program
1. ID Task Name %
Complete
Duration Start Finish Predecessors
0 Force Wedgefield - Workshop, Office & Externals 61% 427 days? Thu 5/05/11 Fri 21/12/12
1
2 PRE - CONSTRUCTION PHASE 79% 427 days? Thu 5/05/11 Fri 21/12/12
3 Quote 100% 47 days? Tue 12/07/11 Wed 14/09/11
4 Receive Scope of Works from Force Equipment 100% 1 day Tue 12/07/11 Tue 12/07/11
5 PM LTD to Submit Final Quote (Rev1) 100% 1 day Wed 31/08/11 Wed 31/08/114
6 PM LTD to Submit Budget Estimate for Additional Office Floor 100% 1 day? Wed 14/09/11 Wed 14/09/115
7 Contract 100% 1 day Mon 31/10/11 Mon 31/10/11
8 PM LTD & Force Equipment to Sign Contract (simple works) 100% 1 day Mon 31/10/11 Mon 31/10/11
9 Design 100% 293 days Thu 5/05/11 Mon 18/06/12
10 Produce Landscaping Drawings 100% 6 days Wed 28/09/11 Wed 5/10/11
11 Produce Workshop & Office Drawings 100% 15 days Thu 5/05/11 Wed 25/05/11
12 Produce Store Drawings 100% 15 days Thu 5/05/11 Wed 25/05/11
13 Produce Structural Engineer Calculations / Design 100% 65 days Tue 3/01/12 Mon 2/04/12
14 Soil Investigation Report 100% 1 day Wed 1/06/11 Wed 1/06/11
15 Finalise Designs to Start Construction Phase 100% 11 days Mon 4/06/12 Mon 18/06/12
16 Specification Completion 100% 1 day Wed 26/10/11 Wed 26/10/11
17 Statutory Approvals 84% 408 days Wed 25/05/11 Fri 14/12/12
18 Development Approval: Workshop & Office 100% 22 days Wed 25/05/11 Thu 23/06/11
19 Prepare Application 100% 1 day Wed 25/05/11 Wed 25/05/1111,12
20 Submission to Council 100% 1 day Wed 25/05/11 Wed 25/05/1119
21 Review Period 100% 21 days Thu 26/05/11 Thu 23/06/11 20
22 Approval 100% 0 days Wed 22/06/11 Wed 22/06/1121
23 Development Approval: Landscaping Plan 100% 29 days Thu 6/10/11 Wed 16/11/11
24 Prepare Application 100% 7 days Thu 6/10/11 Fri 14/10/11 10
25 Submission to Council 100% 1 day Mon 17/10/11 Mon 17/10/11 24
26 Review Period 100% 21 days Tue 18/10/11 Tue 15/11/1125
27 Approval 100% 0 days Wed 16/11/11 Wed 16/11/1126
28 Building Surveyors Independent Review of Proposed Building Licence Drawings 100% 46 days Thu 17/11/11 Fri 20/01/12
29 Selection, Negotiations and Appointment 100% 20 days Thu 17/11/11 Wed 14/12/1127
30 Design Review Period 100% 26 days Thu 15/12/11 Thu 19/01/12 29
31 Issue of Comments 100% 0 days Fri 20/01/12 Fri 20/01/12 30
32 Environmental Health Services: Septic Tank & Leach Drain 100% 57 days Mon 23/01/12 Wed 11/04/12
33 Prepare & Submit Application 100% 21 days Mon 23/01/12 Mon 20/02/12 31
34 Application Review Process 100% 36 days Tue 21/02/12 Tue 10/04/12 33
35 Review and respond to conditions 100% 1 day Wed 29/02/12 Wed 29/02/12
36 Approval 100% 0 days Wed 11/04/12 Wed 11/04/1234,35
37 Water Application 100% 11 days Mon 2/04/12 Mon 16/04/12
38 Prepare and Submit Water Application 100% 3 days Mon 2/04/12 Wed 4/04/12
39 Review Period 100% 8 days Thu 5/04/12 Mon 16/04/12 38
40 Approval 100% 0 days Mon 16/04/12 Mon 16/04/12 39
41 FESA 100% 55 days Wed 1/02/12 Wed 18/04/12
42 Prepare and Submit to FESA 100% 16 days Wed 1/02/12 Wed 22/02/12
43 Review Period 100% 39 days Thu 23/02/12 Tue 17/04/12 42
44 Submit Confirmation of Building Classification to FESA 100% 1 day Wed 11/04/12 Wed 11/04/12
45 Approval 100% 0 days Wed 18/04/12 Wed 18/04/12 44,43
46 Building Licence: Workshop & Office 100% 81 days Mon 2/04/12 Tue 24/07/12
47 Prepare and Submit Application to Council 100% 12 days Mon 2/04/12 Tue 17/04/12
48 Review Period 100% 70 days Tue 17/04/12 Mon 23/07/12 47
49 Issue Energy Efficiency Declaration for Windows & Doors 100% 1 day Mon 14/05/12 Mon 14/05/12
50 Issue Energy Efficiency Declaration for Office (Aircon & Ventilation Systems) 100% 1 day Tue 12/06/12 Tue 12/06/12
51 Respond to Conditions 100% 1 day Thu 14/06/12 Thu 14/06/12
52 Building License Approval (permit nr. 10714) 100% 0 days Tue 24/07/12 Tue 24/07/12 48,49,50,51
53 Horizon Power 34% 95 days Mon 6/08/12 Fri 14/12/12
54 Prepare and Submit Application 100% 19 days Mon 6/08/12 Thu 30/08/12
55 Review Period 20% 66 days Fri 31/08/12 Fri 30/11/12 54
56 Approval and Undertake Works 0% 10 days Mon 3/12/12 Fri 14/12/12 55
57 Health & Safety 50% 130 days Mon 25/06/12 Fri 21/12/12
58 OSHE Management Plan 47% 125 days Mon 2/07/12 Fri 21/12/12
59 Issue DRAFT OSHE Management Plan to Site 100% 1 day Mon 2/07/12 Mon 2/07/12
60 Produce FINAL OSHE Management Plan 100% 21 days Tue 3/07/12 Tue 31/07/12 59
61 Issue FINAL OSHE Management Plan to Site 100% 1 day Wed 1/08/12 Wed 1/08/12 60
62 Site Supervisor to Review & Amend OHSE documents (until end of project) 35% 102 days Thu 2/08/12 Fri 21/12/12 61
63 Method Statements, JSA's and Workers Documents 50% 130 days Mon 25/06/12 Fri 21/12/12
64 Site Supervisor to Receive & Review Method Statements (from sub contractors - until end of project) 50% 130 days Mon 25/06/12 Fri 21/12/12
65 Site Supervisor to Receive & Review JSA's (from Sub Contractors - until end of project) 50% 130 days Mon 25/06/12 Fri 21/12/12
66 Site Supervisor to review all sub contractors blue/white cards, licences, etc. (until end of project) 50% 130 days Mon 25/06/12 Fri 21/12/12
67 Worksafe 100% 26 days Tue 3/07/12 Tue 7/08/12
68 Notify Worksafe to the Proposed Tilt Panel Works 100% 1 day Tue 3/07/12 Tue 3/07/12
69 Date for Inspection 100% 2 days Mon 6/08/12 Tue 7/08/12 68
70 Procurement and Finance 95% 120 days Mon 16/04/12 Sat 29/09/12
71 Sub Contractors 96% 120 days Mon 16/04/12 Sat 29/09/12
72 Select subcontractors to gain Quotes (on-going) 100% 81 days Tue 22/05/12 Tue 11/09/12
73 Quote analysis and review (on-going) 100% 81 days Tue 22/05/12 Tue 11/09/12
74 Choose Sub Contractor to undertake works (on-going) 100% 81 days Tue 22/05/12 Tue 11/09/12
75 Work Packages and Purchase Orders 76% 121 days Mon 16/04/12 Sat 29/09/12
76 Civil Works (to dampen ground) 100% 1 day Fri 20/07/12 Fri 20/07/12
77 Screw Piles 100% 1 day Tue 29/05/12 Tue 29/05/12
78 Concreting and Tilt Panels 100% 4 days Tue 3/07/12 Fri 6/07/12
79 Termite Control 100% 1 day Tue 17/07/12 Tue 17/07/12
80 Electrics 100% 3 days Mon 9/07/12 Wed 11/07/12
81 Plumbing 100% 3 days Thu 5/07/12 Mon 9/07/12
82 Air Conditioning 100% 3 days Tue 3/07/12 Thu 5/07/12
83 Mesh, insulation and Sheeting 100% 5 days Wed 29/08/12 Tue 4/09/12
84 Structural Steel Rigging 100% 3 days Thu 23/08/12 Mon 27/08/12
85 Fire Services 100% 3 days Wed 29/08/12 Fri 31/08/12
86 Internal Stud Walls / Gyprock 100% 3 days Wed 5/09/12 Fri 7/09/12
87 Tiling 100% 1 day Mon 30/07/12 Mon 30/07/12
88 Windows 100% 1 day Mon 3/09/12 Mon 3/09/12
89 Joinery 0% 5 days Mon 17/09/12 Fri 21/09/12
90 Painting 0% 5 days Mon 17/09/12 Fri 21/09/12
91 Suppliers 95% 117 days Thu 19/04/12 Fri 28/09/12
92 Select suppliers to supply materials (on-going) 95% 117 days Thu 19/04/12 Fri 28/09/12
93 Quote analysis and review (on-going) 95% 117 days Thu 19/04/12 Fri 28/09/12
94 Choose Supplier to undertake works (on-going) 95% 117 days Thu 19/04/12 Fri 28/09/12
95 Issue Purchase Orders 85% 109 days Thu 19/04/12 Tue 18/09/12
96 Concrete Supply Nr. 1 100% 1 day Thu 19/04/12 Thu 19/04/12
97 Concrete Supply Nr. 2 100% 1 day Mon 25/06/12 Mon 25/06/12
98 Steel Fabricators (structural steel and Prefab Stud Walls) 100% 1 day Fri 13/07/12 Fri 13/07/12
99 Health & Safety Signage 100% 1 day Tue 17/07/12 Tue 17/07/12
100 Tiling Supply 100% 1 day Tue 24/07/12 Tue 24/07/12
101 Concrete mesh and Reo 100% 1 day Tue 24/07/12 Tue 24/07/12
102 Window Manufacturers 100% 1 day Mon 3/09/12 Mon 3/09/12
103 Roof / Wall Mesh 100% 1 day Wed 12/09/12 Wed 12/09/12
104 External Roof / Walls Insulation 100% 1 day Wed 12/09/12 Wed 12/09/12
105 Internal Walls Insulation 100% 1 day Wed 12/09/12 Wed 12/09/12
106 External Roof Office Sheeting 100% 1 day Wed 12/09/12 Wed 12/09/12
107 External Workshop Roof / Wall Sheeting 0% 1 day Tue 18/09/12 Tue 18/09/12
108 Wash Room Items (pans, soap dispensers, etc.) 0% 1 day Tue 18/09/12 Tue 18/09/12
109
110
111 CONSTRUCTION PHASE 22% 130 days? Mon 25/06/12 Fri 21/12/12
112 Site Set-up 100% 2 days Mon 25/06/12 Tue 26/06/12
113 Install Site Office 100% 2 days Mon 25/06/12 Tue 26/06/12
114 Install Toilet with Waste Storage 100% 2 days Mon 25/06/12 Tue 26/06/12
115 Install Storage Container 100% 2 days Mon 25/06/12 Tue 26/06/12
116 Install H&S Site Items (e.g.: Signage) 100% 2 days Mon 25/06/12 Tue 26/06/12
117
118 Substructure: Workshop & Office 100% 24 days Wed 27/06/12 Mon 30/07/12
119 Earthworks 100% 6 days Wed 27/06/12 Wed 4/07/12
120 Clearance 100% 1 day Wed 27/06/12 Wed 27/06/12 113,114,115,116
121 Fill, compaction and level to higher level 100% 4 days Thu 28/06/12 Tue 3/07/12 120
122 Survey & Peg Site 100% 1 day Wed 4/07/12 Wed 4/07/12 121
123 Wash down bay tanks 100% 1 day Thu 5/07/12 Thu 5/07/12
124 Excavate to reduce levels for wash down bay tanks 100% 1 day Thu 5/07/12 Thu 5/07/12 122
125 Insert tanks and drainage pipework 100% 1 day Thu 5/07/12 Thu 5/07/12 122
126 Concrete Foundations 100% 7 days Thu 5/07/12 Fri 13/07/12
127 Excavate to reduce levels for foundations 100% 1 day Thu 5/07/12 Thu 5/07/12 122
128 Install screw piles 100% 2 days Thu 5/07/12 Fri 6/07/12 122
129 Install Reinforcement 100% 2 days Thu 5/07/12 Fri 6/07/12 122
130 Place Concrete 100% 2 days Thu 5/07/12 Fri 6/07/12 122
131 Curing 100% 5 days Fri 6/07/12 Thu 12/07/12 130
132 Apply Termite Treatment 100% 1 day Fri 13/07/12 Fri 13/07/12 131
133 Concrete Slab 100% 11 days Mon 16/07/12 Mon 30/07/12
134 Excavate to reduce levels for slab 100% 1 day Mon 16/07/12 Mon 16/07/12 132
135 Install Reinforcement and prelay 100% 4 days Tue 17/07/12 Fri 20/07/12 134
136 Place concrete 100% 2 days Mon 23/07/12 Tue 24/07/12 135
137 Curing 100% 4 days Wed 25/07/12 Mon 30/07/12 136
138 Super Structure: Workshop & Office 43% 79 days Mon 30/07/12 Thu 15/11/12
139 Tilt Panels 84% 40 days Mon 30/07/12 Fri 21/09/12
140 Setting out / Formwork 100% 5 days Mon 30/07/12 Fri 3/08/12 137
141 Formwork and make tilt panels 100% 10 days Mon 6/08/12 Wed 22/08/12 140
142 Curing 100% 10 days Thu 23/08/12 Wed 5/09/12 141
143 Erect tilt panels 100% 2 days Thu 6/09/12 Fri 7/09/12 142
144 Structural Engineer Sign Off 0% 5 days Mon 17/09/12 Fri 21/09/12 143
145 Structural Steel 85% 45 days Mon 30/07/12 Fri 28/09/12
146 Shop Detail Dwgs & Approvals 100% 5 days Mon 30/07/12 Fri 3/08/12
147 Fabrication and hot dip galvanising 100% 30 days Mon 6/08/12 Fri 14/09/12 146
148 Delivery to Site 80% 22 days Tue 21/08/12 Wed 19/09/12
149 First Delivery 100% 3 days Tue 21/08/12 Thu 23/08/12
150 Second Delivery 100% 3 days Fri 24/08/12 Tue 28/08/12
151 Third Delivery 100% 3 days Fri 31/08/12 Tue 4/09/12
152 Fourth Delivery 100% 3 days Tue 4/09/12 Thu 6/09/12
153 Fifth Delivery 0% 3 days Mon 17/09/12 Wed 19/09/12
154 Erection 55% 15 days Mon 10/09/12 Fri 28/09/12 149,150,151,152,153
155 Sheeting 0% 44 days Mon 17/09/12 Thu 15/11/12
156 Office 0% 8 days Mon 17/09/12 Wed 26/09/12
157 Delivery of Materials to Site 0% 3 days Mon 17/09/12 Wed 19/09/12
158 Install Wire Mesh, Anticon and Roof Sheeting 0% 5 days Thu 20/09/12 Wed 26/09/12 157
159 Workshop 0% 40 days Mon 17/09/12 Fri 9/11/12
160 Delivery of Materials to Site 0% 3 days Mon 17/09/12 Wed 19/09/12
161 Roof Safety Access System Install 0% 5 days Thu 20/09/12 Wed 26/09/12 160
162 Install Wire Mesh, Anticon and Roof Sheeting 0% 37 days Thu 20/09/12 Fri 9/11/12 160
163 Office & Workshop 0% 19 days Mon 22/10/12 Thu 15/11/12
164 Site Measure and Drawings for Pressings (window flashings, etc.) 0% 3 days Mon 22/10/12 Wed 24/10/12
165 Manufacture 0% 10 days Thu 25/10/12 Wed 7/11/12164
166 Delivery of materials to site 0% 3 days Thu 8/11/12 Mon 12/11/12 165
167 Install flashings 0% 3 days Tue 13/11/12 Thu 15/11/12 166
168 Doors (External) 0% 23 days Mon 24/09/12 Wed 24/10/12
169 Manufacture and Delivery 0% 15 days Mon 24/09/12 Fri 12/10/12
170 Install Doors and Frames 0% 3 days Mon 15/10/12 Wed 17/10/12 169
171 Install Glazing 0% 2 days Thu 18/10/12 Fri 19/10/12 170
172 Install Hardware 0% 3 days Mon 22/10/12 Wed 24/10/12 171
173 Install Roller Doors 0% 8 days Mon 15/10/12 Wed 24/10/12 169
174 Windows (External) 54% 18 days Mon 10/09/12 Wed 3/10/12
175 Tilt Panels 50% 18 days Mon 10/09/12 Wed 3/10/12
176 Site Measure 100% 1 day Mon 10/09/12 Mon 10/09/12
177 Manufacture and Delivery 80% 10 days Tue 11/09/12 Mon 24/09/12 176
178 Install Windows to Office 0% 7 days Tue 25/09/12 Wed 3/10/12 177
179 Workshop 57% 17 days Tue 11/09/12 Wed 3/10/12
180 Manufacture and Delivery 98% 10 days Tue 11/09/12 Mon 24/09/12
181 Install Windows to Workshop 0% 7 days Tue 25/09/12 Wed 3/10/12 180
182 Internals: Workshop & Office 2% 49 days Tue 11/09/12 Fri 16/11/12
183 Prelay / Tube Out 0% 16 days Fri 21/09/12 Fri 12/10/12
184 Plumbing Pre Set 0% 6 days Fri 21/09/12 Fri 28/09/12
185 Plumbing Tube Out 0% 4 days Mon 1/10/12 Thu 4/10/12 184
186 Electrical and Data Pre Wire 0% 4 days Mon 1/10/12 Thu 4/10/12
187 Installation of Air Conditioning Ducting 0% 5 days Mon 8/10/12 Fri 12/10/12
188 Internal Cladding (Gyprock) 6% 38 days Tue 11/09/12 Thu 1/11/12
189 Materials Delivery 0% 3 days Mon 24/09/12 Wed 26/09/12
190 65mm Stud Wall Erection 0% 10 days Thu 27/09/12 Wed 10/10/12 189
191 75mm thick Stud Wall Manufacture and Delivery 18% 28 days Tue 11/09/12 Thu 18/10/12
192 75mm Stud Wall Erection 0% 5 days Mon 24/09/12 Fri 28/09/12 191
193 Gyprock to Walls Install 0% 20 days Fri 5/10/12 Thu 1/11/12 192,185,186
194 Ceiling Batten Install 0% 20 days Fri 5/10/12 Thu 1/11/12 192,185,186
195 Final Fit Off 0% 28 days Wed 10/10/12 Fri 16/11/12
196 Electrical Fit off 0% 10 days Mon 5/11/12 Fri 16/11/12
197 Electrical Fixture Installation 0% 10 days Mon 5/11/12 Fri 16/11/12
198 Electrical Appliance Installation 0% 10 days Mon 5/11/12 Fri 16/11/12
199 Plumbing Fit off 0% 10 days Mon 29/10/12 Fri 9/11/12
200 Delivery of Cubicles to Site 0% 5 days Mon 29/10/12 Fri 2/11/12
201 Install Toilet Cubicles 0% 5 days Mon 5/11/12 Fri 9/11/12 200
202 Plumbing Fixture Installation 0% 5 days Mon 5/11/12 Fri 9/11/12 200
203 Mechanical Fit off 0% 2 days Fri 9/11/12 Mon 12/11/12
204 Hydraulic (AirCon) Fitoff 0% 2 days Fri 9/11/12 Mon 12/11/12
205 Internal Doors & Windows 0% 18 days Wed 10/10/12 Fri 2/11/12
206 Delivery of Doors and Windows 0% 3 days Wed 10/10/12 Fri 12/10/12
207 Install doors and frames 0% 5 days Mon 15/10/12 Fri 19/10/12
208 Install Glazing 0% 5 days Mon 22/10/12 Fri 26/10/12 207
209 Installation of Door & Window Hardware 0% 5 days Mon 29/10/12 Fri 2/11/12 208
210 Carpentry 0% 8 days Fri 12/10/12 Tue 23/10/12
211 Delivery of Materials to Site 0% 3 days Fri 12/10/12 Tue 16/10/12
212 Cabinetworks/Benches/Tables 0% 5 days Wed 17/10/12 Tue 23/10/12 211
213 Skirting 0% 5 days Wed 17/10/12 Tue 23/10/12 211
214 Finishes 0% 28 days Mon 8/10/12 Wed 14/11/12
215 Floor Finishes 0% 20 days Mon 8/10/12 Fri 2/11/12
216 Delivery of tiles to site 0% 3 days Mon 8/10/12 Wed 10/10/12
217 Tiling 0% 17 days Thu 11/10/12 Fri 2/11/12 216
218 Painting 0% 13 days Mon 29/10/12 Wed 14/11/12
219 Delivery of Paint to Site 0% 3 days Mon 29/10/12 Wed 31/10/12
220 Painting 0% 10 days Thu 1/11/12 Wed 14/11/12219
221 Externals 0% 96 days? Fri 3/08/12 Fri 14/12/12
222 Retaining Wall 0% 19 days? Fri 3/08/12 Wed 29/08/12
223 Civil Works 0% 3 days Fri 3/08/12 Tue 7/08/12
224 Form Concrete Foundations 0% 10 days Wed 8/08/12 Tue 21/08/12 223
225 Form Retaining Wall Panels 0% 5 days Wed 22/08/12 Tue 28/08/12 224
226 Insert Retaining Wall Panels 0% 1 day? Wed 29/08/12 Wed 29/08/12 225
227 Fire Services (FESA) 0% 38 days Wed 19/09/12 Fri 9/11/12
228 Fire Tanks 0% 28 days Wed 19/09/12 Fri 26/10/12
229 Civil Works 0% 3 days Wed 19/09/12 Fri 21/09/12
230 Pour concrete pads 0% 6 days Mon 24/09/12 Mon 1/10/12 229
231 Install Tanks 0% 10 days Mon 15/10/12 Fri 26/10/12 230
232 Hydrants and Pump House 0% 20 days Mon 15/10/12 Fri 9/11/12
233 Civil Works 0% 5 days Mon 15/10/12 Fri 19/10/12
234 Install pump house, hydrants and pipework 0% 10 days Mon 22/10/12 Fri 2/11/12 233
235 Pressure Test and Certify 0% 5 days Mon 5/11/12 Fri 9/11/12 234
236 Parking Area 0% 15 days Fri 9/11/12 Thu 29/11/12
237 Base Preparation 0% 3 days Fri 9/11/12 Tue 13/11/12
238 Bitumen 0% 10 days Wed 14/11/12 Tue 27/11/12237
239 Kerbing 0% 10 days Wed 14/11/12 Tue 27/11/12237
240 Line Marking 0% 2 days Wed 28/11/12 Thu 29/11/12 238,239
241 Landscaping 0% 15 days Mon 26/11/12 Fri 14/12/12
242 Civil Works and Concrete Stormwater Tanks and Run Off 0% 15 days Mon 26/11/12 Fri 14/12/12
243 Reticulation 0% 15 days Mon 26/11/12 Fri 14/12/12
244 Paving 0% 15 days Mon 26/11/12 Fri 14/12/12
245 Plants/Shrubs 0% 15 days Mon 26/11/12 Fri 14/12/12
246 Hydraulics and Septic System inc. testing and certifying 0% 9 days? Mon 5/11/12 Thu 15/11/12
247 Civil Works 0% 5 days Mon 5/11/12 Fri 9/11/12
248 Drainage 0% 3 days? Mon 12/11/12 Wed 14/11/12
249 Insert pipework 0% 1 day? Mon 12/11/12 Mon 12/11/12 247
250 Test and certify 0% 1 day? Tue 13/11/12 Tue 13/11/12249
251 Backfill 0% 1 day? Wed 14/11/12 Wed 14/11/12250
252 Septic System 0% 4 days? Mon 12/11/12 Thu 15/11/12
253 Insert Septic System 0% 1 day? Mon 12/11/12 Mon 12/11/12 247
254 Notify EHS of installed Works (prior to back fill) Note: Lead-in time not known 0% 1 day? Mon 12/11/12 Mon 12/11/12 247
255 On site Inspection by EHS 0% 1 day? Tue 13/11/12 Tue 13/11/12253
256 Test and certify 0% 1 day? Wed 14/11/12 Wed 14/11/12255
257 Backfill 0% 1 day? Thu 15/11/12 Thu 15/11/12 256
258 Other 0% 10 days Mon 26/11/12 Fri 7/12/12
259 Fencing 0% 10 days Mon 26/11/12 Fri 7/12/12
260 Signage 0% 1 day Mon 3/12/12 Mon 3/12/12
261 Preliminary Practical Completion 0% 15 days Mon 3/12/12 Fri 21/12/12
262 Force Equipment Inspection 0% 1 day Fri 14/12/12 Fri 14/12/12
263 Rectifications 0% 5 days Mon 17/12/12 Fri 21/12/12 262
264 Building Surveyors Report and rectification 0% 15 days Mon 3/12/12 Fri 21/12/12
265
266 POST CONSTRUCTION PHASE 0% 28 days Wed 14/11/12 Fri 21/12/12
267 Client Inspection and Hand Over 0% 1 day Fri 21/12/12 Fri 21/12/12
268 Demob from Site 0% 1 day Fri 21/12/12 Fri 21/12/12
269 Start 12 Month Defects Liability Period 0% 1 day Fri 21/12/12 Fri 21/12/12
270 Settle Final Account with Client & Sub Contractors 0% 10 days Mon 10/12/12 Fri 21/12/12
271 Produce & Issue 'As Built' Drawings 0% 28 days Wed 14/11/12 Fri 21/12/12
272 Key/Warranty/Certificate Compilation 0% 28 days Wed 14/11/12 Fri 21/12/12
427 days?
PRE - CONSTRUCTION PHASE
Design
Produce Structural Engineer Calculations / Design
Finalise Designs to Start Construction Phase
Statutory Approvals
Building Surveyors Independent Review of Proposed Building Licence Drawings
Design Review Period
Environmental Health Services: Septic Tank & Leach Drain
Prepare & Submit ApplicationPrepare & Submit Application
Application Review Process
Review and respond to conditions
11/04
Water Application
Prepare and Submit Water Application
Review Period
16/04
FESA
Prepare and Submit to FESA
Review Period
Complete FESA Approval
Building Licence: Workshop & Office
Prepare and Submit Application to Council
Review Period
Issue Energy Efficiency Declaration for Windows & DoorsIssue Energy Efficiency Declaration for Windows & Doors
Issue Energy Efficiency Declaration for Office (Aircon & Ventilation Systems)Issue Energy Efficiency Declaration for Office (Aircon & Ventilation Systems)
Respond to ConditionsRespond to Conditions
24/07
Prepare and Submit Application
Review Period
Approval and Undertake Works
Health & Safety
OSHE Management Plan
Issue DRAFT OSHE Management Plan to SiteIssue DRAFT OSHE Management Plan to Site
Produce FINAL OSHE Management Plan
Issue FINAL OSHE Management Plan to SiteIssue FINAL OSHE Management Plan to Site
Site Supervisor to Review & Amend OHSE documents (unt
Site Supervisor to Receive & Review Method Statements (fr
Site Supervisor to Receive & Review JSA's (from Sub Contr
Site Supervisor to review all sub contractors blue/white car
Worksafe
Notify Worksafe to the Proposed Tilt Panel WorksNotify Worksafe to the Proposed Tilt Panel Works
Date for Inspection
Procurement and Finance
Sub Contractors
Select subcontractors to gain Quotes (on-going)
Quote analysis and review (on-going)
Choose Sub Contractor to undertake works (on-going)
Civil Works (to dampen ground)
Screw Piles
Concreting and Tilt Panels
Termite Control
Electrics
PlumbingPlumbing
Air Conditioning
Mesh, insulation and Sheeting
Structural Steel Rigging
Fire Services
Internal Stud Walls / Gyprock
Tiling
Windows
Joinery
Painting
Select suppliers to supply materials (on-going)
Quote analysis and review (on-going)
Choose Supplier to undertake works (on-going)
Concrete Supply Nr. 1
Concrete Supply Nr. 2
Steel Fabricators (structural steel and Prefab Stud Walls)
Health & Safety Signage
Tiling Supply
Concrete mesh and Reo
Window Manufacturers
Roof / Wall Mesh
External Roof / Walls Insulation
Internal Walls Insulation
External Roof Office Sheeting
External Workshop Roof / Wall Sheeting
Wash Room Items (pans, soap dispensers, etc.)
CONSTRUCTION PHASE
Site Set-up
Install Site OfficeInstall Site Office
Install Toilet with Waste StorageInstall Toilet with Waste Storage
Install Storage Container
Install H&S Site Items (e.g.: Signage)Install H&S Site Items (e.g.: Signage)
Substructure: Workshop & Office
Earthworks
ClearanceClearance
Fill, compaction and level to higher levelFill, compaction and level to higher level
Survey & Peg Site
Wash down bay tanks
Excavate to reduce levels for wash down bay tanksExcavate to reduce levels for wash down bay tanks
Insert tanks and drainage pipeworkInsert tanks and drainage pipework
Concrete Foundations
Excavate to reduce levels for foundationsExcavate to reduce levels for foundations
Install screw pilesInstall screw piles
Install ReinforcementInstall Reinforcement
Place ConcretePlace Concrete
CuringCuring
Apply Termite TreatmentApply Termite Treatment
Concrete Slab
Excavate to reduce levels for slabExcavate to reduce levels for slab
Install Reinforcement and prelayInstall Reinforcement and prelay
Place concretePlace concrete
Curing
Tilt Panels
Setting out / FormworkSetting out / Formwork
Formwork and make tilt panels
Curing
Erect tilt panels
Structural Engineer Sign Off
Structural Steel
Shop Detail Dwgs & Approvals
Fabrication and hot dip galvanising
Delivery to Site
First Delivery
Second Delivery
Third Delivery
Fourth Delivery
Fifth Delivery
Erection
Sheeting
Office
Delivery of Materials to Site
Install Wire Mesh, Anticon and Roof Sheeting
Workshop
Delivery of Materials to Site
Roof Safety Access System Install
Install Wire Mesh, Anticon and Roof Sheeting
Office & Workshop
Site Measure and Drawings for Pressings (window flashings, etc.)
Manufacture
Delivery of materials to site
Install flashings
Doors (External)
Manufacture and Delivery
Install Doors and Frames
Install Glazing
Install Hardware
Install Roller Doors
Windows (External)
Tilt Panels
Site Measure
Manufacture and Delivery
Install Windows to Office
Manufacture and Delivery
Install Windows to Workshop
Internals: Workshop & Office
Prelay / Tube Out
Plumbing Pre Set
Plumbing Tube Out
Electrical and Data Pre Wire
Installation of Air Conditioning Ducting
Internal Cladding (Gyprock)
Materials Delivery
65mm Stud Wall Erection
75mm thick Stud Wall Manufacture and Delivery
75mm Stud Wall Erection
Gyprock to Walls Install
Ceiling Batten Install
Final Fit Off
Electrical Fit off
Electrical Fixture Installation
Electrical Appliance Installation
Plumbing Fit off
Delivery of Cubicles to Site
Install Toilet Cubicles
Plumbing Fixture Installation
Mechanical Fit off
Hydraulic (AirCon) Fitoff
Internal Doors & Windows
Delivery of Doors and Windows
Install doors and frames
Install Glazing
Installation of Door & Window Hardware
Carpentry
Delivery of Materials to Site
Cabinetworks/Benches/Tables
Skirting
Finishes
Floor Finishes
Delivery of tiles to site
Tiling
Painting
Delivery of Paint to Site
Painting
Externals
Civil Works
Form Concrete Foundations
Form Retaining Wall Panels
Insert Retaining Wall Panels
Civil Works
Pour concrete pads
Install Tanks
Civil Works
Install pump house, hydrants and pipework
Pressure Test and Certify
Parking Area
Base Preparation
Bitumen
Kerbing
Line Marking
Landscaping
Civil Works and Concrete Stormwater Tanks and Run Off
Reticulation
Paving
Plants/Shrubs
Civil Works
Insert pipework
Test and certify
Backfill
Insert Septic System
Notify EHS of installed Works (prior to back fill) Note: Lead-in time not known
On site Inspection by EHS
Test and certify
Backfill
Other
Fencing
Signage
Preliminary Practical Completion
Force Equipment Inspection
Rectifications
Building Surveyors Report and rectification
POST CONSTRUCTION PHASE
Client Inspection and Hand Over
Demob from Site
Start 12 Month Defects Liability Period
Settle Final Account with Client & Sub Contractors
Produce & Issue 'As Built' Drawings
Key/Warranty/Certificate Compilation
T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F
23 Jan '12 6 Feb '12 20 Feb '12 5 Mar '12 19 Mar '12 2 Apr '12 16 Apr '12 30 Apr '12 14 May '12 28 May '12 11 Jun '12 25 Jun '12 9 Jul '12 23 Jul '12 6 Aug '12 20 Aug '12 3 Sep '12 17 Sep '12 1 Oct '12 15 Oct '12 29 Oct '12 12 Nov '12 26 Nov '12 10 Dec '12 24 Dec '12 7 Jan '13 21 Jan '13
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Progress
Deadline
PERTHMETRO ERECTION OF WORKSHOP & OFFICE AND EXTERNAL WORKS
PROGRAM REV 01
FORCE EQUIPMENT - WEDGEFIELD
Page 1
Project: Force Wedgefield - Workshop
Date: Sun 16/09/12