PROJECT
PRESENTATION
AL MUHAIDIB CONTRACTING CO.
September 11, 2014
KAU PROJECTS
AL MUHAIDIB CONTRACTING CO.
2
INDEX
1- CN 1300 & 1400 - Completion of Faculty Environmental Design…………………. 4
2- CN 6600 - General Materials and Laboratories…………………………………….. 5
3- CN 6601 - Completion of Faculty of Science……………………………………….. 6
4- CN 6300 - Biotechnoly and Laboratories…………………………………………… 7
5- CN 2650 - Car Parking……………………………………………………………...... 8
6- CN 460 - Class Rooms for 3 Buildings ( slemaniyah 1 – slemaneyah 2 – faysaleyah ). 9
7- CN 711 - Completion of Scientific Societies……………………………………….. 10
8- CN 241 - English Language Center ( 2 Building )…………………………………… 11
9- Organization Chart…………………………………………………………………... 12
10- Planned VS Actual…………………………………………………………………… 13
11- Penalty Amount……………………………………………………………………… 14
3
Page
Al Muhaidib Contracting Co.
KAU PROJECTS ( CN 1300 & 1400 )
Client FLUOR Arabia Limited
Contract Type Re-Measured
Start AUG 2010
Finish DEC 2012
Progress 100 %
Project Value 36,554 Million SAR
Earned Value 33,244 Million SAR
Invoiced 3,310 Million SAR Penalty
deducted
Variance Balanced 0 SAR
Manpower 0
Al Muhaidib Contracting Co. 4
Project Scope
Completion of Faculty Environmental
Design
Remaining Work &
Issues
• Paper works on going
Comments Building already occupied by client
Expected Final
Handover
20-OCT-2014
Client FLUOR Arabia Limited
Contract Type Re-Measured
Start AUG 2006
Finish OCT 2010
Progress 100 %
Project Value 87,999 Million SAR
Earned Value 87,999 Million SAR
Net Invoiced 0 SAR
Variance Balanced 0 SAR
Manpower 0
CN 1300
CN 1400
KAU PROJECTS ( CN 6600 )
Client FLUOR Arabia Limited
Contract Type Re-Measured
Start DEC 2008
Finish MAR 2013
Progress 100 %
Project Value 87,999 Million SAR
Earned Value 75,388 Million SAR
Net Invoiced 1,760 Million SAR 2% retention
31/NOV/2013 Submit
21/DEC/2013 Approved
10,851 Million SAR Penalty
Variance Balanced 0 SAR
Manpower 0
Al Muhaidib Contracting Co. 5
Project Scope
General Materials and Laboratories
. The structure includes lower level parking and five levels for the facilities including
the pent house.
. Scope of work includes construction of the structure and the finishing of the first
and the fourth floor including electro-mechanical facilities
Remaining Work & Issues • Completed and paper works on going
Comment Building already occupied by client
Expected Final Handover 20-OCT-2014
KAU PROJECTS ( CN 6601 )
Client FLUOR Arabia Limited
Contract Type Re-Measured
Start OCT 2011
Finish SEP 2013
Progress 100 %
Project Value 47,971 Million SAR
Earned Value 41,890 Million SAR
Net Invoiced 960,117 Thousand SAR 2% retention
5,120 Million SAR Penalty
Variance Balanced 0 SAR
Manpower( Direct ) 0
Manpower( Indirect ) 3 Guard
Al Muhaidib Contracting Co. 6
Project Scope
Completion of Faculty of Science
. Scope of work includes finishing works of second and the third floor including
electro-mechanical facilities
Remaining Work & Issues
• Completed and paper works on going
Comment Building already occupied by client
Expected Final Handover 20-OCT-2014
KAU PROJECTS ( CN 6300 )
Client FLUOR Arabia Limited
Contract Type Re-Measured
Start MAY 2010
Finish JUL 2013
Progress 90 %
Project Value 106,094 Million SAR
Earned Value 105,701Million SAR
Net Invoiced 0 SAR
392,770 Thousand SAR Supervision Fees
Variance Balanced 0 SAR
Manpower ( Direct ) 37
Manpower ( Indirect ) 41
Saudi 22
Al Muhaidib Contracting Co. 7
Project Scope
Biotechnology and Laboratories
. The structure includes lower level parking and four levels for the facilities including the pent house.
. Scope of work includes construction of laboratories, research areas, museums, storage for chemicals
/ gases, office spaces, and conference facilities.
Remaining Work & Issues
• Radiation Room ( Additional Work )
• Fire Fighting ( Only Chemical Flashing )
• White and Turk Board
• Air balance
• B.M.S
Expected Final Handover END OF DEC 2014
KAU PROJECTS ( CN 2650 )
Client FLUOR Arabia Limited
Contract Type Re-Measured
Start APR 2011
Finish SEP 2013
Progress 100 %
Project Value 20,358 Million SAR
Earned Value 17,810 Million SAR
Net Invoiced 407,172 Thousand SAR 2% Retention
2,140 Million SAR Penalty
Variance Balanced 0 SAR
Al Muhaidib Contracting Co. 8
Project Scope
Car Parking
. Scope of work includes finishing works in
the car parking under the academic square.
Remaining Work &
Issues
• paper work on going
Expected Final
Handover
20-OCT-2014
KAU PROJECTS ( CN 460 )
Client Zuhair Fayez Partnership
Contract Type Re-Measured
Start AUG 2010
Finish AUG 2011
Progress 90 %
Project Value 55,785 Million SAR
Earned Value 54,687Million SAR
1,097 Million SAR Penalty
Net Invoiced 0 SAR
Variance Balanced 0 SAR
Al Muhaidib Contracting Co. 9
Project Scope
Class Rooms for 3 Buildings :
1. Boys
2. Girls
3. Faysaliyah
Remaining Work &
Issues
• Cladding ( Under Inspection )
• AHU ( by end of OCT )
Comment • Building already occupied by client
Expected Final
Handover
Pending Complete
KAU PROJECTS ( CN 711 )
Client Zuhair Fayez
Partnership
Contract Type Re-Measured
Start DEC 2011
Finish JUL 2012
Progress 100 %
Project Value 14,856 Million SAR
Earned Value 14,113 Million SAR
Net Invoiced 742,838 Thousand SAR 2% Retention
Variance Balanced 0 SAR
Al Muhaidib Contracting Co. 10
Project Scope
Completion of Scientific Societies
. Scope of work includes finishing of conference facilities, office spaces, seminar
lounges and auditorium along with the site development which involves, asphalt
road, interlocking pavements and landscape.
Remaining Work & Issues • Paper work on going
Expected Final Handover 20-OCT-2014
KAU PROJECTS ( CN 241 )
Client Zuhair Fayez Partnership
Contract Type Re-Measured
Start JAN 2012
Finish DEC 2014
Progress 67.37 %
Project Value 141 Million SAR
Earned Value 77,694 Million SAR
Net Invoiced 2,150 Million SAR 25-AUG-2014
Variance Balanced 63,306 Million SAR
2,848 Million SAR Invoice
submitted not
approved from
Consultant
Manpower ( Direct ) 273
Manpower ( Indirect ) 76
Saudi 40
Al Muhaidib Contracting Co. 11
Project Scope
English Language Center ( 2 Building )
The structure includes four levels for the
facilities including the pent house.
Remaining Work &
Issues
• Elevator ( In Progress )
• BMS
Expected Primary
Handover
• 30-DEC-2014
Part A
Part B
CN 241 - Part A
Project Scope
English Language Center ( 2 Building )
The structure includes four levels for the
facilities including the pent house.
Remaining Work &
Issues
• ( In Progress )
Expected Primary
Handover
• 30-DEC-2014
CN 241 - Part B
12
Organization Chart
CN 240
Planned VS Actual
13
1.24%
0.75%
0.79%
0.96%
0.48%
0.60%
0.75%
0.45%
0.31%
0.25%
0.43%
0.51%
0.43%
0.16%
0.28%
0.08%
0.45%
0.43%
0.74%
0.28%
0.10%
0.29%
0.50%
0.50%
0.99%
0.21%
0.47%
1.31%
0.40%
0.13%
0.31%
0.44%
0.59%
0.59%
0.90%
0.37%
0.63%
0.00%
10.00%
20.00%
30.00%
40.00%
50.00%
60.00%
70.00%
80.00%
90.00%
100.00%
0.00%
0.50%
1.00%
1.50%
2.00%
2.50%
3.00%
7-Jan-14
14-Jan-14
21-Jan-14
28-Jan-14
4-Feb-14
11-Feb-14
18-Feb-14
25-Feb-14
4-Mar-14
11-Mar-14
18-Mar-14
25-Mar-14
1-Apr-14
8-Apr-14
15-Apr-14
22-Apr-14
29-Apr-14
6-May-14
13-May-14
20-May-14
27-May-14
3-Jun-14
10-Jun-14
17-Jun-14
24-Jun-14
1-Jul-14
8-Jul-14
15-Jul-14
22-Jul-14
29-Jul-14
5-Aug-14
12-Aug-14
19-Aug-14
26-Aug-14
2-Sep-14
9-Sep-14
16-Sep-14
23-Sep-14
30-Sep-14
7-Oct-14
14-Oct-14
WEEKS
Actual Weekly Work
Progess %
Penalty Amount
PROJECT Total Penalty Remarks
KAAU-6601 5,120,420.64
4,797,120.00 ( 10% of contract )
323,300.64 ( supervision fees )
KAAU-6600 10,851,929.52
8,799,998.59 ( 10% of contract )
912,420.91 ( supervision fees )
1,139,510.02 ( penalty CN:1400 )
KAAU-460 1,097,566.63
KAAU-2650 2,140,778.75
2,035,860.50 ( 10% of contract )
104,918.25 ( supervision fees )
KAAU-1400 3,310,167.57
3,655,453.39 ( all this invoice deducted-penalty is 10% of contract )
794,224.20 ( supervision fees )
- 1,139,510.02 ( so remaining penalty deducted from 6.600 )
KAAU-6300 392,770.00
337,778.91 ( 0.32% of contract )
54,991.34 ( fees supervision )
22,913,633.11
14
Al Muhaidib Contracting Co.
THANK YOU
AL MUHAIDIB CONTRACTING CO.
15
ENG. Abdullah Bakhsh

More Related Content

What's hot

Power Point Presentation for (Advance Project Management)
Power Point Presentation for (Advance Project Management)Power Point Presentation for (Advance Project Management)
Power Point Presentation for (Advance Project Management)
Obi-Ugbo Alex
 
SUBIN_SINGH_STEEL_STRUCTURAL_ENGINEER.PDF
SUBIN_SINGH_STEEL_STRUCTURAL_ENGINEER.PDFSUBIN_SINGH_STEEL_STRUCTURAL_ENGINEER.PDF
SUBIN_SINGH_STEEL_STRUCTURAL_ENGINEER.PDF
Subin Singh
 
ibrahim moustafa_CV_Last update dated8_2016.DOC
ibrahim moustafa_CV_Last update dated8_2016.DOCibrahim moustafa_CV_Last update dated8_2016.DOC
ibrahim moustafa_CV_Last update dated8_2016.DOC
Ibrahim Moustafa Farag
 
Faisalaiah project (english) 3 REV.03
Faisalaiah project (english) 3 REV.03Faisalaiah project (english) 3 REV.03
Faisalaiah project (english) 3 REV.03
Wael Nafad
 
R_S_Rajaram_CV_Feb_2017
R_S_Rajaram_CV_Feb_2017R_S_Rajaram_CV_Feb_2017
R_S_Rajaram_CV_Feb_2017
R S Rajaram
 
CBI-electric Renewable Cabins Presentation
CBI-electric Renewable Cabins PresentationCBI-electric Renewable Cabins Presentation
CBI-electric Renewable Cabins Presentation
Damian Coetzee
 
Engineer and Project management CV 'Ali Al Obaidy
Engineer and Project management  CV 'Ali Al ObaidyEngineer and Project management  CV 'Ali Al Obaidy
Engineer and Project management CV 'Ali Al Obaidy
Ali Alobaidy
 

What's hot (20)

Power Point Presentation for (Advance Project Management)
Power Point Presentation for (Advance Project Management)Power Point Presentation for (Advance Project Management)
Power Point Presentation for (Advance Project Management)
 
SUBIN_SINGH_STEEL_STRUCTURAL_ENGINEER.PDF
SUBIN_SINGH_STEEL_STRUCTURAL_ENGINEER.PDFSUBIN_SINGH_STEEL_STRUCTURAL_ENGINEER.PDF
SUBIN_SINGH_STEEL_STRUCTURAL_ENGINEER.PDF
 
Hrc nmmc guidelines
Hrc nmmc guidelinesHrc nmmc guidelines
Hrc nmmc guidelines
 
Projects Annex
Projects AnnexProjects Annex
Projects Annex
 
CV Bernard Graves
CV Bernard GravesCV Bernard Graves
CV Bernard Graves
 
Survey Engr
Survey EngrSurvey Engr
Survey Engr
 
ibrahim moustafa_CV_Last update dated8_2016.DOC
ibrahim moustafa_CV_Last update dated8_2016.DOCibrahim moustafa_CV_Last update dated8_2016.DOC
ibrahim moustafa_CV_Last update dated8_2016.DOC
 
Faisalaiah project (english) 3 REV.03
Faisalaiah project (english) 3 REV.03Faisalaiah project (english) 3 REV.03
Faisalaiah project (english) 3 REV.03
 
Manimaran
ManimaranManimaran
Manimaran
 
2014 Enbridge Day - Major Projects
2014 Enbridge Day - Major Projects2014 Enbridge Day - Major Projects
2014 Enbridge Day - Major Projects
 
R_S_Rajaram_CV_Feb_2017
R_S_Rajaram_CV_Feb_2017R_S_Rajaram_CV_Feb_2017
R_S_Rajaram_CV_Feb_2017
 
CBI-electric Renewable Cabins Presentation
CBI-electric Renewable Cabins PresentationCBI-electric Renewable Cabins Presentation
CBI-electric Renewable Cabins Presentation
 
Sachin Mohelay
Sachin MohelaySachin Mohelay
Sachin Mohelay
 
محمد جمال
محمد جمالمحمد جمال
محمد جمال
 
Engineer and Project management CV 'Ali Al Obaidy
Engineer and Project management  CV 'Ali Al ObaidyEngineer and Project management  CV 'Ali Al Obaidy
Engineer and Project management CV 'Ali Al Obaidy
 
CVPLAING
CVPLAINGCVPLAING
CVPLAING
 
RESUME-RDP
RESUME-RDPRESUME-RDP
RESUME-RDP
 
RCREEE-enerMENA_pgesco profile-rcree
RCREEE-enerMENA_pgesco profile-rcreeRCREEE-enerMENA_pgesco profile-rcree
RCREEE-enerMENA_pgesco profile-rcree
 
Procurement of equipment_packages_at_aker_engineering
Procurement of equipment_packages_at_aker_engineeringProcurement of equipment_packages_at_aker_engineering
Procurement of equipment_packages_at_aker_engineering
 
RESUME-RDP
RESUME-RDPRESUME-RDP
RESUME-RDP
 

Similar to Presentation Sample KAAU

CV QS AKHTAR RASUL
CV QS AKHTAR RASULCV QS AKHTAR RASUL
CV QS AKHTAR RASUL
Akhtar Rasul
 
Ehsan New CV 17.8.2016
Ehsan New CV 17.8.2016Ehsan New CV 17.8.2016
Ehsan New CV 17.8.2016
ehsan nazeer
 
Ehsan New CV 17.8.2016
Ehsan New CV 17.8.2016Ehsan New CV 17.8.2016
Ehsan New CV 17.8.2016
ehsan nazeer
 
ALI FAKHIR IBRAHEEM - C.V
ALI FAKHIR IBRAHEEM -  C.VALI FAKHIR IBRAHEEM -  C.V
ALI FAKHIR IBRAHEEM - C.V
Ali Fakhir
 
NASHAT_CV updated FOR NOORS
NASHAT_CV updated FOR NOORSNASHAT_CV updated FOR NOORS
NASHAT_CV updated FOR NOORS
Nshaat Hafez
 

Similar to Presentation Sample KAAU (20)

CV QS AKHTAR RASUL
CV QS AKHTAR RASULCV QS AKHTAR RASUL
CV QS AKHTAR RASUL
 
Ehsan New CV 17.8.2016
Ehsan New CV 17.8.2016Ehsan New CV 17.8.2016
Ehsan New CV 17.8.2016
 
Ehsan New CV 17.8.2016
Ehsan New CV 17.8.2016Ehsan New CV 17.8.2016
Ehsan New CV 17.8.2016
 
Mahmoud Ahmed ElbadawyCV
Mahmoud Ahmed ElbadawyCVMahmoud Ahmed ElbadawyCV
Mahmoud Ahmed ElbadawyCV
 
Rihan Height Project Execution Plan-Rev00
Rihan Height Project Execution Plan-Rev00Rihan Height Project Execution Plan-Rev00
Rihan Height Project Execution Plan-Rev00
 
hdebelenjr-latest-CV
hdebelenjr-latest-CVhdebelenjr-latest-CV
hdebelenjr-latest-CV
 
Mahendran resume updated
Mahendran resume updated Mahendran resume updated
Mahendran resume updated
 
CV - Senior QAQC Engineer-Civil
CV - Senior QAQC Engineer-CivilCV - Senior QAQC Engineer-Civil
CV - Senior QAQC Engineer-Civil
 
Sagar_cv
Sagar_cv Sagar_cv
Sagar_cv
 
Amr. 2015....
Amr. 2015....Amr. 2015....
Amr. 2015....
 
M SUBBA RAO CV latest
M SUBBA RAO CV latestM SUBBA RAO CV latest
M SUBBA RAO CV latest
 
Hossam salah-cv
Hossam salah-cvHossam salah-cv
Hossam salah-cv
 
ALI FAKHIR IBRAHEEM - C.V
ALI FAKHIR IBRAHEEM -  C.VALI FAKHIR IBRAHEEM -  C.V
ALI FAKHIR IBRAHEEM - C.V
 
NASHAT_CV updated FOR NOORS
NASHAT_CV updated FOR NOORSNASHAT_CV updated FOR NOORS
NASHAT_CV updated FOR NOORS
 
Salakidis Savvas
Salakidis SavvasSalakidis Savvas
Salakidis Savvas
 
CV Updated
CV UpdatedCV Updated
CV Updated
 
V.GUHAN-CV 01 link
V.GUHAN-CV 01 linkV.GUHAN-CV 01 link
V.GUHAN-CV 01 link
 
riyasdeen - qs
riyasdeen - qsriyasdeen - qs
riyasdeen - qs
 
Akhila CV
Akhila CVAkhila CV
Akhila CV
 
01_HVAC-R5_Tecni
01_HVAC-R5_Tecni01_HVAC-R5_Tecni
01_HVAC-R5_Tecni
 

Presentation Sample KAAU

  • 2. KAU PROJECTS AL MUHAIDIB CONTRACTING CO. 2
  • 3. INDEX 1- CN 1300 & 1400 - Completion of Faculty Environmental Design…………………. 4 2- CN 6600 - General Materials and Laboratories…………………………………….. 5 3- CN 6601 - Completion of Faculty of Science……………………………………….. 6 4- CN 6300 - Biotechnoly and Laboratories…………………………………………… 7 5- CN 2650 - Car Parking……………………………………………………………...... 8 6- CN 460 - Class Rooms for 3 Buildings ( slemaniyah 1 – slemaneyah 2 – faysaleyah ). 9 7- CN 711 - Completion of Scientific Societies……………………………………….. 10 8- CN 241 - English Language Center ( 2 Building )…………………………………… 11 9- Organization Chart…………………………………………………………………... 12 10- Planned VS Actual…………………………………………………………………… 13 11- Penalty Amount……………………………………………………………………… 14 3 Page Al Muhaidib Contracting Co.
  • 4. KAU PROJECTS ( CN 1300 & 1400 ) Client FLUOR Arabia Limited Contract Type Re-Measured Start AUG 2010 Finish DEC 2012 Progress 100 % Project Value 36,554 Million SAR Earned Value 33,244 Million SAR Invoiced 3,310 Million SAR Penalty deducted Variance Balanced 0 SAR Manpower 0 Al Muhaidib Contracting Co. 4 Project Scope Completion of Faculty Environmental Design Remaining Work & Issues • Paper works on going Comments Building already occupied by client Expected Final Handover 20-OCT-2014 Client FLUOR Arabia Limited Contract Type Re-Measured Start AUG 2006 Finish OCT 2010 Progress 100 % Project Value 87,999 Million SAR Earned Value 87,999 Million SAR Net Invoiced 0 SAR Variance Balanced 0 SAR Manpower 0 CN 1300 CN 1400
  • 5. KAU PROJECTS ( CN 6600 ) Client FLUOR Arabia Limited Contract Type Re-Measured Start DEC 2008 Finish MAR 2013 Progress 100 % Project Value 87,999 Million SAR Earned Value 75,388 Million SAR Net Invoiced 1,760 Million SAR 2% retention 31/NOV/2013 Submit 21/DEC/2013 Approved 10,851 Million SAR Penalty Variance Balanced 0 SAR Manpower 0 Al Muhaidib Contracting Co. 5 Project Scope General Materials and Laboratories . The structure includes lower level parking and five levels for the facilities including the pent house. . Scope of work includes construction of the structure and the finishing of the first and the fourth floor including electro-mechanical facilities Remaining Work & Issues • Completed and paper works on going Comment Building already occupied by client Expected Final Handover 20-OCT-2014
  • 6. KAU PROJECTS ( CN 6601 ) Client FLUOR Arabia Limited Contract Type Re-Measured Start OCT 2011 Finish SEP 2013 Progress 100 % Project Value 47,971 Million SAR Earned Value 41,890 Million SAR Net Invoiced 960,117 Thousand SAR 2% retention 5,120 Million SAR Penalty Variance Balanced 0 SAR Manpower( Direct ) 0 Manpower( Indirect ) 3 Guard Al Muhaidib Contracting Co. 6 Project Scope Completion of Faculty of Science . Scope of work includes finishing works of second and the third floor including electro-mechanical facilities Remaining Work & Issues • Completed and paper works on going Comment Building already occupied by client Expected Final Handover 20-OCT-2014
  • 7. KAU PROJECTS ( CN 6300 ) Client FLUOR Arabia Limited Contract Type Re-Measured Start MAY 2010 Finish JUL 2013 Progress 90 % Project Value 106,094 Million SAR Earned Value 105,701Million SAR Net Invoiced 0 SAR 392,770 Thousand SAR Supervision Fees Variance Balanced 0 SAR Manpower ( Direct ) 37 Manpower ( Indirect ) 41 Saudi 22 Al Muhaidib Contracting Co. 7 Project Scope Biotechnology and Laboratories . The structure includes lower level parking and four levels for the facilities including the pent house. . Scope of work includes construction of laboratories, research areas, museums, storage for chemicals / gases, office spaces, and conference facilities. Remaining Work & Issues • Radiation Room ( Additional Work ) • Fire Fighting ( Only Chemical Flashing ) • White and Turk Board • Air balance • B.M.S Expected Final Handover END OF DEC 2014
  • 8. KAU PROJECTS ( CN 2650 ) Client FLUOR Arabia Limited Contract Type Re-Measured Start APR 2011 Finish SEP 2013 Progress 100 % Project Value 20,358 Million SAR Earned Value 17,810 Million SAR Net Invoiced 407,172 Thousand SAR 2% Retention 2,140 Million SAR Penalty Variance Balanced 0 SAR Al Muhaidib Contracting Co. 8 Project Scope Car Parking . Scope of work includes finishing works in the car parking under the academic square. Remaining Work & Issues • paper work on going Expected Final Handover 20-OCT-2014
  • 9. KAU PROJECTS ( CN 460 ) Client Zuhair Fayez Partnership Contract Type Re-Measured Start AUG 2010 Finish AUG 2011 Progress 90 % Project Value 55,785 Million SAR Earned Value 54,687Million SAR 1,097 Million SAR Penalty Net Invoiced 0 SAR Variance Balanced 0 SAR Al Muhaidib Contracting Co. 9 Project Scope Class Rooms for 3 Buildings : 1. Boys 2. Girls 3. Faysaliyah Remaining Work & Issues • Cladding ( Under Inspection ) • AHU ( by end of OCT ) Comment • Building already occupied by client Expected Final Handover Pending Complete
  • 10. KAU PROJECTS ( CN 711 ) Client Zuhair Fayez Partnership Contract Type Re-Measured Start DEC 2011 Finish JUL 2012 Progress 100 % Project Value 14,856 Million SAR Earned Value 14,113 Million SAR Net Invoiced 742,838 Thousand SAR 2% Retention Variance Balanced 0 SAR Al Muhaidib Contracting Co. 10 Project Scope Completion of Scientific Societies . Scope of work includes finishing of conference facilities, office spaces, seminar lounges and auditorium along with the site development which involves, asphalt road, interlocking pavements and landscape. Remaining Work & Issues • Paper work on going Expected Final Handover 20-OCT-2014
  • 11. KAU PROJECTS ( CN 241 ) Client Zuhair Fayez Partnership Contract Type Re-Measured Start JAN 2012 Finish DEC 2014 Progress 67.37 % Project Value 141 Million SAR Earned Value 77,694 Million SAR Net Invoiced 2,150 Million SAR 25-AUG-2014 Variance Balanced 63,306 Million SAR 2,848 Million SAR Invoice submitted not approved from Consultant Manpower ( Direct ) 273 Manpower ( Indirect ) 76 Saudi 40 Al Muhaidib Contracting Co. 11 Project Scope English Language Center ( 2 Building ) The structure includes four levels for the facilities including the pent house. Remaining Work & Issues • Elevator ( In Progress ) • BMS Expected Primary Handover • 30-DEC-2014 Part A Part B CN 241 - Part A Project Scope English Language Center ( 2 Building ) The structure includes four levels for the facilities including the pent house. Remaining Work & Issues • ( In Progress ) Expected Primary Handover • 30-DEC-2014 CN 241 - Part B
  • 14. Penalty Amount PROJECT Total Penalty Remarks KAAU-6601 5,120,420.64 4,797,120.00 ( 10% of contract ) 323,300.64 ( supervision fees ) KAAU-6600 10,851,929.52 8,799,998.59 ( 10% of contract ) 912,420.91 ( supervision fees ) 1,139,510.02 ( penalty CN:1400 ) KAAU-460 1,097,566.63 KAAU-2650 2,140,778.75 2,035,860.50 ( 10% of contract ) 104,918.25 ( supervision fees ) KAAU-1400 3,310,167.57 3,655,453.39 ( all this invoice deducted-penalty is 10% of contract ) 794,224.20 ( supervision fees ) - 1,139,510.02 ( so remaining penalty deducted from 6.600 ) KAAU-6300 392,770.00 337,778.91 ( 0.32% of contract ) 54,991.34 ( fees supervision ) 22,913,633.11 14 Al Muhaidib Contracting Co.
  • 15. THANK YOU AL MUHAIDIB CONTRACTING CO. 15 ENG. Abdullah Bakhsh