SlideShare a Scribd company logo
1 of 43
Download to read offline
MRTU Implementation Workshop
November 13, 2008
Slide 2California ISO Confidential. Do not release outside the California ISO.
Agenda—November 13, 2008
Jim PricePartial Loop Network Configuration2:20 – 2:50
Jami LongStructure and Plans for Cutover Plan
Walkthrough
ī‚§ Detailed Walkthrough Scheduled for
November 20, 2008
2:00 – 2:20
Jason IacobucciContinued Discussion of IMS Plans1:00 – 2:00
Lunch12:00 – 1:00
Jason IacobucciMRTU Business Implementation
ī‚§ Business Implementation Schedule
ī‚§ Parallel Operations Testing
10:00 – 12:00
PresenterTopicTime
MRTU Implementation Workshop
MRTU Business Implementation Schedule
November 13, 2008
Slide 4California ISO Confidential. Do not release outside the California ISO.
Background
ī‚§ Major remaining tasks:
ī‚§ Completion of Update 2
ī‚§ Commencement of Pre-Production phase of Program
ī‚§ Objectives
ī‚§ Complete functional phases of Market Simulation
ī‚§ Build ISO and Market Participant confidence in cutover activities
and MRTU production business processes
ī‚§ Prepare for Go-Live
Slide 5California ISO Confidential. Do not release outside the California ISO.
Definitions
ī‚§ For the purposes of this presentation, the following terms
are used:
ī‚§ Pre-Production
ī‚§ Testing phase focuses on preparing people, process, and technology for
MRTU market launch. Includes elements of Parallel Operations, Cutover
/Reversion testing, and ultimately cutover and Go-Live
ī‚§ Parallel Operations
ī‚§ Activities comprised of defined test cycles where some aspect of the MRTU
simulation parallels Production Business and/ or Technical processes (e.g.
RT Operational Support, following Production Load Forecast, etc.)
ī‚§ Cutover / Reversion
ī‚§ Testing and execution activities intended to prepare CAISO and Market
Participants for MRTU Go-Live, including a series of Open-Loop tests
Slide 6California ISO Confidential. Do not release outside the California ISO.
MRTU Business Implementation Schedule
Sep 2008 Oct 2008 Nov 2008 Dec 2008 Jan 2009
MRTUProgramSchedule
Target U2 Exit
Criteria Met
â€ĸScenario Testing Priority1
â€ĸ9/8-9/26
Go-Live
2/1/09
FERC 60 Day
Certification Filing
Production
Environment and
Network Model
Upgrades
`
MRTU Release Management
10/1 – Go-live
Desktop Cutover/
Reversion Plan
Walkthrough with
MPs
Market Participant Testing Pre-Production/ Cutover
â€ĸScenario Testing
Priority2
â€ĸ10/6-10/17
Downtime
10/18-10/25
Market Participant Testing
Downtime
12/20-12/27
`Cutover/ Reversion Planning
` CRR Allocation
LECG Final Report
9/26 Tier 1
Results
MP Final Readiness
Assessments
FERC 30 Day
Readiness
Filing
10/13 Tier 2
Results
10/28 Long-
term Results
11/11 Tier 3
Results
12/2 Annual
Auction
Results
`CRR Auction
MP Readiness
Assessment
â€ĸ11/
3-
11/
7
Slide 7California ISO Confidential. Do not release outside the California ISO.
MRTU Business Implementation Schedule
Sep 2008 Oct 2008 Nov 2008 Dec 2008 Jan 2009
MRTUProgramSchedule
Go-Live
2/1/09
9/14
2 Week Master File Publishing
Schedule
Weekly Master File Publishing
Schedule
Daily Master File Publishing
Schedule
9/28 10/12 11/2 11/9
Downtime
10/18-10/25
Downtime
12/20-12/27
10/26
12/28
Network Model
Update
Network Model
Update – Go Live
DB23 DB32 DB 32++DB32+
MRTU Implementation Workshop
MRTU Parallel Operations Testing
November 13, 2008
Slide 9California ISO Confidential. Do not release outside the California ISO.
Agenda
ī‚§ Introduction
ī‚§ Objectives
ī‚§ Proposed Test Cycles
ī‚§ Open Loop Test 1 (OL-1)
ī‚§ Simulated Closed Loop Test 2 (SCL-2)
ī‚§ Open Loop Tests 3 (OL-3) and 4 (OL-4)
ī‚§ Proposed Schedule
Slide 10California ISO Confidential. Do not release outside the California ISO.
Parallel Ops Test
Objectives
ī‚§ Establish confidence in the operational processes and systems
associated with the MRTU implementation
ī‚§ Demonstrate the infrastructure required for the California ISO to
support MRTU Pre-Production functions
ī‚§ Demonstrate the infrastructure required for the California ISO to
support the Cutover/Reversion Plan
ī‚§ Provide Market Participants with mock/test versions of the Pre-
Production and Cutover phases
Slide 11California ISO Confidential. Do not release outside the California ISO.
Proposed Test Cycles
ī‚§ CAISO proposes four test cycles during Parallel Ops, reflecting two
general categories:
ī‚§ Open Loop testing, where pre-MRTU Production EMS communicates
directly with market systems in the MRTU environment
ī‚§ Simulated Closed Loop testing, involving a simulated EMS State
Estimator solution and telemetry
Test Cycle
ID
Description Duration Test Circuit-
Resource
Feedback Loop
SE Solution Load Forecast Outages
(SLIC)
Intertie
Schedules
(OATI)
Bidsets
(SIBR)
Dispatch
Instructions
(ADS)
OL-1 Open loop testing with a single SC for a single resource.
Production EMS will feed MRTU Market Simulation
environment only.
30 minutes Open EMS Production MRTU MRTU MRTU Production
SCL-2 Simulation of all MRTU business processes and systems with
24x7 inputs from Market Participants. Current Production
Load Forecast is fed into MRTU ALFS in order to more
accurately simulate transition between operating days. ISO
provides 24x7 Grid Operations support.
60 days Simulated Closed GOTS 1. Summer week
(pre-DB37)
2. Production (post-
DB37)
MRTU
(Open)
MRTU
(Open)
MRTU
(Follow
Production
Load
Forecast)
MRTU
OL-3 Open loop test, where the MRTU environment shadows
Production as closely as possible but units do not adhere to
MRTU dispatches (therefore EMS feeds back in do not mirror
MRTU results). Network model descprepencies will be
handled on a case-by-case basis
30 minutes Open EMS Production MRTU
(Shadow
Production)
MRTU
(Shadow
Production)
MRTU
(Shadow
Production)
Production
OL-4 Synchronize network model with Production 60 minutes Open EMS Production MRTU
(Shadow
Production)
MRTU
(Shadow
Production)
MRTU
(Shadow
Production)
Production
Slide 12California ISO Confidential. Do not release outside the California ISO.
Proposed Test Cycles
Open Loop Test 1
ī‚§ Description
ī‚§ Open loop testing with a single SC for a single resource
ī‚§ Production EMS will feed MRTU Market Simulation environment
only
ī‚§ Objective
ī‚§ Test the integration of Production EMS with the MRTU market
systems
ī‚§ Expected result
ī‚§ Integration successful: communication established between
Production EMS for one unit with MRTU market systems
Slide 13California ISO Confidential. Do not release outside the California ISO.
Proposed Test Cycles
Open Loop Test 1
ī‚§ MRTU Data Feeds
ī‚§ SE Solution/Telemetry: Production EMS
ī‚§ Load Forecast: Production
ī‚§ Outages: MRTU (Not mirroring Production)
ī‚§ Intertie Schedules: MRTU (Not mirroring Production)
ī‚§ Bidsets: MRTU (Not mirroring Production)
ī‚§ Dispatch Instructions: MRTU (No dispatches to real units)
Slide 14California ISO Confidential. Do not release outside the California ISO.
Proposed Test Cycles
Simulated Closed Loop Test 2
ī‚§ Description
ī‚§ Simulation of all MRTU business processes and systems with 24x7
inputs from Market Participants
ī‚§ Current Production Load Forecast is fed into MRTU ALFS in order to
more accurately simulate transition between operating days
ī‚§ ISO provides 24x7 Grid Operations support
ī‚§ Objectives
ī‚§ Provide Market Participants with as close to Production-like Business
Processes as possible.
ī‚§ Specifically, during this test CAISO will rely on Market Participants to
provide all of the same inputs – from bids and schedules through
dispatch acceptance and meter data – that they would in MRTU
Production
Slide 15California ISO Confidential. Do not release outside the California ISO.
Proposed Test Cycles
Simulated Closed Loop Test 2
ī‚§ MRTU Data Feeds
ī‚§ SE Solution/Telemetry: GOTS (Simulated EMS)
ī‚§ Load Forecast: Summer week (pre-DB37)
Production (after DB37 deployed)
ī‚§ Outages: MRTU (Open)
ī‚§ Intertie Schedules: MRTU (Open)
ī‚§ Bidsets: MRTU (Follow Production Load
Forecast)
ī‚§ Dispatch Instructions: MRTU (No dispatches to real units)
Slide 16California ISO Confidential. Do not release outside the California ISO.
Proposed Test Cycles
Open Loop Tests 3 and 4
ī‚§ Description
ī‚§ Prepare both the ISO and Market Participants for the short
overlap time during Go-Live where current Production must
mirror MRTU
ī‚§ OL-4 provides a longer duration than OL-3
ī‚§ Objectives
ī‚§ Simulate the cutover period by having Market Participants mirror
Production as closely as possible, including matching bidding to
balanced schedules
ī‚§ Production outages and intertie schedules are reflected in RTM
results, do not cause major issues with RTM solutions
Slide 17California ISO Confidential. Do not release outside the California ISO.
Proposed Test Cycles
Open Loop Tests 3 and 4
ī‚§ Data Feeds
ī‚§ SE Solution/Telemetry: EMS
ī‚§ Load Forecast: Production
ī‚§ Outages: MRTU (Shadow Production*)
ī‚§ Intertie Schedules: MRTU (Shadow Production)
ī‚§ Bidsets: MRTU (Shadow Production)
ī‚§ Dispatch Instructions: MRTU (No dispatches to real units)
* CAISO will facilitate shadowing production by providing a matrix to map pre-MRTU Production inputs
to MRTU inputs
Slide 18California ISO Confidential. Do not release outside the California ISO.
Parallel Ops Test
Proposed Schedule
ī‚§ In the proposed schedule below:
ī‚§ SCL-2 will be supported by Grid Operations on an ongoing, 24x7
basis over a long duration
ī‚§ Multiple iterations of OL-1, OL-2, and OL-3 may be run on single
dates throughout the testing period
Slide 19California ISO Confidential. Do not release outside the California ISO.
Parallel Ops Test
Proposed Schedule
ī‚§ Grid Operations Ramp-Up
ī‚§ Grid Operations support will be phased in over the final two weeks of
November:
ī‚§ 11/17 – 11/21
6AM to 6PM daily support of SLIC Outages and ADS dispatches; ADS auto-approve
script is disabled
ī‚§ 11/24 – 11/26
6AM to 6PM daily support of SLIC Outages, ADS dispatches, and CAS eTags (intertie
schedules); ADS auto-accept script is disabled, CAS schedule-creation script is
disabled
ī‚§ 12/1 – 12/20
24x7 support for SLIC Outages, ADS dispatches, and CAS eTags
ī‚§ SCL-2 will be supported by Grid Operations on an ongoing, 24x7 basis
over a long duration
ī‚§ RT Operations contact numbers will be provided by end of week
Slide 20California ISO Confidential. Do not release outside the California ISO.
Questions / Feedback
CAISO MRTU Cutover & Reversion
C&R Planning Overview
November 13, 2008
Jami Long, Manager, Operations Information
Technology
Slide 22California ISO Confidential. Do not release outside the California ISO.
Agenda
ī‚§ Phases & Deliverables
ī‚§ Planning Phase - Internal
ī‚§ Planning Phase – External
ī‚§ Preparation
ī‚§ Transition
ī‚§ Closure
ī‚§ Review Approach
ī‚§ System Access Approach
Slide 23California ISO Confidential. Do not release outside the California ISO.
C&R Planning Phase - Internal
ī‚§ Planning Phase includes all artifacts required to execute
Preparation and Transition phases
ī‚§ Internal Deliverables Include:
ī‚§ Communication Plan
ī‚§ Detailed Application C&R Plans
ī‚§ Detailed Cutover Schedule
ī‚§ Detailed Reversion Schedule
ī‚§ Support Plan
Slide 24California ISO Confidential. Do not release outside the California ISO.
Cutover Planning Phase - External
ī‚§ External deliverables include:
ī‚§ C&R External Overview
ī‚§ Cutover Timeline
ī‚§ Detailed External Cutover Schedule
ī‚§ Detailed External Reversion Schedule
ī‚§ C&R Plan Validation will occur during Parallel
Operations
Slide 25California ISO Confidential. Do not release outside the California ISO.
Cutover Preparation Phase
ī‚§ Preparation includes system readiness activities that will
occur throughout the Parallel Operation and Pre-
Production windows
ī‚§ Data Migration
ī‚§ Data Purging Preparation
ī‚§ System Access Validation
ī‚§ Finalize Support Plan
Slide 26California ISO Confidential. Do not release outside the California ISO.
Cutover Transition Phase
ī‚§ Transition is the execution of tasks to prepare data and
begin using systems for production purposes
ī‚§ Data Migration True-up
ī‚§ Data Purge
ī‚§ Cutover Scripts/Tasks
ī‚§ Transition begins TD-15
Slide 27California ISO Confidential. Do not release outside the California ISO.
Cutover Closure Phase
ī‚§ Closure is the phase following the reversion window.
This phase includes:
ī‚§ Legacy System Plan Execution
ī‚§ Lessons Learned
Slide 28California ISO Confidential. Do not release outside the California ISO.
Cutover & Reversion Review Approach
ī‚§ 11/20
ī‚§ Review Cutover External Overview Updates
ī‚§ Walkthrough Detailed Cutover Schedule
ī‚§ Communications and Support Plan Overview
ī‚§ 12/04
ī‚§ Review Reversion External Overview Updates
ī‚§ Walkthrough Detailed Reversion Schedule
ī‚§ 12/18
ī‚§ Walkthrough Final Changes
ī‚§ Follow Up on Open Items
Slide 29California ISO Confidential. Do not release outside the California ISO.
System Access
ī‚§ MRTU Production Access Requests Form (ARF) allows submission
of all users for an application or set of applications on a single form.
ī‚§ 11/15 – Production access requests are due back from POCs.
ī‚§ 12/1 – All production user access permissions are configured in both
market simulation and Folsom production.
ī‚§ 12/14 – All external non-production access will be removed from
Folsom production. This will allow us to identify any “missed”
people or systems.
ī‚§ New production users without market simulation access must submit
an MRTU production ARF.
Slide 30California ISO Confidential. Do not release outside the California ISO.
System Access
ī‚§ Existing market simulation users that require production access:
ī‚§ Must submit a production ARF for SIBR, CMRI, BAPI and CRN
ī‚§ Must submit production ARF for legacy systems (ADS, SLIC, PIRP, and
OMAR) IF you do not have production access today. If you already have
production access, you do not need to request access.
ī‚§ New certificates are not required as production certificates are currently
in use.
ī‚§ Existing market simulation users that require test/market simulation
access only will no longer have access to MRTU Folsom production
effective 12/14. Access/certificates will be carried over to the new
market simulation environment when Folsom production access is
eliminated.
Implementation of “Partial Loop” Intertie
Network Configuration
Jim Price
Lead Engineering Specialist
Market & Product Development
MRTU Implementation Workshop
November 13, 2008
Slide 32California ISO Confidential. Do not release outside the California ISO.
Topics of Discussion
Extension of MRTU modeling of external areas other than
Integrated Balancing Authority Areas, for more accurate
congestion management and LMPs:
ī‚§ Market simulation results have showed needs for
expanding the Full Network Model outside the ISO. ISO is
adding external lines in DB37 model.
Presentation:
ī‚§ Background of previous modeling of “New PTO” and
“partial loop” networks
ī‚§ Addition of transmission lines outside California, as “partial
loop” model
ī‚§ Plans for further improvement in modeling of external
transmission systems
Slide 33California ISO Confidential. Do not release outside the California ISO.
The “New PTO” network consists of “Converted Rights” on
transmission outside the CAISO area. The “New PTO” area in
Southern California, Nevada, and Arizona is documented in the
Full Network Model BPM (section 4.2.4.3), and in a 8/25/2006
white paper at http://www.caiso.com/185d/185db75028b00.pdf.
Operating Procedure S-326 will provide further detail.
MRTU Transmission Model Includes “New PTO”
Network
Slide 34California ISO Confidential. Do not release outside the California ISO.
“New PTO” Modeling Introduced External Loops of
500 kV Lines in Original MRTU Market FNM
MOENKOPI
WESTWING
PALO VERDE
MEAD
McCULLOUGH
MIDWAY
ADELANTO
VALLEY
DEVERS
SERRANO
LUGO
MIRA LOMA
ELDORADO
MARKETPLAC
E
VINCENT
HASSAYAMPA
TO FOUR
CORNERS
MIGUEL IMPERIAL
VALLEY
NORTH
GILA
MOHAVEVICTORVILLE
West
of
River East of
River
500 kV line
C
alifornia
N
evada
N evada
Arizona
Arizona
California
Original MRTU Market FNM consisted of ISO Controlled Grid and “open loop”
interties, New PTO network, embedded and adjacent control area concepts, and
external branch group connections.
Slide 35California ISO Confidential. Do not release outside the California ISO.
Early Testing Experience Showed Problems with
“Open Loop” Intertie Model
ī‚§ Simulations in LMP Studies and CRR Dry Run identified
mismatches between modeled flows and actual flows
measured by telemetry, using original “open loop” model:
ī‚§ Excessive modeled flow on Palo Verde – Devers 500 kV line
caused adverse LMP impacts in LMP Study (discussed in 4/20/07
LMP Study Update and 1/8/08 IBAA stakeholder meeting)
ī‚§ LMP Studies 3A and 3C showed significant congestion at Miguel substation
from August 2003, when new generators started operation, to December
2004, when transmission upgrades were complete.
ī‚§ Since December 2004, new generators operate at higher output, and original
“open loop” model showed congestion on Palo Verde to Devers 500 kV line.
ī‚§ Unrealistic binding constraint on El Dorado – Lugo 500 kV line, in
CRR Dry Run results
Slide 36California ISO Confidential. Do not release outside the California ISO.
Revised MRTU Market FNM Added 500 kV Lines
in Arizona, to Improve Power flow Modeling
MOENKOPI
WESTWING
YAVAPAI
PALO VERDE
MEAD
McCULLOUGH
MIDWAY
ADELANTO
VALLEY
DEVERS
SERRANO
LUGO
MIRA LOMA
ELDORADO
MARKETPLAC
E
VINCENT
HASSAYAMPA
TO FOUR
CORNERS
MIGUEL IMPERIAL
VALLEY
NORTH
GILA
MOHAVEVICTORVILLE
West
of
River East of
River
500 kV line
C
alifornia
N
evada
N
evada
Arizona
Arizona
California
ī‚§ Addition of initial “partial loop” FNM added Palo Verde-Westwing and
Westwing-Yavapai-Moenkopi lines.
Slide 37California ISO Confidential. Do not release outside the California ISO.
Additional Testing Experience Has Showed Needs
for Expanding the External Network Model
ī‚§ Example: Hinds to Mirage 230 kV line binding in many hours of
market simulation in August-September, with high impact on LMPs
ī‚§ Impacts in “MRTU Market Simulation Results Review for Week of
8/18/08 thru 8/24/08” (http://www.caiso.com/202f/202fc075dad0.pdf)
ī‚§ Cause of impact was contingency of loss of Victorville-Lugo 500 kV line,
but (1) base case flow on Hinds-Mirage significantly exceeded actual
flow, and (2) impact of contingency significantly exceeded its impact
using a complete network model.
ī‚§ Using a more complete external network results in more accurate
results.
ī‚§ Additional external network modeling also addresses stakeholder
requests
ī‚§ Example: Distribution of flow from sources near Imperial Valley
substation by adding network through Imperial Irrigation District.
Slide 38California ISO Confidential. Do not release outside the California ISO.
ISO is Adding External Lines to FNM in DB37 to
Address the Identified Issues
ī‚§ Additions to FNM in Arizona, Southern Nevada, and
Imperial Irrigation District include:
ī‚§ 500 kV and 345 kV branches,
ī‚§ Connections of all Southern California Scheduling Points to the
500/345 kV grid, except where capacity under ISO operational
control is export-only (i.e., Laughlin intertie), and
ī‚§ Equivalent lines as needed to represent parallel 230 kV and
lower voltage transmission grid.
ī‚§ Additions consist of:
ī‚§ 14 new 500 kV buses, 22 new 345 kV buses, 45 new buses at
230 kV or lower
ī‚§ 211 new lines and transformers
ī‚§ Additions do not change any Scheduling Points.
Slide 39California ISO Confidential. Do not release outside the California ISO.
Additions to FNM in DB37 Nearly Complete the
500 kV Grid in the Southwest
This revised FNM has been used in annual CRR process for
2009 CRRs, and in subsequent Update 2 testing.
Slide 40California ISO Confidential. Do not release outside the California ISO.
Eventually, FNM May Match Physical Model
N AV A JO
M O E N KO PI
W E ST W IN G
Y A VA PA I
P AL O VE R D E
M E AD
M cC U LLO U G H
C R YS TA L
M ID W AY
AD ELA N T O
V A LLE Y
D EV E R S
S ER R A N O
LU G O
M IR A LO M A
E LD O R A D O
M A R KE TP LA C
E
VIN C EN T
R IN ALD I
TO L U C A
G ILA R IVE R
H A R Q U A H A LA
H AS SA Y AM P A
R U D D
JO JO B A
TO KY R E N E
TO FO U R
C O R N ER S
M IG U E L IM P ER IA L
V ALL EY
N O R T H
G ILA
P E R KIN S
M O H AV EV IC TO R VILL E
H A R R Y
A LLE N
W est
of
R iver E ast of
R iver
Ph ase S hifter
500 kV line
C
a
liforn
ia
N
eva
d
a
N e v a d a
A riz o n a
Arizona
California
â€ĸ The complete 500 kV transmission system near the ISO includes lines
operated by LADWP as well as APS, Nevada Power, and WAPA.
â€ĸ Modeling issues include DC lines and phase shifters, as well as loop flow.
Physical model also has loops to Pacific Northwest
Slide 41California ISO Confidential. Do not release outside the California ISO.
Why Not Do More Now?
ī‚§ As stated in 7/21/03 Amended Comprehensive Market Design Proposal,
ISO will ultimately use a FNM that models the external WECC grid.
ī‚§ However, regional flows are complex, with no consistent daily pattern. At
CA-OR border, variation exceeds the average unscheduled (loop) flow.
Actual Unscheduled Flow at Calif.-Oregon Border (S-N)
-1000
-800
-600
-400
-200
0
200
400
600
800
1000
5/1/20060:00
5/16/20060:00
5/31/20060:00
6/15/20060:00
6/30/20060:00
7/15/20060:00
7/30/20060:00
8/14/20060:00
8/29/20060:00
9/13/20060:00
9/28/20060:00
Time
MW
Mean = -53.6, Standard Deviation = 284.0
Slide 42California ISO Confidential. Do not release outside the California ISO.
Simplistic Modeling of Closed Loop Would Not
Produce Correct Results
ī‚§ LMP Study 3A used a closed loop WECC model, without data on
external schedules. Modeled unscheduled flow is difference between
COI schedules and modeled flows on COI branch group.
ī‚§ Result: Poor correlation with actual loop flow (R=0.17). Error in model
of unscheduled flow sometimes exceeds the actual unscheduled flow.
Result of Simplistic Unscheduled Flow Model at
Malin (South to North)
-600
-400
-200
0
200
400
600
8/3/20030:00
8/3/200312:00
8/4/20030:00
8/4/200312:00
8/5/20030:00
8/5/200312:00
8/6/20030:00
8/6/200312:00
8/7/20030:00
8/7/200312:00
8/8/20030:00
8/8/200312:00
8/9/20030:00
8/9/200312:00
8/10/20030:00
Time
MW
Actual Modeled CAISO External Flow
Correlation: R = 0.1706
Slide 43California ISO Confidential. Do not release outside the California ISO.
Plans for further improvement in modeling of
external transmission systems
ī‚§ ISO developed Integrated Balancing Authority Area (IBAA)
modeling of SMUD and TID BAAs using schedules in ISO
Markets, to improve the ISO’s congestion management.
ī‚§ ISO encourages WECC-wide coordination of congestion
management and data exchange, through WECC Seams
Issues Subcommittee (SIS).
ī‚§ In parallel with larger regional effort, ISO will develop
improved BAA modeling using existing data sources:
ī‚§ ISO Market Schedules and e-tags
ī‚§ WECC planning models and Extra High Voltage (EHV) data pool,
subject to WECC confidentiality provisions

More Related Content

Similar to Caiso MRTU implementation workshop nov 2008

NAM Q4a 2011 UAT Strategy Document v1 0
NAM Q4a 2011 UAT Strategy Document v1 0NAM Q4a 2011 UAT Strategy Document v1 0
NAM Q4a 2011 UAT Strategy Document v1 0David Crane
 
Reducing Cycle Time for iDEN Releases – A Development and Test Perspective
Reducing Cycle Time for iDEN Releases – A Development and Test PerspectiveReducing Cycle Time for iDEN Releases – A Development and Test Perspective
Reducing Cycle Time for iDEN Releases – A Development and Test PerspectivePraveen Srivastava
 
Reducing Cycle Time for iDEN Releases – A Development and Test Perspective
Reducing Cycle Time for iDEN Releases – A Development and Test PerspectiveReducing Cycle Time for iDEN Releases – A Development and Test Perspective
Reducing Cycle Time for iDEN Releases – A Development and Test PerspectivePraveen Srivastava
 
UTC Aerospace System - Value Stream Mapping
UTC Aerospace System - Value Stream MappingUTC Aerospace System - Value Stream Mapping
UTC Aerospace System - Value Stream MappingLean6Sigma4all
 
Reliability analysis of wireless automotive applications with transceiver red...
Reliability analysis of wireless automotive applications with transceiver red...Reliability analysis of wireless automotive applications with transceiver red...
Reliability analysis of wireless automotive applications with transceiver red...rchulyada
 
Project Portfolio Francois Bourcier
Project Portfolio Francois BourcierProject Portfolio Francois Bourcier
Project Portfolio Francois BourcierFrancois Bourcier
 
132kV PIPAR CITY GSS - RTU Accessories Pre-SAT Procedure (1).docx
132kV PIPAR CITY  GSS - RTU  Accessories Pre-SAT Procedure (1).docx132kV PIPAR CITY  GSS - RTU  Accessories Pre-SAT Procedure (1).docx
132kV PIPAR CITY GSS - RTU Accessories Pre-SAT Procedure (1).docxAniketSingh198707
 
Scheduling Dedicated
Scheduling DedicatedScheduling Dedicated
Scheduling Dedicatedahmad bassiouny
 
Manufacturing Flow Time Reduction using Digital Twins and Operations Excellen...
Manufacturing Flow Time Reduction using Digital Twins and Operations Excellen...Manufacturing Flow Time Reduction using Digital Twins and Operations Excellen...
Manufacturing Flow Time Reduction using Digital Twins and Operations Excellen...DPrestin1
 
Michael Monaghan - Evolution of New Feature Verification in 3G Networks
Michael Monaghan - Evolution of New Feature Verification in 3G NetworksMichael Monaghan - Evolution of New Feature Verification in 3G Networks
Michael Monaghan - Evolution of New Feature Verification in 3G NetworksTEST Huddle
 
Alfredo paganophd 3y
Alfredo paganophd 3yAlfredo paganophd 3y
Alfredo paganophd 3yAlfredo Pagano
 
65sp3 Rdidp Milestones.07.23.09
65sp3 Rdidp Milestones.07.23.0965sp3 Rdidp Milestones.07.23.09
65sp3 Rdidp Milestones.07.23.09flau3388
 
P1 cl39 bm_dt kpi_acceptance report
P1 cl39 bm_dt kpi_acceptance reportP1 cl39 bm_dt kpi_acceptance report
P1 cl39 bm_dt kpi_acceptance reportaqazad
 
Viavi_TeraVM Core Emulator.pptx
Viavi_TeraVM Core Emulator.pptxViavi_TeraVM Core Emulator.pptx
Viavi_TeraVM Core Emulator.pptxmani723
 
P1 cl11 bm_dt kpi_acceptance report
P1 cl11 bm_dt kpi_acceptance reportP1 cl11 bm_dt kpi_acceptance report
P1 cl11 bm_dt kpi_acceptance reportaqazad
 
Introducing the Galileo PVT App:from Assisted GNSS to NeQuick model in Android
Introducing the Galileo PVT App:from Assisted GNSS to NeQuick model in AndroidIntroducing the Galileo PVT App:from Assisted GNSS to NeQuick model in Android
Introducing the Galileo PVT App:from Assisted GNSS to NeQuick model in AndroidThe European GNSS Agency (GSA)
 
Emerson Eduardo Rodrigues - ENGINEERING STUDIES1 Rp 160667 l2 new wid for l2 ...
Emerson Eduardo Rodrigues - ENGINEERING STUDIES1 Rp 160667 l2 new wid for l2 ...Emerson Eduardo Rodrigues - ENGINEERING STUDIES1 Rp 160667 l2 new wid for l2 ...
Emerson Eduardo Rodrigues - ENGINEERING STUDIES1 Rp 160667 l2 new wid for l2 ...EMERSON EDUARDO RODRIGUES
 
IRJET- A Testbed for Real Time Water Level Control System
IRJET- 	  A Testbed for Real Time Water Level Control SystemIRJET- 	  A Testbed for Real Time Water Level Control System
IRJET- A Testbed for Real Time Water Level Control SystemIRJET Journal
 
NATO MSG-136: M&S as a Service
NATO MSG-136: M&S as a ServiceNATO MSG-136: M&S as a Service
NATO MSG-136: M&S as a ServiceRobert Siegfried
 

Similar to Caiso MRTU implementation workshop nov 2008 (20)

NAM Q4a 2011 UAT Strategy Document v1 0
NAM Q4a 2011 UAT Strategy Document v1 0NAM Q4a 2011 UAT Strategy Document v1 0
NAM Q4a 2011 UAT Strategy Document v1 0
 
Reducing Cycle Time for iDEN Releases – A Development and Test Perspective
Reducing Cycle Time for iDEN Releases – A Development and Test PerspectiveReducing Cycle Time for iDEN Releases – A Development and Test Perspective
Reducing Cycle Time for iDEN Releases – A Development and Test Perspective
 
Reducing Cycle Time for iDEN Releases – A Development and Test Perspective
Reducing Cycle Time for iDEN Releases – A Development and Test PerspectiveReducing Cycle Time for iDEN Releases – A Development and Test Perspective
Reducing Cycle Time for iDEN Releases – A Development and Test Perspective
 
UTC Aerospace System - Value Stream Mapping
UTC Aerospace System - Value Stream MappingUTC Aerospace System - Value Stream Mapping
UTC Aerospace System - Value Stream Mapping
 
Reliability analysis of wireless automotive applications with transceiver red...
Reliability analysis of wireless automotive applications with transceiver red...Reliability analysis of wireless automotive applications with transceiver red...
Reliability analysis of wireless automotive applications with transceiver red...
 
Project Portfolio Francois Bourcier
Project Portfolio Francois BourcierProject Portfolio Francois Bourcier
Project Portfolio Francois Bourcier
 
132kV PIPAR CITY GSS - RTU Accessories Pre-SAT Procedure (1).docx
132kV PIPAR CITY  GSS - RTU  Accessories Pre-SAT Procedure (1).docx132kV PIPAR CITY  GSS - RTU  Accessories Pre-SAT Procedure (1).docx
132kV PIPAR CITY GSS - RTU Accessories Pre-SAT Procedure (1).docx
 
Scheduling Dedicated
Scheduling DedicatedScheduling Dedicated
Scheduling Dedicated
 
Manufacturing Flow Time Reduction using Digital Twins and Operations Excellen...
Manufacturing Flow Time Reduction using Digital Twins and Operations Excellen...Manufacturing Flow Time Reduction using Digital Twins and Operations Excellen...
Manufacturing Flow Time Reduction using Digital Twins and Operations Excellen...
 
Temp efv
Temp efvTemp efv
Temp efv
 
Michael Monaghan - Evolution of New Feature Verification in 3G Networks
Michael Monaghan - Evolution of New Feature Verification in 3G NetworksMichael Monaghan - Evolution of New Feature Verification in 3G Networks
Michael Monaghan - Evolution of New Feature Verification in 3G Networks
 
Alfredo paganophd 3y
Alfredo paganophd 3yAlfredo paganophd 3y
Alfredo paganophd 3y
 
65sp3 Rdidp Milestones.07.23.09
65sp3 Rdidp Milestones.07.23.0965sp3 Rdidp Milestones.07.23.09
65sp3 Rdidp Milestones.07.23.09
 
P1 cl39 bm_dt kpi_acceptance report
P1 cl39 bm_dt kpi_acceptance reportP1 cl39 bm_dt kpi_acceptance report
P1 cl39 bm_dt kpi_acceptance report
 
Viavi_TeraVM Core Emulator.pptx
Viavi_TeraVM Core Emulator.pptxViavi_TeraVM Core Emulator.pptx
Viavi_TeraVM Core Emulator.pptx
 
P1 cl11 bm_dt kpi_acceptance report
P1 cl11 bm_dt kpi_acceptance reportP1 cl11 bm_dt kpi_acceptance report
P1 cl11 bm_dt kpi_acceptance report
 
Introducing the Galileo PVT App:from Assisted GNSS to NeQuick model in Android
Introducing the Galileo PVT App:from Assisted GNSS to NeQuick model in AndroidIntroducing the Galileo PVT App:from Assisted GNSS to NeQuick model in Android
Introducing the Galileo PVT App:from Assisted GNSS to NeQuick model in Android
 
Emerson Eduardo Rodrigues - ENGINEERING STUDIES1 Rp 160667 l2 new wid for l2 ...
Emerson Eduardo Rodrigues - ENGINEERING STUDIES1 Rp 160667 l2 new wid for l2 ...Emerson Eduardo Rodrigues - ENGINEERING STUDIES1 Rp 160667 l2 new wid for l2 ...
Emerson Eduardo Rodrigues - ENGINEERING STUDIES1 Rp 160667 l2 new wid for l2 ...
 
IRJET- A Testbed for Real Time Water Level Control System
IRJET- 	  A Testbed for Real Time Water Level Control SystemIRJET- 	  A Testbed for Real Time Water Level Control System
IRJET- A Testbed for Real Time Water Level Control System
 
NATO MSG-136: M&S as a Service
NATO MSG-136: M&S as a ServiceNATO MSG-136: M&S as a Service
NATO MSG-136: M&S as a Service
 

More from Kevin Forbes

20071005 jcm-loop-flow-study-phase-02
20071005 jcm-loop-flow-study-phase-0220071005 jcm-loop-flow-study-phase-02
20071005 jcm-loop-flow-study-phase-02Kevin Forbes
 
20070525 loop-flow-investigation-report
20070525 loop-flow-investigation-report20070525 loop-flow-investigation-report
20070525 loop-flow-investigation-reportKevin Forbes
 
ELtra 2004 annual report
ELtra 2004 annual report ELtra 2004 annual report
ELtra 2004 annual report Kevin Forbes
 
Saee presentation august 24 2016 v2
Saee presentation   august 24 2016 v2Saee presentation   august 24 2016 v2
Saee presentation august 24 2016 v2Kevin Forbes
 
Forbes ams presentation 23 jan 2017
Forbes ams presentation   23 jan 2017Forbes ams presentation   23 jan 2017
Forbes ams presentation 23 jan 2017Kevin Forbes
 
Forbes usaee lecture lehigh university nov 5 2015
Forbes usaee lecture    lehigh university nov 5 2015Forbes usaee lecture    lehigh university nov 5 2015
Forbes usaee lecture lehigh university nov 5 2015Kevin Forbes
 
Forbes co2 and temperature presentation for earth day at cua april 22 2015 ...
Forbes   co2 and temperature presentation for earth day at cua april 22 2015 ...Forbes   co2 and temperature presentation for earth day at cua april 22 2015 ...
Forbes co2 and temperature presentation for earth day at cua april 22 2015 ...Kevin Forbes
 

More from Kevin Forbes (7)

20071005 jcm-loop-flow-study-phase-02
20071005 jcm-loop-flow-study-phase-0220071005 jcm-loop-flow-study-phase-02
20071005 jcm-loop-flow-study-phase-02
 
20070525 loop-flow-investigation-report
20070525 loop-flow-investigation-report20070525 loop-flow-investigation-report
20070525 loop-flow-investigation-report
 
ELtra 2004 annual report
ELtra 2004 annual report ELtra 2004 annual report
ELtra 2004 annual report
 
Saee presentation august 24 2016 v2
Saee presentation   august 24 2016 v2Saee presentation   august 24 2016 v2
Saee presentation august 24 2016 v2
 
Forbes ams presentation 23 jan 2017
Forbes ams presentation   23 jan 2017Forbes ams presentation   23 jan 2017
Forbes ams presentation 23 jan 2017
 
Forbes usaee lecture lehigh university nov 5 2015
Forbes usaee lecture    lehigh university nov 5 2015Forbes usaee lecture    lehigh university nov 5 2015
Forbes usaee lecture lehigh university nov 5 2015
 
Forbes co2 and temperature presentation for earth day at cua april 22 2015 ...
Forbes   co2 and temperature presentation for earth day at cua april 22 2015 ...Forbes   co2 and temperature presentation for earth day at cua april 22 2015 ...
Forbes co2 and temperature presentation for earth day at cua april 22 2015 ...
 

Recently uploaded

MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Study on Air-Water & Water-Water Heat Exchange in a Finned īģŋTube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned īģŋTube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned īģŋTube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned īģŋTube ExchangerAnamika Sarkar
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoÃŖo Esperancinha
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEslot gacor bisa pakai pulsa
 

Recently uploaded (20)

MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
Study on Air-Water & Water-Water Heat Exchange in a Finned īģŋTube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned īģŋTube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned īģŋTube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned īģŋTube Exchanger
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 

Caiso MRTU implementation workshop nov 2008

  • 2. Slide 2California ISO Confidential. Do not release outside the California ISO. Agenda—November 13, 2008 Jim PricePartial Loop Network Configuration2:20 – 2:50 Jami LongStructure and Plans for Cutover Plan Walkthrough ī‚§ Detailed Walkthrough Scheduled for November 20, 2008 2:00 – 2:20 Jason IacobucciContinued Discussion of IMS Plans1:00 – 2:00 Lunch12:00 – 1:00 Jason IacobucciMRTU Business Implementation ī‚§ Business Implementation Schedule ī‚§ Parallel Operations Testing 10:00 – 12:00 PresenterTopicTime
  • 3. MRTU Implementation Workshop MRTU Business Implementation Schedule November 13, 2008
  • 4. Slide 4California ISO Confidential. Do not release outside the California ISO. Background ī‚§ Major remaining tasks: ī‚§ Completion of Update 2 ī‚§ Commencement of Pre-Production phase of Program ī‚§ Objectives ī‚§ Complete functional phases of Market Simulation ī‚§ Build ISO and Market Participant confidence in cutover activities and MRTU production business processes ī‚§ Prepare for Go-Live
  • 5. Slide 5California ISO Confidential. Do not release outside the California ISO. Definitions ī‚§ For the purposes of this presentation, the following terms are used: ī‚§ Pre-Production ī‚§ Testing phase focuses on preparing people, process, and technology for MRTU market launch. Includes elements of Parallel Operations, Cutover /Reversion testing, and ultimately cutover and Go-Live ī‚§ Parallel Operations ī‚§ Activities comprised of defined test cycles where some aspect of the MRTU simulation parallels Production Business and/ or Technical processes (e.g. RT Operational Support, following Production Load Forecast, etc.) ī‚§ Cutover / Reversion ī‚§ Testing and execution activities intended to prepare CAISO and Market Participants for MRTU Go-Live, including a series of Open-Loop tests
  • 6. Slide 6California ISO Confidential. Do not release outside the California ISO. MRTU Business Implementation Schedule Sep 2008 Oct 2008 Nov 2008 Dec 2008 Jan 2009 MRTUProgramSchedule Target U2 Exit Criteria Met â€ĸScenario Testing Priority1 â€ĸ9/8-9/26 Go-Live 2/1/09 FERC 60 Day Certification Filing Production Environment and Network Model Upgrades ` MRTU Release Management 10/1 – Go-live Desktop Cutover/ Reversion Plan Walkthrough with MPs Market Participant Testing Pre-Production/ Cutover â€ĸScenario Testing Priority2 â€ĸ10/6-10/17 Downtime 10/18-10/25 Market Participant Testing Downtime 12/20-12/27 `Cutover/ Reversion Planning ` CRR Allocation LECG Final Report 9/26 Tier 1 Results MP Final Readiness Assessments FERC 30 Day Readiness Filing 10/13 Tier 2 Results 10/28 Long- term Results 11/11 Tier 3 Results 12/2 Annual Auction Results `CRR Auction MP Readiness Assessment â€ĸ11/ 3- 11/ 7
  • 7. Slide 7California ISO Confidential. Do not release outside the California ISO. MRTU Business Implementation Schedule Sep 2008 Oct 2008 Nov 2008 Dec 2008 Jan 2009 MRTUProgramSchedule Go-Live 2/1/09 9/14 2 Week Master File Publishing Schedule Weekly Master File Publishing Schedule Daily Master File Publishing Schedule 9/28 10/12 11/2 11/9 Downtime 10/18-10/25 Downtime 12/20-12/27 10/26 12/28 Network Model Update Network Model Update – Go Live DB23 DB32 DB 32++DB32+
  • 8. MRTU Implementation Workshop MRTU Parallel Operations Testing November 13, 2008
  • 9. Slide 9California ISO Confidential. Do not release outside the California ISO. Agenda ī‚§ Introduction ī‚§ Objectives ī‚§ Proposed Test Cycles ī‚§ Open Loop Test 1 (OL-1) ī‚§ Simulated Closed Loop Test 2 (SCL-2) ī‚§ Open Loop Tests 3 (OL-3) and 4 (OL-4) ī‚§ Proposed Schedule
  • 10. Slide 10California ISO Confidential. Do not release outside the California ISO. Parallel Ops Test Objectives ī‚§ Establish confidence in the operational processes and systems associated with the MRTU implementation ī‚§ Demonstrate the infrastructure required for the California ISO to support MRTU Pre-Production functions ī‚§ Demonstrate the infrastructure required for the California ISO to support the Cutover/Reversion Plan ī‚§ Provide Market Participants with mock/test versions of the Pre- Production and Cutover phases
  • 11. Slide 11California ISO Confidential. Do not release outside the California ISO. Proposed Test Cycles ī‚§ CAISO proposes four test cycles during Parallel Ops, reflecting two general categories: ī‚§ Open Loop testing, where pre-MRTU Production EMS communicates directly with market systems in the MRTU environment ī‚§ Simulated Closed Loop testing, involving a simulated EMS State Estimator solution and telemetry Test Cycle ID Description Duration Test Circuit- Resource Feedback Loop SE Solution Load Forecast Outages (SLIC) Intertie Schedules (OATI) Bidsets (SIBR) Dispatch Instructions (ADS) OL-1 Open loop testing with a single SC for a single resource. Production EMS will feed MRTU Market Simulation environment only. 30 minutes Open EMS Production MRTU MRTU MRTU Production SCL-2 Simulation of all MRTU business processes and systems with 24x7 inputs from Market Participants. Current Production Load Forecast is fed into MRTU ALFS in order to more accurately simulate transition between operating days. ISO provides 24x7 Grid Operations support. 60 days Simulated Closed GOTS 1. Summer week (pre-DB37) 2. Production (post- DB37) MRTU (Open) MRTU (Open) MRTU (Follow Production Load Forecast) MRTU OL-3 Open loop test, where the MRTU environment shadows Production as closely as possible but units do not adhere to MRTU dispatches (therefore EMS feeds back in do not mirror MRTU results). Network model descprepencies will be handled on a case-by-case basis 30 minutes Open EMS Production MRTU (Shadow Production) MRTU (Shadow Production) MRTU (Shadow Production) Production OL-4 Synchronize network model with Production 60 minutes Open EMS Production MRTU (Shadow Production) MRTU (Shadow Production) MRTU (Shadow Production) Production
  • 12. Slide 12California ISO Confidential. Do not release outside the California ISO. Proposed Test Cycles Open Loop Test 1 ī‚§ Description ī‚§ Open loop testing with a single SC for a single resource ī‚§ Production EMS will feed MRTU Market Simulation environment only ī‚§ Objective ī‚§ Test the integration of Production EMS with the MRTU market systems ī‚§ Expected result ī‚§ Integration successful: communication established between Production EMS for one unit with MRTU market systems
  • 13. Slide 13California ISO Confidential. Do not release outside the California ISO. Proposed Test Cycles Open Loop Test 1 ī‚§ MRTU Data Feeds ī‚§ SE Solution/Telemetry: Production EMS ī‚§ Load Forecast: Production ī‚§ Outages: MRTU (Not mirroring Production) ī‚§ Intertie Schedules: MRTU (Not mirroring Production) ī‚§ Bidsets: MRTU (Not mirroring Production) ī‚§ Dispatch Instructions: MRTU (No dispatches to real units)
  • 14. Slide 14California ISO Confidential. Do not release outside the California ISO. Proposed Test Cycles Simulated Closed Loop Test 2 ī‚§ Description ī‚§ Simulation of all MRTU business processes and systems with 24x7 inputs from Market Participants ī‚§ Current Production Load Forecast is fed into MRTU ALFS in order to more accurately simulate transition between operating days ī‚§ ISO provides 24x7 Grid Operations support ī‚§ Objectives ī‚§ Provide Market Participants with as close to Production-like Business Processes as possible. ī‚§ Specifically, during this test CAISO will rely on Market Participants to provide all of the same inputs – from bids and schedules through dispatch acceptance and meter data – that they would in MRTU Production
  • 15. Slide 15California ISO Confidential. Do not release outside the California ISO. Proposed Test Cycles Simulated Closed Loop Test 2 ī‚§ MRTU Data Feeds ī‚§ SE Solution/Telemetry: GOTS (Simulated EMS) ī‚§ Load Forecast: Summer week (pre-DB37) Production (after DB37 deployed) ī‚§ Outages: MRTU (Open) ī‚§ Intertie Schedules: MRTU (Open) ī‚§ Bidsets: MRTU (Follow Production Load Forecast) ī‚§ Dispatch Instructions: MRTU (No dispatches to real units)
  • 16. Slide 16California ISO Confidential. Do not release outside the California ISO. Proposed Test Cycles Open Loop Tests 3 and 4 ī‚§ Description ī‚§ Prepare both the ISO and Market Participants for the short overlap time during Go-Live where current Production must mirror MRTU ī‚§ OL-4 provides a longer duration than OL-3 ī‚§ Objectives ī‚§ Simulate the cutover period by having Market Participants mirror Production as closely as possible, including matching bidding to balanced schedules ī‚§ Production outages and intertie schedules are reflected in RTM results, do not cause major issues with RTM solutions
  • 17. Slide 17California ISO Confidential. Do not release outside the California ISO. Proposed Test Cycles Open Loop Tests 3 and 4 ī‚§ Data Feeds ī‚§ SE Solution/Telemetry: EMS ī‚§ Load Forecast: Production ī‚§ Outages: MRTU (Shadow Production*) ī‚§ Intertie Schedules: MRTU (Shadow Production) ī‚§ Bidsets: MRTU (Shadow Production) ī‚§ Dispatch Instructions: MRTU (No dispatches to real units) * CAISO will facilitate shadowing production by providing a matrix to map pre-MRTU Production inputs to MRTU inputs
  • 18. Slide 18California ISO Confidential. Do not release outside the California ISO. Parallel Ops Test Proposed Schedule ī‚§ In the proposed schedule below: ī‚§ SCL-2 will be supported by Grid Operations on an ongoing, 24x7 basis over a long duration ī‚§ Multiple iterations of OL-1, OL-2, and OL-3 may be run on single dates throughout the testing period
  • 19. Slide 19California ISO Confidential. Do not release outside the California ISO. Parallel Ops Test Proposed Schedule ī‚§ Grid Operations Ramp-Up ī‚§ Grid Operations support will be phased in over the final two weeks of November: ī‚§ 11/17 – 11/21 6AM to 6PM daily support of SLIC Outages and ADS dispatches; ADS auto-approve script is disabled ī‚§ 11/24 – 11/26 6AM to 6PM daily support of SLIC Outages, ADS dispatches, and CAS eTags (intertie schedules); ADS auto-accept script is disabled, CAS schedule-creation script is disabled ī‚§ 12/1 – 12/20 24x7 support for SLIC Outages, ADS dispatches, and CAS eTags ī‚§ SCL-2 will be supported by Grid Operations on an ongoing, 24x7 basis over a long duration ī‚§ RT Operations contact numbers will be provided by end of week
  • 20. Slide 20California ISO Confidential. Do not release outside the California ISO. Questions / Feedback
  • 21. CAISO MRTU Cutover & Reversion C&R Planning Overview November 13, 2008 Jami Long, Manager, Operations Information Technology
  • 22. Slide 22California ISO Confidential. Do not release outside the California ISO. Agenda ī‚§ Phases & Deliverables ī‚§ Planning Phase - Internal ī‚§ Planning Phase – External ī‚§ Preparation ī‚§ Transition ī‚§ Closure ī‚§ Review Approach ī‚§ System Access Approach
  • 23. Slide 23California ISO Confidential. Do not release outside the California ISO. C&R Planning Phase - Internal ī‚§ Planning Phase includes all artifacts required to execute Preparation and Transition phases ī‚§ Internal Deliverables Include: ī‚§ Communication Plan ī‚§ Detailed Application C&R Plans ī‚§ Detailed Cutover Schedule ī‚§ Detailed Reversion Schedule ī‚§ Support Plan
  • 24. Slide 24California ISO Confidential. Do not release outside the California ISO. Cutover Planning Phase - External ī‚§ External deliverables include: ī‚§ C&R External Overview ī‚§ Cutover Timeline ī‚§ Detailed External Cutover Schedule ī‚§ Detailed External Reversion Schedule ī‚§ C&R Plan Validation will occur during Parallel Operations
  • 25. Slide 25California ISO Confidential. Do not release outside the California ISO. Cutover Preparation Phase ī‚§ Preparation includes system readiness activities that will occur throughout the Parallel Operation and Pre- Production windows ī‚§ Data Migration ī‚§ Data Purging Preparation ī‚§ System Access Validation ī‚§ Finalize Support Plan
  • 26. Slide 26California ISO Confidential. Do not release outside the California ISO. Cutover Transition Phase ī‚§ Transition is the execution of tasks to prepare data and begin using systems for production purposes ī‚§ Data Migration True-up ī‚§ Data Purge ī‚§ Cutover Scripts/Tasks ī‚§ Transition begins TD-15
  • 27. Slide 27California ISO Confidential. Do not release outside the California ISO. Cutover Closure Phase ī‚§ Closure is the phase following the reversion window. This phase includes: ī‚§ Legacy System Plan Execution ī‚§ Lessons Learned
  • 28. Slide 28California ISO Confidential. Do not release outside the California ISO. Cutover & Reversion Review Approach ī‚§ 11/20 ī‚§ Review Cutover External Overview Updates ī‚§ Walkthrough Detailed Cutover Schedule ī‚§ Communications and Support Plan Overview ī‚§ 12/04 ī‚§ Review Reversion External Overview Updates ī‚§ Walkthrough Detailed Reversion Schedule ī‚§ 12/18 ī‚§ Walkthrough Final Changes ī‚§ Follow Up on Open Items
  • 29. Slide 29California ISO Confidential. Do not release outside the California ISO. System Access ī‚§ MRTU Production Access Requests Form (ARF) allows submission of all users for an application or set of applications on a single form. ī‚§ 11/15 – Production access requests are due back from POCs. ī‚§ 12/1 – All production user access permissions are configured in both market simulation and Folsom production. ī‚§ 12/14 – All external non-production access will be removed from Folsom production. This will allow us to identify any “missed” people or systems. ī‚§ New production users without market simulation access must submit an MRTU production ARF.
  • 30. Slide 30California ISO Confidential. Do not release outside the California ISO. System Access ī‚§ Existing market simulation users that require production access: ī‚§ Must submit a production ARF for SIBR, CMRI, BAPI and CRN ī‚§ Must submit production ARF for legacy systems (ADS, SLIC, PIRP, and OMAR) IF you do not have production access today. If you already have production access, you do not need to request access. ī‚§ New certificates are not required as production certificates are currently in use. ī‚§ Existing market simulation users that require test/market simulation access only will no longer have access to MRTU Folsom production effective 12/14. Access/certificates will be carried over to the new market simulation environment when Folsom production access is eliminated.
  • 31. Implementation of “Partial Loop” Intertie Network Configuration Jim Price Lead Engineering Specialist Market & Product Development MRTU Implementation Workshop November 13, 2008
  • 32. Slide 32California ISO Confidential. Do not release outside the California ISO. Topics of Discussion Extension of MRTU modeling of external areas other than Integrated Balancing Authority Areas, for more accurate congestion management and LMPs: ī‚§ Market simulation results have showed needs for expanding the Full Network Model outside the ISO. ISO is adding external lines in DB37 model. Presentation: ī‚§ Background of previous modeling of “New PTO” and “partial loop” networks ī‚§ Addition of transmission lines outside California, as “partial loop” model ī‚§ Plans for further improvement in modeling of external transmission systems
  • 33. Slide 33California ISO Confidential. Do not release outside the California ISO. The “New PTO” network consists of “Converted Rights” on transmission outside the CAISO area. The “New PTO” area in Southern California, Nevada, and Arizona is documented in the Full Network Model BPM (section 4.2.4.3), and in a 8/25/2006 white paper at http://www.caiso.com/185d/185db75028b00.pdf. Operating Procedure S-326 will provide further detail. MRTU Transmission Model Includes “New PTO” Network
  • 34. Slide 34California ISO Confidential. Do not release outside the California ISO. “New PTO” Modeling Introduced External Loops of 500 kV Lines in Original MRTU Market FNM MOENKOPI WESTWING PALO VERDE MEAD McCULLOUGH MIDWAY ADELANTO VALLEY DEVERS SERRANO LUGO MIRA LOMA ELDORADO MARKETPLAC E VINCENT HASSAYAMPA TO FOUR CORNERS MIGUEL IMPERIAL VALLEY NORTH GILA MOHAVEVICTORVILLE West of River East of River 500 kV line C alifornia N evada N evada Arizona Arizona California Original MRTU Market FNM consisted of ISO Controlled Grid and “open loop” interties, New PTO network, embedded and adjacent control area concepts, and external branch group connections.
  • 35. Slide 35California ISO Confidential. Do not release outside the California ISO. Early Testing Experience Showed Problems with “Open Loop” Intertie Model ī‚§ Simulations in LMP Studies and CRR Dry Run identified mismatches between modeled flows and actual flows measured by telemetry, using original “open loop” model: ī‚§ Excessive modeled flow on Palo Verde – Devers 500 kV line caused adverse LMP impacts in LMP Study (discussed in 4/20/07 LMP Study Update and 1/8/08 IBAA stakeholder meeting) ī‚§ LMP Studies 3A and 3C showed significant congestion at Miguel substation from August 2003, when new generators started operation, to December 2004, when transmission upgrades were complete. ī‚§ Since December 2004, new generators operate at higher output, and original “open loop” model showed congestion on Palo Verde to Devers 500 kV line. ī‚§ Unrealistic binding constraint on El Dorado – Lugo 500 kV line, in CRR Dry Run results
  • 36. Slide 36California ISO Confidential. Do not release outside the California ISO. Revised MRTU Market FNM Added 500 kV Lines in Arizona, to Improve Power flow Modeling MOENKOPI WESTWING YAVAPAI PALO VERDE MEAD McCULLOUGH MIDWAY ADELANTO VALLEY DEVERS SERRANO LUGO MIRA LOMA ELDORADO MARKETPLAC E VINCENT HASSAYAMPA TO FOUR CORNERS MIGUEL IMPERIAL VALLEY NORTH GILA MOHAVEVICTORVILLE West of River East of River 500 kV line C alifornia N evada N evada Arizona Arizona California ī‚§ Addition of initial “partial loop” FNM added Palo Verde-Westwing and Westwing-Yavapai-Moenkopi lines.
  • 37. Slide 37California ISO Confidential. Do not release outside the California ISO. Additional Testing Experience Has Showed Needs for Expanding the External Network Model ī‚§ Example: Hinds to Mirage 230 kV line binding in many hours of market simulation in August-September, with high impact on LMPs ī‚§ Impacts in “MRTU Market Simulation Results Review for Week of 8/18/08 thru 8/24/08” (http://www.caiso.com/202f/202fc075dad0.pdf) ī‚§ Cause of impact was contingency of loss of Victorville-Lugo 500 kV line, but (1) base case flow on Hinds-Mirage significantly exceeded actual flow, and (2) impact of contingency significantly exceeded its impact using a complete network model. ī‚§ Using a more complete external network results in more accurate results. ī‚§ Additional external network modeling also addresses stakeholder requests ī‚§ Example: Distribution of flow from sources near Imperial Valley substation by adding network through Imperial Irrigation District.
  • 38. Slide 38California ISO Confidential. Do not release outside the California ISO. ISO is Adding External Lines to FNM in DB37 to Address the Identified Issues ī‚§ Additions to FNM in Arizona, Southern Nevada, and Imperial Irrigation District include: ī‚§ 500 kV and 345 kV branches, ī‚§ Connections of all Southern California Scheduling Points to the 500/345 kV grid, except where capacity under ISO operational control is export-only (i.e., Laughlin intertie), and ī‚§ Equivalent lines as needed to represent parallel 230 kV and lower voltage transmission grid. ī‚§ Additions consist of: ī‚§ 14 new 500 kV buses, 22 new 345 kV buses, 45 new buses at 230 kV or lower ī‚§ 211 new lines and transformers ī‚§ Additions do not change any Scheduling Points.
  • 39. Slide 39California ISO Confidential. Do not release outside the California ISO. Additions to FNM in DB37 Nearly Complete the 500 kV Grid in the Southwest This revised FNM has been used in annual CRR process for 2009 CRRs, and in subsequent Update 2 testing.
  • 40. Slide 40California ISO Confidential. Do not release outside the California ISO. Eventually, FNM May Match Physical Model N AV A JO M O E N KO PI W E ST W IN G Y A VA PA I P AL O VE R D E M E AD M cC U LLO U G H C R YS TA L M ID W AY AD ELA N T O V A LLE Y D EV E R S S ER R A N O LU G O M IR A LO M A E LD O R A D O M A R KE TP LA C E VIN C EN T R IN ALD I TO L U C A G ILA R IVE R H A R Q U A H A LA H AS SA Y AM P A R U D D JO JO B A TO KY R E N E TO FO U R C O R N ER S M IG U E L IM P ER IA L V ALL EY N O R T H G ILA P E R KIN S M O H AV EV IC TO R VILL E H A R R Y A LLE N W est of R iver E ast of R iver Ph ase S hifter 500 kV line C a liforn ia N eva d a N e v a d a A riz o n a Arizona California â€ĸ The complete 500 kV transmission system near the ISO includes lines operated by LADWP as well as APS, Nevada Power, and WAPA. â€ĸ Modeling issues include DC lines and phase shifters, as well as loop flow. Physical model also has loops to Pacific Northwest
  • 41. Slide 41California ISO Confidential. Do not release outside the California ISO. Why Not Do More Now? ī‚§ As stated in 7/21/03 Amended Comprehensive Market Design Proposal, ISO will ultimately use a FNM that models the external WECC grid. ī‚§ However, regional flows are complex, with no consistent daily pattern. At CA-OR border, variation exceeds the average unscheduled (loop) flow. Actual Unscheduled Flow at Calif.-Oregon Border (S-N) -1000 -800 -600 -400 -200 0 200 400 600 800 1000 5/1/20060:00 5/16/20060:00 5/31/20060:00 6/15/20060:00 6/30/20060:00 7/15/20060:00 7/30/20060:00 8/14/20060:00 8/29/20060:00 9/13/20060:00 9/28/20060:00 Time MW Mean = -53.6, Standard Deviation = 284.0
  • 42. Slide 42California ISO Confidential. Do not release outside the California ISO. Simplistic Modeling of Closed Loop Would Not Produce Correct Results ī‚§ LMP Study 3A used a closed loop WECC model, without data on external schedules. Modeled unscheduled flow is difference between COI schedules and modeled flows on COI branch group. ī‚§ Result: Poor correlation with actual loop flow (R=0.17). Error in model of unscheduled flow sometimes exceeds the actual unscheduled flow. Result of Simplistic Unscheduled Flow Model at Malin (South to North) -600 -400 -200 0 200 400 600 8/3/20030:00 8/3/200312:00 8/4/20030:00 8/4/200312:00 8/5/20030:00 8/5/200312:00 8/6/20030:00 8/6/200312:00 8/7/20030:00 8/7/200312:00 8/8/20030:00 8/8/200312:00 8/9/20030:00 8/9/200312:00 8/10/20030:00 Time MW Actual Modeled CAISO External Flow Correlation: R = 0.1706
  • 43. Slide 43California ISO Confidential. Do not release outside the California ISO. Plans for further improvement in modeling of external transmission systems ī‚§ ISO developed Integrated Balancing Authority Area (IBAA) modeling of SMUD and TID BAAs using schedules in ISO Markets, to improve the ISO’s congestion management. ī‚§ ISO encourages WECC-wide coordination of congestion management and data exchange, through WECC Seams Issues Subcommittee (SIS). ī‚§ In parallel with larger regional effort, ISO will develop improved BAA modeling using existing data sources: ī‚§ ISO Market Schedules and e-tags ī‚§ WECC planning models and Extra High Voltage (EHV) data pool, subject to WECC confidentiality provisions