ID Task Name %
Complete
Duration Start Finish Predecessors
0 Force Wedgefield - Workshop, Office & Externals 61% 427 days? Thu 5/05/11 Fri 21/12/12
1
2 PRE - CONSTRUCTION PHASE 79% 427 days? Thu 5/05/11 Fri 21/12/12
3 Quote 100% 47 days? Tue 12/07/11 Wed 14/09/11
4 Receive Scope of Works from Force Equipment 100% 1 day Tue 12/07/11 Tue 12/07/11
5 PM LTD to Submit Final Quote (Rev1) 100% 1 day Wed 31/08/11 Wed 31/08/114
6 PM LTD to Submit Budget Estimate for Additional Office Floor 100% 1 day? Wed 14/09/11 Wed 14/09/115
7 Contract 100% 1 day Mon 31/10/11 Mon 31/10/11
8 PM LTD & Force Equipment to Sign Contract (simple works) 100% 1 day Mon 31/10/11 Mon 31/10/11
9 Design 100% 293 days Thu 5/05/11 Mon 18/06/12
10 Produce Landscaping Drawings 100% 6 days Wed 28/09/11 Wed 5/10/11
11 Produce Workshop & Office Drawings 100% 15 days Thu 5/05/11 Wed 25/05/11
12 Produce Store Drawings 100% 15 days Thu 5/05/11 Wed 25/05/11
13 Produce Structural Engineer Calculations / Design 100% 65 days Tue 3/01/12 Mon 2/04/12
14 Soil Investigation Report 100% 1 day Wed 1/06/11 Wed 1/06/11
15 Finalise Designs to Start Construction Phase 100% 11 days Mon 4/06/12 Mon 18/06/12
16 Specification Completion 100% 1 day Wed 26/10/11 Wed 26/10/11
17 Statutory Approvals 84% 408 days Wed 25/05/11 Fri 14/12/12
18 Development Approval: Workshop & Office 100% 22 days Wed 25/05/11 Thu 23/06/11
19 Prepare Application 100% 1 day Wed 25/05/11 Wed 25/05/1111,12
20 Submission to Council 100% 1 day Wed 25/05/11 Wed 25/05/1119
21 Review Period 100% 21 days Thu 26/05/11 Thu 23/06/11 20
22 Approval 100% 0 days Wed 22/06/11 Wed 22/06/1121
23 Development Approval: Landscaping Plan 100% 29 days Thu 6/10/11 Wed 16/11/11
24 Prepare Application 100% 7 days Thu 6/10/11 Fri 14/10/11 10
25 Submission to Council 100% 1 day Mon 17/10/11 Mon 17/10/11 24
26 Review Period 100% 21 days Tue 18/10/11 Tue 15/11/1125
27 Approval 100% 0 days Wed 16/11/11 Wed 16/11/1126
28 Building Surveyors Independent Review of Proposed Building Licence Drawings 100% 46 days Thu 17/11/11 Fri 20/01/12
29 Selection, Negotiations and Appointment 100% 20 days Thu 17/11/11 Wed 14/12/1127
30 Design Review Period 100% 26 days Thu 15/12/11 Thu 19/01/12 29
31 Issue of Comments 100% 0 days Fri 20/01/12 Fri 20/01/12 30
32 Environmental Health Services: Septic Tank & Leach Drain 100% 57 days Mon 23/01/12 Wed 11/04/12
33 Prepare & Submit Application 100% 21 days Mon 23/01/12 Mon 20/02/12 31
34 Application Review Process 100% 36 days Tue 21/02/12 Tue 10/04/12 33
35 Review and respond to conditions 100% 1 day Wed 29/02/12 Wed 29/02/12
36 Approval 100% 0 days Wed 11/04/12 Wed 11/04/1234,35
37 Water Application 100% 11 days Mon 2/04/12 Mon 16/04/12
38 Prepare and Submit Water Application 100% 3 days Mon 2/04/12 Wed 4/04/12
39 Review Period 100% 8 days Thu 5/04/12 Mon 16/04/12 38
40 Approval 100% 0 days Mon 16/04/12 Mon 16/04/12 39
41 FESA 100% 55 days Wed 1/02/12 Wed 18/04/12
42 Prepare and Submit to FESA 100% 16 days Wed 1/02/12 Wed 22/02/12
43 Review Period 100% 39 days Thu 23/02/12 Tue 17/04/12 42
44 Submit Confirmation of Building Classification to FESA 100% 1 day Wed 11/04/12 Wed 11/04/12
45 Approval 100% 0 days Wed 18/04/12 Wed 18/04/12 44,43
46 Building Licence: Workshop & Office 100% 81 days Mon 2/04/12 Tue 24/07/12
47 Prepare and Submit Application to Council 100% 12 days Mon 2/04/12 Tue 17/04/12
48 Review Period 100% 70 days Tue 17/04/12 Mon 23/07/12 47
49 Issue Energy Efficiency Declaration for Windows & Doors 100% 1 day Mon 14/05/12 Mon 14/05/12
50 Issue Energy Efficiency Declaration for Office (Aircon & Ventilation Systems) 100% 1 day Tue 12/06/12 Tue 12/06/12
51 Respond to Conditions 100% 1 day Thu 14/06/12 Thu 14/06/12
52 Building License Approval (permit nr. 10714) 100% 0 days Tue 24/07/12 Tue 24/07/12 48,49,50,51
53 Horizon Power 34% 95 days Mon 6/08/12 Fri 14/12/12
54 Prepare and Submit Application 100% 19 days Mon 6/08/12 Thu 30/08/12
55 Review Period 20% 66 days Fri 31/08/12 Fri 30/11/12 54
56 Approval and Undertake Works 0% 10 days Mon 3/12/12 Fri 14/12/12 55
57 Health & Safety 50% 130 days Mon 25/06/12 Fri 21/12/12
58 OSHE Management Plan 47% 125 days Mon 2/07/12 Fri 21/12/12
59 Issue DRAFT OSHE Management Plan to Site 100% 1 day Mon 2/07/12 Mon 2/07/12
60 Produce FINAL OSHE Management Plan 100% 21 days Tue 3/07/12 Tue 31/07/12 59
61 Issue FINAL OSHE Management Plan to Site 100% 1 day Wed 1/08/12 Wed 1/08/12 60
62 Site Supervisor to Review & Amend OHSE documents (until end of project) 35% 102 days Thu 2/08/12 Fri 21/12/12 61
63 Method Statements, JSA's and Workers Documents 50% 130 days Mon 25/06/12 Fri 21/12/12
64 Site Supervisor to Receive & Review Method Statements (from sub contractors - until end of project) 50% 130 days Mon 25/06/12 Fri 21/12/12
65 Site Supervisor to Receive & Review JSA's (from Sub Contractors - until end of project) 50% 130 days Mon 25/06/12 Fri 21/12/12
66 Site Supervisor to review all sub contractors blue/white cards, licences, etc. (until end of project) 50% 130 days Mon 25/06/12 Fri 21/12/12
67 Worksafe 100% 26 days Tue 3/07/12 Tue 7/08/12
68 Notify Worksafe to the Proposed Tilt Panel Works 100% 1 day Tue 3/07/12 Tue 3/07/12
69 Date for Inspection 100% 2 days Mon 6/08/12 Tue 7/08/12 68
70 Procurement and Finance 95% 120 days Mon 16/04/12 Sat 29/09/12
71 Sub Contractors 96% 120 days Mon 16/04/12 Sat 29/09/12
72 Select subcontractors to gain Quotes (on-going) 100% 81 days Tue 22/05/12 Tue 11/09/12
73 Quote analysis and review (on-going) 100% 81 days Tue 22/05/12 Tue 11/09/12
74 Choose Sub Contractor to undertake works (on-going) 100% 81 days Tue 22/05/12 Tue 11/09/12
75 Work Packages and Purchase Orders 76% 121 days Mon 16/04/12 Sat 29/09/12
76 Civil Works (to dampen ground) 100% 1 day Fri 20/07/12 Fri 20/07/12
77 Screw Piles 100% 1 day Tue 29/05/12 Tue 29/05/12
78 Concreting and Tilt Panels 100% 4 days Tue 3/07/12 Fri 6/07/12
79 Termite Control 100% 1 day Tue 17/07/12 Tue 17/07/12
80 Electrics 100% 3 days Mon 9/07/12 Wed 11/07/12
81 Plumbing 100% 3 days Thu 5/07/12 Mon 9/07/12
82 Air Conditioning 100% 3 days Tue 3/07/12 Thu 5/07/12
83 Mesh, insulation and Sheeting 100% 5 days Wed 29/08/12 Tue 4/09/12
84 Structural Steel Rigging 100% 3 days Thu 23/08/12 Mon 27/08/12
85 Fire Services 100% 3 days Wed 29/08/12 Fri 31/08/12
86 Internal Stud Walls / Gyprock 100% 3 days Wed 5/09/12 Fri 7/09/12
87 Tiling 100% 1 day Mon 30/07/12 Mon 30/07/12
88 Windows 100% 1 day Mon 3/09/12 Mon 3/09/12
89 Joinery 0% 5 days Mon 17/09/12 Fri 21/09/12
90 Painting 0% 5 days Mon 17/09/12 Fri 21/09/12
91 Suppliers 95% 117 days Thu 19/04/12 Fri 28/09/12
92 Select suppliers to supply materials (on-going) 95% 117 days Thu 19/04/12 Fri 28/09/12
93 Quote analysis and review (on-going) 95% 117 days Thu 19/04/12 Fri 28/09/12
94 Choose Supplier to undertake works (on-going) 95% 117 days Thu 19/04/12 Fri 28/09/12
95 Issue Purchase Orders 85% 109 days Thu 19/04/12 Tue 18/09/12
96 Concrete Supply Nr. 1 100% 1 day Thu 19/04/12 Thu 19/04/12
97 Concrete Supply Nr. 2 100% 1 day Mon 25/06/12 Mon 25/06/12
98 Steel Fabricators (structural steel and Prefab Stud Walls) 100% 1 day Fri 13/07/12 Fri 13/07/12
99 Health & Safety Signage 100% 1 day Tue 17/07/12 Tue 17/07/12
100 Tiling Supply 100% 1 day Tue 24/07/12 Tue 24/07/12
101 Concrete mesh and Reo 100% 1 day Tue 24/07/12 Tue 24/07/12
102 Window Manufacturers 100% 1 day Mon 3/09/12 Mon 3/09/12
103 Roof / Wall Mesh 100% 1 day Wed 12/09/12 Wed 12/09/12
104 External Roof / Walls Insulation 100% 1 day Wed 12/09/12 Wed 12/09/12
105 Internal Walls Insulation 100% 1 day Wed 12/09/12 Wed 12/09/12
106 External Roof Office Sheeting 100% 1 day Wed 12/09/12 Wed 12/09/12
107 External Workshop Roof / Wall Sheeting 0% 1 day Tue 18/09/12 Tue 18/09/12
108 Wash Room Items (pans, soap dispensers, etc.) 0% 1 day Tue 18/09/12 Tue 18/09/12
109
110
111 CONSTRUCTION PHASE 22% 130 days? Mon 25/06/12 Fri 21/12/12
112 Site Set-up 100% 2 days Mon 25/06/12 Tue 26/06/12
113 Install Site Office 100% 2 days Mon 25/06/12 Tue 26/06/12
114 Install Toilet with Waste Storage 100% 2 days Mon 25/06/12 Tue 26/06/12
115 Install Storage Container 100% 2 days Mon 25/06/12 Tue 26/06/12
116 Install H&S Site Items (e.g.: Signage) 100% 2 days Mon 25/06/12 Tue 26/06/12
117
118 Substructure: Workshop & Office 100% 24 days Wed 27/06/12 Mon 30/07/12
119 Earthworks 100% 6 days Wed 27/06/12 Wed 4/07/12
120 Clearance 100% 1 day Wed 27/06/12 Wed 27/06/12 113,114,115,116
121 Fill, compaction and level to higher level 100% 4 days Thu 28/06/12 Tue 3/07/12 120
122 Survey & Peg Site 100% 1 day Wed 4/07/12 Wed 4/07/12 121
123 Wash down bay tanks 100% 1 day Thu 5/07/12 Thu 5/07/12
124 Excavate to reduce levels for wash down bay tanks 100% 1 day Thu 5/07/12 Thu 5/07/12 122
125 Insert tanks and drainage pipework 100% 1 day Thu 5/07/12 Thu 5/07/12 122
126 Concrete Foundations 100% 7 days Thu 5/07/12 Fri 13/07/12
127 Excavate to reduce levels for foundations 100% 1 day Thu 5/07/12 Thu 5/07/12 122
128 Install screw piles 100% 2 days Thu 5/07/12 Fri 6/07/12 122
129 Install Reinforcement 100% 2 days Thu 5/07/12 Fri 6/07/12 122
130 Place Concrete 100% 2 days Thu 5/07/12 Fri 6/07/12 122
131 Curing 100% 5 days Fri 6/07/12 Thu 12/07/12 130
132 Apply Termite Treatment 100% 1 day Fri 13/07/12 Fri 13/07/12 131
133 Concrete Slab 100% 11 days Mon 16/07/12 Mon 30/07/12
134 Excavate to reduce levels for slab 100% 1 day Mon 16/07/12 Mon 16/07/12 132
135 Install Reinforcement and prelay 100% 4 days Tue 17/07/12 Fri 20/07/12 134
136 Place concrete 100% 2 days Mon 23/07/12 Tue 24/07/12 135
137 Curing 100% 4 days Wed 25/07/12 Mon 30/07/12 136
138 Super Structure: Workshop & Office 43% 79 days Mon 30/07/12 Thu 15/11/12
139 Tilt Panels 84% 40 days Mon 30/07/12 Fri 21/09/12
140 Setting out / Formwork 100% 5 days Mon 30/07/12 Fri 3/08/12 137
141 Formwork and make tilt panels 100% 10 days Mon 6/08/12 Wed 22/08/12 140
142 Curing 100% 10 days Thu 23/08/12 Wed 5/09/12 141
143 Erect tilt panels 100% 2 days Thu 6/09/12 Fri 7/09/12 142
144 Structural Engineer Sign Off 0% 5 days Mon 17/09/12 Fri 21/09/12 143
145 Structural Steel 85% 45 days Mon 30/07/12 Fri 28/09/12
146 Shop Detail Dwgs & Approvals 100% 5 days Mon 30/07/12 Fri 3/08/12
147 Fabrication and hot dip galvanising 100% 30 days Mon 6/08/12 Fri 14/09/12 146
148 Delivery to Site 80% 22 days Tue 21/08/12 Wed 19/09/12
149 First Delivery 100% 3 days Tue 21/08/12 Thu 23/08/12
150 Second Delivery 100% 3 days Fri 24/08/12 Tue 28/08/12
151 Third Delivery 100% 3 days Fri 31/08/12 Tue 4/09/12
152 Fourth Delivery 100% 3 days Tue 4/09/12 Thu 6/09/12
153 Fifth Delivery 0% 3 days Mon 17/09/12 Wed 19/09/12
154 Erection 55% 15 days Mon 10/09/12 Fri 28/09/12 149,150,151,152,153
155 Sheeting 0% 44 days Mon 17/09/12 Thu 15/11/12
156 Office 0% 8 days Mon 17/09/12 Wed 26/09/12
157 Delivery of Materials to Site 0% 3 days Mon 17/09/12 Wed 19/09/12
158 Install Wire Mesh, Anticon and Roof Sheeting 0% 5 days Thu 20/09/12 Wed 26/09/12 157
159 Workshop 0% 40 days Mon 17/09/12 Fri 9/11/12
160 Delivery of Materials to Site 0% 3 days Mon 17/09/12 Wed 19/09/12
161 Roof Safety Access System Install 0% 5 days Thu 20/09/12 Wed 26/09/12 160
162 Install Wire Mesh, Anticon and Roof Sheeting 0% 37 days Thu 20/09/12 Fri 9/11/12 160
163 Office & Workshop 0% 19 days Mon 22/10/12 Thu 15/11/12
164 Site Measure and Drawings for Pressings (window flashings, etc.) 0% 3 days Mon 22/10/12 Wed 24/10/12
165 Manufacture 0% 10 days Thu 25/10/12 Wed 7/11/12164
166 Delivery of materials to site 0% 3 days Thu 8/11/12 Mon 12/11/12 165
167 Install flashings 0% 3 days Tue 13/11/12 Thu 15/11/12 166
168 Doors (External) 0% 23 days Mon 24/09/12 Wed 24/10/12
169 Manufacture and Delivery 0% 15 days Mon 24/09/12 Fri 12/10/12
170 Install Doors and Frames 0% 3 days Mon 15/10/12 Wed 17/10/12 169
171 Install Glazing 0% 2 days Thu 18/10/12 Fri 19/10/12 170
172 Install Hardware 0% 3 days Mon 22/10/12 Wed 24/10/12 171
173 Install Roller Doors 0% 8 days Mon 15/10/12 Wed 24/10/12 169
174 Windows (External) 54% 18 days Mon 10/09/12 Wed 3/10/12
175 Tilt Panels 50% 18 days Mon 10/09/12 Wed 3/10/12
176 Site Measure 100% 1 day Mon 10/09/12 Mon 10/09/12
177 Manufacture and Delivery 80% 10 days Tue 11/09/12 Mon 24/09/12 176
178 Install Windows to Office 0% 7 days Tue 25/09/12 Wed 3/10/12 177
179 Workshop 57% 17 days Tue 11/09/12 Wed 3/10/12
180 Manufacture and Delivery 98% 10 days Tue 11/09/12 Mon 24/09/12
181 Install Windows to Workshop 0% 7 days Tue 25/09/12 Wed 3/10/12 180
182 Internals: Workshop & Office 2% 49 days Tue 11/09/12 Fri 16/11/12
183 Prelay / Tube Out 0% 16 days Fri 21/09/12 Fri 12/10/12
184 Plumbing Pre Set 0% 6 days Fri 21/09/12 Fri 28/09/12
185 Plumbing Tube Out 0% 4 days Mon 1/10/12 Thu 4/10/12 184
186 Electrical and Data Pre Wire 0% 4 days Mon 1/10/12 Thu 4/10/12
187 Installation of Air Conditioning Ducting 0% 5 days Mon 8/10/12 Fri 12/10/12
188 Internal Cladding (Gyprock) 6% 38 days Tue 11/09/12 Thu 1/11/12
189 Materials Delivery 0% 3 days Mon 24/09/12 Wed 26/09/12
190 65mm Stud Wall Erection 0% 10 days Thu 27/09/12 Wed 10/10/12 189
191 75mm thick Stud Wall Manufacture and Delivery 18% 28 days Tue 11/09/12 Thu 18/10/12
192 75mm Stud Wall Erection 0% 5 days Mon 24/09/12 Fri 28/09/12 191
193 Gyprock to Walls Install 0% 20 days Fri 5/10/12 Thu 1/11/12 192,185,186
194 Ceiling Batten Install 0% 20 days Fri 5/10/12 Thu 1/11/12 192,185,186
195 Final Fit Off 0% 28 days Wed 10/10/12 Fri 16/11/12
196 Electrical Fit off 0% 10 days Mon 5/11/12 Fri 16/11/12
197 Electrical Fixture Installation 0% 10 days Mon 5/11/12 Fri 16/11/12
198 Electrical Appliance Installation 0% 10 days Mon 5/11/12 Fri 16/11/12
199 Plumbing Fit off 0% 10 days Mon 29/10/12 Fri 9/11/12
200 Delivery of Cubicles to Site 0% 5 days Mon 29/10/12 Fri 2/11/12
201 Install Toilet Cubicles 0% 5 days Mon 5/11/12 Fri 9/11/12 200
202 Plumbing Fixture Installation 0% 5 days Mon 5/11/12 Fri 9/11/12 200
203 Mechanical Fit off 0% 2 days Fri 9/11/12 Mon 12/11/12
204 Hydraulic (AirCon) Fitoff 0% 2 days Fri 9/11/12 Mon 12/11/12
205 Internal Doors & Windows 0% 18 days Wed 10/10/12 Fri 2/11/12
206 Delivery of Doors and Windows 0% 3 days Wed 10/10/12 Fri 12/10/12
207 Install doors and frames 0% 5 days Mon 15/10/12 Fri 19/10/12
208 Install Glazing 0% 5 days Mon 22/10/12 Fri 26/10/12 207
209 Installation of Door & Window Hardware 0% 5 days Mon 29/10/12 Fri 2/11/12 208
210 Carpentry 0% 8 days Fri 12/10/12 Tue 23/10/12
211 Delivery of Materials to Site 0% 3 days Fri 12/10/12 Tue 16/10/12
212 Cabinetworks/Benches/Tables 0% 5 days Wed 17/10/12 Tue 23/10/12 211
213 Skirting 0% 5 days Wed 17/10/12 Tue 23/10/12 211
214 Finishes 0% 28 days Mon 8/10/12 Wed 14/11/12
215 Floor Finishes 0% 20 days Mon 8/10/12 Fri 2/11/12
216 Delivery of tiles to site 0% 3 days Mon 8/10/12 Wed 10/10/12
217 Tiling 0% 17 days Thu 11/10/12 Fri 2/11/12 216
218 Painting 0% 13 days Mon 29/10/12 Wed 14/11/12
219 Delivery of Paint to Site 0% 3 days Mon 29/10/12 Wed 31/10/12
220 Painting 0% 10 days Thu 1/11/12 Wed 14/11/12219
221 Externals 0% 96 days? Fri 3/08/12 Fri 14/12/12
222 Retaining Wall 0% 19 days? Fri 3/08/12 Wed 29/08/12
223 Civil Works 0% 3 days Fri 3/08/12 Tue 7/08/12
224 Form Concrete Foundations 0% 10 days Wed 8/08/12 Tue 21/08/12 223
225 Form Retaining Wall Panels 0% 5 days Wed 22/08/12 Tue 28/08/12 224
226 Insert Retaining Wall Panels 0% 1 day? Wed 29/08/12 Wed 29/08/12 225
227 Fire Services (FESA) 0% 38 days Wed 19/09/12 Fri 9/11/12
228 Fire Tanks 0% 28 days Wed 19/09/12 Fri 26/10/12
229 Civil Works 0% 3 days Wed 19/09/12 Fri 21/09/12
230 Pour concrete pads 0% 6 days Mon 24/09/12 Mon 1/10/12 229
231 Install Tanks 0% 10 days Mon 15/10/12 Fri 26/10/12 230
232 Hydrants and Pump House 0% 20 days Mon 15/10/12 Fri 9/11/12
233 Civil Works 0% 5 days Mon 15/10/12 Fri 19/10/12
234 Install pump house, hydrants and pipework 0% 10 days Mon 22/10/12 Fri 2/11/12 233
235 Pressure Test and Certify 0% 5 days Mon 5/11/12 Fri 9/11/12 234
236 Parking Area 0% 15 days Fri 9/11/12 Thu 29/11/12
237 Base Preparation 0% 3 days Fri 9/11/12 Tue 13/11/12
238 Bitumen 0% 10 days Wed 14/11/12 Tue 27/11/12237
239 Kerbing 0% 10 days Wed 14/11/12 Tue 27/11/12237
240 Line Marking 0% 2 days Wed 28/11/12 Thu 29/11/12 238,239
241 Landscaping 0% 15 days Mon 26/11/12 Fri 14/12/12
242 Civil Works and Concrete Stormwater Tanks and Run Off 0% 15 days Mon 26/11/12 Fri 14/12/12
243 Reticulation 0% 15 days Mon 26/11/12 Fri 14/12/12
244 Paving 0% 15 days Mon 26/11/12 Fri 14/12/12
245 Plants/Shrubs 0% 15 days Mon 26/11/12 Fri 14/12/12
246 Hydraulics and Septic System inc. testing and certifying 0% 9 days? Mon 5/11/12 Thu 15/11/12
247 Civil Works 0% 5 days Mon 5/11/12 Fri 9/11/12
248 Drainage 0% 3 days? Mon 12/11/12 Wed 14/11/12
249 Insert pipework 0% 1 day? Mon 12/11/12 Mon 12/11/12 247
250 Test and certify 0% 1 day? Tue 13/11/12 Tue 13/11/12249
251 Backfill 0% 1 day? Wed 14/11/12 Wed 14/11/12250
252 Septic System 0% 4 days? Mon 12/11/12 Thu 15/11/12
253 Insert Septic System 0% 1 day? Mon 12/11/12 Mon 12/11/12 247
254 Notify EHS of installed Works (prior to back fill) Note: Lead-in time not known 0% 1 day? Mon 12/11/12 Mon 12/11/12 247
255 On site Inspection by EHS 0% 1 day? Tue 13/11/12 Tue 13/11/12253
256 Test and certify 0% 1 day? Wed 14/11/12 Wed 14/11/12255
257 Backfill 0% 1 day? Thu 15/11/12 Thu 15/11/12 256
258 Other 0% 10 days Mon 26/11/12 Fri 7/12/12
259 Fencing 0% 10 days Mon 26/11/12 Fri 7/12/12
260 Signage 0% 1 day Mon 3/12/12 Mon 3/12/12
261 Preliminary Practical Completion 0% 15 days Mon 3/12/12 Fri 21/12/12
262 Force Equipment Inspection 0% 1 day Fri 14/12/12 Fri 14/12/12
263 Rectifications 0% 5 days Mon 17/12/12 Fri 21/12/12 262
264 Building Surveyors Report and rectification 0% 15 days Mon 3/12/12 Fri 21/12/12
265
266 POST CONSTRUCTION PHASE 0% 28 days Wed 14/11/12 Fri 21/12/12
267 Client Inspection and Hand Over 0% 1 day Fri 21/12/12 Fri 21/12/12
268 Demob from Site 0% 1 day Fri 21/12/12 Fri 21/12/12
269 Start 12 Month Defects Liability Period 0% 1 day Fri 21/12/12 Fri 21/12/12
270 Settle Final Account with Client & Sub Contractors 0% 10 days Mon 10/12/12 Fri 21/12/12
271 Produce & Issue 'As Built' Drawings 0% 28 days Wed 14/11/12 Fri 21/12/12
272 Key/Warranty/Certificate Compilation 0% 28 days Wed 14/11/12 Fri 21/12/12
427 days?
PRE - CONSTRUCTION PHASE
Design
Produce Structural Engineer Calculations / Design
Finalise Designs to Start Construction Phase
Statutory Approvals
Building Surveyors Independent Review of Proposed Building Licence Drawings
Design Review Period
Environmental Health Services: Septic Tank & Leach Drain
Prepare & Submit ApplicationPrepare & Submit Application
Application Review Process
Review and respond to conditions
11/04
Water Application
Prepare and Submit Water Application
Review Period
16/04
FESA
Prepare and Submit to FESA
Review Period
Complete FESA Approval
Building Licence: Workshop & Office
Prepare and Submit Application to Council
Review Period
Issue Energy Efficiency Declaration for Windows & DoorsIssue Energy Efficiency Declaration for Windows & Doors
Issue Energy Efficiency Declaration for Office (Aircon & Ventilation Systems)Issue Energy Efficiency Declaration for Office (Aircon & Ventilation Systems)
Respond to ConditionsRespond to Conditions
24/07
Prepare and Submit Application
Review Period
Approval and Undertake Works
Health & Safety
OSHE Management Plan
Issue DRAFT OSHE Management Plan to SiteIssue DRAFT OSHE Management Plan to Site
Produce FINAL OSHE Management Plan
Issue FINAL OSHE Management Plan to SiteIssue FINAL OSHE Management Plan to Site
Site Supervisor to Review & Amend OHSE documents (unt
Site Supervisor to Receive & Review Method Statements (fr
Site Supervisor to Receive & Review JSA's (from Sub Contr
Site Supervisor to review all sub contractors blue/white car
Worksafe
Notify Worksafe to the Proposed Tilt Panel WorksNotify Worksafe to the Proposed Tilt Panel Works
Date for Inspection
Procurement and Finance
Sub Contractors
Select subcontractors to gain Quotes (on-going)
Quote analysis and review (on-going)
Choose Sub Contractor to undertake works (on-going)
Civil Works (to dampen ground)
Screw Piles
Concreting and Tilt Panels
Termite Control
Electrics
PlumbingPlumbing
Air Conditioning
Mesh, insulation and Sheeting
Structural Steel Rigging
Fire Services
Internal Stud Walls / Gyprock
Tiling
Windows
Joinery
Painting
Select suppliers to supply materials (on-going)
Quote analysis and review (on-going)
Choose Supplier to undertake works (on-going)
Concrete Supply Nr. 1
Concrete Supply Nr. 2
Steel Fabricators (structural steel and Prefab Stud Walls)
Health & Safety Signage
Tiling Supply
Concrete mesh and Reo
Window Manufacturers
Roof / Wall Mesh
External Roof / Walls Insulation
Internal Walls Insulation
External Roof Office Sheeting
External Workshop Roof / Wall Sheeting
Wash Room Items (pans, soap dispensers, etc.)
CONSTRUCTION PHASE
Site Set-up
Install Site OfficeInstall Site Office
Install Toilet with Waste StorageInstall Toilet with Waste Storage
Install Storage Container
Install H&S Site Items (e.g.: Signage)Install H&S Site Items (e.g.: Signage)
Substructure: Workshop & Office
Earthworks
ClearanceClearance
Fill, compaction and level to higher levelFill, compaction and level to higher level
Survey & Peg Site
Wash down bay tanks
Excavate to reduce levels for wash down bay tanksExcavate to reduce levels for wash down bay tanks
Insert tanks and drainage pipeworkInsert tanks and drainage pipework
Concrete Foundations
Excavate to reduce levels for foundationsExcavate to reduce levels for foundations
Install screw pilesInstall screw piles
Install ReinforcementInstall Reinforcement
Place ConcretePlace Concrete
CuringCuring
Apply Termite TreatmentApply Termite Treatment
Concrete Slab
Excavate to reduce levels for slabExcavate to reduce levels for slab
Install Reinforcement and prelayInstall Reinforcement and prelay
Place concretePlace concrete
Curing
Tilt Panels
Setting out / FormworkSetting out / Formwork
Formwork and make tilt panels
Curing
Erect tilt panels
Structural Engineer Sign Off
Structural Steel
Shop Detail Dwgs & Approvals
Fabrication and hot dip galvanising
Delivery to Site
First Delivery
Second Delivery
Third Delivery
Fourth Delivery
Fifth Delivery
Erection
Sheeting
Office
Delivery of Materials to Site
Install Wire Mesh, Anticon and Roof Sheeting
Workshop
Delivery of Materials to Site
Roof Safety Access System Install
Install Wire Mesh, Anticon and Roof Sheeting
Office & Workshop
Site Measure and Drawings for Pressings (window flashings, etc.)
Manufacture
Delivery of materials to site
Install flashings
Doors (External)
Manufacture and Delivery
Install Doors and Frames
Install Glazing
Install Hardware
Install Roller Doors
Windows (External)
Tilt Panels
Site Measure
Manufacture and Delivery
Install Windows to Office
Manufacture and Delivery
Install Windows to Workshop
Internals: Workshop & Office
Prelay / Tube Out
Plumbing Pre Set
Plumbing Tube Out
Electrical and Data Pre Wire
Installation of Air Conditioning Ducting
Internal Cladding (Gyprock)
Materials Delivery
65mm Stud Wall Erection
75mm thick Stud Wall Manufacture and Delivery
75mm Stud Wall Erection
Gyprock to Walls Install
Ceiling Batten Install
Final Fit Off
Electrical Fit off
Electrical Fixture Installation
Electrical Appliance Installation
Plumbing Fit off
Delivery of Cubicles to Site
Install Toilet Cubicles
Plumbing Fixture Installation
Mechanical Fit off
Hydraulic (AirCon) Fitoff
Internal Doors & Windows
Delivery of Doors and Windows
Install doors and frames
Install Glazing
Installation of Door & Window Hardware
Carpentry
Delivery of Materials to Site
Cabinetworks/Benches/Tables
Skirting
Finishes
Floor Finishes
Delivery of tiles to site
Tiling
Painting
Delivery of Paint to Site
Painting
Externals
Civil Works
Form Concrete Foundations
Form Retaining Wall Panels
Insert Retaining Wall Panels
Civil Works
Pour concrete pads
Install Tanks
Civil Works
Install pump house, hydrants and pipework
Pressure Test and Certify
Parking Area
Base Preparation
Bitumen
Kerbing
Line Marking
Landscaping
Civil Works and Concrete Stormwater Tanks and Run Off
Reticulation
Paving
Plants/Shrubs
Civil Works
Insert pipework
Test and certify
Backfill
Insert Septic System
Notify EHS of installed Works (prior to back fill) Note: Lead-in time not known
On site Inspection by EHS
Test and certify
Backfill
Other
Fencing
Signage
Preliminary Practical Completion
Force Equipment Inspection
Rectifications
Building Surveyors Report and rectification
POST CONSTRUCTION PHASE
Client Inspection and Hand Over
Demob from Site
Start 12 Month Defects Liability Period
Settle Final Account with Client & Sub Contractors
Produce & Issue 'As Built' Drawings
Key/Warranty/Certificate Compilation
T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F
23 Jan '12 6 Feb '12 20 Feb '12 5 Mar '12 19 Mar '12 2 Apr '12 16 Apr '12 30 Apr '12 14 May '12 28 May '12 11 Jun '12 25 Jun '12 9 Jul '12 23 Jul '12 6 Aug '12 20 Aug '12 3 Sep '12 17 Sep '12 1 Oct '12 15 Oct '12 29 Oct '12 12 Nov '12 26 Nov '12 10 Dec '12 24 Dec '12 7 Jan '13 21 Jan '13
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Progress
Deadline
PERTHMETRO ERECTION OF WORKSHOP & OFFICE AND EXTERNAL WORKS
PROGRAM REV 01
FORCE EQUIPMENT - WEDGEFIELD
Page 1
Project: Force Wedgefield - Workshop
Date: Sun 16/09/12

More Related Content

Similar to program

Northwestern AU+Automation Timeline REV6 6-15-12
Northwestern AU+Automation Timeline REV6  6-15-12Northwestern AU+Automation Timeline REV6  6-15-12
Northwestern AU+Automation Timeline REV6 6-15-12Bin Kallan
 
Engineering Design Center Project Schedule
Engineering Design Center Project ScheduleEngineering Design Center Project Schedule
Engineering Design Center Project ScheduleVirginia Kam
 
Performance Analaysis - Earned Value Analysis
Performance Analaysis - Earned Value AnalysisPerformance Analaysis - Earned Value Analysis
Performance Analaysis - Earned Value AnalysisDeborah Obasogie
 
Rehoboth Beach City Hall Construction Schedule
Rehoboth Beach City Hall Construction ScheduleRehoboth Beach City Hall Construction Schedule
Rehoboth Beach City Hall Construction Schedulerehobothbeachde
 
Proposed Implementation Schedule for Chint.pdf
Proposed Implementation Schedule for Chint.pdfProposed Implementation Schedule for Chint.pdf
Proposed Implementation Schedule for Chint.pdfMarkGeraldCuadra1
 
Town School for Boys Master Schedule
Town School for Boys Master ScheduleTown School for Boys Master Schedule
Town School for Boys Master ScheduleMKThink Strategy
 
Pilkinton tenant improvement schedule
Pilkinton tenant improvement schedulePilkinton tenant improvement schedule
Pilkinton tenant improvement scheduleTylerShisler
 
Carolinas Core Lab BCI Timeline - Rev 4 12-08-14
Carolinas Core Lab BCI Timeline - Rev 4  12-08-14Carolinas Core Lab BCI Timeline - Rev 4  12-08-14
Carolinas Core Lab BCI Timeline - Rev 4 12-08-14Bin Kallan
 
Carolinas Core Lab BCI Timeline - Rev 4 12-08-14
Carolinas Core Lab BCI Timeline - Rev 4  12-08-14Carolinas Core Lab BCI Timeline - Rev 4  12-08-14
Carolinas Core Lab BCI Timeline - Rev 4 12-08-14Bin Kallan
 
ADCO Time plan.pdf
ADCO Time plan.pdfADCO Time plan.pdf
ADCO Time plan.pdfabdo badr
 
Sample_Project Template - 6 0 - Infrastructure Effort
Sample_Project Template - 6 0 - Infrastructure EffortSample_Project Template - 6 0 - Infrastructure Effort
Sample_Project Template - 6 0 - Infrastructure EffortKevin C. McCormack, PMP
 
Weekly Progress.521-67
Weekly Progress.521-67Weekly Progress.521-67
Weekly Progress.521-67Usama Athar
 
Engineering and Permitting Schedule
Engineering and Permitting ScheduleEngineering and Permitting Schedule
Engineering and Permitting ScheduleHonolulu Civil Beat
 

Similar to program (19)

Northwestern AU+Automation Timeline REV6 6-15-12
Northwestern AU+Automation Timeline REV6  6-15-12Northwestern AU+Automation Timeline REV6  6-15-12
Northwestern AU+Automation Timeline REV6 6-15-12
 
Popop
PopopPopop
Popop
 
Engineering Design Center Project Schedule
Engineering Design Center Project ScheduleEngineering Design Center Project Schedule
Engineering Design Center Project Schedule
 
MS Projects - 10 MW Implementation Schedule
MS Projects - 10 MW Implementation ScheduleMS Projects - 10 MW Implementation Schedule
MS Projects - 10 MW Implementation Schedule
 
Performance Analaysis - Earned Value Analysis
Performance Analaysis - Earned Value AnalysisPerformance Analaysis - Earned Value Analysis
Performance Analaysis - Earned Value Analysis
 
Rehoboth Beach City Hall Construction Schedule
Rehoboth Beach City Hall Construction ScheduleRehoboth Beach City Hall Construction Schedule
Rehoboth Beach City Hall Construction Schedule
 
Proposed Implementation Schedule for Chint.pdf
Proposed Implementation Schedule for Chint.pdfProposed Implementation Schedule for Chint.pdf
Proposed Implementation Schedule for Chint.pdf
 
Town School for Boys Master Schedule
Town School for Boys Master ScheduleTown School for Boys Master Schedule
Town School for Boys Master Schedule
 
Pilkinton tenant improvement schedule
Pilkinton tenant improvement schedulePilkinton tenant improvement schedule
Pilkinton tenant improvement schedule
 
network diagram.pdf
network diagram.pdfnetwork diagram.pdf
network diagram.pdf
 
Man cave
Man caveMan cave
Man cave
 
CPM
CPMCPM
CPM
 
Carolinas Core Lab BCI Timeline - Rev 4 12-08-14
Carolinas Core Lab BCI Timeline - Rev 4  12-08-14Carolinas Core Lab BCI Timeline - Rev 4  12-08-14
Carolinas Core Lab BCI Timeline - Rev 4 12-08-14
 
Carolinas Core Lab BCI Timeline - Rev 4 12-08-14
Carolinas Core Lab BCI Timeline - Rev 4  12-08-14Carolinas Core Lab BCI Timeline - Rev 4  12-08-14
Carolinas Core Lab BCI Timeline - Rev 4 12-08-14
 
ADCO Time plan.pdf
ADCO Time plan.pdfADCO Time plan.pdf
ADCO Time plan.pdf
 
Sample_Project Template - 6 0 - Infrastructure Effort
Sample_Project Template - 6 0 - Infrastructure EffortSample_Project Template - 6 0 - Infrastructure Effort
Sample_Project Template - 6 0 - Infrastructure Effort
 
Test
TestTest
Test
 
Weekly Progress.521-67
Weekly Progress.521-67Weekly Progress.521-67
Weekly Progress.521-67
 
Engineering and Permitting Schedule
Engineering and Permitting ScheduleEngineering and Permitting Schedule
Engineering and Permitting Schedule
 

More from grahamelanders

Roof replacement and internal remedial works
Roof replacement and internal remedial worksRoof replacement and internal remedial works
Roof replacement and internal remedial worksgrahamelanders
 
Consultancy case studies
Consultancy case studiesConsultancy case studies
Consultancy case studiesgrahamelanders
 
Johnson Controls case studies - Commercial Project Management
Johnson Controls case studies - Commercial Project ManagementJohnson Controls case studies - Commercial Project Management
Johnson Controls case studies - Commercial Project Managementgrahamelanders
 
Freelance project management residential
Freelance project management residentialFreelance project management residential
Freelance project management residentialgrahamelanders
 
Freelance project management residential
Freelance project management residentialFreelance project management residential
Freelance project management residentialgrahamelanders
 
Freelance project management case studies - residential
Freelance project management case studies - residentialFreelance project management case studies - residential
Freelance project management case studies - residentialgrahamelanders
 
Freelance project management commercial - Case Study
Freelance project management commercial - Case StudyFreelance project management commercial - Case Study
Freelance project management commercial - Case Studygrahamelanders
 
Johnson controls case study consultancy
Johnson controls case study   consultancyJohnson controls case study   consultancy
Johnson controls case study consultancygrahamelanders
 

More from grahamelanders (14)

Roof replacement and internal remedial works
Roof replacement and internal remedial worksRoof replacement and internal remedial works
Roof replacement and internal remedial works
 
Surrey education
Surrey educationSurrey education
Surrey education
 
Perth metro
Perth metroPerth metro
Perth metro
 
Consultancy case studies
Consultancy case studiesConsultancy case studies
Consultancy case studies
 
Johnson Controls case studies - Commercial Project Management
Johnson Controls case studies - Commercial Project ManagementJohnson Controls case studies - Commercial Project Management
Johnson Controls case studies - Commercial Project Management
 
Upload
UploadUpload
Upload
 
Freelance project management residential
Freelance project management residentialFreelance project management residential
Freelance project management residential
 
Freelance project management residential
Freelance project management residentialFreelance project management residential
Freelance project management residential
 
Freelance project management case studies - residential
Freelance project management case studies - residentialFreelance project management case studies - residential
Freelance project management case studies - residential
 
Freelance project management commercial - Case Study
Freelance project management commercial - Case StudyFreelance project management commercial - Case Study
Freelance project management commercial - Case Study
 
Johnson controls case study consultancy
Johnson controls case study   consultancyJohnson controls case study   consultancy
Johnson controls case study consultancy
 
Upload
UploadUpload
Upload
 
PerthMetro Case Study
PerthMetro Case StudyPerthMetro Case Study
PerthMetro Case Study
 
PerthMetro case study
PerthMetro case studyPerthMetro case study
PerthMetro case study
 

Recently uploaded

M3M The Line Brochure - Premium Investment Opportunity for Commercial Ventures
M3M The Line Brochure - Premium Investment Opportunity for Commercial VenturesM3M The Line Brochure - Premium Investment Opportunity for Commercial Ventures
M3M The Line Brochure - Premium Investment Opportunity for Commercial Venturessheltercareglobal
 
Maha Mauka Squarefeet Brochure |Maha Mauka Squarefeet PDF Brochure|
Maha Mauka Squarefeet Brochure |Maha Mauka Squarefeet PDF Brochure|Maha Mauka Squarefeet Brochure |Maha Mauka Squarefeet PDF Brochure|
Maha Mauka Squarefeet Brochure |Maha Mauka Squarefeet PDF Brochure|AkshayJoshi575980
 
Shapoorji Pallonji Joyville Vista Pune | Spend Your Family Time Together
Shapoorji Pallonji Joyville Vista Pune | Spend Your Family Time TogetherShapoorji Pallonji Joyville Vista Pune | Spend Your Family Time Together
Shapoorji Pallonji Joyville Vista Pune | Spend Your Family Time Togetheraidasheikh47
 
3D Architectural Rendering Company by Panoram CGI
3D Architectural Rendering Company by Panoram CGI3D Architectural Rendering Company by Panoram CGI
3D Architectural Rendering Company by Panoram CGIPanoram CGI
 
M3M 129 E Brochure Noida Expressway, Sector 129, Noida
M3M 129 E Brochure Noida Expressway, Sector 129, NoidaM3M 129 E Brochure Noida Expressway, Sector 129, Noida
M3M 129 E Brochure Noida Expressway, Sector 129, Noidasarak0han45400
 
9711199012 Call {Girls Delhi} Very Low rate Vaishali DownLoad PDF
9711199012 Call {Girls Delhi} Very Low rate Vaishali DownLoad PDF9711199012 Call {Girls Delhi} Very Low rate Vaishali DownLoad PDF
9711199012 Call {Girls Delhi} Very Low rate Vaishali DownLoad PDFMs Riya
 
Kohinoor Flats In Hinjewadi Phase 2 | Homes Built To Suit Your Needs
Kohinoor Flats In Hinjewadi Phase 2 | Homes Built To Suit Your NeedsKohinoor Flats In Hinjewadi Phase 2 | Homes Built To Suit Your Needs
Kohinoor Flats In Hinjewadi Phase 2 | Homes Built To Suit Your Needsaidasheikh47
 
Kolte Patil Kharadi Pune E Brochure.pdf
Kolte Patil Kharadi Pune E  Brochure.pdfKolte Patil Kharadi Pune E  Brochure.pdf
Kolte Patil Kharadi Pune E Brochure.pdfabbu831446
 
Girls in Kalyanpuri }Delhi↫8447779280↬Escort Service. In Delhi NCR
Girls in Kalyanpuri }Delhi↫8447779280↬Escort Service. In Delhi NCRGirls in Kalyanpuri }Delhi↫8447779280↬Escort Service. In Delhi NCR
Girls in Kalyanpuri }Delhi↫8447779280↬Escort Service. In Delhi NCRasmaqueen5
 
Telibagh & Call Girls Lucknow - 450+ Call Girl Cash Payment 🎂 8923113531 🎪 Ne...
Telibagh & Call Girls Lucknow - 450+ Call Girl Cash Payment 🎂 8923113531 🎪 Ne...Telibagh & Call Girls Lucknow - 450+ Call Girl Cash Payment 🎂 8923113531 🎪 Ne...
Telibagh & Call Girls Lucknow - 450+ Call Girl Cash Payment 🎂 8923113531 🎪 Ne...gurkirankumar98700
 
Call Girls In Hari Nagar Dadb Block {8447779280}Hari Nagar {West Delhi Escort...
Call Girls In Hari Nagar Dadb Block {8447779280}Hari Nagar {West Delhi Escort...Call Girls In Hari Nagar Dadb Block {8447779280}Hari Nagar {West Delhi Escort...
Call Girls In Hari Nagar Dadb Block {8447779280}Hari Nagar {West Delhi Escort...asmaqueen5
 
Call girls in new Ashok NagarDelhi꧁ 8447779280꧂ Escort Service Women Seeking ...
Call girls in new Ashok NagarDelhi꧁ 8447779280꧂ Escort Service Women Seeking ...Call girls in new Ashok NagarDelhi꧁ 8447779280꧂ Escort Service Women Seeking ...
Call girls in new Ashok NagarDelhi꧁ 8447779280꧂ Escort Service Women Seeking ...asmaqueen5
 
9990771857 Call Girls in Dwarka Sector 1 Delhi (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 1 Delhi (Call Girls) Delhi9990771857 Call Girls in Dwarka Sector 1 Delhi (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 1 Delhi (Call Girls) Delhidelhimodel235
 
Call Girls in Noida Sector 13 Noida 💯Call Us 🔝 9582086666 🔝 South Delhi Escor...
Call Girls in Noida Sector 13 Noida 💯Call Us 🔝 9582086666 🔝 South Delhi Escor...Call Girls in Noida Sector 13 Noida 💯Call Us 🔝 9582086666 🔝 South Delhi Escor...
Call Girls in Noida Sector 13 Noida 💯Call Us 🔝 9582086666 🔝 South Delhi Escor...delhimodel235
 
9990771857 Call Girls in Dwarka Sector 6 Delhi (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 6 Delhi (Call Girls) Delhi9990771857 Call Girls in Dwarka Sector 6 Delhi (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 6 Delhi (Call Girls) Delhidelhimodel235
 
Call Girls In Laxmi Nagar Delhi +91-8447779280! !Best Woman Seeking Man Escor...
Call Girls In Laxmi Nagar Delhi +91-8447779280! !Best Woman Seeking Man Escor...Call Girls In Laxmi Nagar Delhi +91-8447779280! !Best Woman Seeking Man Escor...
Call Girls In Laxmi Nagar Delhi +91-8447779280! !Best Woman Seeking Man Escor...asmaqueen5
 
Call Girls In Vasant Vihar Delhi 💯Call Us 🔝8264348440🔝
Call Girls In Vasant Vihar Delhi 💯Call Us 🔝8264348440🔝Call Girls In Vasant Vihar Delhi 💯Call Us 🔝8264348440🔝
Call Girls In Vasant Vihar Delhi 💯Call Us 🔝8264348440🔝soniya singh
 
Greater Vancouver Realtors Statistics Package April 2024
Greater Vancouver Realtors Statistics Package April 2024Greater Vancouver Realtors Statistics Package April 2024
Greater Vancouver Realtors Statistics Package April 2024VickyAulakh1
 
Purva Soukhyam in Guduvancheri Chennai.pdf
Purva Soukhyam in Guduvancheri Chennai.pdfPurva Soukhyam in Guduvancheri Chennai.pdf
Purva Soukhyam in Guduvancheri Chennai.pdfpritika141199
 
FULL ENJOY 🔝 8264348440 🔝 Call Girls in DLF phase 3 | Gurgaon
FULL ENJOY 🔝 8264348440 🔝 Call Girls in DLF phase 3 | GurgaonFULL ENJOY 🔝 8264348440 🔝 Call Girls in DLF phase 3 | Gurgaon
FULL ENJOY 🔝 8264348440 🔝 Call Girls in DLF phase 3 | Gurgaonsoniya singh
 

Recently uploaded (20)

M3M The Line Brochure - Premium Investment Opportunity for Commercial Ventures
M3M The Line Brochure - Premium Investment Opportunity for Commercial VenturesM3M The Line Brochure - Premium Investment Opportunity for Commercial Ventures
M3M The Line Brochure - Premium Investment Opportunity for Commercial Ventures
 
Maha Mauka Squarefeet Brochure |Maha Mauka Squarefeet PDF Brochure|
Maha Mauka Squarefeet Brochure |Maha Mauka Squarefeet PDF Brochure|Maha Mauka Squarefeet Brochure |Maha Mauka Squarefeet PDF Brochure|
Maha Mauka Squarefeet Brochure |Maha Mauka Squarefeet PDF Brochure|
 
Shapoorji Pallonji Joyville Vista Pune | Spend Your Family Time Together
Shapoorji Pallonji Joyville Vista Pune | Spend Your Family Time TogetherShapoorji Pallonji Joyville Vista Pune | Spend Your Family Time Together
Shapoorji Pallonji Joyville Vista Pune | Spend Your Family Time Together
 
3D Architectural Rendering Company by Panoram CGI
3D Architectural Rendering Company by Panoram CGI3D Architectural Rendering Company by Panoram CGI
3D Architectural Rendering Company by Panoram CGI
 
M3M 129 E Brochure Noida Expressway, Sector 129, Noida
M3M 129 E Brochure Noida Expressway, Sector 129, NoidaM3M 129 E Brochure Noida Expressway, Sector 129, Noida
M3M 129 E Brochure Noida Expressway, Sector 129, Noida
 
9711199012 Call {Girls Delhi} Very Low rate Vaishali DownLoad PDF
9711199012 Call {Girls Delhi} Very Low rate Vaishali DownLoad PDF9711199012 Call {Girls Delhi} Very Low rate Vaishali DownLoad PDF
9711199012 Call {Girls Delhi} Very Low rate Vaishali DownLoad PDF
 
Kohinoor Flats In Hinjewadi Phase 2 | Homes Built To Suit Your Needs
Kohinoor Flats In Hinjewadi Phase 2 | Homes Built To Suit Your NeedsKohinoor Flats In Hinjewadi Phase 2 | Homes Built To Suit Your Needs
Kohinoor Flats In Hinjewadi Phase 2 | Homes Built To Suit Your Needs
 
Kolte Patil Kharadi Pune E Brochure.pdf
Kolte Patil Kharadi Pune E  Brochure.pdfKolte Patil Kharadi Pune E  Brochure.pdf
Kolte Patil Kharadi Pune E Brochure.pdf
 
Girls in Kalyanpuri }Delhi↫8447779280↬Escort Service. In Delhi NCR
Girls in Kalyanpuri }Delhi↫8447779280↬Escort Service. In Delhi NCRGirls in Kalyanpuri }Delhi↫8447779280↬Escort Service. In Delhi NCR
Girls in Kalyanpuri }Delhi↫8447779280↬Escort Service. In Delhi NCR
 
Telibagh & Call Girls Lucknow - 450+ Call Girl Cash Payment 🎂 8923113531 🎪 Ne...
Telibagh & Call Girls Lucknow - 450+ Call Girl Cash Payment 🎂 8923113531 🎪 Ne...Telibagh & Call Girls Lucknow - 450+ Call Girl Cash Payment 🎂 8923113531 🎪 Ne...
Telibagh & Call Girls Lucknow - 450+ Call Girl Cash Payment 🎂 8923113531 🎪 Ne...
 
Call Girls In Hari Nagar Dadb Block {8447779280}Hari Nagar {West Delhi Escort...
Call Girls In Hari Nagar Dadb Block {8447779280}Hari Nagar {West Delhi Escort...Call Girls In Hari Nagar Dadb Block {8447779280}Hari Nagar {West Delhi Escort...
Call Girls In Hari Nagar Dadb Block {8447779280}Hari Nagar {West Delhi Escort...
 
Call girls in new Ashok NagarDelhi꧁ 8447779280꧂ Escort Service Women Seeking ...
Call girls in new Ashok NagarDelhi꧁ 8447779280꧂ Escort Service Women Seeking ...Call girls in new Ashok NagarDelhi꧁ 8447779280꧂ Escort Service Women Seeking ...
Call girls in new Ashok NagarDelhi꧁ 8447779280꧂ Escort Service Women Seeking ...
 
9990771857 Call Girls in Dwarka Sector 1 Delhi (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 1 Delhi (Call Girls) Delhi9990771857 Call Girls in Dwarka Sector 1 Delhi (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 1 Delhi (Call Girls) Delhi
 
Call Girls in Noida Sector 13 Noida 💯Call Us 🔝 9582086666 🔝 South Delhi Escor...
Call Girls in Noida Sector 13 Noida 💯Call Us 🔝 9582086666 🔝 South Delhi Escor...Call Girls in Noida Sector 13 Noida 💯Call Us 🔝 9582086666 🔝 South Delhi Escor...
Call Girls in Noida Sector 13 Noida 💯Call Us 🔝 9582086666 🔝 South Delhi Escor...
 
9990771857 Call Girls in Dwarka Sector 6 Delhi (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 6 Delhi (Call Girls) Delhi9990771857 Call Girls in Dwarka Sector 6 Delhi (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 6 Delhi (Call Girls) Delhi
 
Call Girls In Laxmi Nagar Delhi +91-8447779280! !Best Woman Seeking Man Escor...
Call Girls In Laxmi Nagar Delhi +91-8447779280! !Best Woman Seeking Man Escor...Call Girls In Laxmi Nagar Delhi +91-8447779280! !Best Woman Seeking Man Escor...
Call Girls In Laxmi Nagar Delhi +91-8447779280! !Best Woman Seeking Man Escor...
 
Call Girls In Vasant Vihar Delhi 💯Call Us 🔝8264348440🔝
Call Girls In Vasant Vihar Delhi 💯Call Us 🔝8264348440🔝Call Girls In Vasant Vihar Delhi 💯Call Us 🔝8264348440🔝
Call Girls In Vasant Vihar Delhi 💯Call Us 🔝8264348440🔝
 
Greater Vancouver Realtors Statistics Package April 2024
Greater Vancouver Realtors Statistics Package April 2024Greater Vancouver Realtors Statistics Package April 2024
Greater Vancouver Realtors Statistics Package April 2024
 
Purva Soukhyam in Guduvancheri Chennai.pdf
Purva Soukhyam in Guduvancheri Chennai.pdfPurva Soukhyam in Guduvancheri Chennai.pdf
Purva Soukhyam in Guduvancheri Chennai.pdf
 
FULL ENJOY 🔝 8264348440 🔝 Call Girls in DLF phase 3 | Gurgaon
FULL ENJOY 🔝 8264348440 🔝 Call Girls in DLF phase 3 | GurgaonFULL ENJOY 🔝 8264348440 🔝 Call Girls in DLF phase 3 | Gurgaon
FULL ENJOY 🔝 8264348440 🔝 Call Girls in DLF phase 3 | Gurgaon
 

program

  • 1. ID Task Name % Complete Duration Start Finish Predecessors 0 Force Wedgefield - Workshop, Office & Externals 61% 427 days? Thu 5/05/11 Fri 21/12/12 1 2 PRE - CONSTRUCTION PHASE 79% 427 days? Thu 5/05/11 Fri 21/12/12 3 Quote 100% 47 days? Tue 12/07/11 Wed 14/09/11 4 Receive Scope of Works from Force Equipment 100% 1 day Tue 12/07/11 Tue 12/07/11 5 PM LTD to Submit Final Quote (Rev1) 100% 1 day Wed 31/08/11 Wed 31/08/114 6 PM LTD to Submit Budget Estimate for Additional Office Floor 100% 1 day? Wed 14/09/11 Wed 14/09/115 7 Contract 100% 1 day Mon 31/10/11 Mon 31/10/11 8 PM LTD & Force Equipment to Sign Contract (simple works) 100% 1 day Mon 31/10/11 Mon 31/10/11 9 Design 100% 293 days Thu 5/05/11 Mon 18/06/12 10 Produce Landscaping Drawings 100% 6 days Wed 28/09/11 Wed 5/10/11 11 Produce Workshop & Office Drawings 100% 15 days Thu 5/05/11 Wed 25/05/11 12 Produce Store Drawings 100% 15 days Thu 5/05/11 Wed 25/05/11 13 Produce Structural Engineer Calculations / Design 100% 65 days Tue 3/01/12 Mon 2/04/12 14 Soil Investigation Report 100% 1 day Wed 1/06/11 Wed 1/06/11 15 Finalise Designs to Start Construction Phase 100% 11 days Mon 4/06/12 Mon 18/06/12 16 Specification Completion 100% 1 day Wed 26/10/11 Wed 26/10/11 17 Statutory Approvals 84% 408 days Wed 25/05/11 Fri 14/12/12 18 Development Approval: Workshop & Office 100% 22 days Wed 25/05/11 Thu 23/06/11 19 Prepare Application 100% 1 day Wed 25/05/11 Wed 25/05/1111,12 20 Submission to Council 100% 1 day Wed 25/05/11 Wed 25/05/1119 21 Review Period 100% 21 days Thu 26/05/11 Thu 23/06/11 20 22 Approval 100% 0 days Wed 22/06/11 Wed 22/06/1121 23 Development Approval: Landscaping Plan 100% 29 days Thu 6/10/11 Wed 16/11/11 24 Prepare Application 100% 7 days Thu 6/10/11 Fri 14/10/11 10 25 Submission to Council 100% 1 day Mon 17/10/11 Mon 17/10/11 24 26 Review Period 100% 21 days Tue 18/10/11 Tue 15/11/1125 27 Approval 100% 0 days Wed 16/11/11 Wed 16/11/1126 28 Building Surveyors Independent Review of Proposed Building Licence Drawings 100% 46 days Thu 17/11/11 Fri 20/01/12 29 Selection, Negotiations and Appointment 100% 20 days Thu 17/11/11 Wed 14/12/1127 30 Design Review Period 100% 26 days Thu 15/12/11 Thu 19/01/12 29 31 Issue of Comments 100% 0 days Fri 20/01/12 Fri 20/01/12 30 32 Environmental Health Services: Septic Tank & Leach Drain 100% 57 days Mon 23/01/12 Wed 11/04/12 33 Prepare & Submit Application 100% 21 days Mon 23/01/12 Mon 20/02/12 31 34 Application Review Process 100% 36 days Tue 21/02/12 Tue 10/04/12 33 35 Review and respond to conditions 100% 1 day Wed 29/02/12 Wed 29/02/12 36 Approval 100% 0 days Wed 11/04/12 Wed 11/04/1234,35 37 Water Application 100% 11 days Mon 2/04/12 Mon 16/04/12 38 Prepare and Submit Water Application 100% 3 days Mon 2/04/12 Wed 4/04/12 39 Review Period 100% 8 days Thu 5/04/12 Mon 16/04/12 38 40 Approval 100% 0 days Mon 16/04/12 Mon 16/04/12 39 41 FESA 100% 55 days Wed 1/02/12 Wed 18/04/12 42 Prepare and Submit to FESA 100% 16 days Wed 1/02/12 Wed 22/02/12 43 Review Period 100% 39 days Thu 23/02/12 Tue 17/04/12 42 44 Submit Confirmation of Building Classification to FESA 100% 1 day Wed 11/04/12 Wed 11/04/12 45 Approval 100% 0 days Wed 18/04/12 Wed 18/04/12 44,43 46 Building Licence: Workshop & Office 100% 81 days Mon 2/04/12 Tue 24/07/12 47 Prepare and Submit Application to Council 100% 12 days Mon 2/04/12 Tue 17/04/12 48 Review Period 100% 70 days Tue 17/04/12 Mon 23/07/12 47 49 Issue Energy Efficiency Declaration for Windows & Doors 100% 1 day Mon 14/05/12 Mon 14/05/12 50 Issue Energy Efficiency Declaration for Office (Aircon & Ventilation Systems) 100% 1 day Tue 12/06/12 Tue 12/06/12 51 Respond to Conditions 100% 1 day Thu 14/06/12 Thu 14/06/12 52 Building License Approval (permit nr. 10714) 100% 0 days Tue 24/07/12 Tue 24/07/12 48,49,50,51 53 Horizon Power 34% 95 days Mon 6/08/12 Fri 14/12/12 54 Prepare and Submit Application 100% 19 days Mon 6/08/12 Thu 30/08/12 55 Review Period 20% 66 days Fri 31/08/12 Fri 30/11/12 54 56 Approval and Undertake Works 0% 10 days Mon 3/12/12 Fri 14/12/12 55 57 Health & Safety 50% 130 days Mon 25/06/12 Fri 21/12/12 58 OSHE Management Plan 47% 125 days Mon 2/07/12 Fri 21/12/12 59 Issue DRAFT OSHE Management Plan to Site 100% 1 day Mon 2/07/12 Mon 2/07/12 60 Produce FINAL OSHE Management Plan 100% 21 days Tue 3/07/12 Tue 31/07/12 59 61 Issue FINAL OSHE Management Plan to Site 100% 1 day Wed 1/08/12 Wed 1/08/12 60 62 Site Supervisor to Review & Amend OHSE documents (until end of project) 35% 102 days Thu 2/08/12 Fri 21/12/12 61 63 Method Statements, JSA's and Workers Documents 50% 130 days Mon 25/06/12 Fri 21/12/12 64 Site Supervisor to Receive & Review Method Statements (from sub contractors - until end of project) 50% 130 days Mon 25/06/12 Fri 21/12/12 65 Site Supervisor to Receive & Review JSA's (from Sub Contractors - until end of project) 50% 130 days Mon 25/06/12 Fri 21/12/12 66 Site Supervisor to review all sub contractors blue/white cards, licences, etc. (until end of project) 50% 130 days Mon 25/06/12 Fri 21/12/12 67 Worksafe 100% 26 days Tue 3/07/12 Tue 7/08/12 68 Notify Worksafe to the Proposed Tilt Panel Works 100% 1 day Tue 3/07/12 Tue 3/07/12 69 Date for Inspection 100% 2 days Mon 6/08/12 Tue 7/08/12 68 70 Procurement and Finance 95% 120 days Mon 16/04/12 Sat 29/09/12 71 Sub Contractors 96% 120 days Mon 16/04/12 Sat 29/09/12 72 Select subcontractors to gain Quotes (on-going) 100% 81 days Tue 22/05/12 Tue 11/09/12 73 Quote analysis and review (on-going) 100% 81 days Tue 22/05/12 Tue 11/09/12 74 Choose Sub Contractor to undertake works (on-going) 100% 81 days Tue 22/05/12 Tue 11/09/12 75 Work Packages and Purchase Orders 76% 121 days Mon 16/04/12 Sat 29/09/12 76 Civil Works (to dampen ground) 100% 1 day Fri 20/07/12 Fri 20/07/12 77 Screw Piles 100% 1 day Tue 29/05/12 Tue 29/05/12 78 Concreting and Tilt Panels 100% 4 days Tue 3/07/12 Fri 6/07/12 79 Termite Control 100% 1 day Tue 17/07/12 Tue 17/07/12 80 Electrics 100% 3 days Mon 9/07/12 Wed 11/07/12 81 Plumbing 100% 3 days Thu 5/07/12 Mon 9/07/12 82 Air Conditioning 100% 3 days Tue 3/07/12 Thu 5/07/12 83 Mesh, insulation and Sheeting 100% 5 days Wed 29/08/12 Tue 4/09/12 84 Structural Steel Rigging 100% 3 days Thu 23/08/12 Mon 27/08/12 85 Fire Services 100% 3 days Wed 29/08/12 Fri 31/08/12 86 Internal Stud Walls / Gyprock 100% 3 days Wed 5/09/12 Fri 7/09/12 87 Tiling 100% 1 day Mon 30/07/12 Mon 30/07/12 88 Windows 100% 1 day Mon 3/09/12 Mon 3/09/12 89 Joinery 0% 5 days Mon 17/09/12 Fri 21/09/12 90 Painting 0% 5 days Mon 17/09/12 Fri 21/09/12 91 Suppliers 95% 117 days Thu 19/04/12 Fri 28/09/12 92 Select suppliers to supply materials (on-going) 95% 117 days Thu 19/04/12 Fri 28/09/12 93 Quote analysis and review (on-going) 95% 117 days Thu 19/04/12 Fri 28/09/12 94 Choose Supplier to undertake works (on-going) 95% 117 days Thu 19/04/12 Fri 28/09/12 95 Issue Purchase Orders 85% 109 days Thu 19/04/12 Tue 18/09/12 96 Concrete Supply Nr. 1 100% 1 day Thu 19/04/12 Thu 19/04/12 97 Concrete Supply Nr. 2 100% 1 day Mon 25/06/12 Mon 25/06/12 98 Steel Fabricators (structural steel and Prefab Stud Walls) 100% 1 day Fri 13/07/12 Fri 13/07/12 99 Health & Safety Signage 100% 1 day Tue 17/07/12 Tue 17/07/12 100 Tiling Supply 100% 1 day Tue 24/07/12 Tue 24/07/12 101 Concrete mesh and Reo 100% 1 day Tue 24/07/12 Tue 24/07/12 102 Window Manufacturers 100% 1 day Mon 3/09/12 Mon 3/09/12 103 Roof / Wall Mesh 100% 1 day Wed 12/09/12 Wed 12/09/12 104 External Roof / Walls Insulation 100% 1 day Wed 12/09/12 Wed 12/09/12 105 Internal Walls Insulation 100% 1 day Wed 12/09/12 Wed 12/09/12 106 External Roof Office Sheeting 100% 1 day Wed 12/09/12 Wed 12/09/12 107 External Workshop Roof / Wall Sheeting 0% 1 day Tue 18/09/12 Tue 18/09/12 108 Wash Room Items (pans, soap dispensers, etc.) 0% 1 day Tue 18/09/12 Tue 18/09/12 109 110 111 CONSTRUCTION PHASE 22% 130 days? Mon 25/06/12 Fri 21/12/12 112 Site Set-up 100% 2 days Mon 25/06/12 Tue 26/06/12 113 Install Site Office 100% 2 days Mon 25/06/12 Tue 26/06/12 114 Install Toilet with Waste Storage 100% 2 days Mon 25/06/12 Tue 26/06/12 115 Install Storage Container 100% 2 days Mon 25/06/12 Tue 26/06/12 116 Install H&S Site Items (e.g.: Signage) 100% 2 days Mon 25/06/12 Tue 26/06/12 117 118 Substructure: Workshop & Office 100% 24 days Wed 27/06/12 Mon 30/07/12 119 Earthworks 100% 6 days Wed 27/06/12 Wed 4/07/12 120 Clearance 100% 1 day Wed 27/06/12 Wed 27/06/12 113,114,115,116 121 Fill, compaction and level to higher level 100% 4 days Thu 28/06/12 Tue 3/07/12 120 122 Survey & Peg Site 100% 1 day Wed 4/07/12 Wed 4/07/12 121 123 Wash down bay tanks 100% 1 day Thu 5/07/12 Thu 5/07/12 124 Excavate to reduce levels for wash down bay tanks 100% 1 day Thu 5/07/12 Thu 5/07/12 122 125 Insert tanks and drainage pipework 100% 1 day Thu 5/07/12 Thu 5/07/12 122 126 Concrete Foundations 100% 7 days Thu 5/07/12 Fri 13/07/12 127 Excavate to reduce levels for foundations 100% 1 day Thu 5/07/12 Thu 5/07/12 122 128 Install screw piles 100% 2 days Thu 5/07/12 Fri 6/07/12 122 129 Install Reinforcement 100% 2 days Thu 5/07/12 Fri 6/07/12 122 130 Place Concrete 100% 2 days Thu 5/07/12 Fri 6/07/12 122 131 Curing 100% 5 days Fri 6/07/12 Thu 12/07/12 130 132 Apply Termite Treatment 100% 1 day Fri 13/07/12 Fri 13/07/12 131 133 Concrete Slab 100% 11 days Mon 16/07/12 Mon 30/07/12 134 Excavate to reduce levels for slab 100% 1 day Mon 16/07/12 Mon 16/07/12 132 135 Install Reinforcement and prelay 100% 4 days Tue 17/07/12 Fri 20/07/12 134 136 Place concrete 100% 2 days Mon 23/07/12 Tue 24/07/12 135 137 Curing 100% 4 days Wed 25/07/12 Mon 30/07/12 136 138 Super Structure: Workshop & Office 43% 79 days Mon 30/07/12 Thu 15/11/12 139 Tilt Panels 84% 40 days Mon 30/07/12 Fri 21/09/12 140 Setting out / Formwork 100% 5 days Mon 30/07/12 Fri 3/08/12 137 141 Formwork and make tilt panels 100% 10 days Mon 6/08/12 Wed 22/08/12 140 142 Curing 100% 10 days Thu 23/08/12 Wed 5/09/12 141 143 Erect tilt panels 100% 2 days Thu 6/09/12 Fri 7/09/12 142 144 Structural Engineer Sign Off 0% 5 days Mon 17/09/12 Fri 21/09/12 143 145 Structural Steel 85% 45 days Mon 30/07/12 Fri 28/09/12 146 Shop Detail Dwgs & Approvals 100% 5 days Mon 30/07/12 Fri 3/08/12 147 Fabrication and hot dip galvanising 100% 30 days Mon 6/08/12 Fri 14/09/12 146 148 Delivery to Site 80% 22 days Tue 21/08/12 Wed 19/09/12 149 First Delivery 100% 3 days Tue 21/08/12 Thu 23/08/12 150 Second Delivery 100% 3 days Fri 24/08/12 Tue 28/08/12 151 Third Delivery 100% 3 days Fri 31/08/12 Tue 4/09/12 152 Fourth Delivery 100% 3 days Tue 4/09/12 Thu 6/09/12 153 Fifth Delivery 0% 3 days Mon 17/09/12 Wed 19/09/12 154 Erection 55% 15 days Mon 10/09/12 Fri 28/09/12 149,150,151,152,153 155 Sheeting 0% 44 days Mon 17/09/12 Thu 15/11/12 156 Office 0% 8 days Mon 17/09/12 Wed 26/09/12 157 Delivery of Materials to Site 0% 3 days Mon 17/09/12 Wed 19/09/12 158 Install Wire Mesh, Anticon and Roof Sheeting 0% 5 days Thu 20/09/12 Wed 26/09/12 157 159 Workshop 0% 40 days Mon 17/09/12 Fri 9/11/12 160 Delivery of Materials to Site 0% 3 days Mon 17/09/12 Wed 19/09/12 161 Roof Safety Access System Install 0% 5 days Thu 20/09/12 Wed 26/09/12 160 162 Install Wire Mesh, Anticon and Roof Sheeting 0% 37 days Thu 20/09/12 Fri 9/11/12 160 163 Office & Workshop 0% 19 days Mon 22/10/12 Thu 15/11/12 164 Site Measure and Drawings for Pressings (window flashings, etc.) 0% 3 days Mon 22/10/12 Wed 24/10/12 165 Manufacture 0% 10 days Thu 25/10/12 Wed 7/11/12164 166 Delivery of materials to site 0% 3 days Thu 8/11/12 Mon 12/11/12 165 167 Install flashings 0% 3 days Tue 13/11/12 Thu 15/11/12 166 168 Doors (External) 0% 23 days Mon 24/09/12 Wed 24/10/12 169 Manufacture and Delivery 0% 15 days Mon 24/09/12 Fri 12/10/12 170 Install Doors and Frames 0% 3 days Mon 15/10/12 Wed 17/10/12 169 171 Install Glazing 0% 2 days Thu 18/10/12 Fri 19/10/12 170 172 Install Hardware 0% 3 days Mon 22/10/12 Wed 24/10/12 171 173 Install Roller Doors 0% 8 days Mon 15/10/12 Wed 24/10/12 169 174 Windows (External) 54% 18 days Mon 10/09/12 Wed 3/10/12 175 Tilt Panels 50% 18 days Mon 10/09/12 Wed 3/10/12 176 Site Measure 100% 1 day Mon 10/09/12 Mon 10/09/12 177 Manufacture and Delivery 80% 10 days Tue 11/09/12 Mon 24/09/12 176 178 Install Windows to Office 0% 7 days Tue 25/09/12 Wed 3/10/12 177 179 Workshop 57% 17 days Tue 11/09/12 Wed 3/10/12 180 Manufacture and Delivery 98% 10 days Tue 11/09/12 Mon 24/09/12 181 Install Windows to Workshop 0% 7 days Tue 25/09/12 Wed 3/10/12 180 182 Internals: Workshop & Office 2% 49 days Tue 11/09/12 Fri 16/11/12 183 Prelay / Tube Out 0% 16 days Fri 21/09/12 Fri 12/10/12 184 Plumbing Pre Set 0% 6 days Fri 21/09/12 Fri 28/09/12 185 Plumbing Tube Out 0% 4 days Mon 1/10/12 Thu 4/10/12 184 186 Electrical and Data Pre Wire 0% 4 days Mon 1/10/12 Thu 4/10/12 187 Installation of Air Conditioning Ducting 0% 5 days Mon 8/10/12 Fri 12/10/12 188 Internal Cladding (Gyprock) 6% 38 days Tue 11/09/12 Thu 1/11/12 189 Materials Delivery 0% 3 days Mon 24/09/12 Wed 26/09/12 190 65mm Stud Wall Erection 0% 10 days Thu 27/09/12 Wed 10/10/12 189 191 75mm thick Stud Wall Manufacture and Delivery 18% 28 days Tue 11/09/12 Thu 18/10/12 192 75mm Stud Wall Erection 0% 5 days Mon 24/09/12 Fri 28/09/12 191 193 Gyprock to Walls Install 0% 20 days Fri 5/10/12 Thu 1/11/12 192,185,186 194 Ceiling Batten Install 0% 20 days Fri 5/10/12 Thu 1/11/12 192,185,186 195 Final Fit Off 0% 28 days Wed 10/10/12 Fri 16/11/12 196 Electrical Fit off 0% 10 days Mon 5/11/12 Fri 16/11/12 197 Electrical Fixture Installation 0% 10 days Mon 5/11/12 Fri 16/11/12 198 Electrical Appliance Installation 0% 10 days Mon 5/11/12 Fri 16/11/12 199 Plumbing Fit off 0% 10 days Mon 29/10/12 Fri 9/11/12 200 Delivery of Cubicles to Site 0% 5 days Mon 29/10/12 Fri 2/11/12 201 Install Toilet Cubicles 0% 5 days Mon 5/11/12 Fri 9/11/12 200 202 Plumbing Fixture Installation 0% 5 days Mon 5/11/12 Fri 9/11/12 200 203 Mechanical Fit off 0% 2 days Fri 9/11/12 Mon 12/11/12 204 Hydraulic (AirCon) Fitoff 0% 2 days Fri 9/11/12 Mon 12/11/12 205 Internal Doors & Windows 0% 18 days Wed 10/10/12 Fri 2/11/12 206 Delivery of Doors and Windows 0% 3 days Wed 10/10/12 Fri 12/10/12 207 Install doors and frames 0% 5 days Mon 15/10/12 Fri 19/10/12 208 Install Glazing 0% 5 days Mon 22/10/12 Fri 26/10/12 207 209 Installation of Door & Window Hardware 0% 5 days Mon 29/10/12 Fri 2/11/12 208 210 Carpentry 0% 8 days Fri 12/10/12 Tue 23/10/12 211 Delivery of Materials to Site 0% 3 days Fri 12/10/12 Tue 16/10/12 212 Cabinetworks/Benches/Tables 0% 5 days Wed 17/10/12 Tue 23/10/12 211 213 Skirting 0% 5 days Wed 17/10/12 Tue 23/10/12 211 214 Finishes 0% 28 days Mon 8/10/12 Wed 14/11/12 215 Floor Finishes 0% 20 days Mon 8/10/12 Fri 2/11/12 216 Delivery of tiles to site 0% 3 days Mon 8/10/12 Wed 10/10/12 217 Tiling 0% 17 days Thu 11/10/12 Fri 2/11/12 216 218 Painting 0% 13 days Mon 29/10/12 Wed 14/11/12 219 Delivery of Paint to Site 0% 3 days Mon 29/10/12 Wed 31/10/12 220 Painting 0% 10 days Thu 1/11/12 Wed 14/11/12219 221 Externals 0% 96 days? Fri 3/08/12 Fri 14/12/12 222 Retaining Wall 0% 19 days? Fri 3/08/12 Wed 29/08/12 223 Civil Works 0% 3 days Fri 3/08/12 Tue 7/08/12 224 Form Concrete Foundations 0% 10 days Wed 8/08/12 Tue 21/08/12 223 225 Form Retaining Wall Panels 0% 5 days Wed 22/08/12 Tue 28/08/12 224 226 Insert Retaining Wall Panels 0% 1 day? Wed 29/08/12 Wed 29/08/12 225 227 Fire Services (FESA) 0% 38 days Wed 19/09/12 Fri 9/11/12 228 Fire Tanks 0% 28 days Wed 19/09/12 Fri 26/10/12 229 Civil Works 0% 3 days Wed 19/09/12 Fri 21/09/12 230 Pour concrete pads 0% 6 days Mon 24/09/12 Mon 1/10/12 229 231 Install Tanks 0% 10 days Mon 15/10/12 Fri 26/10/12 230 232 Hydrants and Pump House 0% 20 days Mon 15/10/12 Fri 9/11/12 233 Civil Works 0% 5 days Mon 15/10/12 Fri 19/10/12 234 Install pump house, hydrants and pipework 0% 10 days Mon 22/10/12 Fri 2/11/12 233 235 Pressure Test and Certify 0% 5 days Mon 5/11/12 Fri 9/11/12 234 236 Parking Area 0% 15 days Fri 9/11/12 Thu 29/11/12 237 Base Preparation 0% 3 days Fri 9/11/12 Tue 13/11/12 238 Bitumen 0% 10 days Wed 14/11/12 Tue 27/11/12237 239 Kerbing 0% 10 days Wed 14/11/12 Tue 27/11/12237 240 Line Marking 0% 2 days Wed 28/11/12 Thu 29/11/12 238,239 241 Landscaping 0% 15 days Mon 26/11/12 Fri 14/12/12 242 Civil Works and Concrete Stormwater Tanks and Run Off 0% 15 days Mon 26/11/12 Fri 14/12/12 243 Reticulation 0% 15 days Mon 26/11/12 Fri 14/12/12 244 Paving 0% 15 days Mon 26/11/12 Fri 14/12/12 245 Plants/Shrubs 0% 15 days Mon 26/11/12 Fri 14/12/12 246 Hydraulics and Septic System inc. testing and certifying 0% 9 days? Mon 5/11/12 Thu 15/11/12 247 Civil Works 0% 5 days Mon 5/11/12 Fri 9/11/12 248 Drainage 0% 3 days? Mon 12/11/12 Wed 14/11/12 249 Insert pipework 0% 1 day? Mon 12/11/12 Mon 12/11/12 247 250 Test and certify 0% 1 day? Tue 13/11/12 Tue 13/11/12249 251 Backfill 0% 1 day? Wed 14/11/12 Wed 14/11/12250 252 Septic System 0% 4 days? Mon 12/11/12 Thu 15/11/12 253 Insert Septic System 0% 1 day? Mon 12/11/12 Mon 12/11/12 247 254 Notify EHS of installed Works (prior to back fill) Note: Lead-in time not known 0% 1 day? Mon 12/11/12 Mon 12/11/12 247 255 On site Inspection by EHS 0% 1 day? Tue 13/11/12 Tue 13/11/12253 256 Test and certify 0% 1 day? Wed 14/11/12 Wed 14/11/12255 257 Backfill 0% 1 day? Thu 15/11/12 Thu 15/11/12 256 258 Other 0% 10 days Mon 26/11/12 Fri 7/12/12 259 Fencing 0% 10 days Mon 26/11/12 Fri 7/12/12 260 Signage 0% 1 day Mon 3/12/12 Mon 3/12/12 261 Preliminary Practical Completion 0% 15 days Mon 3/12/12 Fri 21/12/12 262 Force Equipment Inspection 0% 1 day Fri 14/12/12 Fri 14/12/12 263 Rectifications 0% 5 days Mon 17/12/12 Fri 21/12/12 262 264 Building Surveyors Report and rectification 0% 15 days Mon 3/12/12 Fri 21/12/12 265 266 POST CONSTRUCTION PHASE 0% 28 days Wed 14/11/12 Fri 21/12/12 267 Client Inspection and Hand Over 0% 1 day Fri 21/12/12 Fri 21/12/12 268 Demob from Site 0% 1 day Fri 21/12/12 Fri 21/12/12 269 Start 12 Month Defects Liability Period 0% 1 day Fri 21/12/12 Fri 21/12/12 270 Settle Final Account with Client & Sub Contractors 0% 10 days Mon 10/12/12 Fri 21/12/12 271 Produce & Issue 'As Built' Drawings 0% 28 days Wed 14/11/12 Fri 21/12/12 272 Key/Warranty/Certificate Compilation 0% 28 days Wed 14/11/12 Fri 21/12/12 427 days? PRE - CONSTRUCTION PHASE Design Produce Structural Engineer Calculations / Design Finalise Designs to Start Construction Phase Statutory Approvals Building Surveyors Independent Review of Proposed Building Licence Drawings Design Review Period Environmental Health Services: Septic Tank & Leach Drain Prepare & Submit ApplicationPrepare & Submit Application Application Review Process Review and respond to conditions 11/04 Water Application Prepare and Submit Water Application Review Period 16/04 FESA Prepare and Submit to FESA Review Period Complete FESA Approval Building Licence: Workshop & Office Prepare and Submit Application to Council Review Period Issue Energy Efficiency Declaration for Windows & DoorsIssue Energy Efficiency Declaration for Windows & Doors Issue Energy Efficiency Declaration for Office (Aircon & Ventilation Systems)Issue Energy Efficiency Declaration for Office (Aircon & Ventilation Systems) Respond to ConditionsRespond to Conditions 24/07 Prepare and Submit Application Review Period Approval and Undertake Works Health & Safety OSHE Management Plan Issue DRAFT OSHE Management Plan to SiteIssue DRAFT OSHE Management Plan to Site Produce FINAL OSHE Management Plan Issue FINAL OSHE Management Plan to SiteIssue FINAL OSHE Management Plan to Site Site Supervisor to Review & Amend OHSE documents (unt Site Supervisor to Receive & Review Method Statements (fr Site Supervisor to Receive & Review JSA's (from Sub Contr Site Supervisor to review all sub contractors blue/white car Worksafe Notify Worksafe to the Proposed Tilt Panel WorksNotify Worksafe to the Proposed Tilt Panel Works Date for Inspection Procurement and Finance Sub Contractors Select subcontractors to gain Quotes (on-going) Quote analysis and review (on-going) Choose Sub Contractor to undertake works (on-going) Civil Works (to dampen ground) Screw Piles Concreting and Tilt Panels Termite Control Electrics PlumbingPlumbing Air Conditioning Mesh, insulation and Sheeting Structural Steel Rigging Fire Services Internal Stud Walls / Gyprock Tiling Windows Joinery Painting Select suppliers to supply materials (on-going) Quote analysis and review (on-going) Choose Supplier to undertake works (on-going) Concrete Supply Nr. 1 Concrete Supply Nr. 2 Steel Fabricators (structural steel and Prefab Stud Walls) Health & Safety Signage Tiling Supply Concrete mesh and Reo Window Manufacturers Roof / Wall Mesh External Roof / Walls Insulation Internal Walls Insulation External Roof Office Sheeting External Workshop Roof / Wall Sheeting Wash Room Items (pans, soap dispensers, etc.) CONSTRUCTION PHASE Site Set-up Install Site OfficeInstall Site Office Install Toilet with Waste StorageInstall Toilet with Waste Storage Install Storage Container Install H&S Site Items (e.g.: Signage)Install H&S Site Items (e.g.: Signage) Substructure: Workshop & Office Earthworks ClearanceClearance Fill, compaction and level to higher levelFill, compaction and level to higher level Survey & Peg Site Wash down bay tanks Excavate to reduce levels for wash down bay tanksExcavate to reduce levels for wash down bay tanks Insert tanks and drainage pipeworkInsert tanks and drainage pipework Concrete Foundations Excavate to reduce levels for foundationsExcavate to reduce levels for foundations Install screw pilesInstall screw piles Install ReinforcementInstall Reinforcement Place ConcretePlace Concrete CuringCuring Apply Termite TreatmentApply Termite Treatment Concrete Slab Excavate to reduce levels for slabExcavate to reduce levels for slab Install Reinforcement and prelayInstall Reinforcement and prelay Place concretePlace concrete Curing Tilt Panels Setting out / FormworkSetting out / Formwork Formwork and make tilt panels Curing Erect tilt panels Structural Engineer Sign Off Structural Steel Shop Detail Dwgs & Approvals Fabrication and hot dip galvanising Delivery to Site First Delivery Second Delivery Third Delivery Fourth Delivery Fifth Delivery Erection Sheeting Office Delivery of Materials to Site Install Wire Mesh, Anticon and Roof Sheeting Workshop Delivery of Materials to Site Roof Safety Access System Install Install Wire Mesh, Anticon and Roof Sheeting Office & Workshop Site Measure and Drawings for Pressings (window flashings, etc.) Manufacture Delivery of materials to site Install flashings Doors (External) Manufacture and Delivery Install Doors and Frames Install Glazing Install Hardware Install Roller Doors Windows (External) Tilt Panels Site Measure Manufacture and Delivery Install Windows to Office Manufacture and Delivery Install Windows to Workshop Internals: Workshop & Office Prelay / Tube Out Plumbing Pre Set Plumbing Tube Out Electrical and Data Pre Wire Installation of Air Conditioning Ducting Internal Cladding (Gyprock) Materials Delivery 65mm Stud Wall Erection 75mm thick Stud Wall Manufacture and Delivery 75mm Stud Wall Erection Gyprock to Walls Install Ceiling Batten Install Final Fit Off Electrical Fit off Electrical Fixture Installation Electrical Appliance Installation Plumbing Fit off Delivery of Cubicles to Site Install Toilet Cubicles Plumbing Fixture Installation Mechanical Fit off Hydraulic (AirCon) Fitoff Internal Doors & Windows Delivery of Doors and Windows Install doors and frames Install Glazing Installation of Door & Window Hardware Carpentry Delivery of Materials to Site Cabinetworks/Benches/Tables Skirting Finishes Floor Finishes Delivery of tiles to site Tiling Painting Delivery of Paint to Site Painting Externals Civil Works Form Concrete Foundations Form Retaining Wall Panels Insert Retaining Wall Panels Civil Works Pour concrete pads Install Tanks Civil Works Install pump house, hydrants and pipework Pressure Test and Certify Parking Area Base Preparation Bitumen Kerbing Line Marking Landscaping Civil Works and Concrete Stormwater Tanks and Run Off Reticulation Paving Plants/Shrubs Civil Works Insert pipework Test and certify Backfill Insert Septic System Notify EHS of installed Works (prior to back fill) Note: Lead-in time not known On site Inspection by EHS Test and certify Backfill Other Fencing Signage Preliminary Practical Completion Force Equipment Inspection Rectifications Building Surveyors Report and rectification POST CONSTRUCTION PHASE Client Inspection and Hand Over Demob from Site Start 12 Month Defects Liability Period Settle Final Account with Client & Sub Contractors Produce & Issue 'As Built' Drawings Key/Warranty/Certificate Compilation T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F 23 Jan '12 6 Feb '12 20 Feb '12 5 Mar '12 19 Mar '12 2 Apr '12 16 Apr '12 30 Apr '12 14 May '12 28 May '12 11 Jun '12 25 Jun '12 9 Jul '12 23 Jul '12 6 Aug '12 20 Aug '12 3 Sep '12 17 Sep '12 1 Oct '12 15 Oct '12 29 Oct '12 12 Nov '12 26 Nov '12 10 Dec '12 24 Dec '12 7 Jan '13 21 Jan '13 Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Progress Deadline PERTHMETRO ERECTION OF WORKSHOP & OFFICE AND EXTERNAL WORKS PROGRAM REV 01 FORCE EQUIPMENT - WEDGEFIELD Page 1 Project: Force Wedgefield - Workshop Date: Sun 16/09/12