ROY HILL BULK
EARTHWORKS &
CONCRETE PACKAGECLIENT
Samsung C&T
PROJECT
Roy Hill Concrete and
Earthworks
LOCATION
Pilbara, Western Australia
VALUE
AU $200 million
COMMENCED
April 2014
COMPLETED
Scheduled for June 2015
PROJECT SUMMARY
The proposed scope of works includes Concrete and detailed
Earthworks for the Iron Ore Processing Plant, Stockyard,
Overland Conveyors and Crushing areas.
Specific works to be undertaken include:
•	 53,000cm of structural concrete
•	 800,000cm of backfill/excavations
•	 15km of underground piping
•	 5km of Rail works for the Stackers and Reclaimers.
The project has a duration of twelve months commencing
in April 2014 with manning on site estimated to peak at 660
personnel.
PFS-C077 Current

More Related Content

What's hot (20)

IRON SAND
IRON SANDIRON SAND
IRON SAND
 
CV Bernard Graves
CV Bernard GravesCV Bernard Graves
CV Bernard Graves
 
Resume_updated 2014
Resume_updated 2014Resume_updated 2014
Resume_updated 2014
 
Rudy Wick Resume
Rudy Wick ResumeRudy Wick Resume
Rudy Wick Resume
 
Ainley & Associates
Ainley & AssociatesAinley & Associates
Ainley & Associates
 
Huntingdonshire Regional college Refurbishment
Huntingdonshire Regional college RefurbishmentHuntingdonshire Regional college Refurbishment
Huntingdonshire Regional college Refurbishment
 
CV_WeifnegLi_2016
CV_WeifnegLi_2016CV_WeifnegLi_2016
CV_WeifnegLi_2016
 
2014 CRW - Omega Morgan Rigging Job of the Year
2014 CRW - Omega Morgan Rigging Job of the Year2014 CRW - Omega Morgan Rigging Job of the Year
2014 CRW - Omega Morgan Rigging Job of the Year
 
Dale Lochhead Resume
Dale Lochhead  Resume Dale Lochhead  Resume
Dale Lochhead Resume
 
RESUME RAJBIR SINGH (1)
RESUME RAJBIR SINGH (1)RESUME RAJBIR SINGH (1)
RESUME RAJBIR SINGH (1)
 
Len Platten-CV
Len Platten-CVLen Platten-CV
Len Platten-CV
 
Potomac Place Shopping Center
Potomac Place Shopping CenterPotomac Place Shopping Center
Potomac Place Shopping Center
 
Client Presentation
Client PresentationClient Presentation
Client Presentation
 
Bics Recycling Facility
Bics Recycling FacilityBics Recycling Facility
Bics Recycling Facility
 
CV Shahid L. Malik, August 2015
CV  Shahid L. Malik, August 2015CV  Shahid L. Malik, August 2015
CV Shahid L. Malik, August 2015
 
Project - Nammuldi Mining and Ore Haulage
Project - Nammuldi Mining and Ore HaulageProject - Nammuldi Mining and Ore Haulage
Project - Nammuldi Mining and Ore Haulage
 
Wankhede nomination 31-08-2013
Wankhede nomination   31-08-2013Wankhede nomination   31-08-2013
Wankhede nomination 31-08-2013
 
project proposal takunda mubaiwa
project proposal takunda mubaiwaproject proposal takunda mubaiwa
project proposal takunda mubaiwa
 
Tristan Rhodes LCBB Slides
Tristan Rhodes LCBB SlidesTristan Rhodes LCBB Slides
Tristan Rhodes LCBB Slides
 
NAVI MUMBAI SPECIAL ECONOMIC ZONE
NAVI MUMBAI SPECIAL ECONOMIC ZONENAVI MUMBAI SPECIAL ECONOMIC ZONE
NAVI MUMBAI SPECIAL ECONOMIC ZONE
 

Project - Roy Hill Bulk Earthworks and Concrete Package

  • 1. ROY HILL BULK EARTHWORKS & CONCRETE PACKAGECLIENT Samsung C&T PROJECT Roy Hill Concrete and Earthworks LOCATION Pilbara, Western Australia VALUE AU $200 million COMMENCED April 2014 COMPLETED Scheduled for June 2015 PROJECT SUMMARY The proposed scope of works includes Concrete and detailed Earthworks for the Iron Ore Processing Plant, Stockyard, Overland Conveyors and Crushing areas. Specific works to be undertaken include: • 53,000cm of structural concrete • 800,000cm of backfill/excavations • 15km of underground piping • 5km of Rail works for the Stackers and Reclaimers. The project has a duration of twelve months commencing in April 2014 with manning on site estimated to peak at 660 personnel. PFS-C077 Current