SlideShare a Scribd company logo
1 of 11
Download to read offline
Copyright 2001 AADE National Drilling Technical Conference
This paper was prepared for presentation at the AADE 2001 National Drilling Conference, “Drilling Technology- The Next 100 years”, held at the Omni in Houston, Texas, March 27 - 29, 2001. This
conference was hosted by the Houston Chapter of the American Association of Drilling Engineers. The information presented in this paper does not reflect any position, claim or endorsement made or
implied by the American Association of Drilling Engineers, their officers or members. Questions concerning the content of this paper should be directed to the individuals listed as author/s of this work.
Abstract
A System Cost Analysis is a methodology used to
quantify drilling fluid costs to a common value, the
monies spent/saved which are impacted by the mud
system. Traditionally, most drilling fluid vendors and
operators are concerned only with the actual costs of the
mud materials, trucking, etc.. These “costs” only provide
a minor piece of the total impact which mud has on the
total well drilling costs. The System Cost Analysis
provides a more complete picture of drilling fluid costs by
considering both the material costs and actual time lost
and/or gained due to the fluid. In addition, production
data is readily included in a System Cost Analysis to
ascertain the amount of impairment seen in the drilling
process.
Items considered in an analysis include lost time due to
mud related problems such as lost circulation, borehole
instability, inability to log properly, ineffective solids
control, etc.. In addition, drilling fluids can have a
positive/negative impact on time by
increasing/decreasing ROP’s; the System Cost Analysis
fixes a dollar value to this important variable.
The measurement method provides a framework for
measuring both past, present and future performance of
drilling fluid performance in a given study area. This
paper describes how a System Cost Analysis is done
and gives examples of analyses completed on projects
in Western Canada and South America.
Introduction
Over the last number of years, the quantification of
drilling costs has been rising dramatically, especially in
offshore and remote locations. As a result, a number of
studies have been published on quantifying those costs
in order to both understand where the dollars are being
spent and where savings potential exists.
1-4
While drilling fluids normally account for a relatively
small percentage (< 10% normally) of a well cost, they
are directly involved in a large number of the costs
incurred on a well. This is especially true for borehole
instability where the correct drilling fluid choice can
eliminate problems, or conversely lead to large cost
overruns. Similarly, improper handling of solids control
equipment can lead to massive wellbore problems and
needlessly expensive drilling costs.
This paper will describe the use of a “System Costs
Analysis” methodology to quantify the actual costs of a
drilling fluid on the actual costs of drilling a well. The
analysis looks at more than just the material costs of
mud products. It also focuses on the problems
associated with poor drilling fluid performance and on
the benefits of that drilling fluids can provide in drilling
wells faster.
System Cost Analysis Methodology
A System Cost Analysis (SCA), in basic terms, equates
all incidences on a well impacted by drilling fluids, either
positive or negative, back to a fundamental value –
dollars and cents. The analysis attempts to remove the
“fuzzy” qualitative feelings often associated with drilling,
items such as “trying hard, unforseen circumstances,
bad luck, etc.”. While there will always be some
qualitative measurement needed to reflect trust and
honesty on the multidisciplinary task of drilling a well, the
System Cost Analysis provides a quantitiative
measurement tool. This tool is a direct measuring stick
on how well an operator and service company perform.
The simplest version of a System Cost Analysis for
drilling fluids is determined in one simple equation:
System Cost = Material Costs + Unproductive Time
This System Cost has been further refined, as will be
discussed in the following section.
The material costs are quite simple, the costs of the
drilling fluids added to the well, plus any associated
costs as required for trucking, engineering services, etc..
It is generally common for drilling fluid companies and
the contribution of fluids to be evaluated on this “material
AADE 01-NC-HO-19
Using a System Cost Analysis to Quantify Drilling Fluids and Solids Control Costs
Brent Warren and Leonard Baltoiu, Q’Max Solutions Inc.
2 BRENT WARREN AND LEONARD BALTOIU AADE 2001
cost” alone.
The unproductive or problem time for drilling fluids
involves any drilling function that has to do with drilling
fluids. A list of items is given in Table 1. Reaming and
cleaning, lost circulation, stuck pipe and mud rings are
just some of the items included in the trouble time cost.
The actual dollar value of the trouble time cost is
governed by the rig cost, usually determined on an
hourly basis.
In practice, the rig cost is agreed upon by the operator
and drilling fluid provider prior to the commencement of
the analysis. Any additional items to be covered in the
trouble time costs are also agreed upon by the parties
involved.
System Cost Analysis Methodology - Enhanced
Quantitative measurement of drilling fluid performance is
only one step in the process of how mud impacts on the
well performance and costs. Three additional items may
be included in a System Cost Analysis. First, drilling
fluids will certainly impact the time to drill as seen in rate-
of-penetration (ROP). ROP’s will vary greatly depending
upon densities, viscosities and filtration control
properties. Solids control and disposal costs are directly
related to mud types, especially in offshore and
environmentally sensitive regions. Thirdly, the
production of hydrocarbons from wells and fields may be
included if formation impairment is a real possibility.
Therefore the expanded System Cost equation is:
System Cost = Material Costs + (Trouble Time*hourly rig cost)
+ ROP impact + solids control/disposal + production
For example, comparison of water-based and oil-based
fluids by only the material costs only will invariably show
that water-based fluids cost less. The SCA may provide
a different answer once unproductive time, ROP,
solids/disposal costs and production data is included.
Benefits of a System Cost Analysis
System Cost Analyses can be done for any drilling
project, but are best utilized in areas where drilling is
troublesome and where a number of wells have
previously been drilled. In order to provide a relevant
analysis, ideally the wells included in the study should be
less than two years old. Wells older than this tend drill
somewhat slower (and are more costly) because of the
changes in technology (bits, MWD, etc.). In addition, the
wells used in the study should be of similar deviational
design and pass through similar lithologies since
wellbore trajectory plays a major part in well costs.
Drilling fluids system costs analysis are primarily used
for the following applications:
• Benchmarking: Drilling in troublesome areas often
involves problems with borehole instability. A
number of drilling fluids are often used to alleviate
that instability with varying degrees of success. The
System Cost Analysis provides a means of
determining which drilling fluid, casing design, etc. is
the most efficient fluid to use. In addition,
benchmarking provides a dollar value on the
problems which are most acute in the drilling region.
A risk cost analysis at this stage provides an
excellent tool for determining which drilling fluid and
casing design is optimum for drilling difficult,
expensive wells.
• Measuring change: Benchmarking in itself is a good
tool to determine the optimal method of how a
well/area is drilled now. Most times in difficult drilling
areas, the benchmarking exercise provides a tool for
indicating where improvements need to be made
and then provides a method of measuring those
changes. The real beauty of a dedicated system
cost analysis is in the cooperation of the drilling fluid
supplier to lower the overall well costs to the
operator by the cost effective means of mud
technologies and practices. Measuring change
provides a method of accomplishing this objective in
a quantifiable organized manner.
• Production measurement: Drilling fluids are the first
fluid to contact the native reservoir and often have a
large impact on the formation impairment of a
well/field. The System Cost Analysis is easily
modified to include the fluid costs as well as the
production numbers in a field. This type of analysis
is ideal for fields where different mud types are
being used and/or horizontal and vertical wells have
or will be drilled.
System Cost Analysis - Examples
1. Chicken/Route Area – Western Canada
The Chicken/Route area of the Alberta Foothills
(Figure 1) is characterized by instability problems
leading to some reaming and cleaning, but primarily
an inability to get logs to bottom. A system cost
analysis of 38 wells in the field was undertaken to
determine the root cause of the problem, whether
different drilling fluid types have helped this problem,
whether the problem was localized to a certain
portion of the field, and to determine if any
improvements could be made to the drilling fluid and
drilling practises. Typical well design in this field is
to drill with flocculated water as deep as possible
AADE 2001 Using a System Cost Analysis to Quantify Drilling Fluids and Solids Control Costs 3
(usually about 3600-3900 feet) and then mud-up to
either a gel-polymer or K2SO4-gel mud system to TD
around 5300 feet.
Figure 2 shows the wells in which logs either bridged
on first (or more) attempts and wells in which no logs
were obtained. Also on this area map is an
indication of where major lost circulation occurred.
As can be seen, logging problems were evident on
23 of the 38 wells in the study. These problems are
evident in the system costs per foot seen in the wells
as shown in Table 2 and Figure 3. Wells with the
bridging problems always had greater system costs
than those without the problems. Note that the data
is given per foot to normalize the data and is only for
the main hole section where mud was in the hole.
Following completion of the data gathering and
analysis phases of the SCA, a number of
conclusions and recommendations were made,
including:
- Wells in the 62-8 sector were generally trouble
free as seen by the system cost being twice the
material cost. This “twice value” or less of
system cost over material cost is generally seen
for land-based wells experiencing only minor
problems.
- majority of lost time which increased system
costs were due to logging difficulties as caused
by poor hole conditions. Logs normally bridged
somewhere in the water drilled section of the
well between 2625 and 3275 feet.
- A direct correlation existed between logging
problems and mud-up depth in which wells
which mudded-up deeper than 3925 feet were
most likely to experience logging problems. For
future wells, recommendations to drill no deeper
than 3900 feet with water were made.
- For all wells in area study, recommendation was
made to use silicate sweeps while floc water
drilling to stabailize the wellbore.
- Recommend drilling wells in 62-8 sector with
simple gel polymer mud systems previously
used. In all other areas, an inhibited fluid with
K+ as provided from K2SO4 was recommended.
The recommendations were implemented in the field
over a series of wells. The results from some of the
wells are shown in Table 3. All of the newly drilled
wells successfully ran logs to bottom on the first
attempt and hole problems due to wellbore instability
were minor. While the material costs were higher for
the post System Cost Analysis wells, the fewer
problems hours resulted in lower system costs.
2. Tipischa Jungle Basin – Ecuador
A System Cost Analysis in the Tipischa basin
compared the performance of an initial 14 well
program to a later 12 well program. The initial 14
wells were drilled with gel PHPA muds while a KNO3
ss-PHPA fluid was used on the later wells. A typical
well schematic with intermediate casing is shown in
Figure 4.
Table 4 and Figure 5 summarize the material and
system costs for the total well data for wells. Also
included is the solids control costs for the wells. The
following conclusions were made from the
information contained within the data:
- material costs/ft for the later drilled set of wells
was 13% greater than the previous wells. In
contrast the system costs were 5% less for the
later well grouping. The average amount of
unproductive time on the earlier wells was 79
hours while the later wells had 60 hours of
unproductive time.
- Solids control costs improved on the later wells
by 25% of $4.40/ft drilled. The savings were a
direct result of the KNO3 ss-PHPA system being
easier to strip solids from and tereby minimize
dumping and dilution of drilling fluid.
The Tipischa SCA study also analyzed drilling time
in terms of ROP, time to TD and time to rig release.
The data is summarized in Table 5 and Figure 6.
While the drilling fluid is certainly not the only
parameter which influences ROP, it is an important
variable. Other parameters such as bit type, weight
on bit, rpm, etc. are also of major importance. The
conclusions drawn from the data include:
- ROP, as refelcted in the drilling ft/day was ~ 175
ft/day faster in the later well set.
- The later well set was about 10% faster or 1.8
days to TD. This is due to a combination of
higher ROP’s and fewer unproductive hours.
- The days to rig release was also faster, 2.4 days
faster, on the later well set. The additional 0.6
days of savings resulted from increased
efficiencies in running logs and in conducting
liner/cementing operations.
Conclusions
• A System Cost Analysis provides a quantitative tool
for measuring the actual costs of drilling fluids on
overall well drilling costs.
• Simple System Cost is composed of drilling fluid
material costs, unproductive time due to drilling fluid
performance - converted to cost.
• An ideal total analysis of driling fluid performance
will include the System Cost as noted above, an
ROP analysis, solids control/disposal impact
4 BRENT WARREN AND LEONARD BALTOIU AADE 2001
analysis and formation impairment – production
review.
• The prime benefits of a SCA are (1) benchmarking
current drilling fluid performance and (2) measuring
the impact of changes on the drilling fluid
performance.
• System cost Analysis provides operators and service
companies with methodology of determining where
costs are most prevalent.
• In general terms for a land-based operation, a well
with minimal problems related to mud will have
System Costs no greater than twice the material
cost.
• SCA lends itself well to using a risk analysis method
for determing relative well costs using varying well
casing and drilling fluid combinations. The SCA will
provide a large number of accurate input data sets in
order to generate accurate output well cost
information.
Acknowledgements
The authors would like to thank the many people
involved in the gathering of the data included in these
studies and in this paper. Special thanks goes to
George Rajbar of Q’Max who has brought the SCA to a
usable and functional methodology.
Nomenclature
ft = feet
K+ = potassium sulphate containing fluids
KNO3 =potassium nitrate
K2SO4 = potassium sulfate
MWD = measurement while drilling
N/A = not available
PHPA = partially hydrolyzed polyacrylamide
ROP = drilling rate of penetration
rpm = revolutions per minute
ss-PHPA = sterically stabilized partially hydrolyzed
polyacrylamide
SCA = System Cost Analysis
TD=total depth
References
1. Carter, T.: “A Model for Evaluating Mud Engineer
Perfromance” presented at the 1996 AADE Drilling Fluids
Technology Conference, Houston, Texas, April 3-4.
2. Trantham J.A. and Deagen J.M.: “Barrier-Free Learning for
Well Construction” SPE Paper No. 62833, presented at
the 2000 SPE/AAPG Western Regional Meeting, Long
Beach, California, June 19-23
3. Thorogood, L., Jackson, M.D., Thorsen, O.H., “Delivering
World-Class Exploration Drilling-Integration of Design,
Planning, and Execution”, SPE Paper No. 61798,
presented at the 2000 IADC/SPE Drilling Conference,
New Orleans, February 23-25.
4. Aldred, W.D., “Improving Drilling Efficiency Through the
Application of PERFORM*, Performance by Risk
Management”, SPE Paper No. 57574, presented at the
1999 SPE/IADC Middle East Drilling Technology
Conference, Abu Dhabi, UAE, November 8-10.
AADE 2001 Using a System Cost Analysis to Quantify Drilling Fluids and Solids Control Costs 5
SYSTEM COST ITEM DESCRIPTION OF TROUBLE TIME INCLUDED
Lost Circulation § Material costs and time (rig and other items such as water hauler).
Reaming and Cleaning § Reaming and/or cleaning while rih or pooh due to poor hole conditions. Does not
normally include reaming undergauge hole after motor drilling.
Logs Bridging § Due to poor hole conditions. Includes time spent reaming logging tool to bottom,
time lost due to no logs run, hole conditioning and running tool back into hole.
Casing/Liner § As above noted in “Logs Bridging” section.
Sidetrack/Redrill § Includes time and material costs incurred from running cement plugs to reaching
original depth before plugging back. Does not include sidetracks for geological
reasons.
Stuck Pipe § Includes material/time due mechanically stuck pipe. May or may not include
problems because of differentially stuck pipe.
Gravel/Boulders § Material costs and time.
Mud Rings § Material costs and time.
Kicks § Material costs and time.
Additional Costs § Includes items such as cementing, disposal (fluids and cuttings), trucking,
engineering, etc. as appropriate.
Rate-of-Penetration § Hours on bitover footage intervals. May include time spent on trips.
Production Comparisons § Captures formation damage issues. Works best for large sample sets and fairly
homogeneous reservoirs.
Table 1 – Items Included in a System Cost Analysis
6 BRENT WARREN AND LEONARD BALTOIU AADE 2001
Well LSD Mud Type ft drilled $ material $ material/ft $ system cost $ sc/ft
02-20-61-7 W6 K+/K+ 1365 33445 24.50 42445 31.10
12-26-61-7W6 PHPA 3491 25248 7.23 70623 20.23
05-33-61-7 W6 gel chem 1654 18586 11.24 76336 46.17
09-11-62-7 W6 PHPA 738 2735 3.71 9860 13.36
07-03-62-7 W6 PHPA 3940 33261 8.44 151761 38.52
16-21-62-7W6 PHPA 1165 16614 14.26 46052 39.54
06-22-62-7 W6 PHPA 3694 13640 3.69 25265 6.84
16-20-62-7W6 gel chem 3002 11939 3.98 43252 14.41
09-31-62-7 W6 PHPA 1388 10423 7.51 37611 27.10
14-07-62-7 W6 PHPA 965 28023 29.05 38336 39.74
16-15-62-7 W6 K+/K+ 978 22792 23.31 97417 99.64
16-14-62-7 W6 /K+ 2510 38744 15.44 56744 22.61
05-12-62-7 W6 /K+ 2707 25330 9.36 30393 11.23
11-23-62-7 W6 K+/K+ 2461 34095 13.86 53408 21.70
03-28-62-7 W6 K+/K+ 2411 34830 14.44 48143 19.96
04-18-62-7 W6 K+/K+ 2871 45434 15.83 62872 21.90
10-23-62-8W6 PHPA 548 4467 8.15 13280 24.24
14-11-62-8W6 PHPA 2126 12649 5.95 25024 11.77
11-14-62-8W6 PHPA 1234 13168 10.67 32293 26.18
05-26-62-8 W6 /K+ 2280 23632 10.36 33945 14.89
01-33-62-8 W6 PHPA 1772 8972 5.06 18160 10.25
02-04-63-8 W6 PHPA 1611 9102 5.65 29352 18.22
04-09-63-8 W6 PHPA 1453 5655 3.89 16530 11.37
08-12-63-8 W6 gel chem 600 9755 16.25 75943 126.49
13-12-63-8W6 gel chem 876 10353 11.82 45228 51.63
03-13-63-8W6 gel chem 1732 20868 12.05 30993 17.89
06-14-63-8 W6 gel chem 912 9742 10.68 63180 69.27
13-28-63-8W6 PHPA 1188 5480 4.61 15043 12.67
02-31-63-8W6 PHPA 1401 5297 3.78 16360 11.68
12-32-63-8W6 PHPA 1332 5190 3.90 13440 10.09
12-33-63-8W6 PHPA 1690 6667 3.95 28042 16.60
16-20-63-8W6 PHPA 755 5603 7.43 60353 79.98
13-14-63-8W6 PHPA 2051 11880 5.79 19005 9.27
04-15-63-8W6 PHPA 1325 6903 5.21 47966 36.19
10-18-63-8W6 PHPA 509 6102 12.00 32915 64.72
13-19-63-8W6 PHPA 525 5463 10.41 9963 18.98
07-21-63-8W6 PHPA 2461 5204 2.11 7829 3.18
05-22-63-8W6 PHPA 2927 6824 2.33 46387 15.85
10-22-63-8W6 gel chem 663 10699 16.14 66762 100.74
TOTAL WELL MEAN 1712 15265 9.73 41408 31.29
61-7 MEAN 2170 25760 14.33 63135 32.50
62-7 MEAN 2218 24451 12.53 53932 28.97
62-8 MEAN 1592 12578 8.04 24540 17.46
63-8 MEAN 1334 8155 7.67 34738 37.49
Table 2 - Chicken Area (Alberta) Material and System Cost Values in Main hole mud drilled section. Lowest
mean material cost/ft as well as the highest system cost/ft was in the 63-8 section. The 62-8 section had the
lowest system cost mean and therefore the fewest amount of problems.
AADE 2001 Using a System Cost Analysis to Quantify Drilling Fluids and Solids Control Costs 7
Well LSD Mud Type ft drilled $ material $ material/ft $ system cost $ sc/ft
61-7 MEAN 2170 25760 14.33 63135 32.50
06-36-61-07 K2SO4 2648 78335 29.58 90335 34.11
62-7 MEAN 2218 24451 12.53 53932 28.97
16-30-62-07 K2SO4 2415 29286 12.13 56474 23.38
12-18-62-07 K2SO4 2740 45821 16.73 64196 23.43
63-8 MEAN 1334 8155 7.67 34738 37.49
12-27-63-08 K2SO4 722 6720 9.31 24720 34.23
16-07-63-08 K2SO4 6115 46163 7.55 54788 8.96
Table 3 - Chicken Area System Cost Analysis Comparison for wells drilled pre- and post-analysis. The
individual well locations are for the post-drilled SCA wells. Note that all of the post-analysis wells achieved
successful logs on first attempt. The well @ 06-36-61-07 had a high material cost due to massive lost circulation.
WELL NAME Ft
DRILLED
$
MATERIAL
$ MATERIAL/ft $ SYSTEM
COST
$ SYSTEM
COST/ft
$ SOLIDS
CONTROL
$ SOLIDS
CONTROL/ft
INITIAL 14 WELL SET
M 8 8870 297531 33.54 421281 47.50 172,000 19.39
D 1 9599 351809 35.77 735559 74.79 186,000 19.38
F 18b 13 8656 135135 15.74 300135 34.96 132,000 15.25
F 18b 14 8557 122928 14.37 244178 28.54 122,000 14.26
F18b 15 8762 96549 11.02 96549 11.02 136,000 15.52
D 2 9600 216650 22.60 352900 36.81 134,000 13.96
F 18b 16 8150 149112 18.28 229112 28.08 116,000 14.23
D 3 9356 305746 32.68 610746 65.28 232,000 24.80
D 7 10805 218232 20.20 385732 35.70 148,000 13.70
F 18b 20 8880 N/A N/A N/A N/A 145,000 16.33
D 8 9093 148487 16.33 343487 37.77 100,000 11.00
F 18b 21 8880 N/A N/A N/A N/A 188,000 21.17
M 4A 9145 144592 15.81 144592 15.81 125,000 13.67
F 18b 26 9388 240252 25.65 547752 58.47 166,000 17.68
LATER 12 WELL SET
T 1 10255 193515 18.87 434765 42.40 159,000 15.50
F18b 27 9061 281302 31.04 753802 83.18 130,000 14.35
P 1 9017 243320 26.98 329570 36.55 141,000 15.64
F 18b 25 9036 191113 21.15 256113 28.34 57,000 6.31
F 18b 37 9413 427153 43.93 528403 54.35 121,000 12.85
D 6 9220 243940 26.46 360190 39.07 131,000 14.21
M 4A2 8771 234838 26.77 347338 39.60 84,000 9.58
M 4A3 9362 163872 17.50 321997 34.39 93,000 9.93
T 1 9249 219644 23.75 318394 34.42 98,000 10.60
F 18b 46 8890 264718 29.78 395968 44.54 93,000 10.46
M 4A4 9207 N/A N/A N/A N/A 89,000 9.67
T 2 9088 239000 26.30 312750 34.41 138,000 15.18
Initial 14 MEAN 9135 218588 23.51 417088 44.79 150,100 16.43
Later 12 MEAN 9240 245674 26.59 396299 42.84 111,200 12.03
Table 4 - System Cost Analysis raw data and solids handling costs for Ecuador Tipischa Basin area. Data is
included for total well analysis, surface hole to TD.
8 BRENT WARREN AND LEONARD BALTOIU AADE 2001
WELL
NAME
Ft
DRILLED
DRILLING
DAYS
ft/
DRILLING
DAY
DAYS
to TD
ft/ DAYS
to TD
DAYS to
RIG
RELEASE
ft/ DAYS to
RIG RELEASE
TROUBLE
TIME (hrs)
INITIAL 14 WELL
SET
M 8 8870 6.7 1318 24.0 370 26.6 334 49.5
D 1 9599 12.4 795 31.0 317 35.0 281 153.5
F 18b 13 8656 7.4 1168 14.0 615 15.7 546 66.0
F 18b 14 8557 7.3 1170 13.7 623 19.1 448 48.5
F18b 15 8762 N/A N/A N/A N/A 17.0 515 N/A
D 2 9600 8.8 1085 19.0 505 21.0 457 54.5
F 18b 16 8150 7.5 1094 13.6 600 17.4 470 22.0
D 3 9356 10.5 888 31.0 302 41.0 228 122.0
D 7 10805 14.7 735 24.6 440 27.5 393 67.0
F 18b 20 8880 8.9 1003 21.0 423 25.0 355 20.5
D 8 9093 7.8 1173 16.8 541 21.0 433 78.0
F 18b 21 8880 N/A N/A N/A N/A 34.0 261 N/A
M 4A 9145 N/A N/A N/A N/A 24.0 381 N/A
F 18b 26 9388 13.9 675 26.5 353 29.9 313 123.0
LATER 12 WELL
SET
T 1 10255 13.0 789 28.7 357 31.7 323 96.5
F18b 27 9061 11.3 801 18.7 485 29.4 308 179.0
P 1 9017 9.2 977 23.5 384 26.3 343 34.5
F 18b 25 9036 5.4 1662 11.3 799 14.6 620 26.0
F 18b 37 9413 7.4 1317 26.5 367 32.1 303 40.5
D 6 9220 5.9 1553 17.1 540 19.5 474 46.5
M 4A2 8771 8.3 1053 17.0 516 19.6 448 45.0
M 4A3 9362 9.8 955 18.6 502 19.5 479 63.25
T 1 9249 5.8 1591 16.4 565 17.5 528 39.5
F 18b 46 8890 9.3 956 18.9 471 22.5 396 52.5
M 4A4 9207 N/A N/A N/A N/A 21.0 438 N/A
T 2 9088 6.5 1398 19.2 474 20.8 438 29.5
Initial 14
MEAN
9135 9.6 1009 21.4 463 25.4 387 79
Later 12
MEAN
9240 8.4 1186 19.6 496 23.0 424 60
Table 5 - Time Analysis information for wells drilled in Ecuador Tipischa Basin area. Initial 14 wells used a gel-
PHPA system while the later 12 wells used a KNO3 ss-PHPA fluid. Drilling Days is a measure of rotating time to
reach total depth.
AADE 2001 Using a System Cost Analysis to Quantify Drilling Fluids and Solids Control Costs 9
Figure 1 - Location of Chicken/Route area in West Central Alberta
ΠΠ ΠΠ σσ
ΠΠ
ƒƒ σσ σσ ƒƒσσ
σσ σσ σσ σσσσσσ ΠΠ
ƒƒΠΠ
σσσσ
63
∋∋ σσ
∋∋ ΠΠ
ΠΠ ΠΠ ΠΠ ΠΠ σσ
σσ ΠΠ ƒƒ σσ
ΠΠ ΠΠ ΠΠ ƒƒ
ΠΠ
62
σσ
σσ
∋∋
61
08 07
Figure 2 – Chicken/Route area detailed well map. Wells with ΠΠ symbol indicate those with no logging or lost
circulation problems, σσ symbol indicates logging problems or no logs run and ∋∋ symbol is for wells with lost
circulation. A well with ƒƒ symbol has both logging and lost circulation problems.
Edmonton
Calgary
∗∗
∗∗
AALLBBEERRTTAA
Chicken/
Route
10 BRENT WARREN AND LEONARD BALTOIU AADE 2001
Figure 3 – Comparative material and system costs for Main Hole section of wells in the various sectors of the
Chicken/Route area. Data taken from Table 2.
HOLE SIZE DEPTH CASING SIZE
17.5" 1400-1700' 13.375"
12.25" 7000-9000' 9.625"
8.5" 8500-10000' 7"
Figure 4 – Typical well design for Ecuadorian Tipischa Jungle basin wells.
0
5
10
15
20
25
30
35
40
61-7 MEAN 62-7 MEAN 62-8 MEAN 63-8 MEAN
$/ftcost
$ material/ft
$ system cost/ft
AADE 2001 Using a System Cost Analysis to Quantify Drilling Fluids and Solids Control Costs 11
Figure 5 – Comparison of material costs, system costs and solids costs for initial 14 and later 12 wells in
Tipischa study area. Costs are given per foot to normalize the data and are shown for the entire well. Data taken
from Table 4.
Figure 6 – Comparison of drilling rate (ROP), time to total depth and time to rig release for initial 14 and later 12
wells in Tipischa study area. Information is presented in value ft per days to normalize data. Data taken from
Table 5.
0
5
10
15
20
25
30
35
40
45
50
$ material/ft $ system cost/ft $ solids cost/ft
$/ftcost
Initial 14 MEAN
Later 12 MEAN
0
200
400
600
800
1000
1200
1400
ft/ DRILLING DAY ft/ DAYS to TD ft/ DAYS to RIG
RELEASE
ft/day
Initial 14 MEAN
Later 12 MEAN

More Related Content

What's hot

A mathematical modeling proposal for a Multiple Tasks Periodic Capacitated Ar...
A mathematical modeling proposal for a Multiple Tasks Periodic Capacitated Ar...A mathematical modeling proposal for a Multiple Tasks Periodic Capacitated Ar...
A mathematical modeling proposal for a Multiple Tasks Periodic Capacitated Ar...IJERA Editor
 
Use of GCxGC-TOFMS in litigious mixed condensate plumes: Environmental forens...
Use of GCxGC-TOFMS in litigious mixed condensate plumes: Environmental forens...Use of GCxGC-TOFMS in litigious mixed condensate plumes: Environmental forens...
Use of GCxGC-TOFMS in litigious mixed condensate plumes: Environmental forens...Chemistry Matters Inc.
 
Final Newea 9 09 10 Mh Rehab
Final Newea 9 09 10 Mh RehabFinal Newea 9 09 10 Mh Rehab
Final Newea 9 09 10 Mh Rehabmfrench62
 
UntitledExcessive Water Production Diagnostic and Control - Case Study Jake O...
UntitledExcessive Water Production Diagnostic and Control - Case Study Jake O...UntitledExcessive Water Production Diagnostic and Control - Case Study Jake O...
UntitledExcessive Water Production Diagnostic and Control - Case Study Jake O...Mohanned Mahjoup
 
Session 83 Ola Wik
Session 83 Ola WikSession 83 Ola Wik
Session 83 Ola WikOla Wik
 
Black Oil Reservoir Simulation Model Mis-Match Assessment through Computer-As...
Black Oil Reservoir Simulation Model Mis-Match Assessment through Computer-As...Black Oil Reservoir Simulation Model Mis-Match Assessment through Computer-As...
Black Oil Reservoir Simulation Model Mis-Match Assessment through Computer-As...Carlos R. Conde
 
Cost (& Time) Optimization of Hydrogeological Studies
Cost (& Time) Optimization of Hydrogeological StudiesCost (& Time) Optimization of Hydrogeological Studies
Cost (& Time) Optimization of Hydrogeological StudiesGidahatari Agua
 
15 Reasons Not to Use Percent Removals
15 Reasons Not to Use Percent Removals15 Reasons Not to Use Percent Removals
15 Reasons Not to Use Percent RemovalsMarcus Quigley
 
Economic analysis for cvat panama
Economic analysis for cvat panamaEconomic analysis for cvat panama
Economic analysis for cvat panamaofrias1
 
In situ permeability testing in boreholes
In situ permeability testing in boreholesIn situ permeability testing in boreholes
In situ permeability testing in boreholesMartin Preene
 
Download-manuals-ground water-manual-gw-volume4fieldmanualgeo-hydrologypartiii
 Download-manuals-ground water-manual-gw-volume4fieldmanualgeo-hydrologypartiii Download-manuals-ground water-manual-gw-volume4fieldmanualgeo-hydrologypartiii
Download-manuals-ground water-manual-gw-volume4fieldmanualgeo-hydrologypartiiihydrologyproject001
 
Liquid & Gas Flowmetering & Custody Measurement
Liquid & Gas Flowmetering & Custody MeasurementLiquid & Gas Flowmetering & Custody Measurement
Liquid & Gas Flowmetering & Custody MeasurementpetroEDGE
 
IRJET- Experimental Study on Flow through Venturimeter
IRJET- Experimental Study on Flow through VenturimeterIRJET- Experimental Study on Flow through Venturimeter
IRJET- Experimental Study on Flow through VenturimeterIRJET Journal
 
Impact of the Hydrographic Changing in the Open Drains Cross Sections on the ...
Impact of the Hydrographic Changing in the Open Drains Cross Sections on the ...Impact of the Hydrographic Changing in the Open Drains Cross Sections on the ...
Impact of the Hydrographic Changing in the Open Drains Cross Sections on the ...IJMER
 
Exergo-economic analysis of a seawater reverse osmosis plant with various ret...
Exergo-economic analysis of a seawater reverse osmosis plant with various ret...Exergo-economic analysis of a seawater reverse osmosis plant with various ret...
Exergo-economic analysis of a seawater reverse osmosis plant with various ret...ahmad598
 
EXPERIMENTAL STUDIES ON THE INTAKE PORT OF A DIESEL ENGINE TO DETERMINE SWIRL
EXPERIMENTAL STUDIES ON THE INTAKE PORT OF A DIESEL ENGINE TO DETERMINE SWIRLEXPERIMENTAL STUDIES ON THE INTAKE PORT OF A DIESEL ENGINE TO DETERMINE SWIRL
EXPERIMENTAL STUDIES ON THE INTAKE PORT OF A DIESEL ENGINE TO DETERMINE SWIRLijmech
 
Download-manuals-surface water-manual-sw-volume3fieldmanualhydro-meteorology...
 Download-manuals-surface water-manual-sw-volume3fieldmanualhydro-meteorology... Download-manuals-surface water-manual-sw-volume3fieldmanualhydro-meteorology...
Download-manuals-surface water-manual-sw-volume3fieldmanualhydro-meteorology...hydrologyproject001
 

What's hot (19)

A mathematical modeling proposal for a Multiple Tasks Periodic Capacitated Ar...
A mathematical modeling proposal for a Multiple Tasks Periodic Capacitated Ar...A mathematical modeling proposal for a Multiple Tasks Periodic Capacitated Ar...
A mathematical modeling proposal for a Multiple Tasks Periodic Capacitated Ar...
 
Use of GCxGC-TOFMS in litigious mixed condensate plumes: Environmental forens...
Use of GCxGC-TOFMS in litigious mixed condensate plumes: Environmental forens...Use of GCxGC-TOFMS in litigious mixed condensate plumes: Environmental forens...
Use of GCxGC-TOFMS in litigious mixed condensate plumes: Environmental forens...
 
Final Newea 9 09 10 Mh Rehab
Final Newea 9 09 10 Mh RehabFinal Newea 9 09 10 Mh Rehab
Final Newea 9 09 10 Mh Rehab
 
UntitledExcessive Water Production Diagnostic and Control - Case Study Jake O...
UntitledExcessive Water Production Diagnostic and Control - Case Study Jake O...UntitledExcessive Water Production Diagnostic and Control - Case Study Jake O...
UntitledExcessive Water Production Diagnostic and Control - Case Study Jake O...
 
Session 83 Ola Wik
Session 83 Ola WikSession 83 Ola Wik
Session 83 Ola Wik
 
Black Oil Reservoir Simulation Model Mis-Match Assessment through Computer-As...
Black Oil Reservoir Simulation Model Mis-Match Assessment through Computer-As...Black Oil Reservoir Simulation Model Mis-Match Assessment through Computer-As...
Black Oil Reservoir Simulation Model Mis-Match Assessment through Computer-As...
 
Cost (& Time) Optimization of Hydrogeological Studies
Cost (& Time) Optimization of Hydrogeological StudiesCost (& Time) Optimization of Hydrogeological Studies
Cost (& Time) Optimization of Hydrogeological Studies
 
HECRAS Bridge Scour Analysis
HECRAS Bridge Scour AnalysisHECRAS Bridge Scour Analysis
HECRAS Bridge Scour Analysis
 
15 Reasons Not to Use Percent Removals
15 Reasons Not to Use Percent Removals15 Reasons Not to Use Percent Removals
15 Reasons Not to Use Percent Removals
 
Economic analysis for cvat panama
Economic analysis for cvat panamaEconomic analysis for cvat panama
Economic analysis for cvat panama
 
In situ permeability testing in boreholes
In situ permeability testing in boreholesIn situ permeability testing in boreholes
In situ permeability testing in boreholes
 
CPTu quality
CPTu qualityCPTu quality
CPTu quality
 
Download-manuals-ground water-manual-gw-volume4fieldmanualgeo-hydrologypartiii
 Download-manuals-ground water-manual-gw-volume4fieldmanualgeo-hydrologypartiii Download-manuals-ground water-manual-gw-volume4fieldmanualgeo-hydrologypartiii
Download-manuals-ground water-manual-gw-volume4fieldmanualgeo-hydrologypartiii
 
Liquid & Gas Flowmetering & Custody Measurement
Liquid & Gas Flowmetering & Custody MeasurementLiquid & Gas Flowmetering & Custody Measurement
Liquid & Gas Flowmetering & Custody Measurement
 
IRJET- Experimental Study on Flow through Venturimeter
IRJET- Experimental Study on Flow through VenturimeterIRJET- Experimental Study on Flow through Venturimeter
IRJET- Experimental Study on Flow through Venturimeter
 
Impact of the Hydrographic Changing in the Open Drains Cross Sections on the ...
Impact of the Hydrographic Changing in the Open Drains Cross Sections on the ...Impact of the Hydrographic Changing in the Open Drains Cross Sections on the ...
Impact of the Hydrographic Changing in the Open Drains Cross Sections on the ...
 
Exergo-economic analysis of a seawater reverse osmosis plant with various ret...
Exergo-economic analysis of a seawater reverse osmosis plant with various ret...Exergo-economic analysis of a seawater reverse osmosis plant with various ret...
Exergo-economic analysis of a seawater reverse osmosis plant with various ret...
 
EXPERIMENTAL STUDIES ON THE INTAKE PORT OF A DIESEL ENGINE TO DETERMINE SWIRL
EXPERIMENTAL STUDIES ON THE INTAKE PORT OF A DIESEL ENGINE TO DETERMINE SWIRLEXPERIMENTAL STUDIES ON THE INTAKE PORT OF A DIESEL ENGINE TO DETERMINE SWIRL
EXPERIMENTAL STUDIES ON THE INTAKE PORT OF A DIESEL ENGINE TO DETERMINE SWIRL
 
Download-manuals-surface water-manual-sw-volume3fieldmanualhydro-meteorology...
 Download-manuals-surface water-manual-sw-volume3fieldmanualhydro-meteorology... Download-manuals-surface water-manual-sw-volume3fieldmanualhydro-meteorology...
Download-manuals-surface water-manual-sw-volume3fieldmanualhydro-meteorology...
 

Similar to Using a system cost analysis to quantify drilling fluids and

[Oil & Gas White Paper] Getting Ahead of the Game: adopting best practices in...
[Oil & Gas White Paper] Getting Ahead of the Game: adopting best practices in...[Oil & Gas White Paper] Getting Ahead of the Game: adopting best practices in...
[Oil & Gas White Paper] Getting Ahead of the Game: adopting best practices in...Schneider Electric
 
Artificial lifting method
Artificial lifting methodArtificial lifting method
Artificial lifting methodNafihTaher
 
Drilling Engineering - Drilling Economics
Drilling Engineering - Drilling EconomicsDrilling Engineering - Drilling Economics
Drilling Engineering - Drilling EconomicsJames Craig
 
Mastering pipe prover calibration methods.
Mastering pipe prover calibration methods.Mastering pipe prover calibration methods.
Mastering pipe prover calibration methods.Erik Smits
 
Experimental and Computational Fluid Dynamics (CFD) Analysis of Additively Ma...
Experimental and Computational Fluid Dynamics (CFD) Analysis of Additively Ma...Experimental and Computational Fluid Dynamics (CFD) Analysis of Additively Ma...
Experimental and Computational Fluid Dynamics (CFD) Analysis of Additively Ma...IRJET Journal
 
MASS MASTER METERING SOLUTION FOR USERS PAIN_ FCRI 2012 KS NR _2_
MASS MASTER METERING SOLUTION FOR USERS PAIN_ FCRI 2012 KS NR _2_MASS MASTER METERING SOLUTION FOR USERS PAIN_ FCRI 2012 KS NR _2_
MASS MASTER METERING SOLUTION FOR USERS PAIN_ FCRI 2012 KS NR _2_Naimish Raval
 
Basics of Preparing an Air Emissions Inventory
Basics of Preparing an Air Emissions InventoryBasics of Preparing an Air Emissions Inventory
Basics of Preparing an Air Emissions InventoryMarcKarell
 
Reducing Manufacturing Cost through Value Stream Mapping
Reducing Manufacturing Cost through Value Stream MappingReducing Manufacturing Cost through Value Stream Mapping
Reducing Manufacturing Cost through Value Stream MappingEditor IJCATR
 
SPE 171517_Estimating Probability of Failure _2014_Final
SPE 171517_Estimating Probability of Failure _2014_FinalSPE 171517_Estimating Probability of Failure _2014_Final
SPE 171517_Estimating Probability of Failure _2014_FinalKatrina Carter-Journet
 
A practical approach for ship construction cost estimation
A practical approach for ship construction cost estimationA practical approach for ship construction cost estimation
A practical approach for ship construction cost estimationGopalakrishnan P
 
Remedial Process Optimization - Moffett RAB
Remedial Process Optimization - Moffett RABRemedial Process Optimization - Moffett RAB
Remedial Process Optimization - Moffett RABSteve Williams
 
Navy Moffett Environmental Restoration Program 2008 Review/2009 Goals
Navy Moffett Environmental Restoration Program 2008 Review/2009 GoalsNavy Moffett Environmental Restoration Program 2008 Review/2009 Goals
Navy Moffett Environmental Restoration Program 2008 Review/2009 GoalsSteve Williams
 
HOW-TO-REDUCE-TIME-SPENT-BY-DRIVERS-ON-SITE-AND-IMPROVE-THEIR-TREATMENT-ISSUE...
HOW-TO-REDUCE-TIME-SPENT-BY-DRIVERS-ON-SITE-AND-IMPROVE-THEIR-TREATMENT-ISSUE...HOW-TO-REDUCE-TIME-SPENT-BY-DRIVERS-ON-SITE-AND-IMPROVE-THEIR-TREATMENT-ISSUE...
HOW-TO-REDUCE-TIME-SPENT-BY-DRIVERS-ON-SITE-AND-IMPROVE-THEIR-TREATMENT-ISSUE...soledad520819
 
Improving the Availability of Lift Stations through Optimized Redundant / Bac...
Improving the Availability of Lift Stations through Optimized Redundant / Bac...Improving the Availability of Lift Stations through Optimized Redundant / Bac...
Improving the Availability of Lift Stations through Optimized Redundant / Bac...Vecoin
 
IRJET- Value Engineering: Better Way of Implementing Conventional Methods
IRJET- Value Engineering: Better Way of Implementing Conventional MethodsIRJET- Value Engineering: Better Way of Implementing Conventional Methods
IRJET- Value Engineering: Better Way of Implementing Conventional MethodsIRJET Journal
 
An optimised approach for the inspection of aboveground
An optimised approach for the inspection of abovegroundAn optimised approach for the inspection of aboveground
An optimised approach for the inspection of abovegroundPatrick Schüller
 
A Novel Integrated Approach To Oil Production Optimization And Limiting The W...
A Novel Integrated Approach To Oil Production Optimization And Limiting The W...A Novel Integrated Approach To Oil Production Optimization And Limiting The W...
A Novel Integrated Approach To Oil Production Optimization And Limiting The W...Amy Isleb
 

Similar to Using a system cost analysis to quantify drilling fluids and (20)

[Oil & Gas White Paper] Getting Ahead of the Game: adopting best practices in...
[Oil & Gas White Paper] Getting Ahead of the Game: adopting best practices in...[Oil & Gas White Paper] Getting Ahead of the Game: adopting best practices in...
[Oil & Gas White Paper] Getting Ahead of the Game: adopting best practices in...
 
Artificial lifting method
Artificial lifting methodArtificial lifting method
Artificial lifting method
 
Drilling Engineering - Drilling Economics
Drilling Engineering - Drilling EconomicsDrilling Engineering - Drilling Economics
Drilling Engineering - Drilling Economics
 
Mastering pipe prover calibration methods.
Mastering pipe prover calibration methods.Mastering pipe prover calibration methods.
Mastering pipe prover calibration methods.
 
Experimental and Computational Fluid Dynamics (CFD) Analysis of Additively Ma...
Experimental and Computational Fluid Dynamics (CFD) Analysis of Additively Ma...Experimental and Computational Fluid Dynamics (CFD) Analysis of Additively Ma...
Experimental and Computational Fluid Dynamics (CFD) Analysis of Additively Ma...
 
MASS MASTER METERING SOLUTION FOR USERS PAIN_ FCRI 2012 KS NR _2_
MASS MASTER METERING SOLUTION FOR USERS PAIN_ FCRI 2012 KS NR _2_MASS MASTER METERING SOLUTION FOR USERS PAIN_ FCRI 2012 KS NR _2_
MASS MASTER METERING SOLUTION FOR USERS PAIN_ FCRI 2012 KS NR _2_
 
Basics of Preparing an Air Emissions Inventory
Basics of Preparing an Air Emissions InventoryBasics of Preparing an Air Emissions Inventory
Basics of Preparing an Air Emissions Inventory
 
Reducing Manufacturing Cost through Value Stream Mapping
Reducing Manufacturing Cost through Value Stream MappingReducing Manufacturing Cost through Value Stream Mapping
Reducing Manufacturing Cost through Value Stream Mapping
 
Preventive maintenance
Preventive maintenancePreventive maintenance
Preventive maintenance
 
SPE 171517_Estimating Probability of Failure _2014_Final
SPE 171517_Estimating Probability of Failure _2014_FinalSPE 171517_Estimating Probability of Failure _2014_Final
SPE 171517_Estimating Probability of Failure _2014_Final
 
A practical approach for ship construction cost estimation
A practical approach for ship construction cost estimationA practical approach for ship construction cost estimation
A practical approach for ship construction cost estimation
 
Remedial Process Optimization - Moffett RAB
Remedial Process Optimization - Moffett RABRemedial Process Optimization - Moffett RAB
Remedial Process Optimization - Moffett RAB
 
Navy Moffett Environmental Restoration Program 2008 Review/2009 Goals
Navy Moffett Environmental Restoration Program 2008 Review/2009 GoalsNavy Moffett Environmental Restoration Program 2008 Review/2009 Goals
Navy Moffett Environmental Restoration Program 2008 Review/2009 Goals
 
Vsm
VsmVsm
Vsm
 
HOW-TO-REDUCE-TIME-SPENT-BY-DRIVERS-ON-SITE-AND-IMPROVE-THEIR-TREATMENT-ISSUE...
HOW-TO-REDUCE-TIME-SPENT-BY-DRIVERS-ON-SITE-AND-IMPROVE-THEIR-TREATMENT-ISSUE...HOW-TO-REDUCE-TIME-SPENT-BY-DRIVERS-ON-SITE-AND-IMPROVE-THEIR-TREATMENT-ISSUE...
HOW-TO-REDUCE-TIME-SPENT-BY-DRIVERS-ON-SITE-AND-IMPROVE-THEIR-TREATMENT-ISSUE...
 
Improving the Availability of Lift Stations through Optimized Redundant / Bac...
Improving the Availability of Lift Stations through Optimized Redundant / Bac...Improving the Availability of Lift Stations through Optimized Redundant / Bac...
Improving the Availability of Lift Stations through Optimized Redundant / Bac...
 
IRJET- Value Engineering: Better Way of Implementing Conventional Methods
IRJET- Value Engineering: Better Way of Implementing Conventional MethodsIRJET- Value Engineering: Better Way of Implementing Conventional Methods
IRJET- Value Engineering: Better Way of Implementing Conventional Methods
 
software Paper published.pdf
software Paper published.pdfsoftware Paper published.pdf
software Paper published.pdf
 
An optimised approach for the inspection of aboveground
An optimised approach for the inspection of abovegroundAn optimised approach for the inspection of aboveground
An optimised approach for the inspection of aboveground
 
A Novel Integrated Approach To Oil Production Optimization And Limiting The W...
A Novel Integrated Approach To Oil Production Optimization And Limiting The W...A Novel Integrated Approach To Oil Production Optimization And Limiting The W...
A Novel Integrated Approach To Oil Production Optimization And Limiting The W...
 

More from amrhaggag

بنعمل ايه على الصفحة والجروب - أزاى نتعامل مع السكر 1 و 2 من واقع التجربة
بنعمل ايه على الصفحة والجروب - أزاى نتعامل مع السكر 1 و 2 من واقع التجربةبنعمل ايه على الصفحة والجروب - أزاى نتعامل مع السكر 1 و 2 من واقع التجربة
بنعمل ايه على الصفحة والجروب - أزاى نتعامل مع السكر 1 و 2 من واقع التجربةamrhaggag
 
Drilling rig operations a to z rotary drilling rig components
Drilling rig operations  a to z rotary drilling rig componentsDrilling rig operations  a to z rotary drilling rig components
Drilling rig operations a to z rotary drilling rig componentsamrhaggag
 
Drilling rig components ( illustrated glossary )
Drilling rig components ( illustrated glossary )Drilling rig components ( illustrated glossary )
Drilling rig components ( illustrated glossary )amrhaggag
 
Directional drilling
Directional drillingDirectional drilling
Directional drillingamrhaggag
 
rig drilling_equipment
 rig drilling_equipment rig drilling_equipment
rig drilling_equipmentamrhaggag
 
Wild well wc formulas and graphas
Wild well wc formulas and graphasWild well wc formulas and graphas
Wild well wc formulas and graphasamrhaggag
 
Tubing standard
Tubing standardTubing standard
Tubing standardamrhaggag
 
Sysdrill.pdf
Sysdrill.pdfSysdrill.pdf
Sysdrill.pdfamrhaggag
 
Check list for drilling new well
Check list for drilling new wellCheck list for drilling new well
Check list for drilling new wellamrhaggag
 
Wait and weight vs. driller
Wait and weight vs. drillerWait and weight vs. driller
Wait and weight vs. drilleramrhaggag
 
Directional survey hand book
Directional survey hand book Directional survey hand book
Directional survey hand book amrhaggag
 
Wellhead specifications
Wellhead specificationsWellhead specifications
Wellhead specificationsamrhaggag
 
Well control intro presentation
Well control intro presentationWell control intro presentation
Well control intro presentationamrhaggag
 
Oilfield glossary
Oilfield glossaryOilfield glossary
Oilfield glossaryamrhaggag
 
Land rig handbook
Land rig handbookLand rig handbook
Land rig handbookamrhaggag
 
Intro to petroleum geology
Intro to petroleum geologyIntro to petroleum geology
Intro to petroleum geologyamrhaggag
 
Intro to oil well drilling ops pt 4
Intro to oil well drilling ops pt 4Intro to oil well drilling ops pt 4
Intro to oil well drilling ops pt 4amrhaggag
 

More from amrhaggag (20)

بنعمل ايه على الصفحة والجروب - أزاى نتعامل مع السكر 1 و 2 من واقع التجربة
بنعمل ايه على الصفحة والجروب - أزاى نتعامل مع السكر 1 و 2 من واقع التجربةبنعمل ايه على الصفحة والجروب - أزاى نتعامل مع السكر 1 و 2 من واقع التجربة
بنعمل ايه على الصفحة والجروب - أزاى نتعامل مع السكر 1 و 2 من واقع التجربة
 
Drilling rig operations a to z rotary drilling rig components
Drilling rig operations  a to z rotary drilling rig componentsDrilling rig operations  a to z rotary drilling rig components
Drilling rig operations a to z rotary drilling rig components
 
Drilling rig components ( illustrated glossary )
Drilling rig components ( illustrated glossary )Drilling rig components ( illustrated glossary )
Drilling rig components ( illustrated glossary )
 
Directional drilling
Directional drillingDirectional drilling
Directional drilling
 
rig drilling_equipment
 rig drilling_equipment rig drilling_equipment
rig drilling_equipment
 
Wild well wc formulas and graphas
Wild well wc formulas and graphasWild well wc formulas and graphas
Wild well wc formulas and graphas
 
Tubing standard
Tubing standardTubing standard
Tubing standard
 
Sysdrill.pdf
Sysdrill.pdfSysdrill.pdf
Sysdrill.pdf
 
DDMS
DDMSDDMS
DDMS
 
Check list for drilling new well
Check list for drilling new wellCheck list for drilling new well
Check list for drilling new well
 
Wait and weight vs. driller
Wait and weight vs. drillerWait and weight vs. driller
Wait and weight vs. driller
 
Kill sheet
Kill sheetKill sheet
Kill sheet
 
Directional survey hand book
Directional survey hand book Directional survey hand book
Directional survey hand book
 
Wellhead
WellheadWellhead
Wellhead
 
Wellhead specifications
Wellhead specificationsWellhead specifications
Wellhead specifications
 
Well control intro presentation
Well control intro presentationWell control intro presentation
Well control intro presentation
 
Oilfield glossary
Oilfield glossaryOilfield glossary
Oilfield glossary
 
Land rig handbook
Land rig handbookLand rig handbook
Land rig handbook
 
Intro to petroleum geology
Intro to petroleum geologyIntro to petroleum geology
Intro to petroleum geology
 
Intro to oil well drilling ops pt 4
Intro to oil well drilling ops pt 4Intro to oil well drilling ops pt 4
Intro to oil well drilling ops pt 4
 

Recently uploaded

Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 

Recently uploaded (20)

Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 

Using a system cost analysis to quantify drilling fluids and

  • 1. Copyright 2001 AADE National Drilling Technical Conference This paper was prepared for presentation at the AADE 2001 National Drilling Conference, “Drilling Technology- The Next 100 years”, held at the Omni in Houston, Texas, March 27 - 29, 2001. This conference was hosted by the Houston Chapter of the American Association of Drilling Engineers. The information presented in this paper does not reflect any position, claim or endorsement made or implied by the American Association of Drilling Engineers, their officers or members. Questions concerning the content of this paper should be directed to the individuals listed as author/s of this work. Abstract A System Cost Analysis is a methodology used to quantify drilling fluid costs to a common value, the monies spent/saved which are impacted by the mud system. Traditionally, most drilling fluid vendors and operators are concerned only with the actual costs of the mud materials, trucking, etc.. These “costs” only provide a minor piece of the total impact which mud has on the total well drilling costs. The System Cost Analysis provides a more complete picture of drilling fluid costs by considering both the material costs and actual time lost and/or gained due to the fluid. In addition, production data is readily included in a System Cost Analysis to ascertain the amount of impairment seen in the drilling process. Items considered in an analysis include lost time due to mud related problems such as lost circulation, borehole instability, inability to log properly, ineffective solids control, etc.. In addition, drilling fluids can have a positive/negative impact on time by increasing/decreasing ROP’s; the System Cost Analysis fixes a dollar value to this important variable. The measurement method provides a framework for measuring both past, present and future performance of drilling fluid performance in a given study area. This paper describes how a System Cost Analysis is done and gives examples of analyses completed on projects in Western Canada and South America. Introduction Over the last number of years, the quantification of drilling costs has been rising dramatically, especially in offshore and remote locations. As a result, a number of studies have been published on quantifying those costs in order to both understand where the dollars are being spent and where savings potential exists. 1-4 While drilling fluids normally account for a relatively small percentage (< 10% normally) of a well cost, they are directly involved in a large number of the costs incurred on a well. This is especially true for borehole instability where the correct drilling fluid choice can eliminate problems, or conversely lead to large cost overruns. Similarly, improper handling of solids control equipment can lead to massive wellbore problems and needlessly expensive drilling costs. This paper will describe the use of a “System Costs Analysis” methodology to quantify the actual costs of a drilling fluid on the actual costs of drilling a well. The analysis looks at more than just the material costs of mud products. It also focuses on the problems associated with poor drilling fluid performance and on the benefits of that drilling fluids can provide in drilling wells faster. System Cost Analysis Methodology A System Cost Analysis (SCA), in basic terms, equates all incidences on a well impacted by drilling fluids, either positive or negative, back to a fundamental value – dollars and cents. The analysis attempts to remove the “fuzzy” qualitative feelings often associated with drilling, items such as “trying hard, unforseen circumstances, bad luck, etc.”. While there will always be some qualitative measurement needed to reflect trust and honesty on the multidisciplinary task of drilling a well, the System Cost Analysis provides a quantitiative measurement tool. This tool is a direct measuring stick on how well an operator and service company perform. The simplest version of a System Cost Analysis for drilling fluids is determined in one simple equation: System Cost = Material Costs + Unproductive Time This System Cost has been further refined, as will be discussed in the following section. The material costs are quite simple, the costs of the drilling fluids added to the well, plus any associated costs as required for trucking, engineering services, etc.. It is generally common for drilling fluid companies and the contribution of fluids to be evaluated on this “material AADE 01-NC-HO-19 Using a System Cost Analysis to Quantify Drilling Fluids and Solids Control Costs Brent Warren and Leonard Baltoiu, Q’Max Solutions Inc.
  • 2. 2 BRENT WARREN AND LEONARD BALTOIU AADE 2001 cost” alone. The unproductive or problem time for drilling fluids involves any drilling function that has to do with drilling fluids. A list of items is given in Table 1. Reaming and cleaning, lost circulation, stuck pipe and mud rings are just some of the items included in the trouble time cost. The actual dollar value of the trouble time cost is governed by the rig cost, usually determined on an hourly basis. In practice, the rig cost is agreed upon by the operator and drilling fluid provider prior to the commencement of the analysis. Any additional items to be covered in the trouble time costs are also agreed upon by the parties involved. System Cost Analysis Methodology - Enhanced Quantitative measurement of drilling fluid performance is only one step in the process of how mud impacts on the well performance and costs. Three additional items may be included in a System Cost Analysis. First, drilling fluids will certainly impact the time to drill as seen in rate- of-penetration (ROP). ROP’s will vary greatly depending upon densities, viscosities and filtration control properties. Solids control and disposal costs are directly related to mud types, especially in offshore and environmentally sensitive regions. Thirdly, the production of hydrocarbons from wells and fields may be included if formation impairment is a real possibility. Therefore the expanded System Cost equation is: System Cost = Material Costs + (Trouble Time*hourly rig cost) + ROP impact + solids control/disposal + production For example, comparison of water-based and oil-based fluids by only the material costs only will invariably show that water-based fluids cost less. The SCA may provide a different answer once unproductive time, ROP, solids/disposal costs and production data is included. Benefits of a System Cost Analysis System Cost Analyses can be done for any drilling project, but are best utilized in areas where drilling is troublesome and where a number of wells have previously been drilled. In order to provide a relevant analysis, ideally the wells included in the study should be less than two years old. Wells older than this tend drill somewhat slower (and are more costly) because of the changes in technology (bits, MWD, etc.). In addition, the wells used in the study should be of similar deviational design and pass through similar lithologies since wellbore trajectory plays a major part in well costs. Drilling fluids system costs analysis are primarily used for the following applications: • Benchmarking: Drilling in troublesome areas often involves problems with borehole instability. A number of drilling fluids are often used to alleviate that instability with varying degrees of success. The System Cost Analysis provides a means of determining which drilling fluid, casing design, etc. is the most efficient fluid to use. In addition, benchmarking provides a dollar value on the problems which are most acute in the drilling region. A risk cost analysis at this stage provides an excellent tool for determining which drilling fluid and casing design is optimum for drilling difficult, expensive wells. • Measuring change: Benchmarking in itself is a good tool to determine the optimal method of how a well/area is drilled now. Most times in difficult drilling areas, the benchmarking exercise provides a tool for indicating where improvements need to be made and then provides a method of measuring those changes. The real beauty of a dedicated system cost analysis is in the cooperation of the drilling fluid supplier to lower the overall well costs to the operator by the cost effective means of mud technologies and practices. Measuring change provides a method of accomplishing this objective in a quantifiable organized manner. • Production measurement: Drilling fluids are the first fluid to contact the native reservoir and often have a large impact on the formation impairment of a well/field. The System Cost Analysis is easily modified to include the fluid costs as well as the production numbers in a field. This type of analysis is ideal for fields where different mud types are being used and/or horizontal and vertical wells have or will be drilled. System Cost Analysis - Examples 1. Chicken/Route Area – Western Canada The Chicken/Route area of the Alberta Foothills (Figure 1) is characterized by instability problems leading to some reaming and cleaning, but primarily an inability to get logs to bottom. A system cost analysis of 38 wells in the field was undertaken to determine the root cause of the problem, whether different drilling fluid types have helped this problem, whether the problem was localized to a certain portion of the field, and to determine if any improvements could be made to the drilling fluid and drilling practises. Typical well design in this field is to drill with flocculated water as deep as possible
  • 3. AADE 2001 Using a System Cost Analysis to Quantify Drilling Fluids and Solids Control Costs 3 (usually about 3600-3900 feet) and then mud-up to either a gel-polymer or K2SO4-gel mud system to TD around 5300 feet. Figure 2 shows the wells in which logs either bridged on first (or more) attempts and wells in which no logs were obtained. Also on this area map is an indication of where major lost circulation occurred. As can be seen, logging problems were evident on 23 of the 38 wells in the study. These problems are evident in the system costs per foot seen in the wells as shown in Table 2 and Figure 3. Wells with the bridging problems always had greater system costs than those without the problems. Note that the data is given per foot to normalize the data and is only for the main hole section where mud was in the hole. Following completion of the data gathering and analysis phases of the SCA, a number of conclusions and recommendations were made, including: - Wells in the 62-8 sector were generally trouble free as seen by the system cost being twice the material cost. This “twice value” or less of system cost over material cost is generally seen for land-based wells experiencing only minor problems. - majority of lost time which increased system costs were due to logging difficulties as caused by poor hole conditions. Logs normally bridged somewhere in the water drilled section of the well between 2625 and 3275 feet. - A direct correlation existed between logging problems and mud-up depth in which wells which mudded-up deeper than 3925 feet were most likely to experience logging problems. For future wells, recommendations to drill no deeper than 3900 feet with water were made. - For all wells in area study, recommendation was made to use silicate sweeps while floc water drilling to stabailize the wellbore. - Recommend drilling wells in 62-8 sector with simple gel polymer mud systems previously used. In all other areas, an inhibited fluid with K+ as provided from K2SO4 was recommended. The recommendations were implemented in the field over a series of wells. The results from some of the wells are shown in Table 3. All of the newly drilled wells successfully ran logs to bottom on the first attempt and hole problems due to wellbore instability were minor. While the material costs were higher for the post System Cost Analysis wells, the fewer problems hours resulted in lower system costs. 2. Tipischa Jungle Basin – Ecuador A System Cost Analysis in the Tipischa basin compared the performance of an initial 14 well program to a later 12 well program. The initial 14 wells were drilled with gel PHPA muds while a KNO3 ss-PHPA fluid was used on the later wells. A typical well schematic with intermediate casing is shown in Figure 4. Table 4 and Figure 5 summarize the material and system costs for the total well data for wells. Also included is the solids control costs for the wells. The following conclusions were made from the information contained within the data: - material costs/ft for the later drilled set of wells was 13% greater than the previous wells. In contrast the system costs were 5% less for the later well grouping. The average amount of unproductive time on the earlier wells was 79 hours while the later wells had 60 hours of unproductive time. - Solids control costs improved on the later wells by 25% of $4.40/ft drilled. The savings were a direct result of the KNO3 ss-PHPA system being easier to strip solids from and tereby minimize dumping and dilution of drilling fluid. The Tipischa SCA study also analyzed drilling time in terms of ROP, time to TD and time to rig release. The data is summarized in Table 5 and Figure 6. While the drilling fluid is certainly not the only parameter which influences ROP, it is an important variable. Other parameters such as bit type, weight on bit, rpm, etc. are also of major importance. The conclusions drawn from the data include: - ROP, as refelcted in the drilling ft/day was ~ 175 ft/day faster in the later well set. - The later well set was about 10% faster or 1.8 days to TD. This is due to a combination of higher ROP’s and fewer unproductive hours. - The days to rig release was also faster, 2.4 days faster, on the later well set. The additional 0.6 days of savings resulted from increased efficiencies in running logs and in conducting liner/cementing operations. Conclusions • A System Cost Analysis provides a quantitative tool for measuring the actual costs of drilling fluids on overall well drilling costs. • Simple System Cost is composed of drilling fluid material costs, unproductive time due to drilling fluid performance - converted to cost. • An ideal total analysis of driling fluid performance will include the System Cost as noted above, an ROP analysis, solids control/disposal impact
  • 4. 4 BRENT WARREN AND LEONARD BALTOIU AADE 2001 analysis and formation impairment – production review. • The prime benefits of a SCA are (1) benchmarking current drilling fluid performance and (2) measuring the impact of changes on the drilling fluid performance. • System cost Analysis provides operators and service companies with methodology of determining where costs are most prevalent. • In general terms for a land-based operation, a well with minimal problems related to mud will have System Costs no greater than twice the material cost. • SCA lends itself well to using a risk analysis method for determing relative well costs using varying well casing and drilling fluid combinations. The SCA will provide a large number of accurate input data sets in order to generate accurate output well cost information. Acknowledgements The authors would like to thank the many people involved in the gathering of the data included in these studies and in this paper. Special thanks goes to George Rajbar of Q’Max who has brought the SCA to a usable and functional methodology. Nomenclature ft = feet K+ = potassium sulphate containing fluids KNO3 =potassium nitrate K2SO4 = potassium sulfate MWD = measurement while drilling N/A = not available PHPA = partially hydrolyzed polyacrylamide ROP = drilling rate of penetration rpm = revolutions per minute ss-PHPA = sterically stabilized partially hydrolyzed polyacrylamide SCA = System Cost Analysis TD=total depth References 1. Carter, T.: “A Model for Evaluating Mud Engineer Perfromance” presented at the 1996 AADE Drilling Fluids Technology Conference, Houston, Texas, April 3-4. 2. Trantham J.A. and Deagen J.M.: “Barrier-Free Learning for Well Construction” SPE Paper No. 62833, presented at the 2000 SPE/AAPG Western Regional Meeting, Long Beach, California, June 19-23 3. Thorogood, L., Jackson, M.D., Thorsen, O.H., “Delivering World-Class Exploration Drilling-Integration of Design, Planning, and Execution”, SPE Paper No. 61798, presented at the 2000 IADC/SPE Drilling Conference, New Orleans, February 23-25. 4. Aldred, W.D., “Improving Drilling Efficiency Through the Application of PERFORM*, Performance by Risk Management”, SPE Paper No. 57574, presented at the 1999 SPE/IADC Middle East Drilling Technology Conference, Abu Dhabi, UAE, November 8-10.
  • 5. AADE 2001 Using a System Cost Analysis to Quantify Drilling Fluids and Solids Control Costs 5 SYSTEM COST ITEM DESCRIPTION OF TROUBLE TIME INCLUDED Lost Circulation § Material costs and time (rig and other items such as water hauler). Reaming and Cleaning § Reaming and/or cleaning while rih or pooh due to poor hole conditions. Does not normally include reaming undergauge hole after motor drilling. Logs Bridging § Due to poor hole conditions. Includes time spent reaming logging tool to bottom, time lost due to no logs run, hole conditioning and running tool back into hole. Casing/Liner § As above noted in “Logs Bridging” section. Sidetrack/Redrill § Includes time and material costs incurred from running cement plugs to reaching original depth before plugging back. Does not include sidetracks for geological reasons. Stuck Pipe § Includes material/time due mechanically stuck pipe. May or may not include problems because of differentially stuck pipe. Gravel/Boulders § Material costs and time. Mud Rings § Material costs and time. Kicks § Material costs and time. Additional Costs § Includes items such as cementing, disposal (fluids and cuttings), trucking, engineering, etc. as appropriate. Rate-of-Penetration § Hours on bitover footage intervals. May include time spent on trips. Production Comparisons § Captures formation damage issues. Works best for large sample sets and fairly homogeneous reservoirs. Table 1 – Items Included in a System Cost Analysis
  • 6. 6 BRENT WARREN AND LEONARD BALTOIU AADE 2001 Well LSD Mud Type ft drilled $ material $ material/ft $ system cost $ sc/ft 02-20-61-7 W6 K+/K+ 1365 33445 24.50 42445 31.10 12-26-61-7W6 PHPA 3491 25248 7.23 70623 20.23 05-33-61-7 W6 gel chem 1654 18586 11.24 76336 46.17 09-11-62-7 W6 PHPA 738 2735 3.71 9860 13.36 07-03-62-7 W6 PHPA 3940 33261 8.44 151761 38.52 16-21-62-7W6 PHPA 1165 16614 14.26 46052 39.54 06-22-62-7 W6 PHPA 3694 13640 3.69 25265 6.84 16-20-62-7W6 gel chem 3002 11939 3.98 43252 14.41 09-31-62-7 W6 PHPA 1388 10423 7.51 37611 27.10 14-07-62-7 W6 PHPA 965 28023 29.05 38336 39.74 16-15-62-7 W6 K+/K+ 978 22792 23.31 97417 99.64 16-14-62-7 W6 /K+ 2510 38744 15.44 56744 22.61 05-12-62-7 W6 /K+ 2707 25330 9.36 30393 11.23 11-23-62-7 W6 K+/K+ 2461 34095 13.86 53408 21.70 03-28-62-7 W6 K+/K+ 2411 34830 14.44 48143 19.96 04-18-62-7 W6 K+/K+ 2871 45434 15.83 62872 21.90 10-23-62-8W6 PHPA 548 4467 8.15 13280 24.24 14-11-62-8W6 PHPA 2126 12649 5.95 25024 11.77 11-14-62-8W6 PHPA 1234 13168 10.67 32293 26.18 05-26-62-8 W6 /K+ 2280 23632 10.36 33945 14.89 01-33-62-8 W6 PHPA 1772 8972 5.06 18160 10.25 02-04-63-8 W6 PHPA 1611 9102 5.65 29352 18.22 04-09-63-8 W6 PHPA 1453 5655 3.89 16530 11.37 08-12-63-8 W6 gel chem 600 9755 16.25 75943 126.49 13-12-63-8W6 gel chem 876 10353 11.82 45228 51.63 03-13-63-8W6 gel chem 1732 20868 12.05 30993 17.89 06-14-63-8 W6 gel chem 912 9742 10.68 63180 69.27 13-28-63-8W6 PHPA 1188 5480 4.61 15043 12.67 02-31-63-8W6 PHPA 1401 5297 3.78 16360 11.68 12-32-63-8W6 PHPA 1332 5190 3.90 13440 10.09 12-33-63-8W6 PHPA 1690 6667 3.95 28042 16.60 16-20-63-8W6 PHPA 755 5603 7.43 60353 79.98 13-14-63-8W6 PHPA 2051 11880 5.79 19005 9.27 04-15-63-8W6 PHPA 1325 6903 5.21 47966 36.19 10-18-63-8W6 PHPA 509 6102 12.00 32915 64.72 13-19-63-8W6 PHPA 525 5463 10.41 9963 18.98 07-21-63-8W6 PHPA 2461 5204 2.11 7829 3.18 05-22-63-8W6 PHPA 2927 6824 2.33 46387 15.85 10-22-63-8W6 gel chem 663 10699 16.14 66762 100.74 TOTAL WELL MEAN 1712 15265 9.73 41408 31.29 61-7 MEAN 2170 25760 14.33 63135 32.50 62-7 MEAN 2218 24451 12.53 53932 28.97 62-8 MEAN 1592 12578 8.04 24540 17.46 63-8 MEAN 1334 8155 7.67 34738 37.49 Table 2 - Chicken Area (Alberta) Material and System Cost Values in Main hole mud drilled section. Lowest mean material cost/ft as well as the highest system cost/ft was in the 63-8 section. The 62-8 section had the lowest system cost mean and therefore the fewest amount of problems.
  • 7. AADE 2001 Using a System Cost Analysis to Quantify Drilling Fluids and Solids Control Costs 7 Well LSD Mud Type ft drilled $ material $ material/ft $ system cost $ sc/ft 61-7 MEAN 2170 25760 14.33 63135 32.50 06-36-61-07 K2SO4 2648 78335 29.58 90335 34.11 62-7 MEAN 2218 24451 12.53 53932 28.97 16-30-62-07 K2SO4 2415 29286 12.13 56474 23.38 12-18-62-07 K2SO4 2740 45821 16.73 64196 23.43 63-8 MEAN 1334 8155 7.67 34738 37.49 12-27-63-08 K2SO4 722 6720 9.31 24720 34.23 16-07-63-08 K2SO4 6115 46163 7.55 54788 8.96 Table 3 - Chicken Area System Cost Analysis Comparison for wells drilled pre- and post-analysis. The individual well locations are for the post-drilled SCA wells. Note that all of the post-analysis wells achieved successful logs on first attempt. The well @ 06-36-61-07 had a high material cost due to massive lost circulation. WELL NAME Ft DRILLED $ MATERIAL $ MATERIAL/ft $ SYSTEM COST $ SYSTEM COST/ft $ SOLIDS CONTROL $ SOLIDS CONTROL/ft INITIAL 14 WELL SET M 8 8870 297531 33.54 421281 47.50 172,000 19.39 D 1 9599 351809 35.77 735559 74.79 186,000 19.38 F 18b 13 8656 135135 15.74 300135 34.96 132,000 15.25 F 18b 14 8557 122928 14.37 244178 28.54 122,000 14.26 F18b 15 8762 96549 11.02 96549 11.02 136,000 15.52 D 2 9600 216650 22.60 352900 36.81 134,000 13.96 F 18b 16 8150 149112 18.28 229112 28.08 116,000 14.23 D 3 9356 305746 32.68 610746 65.28 232,000 24.80 D 7 10805 218232 20.20 385732 35.70 148,000 13.70 F 18b 20 8880 N/A N/A N/A N/A 145,000 16.33 D 8 9093 148487 16.33 343487 37.77 100,000 11.00 F 18b 21 8880 N/A N/A N/A N/A 188,000 21.17 M 4A 9145 144592 15.81 144592 15.81 125,000 13.67 F 18b 26 9388 240252 25.65 547752 58.47 166,000 17.68 LATER 12 WELL SET T 1 10255 193515 18.87 434765 42.40 159,000 15.50 F18b 27 9061 281302 31.04 753802 83.18 130,000 14.35 P 1 9017 243320 26.98 329570 36.55 141,000 15.64 F 18b 25 9036 191113 21.15 256113 28.34 57,000 6.31 F 18b 37 9413 427153 43.93 528403 54.35 121,000 12.85 D 6 9220 243940 26.46 360190 39.07 131,000 14.21 M 4A2 8771 234838 26.77 347338 39.60 84,000 9.58 M 4A3 9362 163872 17.50 321997 34.39 93,000 9.93 T 1 9249 219644 23.75 318394 34.42 98,000 10.60 F 18b 46 8890 264718 29.78 395968 44.54 93,000 10.46 M 4A4 9207 N/A N/A N/A N/A 89,000 9.67 T 2 9088 239000 26.30 312750 34.41 138,000 15.18 Initial 14 MEAN 9135 218588 23.51 417088 44.79 150,100 16.43 Later 12 MEAN 9240 245674 26.59 396299 42.84 111,200 12.03 Table 4 - System Cost Analysis raw data and solids handling costs for Ecuador Tipischa Basin area. Data is included for total well analysis, surface hole to TD.
  • 8. 8 BRENT WARREN AND LEONARD BALTOIU AADE 2001 WELL NAME Ft DRILLED DRILLING DAYS ft/ DRILLING DAY DAYS to TD ft/ DAYS to TD DAYS to RIG RELEASE ft/ DAYS to RIG RELEASE TROUBLE TIME (hrs) INITIAL 14 WELL SET M 8 8870 6.7 1318 24.0 370 26.6 334 49.5 D 1 9599 12.4 795 31.0 317 35.0 281 153.5 F 18b 13 8656 7.4 1168 14.0 615 15.7 546 66.0 F 18b 14 8557 7.3 1170 13.7 623 19.1 448 48.5 F18b 15 8762 N/A N/A N/A N/A 17.0 515 N/A D 2 9600 8.8 1085 19.0 505 21.0 457 54.5 F 18b 16 8150 7.5 1094 13.6 600 17.4 470 22.0 D 3 9356 10.5 888 31.0 302 41.0 228 122.0 D 7 10805 14.7 735 24.6 440 27.5 393 67.0 F 18b 20 8880 8.9 1003 21.0 423 25.0 355 20.5 D 8 9093 7.8 1173 16.8 541 21.0 433 78.0 F 18b 21 8880 N/A N/A N/A N/A 34.0 261 N/A M 4A 9145 N/A N/A N/A N/A 24.0 381 N/A F 18b 26 9388 13.9 675 26.5 353 29.9 313 123.0 LATER 12 WELL SET T 1 10255 13.0 789 28.7 357 31.7 323 96.5 F18b 27 9061 11.3 801 18.7 485 29.4 308 179.0 P 1 9017 9.2 977 23.5 384 26.3 343 34.5 F 18b 25 9036 5.4 1662 11.3 799 14.6 620 26.0 F 18b 37 9413 7.4 1317 26.5 367 32.1 303 40.5 D 6 9220 5.9 1553 17.1 540 19.5 474 46.5 M 4A2 8771 8.3 1053 17.0 516 19.6 448 45.0 M 4A3 9362 9.8 955 18.6 502 19.5 479 63.25 T 1 9249 5.8 1591 16.4 565 17.5 528 39.5 F 18b 46 8890 9.3 956 18.9 471 22.5 396 52.5 M 4A4 9207 N/A N/A N/A N/A 21.0 438 N/A T 2 9088 6.5 1398 19.2 474 20.8 438 29.5 Initial 14 MEAN 9135 9.6 1009 21.4 463 25.4 387 79 Later 12 MEAN 9240 8.4 1186 19.6 496 23.0 424 60 Table 5 - Time Analysis information for wells drilled in Ecuador Tipischa Basin area. Initial 14 wells used a gel- PHPA system while the later 12 wells used a KNO3 ss-PHPA fluid. Drilling Days is a measure of rotating time to reach total depth.
  • 9. AADE 2001 Using a System Cost Analysis to Quantify Drilling Fluids and Solids Control Costs 9 Figure 1 - Location of Chicken/Route area in West Central Alberta ΠΠ ΠΠ σσ ΠΠ ƒƒ σσ σσ ƒƒσσ σσ σσ σσ σσσσσσ ΠΠ ƒƒΠΠ σσσσ 63 ∋∋ σσ ∋∋ ΠΠ ΠΠ ΠΠ ΠΠ ΠΠ σσ σσ ΠΠ ƒƒ σσ ΠΠ ΠΠ ΠΠ ƒƒ ΠΠ 62 σσ σσ ∋∋ 61 08 07 Figure 2 – Chicken/Route area detailed well map. Wells with ΠΠ symbol indicate those with no logging or lost circulation problems, σσ symbol indicates logging problems or no logs run and ∋∋ symbol is for wells with lost circulation. A well with ƒƒ symbol has both logging and lost circulation problems. Edmonton Calgary ∗∗ ∗∗ AALLBBEERRTTAA Chicken/ Route
  • 10. 10 BRENT WARREN AND LEONARD BALTOIU AADE 2001 Figure 3 – Comparative material and system costs for Main Hole section of wells in the various sectors of the Chicken/Route area. Data taken from Table 2. HOLE SIZE DEPTH CASING SIZE 17.5" 1400-1700' 13.375" 12.25" 7000-9000' 9.625" 8.5" 8500-10000' 7" Figure 4 – Typical well design for Ecuadorian Tipischa Jungle basin wells. 0 5 10 15 20 25 30 35 40 61-7 MEAN 62-7 MEAN 62-8 MEAN 63-8 MEAN $/ftcost $ material/ft $ system cost/ft
  • 11. AADE 2001 Using a System Cost Analysis to Quantify Drilling Fluids and Solids Control Costs 11 Figure 5 – Comparison of material costs, system costs and solids costs for initial 14 and later 12 wells in Tipischa study area. Costs are given per foot to normalize the data and are shown for the entire well. Data taken from Table 4. Figure 6 – Comparison of drilling rate (ROP), time to total depth and time to rig release for initial 14 and later 12 wells in Tipischa study area. Information is presented in value ft per days to normalize data. Data taken from Table 5. 0 5 10 15 20 25 30 35 40 45 50 $ material/ft $ system cost/ft $ solids cost/ft $/ftcost Initial 14 MEAN Later 12 MEAN 0 200 400 600 800 1000 1200 1400 ft/ DRILLING DAY ft/ DAYS to TD ft/ DAYS to RIG RELEASE ft/day Initial 14 MEAN Later 12 MEAN