1. AN INDUSTRIAL TRAINING REPORT – I Done by
G.V.ROHIT Reg. No.:1011010072 At Simplex Infrastructures
Ltd. Brigade Plaza, Anand Rao circle, Bengaluru, Karnataka.
Submitted to Department of Civil Engineering Faculty of
Engineering and Technology SRM University (Under section
3 of UGC Act, 1956) SRM Nagar, Kattankulathur – 603203
Kancheepuram Dist. July 2012 1
2. BONAFIDE CERTIFICATE Certified that this Industrial
Training Report – I is a work ofG.V.ROHIT
(Reg.No.1011010072) who carried out the work at
SIMPLEXINFRASTRUCTURES LTD., Brigade Plaza,
Anand rao circle, Bengaluru,Karnataka.Class In charge
coordinator(Mr. V R PRASATH KUMAR) (Mr. K S
ANANDH) 2
3. 3
4. Acknowledgement It is always a pleasure to remind the
fine peoplein the Engineering program for their sincere
guidance I received touphold my practical as well as
theoretical skills in engineering. Firstly I would like to thank
Dr.C.Muthamizhchelvan (Director of E&T, SRM University)
formeticulously planning academic curriculum in such a way
thatstudents are not only academically sound but also industry
ready byincluding such industrial training patterns. I would
also like to thanks Mr. V.R. PrasathKumar (Class In-charge)
for the positive attitude he showed for mywork, always
allowing me to question him and giving prompt repliesfor my
uncertainties in all the fields including educational, social
andmanagerial work. I would also like to acknowledge and
myheartfelt gratitude to Mr.K.S.Anandh (coordinator) who
continuouslysupported me in every possible way, from initial
advice toencouragement till this date. I express my immense
pleasure and deep senseof gratitude to Sri I.Nanajee (General
Manager, CIVIL) and my guideand solicitor to Mr.Srinivas
2. (Planning) for spending his valuable timewith me and also
helped me in completion of task. Finally, I would also like to
thanks SriDebabrata ray (Site- In charge), Mr.Srikanth
(Asst.Manager) forgiving me this opportunity and guiding me
during the course of thetraining. 4
5. CONTENTSChapter No Topic Page No. 1 Introduction 1
2 Details of the project 2.1 Site location 2 2.2 Site map 3 2.3
About the project 4 3 Details of study 3.1 Detail of structure
5-6 3.2 Process of laying a slab 7-8 3.3 Batching plant 8-10
3.4 QA/QC Lab 10-11 3.5 Process of laying of columns 11-13
3.6 Model flat 14-15 3.7 Amenities provided 16 3.8 Safety 17
4 Conclusions 18 5
6. CHAPTER 1 INTRODUCTION We have been assigned
Hiranandini lake verandahs and Hiranandini hill
crestconstruction sites for field study by the company. These
are part of HIRANDINI UPSCALETOWNSHIP, a 32 acred
luxury residential project located in Begur village gracing
hulimavulake , off the bannerghatta road in Bengaluru .These
residential projects are a premium multistorey residential
towers developed by renoved developers HIRANANDINI.
The construction of the structures has been assigned
toSIMPLEX INFRASTRUCTURES LTD., Bengaluru. The
building has been designed by Architect
HAFEEZCONTRACTOR, Mumbai and the structural
consultants are MAHIMTURACONSULTANTS, the
associate engineers are WSP CANTOR SEINUK, New
York.About Developer Hiranandani is one of the largest real
estate developers in the countrydiversified into entertainment,
healthcare, hospitality, retail and call centers.
HiranandaniConstructions are known to incorporate a
fantastic balance of space management and naturalbeauty in
their Building Constructions. Some of the world renowned
developments areHiranandani Gardens in Powai, Meadows
3. and Estates in Thane.COMPANY PROFILE: Simplex
infrastructures limited are one of the pioneers and a total
solution provider in infrastructure and construction ambit.
Been in business since 1924 and present in almost all the
states and in middle east It employs 8110 people and has
capital equipments worth rupees 1296 crore in FY10 Ranked
7th amongst top 10 infrastructure companies by “construction
week” Has present order book of over 12,000 cr rupees with
over 150 site locations in india and overseas. The company
reported a turnover of 4,500 cr rupees and PAT of 127 cr in
FY10 The company commands a market capitalization of over
3,000 cr rupees. 6
7. CHAPTER 2 DETAILS OF THE PROJECT2.1SITE
LOCATION: The Hiranandini upscale project,Located off
Bannerghatta Road, in a welldeveloped area replete with the
best of social infrastructure, the project is accessible
fromElectronic City, to major corporates like Infosys, Wipro,
Dell, Siemens, 3M & HP, and thecountry’s best educational
institutions including IIM Bangalore, Sarala Birla Academy,
RyanInternational School, in addition to large Multispecialty
hospitals such as Wockhardt andApollo. Figure 2.1 peripheral
view of site location 7
8. 2.2SITE MAP : Figure2.2 Arial view of hiranandini
upscale project, bannerghatta(from left lakeverandahs, hill
crest, club meadows) Thoughtfully planned, secure, easily
accessible, the highlights of thedevelopment include
panoramic vistas from large French decks, a plush club house,
world-class gourmet restaurants, exquisite landscaping and
the best internal amenities. House ofHiranandani has skills to
nurture community, to connect people, to amplify the joys
andhappiness of togetherness. 8
9. 2.3ABOUT THE PROJECT:Hiranandini lake verandahs:
It is a classy project which redefines the style of living .This
4. project gives rich detailand fine finishes of interiors and
exteriors exhibiting unique design and style. It is welldesigned
home with landscaped garden and panoramic views. It is
3BHK multi-storeyedapartment for elite class, with varying
sizes of 1660, 1826 and 2061sq ft .Each flat costsranging from
80lakh to 1.1crore rupees. Figure 2.3 view of lake verandahs
after completion 9
10. CHAPTER 3 DETAILS OF FIELD
STUDY3.1DETAILS OF STRUCTURE: 1. The height of the
structure is 99.5mts. 2. The structure consists of 2 wings
(wing-A and wing-B). 3. Two wings are separated by an
inaccessible partition wall in every floor throughout the
structure. 4. Each wing consists of 4 flats in each floor
totalling 8 flats per floor. 5. The lake verandahs consist of 27
floors totalling 216 flats in them. 6. Apart from the 27 floors
there are 2 subsurface floors designed for parking purpose. 7.
These subsurface floors are well protected by retaining walls
with height varying from 8-12m . 8. A stilt lobby level is also
provided. 9. Each wing consists of 4 lift wells and 2 stair
cases Figure 3.1 a plan describing placement of lift wells and
stair cases in wing-A 10
11. Out of four 3BHK flats in every floor of a wing 1, 2
no.s Flats have area of2061 sqft and 3no has1660 sqft and
4no.has 1826 sqft. Figure 3.2 a typical floor plan of lake
verandahs project Figure3.3 a plan for flat no’s 1, 2 describing
positioning of various rooms 11
12. 3.2PROCESS OF LAYING A SLAB: In this all the
sophisticated equipments are used to finish the work in easy
andsimple method. The thickness of each slab is 20cm and
between 2 wings a strip is not castedimmediately but casted
after 25 days known as Expansion strip. The steel rods used
inconstruction are THERMAX STEEL from Germany. Also
shaft spaces are provided in slab for plumbing work Figure
5. 3.4, 3.5 views of shafts on and below the surface of the slab
Figure 3.6, 3.7 describes work of electrical conduting and cup
locks support After framing using shutter boards filmed with
shuttering oil, electricalconduting will be done, here cup locks
are used to support the frame, and then concrete ispoured over
the frame with the help of hydraulic jack and concrete pipes
which are used topump the concrete from transit mixer to the
place where slab has to be laid. To preventcoagulation inside
pipes, first a cream slurry cement paste has to be passed
through pipes forsmooth flow of concrete 12
13. Tower cranes are used to move the required material
from one place to other insite both vertically and horizontally.
The tower cranes can with held the wind force up toheight of
30m, beyond which they need to be clamped to nearby
column of building forsupport.Each tower crane costs about
Rs.95 lakhs Figure3.8 view of the tower crane from the site
office3.3BATCHING PLANT:M40 concrete mix is used here
for the construction of structure. A separate batching plant
ispresent near the site for the construction of lake verandahs
and hill crest structures. Figure 3.9 batching plant with a
transit mixer 13
14. Figure 3.10, 3.11 describes the control panel and closer
look to batching plant respectively. A Transit mixer is used to
transfer concrete from batching plant to the work site.It carries
around 7cubic mtr volume of concrete and takes about 15 min
to load.The main components of batching plant are Control
panel Silos Cement storage godown Small tower crane for
pushing ingredients into mix using trayThe batching plant
consists of silos which are used to store flyash and chemicals
accelerators and retarders. M15 M20 M25 M30 M35 M40 KG
KG KG KG KG KGCA I 564 538 534 526 521 494CA II 664
576 572 564 558 529FA II 725 738 727 710 697
636CEMENT 256 284 304 326 351 433FLY ASH 76 82 88
6. 94 101 126WATER 180 180 175 180 170 180CH. ADMIX
.8-1.2 % .8-1.2% .8-1.2% .8-1.2% .8-1.2% .8-1.2%W/B
RATIO .54 .49 .44 .42 .37 .32 Table 3.1 A Table describing
Mix Design Per Cubic Meter for various mix designs 14
15. The ingredients used in preparation of concrete are
coarse aggregate I, II andfine aggregate (pit sand, dead river
sand),cement, fly ash, water ,chemical admixtures .TheW/B
Ratio of M40 Mix is 0.32The chemical admixtures used are
MYK Save mix SP3.4Q/A & Q/C LAB (Quality assurance
&quality control lab): In this lab the quality and strength of
various building materials like cement, sand,concrete, water,
coarse aggregate are tested using various testing machines and
apparatus like vicat apparatus, Compression testing machine
flakiness and elongation index gauges, volume measuring jars
digital weighing scale(20kg max. and 2gm accuracy) sample
collecting trays pycnometerFigure 3.12, 3.13 describes view
of QA/QC lab and frame work for concrete cubes for
testingrespectively. 15
16. Figure 3.14 describes the view of curing tank near qa/qc
lab3.5LAYING OF COLUMNS: Figure 3.15 represents view
of various columns from below ground surface 16
17. Figure 3.16, 3.17 describes frame work for column
concreting and tor rings respectively. Columns are laid under
utmost care. steel rods are firmly placed and theseare
connected using different types of TOR RINGS with the help
of binding wire. About 8Tor rings are provided at spacing in
every column. Basically tor rings are of different typeslike
rectangular, square type, triangular, trapezoidal used for
connecting various amount ofsteel rods.tie rod, ropes are used
to place the shutters firmly around the column where
theconcrete is to be laid. Once the shutter is firmly placed then
the concrete is filled manually till0.5 mtr in order to avoid
HONEY COMBING. M40 grade concrete is used for
7. layingcolumns. The date on which concreting is done to a
column is written on column so that carehas to be taken to
cure it for 14 days 17
18. Figure3.18 the checklist for column concreting Prior to
concreting of a column it should fulfil all the requirements of
thechecklist for the column concreting ,it checks all the
activities and should meet theacceptance criteria after
checking the report will be signed by Foreman, Site engineer
andSector engineer before giving a nod to concreting 18
19. 3.6MODEL FLAT:Figure3.19 a view of living room in
model flat A Model flat is constructed near to the construction
site so that the buyers can have aglance about their future
house.Figure3.20 a view of master bedroom in model flat 19
20. Figure3.21 a view of study room in model
flatFigure3.22 a view of kitchen in model flat 20
21. 3.7AMENITIES PROVIDED IN LAKE
VERANDAHS: 100% Power Backup Children’s play area
Gymnasium Marble flooring Swimming pool Club house
Vaastu shaastra VRV central air-conditioning Wooden
flooring in master bedroom Exquisitely landscaped gardens
interspersed with water bodies, statues and childrens play
areas. Tree lined avenues and decorative iron railings set on
natural stone compound wall. Grand entrance hall and well
decorated corridors on all lift lobbies. High speed automatic
lifts. Ample parking space. Modern fire fighting system.
CCTV in entrance lobbies for security. Retail shopping. Club
house features include: Swimming pool. Fully equipped,
modern gymnasium. Tennis & Badminton courts.
Multipurpose hall. Childrens play area. Billiards room. Yoga,
Meditation and Aerobics centre. 21
22. 3.8SAFETY: The company has observed various safety
norms as per ISO standards and A safety office ispresent in
the construction site. Various safety measures have been taken
8. as shown below Figure 3.23, 3.24 represents the view of
safety nets tied around the building edges Figure 3.25 the
following items are provided as per ISO safety norms. 22
23. CHAPTER 4 CONCLUSIONS From the field study
report, it is evident that the construction is going on full
swing, butfrom according to the project monitoring chart, the
project is lagging behind the schedule fora period of about 6
months. As dated on 1st june2012 the construction for slab for
3th floor is going on and stillabout 24 floors are to be
constructed. The schedule to hand over the project is dated
forJanuary, 2014 at the earliest. To accomplish this task the
work should be done in 2 batches of workforce throughoutthe
day and the developers should lend more financial support
than present. Gracing the Hulimavu Lake, this most
happening realty destination for the elite will bea self-
sufficient and all encompassing community where its
residents will prosper forever. 23