dry Run identified
mismatches between modeled flows and actual flows
measured by telemetry, using original âopen loopâ model:
ī§ Excessive modeled flow on Palo Verde â Devers 500 kV line
caused adverse LMP impacts in LMP Study (discussed in 4/20/07
LMP Study Update and 1/8/08 IBAA stakeholder meeting)
ī§ LMP Studies 3A and 3C showed significant congestion at Miguel substation
from August 2003, when new generators started operation, to December
2004, when transmission upgrades were complete.
ī§ Since December 2004, new generators operate at higher output, and original
âopen loopâ model showed congestion on Palo Verde to Devers 500 kV line.
ī§ Unrealistic binding constraint on El Dorado â Lugo 500 kV line, in
CRR Dry Run results
36. Slide 36California ISO Confidential. Do not release outside the California ISO.
Revised MRTU Market FNM Added 500 kV Lines
in Arizona, to Improve Power flow Modeling
MOENKOPI
WESTWING
YAVAPAI
PALO VERDE
MEAD
McCULLOUGH
MIDWAY
ADELANTO
VALLEY
DEVERS
SERRANO
LUGO
MIRA LOMA
ELDORADO
MARKETPLAC
E
VINCENT
HASSAYAMPA
TO FOUR
CORNERS
MIGUEL IMPERIAL
VALLEY
NORTH
GILA
MOHAVEVICTORVILLE
West
of
River East of
River
500 kV line
C
alifornia
N
evada
N
evada
Arizona
Arizona
California
ī§ Addition of initial âpartial loopâ FNM added Palo Verde-Westwing and
Westwing-Yavapai-Moenkopi lines.
37. Slide 37California ISO Confidential. Do not release outside the California ISO.
Additional Testing Experience Has Showed Needs
for Expanding the External Network Model
ī§ Example: Hinds to Mirage 230 kV line binding in many hours of
market simulation in August-September, with high impact on LMPs
ī§ Impacts in âMRTU Market Simulation Results Review for Week of
8/18/08 thru 8/24/08â (http://www.caiso.com/202f/202fc075dad0.pdf)
ī§ Cause of impact was contingency of loss of Victorville-Lugo 500 kV line,
but (1) base case flow on Hinds-Mirage significantly exceeded actual
flow, and (2) impact of contingency significantly exceeded its impact
using a complete network model.
ī§ Using a more complete external network results in more accurate
results.
ī§ Additional external network modeling also addresses stakeholder
requests
ī§ Example: Distribution of flow from sources near Imperial Valley
substation by adding network through Imperial Irrigation District.
38. Slide 38California ISO Confidential. Do not release outside the California ISO.
ISO is Adding External Lines to FNM in DB37 to
Address the Identified Issues
ī§ Additions to FNM in Arizona, Southern Nevada, and
Imperial Irrigation District include:
ī§ 500 kV and 345 kV branches,
ī§ Connections of all Southern California Scheduling Points to the
500/345 kV grid, except where capacity under ISO operational
control is export-only (i.e., Laughlin intertie), and
ī§ Equivalent lines as needed to represent parallel 230 kV and
lower voltage transmission grid.
ī§ Additions consist of:
ī§ 14 new 500 kV buses, 22 new 345 kV buses, 45 new buses at
230 kV or lower
ī§ 211 new lines and transformers
ī§ Additions do not change any Scheduling Points.
39. Slide 39California ISO Confidential. Do not release outside the California ISO.
Additions to FNM in DB37 Nearly Complete the
500 kV Grid in the Southwest
This revised FNM has been used in annual CRR process for
2009 CRRs, and in subsequent Update 2 testing.
40. Slide 40California ISO Confidential. Do not release outside the California ISO.
Eventually, FNM May Match Physical Model
N AV A JO
M O E N KO PI
W E ST W IN G
Y A VA PA I
P AL O VE R D E
M E AD
M cC U LLO U G H
C R YS TA L
M ID W AY
AD ELA N T O
V A LLE Y
D EV E R S
S ER R A N O
LU G O
M IR A LO M A
E LD O R A D O
M A R KE TP LA C
E
VIN C EN T
R IN ALD I
TO L U C A
G ILA R IVE R
H A R Q U A H A LA
H AS SA Y AM P A
R U D D
JO JO B A
TO KY R E N E
TO FO U R
C O R N ER S
M IG U E L IM P ER IA L
V ALL EY
N O R T H
G ILA
P E R KIN S
M O H AV EV IC TO R VILL E
H A R R Y
A LLE N
W est
of
R iver E ast of
R iver
Ph ase S hifter
500 kV line
C
a
liforn
ia
N
eva
d
a
N e v a d a
A riz o n a
Arizona
California
âĸ The complete 500 kV transmission system near the ISO includes lines
operated by LADWP as well as APS, Nevada Power, and WAPA.
âĸ Modeling issues include DC lines and phase shifters, as well as loop flow.
Physical model also has loops to Pacific Northwest
41. Slide 41California ISO Confidential. Do not release outside the California ISO.
Why Not Do More Now?
ī§ As stated in 7/21/03 Amended Comprehensive Market Design Proposal,
ISO will ultimately use a FNM that models the external WECC grid.
ī§ However, regional flows are complex, with no consistent daily pattern. At
CA-OR border, variation exceeds the average unscheduled (loop) flow.
Actual Unscheduled Flow at Calif.-Oregon Border (S-N)
-1000
-800
-600
-400
-200
0
200
400
600
800
1000
5/1/20060:00
5/16/20060:00
5/31/20060:00
6/15/20060:00
6/30/20060:00
7/15/20060:00
7/30/20060:00
8/14/20060:00
8/29/20060:00
9/13/20060:00
9/28/20060:00
Time
MW
Mean = -53.6, Standard Deviation = 284.0
42. Slide 42California ISO Confidential. Do not release outside the California ISO.
Simplistic Modeling of Closed Loop Would Not
Produce Correct Results
ī§ LMP Study 3A used a closed loop WECC model, without data on
external schedules. Modeled unscheduled flow is difference between
COI schedules and modeled flows on COI branch group.
ī§ Result: Poor correlation with actual loop flow (R=0.17). Error in model
of unscheduled flow sometimes exceeds the actual unscheduled flow.
Result of Simplistic Unscheduled Flow Model at
Malin (South to North)
-600
-400
-200
0
200
400
600
8/3/20030:00
8/3/200312:00
8/4/20030:00
8/4/200312:00
8/5/20030:00
8/5/200312:00
8/6/20030:00
8/6/200312:00
8/7/20030:00
8/7/200312:00
8/8/20030:00
8/8/200312:00
8/9/20030:00
8/9/200312:00
8/10/20030:00
Time
MW
Actual Modeled CAISO External Flow
Correlation: R = 0.1706
43. Slide 43California ISO Confidential. Do not release outside the California ISO.
Plans for further improvement in modeling of
external transmission systems
ī§ ISO developed Integrated Balancing Authority Area (IBAA)
modeling of SMUD and TID BAAs using schedules in ISO
Markets, to improve the ISOâs congestion management.
ī§ ISO encourages WECC-wide coordination of congestion
management and data exchange, through WECC Seams
Issues Subcommittee (SIS).
ī§ In parallel with larger regional effort, ISO will develop
improved BAA modeling using existing data sources:
ī§ ISO Market Schedules and e-tags
ī§ WECC planning models and Extra High Voltage (EHV) data pool,
subject to WECC confidentiality provisions