SlideShare a Scribd company logo
1 of 19
Virtual Commissioning + Real-Time Training =
Increased Performance & Profits
info@gses.com
2
Overview
• Gas conversion of existing coal power plant
• Project execution strategy for existing virtual simulator
• Benefits of having a simulator before plant gas startup
commissioning
3
Overview of Gas Conversion
• Increasingly stringent and uncertain regulatory environment
• Plus, falling natural gas prices
• These conditions have made converting existing coal-fired steam-
generating boilers to natural gas firing more and more attractive.
• Based on recent gas conversion announcements, existing coal units
generating a total of approximately 9,000 MW will be converted for
natural gas firing.
Source : Power Engineering Magazine (www.power-eng.com) – “Coal to Natural Gas Conversion – Drivers and Lessons”
4
Overview of Gas Conversion
The major drivers of this trend have been:
– Mercury and Air Toxics Standards (MATS) regulations
– New Source Review (NSR) settlements
– Natural Gas availability and pricing
– The uniqueness of each project to deliver electricity at the required
capacity to make it economically feasible to convert existing coal-fired
units to natural gas-firing capability.
Source : Power Engineering Magazine (www.power-eng.com) – “Coal to Natural Gas Conversion – Drivers and Lessons”
5
Simulator Considerations
• Using natural gas changes the heat absorption characteristics in the boiler
and convection pass. There are modifications that have to be made to
meet the designed steam temperatures and full boiler output.
• In addition, considerations have to be given to achieve low emission goals.
These modifications include:
– Gas Supply: Modifications to the gas supply and vent piping, installation of pressure-
reducing valve station.
– Boiler: Modifications to the radiation and/or convective area to help achieve original
steam temperatures, new burners and igniters, windbox modifications
– Flue Gas Recirculation (FGR): FGR to control NOX and steam temperatures by recycling a
portion of the flue gas from the economizer outlet back into the windbox
– Flue Gas System: Modifications to the Air & Gas System. Forced-draft/induced-draft fan
modifications and other control functions to maintain furnace pressure.
6
• From GSE: Two team members including an
engineering manager
• From DCS: One project engineer
• From plant: Energy production supervisor and two
shift supervisors
Resource Team
7
Overview of Project Execution Strategy
• Schedule
• DCS virtual configuration
• Project staging
• Discrepancy recording system
8
Schedule
Simulator Model Design Process
1. Conference call kickoff meeting
2. Model scope design review meeting
3. Model changes
4. FAT’ed DCS shipped to GSE
5. Integration & testing at GSE
9
Simulator Air & Gas Drawing
10
Simulator Fuel Gas Drawing
11
Simulator Boiler Drawing
12
DCS Virtual Configuration
• DCS was already converted to the DCS vendor’s
virtual controllers
• FAT’ed DCS shipped to GSE
• 3 Dual monitor operator stations
13
Plant Simulator Layout
14
Project Staging
Staged at GSE facility
1. Access to model engineer(s)
2. Plant operators
3. After initial integration, remote access provided to
DCS vendor for support
15
Discrepancy Recording System
GSE Mantis DR System
• An online system where users can be easily added
• Different sections available for different types of
discrepancies
• Severity of discrepancy can be assigned
• Discrepancy can be assigned to people, commented on,
and edited
16
Overall Benefits
Total DCS issues identified: 63
• Potentially costly items
• Drum level reference changed
• Boiler feed pump controls
• Trips were not connected
• Control schemes were changed
17
Overall Benefits Continued
• Plant trip conditions can be tested that require either
third party controls or DCS control logic modifications.
• Startup/shutdown procedures can be adjusted ahead of
time based on interaction with the simulator during
integration.
18
• Real-time training during the integration and FAT Phases
• Required graphics & logic tuning and modifications can be
sent to the plant for more efficient commissioning of the
new gas controls.
Conclusion
Thank you.
For more information, go to:
www.GSES.com
info@gses.com
Or call 800-638-7912

More Related Content

What's hot

Equipment sizing and costing using Petro-SIM
Equipment sizing and costing using Petro-SIMEquipment sizing and costing using Petro-SIM
Equipment sizing and costing using Petro-SIMKBC (A Yokogawa Company)
 
Model based design-Hardware in loop-software in loop
Model based design-Hardware in loop-software in loopModel based design-Hardware in loop-software in loop
Model based design-Hardware in loop-software in loopMahmoud Hussein
 
Europe User Conference: BP - implementing and supporting a multi-model, multi...
Europe User Conference: BP - implementing and supporting a multi-model, multi...Europe User Conference: BP - implementing and supporting a multi-model, multi...
Europe User Conference: BP - implementing and supporting a multi-model, multi...KBC (A Yokogawa Company)
 
Building Grid Resilience
Building Grid ResilienceBuilding Grid Resilience
Building Grid ResilienceAdvisian
 
Europe User Conference: Galp refinery wide model - a real work example
Europe User Conference: Galp refinery wide model - a real work exampleEurope User Conference: Galp refinery wide model - a real work example
Europe User Conference: Galp refinery wide model - a real work exampleKBC (A Yokogawa Company)
 
Asphalt batch process with PLC & SCADA ppt
Asphalt batch process with PLC & SCADA pptAsphalt batch process with PLC & SCADA ppt
Asphalt batch process with PLC & SCADA pptjazz_306
 
Combined Heat and Power Engineering and Installation in the Pacific NW
Combined Heat and Power Engineering and Installation in the Pacific NWCombined Heat and Power Engineering and Installation in the Pacific NW
Combined Heat and Power Engineering and Installation in the Pacific NWmelanie_bissonnette
 
Europe User Conference: KBC Engineering Suite v7
Europe User Conference: KBC Engineering Suite v7Europe User Conference: KBC Engineering Suite v7
Europe User Conference: KBC Engineering Suite v7KBC (A Yokogawa Company)
 
Wind farm re-powering, life extension and decommissioning
Wind farm re-powering, life extension and decommissioningWind farm re-powering, life extension and decommissioning
Wind farm re-powering, life extension and decommissioningAdvisian
 
Mechanical Engineering Seminar 2017_2
Mechanical Engineering Seminar 2017_2Mechanical Engineering Seminar 2017_2
Mechanical Engineering Seminar 2017_2Nicholas Naing
 
Mechanical Engineering Seminar 2017_1
Mechanical Engineering Seminar 2017_1Mechanical Engineering Seminar 2017_1
Mechanical Engineering Seminar 2017_1Nicholas Naing
 
Advisian dynamic process simulation capability june 2019
Advisian dynamic process simulation capability june 2019Advisian dynamic process simulation capability june 2019
Advisian dynamic process simulation capability june 2019Advisian
 

What's hot (20)

Sustaining energy performance
Sustaining energy performanceSustaining energy performance
Sustaining energy performance
 
Equipment sizing and costing using Petro-SIM
Equipment sizing and costing using Petro-SIMEquipment sizing and costing using Petro-SIM
Equipment sizing and costing using Petro-SIM
 
Besf building renewal_021815
Besf building renewal_021815Besf building renewal_021815
Besf building renewal_021815
 
Model based design-Hardware in loop-software in loop
Model based design-Hardware in loop-software in loopModel based design-Hardware in loop-software in loop
Model based design-Hardware in loop-software in loop
 
Europe User Conference: BP - implementing and supporting a multi-model, multi...
Europe User Conference: BP - implementing and supporting a multi-model, multi...Europe User Conference: BP - implementing and supporting a multi-model, multi...
Europe User Conference: BP - implementing and supporting a multi-model, multi...
 
Building Grid Resilience
Building Grid ResilienceBuilding Grid Resilience
Building Grid Resilience
 
Europe User Conference: Galp refinery wide model - a real work example
Europe User Conference: Galp refinery wide model - a real work exampleEurope User Conference: Galp refinery wide model - a real work example
Europe User Conference: Galp refinery wide model - a real work example
 
An introduction to energy management
An introduction to energy managementAn introduction to energy management
An introduction to energy management
 
Asphalt batch process with PLC & SCADA ppt
Asphalt batch process with PLC & SCADA pptAsphalt batch process with PLC & SCADA ppt
Asphalt batch process with PLC & SCADA ppt
 
Combined Heat and Power Engineering and Installation in the Pacific NW
Combined Heat and Power Engineering and Installation in the Pacific NWCombined Heat and Power Engineering and Installation in the Pacific NW
Combined Heat and Power Engineering and Installation in the Pacific NW
 
KBC unit monitoring Petro-SIM and PI-AF
KBC unit monitoring Petro-SIM and PI-AFKBC unit monitoring Petro-SIM and PI-AF
KBC unit monitoring Petro-SIM and PI-AF
 
Europe User Conference: KBC Engineering Suite v7
Europe User Conference: KBC Engineering Suite v7Europe User Conference: KBC Engineering Suite v7
Europe User Conference: KBC Engineering Suite v7
 
11 pv o&m cost modeling for solar fleets
11   pv o&m cost modeling for solar fleets11   pv o&m cost modeling for solar fleets
11 pv o&m cost modeling for solar fleets
 
Wind farm re-powering, life extension and decommissioning
Wind farm re-powering, life extension and decommissioningWind farm re-powering, life extension and decommissioning
Wind farm re-powering, life extension and decommissioning
 
AdamEshkanian_EngProjects
AdamEshkanian_EngProjectsAdamEshkanian_EngProjects
AdamEshkanian_EngProjects
 
Mechanical Engineering Seminar 2017_2
Mechanical Engineering Seminar 2017_2Mechanical Engineering Seminar 2017_2
Mechanical Engineering Seminar 2017_2
 
Mechanical Engineering Seminar 2017_1
Mechanical Engineering Seminar 2017_1Mechanical Engineering Seminar 2017_1
Mechanical Engineering Seminar 2017_1
 
Econoseek
EconoseekEconoseek
Econoseek
 
KBC roadmap
KBC roadmapKBC roadmap
KBC roadmap
 
Advisian dynamic process simulation capability june 2019
Advisian dynamic process simulation capability june 2019Advisian dynamic process simulation capability june 2019
Advisian dynamic process simulation capability june 2019
 

Viewers also liked

Human Performance improvement for the Turkish Energy Sector
Human Performance improvement for the Turkish Energy SectorHuman Performance improvement for the Turkish Energy Sector
Human Performance improvement for the Turkish Energy SectorGSE Systems, Inc.
 
Simulation Training Post Fukushima
Simulation Training Post FukushimaSimulation Training Post Fukushima
Simulation Training Post FukushimaGSE Systems, Inc.
 
Simulator Management: Ideas for Today and Tomorrow
Simulator Management: Ideas for Today and TomorrowSimulator Management: Ideas for Today and Tomorrow
Simulator Management: Ideas for Today and TomorrowGSE Systems, Inc.
 
Are Your Employees Playing Games?
Are Your Employees Playing Games?Are Your Employees Playing Games?
Are Your Employees Playing Games?GSE Systems, Inc.
 
Proposal For a Nuclear Reactor Operations Course at Purdue University
Proposal For a Nuclear Reactor Operations Course at Purdue UniversityProposal For a Nuclear Reactor Operations Course at Purdue University
Proposal For a Nuclear Reactor Operations Course at Purdue UniversityGSE Systems, Inc.
 
VIZRAD - Evolving Simulaton in Radiation Training
VIZRAD - Evolving Simulaton in Radiation TrainingVIZRAD - Evolving Simulaton in Radiation Training
VIZRAD - Evolving Simulaton in Radiation TrainingGSE Systems, Inc.
 
Solving Refining & Petrochemicals Workforce Development Challenges with Perfo...
Solving Refining & Petrochemicals Workforce Development Challenges with Perfo...Solving Refining & Petrochemicals Workforce Development Challenges with Perfo...
Solving Refining & Petrochemicals Workforce Development Challenges with Perfo...GSE Systems, Inc.
 
Designing a High-Fidelity Full-Scope Training Simulator for a Triple-Pressure...
Designing a High-Fidelity Full-Scope Training Simulator for a Triple-Pressure...Designing a High-Fidelity Full-Scope Training Simulator for a Triple-Pressure...
Designing a High-Fidelity Full-Scope Training Simulator for a Triple-Pressure...GSE Systems, Inc.
 
Total Training Solution - Entry2Expert
Total Training Solution - Entry2ExpertTotal Training Solution - Entry2Expert
Total Training Solution - Entry2ExpertGSE Systems, Inc.
 
How to Improve Operator Training Throughput Using Screening & Selection
How to Improve Operator Training Throughput Using Screening & SelectionHow to Improve Operator Training Throughput Using Screening & Selection
How to Improve Operator Training Throughput Using Screening & SelectionGSE Systems, Inc.
 
Improving Operational Performance With Smarter, Cost-Effective Training Programs
Improving Operational Performance With Smarter, Cost-Effective Training ProgramsImproving Operational Performance With Smarter, Cost-Effective Training Programs
Improving Operational Performance With Smarter, Cost-Effective Training ProgramsGSE Systems, Inc.
 
Applying Safety DNA Analytics to Enhance Your E2E Workforce Process
Applying Safety DNA Analytics to Enhance Your E2E Workforce ProcessApplying Safety DNA Analytics to Enhance Your E2E Workforce Process
Applying Safety DNA Analytics to Enhance Your E2E Workforce Process GSE Systems, Inc.
 
Innovation in Nuclear Simulation
Innovation in Nuclear SimulationInnovation in Nuclear Simulation
Innovation in Nuclear SimulationGSE Systems, Inc.
 
Implementation of Dynamic Simulation for Engineering and Human Factors
Implementation of Dynamic Simulation for Engineering and Human FactorsImplementation of Dynamic Simulation for Engineering and Human Factors
Implementation of Dynamic Simulation for Engineering and Human FactorsGSE Systems, Inc.
 
Real-Time Simulation for Design of New Nuclear Plants
Real-Time Simulation for Design of New Nuclear PlantsReal-Time Simulation for Design of New Nuclear Plants
Real-Time Simulation for Design of New Nuclear PlantsGSE Systems, Inc.
 
Investigating Ways to Prevent Electrical Arc Flash
Investigating Ways to Prevent Electrical Arc FlashInvestigating Ways to Prevent Electrical Arc Flash
Investigating Ways to Prevent Electrical Arc FlashGSE Systems, Inc.
 
Increasing ROI Through Simulation and the 'Digital Twin'
Increasing ROI Through Simulation and the 'Digital Twin'Increasing ROI Through Simulation and the 'Digital Twin'
Increasing ROI Through Simulation and the 'Digital Twin'GSE Systems, Inc.
 

Viewers also liked (19)

Human Performance improvement for the Turkish Energy Sector
Human Performance improvement for the Turkish Energy SectorHuman Performance improvement for the Turkish Energy Sector
Human Performance improvement for the Turkish Energy Sector
 
Simulation Training Post Fukushima
Simulation Training Post FukushimaSimulation Training Post Fukushima
Simulation Training Post Fukushima
 
Simulator Management: Ideas for Today and Tomorrow
Simulator Management: Ideas for Today and TomorrowSimulator Management: Ideas for Today and Tomorrow
Simulator Management: Ideas for Today and Tomorrow
 
Are Your Employees Playing Games?
Are Your Employees Playing Games?Are Your Employees Playing Games?
Are Your Employees Playing Games?
 
Proposal For a Nuclear Reactor Operations Course at Purdue University
Proposal For a Nuclear Reactor Operations Course at Purdue UniversityProposal For a Nuclear Reactor Operations Course at Purdue University
Proposal For a Nuclear Reactor Operations Course at Purdue University
 
VIZRAD - Evolving Simulaton in Radiation Training
VIZRAD - Evolving Simulaton in Radiation TrainingVIZRAD - Evolving Simulaton in Radiation Training
VIZRAD - Evolving Simulaton in Radiation Training
 
ANS-3.5 Overview
ANS-3.5 OverviewANS-3.5 Overview
ANS-3.5 Overview
 
Solving Refining & Petrochemicals Workforce Development Challenges with Perfo...
Solving Refining & Petrochemicals Workforce Development Challenges with Perfo...Solving Refining & Petrochemicals Workforce Development Challenges with Perfo...
Solving Refining & Petrochemicals Workforce Development Challenges with Perfo...
 
Designing a High-Fidelity Full-Scope Training Simulator for a Triple-Pressure...
Designing a High-Fidelity Full-Scope Training Simulator for a Triple-Pressure...Designing a High-Fidelity Full-Scope Training Simulator for a Triple-Pressure...
Designing a High-Fidelity Full-Scope Training Simulator for a Triple-Pressure...
 
Total Training Solution - Entry2Expert
Total Training Solution - Entry2ExpertTotal Training Solution - Entry2Expert
Total Training Solution - Entry2Expert
 
How to Improve Operator Training Throughput Using Screening & Selection
How to Improve Operator Training Throughput Using Screening & SelectionHow to Improve Operator Training Throughput Using Screening & Selection
How to Improve Operator Training Throughput Using Screening & Selection
 
Improving Operational Performance With Smarter, Cost-Effective Training Programs
Improving Operational Performance With Smarter, Cost-Effective Training ProgramsImproving Operational Performance With Smarter, Cost-Effective Training Programs
Improving Operational Performance With Smarter, Cost-Effective Training Programs
 
Applying Safety DNA Analytics to Enhance Your E2E Workforce Process
Applying Safety DNA Analytics to Enhance Your E2E Workforce ProcessApplying Safety DNA Analytics to Enhance Your E2E Workforce Process
Applying Safety DNA Analytics to Enhance Your E2E Workforce Process
 
Innovation in Nuclear Simulation
Innovation in Nuclear SimulationInnovation in Nuclear Simulation
Innovation in Nuclear Simulation
 
Implementation of Dynamic Simulation for Engineering and Human Factors
Implementation of Dynamic Simulation for Engineering and Human FactorsImplementation of Dynamic Simulation for Engineering and Human Factors
Implementation of Dynamic Simulation for Engineering and Human Factors
 
Process Modeling Simulation
Process Modeling SimulationProcess Modeling Simulation
Process Modeling Simulation
 
Real-Time Simulation for Design of New Nuclear Plants
Real-Time Simulation for Design of New Nuclear PlantsReal-Time Simulation for Design of New Nuclear Plants
Real-Time Simulation for Design of New Nuclear Plants
 
Investigating Ways to Prevent Electrical Arc Flash
Investigating Ways to Prevent Electrical Arc FlashInvestigating Ways to Prevent Electrical Arc Flash
Investigating Ways to Prevent Electrical Arc Flash
 
Increasing ROI Through Simulation and the 'Digital Twin'
Increasing ROI Through Simulation and the 'Digital Twin'Increasing ROI Through Simulation and the 'Digital Twin'
Increasing ROI Through Simulation and the 'Digital Twin'
 

Similar to Virtual Commissioning and Real-Time Training for Increasing Performance

Revamps for Modern Hydrogen Plants
Revamps for Modern Hydrogen PlantsRevamps for Modern Hydrogen Plants
Revamps for Modern Hydrogen PlantsGerard B. Hawkins
 
Case study -4 Mort Street
Case study -4 Mort StreetCase study -4 Mort Street
Case study -4 Mort StreetShamitha Reddy
 
High-Fidelity Operator Training Simulator for CCGT Implemented Before Plant C...
High-Fidelity Operator Training Simulator for CCGT Implemented Before Plant C...High-Fidelity Operator Training Simulator for CCGT Implemented Before Plant C...
High-Fidelity Operator Training Simulator for CCGT Implemented Before Plant C...GSE Systems, Inc.
 
Retrocommissioning of Existing Buildings
Retrocommissioning of Existing BuildingsRetrocommissioning of Existing Buildings
Retrocommissioning of Existing BuildingsWIGreenBuilding
 
Czero Engineering - Feb 2017
Czero Engineering  - Feb 2017Czero Engineering  - Feb 2017
Czero Engineering - Feb 2017Czero
 
EFEU / FLEXe Nurmoranta Maria advanced control as a key to flexibility capab...
EFEU / FLEXe Nurmoranta  Maria advanced control as a key to flexibility capab...EFEU / FLEXe Nurmoranta  Maria advanced control as a key to flexibility capab...
EFEU / FLEXe Nurmoranta Maria advanced control as a key to flexibility capab...CLIC Innovation Ltd
 
Gas Combustion Turbine System
Gas Combustion Turbine SystemGas Combustion Turbine System
Gas Combustion Turbine SystemPeter Bright
 
Improved power plant performance, Sulzer Technical Review, 2009
Improved power plant performance, Sulzer Technical Review, 2009Improved power plant performance, Sulzer Technical Review, 2009
Improved power plant performance, Sulzer Technical Review, 2009Shaun West
 
Kalpak Mechanical Engineering Project Portfolio
Kalpak Mechanical Engineering Project PortfolioKalpak Mechanical Engineering Project Portfolio
Kalpak Mechanical Engineering Project PortfolioKalpak Dhake
 
Thermal Power Library - Overview
Thermal Power Library - OverviewThermal Power Library - Overview
Thermal Power Library - OverviewModelon
 
353685130-CCGT-Combined-Cycle-Gas-Turbine.ppt
353685130-CCGT-Combined-Cycle-Gas-Turbine.ppt353685130-CCGT-Combined-Cycle-Gas-Turbine.ppt
353685130-CCGT-Combined-Cycle-Gas-Turbine.pptJiji118054
 
Chapter 5b -_cracking_ffcu
Chapter 5b -_cracking_ffcuChapter 5b -_cracking_ffcu
Chapter 5b -_cracking_ffcuHelena Francis
 
Energy Trust New Buildings: Technical Updates for Modelers and Engineers
Energy Trust New Buildings: Technical Updates for Modelers and EngineersEnergy Trust New Buildings: Technical Updates for Modelers and Engineers
Energy Trust New Buildings: Technical Updates for Modelers and Engineersenergytrustor
 
Revamps for Ageing Hydrogen Plants
Revamps for Ageing Hydrogen PlantsRevamps for Ageing Hydrogen Plants
Revamps for Ageing Hydrogen PlantsGerard B. Hawkins
 
Ashrae 90.1 2004 appendix g - performance rating method
Ashrae 90.1   2004 appendix g - performance rating methodAshrae 90.1   2004 appendix g - performance rating method
Ashrae 90.1 2004 appendix g - performance rating methodEduardo Miranda Cáceres
 

Similar to Virtual Commissioning and Real-Time Training for Increasing Performance (20)

Appsolu
AppsoluAppsolu
Appsolu
 
Revamps for Modern Hydrogen Plants
Revamps for Modern Hydrogen PlantsRevamps for Modern Hydrogen Plants
Revamps for Modern Hydrogen Plants
 
Condensing Boiler Optimization
Condensing Boiler OptimizationCondensing Boiler Optimization
Condensing Boiler Optimization
 
Condensing Boiler Optimization
Condensing Boiler OptimizationCondensing Boiler Optimization
Condensing Boiler Optimization
 
Case study -4 Mort Street
Case study -4 Mort StreetCase study -4 Mort Street
Case study -4 Mort Street
 
Epa of cogen
Epa of cogenEpa of cogen
Epa of cogen
 
High-Fidelity Operator Training Simulator for CCGT Implemented Before Plant C...
High-Fidelity Operator Training Simulator for CCGT Implemented Before Plant C...High-Fidelity Operator Training Simulator for CCGT Implemented Before Plant C...
High-Fidelity Operator Training Simulator for CCGT Implemented Before Plant C...
 
Retrocommissioning of Existing Buildings
Retrocommissioning of Existing BuildingsRetrocommissioning of Existing Buildings
Retrocommissioning of Existing Buildings
 
Czero Engineering - Feb 2017
Czero Engineering  - Feb 2017Czero Engineering  - Feb 2017
Czero Engineering - Feb 2017
 
EFEU / FLEXe Nurmoranta Maria advanced control as a key to flexibility capab...
EFEU / FLEXe Nurmoranta  Maria advanced control as a key to flexibility capab...EFEU / FLEXe Nurmoranta  Maria advanced control as a key to flexibility capab...
EFEU / FLEXe Nurmoranta Maria advanced control as a key to flexibility capab...
 
Gas Combustion Turbine System
Gas Combustion Turbine SystemGas Combustion Turbine System
Gas Combustion Turbine System
 
Improved power plant performance, Sulzer Technical Review, 2009
Improved power plant performance, Sulzer Technical Review, 2009Improved power plant performance, Sulzer Technical Review, 2009
Improved power plant performance, Sulzer Technical Review, 2009
 
Kalpak Mechanical Engineering Project Portfolio
Kalpak Mechanical Engineering Project PortfolioKalpak Mechanical Engineering Project Portfolio
Kalpak Mechanical Engineering Project Portfolio
 
Thermal Power Library - Overview
Thermal Power Library - OverviewThermal Power Library - Overview
Thermal Power Library - Overview
 
353685130-CCGT-Combined-Cycle-Gas-Turbine.ppt
353685130-CCGT-Combined-Cycle-Gas-Turbine.ppt353685130-CCGT-Combined-Cycle-Gas-Turbine.ppt
353685130-CCGT-Combined-Cycle-Gas-Turbine.ppt
 
Chapter 5b -_cracking_ffcu
Chapter 5b -_cracking_ffcuChapter 5b -_cracking_ffcu
Chapter 5b -_cracking_ffcu
 
Condensing Boiler Optimization
Condensing Boiler OptimizationCondensing Boiler Optimization
Condensing Boiler Optimization
 
Energy Trust New Buildings: Technical Updates for Modelers and Engineers
Energy Trust New Buildings: Technical Updates for Modelers and EngineersEnergy Trust New Buildings: Technical Updates for Modelers and Engineers
Energy Trust New Buildings: Technical Updates for Modelers and Engineers
 
Revamps for Ageing Hydrogen Plants
Revamps for Ageing Hydrogen PlantsRevamps for Ageing Hydrogen Plants
Revamps for Ageing Hydrogen Plants
 
Ashrae 90.1 2004 appendix g - performance rating method
Ashrae 90.1   2004 appendix g - performance rating methodAshrae 90.1   2004 appendix g - performance rating method
Ashrae 90.1 2004 appendix g - performance rating method
 

More from GSE Systems, Inc.

Hyperspring Implementation of BWROG EP/SAG CONTE 2019
Hyperspring Implementation of BWROG EP/SAG CONTE 2019Hyperspring Implementation of BWROG EP/SAG CONTE 2019
Hyperspring Implementation of BWROG EP/SAG CONTE 2019GSE Systems, Inc.
 
GSE Second Simulator Address Plant Training Needs CONTE 2019
GSE Second Simulator Address Plant Training Needs CONTE 2019GSE Second Simulator Address Plant Training Needs CONTE 2019
GSE Second Simulator Address Plant Training Needs CONTE 2019GSE Systems, Inc.
 
GSE Gaining Value From Virtual Control Panels CONTE 2019
GSE Gaining Value From Virtual Control Panels CONTE 2019GSE Gaining Value From Virtual Control Panels CONTE 2019
GSE Gaining Value From Virtual Control Panels CONTE 2019GSE Systems, Inc.
 
Onyx relap5 Presentation from SCS 2019
Onyx relap5 Presentation from SCS 2019Onyx relap5 Presentation from SCS 2019
Onyx relap5 Presentation from SCS 2019GSE Systems, Inc.
 
GSE Performance Improvement Solutions
GSE Performance Improvement SolutionsGSE Performance Improvement Solutions
GSE Performance Improvement SolutionsGSE Systems, Inc.
 
PSA-HD Simulator for Severe Accidents
PSA-HD Simulator for Severe AccidentsPSA-HD Simulator for Severe Accidents
PSA-HD Simulator for Severe AccidentsGSE Systems, Inc.
 
Potential Model Changes as a Result of Fukushima
Potential Model Changes as a Result of FukushimaPotential Model Changes as a Result of Fukushima
Potential Model Changes as a Result of FukushimaGSE Systems, Inc.
 
Dynamic Simulation for HFE & Control System Design Validation
Dynamic Simulation for HFE & Control System Design ValidationDynamic Simulation for HFE & Control System Design Validation
Dynamic Simulation for HFE & Control System Design ValidationGSE Systems, Inc.
 
Fossil Power Simulator Efficiencies When Using Automated Testing
Fossil Power Simulator Efficiencies When Using Automated TestingFossil Power Simulator Efficiencies When Using Automated Testing
Fossil Power Simulator Efficiencies When Using Automated TestingGSE Systems, Inc.
 
E-learning, 3D and Simulation for Competency Development
E-learning, 3D and Simulation for Competency DevelopmentE-learning, 3D and Simulation for Competency Development
E-learning, 3D and Simulation for Competency DevelopmentGSE Systems, Inc.
 

More from GSE Systems, Inc. (10)

Hyperspring Implementation of BWROG EP/SAG CONTE 2019
Hyperspring Implementation of BWROG EP/SAG CONTE 2019Hyperspring Implementation of BWROG EP/SAG CONTE 2019
Hyperspring Implementation of BWROG EP/SAG CONTE 2019
 
GSE Second Simulator Address Plant Training Needs CONTE 2019
GSE Second Simulator Address Plant Training Needs CONTE 2019GSE Second Simulator Address Plant Training Needs CONTE 2019
GSE Second Simulator Address Plant Training Needs CONTE 2019
 
GSE Gaining Value From Virtual Control Panels CONTE 2019
GSE Gaining Value From Virtual Control Panels CONTE 2019GSE Gaining Value From Virtual Control Panels CONTE 2019
GSE Gaining Value From Virtual Control Panels CONTE 2019
 
Onyx relap5 Presentation from SCS 2019
Onyx relap5 Presentation from SCS 2019Onyx relap5 Presentation from SCS 2019
Onyx relap5 Presentation from SCS 2019
 
GSE Performance Improvement Solutions
GSE Performance Improvement SolutionsGSE Performance Improvement Solutions
GSE Performance Improvement Solutions
 
PSA-HD Simulator for Severe Accidents
PSA-HD Simulator for Severe AccidentsPSA-HD Simulator for Severe Accidents
PSA-HD Simulator for Severe Accidents
 
Potential Model Changes as a Result of Fukushima
Potential Model Changes as a Result of FukushimaPotential Model Changes as a Result of Fukushima
Potential Model Changes as a Result of Fukushima
 
Dynamic Simulation for HFE & Control System Design Validation
Dynamic Simulation for HFE & Control System Design ValidationDynamic Simulation for HFE & Control System Design Validation
Dynamic Simulation for HFE & Control System Design Validation
 
Fossil Power Simulator Efficiencies When Using Automated Testing
Fossil Power Simulator Efficiencies When Using Automated TestingFossil Power Simulator Efficiencies When Using Automated Testing
Fossil Power Simulator Efficiencies When Using Automated Testing
 
E-learning, 3D and Simulation for Competency Development
E-learning, 3D and Simulation for Competency DevelopmentE-learning, 3D and Simulation for Competency Development
E-learning, 3D and Simulation for Competency Development
 

Recently uploaded

(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacingjaychoudhary37
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 

Recently uploaded (20)

(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacing
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 

Virtual Commissioning and Real-Time Training for Increasing Performance

  • 1. Virtual Commissioning + Real-Time Training = Increased Performance & Profits info@gses.com
  • 2. 2 Overview • Gas conversion of existing coal power plant • Project execution strategy for existing virtual simulator • Benefits of having a simulator before plant gas startup commissioning
  • 3. 3 Overview of Gas Conversion • Increasingly stringent and uncertain regulatory environment • Plus, falling natural gas prices • These conditions have made converting existing coal-fired steam- generating boilers to natural gas firing more and more attractive. • Based on recent gas conversion announcements, existing coal units generating a total of approximately 9,000 MW will be converted for natural gas firing. Source : Power Engineering Magazine (www.power-eng.com) – “Coal to Natural Gas Conversion – Drivers and Lessons”
  • 4. 4 Overview of Gas Conversion The major drivers of this trend have been: – Mercury and Air Toxics Standards (MATS) regulations – New Source Review (NSR) settlements – Natural Gas availability and pricing – The uniqueness of each project to deliver electricity at the required capacity to make it economically feasible to convert existing coal-fired units to natural gas-firing capability. Source : Power Engineering Magazine (www.power-eng.com) – “Coal to Natural Gas Conversion – Drivers and Lessons”
  • 5. 5 Simulator Considerations • Using natural gas changes the heat absorption characteristics in the boiler and convection pass. There are modifications that have to be made to meet the designed steam temperatures and full boiler output. • In addition, considerations have to be given to achieve low emission goals. These modifications include: – Gas Supply: Modifications to the gas supply and vent piping, installation of pressure- reducing valve station. – Boiler: Modifications to the radiation and/or convective area to help achieve original steam temperatures, new burners and igniters, windbox modifications – Flue Gas Recirculation (FGR): FGR to control NOX and steam temperatures by recycling a portion of the flue gas from the economizer outlet back into the windbox – Flue Gas System: Modifications to the Air & Gas System. Forced-draft/induced-draft fan modifications and other control functions to maintain furnace pressure.
  • 6. 6 • From GSE: Two team members including an engineering manager • From DCS: One project engineer • From plant: Energy production supervisor and two shift supervisors Resource Team
  • 7. 7 Overview of Project Execution Strategy • Schedule • DCS virtual configuration • Project staging • Discrepancy recording system
  • 8. 8 Schedule Simulator Model Design Process 1. Conference call kickoff meeting 2. Model scope design review meeting 3. Model changes 4. FAT’ed DCS shipped to GSE 5. Integration & testing at GSE
  • 9. 9 Simulator Air & Gas Drawing
  • 12. 12 DCS Virtual Configuration • DCS was already converted to the DCS vendor’s virtual controllers • FAT’ed DCS shipped to GSE • 3 Dual monitor operator stations
  • 14. 14 Project Staging Staged at GSE facility 1. Access to model engineer(s) 2. Plant operators 3. After initial integration, remote access provided to DCS vendor for support
  • 15. 15 Discrepancy Recording System GSE Mantis DR System • An online system where users can be easily added • Different sections available for different types of discrepancies • Severity of discrepancy can be assigned • Discrepancy can be assigned to people, commented on, and edited
  • 16. 16 Overall Benefits Total DCS issues identified: 63 • Potentially costly items • Drum level reference changed • Boiler feed pump controls • Trips were not connected • Control schemes were changed
  • 17. 17 Overall Benefits Continued • Plant trip conditions can be tested that require either third party controls or DCS control logic modifications. • Startup/shutdown procedures can be adjusted ahead of time based on interaction with the simulator during integration.
  • 18. 18 • Real-time training during the integration and FAT Phases • Required graphics & logic tuning and modifications can be sent to the plant for more efficient commissioning of the new gas controls. Conclusion
  • 19. Thank you. For more information, go to: www.GSES.com info@gses.com Or call 800-638-7912