1. CURRICULUM VITAE
PERSONAL DATA
Name: Teitei Fidelis
Date of Birth: 5th
June 1978
Contact Address: No. 1 Niger Cat Road behind Blue Water Hotel
Ekpan-Warri
Tel: 08130281581, 07087266316, 08078662960
Email: f.teitei@yahoo.com
Religion: Christian
Place of Birth: Lagos
Nationality: Nigeria
State of Origin: Delta
INSTITUTION ATTENDED WITH QUALIFICATION:
AmbroseAli University (B.Eng) Mechanical Engineering Second Class Upper 2003-2008
Ekpan Secondary School(SSCE) 1991-1997
Army Day Primary School(FSLC) 1985-1990
PROFESSIONAL QUALIFICATION
Certifiedwelding inspector with CSWIP 3.1 cert No. 77086 TWI registered
American Society for Non Destructive Testing (ASNT) level II INUT, MT, PT, FL and RT
Helicopter underwater escape (HUET & BOSIET)
Survivalat sea (SAS)
SPDC HSELEVEL III supervision course
Confined SpaceTraining
Permit to work awareness (PTW)
Computer literate MS word and excel.
Chevron Incidentand Injury FreeCourse.
ISO 9001, 2000 compliance
Fire and Safety Training.
OffshoreSurvivalTraining.
Good Knowledgeof Chevron Nig Ltd Specifications.
2. PROFESSIONAL WORKAND EXPERIENCE:
COMPANY: Applust RTD Quality ServicesQAQC inspector Warri 2010-2012.
Project: 20”& 10”EGP 3A pipe line Okan-MejiPipeline construction Escravos.
Review and proposeWPS for the facility piping.
Review and update inspection and test plans,
Record of all quality control carried out sub contractors
Update welding performancelog
Supervisethe overall QA/QCactivities on site and base
Develop projectquality plan when required
Reply all technical queries
InterpretISO/Alignmentsheetdrawing
PrepareAudit report
Supervises valveto flange alignment and all fitting
Monitor, investigate, identify and resolveproject quality issues.
Preparepre commissioning documents and supervision
Review Radiographic film interpretation and signing Of NDTreports
Review /update applicable procedure
COMPANY:Adamac Groupof companies
WORK EXPERIENCE:
Position: WELDING INSPECTOR (2007-2008)
Project: Escravos Gas line construction
Crawler operator, darkroomtechnician and film interpreter.
Also carry out die pen and magnetic particle inspection.
Supervision of PWHTand documentation
Execution of Onsite Assessmentof IndividualFlanged Joints.
Development of Joint Integrity AssessmentProcedures and FlangeManagement
Procedure.
Development of Joint/Flange Integrity AssessmentPrograms.
Development and Population of Joint Integrity AssessmentRecords.
Joint/ Flange Integrity Verification.
3. PressureTesting Of Valves and Spools.
Documentation of project daily reports.
Issuanceof NCRand CAR
Carry out material inspection both pipe and plate.
Daily visualinspection, preparing welding reports and NDE request
Monitor NDT application whether required as per project specification
Inspection of fabrication and welding works in project covering structuralsteel/piping in
accordancewith AWS D1 1. ASME B31.3
Prepare/review of WPS
Conduct/supervises welder qualification test (WQT)
Supervises valveto flange alignment
Prepareaudit reports.
NDT documentation and request
Attending weekly QCmeetings with client
Carry out punch list inspection prior to commissioning of gas turbine
Review and recommends replies to projectchange request.
Carry out inspection on the inter-connecting piping of turbine.
COMPANY:oceaneering (2005-2007) NDT/QC inspector (OCTG) (ASNTlevelII- MT, PT, RT &
UT)
WORK EXPERIENCE:
Inspection of fabrication and welding works in project covering structuralsteel in
accordancewith AWS D1.1 ASMEB31.3 API 1104
Prepare/review of WPS
Update welders performancelog
Supervises theoverall OA/QCactivities on site and base
Develop projectquality plan when required
Review and update projectITP
Reply all technical queries.
InterpretISO/Alignmentsheetdrawing
Prepareaudit report
Supervises valveto flange alignment, pipe flange alignment and all fittings.
Monitor, investigate, identify and resolveproject issues.
Review Radiographic films interpretation and signing of NDT reports.
Preparedimensional checks reports.
Review record of internal and external audit performed by various contractors
4. Review sub-contractors invoicetime sheet
Supervises all sub contractors’ QA/QCrelated jobs.
Carry out visualwelding inspection before, during and after welding 24”, 12 “pipes and
structuralwelding.
Supervision of piping operation.
Supervision of all piping equipment installation as per installation procedures.
Supervises tie-in Hook-up operations as per WPS
Review all inspectors’ daily reports and prepareQA/QCweekly and monthly reports.
Conducts and supervises welders qualification Test ( WQT) and procedurequalification
Test (PQT)
IssueNCR
Develop and monitor electrode control/consumablelog.
Review/update applicable procedures.
COMPANY:APPLUS RTD WARRI QAQCINSPECTOR 2008-2010
Field integration projectpiping/sub-sea pipeline Oron west-south wellhead platform Addax
offshore
WORK EXPERIENCE:
Carryoutwelding inspection on the production of manifolds.
Inspects fabricated spools and flanges before fit up and welding as per drawing and
codes and standard.
Check for pipe and flange alignment and valveto flange alignment.
Review and update applicable WPS.
Review and document NDT, welders’ qualification and equipment and calibration
certificates.
Review and updates inspection and Test plan (ITP)
Preparewelders performancelog.
PrepareAudit report at site.
InterpretISO drawings
Supervises touch up and painting in accordanceto painting procedures.
PrepareNDE request and documentation.
Preparedaily visual reports, weld summary reports and traceability reports.
Supervises field coating inspection on the sub-sea tie in spools
Supervises welder qualification test (WOT)
Supervises PWHTand documentation
PrepareHydro test package/supervision
5. Carry out punch list inspection before commissioning
Prepareequipment calibration log
Review and document third party qualification and certification.
Attending weekly progress meetings.
NDT documentation and request.
COMPANY Oceaneering QAQC INSPECTOR (2002-004)
Projectfabrication of platform manifold, Jacket legs, Flare Bums Bridges etc. for chevron
WORK EXPERIENCE
Review of fittings and installation plan (Rigging) plan for pre-fabrication structures
assemblies and pipes.
Review approved ISO drawings.
Check materials specs on board.
Check for mechanical damage, lamination and condition.
Supervises and review pressuretestexercise.
Assigns numbers to the spools (pipe number, heat and spool numbers)
Check for spoolorientation and elevation
Check for pipe to pipe alignment.
Checks for spool to flange alignment.
Check for valve and equipment alignment.
Check for valve and equipment installation.
Review piping instrumental drawings (P&IDs)
Develop weld map drawing for QCdepartment.
Develop all engineering procedures.
Advice the detailed Design contractor’s piping and related equipment activities with
respect to: Equipment data sheet completeness and accuracy, piping and related
equipment engineering studies and analysis, inspection and test plan.
Providetiming review of contractor’s review of piping and pipeline design and
deliverables.
Review and monitor’s projectpiping engineering deliverables, vendor data and design
changes.
Prepareprogress reportlog.
Reply technical queries.
Review of sub-contractor Technicaldocuments-procedures and work plans.
Piping progress monitoring and reporting to line manager.
Review and recommend replies to projectchange requests.
Provideadequate shielding of the exposed rotating parts.
6. Keeping the engine mount/skid free fromoil, filters and debris.
Making daily reports.
Construction /installation of exhaust manifold and piping.
Rig inspection and auditing.
Carry out inspection during rigging up and down.
Interpretation of rig as built drawing.
Inspection of rig Songa Tellus (offshore)
Inspection of Stana Tay (Offshore)
Inspection of rig 101 NRG rig
Safety training
SPDC HSE level III supervision course
IIF (incidental& injury free) courseby Chevron Nigeria limited.
OffshoreSafety Training (Huet and Bosiet)
Confined SpaceTraining
PTW Awareness.
HYUNDAI AUG 2013 - MARCH 2015
POSITION QA/QC inspector.
PROJECT DSO SONAM/MEREMGGCP NWP CHEVRON.
Prepare/review of WPS
Review of contingency plan with NDT crew.
Review of radiation safety procedurewith all NDTcrew.
Answer all technical queries
Ensureall NDT personneldeployed for NDT operation are classified as per
requirements.
review of structuraldrawing beforefabrication
Conduct/supervises welder qualification test (WQT)
carry out visualinspection
Prepareaudit reports.
NDT documentation and request
Review of NDT reportas per AWS D1.1 structuralcode.
Ensureall NDT equipment to be used is ok, and functional.
Ensureall NDT personnelextremely safety conscious with ionizing radiation.
Attending weekly QCmeetings with client
carry out dimensional check before and after welding
Review of all inspection document and report.
Review and recommends replies to projectchange request.
7. In depth knowledgeof Quality Assuranceand quality control, for OCTG products
manufactured (API) code.
Good technical understanding of manufacturing process to international Standard.
Inspection of fabrication and welding works in project covering structuralsteel/piping in
accordancewith AWS D1.1 ASMEB31.3
Company SGS InspectionServicesP.H March2015 –MAY 2015
PositionOCTG QA/QC INSPECTOR
Project Snepco13"/3/8 Pipe Threading WithBTC Inspector at BKTNL Onne Port Harcourt.
Inspector verified ID and OD, Drift used for test. (verified and Accepted)
Inspector verified specific Instructions for job per Snepco Instructions and API 5CT, API 5B Latest
Edition. Specs.
Inspector verifies gauges required and calibration status.
Inspect API Triangle Stamp 3/8" For conformance.
Inspect make up operation.
Inspect threaded Pipe Pin End and (Box End).
Inspector Witness 100% Thread Inspection on Pin/Box End.
Inspect Stenciling, Measurement, Dope Application And Storage.
Inspector Witness and Verified Calibration of All Inspection Gauges per Calibration Process for
Verification of Threaded Products.
Inspector Witness Full Lengths Drifting And Threading of 13-3/18" Pipes Respectively.
Inspector Witness Full Length Drifting Control and Carry out Visual Inspection.
Inspector Also Witness Coupling And Ensure Torque Values Are Maintained According To Spec.
Carry out Visual Inspection on the Couplings, Final Inspection on arm length Drifting coupling And
Ovality Check
Company SGS InspectionServicesP.H 14 June2015 –15 sep 2016
PositionOCTG QA/QC INSPECTOR
Vam Onne PH.
Inspect and WitnessedManufacturing of Vam Top 5 1/2 x20lb/ft. Vm8013cr VAMTO.
Inspect WitnessedConditioning AndEndCovers AndVerify Conditioning Reports.
Pipes Where DriftedAndLengths TakenAccordingly.
WitnessedStenciling AndToughValues, Carry Final Visual InspectionBefore LoadOut.
8. HOBBIES:
Reading
Swimming
football
REFEREE:
Mr. IvieFestus
QAQC inspector
Chevron Nigeria Ltd
07089344135
Mr Francis Amadhe
Managing Director
Applus RTD Inspection Services Warri
08033367195