SlideShare a Scribd company logo
1 of 34
Presented by: Aditi
Manoj
Charul
 The CPM, time is related to cost and the objective
is to develop an optimum time –cost relationship.
Sometimes it becomes necessary to complete the
project earlier than the normal time, in such
situations the cost of expediting the operations has
to be considered.
CPM makes the use of cost estimate alongwith
time estimate and provides a schedule for
completing the activities at the minimum total
cost.
LIMIT STATE
METHOD
This procedure improves planning, scheduling
and controlling of the project and also assesses the
possibility to arrive at a feasible and desirable time
cost relationship.
The project duration can be reduced by reducing
the duration of only the critical activities in the
project network.
Reduction in the time duration can be done by:
1) Deploying more resources for early completion.
2)Relaxing the technical specifications
LIMIT STATE
METHOD
OPTIMUM DURATION:
the duration which gives the most economic cost
for completing the project.
TIME-COST ESTIMATES:
1) NORMAL ESTIMATE:
emphasis is on cost with time being associated
with minimum cost.
2) CRASH ESTIMATE:
emphasis is on time . It involves the absolute
minimum time required for the job and the cost
necessary to achieve it. LIMIT STATE
METHOD
LIMIT STATE
METHOD
5
COST
TIME
Minimum cost
Optimum duration
Cost rises if project is
prolonged
Cost rises if project is crashed
LIMIT STATE
METHOD
LIMIT STATE
METHOD
INDIRECTCOST
TIME
Total indirect cost curve
Over heads
Outage loss
 These are those expenditures which cannot clearly
allocated to the individual activities of a project,
but are assessed as whole.
It includes expenditure related to administrative
and establishment charges, supervision,
expenditures on central store organisation, loss of
revenue, lost profit, penalty etc.
Indirect cost rises with increased duration.
OUTAGE LOSS : loss in profits due to inability to
meet demand or penalty due to delay. LIMIT STATE
METHOD
 Those expenditures which are directly chargeable
to and can be identified specifically with the
activities of the project.
These include labour cost, material cost,
equipment cost etc.
LIMIT STATE
METHOD
LIMIT STATE
METHOD
COST
TIME
Cc
tn
Normal Duration
tc
Crash duration
Cn
 NORMAL TIME(tn):
Standard time that an estimator whould usually
allow for an activity.
CRASH TIME(tc):
minimum possible time in which an activity can be
completed, by employing extra resources.
NORMAL COST(Cn):
Direct cost required to complete the acticity in
normal time.
CRASH COST(Cc):
Direct cost corresponding to completion of activity
within crash time. LIMIT STATE
METHOD
 COST SLOPE:
It is the slope of the direct cost curve, approximated
as a straight line in order to have a single cross
slope.
Cost Slope = crash cost-normal cost
Normal time-crash time
CS = Cc-Cn = ∆C
tn-tc ∆t
LIMIT STATE
METHOD
 It is the sum of direct and indirect costs.
LIMIT STATE
METHOD
COST
TIME
Indirect cost curve
direct cost curve
total cost curve
tc crash tn
normal
to
optimum
Minimum cost
To examine « what will be the cost structure of the
project if some or all of the activities is crashed ? »
we should have following data with us :-
- Normal direct cost data for each activity if it is to
be completed in normal time duration .
- crashed direct cost data if that activity is crashed.
After this cost slope for each activity can be
determined.
- The indirect cost rate should also be known so that
total cost can be determined.
LIMIT STATE
METHOD
 Normal time of project- sum of the normal durations of
each activity along the critical path.
 Minimum time of project – sum of the crashed time
duration of each activity along the critical path.
 Non-critical activity need not to be speed up as their
crashing is not going to decrease the project duration
further. Moreover the cost will be high without any
additional advantage.
 Some non-critical activities become critical in the process
of crashing the critical activities.
 It is always better to start with crashing first that critical
activity that has the lowest cost slope.Then we take
another critical activity which is having next higher slope.
 While crashing an activity fully by time “t” ,it should be
examined whether its affecting the non –critical
activity or not.
1 2 3 4
9(2)
c
A
5(4)
B
6(2)
D
5(3)
STEPS IN TIME COST OPTIMISATION
1. Establish:- Direct cost time relationship for various
activities of the project.
2. Determine:- Cost slope for various activities and
arrange them in the ascending order of cost slope.
3. Compute:- Direct cost for the network with normal
duration of activities.
4. Crash:- The activities in the critical path as per
ranking i.e starting with the the activity having the
lowest slope.
5. Continue:-Crashing the critical activities in the
ascending order of the slope.
6. Crash:- Parallel non-critical activities which have
become critical by the reduction of critical path duration
due to crashing in steps 4 and 5.
7. Continue :- Crashing process through steps 4 to 6 , till a
stage is reached beyond which no further crashing is
possible.
8. Find:- Find total cost of the project at every stage by
adding indirect costs to the direct costs determined
above.
9. Plot:- Total cost–duration curve.
10. Pick Up:-The optimum duration corresponding to
which least total project cost is obtained.
.
LIMIT STATE
METHOD
.
ACTIVITY NORMAL
DURATION
(WEEKS)
NORMAL
COST
(RUPEES)
CRASH
DURATION
(WEEKS)
CRASH COST
(RUPEES)
1-2 4 4000 2 12000
2-3 5 3000 2 7500
2-4 7 3600 5 6000
3-4 4 5000 2 10000
 .
1 2
3
4
4(2)
5(2) 4(2)
7(5)
STEP 1. TIME SCALED VERSION OF NETWORK
1 32 4
7(5)
4(2) 4(2)
5(2)
ACTIVITY Δ C
(RUPEES)
Δ t
(WEEKS)
COST
SLOPE
RS./WEEK
1-2 8000 2 4000
2-3 4500 3 1500
2-4 2400 2 1200
3-4 5000 2 2500
The normal; duration of the project is the sum of the
normal durations of each activity on the critical path.
(It is not the sum of normal durations of all the
activities).
Therefore, Normal duration of the project
= 4+5+4 = 13 weeks.
Direct cost = 4000+3000+3600+5000
= 15600
While crashing the activities, we shall first select that critical activity
which has minimum cost slope.
Let say Activity 2-4 has minimum cost slope of 1500 per week.
Crash period is 2 weeks i.e. Δt = 5-2 = 3 weeks.
However, crashing it by 3 weeks will affect non-critical activity 2-4 which
has float of only 2 weeks. Hence restrict the crashing of 2-3 by 2 weeks
only, in the first stage.
New duration of the project= 13-2 = 11 weeks.
Extra cost of crashing activity 2-3 by 2 weeks
= 2*1500 = 3000
Direct cost of the project of 11 weeks duration
= 15600 + 3000 = 18600
The time-scaled version of the network, after first stage crashing, for the
project of 11 weeks duration is shown in the figure.
41 2 34(2) 3(2) 4(2)
7(5)
From the figure above it is clear that activity 2-4 lying on the parallel path
has also become critical, though activity 2-3 has still 1 week crashing left.
However, Activity 2-3 cannot be crashed unless 2-4 is also crashed. So
crash 2-3 &2-4 for 1 week simultaneously.
Further crashing can be done with three alternatives:
 crashing activities 2-3 & 2-4 simultaneously, having a combined cost
slope of 1500 + 1200 = 2700 per week.
 Crashing activities 3-4 & 2-4 simultaneously, having a combined cost
slope of 2500 + 1200 = 3700 per week
 Crashing activity 1-2 alone, having a cost slope of rupees 4500 per week
out of these, the first alternative has the minimum cost slope.
Thus, the extra cost of crashing 2-3 & 2-4 by 1 week
= 2700
therefore, Direct cost of Project for 10 weeks duration
= 18600 + 2700 = 21300
In this step, activity 2-3 has been crashed to its fullest extent.
1 2 3 4
4(2) 2(2) 4(2)
6(5)
The remaining activities to be crashed are 1-2 , 2-4, 3-4.
out of these, activities 2-4 & 3-4 are to be crashed
jointly, with a combined cost slope of 2500 + 1200 =
3700.
The cost slope of activity 1-2 is 4000 which is higher .
Hence period of 6-5 = 1 week left.
Hence only 1 week crashing will be done in this step,
leading to a project duration of 9 weeks.
cost of crashing 2-4 & 3-4 by 1 week.
= 3700 * 1 = 3700
Therefore, cost of project for 9 weeks duration
= 21300 + 3700 = 25000.
The Time scaled version of the network for 9 weeks
duration is shown in fig. we crashed activity 2-4 also
to its fullest extent.
Time- scaled network for 9 weeks Duration.
1 2 3 4
6(5)
4(2) 2(2) 3(2)
Out of remaining critical activities ( i.e. 1-2&3-4)
Activity 3-4 cannot be further crashed to its fullest crash
period of 2 weeks, since it will affect activity 2-4 which has
already been fully crashed.
Hence activity 1-2 is the only remaining activity to be
crashed. The period by which it can be crashed is = 4-2 = 2
weeks, reducing the project duration to 9-2 = 7 weeks.
Extra cost of crashing 1-2 by 2 weeks = 2*4000 = 8000
Therefore, Direct cost of Project of 7 weeks duration
= 25000 + 8000 = 33000.
1 2 3
5(2)
4
2(2) 2(2) 3(2)
PROJECT
DURATIO
N
13
(NORMAL
)
11 10 9 7
DIRECT
COST (RS.)
15600 18600 21200 25000 31000
INDIRECT
COST (RS.)
26000 22000 20000 18000 14000
TOTAL
COST (RS.)
41600 40600 41300 43000 47000

More Related Content

What's hot

Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project ManagementAravind Samala
 
Purpose of Valuation
Purpose of ValuationPurpose of Valuation
Purpose of ValuationBhavik A Shah
 
SPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATIONSPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATIONAr Naveen Naveen
 
PPT on Construction Costing
PPT on Construction CostingPPT on Construction Costing
PPT on Construction CostingManish Kandpal
 
6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource Smoothing6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource SmoothingDavidMcLachlan1
 
Rate analysis in civil engineering
Rate analysis in civil engineeringRate analysis in civil engineering
Rate analysis in civil engineeringKailash Chander
 
Estimating and-costing book
Estimating and-costing bookEstimating and-costing book
Estimating and-costing bookThomas Britto
 
Introduction-construction management_Construction Management (2180611) (Semes...
Introduction-construction management_Construction Management (2180611) (Semes...Introduction-construction management_Construction Management (2180611) (Semes...
Introduction-construction management_Construction Management (2180611) (Semes...A Makwana
 
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTS.Vijaya Bhaskar
 
Estimation and Costing
Estimation and Costing Estimation and Costing
Estimation and Costing Vijay325
 

What's hot (20)

Estimating & Costing - I
Estimating & Costing - IEstimating & Costing - I
Estimating & Costing - I
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
 
Purpose of Valuation
Purpose of ValuationPurpose of Valuation
Purpose of Valuation
 
Types of estimates
Types of estimatesTypes of estimates
Types of estimates
 
Bar chart
Bar chartBar chart
Bar chart
 
Approximate estimate
Approximate estimateApproximate estimate
Approximate estimate
 
Rate analysis
Rate analysisRate analysis
Rate analysis
 
SPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATIONSPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATION
 
PPT on Construction Costing
PPT on Construction CostingPPT on Construction Costing
PPT on Construction Costing
 
6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource Smoothing6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource Smoothing
 
Valuation
ValuationValuation
Valuation
 
Rate analysis in civil engineering
Rate analysis in civil engineeringRate analysis in civil engineering
Rate analysis in civil engineering
 
Estimating and-costing book
Estimating and-costing bookEstimating and-costing book
Estimating and-costing book
 
Cpm n pert
Cpm n pertCpm n pert
Cpm n pert
 
Valuation(1)
Valuation(1)Valuation(1)
Valuation(1)
 
Construction Cost Control
Construction Cost ControlConstruction Cost Control
Construction Cost Control
 
Introduction-construction management_Construction Management (2180611) (Semes...
Introduction-construction management_Construction Management (2180611) (Semes...Introduction-construction management_Construction Management (2180611) (Semes...
Introduction-construction management_Construction Management (2180611) (Semes...
 
Construction Planning
Construction PlanningConstruction Planning
Construction Planning
 
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERT
 
Estimation and Costing
Estimation and Costing Estimation and Costing
Estimation and Costing
 

Viewers also liked

Cost Optimization
Cost OptimizationCost Optimization
Cost OptimizationLextron
 
Resume - C A - Dillip Kumar Sahoo having post qualification experience 17 ye...
Resume - C A  - Dillip Kumar Sahoo having post qualification experience 17 ye...Resume - C A  - Dillip Kumar Sahoo having post qualification experience 17 ye...
Resume - C A - Dillip Kumar Sahoo having post qualification experience 17 ye...Dillip Sahoo
 
Failure prediction of propeller shaft prototype using finite element analysis
Failure prediction of propeller shaft prototype using finite element analysisFailure prediction of propeller shaft prototype using finite element analysis
Failure prediction of propeller shaft prototype using finite element analysiseSAT Journals
 
Maintenance and Management Best Practices from Support
Maintenance and Management Best Practices from SupportMaintenance and Management Best Practices from Support
Maintenance and Management Best Practices from SupportCA | Automic Software
 
Best Practices - Software Engineering
Best Practices - Software EngineeringBest Practices - Software Engineering
Best Practices - Software Engineering3Quill Softwares
 
Software maintenance Unit5
Software maintenance  Unit5Software maintenance  Unit5
Software maintenance Unit5Mohammad Faizan
 
Utsav Mahendra : Customer Feedback and Service Recovery
Utsav Mahendra : Customer Feedback and Service Recovery Utsav Mahendra : Customer Feedback and Service Recovery
Utsav Mahendra : Customer Feedback and Service Recovery Utsav Mahendra
 
Software Maintenance
Software MaintenanceSoftware Maintenance
Software MaintenanceIfan Dhani
 
Software development best practices & coding guidelines
Software development best practices & coding guidelinesSoftware development best practices & coding guidelines
Software development best practices & coding guidelinesAnkur Goyal
 
Project crashing and job sequencing
Project crashing and job sequencingProject crashing and job sequencing
Project crashing and job sequencingBuha Payal
 
Multinational corporation
Multinational corporationMultinational corporation
Multinational corporationDiwakar Saini
 
Crashing and cost plan-cpm
Crashing and cost plan-cpmCrashing and cost plan-cpm
Crashing and cost plan-cpmJulius Cuaresma
 

Viewers also liked (20)

Cost Optimization
Cost OptimizationCost Optimization
Cost Optimization
 
Resume - C A - Dillip Kumar Sahoo having post qualification experience 17 ye...
Resume - C A  - Dillip Kumar Sahoo having post qualification experience 17 ye...Resume - C A  - Dillip Kumar Sahoo having post qualification experience 17 ye...
Resume - C A - Dillip Kumar Sahoo having post qualification experience 17 ye...
 
Failure prediction of propeller shaft prototype using finite element analysis
Failure prediction of propeller shaft prototype using finite element analysisFailure prediction of propeller shaft prototype using finite element analysis
Failure prediction of propeller shaft prototype using finite element analysis
 
Scheduling
SchedulingScheduling
Scheduling
 
Cost optimisation
Cost optimisationCost optimisation
Cost optimisation
 
Maintenance and Management Best Practices from Support
Maintenance and Management Best Practices from SupportMaintenance and Management Best Practices from Support
Maintenance and Management Best Practices from Support
 
Best Practices - Software Engineering
Best Practices - Software EngineeringBest Practices - Software Engineering
Best Practices - Software Engineering
 
Software maintenance Unit5
Software maintenance  Unit5Software maintenance  Unit5
Software maintenance Unit5
 
Utsav Mahendra : Customer Feedback and Service Recovery
Utsav Mahendra : Customer Feedback and Service Recovery Utsav Mahendra : Customer Feedback and Service Recovery
Utsav Mahendra : Customer Feedback and Service Recovery
 
Software Maintenance
Software MaintenanceSoftware Maintenance
Software Maintenance
 
Software development best practices & coding guidelines
Software development best practices & coding guidelinesSoftware development best practices & coding guidelines
Software development best practices & coding guidelines
 
Project crashing and job sequencing
Project crashing and job sequencingProject crashing and job sequencing
Project crashing and job sequencing
 
Multinational corporation
Multinational corporationMultinational corporation
Multinational corporation
 
Cost Optimisation on AWS
Cost Optimisation on AWSCost Optimisation on AWS
Cost Optimisation on AWS
 
Crashing and cost plan-cpm
Crashing and cost plan-cpmCrashing and cost plan-cpm
Crashing and cost plan-cpm
 
Crashing in Project Management
Crashing in Project ManagementCrashing in Project Management
Crashing in Project Management
 
12 software maintenance
12 software maintenance12 software maintenance
12 software maintenance
 
Software maintenance
Software maintenanceSoftware maintenance
Software maintenance
 
The Art of Negotiating
The Art of NegotiatingThe Art of Negotiating
The Art of Negotiating
 
Purchasing ~Sourcing
Purchasing ~SourcingPurchasing ~Sourcing
Purchasing ~Sourcing
 

Similar to Time cost optimisation

Time Cost Trade Off
Time Cost Trade OffTime Cost Trade Off
Time Cost Trade Offssuserfe1b72
 
ملاحظات مهمة عن تعجيل المشاريع
ملاحظات مهمة عن تعجيل المشاريعملاحظات مهمة عن تعجيل المشاريع
ملاحظات مهمة عن تعجيل المشاريعDr. Mahmoud Al-Naimi
 
construction resource optimization 1.pptx
construction resource optimization 1.pptxconstruction resource optimization 1.pptx
construction resource optimization 1.pptxkimkov119
 
Project : formulation,evaluation and monitoring
Project : formulation,evaluation and monitoringProject : formulation,evaluation and monitoring
Project : formulation,evaluation and monitoringtarzan1990
 
Optimization of Time Restriction in Construction Project Management Using Lin...
Optimization of Time Restriction in Construction Project Management Using Lin...Optimization of Time Restriction in Construction Project Management Using Lin...
Optimization of Time Restriction in Construction Project Management Using Lin...IJERA Editor
 
Project Management & Engineering Economics
Project Management & Engineering EconomicsProject Management & Engineering Economics
Project Management & Engineering EconomicsDeepak Paithankar
 
ACT04Ch7PM - Project Crashing.pptx
ACT04Ch7PM - Project Crashing.pptxACT04Ch7PM - Project Crashing.pptx
ACT04Ch7PM - Project Crashing.pptxssuser85ddaa
 
Cpm module iii reference
Cpm module iii referenceCpm module iii reference
Cpm module iii referenceahsanrabbani
 
Identification of Bottleneck and Reducing Cycle Time of an Industrial Oven by...
Identification of Bottleneck and Reducing Cycle Time of an Industrial Oven by...Identification of Bottleneck and Reducing Cycle Time of an Industrial Oven by...
Identification of Bottleneck and Reducing Cycle Time of an Industrial Oven by...IRJET Journal
 
Project Management Diagnostics for Time Management
Project Management Diagnostics for Time ManagementProject Management Diagnostics for Time Management
Project Management Diagnostics for Time ManagementApril Davies, MA, CAPM
 
4 b. Project management - network analysis
4 b. Project management - network analysis4 b. Project management - network analysis
4 b. Project management - network analysisDr.R. SELVAM
 
PROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptxPROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptxTecnicoItca
 

Similar to Time cost optimisation (20)

vk1
vk1vk1
vk1
 
Time Cost Trade Off
Time Cost Trade OffTime Cost Trade Off
Time Cost Trade Off
 
ملاحظات مهمة عن تعجيل المشاريع
ملاحظات مهمة عن تعجيل المشاريعملاحظات مهمة عن تعجيل المشاريع
ملاحظات مهمة عن تعجيل المشاريع
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
construction resource optimization 1.pptx
construction resource optimization 1.pptxconstruction resource optimization 1.pptx
construction resource optimization 1.pptx
 
Project : formulation,evaluation and monitoring
Project : formulation,evaluation and monitoringProject : formulation,evaluation and monitoring
Project : formulation,evaluation and monitoring
 
Optimization of Time Restriction in Construction Project Management Using Lin...
Optimization of Time Restriction in Construction Project Management Using Lin...Optimization of Time Restriction in Construction Project Management Using Lin...
Optimization of Time Restriction in Construction Project Management Using Lin...
 
Project Management & Engineering Economics
Project Management & Engineering EconomicsProject Management & Engineering Economics
Project Management & Engineering Economics
 
ACT04Ch7PM - Project Crashing.pptx
ACT04Ch7PM - Project Crashing.pptxACT04Ch7PM - Project Crashing.pptx
ACT04Ch7PM - Project Crashing.pptx
 
Cpm module iii reference
Cpm module iii referenceCpm module iii reference
Cpm module iii reference
 
Identification of Bottleneck and Reducing Cycle Time of an Industrial Oven by...
Identification of Bottleneck and Reducing Cycle Time of an Industrial Oven by...Identification of Bottleneck and Reducing Cycle Time of an Industrial Oven by...
Identification of Bottleneck and Reducing Cycle Time of an Industrial Oven by...
 
Project Management Diagnostics for Time Management
Project Management Diagnostics for Time ManagementProject Management Diagnostics for Time Management
Project Management Diagnostics for Time Management
 
4 b. Project management - network analysis
4 b. Project management - network analysis4 b. Project management - network analysis
4 b. Project management - network analysis
 
Pert and CPM
Pert and CPMPert and CPM
Pert and CPM
 
Ch7 time cost
Ch7 time costCh7 time cost
Ch7 time cost
 
CPM AND PERT
CPM AND PERTCPM AND PERT
CPM AND PERT
 
PERT-CPM PPT.pptx
PERT-CPM PPT.pptxPERT-CPM PPT.pptx
PERT-CPM PPT.pptx
 
Per tand project crashing
Per tand project crashingPer tand project crashing
Per tand project crashing
 
PROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptxPROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptx
 
Construction Management
Construction ManagementConstruction Management
Construction Management
 

Recently uploaded

S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxSCMS School of Architecture
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . pptDineshKumar4165
 
Wadi Rum luxhotel lodge Analysis case study.pptx
Wadi Rum luxhotel lodge Analysis case study.pptxWadi Rum luxhotel lodge Analysis case study.pptx
Wadi Rum luxhotel lodge Analysis case study.pptxNadaHaitham1
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationBhangaleSonal
 
Computer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to ComputersComputer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to ComputersMairaAshraf6
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"mphochane1998
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapRishantSharmaFr
 
Engineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planesEngineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planesRAJNEESHKUMAR341697
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARKOUSTAV SARKAR
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfJiananWang21
 
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxOrlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxMuhammadAsimMuhammad6
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxSCMS School of Architecture
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaOmar Fathy
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Call Girls Mumbai
 
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best ServiceTamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Servicemeghakumariji156
 
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxA CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxmaisarahman1
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdfAldoGarca30
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxJuliansyahHarahap1
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...Amil baba
 

Recently uploaded (20)

S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
Wadi Rum luxhotel lodge Analysis case study.pptx
Wadi Rum luxhotel lodge Analysis case study.pptxWadi Rum luxhotel lodge Analysis case study.pptx
Wadi Rum luxhotel lodge Analysis case study.pptx
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
 
Computer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to ComputersComputer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to Computers
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
Engineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planesEngineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planes
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxOrlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
 
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best ServiceTamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
 
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxA CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
 

Time cost optimisation

  • 2.  The CPM, time is related to cost and the objective is to develop an optimum time –cost relationship. Sometimes it becomes necessary to complete the project earlier than the normal time, in such situations the cost of expediting the operations has to be considered. CPM makes the use of cost estimate alongwith time estimate and provides a schedule for completing the activities at the minimum total cost. LIMIT STATE METHOD
  • 3. This procedure improves planning, scheduling and controlling of the project and also assesses the possibility to arrive at a feasible and desirable time cost relationship. The project duration can be reduced by reducing the duration of only the critical activities in the project network. Reduction in the time duration can be done by: 1) Deploying more resources for early completion. 2)Relaxing the technical specifications LIMIT STATE METHOD
  • 4. OPTIMUM DURATION: the duration which gives the most economic cost for completing the project. TIME-COST ESTIMATES: 1) NORMAL ESTIMATE: emphasis is on cost with time being associated with minimum cost. 2) CRASH ESTIMATE: emphasis is on time . It involves the absolute minimum time required for the job and the cost necessary to achieve it. LIMIT STATE METHOD
  • 5. LIMIT STATE METHOD 5 COST TIME Minimum cost Optimum duration Cost rises if project is prolonged Cost rises if project is crashed
  • 7. LIMIT STATE METHOD INDIRECTCOST TIME Total indirect cost curve Over heads Outage loss
  • 8.  These are those expenditures which cannot clearly allocated to the individual activities of a project, but are assessed as whole. It includes expenditure related to administrative and establishment charges, supervision, expenditures on central store organisation, loss of revenue, lost profit, penalty etc. Indirect cost rises with increased duration. OUTAGE LOSS : loss in profits due to inability to meet demand or penalty due to delay. LIMIT STATE METHOD
  • 9.  Those expenditures which are directly chargeable to and can be identified specifically with the activities of the project. These include labour cost, material cost, equipment cost etc. LIMIT STATE METHOD
  • 11.  NORMAL TIME(tn): Standard time that an estimator whould usually allow for an activity. CRASH TIME(tc): minimum possible time in which an activity can be completed, by employing extra resources. NORMAL COST(Cn): Direct cost required to complete the acticity in normal time. CRASH COST(Cc): Direct cost corresponding to completion of activity within crash time. LIMIT STATE METHOD
  • 12.  COST SLOPE: It is the slope of the direct cost curve, approximated as a straight line in order to have a single cross slope. Cost Slope = crash cost-normal cost Normal time-crash time CS = Cc-Cn = ∆C tn-tc ∆t LIMIT STATE METHOD
  • 13.  It is the sum of direct and indirect costs. LIMIT STATE METHOD COST TIME Indirect cost curve direct cost curve total cost curve tc crash tn normal to optimum Minimum cost
  • 14.
  • 15. To examine « what will be the cost structure of the project if some or all of the activities is crashed ? » we should have following data with us :- - Normal direct cost data for each activity if it is to be completed in normal time duration . - crashed direct cost data if that activity is crashed. After this cost slope for each activity can be determined. - The indirect cost rate should also be known so that total cost can be determined. LIMIT STATE METHOD
  • 16.  Normal time of project- sum of the normal durations of each activity along the critical path.  Minimum time of project – sum of the crashed time duration of each activity along the critical path.  Non-critical activity need not to be speed up as their crashing is not going to decrease the project duration further. Moreover the cost will be high without any additional advantage.  Some non-critical activities become critical in the process of crashing the critical activities.  It is always better to start with crashing first that critical activity that has the lowest cost slope.Then we take another critical activity which is having next higher slope.
  • 17.  While crashing an activity fully by time “t” ,it should be examined whether its affecting the non –critical activity or not. 1 2 3 4 9(2) c A 5(4) B 6(2) D 5(3)
  • 18. STEPS IN TIME COST OPTIMISATION 1. Establish:- Direct cost time relationship for various activities of the project. 2. Determine:- Cost slope for various activities and arrange them in the ascending order of cost slope. 3. Compute:- Direct cost for the network with normal duration of activities. 4. Crash:- The activities in the critical path as per ranking i.e starting with the the activity having the lowest slope. 5. Continue:-Crashing the critical activities in the ascending order of the slope.
  • 19. 6. Crash:- Parallel non-critical activities which have become critical by the reduction of critical path duration due to crashing in steps 4 and 5. 7. Continue :- Crashing process through steps 4 to 6 , till a stage is reached beyond which no further crashing is possible. 8. Find:- Find total cost of the project at every stage by adding indirect costs to the direct costs determined above. 9. Plot:- Total cost–duration curve. 10. Pick Up:-The optimum duration corresponding to which least total project cost is obtained.
  • 20. . LIMIT STATE METHOD . ACTIVITY NORMAL DURATION (WEEKS) NORMAL COST (RUPEES) CRASH DURATION (WEEKS) CRASH COST (RUPEES) 1-2 4 4000 2 12000 2-3 5 3000 2 7500 2-4 7 3600 5 6000 3-4 4 5000 2 10000
  • 22. STEP 1. TIME SCALED VERSION OF NETWORK 1 32 4 7(5) 4(2) 4(2) 5(2)
  • 23. ACTIVITY Δ C (RUPEES) Δ t (WEEKS) COST SLOPE RS./WEEK 1-2 8000 2 4000 2-3 4500 3 1500 2-4 2400 2 1200 3-4 5000 2 2500
  • 24. The normal; duration of the project is the sum of the normal durations of each activity on the critical path. (It is not the sum of normal durations of all the activities). Therefore, Normal duration of the project = 4+5+4 = 13 weeks. Direct cost = 4000+3000+3600+5000 = 15600
  • 25. While crashing the activities, we shall first select that critical activity which has minimum cost slope. Let say Activity 2-4 has minimum cost slope of 1500 per week. Crash period is 2 weeks i.e. Δt = 5-2 = 3 weeks. However, crashing it by 3 weeks will affect non-critical activity 2-4 which has float of only 2 weeks. Hence restrict the crashing of 2-3 by 2 weeks only, in the first stage. New duration of the project= 13-2 = 11 weeks. Extra cost of crashing activity 2-3 by 2 weeks = 2*1500 = 3000 Direct cost of the project of 11 weeks duration = 15600 + 3000 = 18600 The time-scaled version of the network, after first stage crashing, for the project of 11 weeks duration is shown in the figure.
  • 26. 41 2 34(2) 3(2) 4(2) 7(5)
  • 27. From the figure above it is clear that activity 2-4 lying on the parallel path has also become critical, though activity 2-3 has still 1 week crashing left. However, Activity 2-3 cannot be crashed unless 2-4 is also crashed. So crash 2-3 &2-4 for 1 week simultaneously. Further crashing can be done with three alternatives:  crashing activities 2-3 & 2-4 simultaneously, having a combined cost slope of 1500 + 1200 = 2700 per week.  Crashing activities 3-4 & 2-4 simultaneously, having a combined cost slope of 2500 + 1200 = 3700 per week  Crashing activity 1-2 alone, having a cost slope of rupees 4500 per week out of these, the first alternative has the minimum cost slope. Thus, the extra cost of crashing 2-3 & 2-4 by 1 week = 2700 therefore, Direct cost of Project for 10 weeks duration = 18600 + 2700 = 21300 In this step, activity 2-3 has been crashed to its fullest extent.
  • 28. 1 2 3 4 4(2) 2(2) 4(2) 6(5)
  • 29. The remaining activities to be crashed are 1-2 , 2-4, 3-4. out of these, activities 2-4 & 3-4 are to be crashed jointly, with a combined cost slope of 2500 + 1200 = 3700. The cost slope of activity 1-2 is 4000 which is higher . Hence period of 6-5 = 1 week left. Hence only 1 week crashing will be done in this step, leading to a project duration of 9 weeks.
  • 30. cost of crashing 2-4 & 3-4 by 1 week. = 3700 * 1 = 3700 Therefore, cost of project for 9 weeks duration = 21300 + 3700 = 25000. The Time scaled version of the network for 9 weeks duration is shown in fig. we crashed activity 2-4 also to its fullest extent.
  • 31. Time- scaled network for 9 weeks Duration. 1 2 3 4 6(5) 4(2) 2(2) 3(2)
  • 32. Out of remaining critical activities ( i.e. 1-2&3-4) Activity 3-4 cannot be further crashed to its fullest crash period of 2 weeks, since it will affect activity 2-4 which has already been fully crashed. Hence activity 1-2 is the only remaining activity to be crashed. The period by which it can be crashed is = 4-2 = 2 weeks, reducing the project duration to 9-2 = 7 weeks. Extra cost of crashing 1-2 by 2 weeks = 2*4000 = 8000 Therefore, Direct cost of Project of 7 weeks duration = 25000 + 8000 = 33000.
  • 33. 1 2 3 5(2) 4 2(2) 2(2) 3(2)
  • 34. PROJECT DURATIO N 13 (NORMAL ) 11 10 9 7 DIRECT COST (RS.) 15600 18600 21200 25000 31000 INDIRECT COST (RS.) 26000 22000 20000 18000 14000 TOTAL COST (RS.) 41600 40600 41300 43000 47000