SlideShare a Scribd company logo
1 of 4
Download to read offline
What is an Environmental Impact
Assessment?
Nowadays, for most dredging projects some sort of
Environmental Impact Assessment (EIA) is normally pre-
pared, often specified and required by law or regulation,
sometimes just as a part of good, modern project manage-
ment. Although no uniform standard for such an assess-
ment is universally accepted, an EIA regularly contains: an
explanation of environmental objectives and policy;
a description of the existing environmental situation (the
baseline conditions); a description of the project; an assess-
ment of the potential effects of the project; a summary
of recommendations; and an Environmental Management
(or action) Plan (EMP).
What is the purpose of an EIA?
The purpose of an EIA is to ensure that dredging activities
are performed in an environmentally acceptable manner,
use sound engineering techniques, that they are economi-
cally warranted and take sufficient consideration of long-
term effects.
	 The scope of an EIA usually includes a survey and
review of prior studies done by others to describe the physi-
cal, chemical, and biological conditions of the study area;
an evaluation of regional dredging and disposal needs; and
a characterisation of physical and chemical properties of
typical regional dredged materials. The EIA will also formu-
late alternatives for dredged material management, perform
a preliminary evaluation of alternatives management meth-
ods, and make recommendations for further evaluation.
What is the difference between an EIA,
an EIS, an EES and an ES?
There is no such thing as the Environmental Impact
Assessment, nor is there one single international organisa-
tion regulating the requirements of the EIA. EIA is often
used as a collective term, which can also refer to the
Environmental Effect Study (EES), the Environmental
Impact Study (EIS) or the Environmental Study (ES), all
indicating some sort of environmental evaluation. In some
cases the term EIA may have a formal or legal specificity,
while in other cases it is a descriptive term comparable
with the ES, the EES or the EIS.
Are EIAs only obligatory for projects
involving contaminated materials?
EIAs preceding a dredging project became obligatory in
specific cases in many industrialised countries in the 1970s,
when the environment first appeared on the political
agenda. In the beginning, the obligation was limited to
dredging projects where contaminated materials were
suspected. Later on, dredging projects with other environ-
mental considerations, for instance habitat protection,
required an EIA.
	 In the 1980s environmental and ecological consider-
ations also became part of the policies of the International
Finance Institutions (IFIs), such as the World Bank.
This was formalised in the 1990s when an EIA became a
condition for the funding of IFI-sponsored projects.
The World Bank definition of the EIA is important because
it more or less established the minimum requirements.
What is the World Bank definition
of an EIA?
In a World Bank study, the EIA is summarised as: “[…]
environmental impact assessment (EIA) is taken to mean the
systematic examination of the likely environmental conse-
quences of proposed projects. The results of the assessment
– which are assembled in a document known as an
Environmental Statement (ES) – are intended to provide
decision-makers with a balanced assessment of the environ-
mental implications of the proposed action and the alternative
examined. The ES is then used by decision-makers as a con-
tribution to the information base upon which a decision is
made. The overall goal of an EIA is to achieve better devel-
opmental interventions through protecting the environment
(human, physical and biotic).”
	 Simply said, the EIA leads to an ES and the ES ideally
results in a management directive, or Environmental
Management Plan (EMP), a plan for managing and con-
trolling the environmental effects of a project and guiding
the environmental control mechanisms.
Facts About
Environmental Impact Assessments
An Information Update from the IADC – Number 1 – 2008
Is an EIA always required?
Almost always is the short answer. Most dredging projects
will require some type of environmental study. In some
developing countries national environmental legislation
requiring an impact study is not yet in place. Nonetheless,
since almost all projects in developing countries are
(at least partly) funded by IFIs, an EIA will probably be
required. In recent years, even where compliance with IFI
guidelines may not be necessary, many project owners have
adopted a policy of corporate social responsibility and will
no longer operate without taking into account the envi-
ronmental situation.
	 In developed countries, national legislation will often
require an EIA. In fact, the requirements in most industria-
lised countries are often much more specific than the IFIs,
so before embarking on a dredging project, national legisla-
tion should always be studied to find out which legal obli-
gations are applicable. Since legislation is constantly being
renewed, finding the most up-to-date information for a
specific country or region is imperative.
At what stage of a project should an
EIA be undertaken?
The EIA should be part of the project from the start of the
project planning phase, since the EIA is the basis for the
EMP and the EMP must be fully operational as soon as the
execution or construction phase starts. The EMP is often
obligatory, but also in cases where it is not, it is considered
to be “good practice and policy” to conclude the EIA with
some sort of EMP.
What is an Environmental
Management Plan?
Technically speaking, the Environmental Management
Plan or EMP is the synthesis of the information gathered in
the EIA, incorporating the overall assessment into the
entire dredging project, from implementation to construc-
tion to execution.
	 The EMP sets out the actions for controlling, monitor-
ing and evaluating the project during every phase. The EMP
states which parameters should be measured, what the
critical values are and what actions will have to be taken
to stay within the critical boundaries.
	 The EMP often addresses mitigation measures to
­minimise adverse impacts; measures to enhance environ-
mental benefits, if such benefits occur; measures necessary
to ­guarantee effective monitoring; monitoring and auditing
programme details; and resources, funds, contractual and
management arrangements. The EMP maps out the
­processes that managers need to follow to maximise com-
pliance and minimise harm to the environment.
Does an EIA address only ecological
issues?
The European Commission describes the purpose of an
EIA in the directive EC 1985/97: “The environmental
impact assessment shall identify, describe and assess in an
appropriate manner, in the light of each individual case […]
the direct and indirect effects of a project on the following
factors:
-	 human beings, fauna and flora;
-	 soil, water, air, climate and the landscape;
-	 material assets and the cultural heritage;
-	 the interaction between the factors mentioned in the first,
second and third indents.”
	 This clearly shows that “environment” has become a
much broader concept than simply ecology. EIAs now
reach beyond assessing only possible contamination, and
now include assessing material assets and political, social
and cultural heritage. This broader view of environment
can be seen as part of the recent “sustainability move-
ment”. Other terms used to describe this concept are the
“triple bottom approach” or the 3 Ps, that is “people,
planet, profit”, meaning that social, environmental and
financial considerations must all be integrated in decision-
making processes. Most major dredging companies have
already embraced this socially responsible way of working.
What are the main steps of an EIA?
An EIA is a data management process with three compo-
nents: First, the appropriate information must be identified
and collated. Secondly, changes in environmental param-
eters resulting from the proposed project must be forecast
and compared with so-called “baseline conditions”.
Finally, the effects of the actual changes, with and without
mitigation measures in place, must be assessed and com-
municated to the decision-makers. An EIA should answer
the question: Is a project as planned environmentally
acceptable? And if not, can changes be made to mitigate
impacts, or to improve the overall project acceptability?
What are baseline conditions?
Baseline conditions describe the circumstances of the
dredging site and the potential placement site(s) prior to
the start of the project. These conditions are far from static
and part of baseline conditions should also include the
natural variability of the sites, including extreme events
like storms and long-term developments such as seasonal
influences. Collection of these data can be time-consum-
ing, but it is worth the investment. If an EIA is based
solely on average conditions then the results of a severe
storm, which may have more impact than the dredging
activities, could not be taken into account.
What other types of data should be
collected?
An EIA looks at a broad scope of effects of dredging, rang-
ing from the consequences of suspended sediments on
water quality to the consequences for local communities
with respect to their livelihoods (access to fishing grounds)
or to archaeological remains. In short, a typical EIA will
include data about physical, chemical, biological and eco-
logical impacts as well as economic, social and political
effects. Depending on the type of project (capital, mainte-
nance or remedial) and its location, these data may include
assessing flood risks, salt intrusion, turbidity, and the vul-
nerability of local marine life and habitats. In addition, an
EIA may also consider noise and air quality, aesthetics such
as landscapes and seascapes, and interactions with other
public uses of the water and adjacent land areas for recre-
ation or commerce. Each EIA must be tailored to the par-
ticular project.
Who conducts the EIA? And who
implements it?
Ideally the project owner hires independent consultants
after an open and transparent tender procedure.
These consultants are environmental engineers, who
should give an unbiased assessment which should include
an accurate sustainability appraisal, planning support, and
ecological risk assessment. Careful consideration of the
choice of a reliable consultant is crucial. In a certain cases
the project owner requires contractors to participate in the
application process for a dredging licence or permit.
Whoever conducts the EIA, the project owner is respon-
sible vis-à-vis the authorities for the implementation of
and adherence to the EIA. On the other hand, the con-
tractor will have to guarantee in the final contract that the
execution of the project will meet the standards set out in
the EMP, which is based on the EIA.
After the EIA is completed, then what?
An EIA offers a summary of the environmental issues that
became apparent, for instance, the scope of the environ-
mental impacts, the risks and/or the benefits; the signifi-
cance of these impacts, risks and/or benefits and the likely
mitigation measures required; and the actions to be taken
(and by whom!). Processes then need to be implemented
to enhance the environmental benefits of the proposed
project (this can be the re-use of the dredged material);
to ensure compliance with relevant regulations and inter-
national agreements (e.g., the DMAF or the London
Convention); to consider alternatives; to identify signifi-
cant adverse environmental effects and identify action;
to provide for public consultation and input; to define the
data assembly needs and necessary survey activities; and to
determine the predictive techniques that are to be
employed.
An initial environmental
evaluation provides a basis
for determining whether or
not to proceed with dredg-
ing. It should answer the
question, is a project as
planned environmentally
acceptable, and if not, what
can be done to improve
overall acceptability.
Initial Environmental Evaluation
If this leads to the conclusion that (mitigation) mea-
sures are necessary, these measures should be applied to the
design & planning phase (“project effects”) and/or the
construction phase (“process effects”). In the first case the
measures will probably have to be taken by the project
owner, in the second case by the contractor.
Should the public be involved?
The process of impact identification is based upon an
appreciation of how the proposed project might interact
with the environment, both in the dredging and the place-
ment sites and during the transport between the two. As
such, this requires an appreciation of what are considered
to be the valued environmental and community resources
within the vicinity of both sites. Communication with the
public about this is essential; they need to be informed and
an explanation of the assessments made should be offered.
In some cases, the public may identify additional impacts
and might ask for broader impact consideration or further
mitigation.
How can impacts be predicted?
Impacts can be predicted using logical, physical, biological
or mathematical modelling. These may identify potential
negative impacts, but also indicate options for enhance-
ment of positive impacts (e.g., the re-use of dredged mate-
rial). Once the possible impacts are identified, the project
design must be adapted to attempt to minimise the adverse
impacts and maximise the beneficial impacts. As soon as
the project design is optimised, the effects must be forecast
in different ways: The affected feature, the magnitude, the
resource and/or population, the action causing the effect,
the duration of the effect, and the proposed mitigation
(or enhancement) measures.
	 Predicted effects can be divided into short-term (less
than one week) or long-term (more than one week) effects
and near-field (less than one kilometre) or far-field (more
than one kilometre) effects, for both the dredging and
placement site and along the transport route. In general
effects created by the construction works are short term
and near field, while impacts caused by the overall project
can be far field and long term.
What are the advantages of conducting
an EIA?
A well-executed and thorough EIA can lead to cost-effec-
tive mitigation and/or enhancement. When environmen-
tal mitigation is integrated as a fundamental part of project
design, rather than as an add-on exercise, it will reduce
project costs and lower community costs. For instance,
mitigation of impacts to fauna and flora may be as simple
as planning to adhere to seasonal restrictions by dredging
during a window that does not interfere with marine life
reproduction cycles. This is not to say that the costs of
measures resulting from an EIA are lower than if no EIA
had been conducted at all. But the costs will certainly be
higher, if the plans have to be changed midstream when
the project is already underway.
	 The EIA is an important tool for project planning and
as such can minimise the risks for misunderstandings,
provide clarity about environmental implications and lead
to better cooperation between all stakeholders including
project owners, dredging contractors and the public.
For further reading and information
Bray R.N. (Editor), (2008). Environmental Aspects of Dredging.
IADC/CEDA-Taylor and Francis, London, UK.
Doorn-Groen, S.M. et al. (2007). Environmental monitoring and man-
agement of reclamation works close to sensitive habitats, Proceedings
World Dredging Congress XVIII, Lake Buena Vista, FL, USA. Also
reprinted­in Terra et Aqua, nr. 108, September 2007.
Hufschmidt et al. (1983). Environment, Natural Systems, and Development
– An Economic Valuation Guide, The John Hopkins University Press,
Baltimore, MD, USA.
Jensen, K. et al. (1998). Environmental Impact Assessment using the
Rapid Impact Assessment Matrix (RIAM). Olesen & Olesen, Fredensborg,
Denmark.
PIANC EnviCom (2006). Environmental Risk Assessment of Dredging and
Disposal Operations. Report from Working Group 10 of the Environment
Commission. International Navigation Association. Brussels, Belgium.
International Association of Dredging Companies, PO Box 80521, 2508 GM The Hague, The Netherlands
tel. +31 070 352 3334, fax +31 070 351 2654, e-mail: info@iadc-dredging.com, www.iadc-dredging.com
This brochure is presented by the International Association of Dredging
Companies whose members offer the highest quality and
professionalism in dredging and maritime construction. The information
presented here is part of an on-going effort to support clients and others
in understanding the fundamental
principles of dredging and maritime
construction.

More Related Content

What's hot

Environmental Impact Assessment
Environmental Impact AssessmentEnvironmental Impact Assessment
Environmental Impact AssessmentPrateek Bansal
 
Environmental inventory / baseline studies
Environmental inventory / baseline studiesEnvironmental inventory / baseline studies
Environmental inventory / baseline studiesSyed Javed
 
Environment impact assessment
Environment impact assessmentEnvironment impact assessment
Environment impact assessmentPramoda Raj
 
Eia a tool to conserve biodiversity
Eia a tool to conserve biodiversityEia a tool to conserve biodiversity
Eia a tool to conserve biodiversityRohina Tabassam
 
Environmental Impact Assessment
Environmental Impact AssessmentEnvironmental Impact Assessment
Environmental Impact AssessmentPrithvi Ghag
 
Tourism planning environmental impact assessment eia - rahul garg
Tourism planning  environmental impact assessment eia - rahul gargTourism planning  environmental impact assessment eia - rahul garg
Tourism planning environmental impact assessment eia - rahul gargrahul garg
 
Environment Impact Assessment
Environment Impact Assessment Environment Impact Assessment
Environment Impact Assessment Istiak Asif
 
13 environmental impact assessment
13 environmental impact assessment13 environmental impact assessment
13 environmental impact assessmentPrabha Panth
 
Unit 7 eia and sd
Unit 7 eia and sd Unit 7 eia and sd
Unit 7 eia and sd Kumar
 
ENVIRONMENTAL IMPACT ASSESSMENT - EIA
ENVIRONMENTAL IMPACT ASSESSMENT - EIAENVIRONMENTAL IMPACT ASSESSMENT - EIA
ENVIRONMENTAL IMPACT ASSESSMENT - EIASakthivel R
 
ENVIRONMENT IMPACT ASSESSMENT: CONCEPT & CHALENGES
ENVIRONMENT IMPACT ASSESSMENT:  CONCEPT & CHALENGESENVIRONMENT IMPACT ASSESSMENT:  CONCEPT & CHALENGES
ENVIRONMENT IMPACT ASSESSMENT: CONCEPT & CHALENGESAnamika Rana
 
Environment Impact Assessment: Significance, Process And Problems
Environment Impact Assessment: Significance, Process And ProblemsEnvironment Impact Assessment: Significance, Process And Problems
Environment Impact Assessment: Significance, Process And Problemsinventionjournals
 
Environment impact Assessment (EIA) in Uganda
Environment impact Assessment (EIA) in UgandaEnvironment impact Assessment (EIA) in Uganda
Environment impact Assessment (EIA) in Ugandakayondo alex
 

What's hot (20)

21000
2100021000
21000
 
Environmental Impact Assessment
Environmental Impact AssessmentEnvironmental Impact Assessment
Environmental Impact Assessment
 
Environmental inventory / baseline studies
Environmental inventory / baseline studiesEnvironmental inventory / baseline studies
Environmental inventory / baseline studies
 
Environment impact assessment
Environment impact assessmentEnvironment impact assessment
Environment impact assessment
 
Ppt 1
Ppt 1Ppt 1
Ppt 1
 
Eia a tool to conserve biodiversity
Eia a tool to conserve biodiversityEia a tool to conserve biodiversity
Eia a tool to conserve biodiversity
 
Eia pakistan perspective
Eia   pakistan perspectiveEia   pakistan perspective
Eia pakistan perspective
 
Environmental Impact Assessment
Environmental Impact AssessmentEnvironmental Impact Assessment
Environmental Impact Assessment
 
Tourism planning environmental impact assessment eia - rahul garg
Tourism planning  environmental impact assessment eia - rahul gargTourism planning  environmental impact assessment eia - rahul garg
Tourism planning environmental impact assessment eia - rahul garg
 
Environment Impact Assessment
Environment Impact Assessment Environment Impact Assessment
Environment Impact Assessment
 
EIA Introduction
EIA IntroductionEIA Introduction
EIA Introduction
 
EIA Evolution
EIA EvolutionEIA Evolution
EIA Evolution
 
13 environmental impact assessment
13 environmental impact assessment13 environmental impact assessment
13 environmental impact assessment
 
Unit 7 eia and sd
Unit 7 eia and sd Unit 7 eia and sd
Unit 7 eia and sd
 
What is EIA????
What is EIA????What is EIA????
What is EIA????
 
ENVIRONMENTAL IMPACT ASSESSMENT - EIA
ENVIRONMENTAL IMPACT ASSESSMENT - EIAENVIRONMENTAL IMPACT ASSESSMENT - EIA
ENVIRONMENTAL IMPACT ASSESSMENT - EIA
 
ENVIRONMENT IMPACT ASSESSMENT: CONCEPT & CHALENGES
ENVIRONMENT IMPACT ASSESSMENT:  CONCEPT & CHALENGESENVIRONMENT IMPACT ASSESSMENT:  CONCEPT & CHALENGES
ENVIRONMENT IMPACT ASSESSMENT: CONCEPT & CHALENGES
 
Environmental Impact Assessment
Environmental Impact AssessmentEnvironmental Impact Assessment
Environmental Impact Assessment
 
Environment Impact Assessment: Significance, Process And Problems
Environment Impact Assessment: Significance, Process And ProblemsEnvironment Impact Assessment: Significance, Process And Problems
Environment Impact Assessment: Significance, Process And Problems
 
Environment impact Assessment (EIA) in Uganda
Environment impact Assessment (EIA) in UgandaEnvironment impact Assessment (EIA) in Uganda
Environment impact Assessment (EIA) in Uganda
 

Viewers also liked

Samuel CV 2016_v4
Samuel CV 2016_v4Samuel CV 2016_v4
Samuel CV 2016_v4Samuel Tsai
 
Puste Miejsce
Puste MiejscePuste Miejsce
Puste MiejsceEwaB
 
Про проведення І-ІІ етапів конкурсу ім. Тараса Шевченка
Про проведення І-ІІ етапів конкурсу ім. Тараса ШевченкаПро проведення І-ІІ етапів конкурсу ім. Тараса Шевченка
Про проведення І-ІІ етапів конкурсу ім. Тараса ШевченкаСвітлана Тацієнко
 
Lead developer position
Lead developer positionLead developer position
Lead developer positionMark Long
 
Global Post, martes 22 de noviembre de 2016
Global Post, martes 22 de noviembre de 2016Global Post, martes 22 de noviembre de 2016
Global Post, martes 22 de noviembre de 2016Gerencia del Poder
 
Konferencja PK Koszalin 2008 - Długi ogon wyszukiwania
Konferencja PK Koszalin 2008 - Długi ogon wyszukiwaniaKonferencja PK Koszalin 2008 - Długi ogon wyszukiwania
Konferencja PK Koszalin 2008 - Długi ogon wyszukiwaniaEwaB
 
Siemens handbook of emerging technologies for learning
Siemens handbook of emerging technologies for learningSiemens handbook of emerging technologies for learning
Siemens handbook of emerging technologies for learningMinisterio de Educación
 
Количественные числительные
Количественные числительныеКоличественные числительные
Количественные числительныеNatalya Dyrda
 
The influence of feedback environment on teaching self efficacy
The influence of feedback environment on teaching self efficacyThe influence of feedback environment on teaching self efficacy
The influence of feedback environment on teaching self efficacyUniversiti Sains Malaysia
 
Уход за волосами "Овощи и пряности" GREEN PLANET
Уход за волосами "Овощи и пряности" GREEN PLANETУход за волосами "Овощи и пряности" GREEN PLANET
Уход за волосами "Овощи и пряности" GREEN PLANETGREEN PLANET
 
MÓDULO 6: EVALUACIÓN DE LA SUB RASANTE - FERNANDO SÁNCHEZ SABOGAL
MÓDULO 6: EVALUACIÓN DE LA SUB RASANTE - FERNANDO SÁNCHEZ SABOGALMÓDULO 6: EVALUACIÓN DE LA SUB RASANTE - FERNANDO SÁNCHEZ SABOGAL
MÓDULO 6: EVALUACIÓN DE LA SUB RASANTE - FERNANDO SÁNCHEZ SABOGALEmilio Castillo
 
ex special forces military human resources worldwide
ex special forces military human resources worldwideex special forces military human resources worldwide
ex special forces military human resources worldwideAgha A
 

Viewers also liked (17)

Samuel CV 2016_v4
Samuel CV 2016_v4Samuel CV 2016_v4
Samuel CV 2016_v4
 
MUHAIMINUR RAHMAN CSE
MUHAIMINUR RAHMAN CSEMUHAIMINUR RAHMAN CSE
MUHAIMINUR RAHMAN CSE
 
Puste Miejsce
Puste MiejscePuste Miejsce
Puste Miejsce
 
Про проведення І-ІІ етапів конкурсу ім. Тараса Шевченка
Про проведення І-ІІ етапів конкурсу ім. Тараса ШевченкаПро проведення І-ІІ етапів конкурсу ім. Тараса Шевченка
Про проведення І-ІІ етапів конкурсу ім. Тараса Шевченка
 
Lead developer position
Lead developer positionLead developer position
Lead developer position
 
Global Post, martes 22 de noviembre de 2016
Global Post, martes 22 de noviembre de 2016Global Post, martes 22 de noviembre de 2016
Global Post, martes 22 de noviembre de 2016
 
Konferencja PK Koszalin 2008 - Długi ogon wyszukiwania
Konferencja PK Koszalin 2008 - Długi ogon wyszukiwaniaKonferencja PK Koszalin 2008 - Długi ogon wyszukiwania
Konferencja PK Koszalin 2008 - Długi ogon wyszukiwania
 
Siemens handbook of emerging technologies for learning
Siemens handbook of emerging technologies for learningSiemens handbook of emerging technologies for learning
Siemens handbook of emerging technologies for learning
 
Количественные числительные
Количественные числительныеКоличественные числительные
Количественные числительные
 
The influence of feedback environment on teaching self efficacy
The influence of feedback environment on teaching self efficacyThe influence of feedback environment on teaching self efficacy
The influence of feedback environment on teaching self efficacy
 
Уход за волосами "Овощи и пряности" GREEN PLANET
Уход за волосами "Овощи и пряности" GREEN PLANETУход за волосами "Овощи и пряности" GREEN PLANET
Уход за волосами "Овощи и пряности" GREEN PLANET
 
Ph ys journ_17-18(309-310)
Ph ys journ_17-18(309-310)Ph ys journ_17-18(309-310)
Ph ys journ_17-18(309-310)
 
pharm
pharmpharm
pharm
 
MÓDULO 6: EVALUACIÓN DE LA SUB RASANTE - FERNANDO SÁNCHEZ SABOGAL
MÓDULO 6: EVALUACIÓN DE LA SUB RASANTE - FERNANDO SÁNCHEZ SABOGALMÓDULO 6: EVALUACIÓN DE LA SUB RASANTE - FERNANDO SÁNCHEZ SABOGAL
MÓDULO 6: EVALUACIÓN DE LA SUB RASANTE - FERNANDO SÁNCHEZ SABOGAL
 
Mikrotik API
Mikrotik APIMikrotik API
Mikrotik API
 
The Power of A Success Mindset
The Power of A Success Mindset The Power of A Success Mindset
The Power of A Success Mindset
 
ex special forces military human resources worldwide
ex special forces military human resources worldwideex special forces military human resources worldwide
ex special forces military human resources worldwide
 

Similar to Facts about-environmental-impact-assessments

Environmental impact assessment
Environmental impact assessmentEnvironmental impact assessment
Environmental impact assessmentSamanth kumar
 
BasConcept of Eic nvironmental Impact Assessment-pages-2-13,18-65.pdf
BasConcept of  Eic nvironmental Impact Assessment-pages-2-13,18-65.pdfBasConcept of  Eic nvironmental Impact Assessment-pages-2-13,18-65.pdf
BasConcept of Eic nvironmental Impact Assessment-pages-2-13,18-65.pdfTausifAhmad53
 
What is an Environmental Clearance Certificate and How to Obtain It.pdf
What is an Environmental Clearance Certificate and How to Obtain It.pdfWhat is an Environmental Clearance Certificate and How to Obtain It.pdf
What is an Environmental Clearance Certificate and How to Obtain It.pdfPranshuSharma18498
 
EIA-GeES 3112 Chapter 1.ppt Basic Concept of Environmental Impact Assessment...
EIA-GeES 3112 Chapter 1.ppt Basic Concept of  Environmental Impact Assessment...EIA-GeES 3112 Chapter 1.ppt Basic Concept of  Environmental Impact Assessment...
EIA-GeES 3112 Chapter 1.ppt Basic Concept of Environmental Impact Assessment...AbdirahmanYusufAli1
 
Environment impact assessment
Environment impact assessmentEnvironment impact assessment
Environment impact assessmentBimal Antony
 
Environmental Impact Assessment for the marine environment
Environmental Impact Assessment for the marine environmentEnvironmental Impact Assessment for the marine environment
Environmental Impact Assessment for the marine environmentDr. Felicia Chinwe Mogo
 
Environemental Impact Assessment.pptx
Environemental Impact Assessment.pptxEnvironemental Impact Assessment.pptx
Environemental Impact Assessment.pptxKalaimani
 
ENVIRONMENTAL IMPACTS ASSESMENT (EIA)
ENVIRONMENTAL  IMPACTS ASSESMENT (EIA)ENVIRONMENTAL  IMPACTS ASSESMENT (EIA)
ENVIRONMENTAL IMPACTS ASSESMENT (EIA)Lucasrukona
 
Environment impact assessment in environment impact assessment
Environment impact assessment in environment impact assessmentEnvironment impact assessment in environment impact assessment
Environment impact assessment in environment impact assessmentArunAngadi5
 
Environmental and Social Impact Assessment
Environmental and Social Impact AssessmentEnvironmental and Social Impact Assessment
Environmental and Social Impact AssessmentTesfahunTesema
 
ENVIRONMENTAL IMPACT ASSESSMENT final na.docx
ENVIRONMENTAL IMPACT ASSESSMENT final na.docxENVIRONMENTAL IMPACT ASSESSMENT final na.docx
ENVIRONMENTAL IMPACT ASSESSMENT final na.docxMarskyUbia
 
environmentalimpactassessmenteia-210826024951.pdf
environmentalimpactassessmenteia-210826024951.pdfenvironmentalimpactassessmenteia-210826024951.pdf
environmentalimpactassessmenteia-210826024951.pdfssusereef268
 
Environmental impact assessment (eia)
Environmental impact assessment (eia)Environmental impact assessment (eia)
Environmental impact assessment (eia)SANDEEP PATRE
 
Auditing the extractive industry-the case of Ghana
Auditing the extractive industry-the case of GhanaAuditing the extractive industry-the case of Ghana
Auditing the extractive industry-the case of GhanaAikinsOsei1
 
ENVIRONMENTAL IMPACT ASSESSMENT (EIA)2.pptx
ENVIRONMENTAL IMPACT ASSESSMENT (EIA)2.pptxENVIRONMENTAL IMPACT ASSESSMENT (EIA)2.pptx
ENVIRONMENTAL IMPACT ASSESSMENT (EIA)2.pptxSubhajitNandi15
 
Environmental impact assessment 2020
Environmental impact assessment 2020Environmental impact assessment 2020
Environmental impact assessment 2020Chandrakant Singh
 

Similar to Facts about-environmental-impact-assessments (20)

Environmental impact assessment
Environmental impact assessmentEnvironmental impact assessment
Environmental impact assessment
 
EIA PPT.pptx
EIA PPT.pptxEIA PPT.pptx
EIA PPT.pptx
 
EIA PPT.pdf
EIA PPT.pdfEIA PPT.pdf
EIA PPT.pdf
 
EIA presentation.pptx
EIA presentation.pptxEIA presentation.pptx
EIA presentation.pptx
 
BasConcept of Eic nvironmental Impact Assessment-pages-2-13,18-65.pdf
BasConcept of  Eic nvironmental Impact Assessment-pages-2-13,18-65.pdfBasConcept of  Eic nvironmental Impact Assessment-pages-2-13,18-65.pdf
BasConcept of Eic nvironmental Impact Assessment-pages-2-13,18-65.pdf
 
What is an Environmental Clearance Certificate and How to Obtain It.pdf
What is an Environmental Clearance Certificate and How to Obtain It.pdfWhat is an Environmental Clearance Certificate and How to Obtain It.pdf
What is an Environmental Clearance Certificate and How to Obtain It.pdf
 
EIA-GeES 3112 Chapter 1.ppt Basic Concept of Environmental Impact Assessment...
EIA-GeES 3112 Chapter 1.ppt Basic Concept of  Environmental Impact Assessment...EIA-GeES 3112 Chapter 1.ppt Basic Concept of  Environmental Impact Assessment...
EIA-GeES 3112 Chapter 1.ppt Basic Concept of Environmental Impact Assessment...
 
Environment impact assessment
Environment impact assessmentEnvironment impact assessment
Environment impact assessment
 
Environmental Impact Assessment for the marine environment
Environmental Impact Assessment for the marine environmentEnvironmental Impact Assessment for the marine environment
Environmental Impact Assessment for the marine environment
 
Environemental Impact Assessment.pptx
Environemental Impact Assessment.pptxEnvironemental Impact Assessment.pptx
Environemental Impact Assessment.pptx
 
ENVIRONMENTAL IMPACTS ASSESMENT (EIA)
ENVIRONMENTAL  IMPACTS ASSESMENT (EIA)ENVIRONMENTAL  IMPACTS ASSESMENT (EIA)
ENVIRONMENTAL IMPACTS ASSESMENT (EIA)
 
Environment impact assessment in environment impact assessment
Environment impact assessment in environment impact assessmentEnvironment impact assessment in environment impact assessment
Environment impact assessment in environment impact assessment
 
Environmental and Social Impact Assessment
Environmental and Social Impact AssessmentEnvironmental and Social Impact Assessment
Environmental and Social Impact Assessment
 
ENVIRONMENTAL IMPACT ASSESSMENT final na.docx
ENVIRONMENTAL IMPACT ASSESSMENT final na.docxENVIRONMENTAL IMPACT ASSESSMENT final na.docx
ENVIRONMENTAL IMPACT ASSESSMENT final na.docx
 
Guidance notoneia (1)
Guidance notoneia (1)Guidance notoneia (1)
Guidance notoneia (1)
 
environmentalimpactassessmenteia-210826024951.pdf
environmentalimpactassessmenteia-210826024951.pdfenvironmentalimpactassessmenteia-210826024951.pdf
environmentalimpactassessmenteia-210826024951.pdf
 
Environmental impact assessment (eia)
Environmental impact assessment (eia)Environmental impact assessment (eia)
Environmental impact assessment (eia)
 
Auditing the extractive industry-the case of Ghana
Auditing the extractive industry-the case of GhanaAuditing the extractive industry-the case of Ghana
Auditing the extractive industry-the case of Ghana
 
ENVIRONMENTAL IMPACT ASSESSMENT (EIA)2.pptx
ENVIRONMENTAL IMPACT ASSESSMENT (EIA)2.pptxENVIRONMENTAL IMPACT ASSESSMENT (EIA)2.pptx
ENVIRONMENTAL IMPACT ASSESSMENT (EIA)2.pptx
 
Environmental impact assessment 2020
Environmental impact assessment 2020Environmental impact assessment 2020
Environmental impact assessment 2020
 

Recently uploaded

Abu Dhabi Sea Beach Visitor Community pp
Abu Dhabi Sea Beach Visitor Community ppAbu Dhabi Sea Beach Visitor Community pp
Abu Dhabi Sea Beach Visitor Community pp202215407
 
9873940964 High Profile Call Girls Delhi |Defence Colony ( MAYA CHOPRA ) DE...
9873940964 High Profile  Call Girls  Delhi |Defence Colony ( MAYA CHOPRA ) DE...9873940964 High Profile  Call Girls  Delhi |Defence Colony ( MAYA CHOPRA ) DE...
9873940964 High Profile Call Girls Delhi |Defence Colony ( MAYA CHOPRA ) DE...Delhi Escorts
 
VIP Call Girls Service Chaitanyapuri Hyderabad Call +91-8250192130
VIP Call Girls Service Chaitanyapuri Hyderabad Call +91-8250192130VIP Call Girls Service Chaitanyapuri Hyderabad Call +91-8250192130
VIP Call Girls Service Chaitanyapuri Hyderabad Call +91-8250192130Suhani Kapoor
 
(PARI) Viman Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
(PARI) Viman Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...(PARI) Viman Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
(PARI) Viman Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...ranjana rawat
 
VIP Call Girls Ramanthapur ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With R...
VIP Call Girls Ramanthapur ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With R...VIP Call Girls Ramanthapur ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With R...
VIP Call Girls Ramanthapur ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With R...Suhani Kapoor
 
(RIYA) Kalyani Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(RIYA) Kalyani Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(RIYA) Kalyani Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(RIYA) Kalyani Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
VIP Call Girls Saharanpur Aaradhya 8250192130 Independent Escort Service Saha...
VIP Call Girls Saharanpur Aaradhya 8250192130 Independent Escort Service Saha...VIP Call Girls Saharanpur Aaradhya 8250192130 Independent Escort Service Saha...
VIP Call Girls Saharanpur Aaradhya 8250192130 Independent Escort Service Saha...Suhani Kapoor
 
VIP Kolkata Call Girl Kalighat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Kalighat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Kalighat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Kalighat 👉 8250192130 Available With Roomdivyansh0kumar0
 
(NANDITA) Hadapsar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
(NANDITA) Hadapsar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...(NANDITA) Hadapsar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
(NANDITA) Hadapsar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...ranjana rawat
 
Hi FI Call Girl Ahmedabad 7397865700 Independent Call Girls
Hi FI Call Girl Ahmedabad 7397865700 Independent Call GirlsHi FI Call Girl Ahmedabad 7397865700 Independent Call Girls
Hi FI Call Girl Ahmedabad 7397865700 Independent Call Girlsssuser7cb4ff
 
(AISHA) Wagholi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(AISHA) Wagholi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(AISHA) Wagholi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(AISHA) Wagholi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
webinaire-green-mirror-episode-2-Smart contracts and virtual purchase agreeme...
webinaire-green-mirror-episode-2-Smart contracts and virtual purchase agreeme...webinaire-green-mirror-episode-2-Smart contracts and virtual purchase agreeme...
webinaire-green-mirror-episode-2-Smart contracts and virtual purchase agreeme...Cluster TWEED
 
Species composition, diversity and community structure of mangroves in Barang...
Species composition, diversity and community structure of mangroves in Barang...Species composition, diversity and community structure of mangroves in Barang...
Species composition, diversity and community structure of mangroves in Barang...Open Access Research Paper
 
VIP Call Girls Mahadevpur Colony ( Hyderabad ) Phone 8250192130 | ₹5k To 25k ...
VIP Call Girls Mahadevpur Colony ( Hyderabad ) Phone 8250192130 | ₹5k To 25k ...VIP Call Girls Mahadevpur Colony ( Hyderabad ) Phone 8250192130 | ₹5k To 25k ...
VIP Call Girls Mahadevpur Colony ( Hyderabad ) Phone 8250192130 | ₹5k To 25k ...Suhani Kapoor
 
Call Girls In Faridabad(Ballabgarh) Book ☎ 8168257667, @4999
Call Girls In Faridabad(Ballabgarh) Book ☎ 8168257667, @4999Call Girls In Faridabad(Ballabgarh) Book ☎ 8168257667, @4999
Call Girls In Faridabad(Ballabgarh) Book ☎ 8168257667, @4999Tina Ji
 
NO1 Famous Kala Jadu specialist Expert in Pakistan kala ilam specialist Exper...
NO1 Famous Kala Jadu specialist Expert in Pakistan kala ilam specialist Exper...NO1 Famous Kala Jadu specialist Expert in Pakistan kala ilam specialist Exper...
NO1 Famous Kala Jadu specialist Expert in Pakistan kala ilam specialist Exper...Amil baba
 

Recently uploaded (20)

Abu Dhabi Sea Beach Visitor Community pp
Abu Dhabi Sea Beach Visitor Community ppAbu Dhabi Sea Beach Visitor Community pp
Abu Dhabi Sea Beach Visitor Community pp
 
Hot Sexy call girls in Nehru Place, 🔝 9953056974 🔝 escort Service
Hot Sexy call girls in Nehru Place, 🔝 9953056974 🔝 escort ServiceHot Sexy call girls in Nehru Place, 🔝 9953056974 🔝 escort Service
Hot Sexy call girls in Nehru Place, 🔝 9953056974 🔝 escort Service
 
9873940964 High Profile Call Girls Delhi |Defence Colony ( MAYA CHOPRA ) DE...
9873940964 High Profile  Call Girls  Delhi |Defence Colony ( MAYA CHOPRA ) DE...9873940964 High Profile  Call Girls  Delhi |Defence Colony ( MAYA CHOPRA ) DE...
9873940964 High Profile Call Girls Delhi |Defence Colony ( MAYA CHOPRA ) DE...
 
VIP Call Girls Service Chaitanyapuri Hyderabad Call +91-8250192130
VIP Call Girls Service Chaitanyapuri Hyderabad Call +91-8250192130VIP Call Girls Service Chaitanyapuri Hyderabad Call +91-8250192130
VIP Call Girls Service Chaitanyapuri Hyderabad Call +91-8250192130
 
(PARI) Viman Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
(PARI) Viman Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...(PARI) Viman Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
(PARI) Viman Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
 
VIP Call Girls Ramanthapur ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With R...
VIP Call Girls Ramanthapur ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With R...VIP Call Girls Ramanthapur ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With R...
VIP Call Girls Ramanthapur ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With R...
 
(RIYA) Kalyani Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(RIYA) Kalyani Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(RIYA) Kalyani Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(RIYA) Kalyani Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
VIP Call Girls Saharanpur Aaradhya 8250192130 Independent Escort Service Saha...
VIP Call Girls Saharanpur Aaradhya 8250192130 Independent Escort Service Saha...VIP Call Girls Saharanpur Aaradhya 8250192130 Independent Escort Service Saha...
VIP Call Girls Saharanpur Aaradhya 8250192130 Independent Escort Service Saha...
 
VIP Kolkata Call Girl Kalighat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Kalighat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Kalighat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Kalighat 👉 8250192130 Available With Room
 
Sexy Call Girls Patel Nagar New Delhi +918448380779 Call Girls Service in Del...
Sexy Call Girls Patel Nagar New Delhi +918448380779 Call Girls Service in Del...Sexy Call Girls Patel Nagar New Delhi +918448380779 Call Girls Service in Del...
Sexy Call Girls Patel Nagar New Delhi +918448380779 Call Girls Service in Del...
 
(NANDITA) Hadapsar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
(NANDITA) Hadapsar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...(NANDITA) Hadapsar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
(NANDITA) Hadapsar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
 
Hi FI Call Girl Ahmedabad 7397865700 Independent Call Girls
Hi FI Call Girl Ahmedabad 7397865700 Independent Call GirlsHi FI Call Girl Ahmedabad 7397865700 Independent Call Girls
Hi FI Call Girl Ahmedabad 7397865700 Independent Call Girls
 
Model Call Girl in Rajiv Chowk Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Rajiv Chowk Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Rajiv Chowk Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Rajiv Chowk Delhi reach out to us at 🔝9953056974🔝
 
(AISHA) Wagholi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(AISHA) Wagholi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(AISHA) Wagholi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(AISHA) Wagholi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
Call Girls In Dhaula Kuan꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
Call Girls In Dhaula Kuan꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCeCall Girls In Dhaula Kuan꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
Call Girls In Dhaula Kuan꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
 
webinaire-green-mirror-episode-2-Smart contracts and virtual purchase agreeme...
webinaire-green-mirror-episode-2-Smart contracts and virtual purchase agreeme...webinaire-green-mirror-episode-2-Smart contracts and virtual purchase agreeme...
webinaire-green-mirror-episode-2-Smart contracts and virtual purchase agreeme...
 
Species composition, diversity and community structure of mangroves in Barang...
Species composition, diversity and community structure of mangroves in Barang...Species composition, diversity and community structure of mangroves in Barang...
Species composition, diversity and community structure of mangroves in Barang...
 
VIP Call Girls Mahadevpur Colony ( Hyderabad ) Phone 8250192130 | ₹5k To 25k ...
VIP Call Girls Mahadevpur Colony ( Hyderabad ) Phone 8250192130 | ₹5k To 25k ...VIP Call Girls Mahadevpur Colony ( Hyderabad ) Phone 8250192130 | ₹5k To 25k ...
VIP Call Girls Mahadevpur Colony ( Hyderabad ) Phone 8250192130 | ₹5k To 25k ...
 
Call Girls In Faridabad(Ballabgarh) Book ☎ 8168257667, @4999
Call Girls In Faridabad(Ballabgarh) Book ☎ 8168257667, @4999Call Girls In Faridabad(Ballabgarh) Book ☎ 8168257667, @4999
Call Girls In Faridabad(Ballabgarh) Book ☎ 8168257667, @4999
 
NO1 Famous Kala Jadu specialist Expert in Pakistan kala ilam specialist Exper...
NO1 Famous Kala Jadu specialist Expert in Pakistan kala ilam specialist Exper...NO1 Famous Kala Jadu specialist Expert in Pakistan kala ilam specialist Exper...
NO1 Famous Kala Jadu specialist Expert in Pakistan kala ilam specialist Exper...
 

Facts about-environmental-impact-assessments

  • 1. What is an Environmental Impact Assessment? Nowadays, for most dredging projects some sort of Environmental Impact Assessment (EIA) is normally pre- pared, often specified and required by law or regulation, sometimes just as a part of good, modern project manage- ment. Although no uniform standard for such an assess- ment is universally accepted, an EIA regularly contains: an explanation of environmental objectives and policy; a description of the existing environmental situation (the baseline conditions); a description of the project; an assess- ment of the potential effects of the project; a summary of recommendations; and an Environmental Management (or action) Plan (EMP). What is the purpose of an EIA? The purpose of an EIA is to ensure that dredging activities are performed in an environmentally acceptable manner, use sound engineering techniques, that they are economi- cally warranted and take sufficient consideration of long- term effects. The scope of an EIA usually includes a survey and review of prior studies done by others to describe the physi- cal, chemical, and biological conditions of the study area; an evaluation of regional dredging and disposal needs; and a characterisation of physical and chemical properties of typical regional dredged materials. The EIA will also formu- late alternatives for dredged material management, perform a preliminary evaluation of alternatives management meth- ods, and make recommendations for further evaluation. What is the difference between an EIA, an EIS, an EES and an ES? There is no such thing as the Environmental Impact Assessment, nor is there one single international organisa- tion regulating the requirements of the EIA. EIA is often used as a collective term, which can also refer to the Environmental Effect Study (EES), the Environmental Impact Study (EIS) or the Environmental Study (ES), all indicating some sort of environmental evaluation. In some cases the term EIA may have a formal or legal specificity, while in other cases it is a descriptive term comparable with the ES, the EES or the EIS. Are EIAs only obligatory for projects involving contaminated materials? EIAs preceding a dredging project became obligatory in specific cases in many industrialised countries in the 1970s, when the environment first appeared on the political agenda. In the beginning, the obligation was limited to dredging projects where contaminated materials were suspected. Later on, dredging projects with other environ- mental considerations, for instance habitat protection, required an EIA. In the 1980s environmental and ecological consider- ations also became part of the policies of the International Finance Institutions (IFIs), such as the World Bank. This was formalised in the 1990s when an EIA became a condition for the funding of IFI-sponsored projects. The World Bank definition of the EIA is important because it more or less established the minimum requirements. What is the World Bank definition of an EIA? In a World Bank study, the EIA is summarised as: “[…] environmental impact assessment (EIA) is taken to mean the systematic examination of the likely environmental conse- quences of proposed projects. The results of the assessment – which are assembled in a document known as an Environmental Statement (ES) – are intended to provide decision-makers with a balanced assessment of the environ- mental implications of the proposed action and the alternative examined. The ES is then used by decision-makers as a con- tribution to the information base upon which a decision is made. The overall goal of an EIA is to achieve better devel- opmental interventions through protecting the environment (human, physical and biotic).” Simply said, the EIA leads to an ES and the ES ideally results in a management directive, or Environmental Management Plan (EMP), a plan for managing and con- trolling the environmental effects of a project and guiding the environmental control mechanisms. Facts About Environmental Impact Assessments An Information Update from the IADC – Number 1 – 2008
  • 2. Is an EIA always required? Almost always is the short answer. Most dredging projects will require some type of environmental study. In some developing countries national environmental legislation requiring an impact study is not yet in place. Nonetheless, since almost all projects in developing countries are (at least partly) funded by IFIs, an EIA will probably be required. In recent years, even where compliance with IFI guidelines may not be necessary, many project owners have adopted a policy of corporate social responsibility and will no longer operate without taking into account the envi- ronmental situation. In developed countries, national legislation will often require an EIA. In fact, the requirements in most industria- lised countries are often much more specific than the IFIs, so before embarking on a dredging project, national legisla- tion should always be studied to find out which legal obli- gations are applicable. Since legislation is constantly being renewed, finding the most up-to-date information for a specific country or region is imperative. At what stage of a project should an EIA be undertaken? The EIA should be part of the project from the start of the project planning phase, since the EIA is the basis for the EMP and the EMP must be fully operational as soon as the execution or construction phase starts. The EMP is often obligatory, but also in cases where it is not, it is considered to be “good practice and policy” to conclude the EIA with some sort of EMP. What is an Environmental Management Plan? Technically speaking, the Environmental Management Plan or EMP is the synthesis of the information gathered in the EIA, incorporating the overall assessment into the entire dredging project, from implementation to construc- tion to execution. The EMP sets out the actions for controlling, monitor- ing and evaluating the project during every phase. The EMP states which parameters should be measured, what the critical values are and what actions will have to be taken to stay within the critical boundaries. The EMP often addresses mitigation measures to ­minimise adverse impacts; measures to enhance environ- mental benefits, if such benefits occur; measures necessary to ­guarantee effective monitoring; monitoring and auditing programme details; and resources, funds, contractual and management arrangements. The EMP maps out the ­processes that managers need to follow to maximise com- pliance and minimise harm to the environment. Does an EIA address only ecological issues? The European Commission describes the purpose of an EIA in the directive EC 1985/97: “The environmental impact assessment shall identify, describe and assess in an appropriate manner, in the light of each individual case […] the direct and indirect effects of a project on the following factors: - human beings, fauna and flora; - soil, water, air, climate and the landscape; - material assets and the cultural heritage; - the interaction between the factors mentioned in the first, second and third indents.” This clearly shows that “environment” has become a much broader concept than simply ecology. EIAs now reach beyond assessing only possible contamination, and now include assessing material assets and political, social and cultural heritage. This broader view of environment can be seen as part of the recent “sustainability move- ment”. Other terms used to describe this concept are the “triple bottom approach” or the 3 Ps, that is “people, planet, profit”, meaning that social, environmental and financial considerations must all be integrated in decision- making processes. Most major dredging companies have already embraced this socially responsible way of working. What are the main steps of an EIA? An EIA is a data management process with three compo- nents: First, the appropriate information must be identified and collated. Secondly, changes in environmental param- eters resulting from the proposed project must be forecast and compared with so-called “baseline conditions”. Finally, the effects of the actual changes, with and without mitigation measures in place, must be assessed and com- municated to the decision-makers. An EIA should answer the question: Is a project as planned environmentally acceptable? And if not, can changes be made to mitigate impacts, or to improve the overall project acceptability? What are baseline conditions? Baseline conditions describe the circumstances of the dredging site and the potential placement site(s) prior to the start of the project. These conditions are far from static and part of baseline conditions should also include the natural variability of the sites, including extreme events like storms and long-term developments such as seasonal influences. Collection of these data can be time-consum- ing, but it is worth the investment. If an EIA is based solely on average conditions then the results of a severe storm, which may have more impact than the dredging activities, could not be taken into account.
  • 3. What other types of data should be collected? An EIA looks at a broad scope of effects of dredging, rang- ing from the consequences of suspended sediments on water quality to the consequences for local communities with respect to their livelihoods (access to fishing grounds) or to archaeological remains. In short, a typical EIA will include data about physical, chemical, biological and eco- logical impacts as well as economic, social and political effects. Depending on the type of project (capital, mainte- nance or remedial) and its location, these data may include assessing flood risks, salt intrusion, turbidity, and the vul- nerability of local marine life and habitats. In addition, an EIA may also consider noise and air quality, aesthetics such as landscapes and seascapes, and interactions with other public uses of the water and adjacent land areas for recre- ation or commerce. Each EIA must be tailored to the par- ticular project. Who conducts the EIA? And who implements it? Ideally the project owner hires independent consultants after an open and transparent tender procedure. These consultants are environmental engineers, who should give an unbiased assessment which should include an accurate sustainability appraisal, planning support, and ecological risk assessment. Careful consideration of the choice of a reliable consultant is crucial. In a certain cases the project owner requires contractors to participate in the application process for a dredging licence or permit. Whoever conducts the EIA, the project owner is respon- sible vis-à-vis the authorities for the implementation of and adherence to the EIA. On the other hand, the con- tractor will have to guarantee in the final contract that the execution of the project will meet the standards set out in the EMP, which is based on the EIA. After the EIA is completed, then what? An EIA offers a summary of the environmental issues that became apparent, for instance, the scope of the environ- mental impacts, the risks and/or the benefits; the signifi- cance of these impacts, risks and/or benefits and the likely mitigation measures required; and the actions to be taken (and by whom!). Processes then need to be implemented to enhance the environmental benefits of the proposed project (this can be the re-use of the dredged material); to ensure compliance with relevant regulations and inter- national agreements (e.g., the DMAF or the London Convention); to consider alternatives; to identify signifi- cant adverse environmental effects and identify action; to provide for public consultation and input; to define the data assembly needs and necessary survey activities; and to determine the predictive techniques that are to be employed. An initial environmental evaluation provides a basis for determining whether or not to proceed with dredg- ing. It should answer the question, is a project as planned environmentally acceptable, and if not, what can be done to improve overall acceptability. Initial Environmental Evaluation
  • 4. If this leads to the conclusion that (mitigation) mea- sures are necessary, these measures should be applied to the design & planning phase (“project effects”) and/or the construction phase (“process effects”). In the first case the measures will probably have to be taken by the project owner, in the second case by the contractor. Should the public be involved? The process of impact identification is based upon an appreciation of how the proposed project might interact with the environment, both in the dredging and the place- ment sites and during the transport between the two. As such, this requires an appreciation of what are considered to be the valued environmental and community resources within the vicinity of both sites. Communication with the public about this is essential; they need to be informed and an explanation of the assessments made should be offered. In some cases, the public may identify additional impacts and might ask for broader impact consideration or further mitigation. How can impacts be predicted? Impacts can be predicted using logical, physical, biological or mathematical modelling. These may identify potential negative impacts, but also indicate options for enhance- ment of positive impacts (e.g., the re-use of dredged mate- rial). Once the possible impacts are identified, the project design must be adapted to attempt to minimise the adverse impacts and maximise the beneficial impacts. As soon as the project design is optimised, the effects must be forecast in different ways: The affected feature, the magnitude, the resource and/or population, the action causing the effect, the duration of the effect, and the proposed mitigation (or enhancement) measures. Predicted effects can be divided into short-term (less than one week) or long-term (more than one week) effects and near-field (less than one kilometre) or far-field (more than one kilometre) effects, for both the dredging and placement site and along the transport route. In general effects created by the construction works are short term and near field, while impacts caused by the overall project can be far field and long term. What are the advantages of conducting an EIA? A well-executed and thorough EIA can lead to cost-effec- tive mitigation and/or enhancement. When environmen- tal mitigation is integrated as a fundamental part of project design, rather than as an add-on exercise, it will reduce project costs and lower community costs. For instance, mitigation of impacts to fauna and flora may be as simple as planning to adhere to seasonal restrictions by dredging during a window that does not interfere with marine life reproduction cycles. This is not to say that the costs of measures resulting from an EIA are lower than if no EIA had been conducted at all. But the costs will certainly be higher, if the plans have to be changed midstream when the project is already underway. The EIA is an important tool for project planning and as such can minimise the risks for misunderstandings, provide clarity about environmental implications and lead to better cooperation between all stakeholders including project owners, dredging contractors and the public. For further reading and information Bray R.N. (Editor), (2008). Environmental Aspects of Dredging. IADC/CEDA-Taylor and Francis, London, UK. Doorn-Groen, S.M. et al. (2007). Environmental monitoring and man- agement of reclamation works close to sensitive habitats, Proceedings World Dredging Congress XVIII, Lake Buena Vista, FL, USA. Also reprinted­in Terra et Aqua, nr. 108, September 2007. Hufschmidt et al. (1983). Environment, Natural Systems, and Development – An Economic Valuation Guide, The John Hopkins University Press, Baltimore, MD, USA. Jensen, K. et al. (1998). Environmental Impact Assessment using the Rapid Impact Assessment Matrix (RIAM). Olesen & Olesen, Fredensborg, Denmark. PIANC EnviCom (2006). Environmental Risk Assessment of Dredging and Disposal Operations. Report from Working Group 10 of the Environment Commission. International Navigation Association. Brussels, Belgium. International Association of Dredging Companies, PO Box 80521, 2508 GM The Hague, The Netherlands tel. +31 070 352 3334, fax +31 070 351 2654, e-mail: info@iadc-dredging.com, www.iadc-dredging.com This brochure is presented by the International Association of Dredging Companies whose members offer the highest quality and professionalism in dredging and maritime construction. The information presented here is part of an on-going effort to support clients and others in understanding the fundamental principles of dredging and maritime construction.