Project Aims and Objectives:
To construct a new 2000 metre square office / workshop
and a new 300 metre square paint shed, for a commercial
mine vehicle hire company.
Project Management Services:
∗ Pproducing and adhering to an accelerated programme
∗ Collating and adjudication of Contractor quotes
∗ Producing Contractor Contracts
∗ Agreeing budgets for all work packages
∗ Determining the financial forecast
∗ Man hours / accommodation schedules / rotas
∗ Fly in / Fly out site visits
∗ Producing and updating H&S Plan
∗ Producing Planning Submission for the Paint Shed
∗ Dealing with Building Regulations 2012 (CDC, CCC, OP)
∗ Electricity connection application
∗ Logistics
∗ Overseeing design & Codes compliance
∗ Stakeholder Reporting
Accomplishments:
Constructing the biggest Commercial premises in Port
Hedland on an accelerated programme. Also changing the
company H&S culture to more acceptable standards.
Site Overview
Tilt Panel Construction Workshop InternalsFire water Tanks & Pump
Project Management Case Study
New Build Cyclone Rate Commercial Property,
Port Hedland, Western Australia.
New Build Workshop / Offices
New Build Laboratory
Various Projects:
As part of the Sino Iron Ore Mine Site (http://www.citicpacificmining.com/our-
operation/sino-iron-project/) various construction projects were required to achieve
mining operations. Projects included:
1. New build (2000 square metre) cyclone rated workshop and office building
2. New build (1000 square metre) cyclone rated laboratory building
3. New build (200 linear metre) cyclone rated warehouse canopy & concrete walkway
4. New build cyclone rated cool rooms
5. New build cyclone rated electrical transformer compounds
Project Management Services
• Defining the Scope of Works and producing detail Scope of Works Documents
• Producing and adhering to programmes
• Adjudication of Contractor quotes and Contractor Contract Management
• Financial Management. Setting budgets and controlling actual spend
• Fly in Fly out to undertake site visits and apply for Permits to Work
• Overseeing the production of H&S Management Plans / CRAWS
• Approved Mine Site Permit Holder
• Logistics Management
• Stakeholder Reporting (Inc. Chinese Clients)
• Manager of in-house diverse team (Inc. Maori’s, Filipino's)
Accomplishments:
Maintaining timely transport deliveries from Perth to the Sino Mine Site, in order to
keep to programmes.
Project Management Case Study
New Build Commercial Projects,
Sino Mine Site,
Cape Preston, Western Australia.

More Related Content

What's hot

ACCESS - Summarized Company profile - 2013
ACCESS - Summarized Company profile - 2013ACCESS - Summarized Company profile - 2013
ACCESS - Summarized Company profile - 2013Herman Smit
 
Power Point Presentation for (Advance Project Management)
Power Point Presentation for (Advance Project Management)Power Point Presentation for (Advance Project Management)
Power Point Presentation for (Advance Project Management)Obi-Ugbo Alex
 
Mr Michael Toye CV 1 (2)
Mr Michael Toye CV 1 (2)Mr Michael Toye CV 1 (2)
Mr Michael Toye CV 1 (2)Mike Toye
 
Project - Roy Hill Bulk Earthworks and Concrete Package
Project - Roy Hill Bulk Earthworks and Concrete PackageProject - Roy Hill Bulk Earthworks and Concrete Package
Project - Roy Hill Bulk Earthworks and Concrete PackageDamian Brandon
 
Valhall Working Environment Case Study
Valhall Working Environment Case StudyValhall Working Environment Case Study
Valhall Working Environment Case StudyMartin Robb CPE
 
RefCard_Altamira CitecDot_11-2016_EN
RefCard_Altamira CitecDot_11-2016_ENRefCard_Altamira CitecDot_11-2016_EN
RefCard_Altamira CitecDot_11-2016_ENRémy Jeandemange
 
F. King CV- Jan 2015
F. King CV- Jan 2015F. King CV- Jan 2015
F. King CV- Jan 2015Frank King
 
QA-QC MANAGER , CONSTRUCTION MANAGER .2016
QA-QC MANAGER , CONSTRUCTION MANAGER .2016QA-QC MANAGER , CONSTRUCTION MANAGER .2016
QA-QC MANAGER , CONSTRUCTION MANAGER .2016NOEL TUAZON
 
2015_01_17 EKO2 Workshop Presentation 13th January 2015 Rev.07b
2015_01_17 EKO2 Workshop Presentation 13th January 2015 Rev.07b2015_01_17 EKO2 Workshop Presentation 13th January 2015 Rev.07b
2015_01_17 EKO2 Workshop Presentation 13th January 2015 Rev.07byasser abouzeid,MD,CCE
 
BK case study FSC
BK case study FSCBK case study FSC
BK case study FSCSam Spencer
 
master cv january 2016 pdf 2
master cv january 2016 pdf 2master cv january 2016 pdf 2
master cv january 2016 pdf 2Gareth Hockaday
 
Introducing Process Group
Introducing Process GroupIntroducing Process Group
Introducing Process Groupprocess group
 
Resume_updated 2014
Resume_updated 2014Resume_updated 2014
Resume_updated 2014J.D. Squire
 
Project mgmt set up of cement plant
Project mgmt set up of cement plantProject mgmt set up of cement plant
Project mgmt set up of cement plantNihar Routray
 
introduction brochure
introduction brochureintroduction brochure
introduction brochureRonald Roest
 

What's hot (20)

ACCESS - Summarized Company profile - 2013
ACCESS - Summarized Company profile - 2013ACCESS - Summarized Company profile - 2013
ACCESS - Summarized Company profile - 2013
 
Power Point Presentation for (Advance Project Management)
Power Point Presentation for (Advance Project Management)Power Point Presentation for (Advance Project Management)
Power Point Presentation for (Advance Project Management)
 
Mr Michael Toye CV 1 (2)
Mr Michael Toye CV 1 (2)Mr Michael Toye CV 1 (2)
Mr Michael Toye CV 1 (2)
 
Project - Roy Hill Bulk Earthworks and Concrete Package
Project - Roy Hill Bulk Earthworks and Concrete PackageProject - Roy Hill Bulk Earthworks and Concrete Package
Project - Roy Hill Bulk Earthworks and Concrete Package
 
Valhall Working Environment Case Study
Valhall Working Environment Case StudyValhall Working Environment Case Study
Valhall Working Environment Case Study
 
RefCard_Altamira CitecDot_11-2016_EN
RefCard_Altamira CitecDot_11-2016_ENRefCard_Altamira CitecDot_11-2016_EN
RefCard_Altamira CitecDot_11-2016_EN
 
F. King CV- Jan 2015
F. King CV- Jan 2015F. King CV- Jan 2015
F. King CV- Jan 2015
 
Mike resume 2015
Mike resume 2015Mike resume 2015
Mike resume 2015
 
QA-QC MANAGER , CONSTRUCTION MANAGER .2016
QA-QC MANAGER , CONSTRUCTION MANAGER .2016QA-QC MANAGER , CONSTRUCTION MANAGER .2016
QA-QC MANAGER , CONSTRUCTION MANAGER .2016
 
CNJ Career Path
CNJ Career PathCNJ Career Path
CNJ Career Path
 
2015_01_17 EKO2 Workshop Presentation 13th January 2015 Rev.07b
2015_01_17 EKO2 Workshop Presentation 13th January 2015 Rev.07b2015_01_17 EKO2 Workshop Presentation 13th January 2015 Rev.07b
2015_01_17 EKO2 Workshop Presentation 13th January 2015 Rev.07b
 
BK case study FSC
BK case study FSCBK case study FSC
BK case study FSC
 
master cv january 2016 pdf 2
master cv january 2016 pdf 2master cv january 2016 pdf 2
master cv january 2016 pdf 2
 
Introducing Process Group
Introducing Process GroupIntroducing Process Group
Introducing Process Group
 
RS_HFZ_V2
RS_HFZ_V2RS_HFZ_V2
RS_HFZ_V2
 
Resume_updated 2014
Resume_updated 2014Resume_updated 2014
Resume_updated 2014
 
rgb up to date cv
rgb up to date cvrgb up to date cv
rgb up to date cv
 
Project mgmt set up of cement plant
Project mgmt set up of cement plantProject mgmt set up of cement plant
Project mgmt set up of cement plant
 
introduction brochure
introduction brochureintroduction brochure
introduction brochure
 
Robert
RobertRobert
Robert
 

Similar to Perth metro

Johnson Controls case studies - Commercial Project Management
Johnson Controls case studies - Commercial Project ManagementJohnson Controls case studies - Commercial Project Management
Johnson Controls case studies - Commercial Project Managementgrahamelanders
 
Johnson controls case study consultancy
Johnson controls case study   consultancyJohnson controls case study   consultancy
Johnson controls case study consultancygrahamelanders
 
CBRE Office Fit Out Track Record Reduced
CBRE Office Fit Out Track Record ReducedCBRE Office Fit Out Track Record Reduced
CBRE Office Fit Out Track Record ReducedNora Vera Jarauta
 
Cv jason dixon dated 20160124
Cv jason dixon dated 20160124Cv jason dixon dated 20160124
Cv jason dixon dated 20160124Jason Dixon
 
Pic booklet screen view 2
Pic booklet   screen view 2Pic booklet   screen view 2
Pic booklet screen view 2Amin Hadjaran
 
RESUME - NAJMUL SAQIB MANIAR
RESUME - NAJMUL SAQIB MANIARRESUME - NAJMUL SAQIB MANIAR
RESUME - NAJMUL SAQIB MANIARSAQIB MANIAR
 
Slides Transcription.docx
Slides Transcription.docxSlides Transcription.docx
Slides Transcription.docxbrian157854
 
RRozek Project List 9 20 15
RRozek Project List 9 20 15RRozek Project List 9 20 15
RRozek Project List 9 20 15Roman Rozek
 
Electrical Engineer Resume
Electrical Engineer ResumeElectrical Engineer Resume
Electrical Engineer ResumeAbdul Rahiman
 
New Brochure 1 Clm
New Brochure 1   ClmNew Brochure 1   Clm
New Brochure 1 Clmconradmaung
 
Ganesh Golande-CV-Senior Contracts Administrator
Ganesh Golande-CV-Senior Contracts AdministratorGanesh Golande-CV-Senior Contracts Administrator
Ganesh Golande-CV-Senior Contracts AdministratorGanesh Golande
 
Tim Read CV January 2016
Tim Read CV January 2016Tim Read CV January 2016
Tim Read CV January 2016Tim Read
 
Tim Read CV January 2016
Tim Read CV January 2016Tim Read CV January 2016
Tim Read CV January 2016Tim Read
 

Similar to Perth metro (20)

Upload
UploadUpload
Upload
 
Johnson Controls case studies - Commercial Project Management
Johnson Controls case studies - Commercial Project ManagementJohnson Controls case studies - Commercial Project Management
Johnson Controls case studies - Commercial Project Management
 
Work Experience
Work ExperienceWork Experience
Work Experience
 
Johnson controls case study consultancy
Johnson controls case study   consultancyJohnson controls case study   consultancy
Johnson controls case study consultancy
 
CBRE Office Fit Out Track Record Reduced
CBRE Office Fit Out Track Record ReducedCBRE Office Fit Out Track Record Reduced
CBRE Office Fit Out Track Record Reduced
 
Emad Hamdy Resume
Emad Hamdy ResumeEmad Hamdy Resume
Emad Hamdy Resume
 
Cv jason dixon dated 20160124
Cv jason dixon dated 20160124Cv jason dixon dated 20160124
Cv jason dixon dated 20160124
 
Pic booklet screen view 2
Pic booklet   screen view 2Pic booklet   screen view 2
Pic booklet screen view 2
 
Appendices
AppendicesAppendices
Appendices
 
RESUME - NAJMUL SAQIB MANIAR
RESUME - NAJMUL SAQIB MANIARRESUME - NAJMUL SAQIB MANIAR
RESUME - NAJMUL SAQIB MANIAR
 
Aac booklet
Aac bookletAac booklet
Aac booklet
 
Slides Transcription.docx
Slides Transcription.docxSlides Transcription.docx
Slides Transcription.docx
 
Gary Affleck Ward CV
Gary Affleck Ward CVGary Affleck Ward CV
Gary Affleck Ward CV
 
RRozek Project List 9 20 15
RRozek Project List 9 20 15RRozek Project List 9 20 15
RRozek Project List 9 20 15
 
Electrical Engineer Resume
Electrical Engineer ResumeElectrical Engineer Resume
Electrical Engineer Resume
 
arco.cv
arco.cvarco.cv
arco.cv
 
New Brochure 1 Clm
New Brochure 1   ClmNew Brochure 1   Clm
New Brochure 1 Clm
 
Ganesh Golande-CV-Senior Contracts Administrator
Ganesh Golande-CV-Senior Contracts AdministratorGanesh Golande-CV-Senior Contracts Administrator
Ganesh Golande-CV-Senior Contracts Administrator
 
Tim Read CV January 2016
Tim Read CV January 2016Tim Read CV January 2016
Tim Read CV January 2016
 
Tim Read CV January 2016
Tim Read CV January 2016Tim Read CV January 2016
Tim Read CV January 2016
 

More from grahamelanders

Roof replacement and internal remedial works
Roof replacement and internal remedial worksRoof replacement and internal remedial works
Roof replacement and internal remedial worksgrahamelanders
 
Freelance project management residential
Freelance project management residentialFreelance project management residential
Freelance project management residentialgrahamelanders
 
Freelance project management residential
Freelance project management residentialFreelance project management residential
Freelance project management residentialgrahamelanders
 
Freelance project management case studies - residential
Freelance project management case studies - residentialFreelance project management case studies - residential
Freelance project management case studies - residentialgrahamelanders
 
Freelance project management commercial - Case Study
Freelance project management commercial - Case StudyFreelance project management commercial - Case Study
Freelance project management commercial - Case Studygrahamelanders
 

More from grahamelanders (7)

Roof replacement and internal remedial works
Roof replacement and internal remedial worksRoof replacement and internal remedial works
Roof replacement and internal remedial works
 
program
programprogram
program
 
Surrey education
Surrey educationSurrey education
Surrey education
 
Freelance project management residential
Freelance project management residentialFreelance project management residential
Freelance project management residential
 
Freelance project management residential
Freelance project management residentialFreelance project management residential
Freelance project management residential
 
Freelance project management case studies - residential
Freelance project management case studies - residentialFreelance project management case studies - residential
Freelance project management case studies - residential
 
Freelance project management commercial - Case Study
Freelance project management commercial - Case StudyFreelance project management commercial - Case Study
Freelance project management commercial - Case Study
 

Perth metro

  • 1. Project Aims and Objectives: To construct a new 2000 metre square office / workshop and a new 300 metre square paint shed, for a commercial mine vehicle hire company. Project Management Services: ∗ Pproducing and adhering to an accelerated programme ∗ Collating and adjudication of Contractor quotes ∗ Producing Contractor Contracts ∗ Agreeing budgets for all work packages ∗ Determining the financial forecast ∗ Man hours / accommodation schedules / rotas ∗ Fly in / Fly out site visits ∗ Producing and updating H&S Plan ∗ Producing Planning Submission for the Paint Shed ∗ Dealing with Building Regulations 2012 (CDC, CCC, OP) ∗ Electricity connection application ∗ Logistics ∗ Overseeing design & Codes compliance ∗ Stakeholder Reporting Accomplishments: Constructing the biggest Commercial premises in Port Hedland on an accelerated programme. Also changing the company H&S culture to more acceptable standards. Site Overview Tilt Panel Construction Workshop InternalsFire water Tanks & Pump Project Management Case Study New Build Cyclone Rate Commercial Property, Port Hedland, Western Australia.
  • 2. New Build Workshop / Offices New Build Laboratory Various Projects: As part of the Sino Iron Ore Mine Site (http://www.citicpacificmining.com/our- operation/sino-iron-project/) various construction projects were required to achieve mining operations. Projects included: 1. New build (2000 square metre) cyclone rated workshop and office building 2. New build (1000 square metre) cyclone rated laboratory building 3. New build (200 linear metre) cyclone rated warehouse canopy & concrete walkway 4. New build cyclone rated cool rooms 5. New build cyclone rated electrical transformer compounds Project Management Services • Defining the Scope of Works and producing detail Scope of Works Documents • Producing and adhering to programmes • Adjudication of Contractor quotes and Contractor Contract Management • Financial Management. Setting budgets and controlling actual spend • Fly in Fly out to undertake site visits and apply for Permits to Work • Overseeing the production of H&S Management Plans / CRAWS • Approved Mine Site Permit Holder • Logistics Management • Stakeholder Reporting (Inc. Chinese Clients) • Manager of in-house diverse team (Inc. Maori’s, Filipino's) Accomplishments: Maintaining timely transport deliveries from Perth to the Sino Mine Site, in order to keep to programmes. Project Management Case Study New Build Commercial Projects, Sino Mine Site, Cape Preston, Western Australia.