There are many opportunities to reduce energy consumption in existing commercial buildings. With some minor adjustments and changes it’s often possible to reduce energy bills by up to 15%. Further reductions can be made through capital improvements involving upgrading walls, windows, roof, HVAC equipment, lighting and domestic hot water systems. This presentation will review the process of evaluating the potential of energy saving opportunities and look at how they are typically implemented in buildings. Case studies of example projects will be presented. We will also highlight grants and incentives that are available to help offset the costs of these upgrades. And we will provide an overview on how retro-commissioning ties into LEED-EB and an explanation of the related pre-requisites and credits.
2. 2Presenters
Manus McDevitt, PE, LEED AP Principal
Sustainable Engineering Group,
Madison, WI
Alex Harris,
Engineer
Sustainable Engineering Group,
Madison, WI
3. 3
•Understand the motivation and methods for accomplishing Retrocommissioning (R-Cx)
•Appreciate the value of Retrocommissioning by considering several case studies
•Recognize some typical issues uncovered by Retrocommissioning
Learning Objectives
4. 4
What is Retro-Cx?
The process of optimizing the performance of an existing building
9. 9
1. Gather Information
From Stakeholders
From Documentation
From Observation
10. 10
Deliverables
• Operational Intent
– Narratives of facility functional use
– Verifiable performance criteria
– Stakeholder requirements for
• usability, operability, maintainability, functionality
• Basis of Operation
– Documents current building operation
• Installed equipment database
• Control sequences
11. 11
10,000SF Office Building Energy Use
Mid-West US (Chicago)
Space Heating,
32%
Space Cooling,
8%
Ventilation , 5%
Water Heating ,
10%
Lighting , 26%
Other, 19%
Building Energy Usage
13. 13
2. Identify Improvements
•Can the system meet your requirements?
–If so, tune the system to meet your needs
•Examples: Calibrate sensors, adjust control sequences, repair or replace equipment
–If not, re-design the system as required
•Costs and savings for each improvement
–Prioritize
14. 14
Deliverable
• Facility Optimization Study
– Narrative and technical evaluation of each improvement opportunity
– Estimate of project costs
– Analysis of utility savings and other benefits
– Includes:
• Discussion of documentation improvements
• Discussion of training needs
15. 15Audit / Investigation Phase
•Collaborate with facilities team to identify opportunities
•Review building drawings and documentation
•Performance testing of building systems
•Develop list of recommended improvements
16. 16Potential Measures
•Operational
–Equipment schedules, set points,
•Maintenance
–Valve and damper control issues
•Design
–Identify space function changes, control optimization
17. 17
Common Problems Identified
•Time clocks disabled
•Control sequences not optimized
•Energy Management Systems not understood or fully utilized
•Controls/sensors/actuators out of calibration
•Ventilation excessive
•Documentation & training inadequate
24. 24
Cooling Tower Exhaust Dampers & Ductwork
Supports have rusted out and fell into tower
Dampers linkages are corroded and not functional
25. 25
Disconnected Actuator
Disconnected actuator is causing cooling tower to run at the same time as boiler. We are heating the water, only to reject the heat to the outdoors
26. 26
Cracked Heat Exchanger
There is risk of carbon monoxide being blown into the occupied space. Unit was shutdown and gas line shut-off to unit.
27. 27
Duct to Nowhere
Supply duct is blowing into plenum space. This area was remodeled and drop ceiling added, but the duct was never capped, as shown on remodel plans.
28. 28
Poor Sensor Location
Heat pump serving this space is always in cooling, even though the room temperature is 65°F.
30. 30
3. Monitor Implementation
RCxprovider’s role varies depending on
1.Needs of the client
2.Number and complexity of improvements
3.Type of improvements
36. 36
6. Final Report
• Based on the Facility Optimization Study
– Includes discussion of implemented projects and testing
– Reference document for future projects and operations
37. 37
Persistence Phase: Verify Persistence of Savings (Optional)
Implementation Phase: ImplementSelected Measures & Verify Actual Savings
Audit Phase: Complete Audit &
Quantify Measures
Qualify Customer & Submit ApplicationFocus on Energy RCx Process
38. 38
Medical Clinic
•Established in 1996
•22 Clinics
•2 million+ outpatient visits
•1 South Park Street
•174,000 ft2
•6 OR’s
•2 MRI’s
•392 kBtu/ft2-yr (source)
Medical Clinic, Madison, WI
39. 39
Medical Clinic
Proposed Phase Workbook
Description
Electric
Energy
Savings
(kW-hr)
Electric
Demand
Savings
(kW)
Natural
Gas
Savings
(Therms)
Measure
Installatio
n
Incentive
($)
Energy
Cost
Savings
($)
Measure
Cost ($)
Simple
Payback
(Years)
M1
On all air handlers, increase economizer
switchover from 51.5°F to 68°F 101,130 - - N/A $7,079 $100 0.0
M2
Modify air handler schedules 123,599 - 5,727 N/A $10,617 $100 0.0
M3 Replace RTU-2 Control Board 44,800 - 5,880 N/A $6,570 $500 0.1
M4
Replace 52W Incadescent Bulbs with
CFL's 6,841 1.8 -134 N/A $231 $200 0.9
M5
Install lighting occupancy sensors on
Floors 5, 6, 7 and lower level 19,314 - -358 N/A $1,098 $9,100 8.3
Proposed Phase Savings
49. 49
Retro-CxEffort at Area School
•Built in 1960’s
•Several additions in 1980’s and 1990’s
•Total area of 250,000 ft2
•30 Air Handling Units
•Mix of Constant Volume
and VAV
•7 Boilers and 2 Chillers
Main concern is
energy consumption
50. 50
Retro-CxEffort at Area School
•A heating system controller was installed to allow for proper sequencing of all boiler units.
•The hot water system has been modified to allow for variable flow operation.
•Schedules have been modified to reflect space occupancy patterns for each air-handling unit zone.
•Economizer modes have been modified to improve comfort and energy efficiency
51. 51
Retro-CxEffort at Area School
•Existing chillers are being replaced with more efficient, variable flow and smaller capacity models.
•Computer labs and the IT room have been removed from main chilled water system and are now cooled by independent cooling units, which results in a shorter seasonal operating window for the chillers and improves comfort in winter.
New
Old
52. 52
Airflow checking and rebalancing results in enhanced occupant comfort and potentially lower operating costs
Retro-CxEffort at Area School
•Staff have reported problems with “stuffiness” in several spaces
•Perimeter areas of Office and Guidance spaces too cold in winter
53. 53
53
Savings of about $30-50,000 / year in gas
Retro-Cx Effort at Area School
Normalized Gas Use Comparison
0
5000
10000
15000
20000
25000
30000
35000
October November December January February March
Gas Use (Therms) )
2005
2006
54. 54
54
Savings of about $10-20,000 / yr in electricity
Retro-Cx Effort at Area School
Electric Use Comparison
0
50000
100000
150000
200000
250000
October November December January February March
Electric Use (kWh) )
2005
2006
55. 55
Retro-CxEffort at Area School
OLD
NEW
Electric Use (kWh)
11,000
1,900
Electric Demand (kW)
18
3
•Existing roof-mounted chilled water pipe insulation is badly deteriorated
•It is being replaced with thicker aluminum shielded, weather- resistant insulation
Savings of about $500 / yr
Savings due to improved insulation
56. 56
Retro-CxEffort at Area School
Annual estimated savings:
$40,000 to $70,000
Estimated cost to realize savings:
~$35,000
Payback period:6-10 months
Bonus: Improved comfort and operation!
60. 60Continuous Commissioning Tools
•BAS Integrated Continuous Commissioning Tools
–“Building Analytics”
–“Building Management Performance Analytic Tools”
•Provide following capabilities
–Equipment and system fault detection and diagnostics
–Ongoing commissioning including optimization of building control
–Demand response
–Performance benchmarking
•Typically Cloud Based
–Monthly subscription fee