SlideShare a Scribd company logo
1 of 8
RISK REGISTER
Ref. No:
Date:
Page 1 of 8
HSE Risk Register
Hazards Identified
Risk
Control Measures
Residual
Risk By Whom
L S R L S R
Use of damage electrical equipment or
machine resulting in electrocution
3 4 12
 Electrical items not to be handled with wet hands.
 Person using electrical equipment must be competent.
 Electrical equipment’s/machines must be inspected before
use for worn out cables or connections.
 All electrical equipment’s / machines to be PAT tested
2 2 4
HSE/QA & QC Project
Management
Use of chemicals
Resulting in spillage/ contact with skin &
eyes (Causing Irritation)
3 4 12
 Staff must be given toolbox talk on safe chemical handling
before commencing the job
 COSHH cards or SDS must be available at site
 Appropriate PPE (Hand gloves, nose mask etc) must be in
place
 Chemical container must be in good condition and labelled
properly
2 2 4
HSE/QA & QC Project
Management
Tripping from electrical cables 2 3 6
 No cables to be trailed across doorways/pathways.
 Extension cables to be used where needed.
 Appropriate warning signage to be used at work.
2 2 4
HSE/QA & QC Project
Management
Absence of PPE resulting in injury or
bruises
2 3 6
 Staff must be briefed on benefits of wearing PPE and
appropriate PPE to be given to employees before
commencing the job.
2 2 4
HSE/QA & QC Project
Management
Project Name: SM NIRMAN
Location: URVISHA
Applicable HSE Legal
Requirements:
Who is affected?
Risk Colour Code:
High Risk
(16-20)
Moderate Risk
(11-15)
Low Risk
(6-10)
Very Low Risk
(1-5)
Only “Very Low” & “Low” Residual Risks are acceptable
RISK REGISTER
Ref. No:
Date:
Page 2 of 8
HSE Risk Register
Step ladder failure/Broken
Resulting in bone fracture and injury
4 4 16
 Step ladders used for intended purpose must be of correct
length and strength.
 Step ladder must be inspected before use.
 Defective step ladders must be labelled to indicate they are
not for use and defect must be reported immediately to
Supervisor or Manager.
2 2 4
HSE/QA & QC Project
Management
Falling Objects from ladder resulting in
head injury/concussion
3 4 12
 Safe working area is cordoned off around the stepladder
and signage is used as appropriate.
 Belt holster or belt hooks are used for carrying tools
up/down stepladders.
 Heavy items are not to be carried up stepladders.
 Work activities are monitored for compliance with any
Permits to Work in place.
2 2 4
HSE/QA & QC Project
Management
Fall due to staff overreaching / stretching
from ladder resulting in injury, bones
fracture
4 4 16
 Stepladders to be placed close to work / activity / object to
be inspected / moved / avoid staff over reaching.
 Stepladders to be secured when appreciable side force is
needed to do the work.
 Work activities are monitored for compliance with any
Permits to Work in place
2 2 4
HSE/QA & QC Project
Management
Slipping of step ladder
Resulting in serious injury
3 4 12
 Pre-use ladder inspections must be in place.
 Stepladders must always be locked into the correct
position.
 Stepladder to be only used on level floor surface.
 Stepladders must not be used on stairs, slippery or unsafe
floor surfaces.
 Stepladders should not propped against a wall.
2 2 4
HSE/QA & QC Project
Management
Overhead or exposed power cables above
ladder
Resulting in electrocution/fatality.
4 5 20
 Inspection of area to be made in order to identify any
electrical hazards / overhead power cables.
 Live supplies to be isolated where necessary.
 Aluminium stepladders not to be used where any electrical
hazard exists.
2 2 4
HSE/QA & QC Project
Management
Lifting heavy items on step ladder 3 4 12
 Long stepladders to be lifted by two or more persons.
 Heavy items should not be carried on stepladders.
2 2 4
HSE/QA & QC Project
Management
RISK REGISTER
Ref. No:
Date:
Page 3 of 8
HSE Risk Register
Resulting in back strain and
musculoskeletal injuries
Unsafe Ladder transport
Resulting in property damage or serious
injury
4 3 12
 Step ladder must be transported horizontally by two
persons always
 Stepladders carried on vehicles must be adequately
supported to avoid sagging and tied to each support point
to minimize movement.
 Pre-use ladder inspections must be undertaken.
 Defective Stepladders to be labelled to indicate that they
are not to be used and defect to be reported to
supervisor/Manager.
2 2 4
HSE/QA & QC Project
Management
Unauthorized use of step ladder
Resulting in property damage or injury
4 3 12
 Where the possibility of unauthorised usage exists
stepladders must be chained / locked to a secure, fixing
point.
2 2 4
HSE/QA & QC Project
Management
Gas Cylinders Storage resulting in
Explosion, sudden gas or fluid release,
exposure to cylinder contents and fire or
struck by a cylinder or suffering a manual
handling injury.
4 5 20
Gas cylinders must suitably segregate:
 1. Incompatible gasses must be stored apart.
 2. Empty and full gas cylinders must be stored apart.
Gas cylinder stores must:
 Be well ventilated
 Be sheltered from indirect heating.
 Be free from naked flame.
 Be secured so as to prevent unauthorized entry and access
to the cylinders.
 Gas cylinders must be stored in an upright position and
secured in trolley and chains so that they cannot fall over.
2 2 4
HSE/QA & QC Project
Management
RISK REGISTER
Ref. No:
Date:
Page 4 of 8
HSE Risk Register
Hazardous / Flammable
Substances Storage
Resulting in Fire,
explosion, release of a
toxic substance, release of
a corrosive substance.
4 4 16
 Hazardous substances to be stored according to guidance in
COSHH assessment or Material Safety Data Sheet provided
by supplier
 Hazardous/Flammable Substances must be stored in
ventilated area or ventilated cabinets
 Hazardous substances must be in original container with
labels and hazard warnings.
 Minimize amount of storage and use of hazardous
substances.
 Dry Powder or CO2 fire extinguisher to be kept in place
where hazardous chemicals are stored.
 Authorized personnel to access store or cupboard
2 2 4
HSE/QA & QC Project
Management
Fire in case of poor electrical sockets,
connection or installation.
4 4 16
 All broken or poor electrical sockets must be rectified.
 All Staff to be briefed for immediate actions in case of fire
referring to fire emergency procedures.
2 2 4
HSE/QA & QC Project
Management
Falling objects from height, ceiling or
storage cabinets incase not secured,
poorly installed or Sited too
high/overloaded
3 4 12
 Items must be properly secured or fixed in place.
 Shelves must not be overloaded.
 Storage must be organized with heavy objects at lower
levels.
 Restricted access to authorized persons.
 Controlled limits of items stored.
2 2 4
HSE/QA &QC Project
Management
Improper Housekeeping in rest areas &
store room resulting in slip, trip and fall
3 3 9
 Rubbish to be removed regularly.
 Recycling bins to be provided and used.
2 2 4
HSE/QA & QC Project
Management
Manual Handling
Resulting in back pain, strain etc
2 3 6
 Staff to be briefed about the dangers of manual handling
and instruct to assess the load before handling.
 Staff to wear appropriate PPE.
 Minimize repetitive bends and ensure to take regular
breaks.
 In case of heavy weight, more than one staff or mechanical
aid to be used.
2 2 4
HSE/QA & QC Project
Management
RISK REGISTER
Ref. No:
Date:
Page 5 of 8
HSE Risk Register
Disposing Hazardous Chemicals
3 4 12
 Staff to be given training on safe handling and disposing of
hazardous chemicals.
 Staff to wear appropriate PPE at all time when disposing
hazardous chemicals in order to avoid contact with skin,
eyes or inhalation of fumes or vapours.
 All hazardous chemicals to be disposed as per local
regulations.
2 2 4
HSE/QA & QC Project
Management
Hygiene and Potential contact
with bio hazard waste
3 4 12
 Staff to be given training on safe handling and disposing of
bio hazard waste.
 Staff to wear appropriate PPE (Hand gloves)
 Staff to wash hands and forearms before eating, drinking,
going to toilet.
 Staff to cover any cut or wound and not to expose to avoid
infection
2 2 4
HSE/QA & QC Project
Management
Not carrying Hand tools / Sharp tools
Properly and resulting in falling or slipping
out of hands
2 3 6
 Proper toolbox or bag to be provided in order to carry hand
tools/sharp tools.
2 2 4
HSE/QA & QC Project
Management
Paint Splashing back causing eyes, skin
irritation and stains on clothes
4 4 16
 Staff to be given orientation/training before commencing of
job by Supervisor
 Staff to carry out safe work practise
 Staff to be given cover all and safety goggles to protect
their skin and eyes.
2 2 4
HSE/QA & QC Project
Management
Staff inhaling fumes emitted by
paints/chemicals
4 3 12
 Staff to be given orientation/training before commencing of
job by Supervisor.
 Proper ventilation to be provided in working area
 Staff to be provided with nose mask
2 2 4
HSE/QA & QC Project
Management
Unsafe or improper use of Power toools
etc (Hilti machine) causing property
damage or injury
4 4 16
 Staff to be fully trained in safe use and handling.
 Equipment to be checked before each use to ensure that
there are no defects in the cable (electric), casing, plug or
chuck, etc.
 Operator will ensure that there is plenty of room to move
comfortably around the material being worked on and that
the material is securely clamped where possible
2 2 4
HSE/QA & QC Project
Management
RISK REGISTER
Ref. No:
Date:
Page 6 of 8
HSE Risk Register
 If drilling into walls, the user will check for hidden cables,
water pipes etc and if present re-plan work.
 If working at height, area to be cordoned off and warning
signs erected
Vibration/Noise/Dust during equipment
usage.
3 4 12
 Suitable gloves, goggles, ear defenders and dust mask to be
provided to employees when using the equipment.
 Dust generated to be removed and disposed of properly
2 2 4
HSE/QA & QC Project
Management
Jobs related to Confined Space or Hot
Work (Cutting, Mixing, Grinding)
4 4 16
 In case of any need for hot work or access to confined
space, permit to work shall be issued &/or risk assessment
shall be provided by HSE/QA & QC dept.
2 2 4
HSE/QA & QC Project
Management
Use of flammable chemicals at work place 3 4 12
 All sources related to fire hazard must be removed before
using flammable chemicals at workplace.
 Workplace must have proper ventilation or appropriate
temperature before using flammable chemicals.
2 2 4
HSE/QA & QC Project
Management
Tools or machinery
With fault or inadequate
guarding resulting in personal injury
4 4 16
 Safety guards must never be removed or tampered
 Low voltage tools to be used
 Equipment must visually checked before use
 Defective equipment must not be used and reported to
supervisor/Manager
2 2 4
HSE/QA & QC Project
Management
Inadequate Lighting Levels / Dark areas
affecting job
2 3 6  Portable lighting or helmet with fixed torch to be used if
lighting levels becomes inadequate
2 2 4 HSE/QA & QC Project
Management
Use of extension leads resulting in
tripping, overloading and external use.
3 4 12
 Ensure sufficient sockets provided and do not overload
sockets.
 Use extension leads and adaptors only when necessary
ensure they are of a suitable length (preferably no longer
than 2 metres) and rated high enough for the job.
 Use of cable covers where cables are a trip hazard
 Work in progress signage to be in place.
 RCD (Residual Current Device) to be used whenever
equipment is used externally.
 Test RCD regularly to check that its mechanism is free and
functioning
2 2 4
HSE/QA & QC Project
Management
RISK REGISTER
Ref. No:
Date:
Page 7 of 8
HSE Risk Register
Fall from height while working at Mobile
Scaffolding resulting in fatality, personal
injury and damage to property. 4 5 20
 Ensure the platform is fully boarded out and guard-rails and
toe-boards are in place.
 Mobile scaffold s must only be used on firm surfaces in case
ground is soft, adequate support must be provided.
 The gap between toe-boards and mid guard-rails, and
between mid and top guard-rails, must not exceed 470 mm
unless otherwise stated by manufacturer.
 Never climb up the outside of a mobile scaffold – use the
stairway or ladder on the inside. Unless ladder is designed
outside
 Follow manufacturer’s instructions on base to height ratio.
 Don’t pull the mobile scaffold along while standing on it.
 Once on mobile scaffold platform use full body harness and
properly connect it to the scaffold body
2 2 4
HSE/QA & QC Project
Management
Contact with overhead objects/
electrocutions while working at Mobile
Scaffolding
3 4 12
 When moving mobile scaffold s ensure there are no
potholes, obstructions or overhead power lines in the way.
 When working, ensure the access hatch is closed on the
platform (if any).
2 2 4
HSE/QA & QC Project
Management
Work in extreme weather condition at
Mobile Scaffolding.
4 5 20
 Work out door using mobile scaffold is not allowed in case
of heavy and storm, rain. In summer work outdoor directly
under sun is not allowed (midday break rule)
2 2 4 HSE/QA & QC Project
Management
Overturning of Mobile Scaffolding
4 4 16
 Check wheels for effective rotation
 Check brakes and locking devices
 Ensure that the surface on which the mobile scaffold will be
erected is even, rigid and will cope with the scaffold load
plus the people and material that will be placed on it.
 Don’t move mobile scaffold on ramps
2 2 4
HSE/QA & QC Project
Management
Using Scaffold in Traffic/ Vehicle
manoeuvring area
3 4 12
 In case of the use of mobile scaffold to various work tasks in
vehicles traffic area then warning tape and traffic cones
shall be placed to warn drivers and if required a flag man
who is wearing high reflective jacket shall be positioned to
warn drivers
2 2 4
HSE/QA & QC Project
Management
RISK REGISTER
Ref. No:
Date:
Page 8 of 8
HSE Risk Register
Use of defective mobile scaffold 3 4 12
 Ensure that all parts of MS are in good physical and
operational condition. If any part of the scaffold found to
be defective it shall be replaced otherwise MS shall never
be used
 Once scaffold is erected then put a green tape or tag on it
to indicate it is safe to be used, but if it is not ready yet then
put a red tape / tag. These colours shall be communicated
and explained to all those who might use the Mobile
scaffold.
2 2 4
HSE/QA & QC Project
Management
Prepared by:
Date:

More Related Content

What's hot

8 lifting operations with mobile crane risk assessment templates
8 lifting operations with mobile crane risk assessment templates8 lifting operations with mobile crane risk assessment templates
8 lifting operations with mobile crane risk assessment templatesDwarika Bhushan Sharma
 
11 piling operations with rebar cage installation risk assessment templates
11 piling operations with rebar cage installation risk assessment templates11 piling operations with rebar cage installation risk assessment templates
11 piling operations with rebar cage installation risk assessment templatesDwarika Bhushan Sharma
 
4 cofferdams (temporary works) risk assessment templates
4 cofferdams (temporary works) risk assessment templates4 cofferdams (temporary works) risk assessment templates
4 cofferdams (temporary works) risk assessment templatesDwarika Bhushan Sharma
 
31 ndrc operations within excavations (temporary works) risk assessment templ...
31 ndrc operations within excavations (temporary works) risk assessment templ...31 ndrc operations within excavations (temporary works) risk assessment templ...
31 ndrc operations within excavations (temporary works) risk assessment templ...Dwarika Bhushan Sharma
 
Risk Assessment (Master).pdf
Risk Assessment (Master).pdfRisk Assessment (Master).pdf
Risk Assessment (Master).pdfRafiullahKhan88
 
Motor vehicle Mechanical repair workshop Risk assessment, safety engineering ...
Motor vehicle Mechanical repair workshop Risk assessment, safety engineering ...Motor vehicle Mechanical repair workshop Risk assessment, safety engineering ...
Motor vehicle Mechanical repair workshop Risk assessment, safety engineering ...Tarun Kumar Cheddy
 
Risk assessment for testing & commissioning of cranes
Risk assessment for  testing & commissioning of cranesRisk assessment for  testing & commissioning of cranes
Risk assessment for testing & commissioning of cranesAzmeel Contracting Company
 
03-hira-for-welding-work-_compress.pdf
03-hira-for-welding-work-_compress.pdf03-hira-for-welding-work-_compress.pdf
03-hira-for-welding-work-_compress.pdfRajkumarArikumar
 
RA for Hot works at MOE-Ghim Moh (Ceiling support works).pdf
RA for Hot works at MOE-Ghim Moh (Ceiling support works).pdfRA for Hot works at MOE-Ghim Moh (Ceiling support works).pdf
RA for Hot works at MOE-Ghim Moh (Ceiling support works).pdfMohPhoolay
 
Roles, duties and responsibilities of a stand-by Man working in a confined space
Roles, duties and responsibilities of a stand-by Man working in a confined spaceRoles, duties and responsibilities of a stand-by Man working in a confined space
Roles, duties and responsibilities of a stand-by Man working in a confined spaceEMMANUEL ESSEN
 
14 use of plant graders and road rollers risk assessment templates
14 use of plant  graders and road rollers risk assessment templates14 use of plant  graders and road rollers risk assessment templates
14 use of plant graders and road rollers risk assessment templatesDwarika Bhushan Sharma
 
Safety PPE Poster (ONE SAFETY)
Safety PPE Poster (ONE SAFETY)Safety PPE Poster (ONE SAFETY)
Safety PPE Poster (ONE SAFETY)Stephen Austria
 
29 workplace temporary lighting risk assessment templates
29 workplace temporary lighting risk assessment templates29 workplace temporary lighting risk assessment templates
29 workplace temporary lighting risk assessment templatesDwarika Bhushan Sharma
 

What's hot (20)

8 lifting operations with mobile crane risk assessment templates
8 lifting operations with mobile crane risk assessment templates8 lifting operations with mobile crane risk assessment templates
8 lifting operations with mobile crane risk assessment templates
 
11 piling operations with rebar cage installation risk assessment templates
11 piling operations with rebar cage installation risk assessment templates11 piling operations with rebar cage installation risk assessment templates
11 piling operations with rebar cage installation risk assessment templates
 
JSA of Arc welding
JSA of Arc weldingJSA of Arc welding
JSA of Arc welding
 
Confined Space Entry
Confined Space EntryConfined Space Entry
Confined Space Entry
 
4 cofferdams (temporary works) risk assessment templates
4 cofferdams (temporary works) risk assessment templates4 cofferdams (temporary works) risk assessment templates
4 cofferdams (temporary works) risk assessment templates
 
31 ndrc operations within excavations (temporary works) risk assessment templ...
31 ndrc operations within excavations (temporary works) risk assessment templ...31 ndrc operations within excavations (temporary works) risk assessment templ...
31 ndrc operations within excavations (temporary works) risk assessment templ...
 
Risk Assessment (Master).pdf
Risk Assessment (Master).pdfRisk Assessment (Master).pdf
Risk Assessment (Master).pdf
 
Confined Space Entry
Confined Space EntryConfined Space Entry
Confined Space Entry
 
HSE Monitoring schedule plan
HSE Monitoring schedule planHSE Monitoring schedule plan
HSE Monitoring schedule plan
 
Motor vehicle Mechanical repair workshop Risk assessment, safety engineering ...
Motor vehicle Mechanical repair workshop Risk assessment, safety engineering ...Motor vehicle Mechanical repair workshop Risk assessment, safety engineering ...
Motor vehicle Mechanical repair workshop Risk assessment, safety engineering ...
 
Risk assessment for testing & commissioning of cranes
Risk assessment for  testing & commissioning of cranesRisk assessment for  testing & commissioning of cranes
Risk assessment for testing & commissioning of cranes
 
03-hira-for-welding-work-_compress.pdf
03-hira-for-welding-work-_compress.pdf03-hira-for-welding-work-_compress.pdf
03-hira-for-welding-work-_compress.pdf
 
Lifting Operation.ppt
Lifting Operation.pptLifting Operation.ppt
Lifting Operation.ppt
 
RA for Hot works at MOE-Ghim Moh (Ceiling support works).pdf
RA for Hot works at MOE-Ghim Moh (Ceiling support works).pdfRA for Hot works at MOE-Ghim Moh (Ceiling support works).pdf
RA for Hot works at MOE-Ghim Moh (Ceiling support works).pdf
 
Roles, duties and responsibilities of a stand-by Man working in a confined space
Roles, duties and responsibilities of a stand-by Man working in a confined spaceRoles, duties and responsibilities of a stand-by Man working in a confined space
Roles, duties and responsibilities of a stand-by Man working in a confined space
 
14 use of plant graders and road rollers risk assessment templates
14 use of plant  graders and road rollers risk assessment templates14 use of plant  graders and road rollers risk assessment templates
14 use of plant graders and road rollers risk assessment templates
 
Confined space
Confined spaceConfined space
Confined space
 
Safety PPE Poster (ONE SAFETY)
Safety PPE Poster (ONE SAFETY)Safety PPE Poster (ONE SAFETY)
Safety PPE Poster (ONE SAFETY)
 
29 workplace temporary lighting risk assessment templates
29 workplace temporary lighting risk assessment templates29 workplace temporary lighting risk assessment templates
29 workplace temporary lighting risk assessment templates
 
Powered Pallet Jack Safety Poster
Powered Pallet Jack Safety PosterPowered Pallet Jack Safety Poster
Powered Pallet Jack Safety Poster
 

Similar to HSE Risk Register.docx

HSE Risk Register | Gaurav Singh Rajput
HSE Risk Register | Gaurav Singh RajputHSE Risk Register | Gaurav Singh Rajput
HSE Risk Register | Gaurav Singh RajputGaurav Singh Rajput
 
008-SWMS-GENERAL-ONSITE-ACTIVITIES-AND-REPAIRS.pdf
008-SWMS-GENERAL-ONSITE-ACTIVITIES-AND-REPAIRS.pdf008-SWMS-GENERAL-ONSITE-ACTIVITIES-AND-REPAIRS.pdf
008-SWMS-GENERAL-ONSITE-ACTIVITIES-AND-REPAIRS.pdfFESTUS RICHARD SIAME
 
LPG Chloride treaters foundation execution_Rev.00.pdf
LPG Chloride treaters foundation execution_Rev.00.pdfLPG Chloride treaters foundation execution_Rev.00.pdf
LPG Chloride treaters foundation execution_Rev.00.pdfJESUSBASILIOANTONIO
 
DPL-SP - Safety Induction Presentation 00.pptx
DPL-SP - Safety Induction Presentation 00.pptxDPL-SP - Safety Induction Presentation 00.pptx
DPL-SP - Safety Induction Presentation 00.pptxAamirAbbas75
 
Fire Suppression System Risk assessment file
Fire Suppression System Risk assessment fileFire Suppression System Risk assessment file
Fire Suppression System Risk assessment filechopriroti
 
Job Safety Analyses For Energization of Substation..doc
Job Safety Analyses For Energization of Substation..docJob Safety Analyses For Energization of Substation..doc
Job Safety Analyses For Energization of Substation..docAtif767782
 
JSA01_De-Ethanizer_Foundation_Execution_Rev00.pdf
JSA01_De-Ethanizer_Foundation_Execution_Rev00.pdfJSA01_De-Ethanizer_Foundation_Execution_Rev00.pdf
JSA01_De-Ethanizer_Foundation_Execution_Rev00.pdfJESUSBASILIOANTONIO
 
Sydney gateway rail duplication induction v1.4
Sydney gateway rail duplication induction v1.4Sydney gateway rail duplication induction v1.4
Sydney gateway rail duplication induction v1.4Garry Pepper
 
Sydney Gateway Rail Duplication Induction v1.4
Sydney Gateway Rail Duplication Induction v1.4Sydney Gateway Rail Duplication Induction v1.4
Sydney Gateway Rail Duplication Induction v1.4Garry Pepper
 
AMA 2A SHE Induction 2022....pdf
AMA 2A SHE Induction 2022....pdfAMA 2A SHE Induction 2022....pdf
AMA 2A SHE Induction 2022....pdfIbukunOwolabi4
 
Iipp haz com-ppe-fp-evac-p65-bp
Iipp haz com-ppe-fp-evac-p65-bpIipp haz com-ppe-fp-evac-p65-bp
Iipp haz com-ppe-fp-evac-p65-bpKJP Consulting
 
150 Question Answers | Occupational Health & Safety
150 Question Answers | Occupational Health & Safety150 Question Answers | Occupational Health & Safety
150 Question Answers | Occupational Health & SafetyMuhammad Usman
 
SITE SAFETY INDUCTION ENGINEERING TRAINING
SITE SAFETY INDUCTION ENGINEERING TRAININGSITE SAFETY INDUCTION ENGINEERING TRAINING
SITE SAFETY INDUCTION ENGINEERING TRAININGsatheesh843134
 
Dropped Object prevention Campaign (1).pptx
Dropped Object prevention Campaign (1).pptxDropped Object prevention Campaign (1).pptx
Dropped Object prevention Campaign (1).pptxssuser926916
 
Case M4K Forklift Truck Service Repair Manual
Case M4K Forklift Truck Service Repair ManualCase M4K Forklift Truck Service Repair Manual
Case M4K Forklift Truck Service Repair Manualjksmemm ekmdm
 

Similar to HSE Risk Register.docx (20)

HSE Risk Register | Gaurav Singh Rajput
HSE Risk Register | Gaurav Singh RajputHSE Risk Register | Gaurav Singh Rajput
HSE Risk Register | Gaurav Singh Rajput
 
008-SWMS-GENERAL-ONSITE-ACTIVITIES-AND-REPAIRS.pdf
008-SWMS-GENERAL-ONSITE-ACTIVITIES-AND-REPAIRS.pdf008-SWMS-GENERAL-ONSITE-ACTIVITIES-AND-REPAIRS.pdf
008-SWMS-GENERAL-ONSITE-ACTIVITIES-AND-REPAIRS.pdf
 
LPG Chloride treaters foundation execution_Rev.00.pdf
LPG Chloride treaters foundation execution_Rev.00.pdfLPG Chloride treaters foundation execution_Rev.00.pdf
LPG Chloride treaters foundation execution_Rev.00.pdf
 
DPL-SP - Safety Induction Presentation 00.pptx
DPL-SP - Safety Induction Presentation 00.pptxDPL-SP - Safety Induction Presentation 00.pptx
DPL-SP - Safety Induction Presentation 00.pptx
 
HIRARC FORM (skylift).pdf
HIRARC FORM (skylift).pdfHIRARC FORM (skylift).pdf
HIRARC FORM (skylift).pdf
 
Fire Suppression System Risk assessment file
Fire Suppression System Risk assessment fileFire Suppression System Risk assessment file
Fire Suppression System Risk assessment file
 
Job Safety Analyses For Energization of Substation..doc
Job Safety Analyses For Energization of Substation..docJob Safety Analyses For Energization of Substation..doc
Job Safety Analyses For Energization of Substation..doc
 
JSA01_De-Ethanizer_Foundation_Execution_Rev00.pdf
JSA01_De-Ethanizer_Foundation_Execution_Rev00.pdfJSA01_De-Ethanizer_Foundation_Execution_Rev00.pdf
JSA01_De-Ethanizer_Foundation_Execution_Rev00.pdf
 
Sydney gateway rail duplication induction v1.4
Sydney gateway rail duplication induction v1.4Sydney gateway rail duplication induction v1.4
Sydney gateway rail duplication induction v1.4
 
Sydney Gateway Rail Duplication Induction v1.4
Sydney Gateway Rail Duplication Induction v1.4Sydney Gateway Rail Duplication Induction v1.4
Sydney Gateway Rail Duplication Induction v1.4
 
Construction Safety Training
Construction Safety TrainingConstruction Safety Training
Construction Safety Training
 
AMA 2A SHE Induction 2022....pdf
AMA 2A SHE Induction 2022....pdfAMA 2A SHE Induction 2022....pdf
AMA 2A SHE Induction 2022....pdf
 
Iipp haz com-ppe-fp-evac-p65-bp
Iipp haz com-ppe-fp-evac-p65-bpIipp haz com-ppe-fp-evac-p65-bp
Iipp haz com-ppe-fp-evac-p65-bp
 
ehs
ehsehs
ehs
 
150 Question Answers | Occupational Health & Safety
150 Question Answers | Occupational Health & Safety150 Question Answers | Occupational Health & Safety
150 Question Answers | Occupational Health & Safety
 
SITE SAFETY INDUCTION ENGINEERING TRAINING
SITE SAFETY INDUCTION ENGINEERING TRAININGSITE SAFETY INDUCTION ENGINEERING TRAINING
SITE SAFETY INDUCTION ENGINEERING TRAINING
 
Hira
HiraHira
Hira
 
Dropped Object prevention Campaign (1).pptx
Dropped Object prevention Campaign (1).pptxDropped Object prevention Campaign (1).pptx
Dropped Object prevention Campaign (1).pptx
 
Safety_induction
Safety_inductionSafety_induction
Safety_induction
 
Case M4K Forklift Truck Service Repair Manual
Case M4K Forklift Truck Service Repair ManualCase M4K Forklift Truck Service Repair Manual
Case M4K Forklift Truck Service Repair Manual
 

Recently uploaded

Delhi Call Girls CP 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Call
Delhi Call Girls CP 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip CallDelhi Call Girls CP 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Call
Delhi Call Girls CP 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Callshivangimorya083
 
Smarteg dropshipping via API with DroFx.pptx
Smarteg dropshipping via API with DroFx.pptxSmarteg dropshipping via API with DroFx.pptx
Smarteg dropshipping via API with DroFx.pptxolyaivanovalion
 
Invezz.com - Grow your wealth with trading signals
Invezz.com - Grow your wealth with trading signalsInvezz.com - Grow your wealth with trading signals
Invezz.com - Grow your wealth with trading signalsInvezz1
 
VIP Call Girls Service Miyapur Hyderabad Call +91-8250192130
VIP Call Girls Service Miyapur Hyderabad Call +91-8250192130VIP Call Girls Service Miyapur Hyderabad Call +91-8250192130
VIP Call Girls Service Miyapur Hyderabad Call +91-8250192130Suhani Kapoor
 
BPAC WITH UFSBI GENERAL PRESENTATION 18_05_2017-1.pptx
BPAC WITH UFSBI GENERAL PRESENTATION 18_05_2017-1.pptxBPAC WITH UFSBI GENERAL PRESENTATION 18_05_2017-1.pptx
BPAC WITH UFSBI GENERAL PRESENTATION 18_05_2017-1.pptxMohammedJunaid861692
 
Call me @ 9892124323 Cheap Rate Call Girls in Vashi with Real Photo 100% Secure
Call me @ 9892124323  Cheap Rate Call Girls in Vashi with Real Photo 100% SecureCall me @ 9892124323  Cheap Rate Call Girls in Vashi with Real Photo 100% Secure
Call me @ 9892124323 Cheap Rate Call Girls in Vashi with Real Photo 100% SecurePooja Nehwal
 
Ukraine War presentation: KNOW THE BASICS
Ukraine War presentation: KNOW THE BASICSUkraine War presentation: KNOW THE BASICS
Ukraine War presentation: KNOW THE BASICSAishani27
 
代办国外大学文凭《原版美国UCLA文凭证书》加州大学洛杉矶分校毕业证制作成绩单修改
代办国外大学文凭《原版美国UCLA文凭证书》加州大学洛杉矶分校毕业证制作成绩单修改代办国外大学文凭《原版美国UCLA文凭证书》加州大学洛杉矶分校毕业证制作成绩单修改
代办国外大学文凭《原版美国UCLA文凭证书》加州大学洛杉矶分校毕业证制作成绩单修改atducpo
 
BabyOno dropshipping via API with DroFx.pptx
BabyOno dropshipping via API with DroFx.pptxBabyOno dropshipping via API with DroFx.pptx
BabyOno dropshipping via API with DroFx.pptxolyaivanovalion
 
BigBuy dropshipping via API with DroFx.pptx
BigBuy dropshipping via API with DroFx.pptxBigBuy dropshipping via API with DroFx.pptx
BigBuy dropshipping via API with DroFx.pptxolyaivanovalion
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...apidays
 
FESE Capital Markets Fact Sheet 2024 Q1.pdf
FESE Capital Markets Fact Sheet 2024 Q1.pdfFESE Capital Markets Fact Sheet 2024 Q1.pdf
FESE Capital Markets Fact Sheet 2024 Q1.pdfMarinCaroMartnezBerg
 
Introduction-to-Machine-Learning (1).pptx
Introduction-to-Machine-Learning (1).pptxIntroduction-to-Machine-Learning (1).pptx
Introduction-to-Machine-Learning (1).pptxfirstjob4
 
Midocean dropshipping via API with DroFx
Midocean dropshipping via API with DroFxMidocean dropshipping via API with DroFx
Midocean dropshipping via API with DroFxolyaivanovalion
 
Low Rate Call Girls Bhilai Anika 8250192130 Independent Escort Service Bhilai
Low Rate Call Girls Bhilai Anika 8250192130 Independent Escort Service BhilaiLow Rate Call Girls Bhilai Anika 8250192130 Independent Escort Service Bhilai
Low Rate Call Girls Bhilai Anika 8250192130 Independent Escort Service BhilaiSuhani Kapoor
 
Brighton SEO | April 2024 | Data Storytelling
Brighton SEO | April 2024 | Data StorytellingBrighton SEO | April 2024 | Data Storytelling
Brighton SEO | April 2024 | Data StorytellingNeil Barnes
 
Edukaciniai dropshipping via API with DroFx
Edukaciniai dropshipping via API with DroFxEdukaciniai dropshipping via API with DroFx
Edukaciniai dropshipping via API with DroFxolyaivanovalion
 
RA-11058_IRR-COMPRESS Do 198 series of 1998
RA-11058_IRR-COMPRESS Do 198 series of 1998RA-11058_IRR-COMPRESS Do 198 series of 1998
RA-11058_IRR-COMPRESS Do 198 series of 1998YohFuh
 
Delhi Call Girls Punjabi Bagh 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Call
Delhi Call Girls Punjabi Bagh 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip CallDelhi Call Girls Punjabi Bagh 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Call
Delhi Call Girls Punjabi Bagh 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Callshivangimorya083
 

Recently uploaded (20)

Delhi Call Girls CP 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Call
Delhi Call Girls CP 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip CallDelhi Call Girls CP 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Call
Delhi Call Girls CP 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Call
 
Smarteg dropshipping via API with DroFx.pptx
Smarteg dropshipping via API with DroFx.pptxSmarteg dropshipping via API with DroFx.pptx
Smarteg dropshipping via API with DroFx.pptx
 
Invezz.com - Grow your wealth with trading signals
Invezz.com - Grow your wealth with trading signalsInvezz.com - Grow your wealth with trading signals
Invezz.com - Grow your wealth with trading signals
 
VIP Call Girls Service Miyapur Hyderabad Call +91-8250192130
VIP Call Girls Service Miyapur Hyderabad Call +91-8250192130VIP Call Girls Service Miyapur Hyderabad Call +91-8250192130
VIP Call Girls Service Miyapur Hyderabad Call +91-8250192130
 
BPAC WITH UFSBI GENERAL PRESENTATION 18_05_2017-1.pptx
BPAC WITH UFSBI GENERAL PRESENTATION 18_05_2017-1.pptxBPAC WITH UFSBI GENERAL PRESENTATION 18_05_2017-1.pptx
BPAC WITH UFSBI GENERAL PRESENTATION 18_05_2017-1.pptx
 
Call me @ 9892124323 Cheap Rate Call Girls in Vashi with Real Photo 100% Secure
Call me @ 9892124323  Cheap Rate Call Girls in Vashi with Real Photo 100% SecureCall me @ 9892124323  Cheap Rate Call Girls in Vashi with Real Photo 100% Secure
Call me @ 9892124323 Cheap Rate Call Girls in Vashi with Real Photo 100% Secure
 
Ukraine War presentation: KNOW THE BASICS
Ukraine War presentation: KNOW THE BASICSUkraine War presentation: KNOW THE BASICS
Ukraine War presentation: KNOW THE BASICS
 
代办国外大学文凭《原版美国UCLA文凭证书》加州大学洛杉矶分校毕业证制作成绩单修改
代办国外大学文凭《原版美国UCLA文凭证书》加州大学洛杉矶分校毕业证制作成绩单修改代办国外大学文凭《原版美国UCLA文凭证书》加州大学洛杉矶分校毕业证制作成绩单修改
代办国外大学文凭《原版美国UCLA文凭证书》加州大学洛杉矶分校毕业证制作成绩单修改
 
BabyOno dropshipping via API with DroFx.pptx
BabyOno dropshipping via API with DroFx.pptxBabyOno dropshipping via API with DroFx.pptx
BabyOno dropshipping via API with DroFx.pptx
 
BigBuy dropshipping via API with DroFx.pptx
BigBuy dropshipping via API with DroFx.pptxBigBuy dropshipping via API with DroFx.pptx
BigBuy dropshipping via API with DroFx.pptx
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
 
FESE Capital Markets Fact Sheet 2024 Q1.pdf
FESE Capital Markets Fact Sheet 2024 Q1.pdfFESE Capital Markets Fact Sheet 2024 Q1.pdf
FESE Capital Markets Fact Sheet 2024 Q1.pdf
 
Introduction-to-Machine-Learning (1).pptx
Introduction-to-Machine-Learning (1).pptxIntroduction-to-Machine-Learning (1).pptx
Introduction-to-Machine-Learning (1).pptx
 
Midocean dropshipping via API with DroFx
Midocean dropshipping via API with DroFxMidocean dropshipping via API with DroFx
Midocean dropshipping via API with DroFx
 
Low Rate Call Girls Bhilai Anika 8250192130 Independent Escort Service Bhilai
Low Rate Call Girls Bhilai Anika 8250192130 Independent Escort Service BhilaiLow Rate Call Girls Bhilai Anika 8250192130 Independent Escort Service Bhilai
Low Rate Call Girls Bhilai Anika 8250192130 Independent Escort Service Bhilai
 
Brighton SEO | April 2024 | Data Storytelling
Brighton SEO | April 2024 | Data StorytellingBrighton SEO | April 2024 | Data Storytelling
Brighton SEO | April 2024 | Data Storytelling
 
Sampling (random) method and Non random.ppt
Sampling (random) method and Non random.pptSampling (random) method and Non random.ppt
Sampling (random) method and Non random.ppt
 
Edukaciniai dropshipping via API with DroFx
Edukaciniai dropshipping via API with DroFxEdukaciniai dropshipping via API with DroFx
Edukaciniai dropshipping via API with DroFx
 
RA-11058_IRR-COMPRESS Do 198 series of 1998
RA-11058_IRR-COMPRESS Do 198 series of 1998RA-11058_IRR-COMPRESS Do 198 series of 1998
RA-11058_IRR-COMPRESS Do 198 series of 1998
 
Delhi Call Girls Punjabi Bagh 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Call
Delhi Call Girls Punjabi Bagh 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip CallDelhi Call Girls Punjabi Bagh 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Call
Delhi Call Girls Punjabi Bagh 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Call
 

HSE Risk Register.docx

  • 1. RISK REGISTER Ref. No: Date: Page 1 of 8 HSE Risk Register Hazards Identified Risk Control Measures Residual Risk By Whom L S R L S R Use of damage electrical equipment or machine resulting in electrocution 3 4 12  Electrical items not to be handled with wet hands.  Person using electrical equipment must be competent.  Electrical equipment’s/machines must be inspected before use for worn out cables or connections.  All electrical equipment’s / machines to be PAT tested 2 2 4 HSE/QA & QC Project Management Use of chemicals Resulting in spillage/ contact with skin & eyes (Causing Irritation) 3 4 12  Staff must be given toolbox talk on safe chemical handling before commencing the job  COSHH cards or SDS must be available at site  Appropriate PPE (Hand gloves, nose mask etc) must be in place  Chemical container must be in good condition and labelled properly 2 2 4 HSE/QA & QC Project Management Tripping from electrical cables 2 3 6  No cables to be trailed across doorways/pathways.  Extension cables to be used where needed.  Appropriate warning signage to be used at work. 2 2 4 HSE/QA & QC Project Management Absence of PPE resulting in injury or bruises 2 3 6  Staff must be briefed on benefits of wearing PPE and appropriate PPE to be given to employees before commencing the job. 2 2 4 HSE/QA & QC Project Management Project Name: SM NIRMAN Location: URVISHA Applicable HSE Legal Requirements: Who is affected? Risk Colour Code: High Risk (16-20) Moderate Risk (11-15) Low Risk (6-10) Very Low Risk (1-5) Only “Very Low” & “Low” Residual Risks are acceptable
  • 2. RISK REGISTER Ref. No: Date: Page 2 of 8 HSE Risk Register Step ladder failure/Broken Resulting in bone fracture and injury 4 4 16  Step ladders used for intended purpose must be of correct length and strength.  Step ladder must be inspected before use.  Defective step ladders must be labelled to indicate they are not for use and defect must be reported immediately to Supervisor or Manager. 2 2 4 HSE/QA & QC Project Management Falling Objects from ladder resulting in head injury/concussion 3 4 12  Safe working area is cordoned off around the stepladder and signage is used as appropriate.  Belt holster or belt hooks are used for carrying tools up/down stepladders.  Heavy items are not to be carried up stepladders.  Work activities are monitored for compliance with any Permits to Work in place. 2 2 4 HSE/QA & QC Project Management Fall due to staff overreaching / stretching from ladder resulting in injury, bones fracture 4 4 16  Stepladders to be placed close to work / activity / object to be inspected / moved / avoid staff over reaching.  Stepladders to be secured when appreciable side force is needed to do the work.  Work activities are monitored for compliance with any Permits to Work in place 2 2 4 HSE/QA & QC Project Management Slipping of step ladder Resulting in serious injury 3 4 12  Pre-use ladder inspections must be in place.  Stepladders must always be locked into the correct position.  Stepladder to be only used on level floor surface.  Stepladders must not be used on stairs, slippery or unsafe floor surfaces.  Stepladders should not propped against a wall. 2 2 4 HSE/QA & QC Project Management Overhead or exposed power cables above ladder Resulting in electrocution/fatality. 4 5 20  Inspection of area to be made in order to identify any electrical hazards / overhead power cables.  Live supplies to be isolated where necessary.  Aluminium stepladders not to be used where any electrical hazard exists. 2 2 4 HSE/QA & QC Project Management Lifting heavy items on step ladder 3 4 12  Long stepladders to be lifted by two or more persons.  Heavy items should not be carried on stepladders. 2 2 4 HSE/QA & QC Project Management
  • 3. RISK REGISTER Ref. No: Date: Page 3 of 8 HSE Risk Register Resulting in back strain and musculoskeletal injuries Unsafe Ladder transport Resulting in property damage or serious injury 4 3 12  Step ladder must be transported horizontally by two persons always  Stepladders carried on vehicles must be adequately supported to avoid sagging and tied to each support point to minimize movement.  Pre-use ladder inspections must be undertaken.  Defective Stepladders to be labelled to indicate that they are not to be used and defect to be reported to supervisor/Manager. 2 2 4 HSE/QA & QC Project Management Unauthorized use of step ladder Resulting in property damage or injury 4 3 12  Where the possibility of unauthorised usage exists stepladders must be chained / locked to a secure, fixing point. 2 2 4 HSE/QA & QC Project Management Gas Cylinders Storage resulting in Explosion, sudden gas or fluid release, exposure to cylinder contents and fire or struck by a cylinder or suffering a manual handling injury. 4 5 20 Gas cylinders must suitably segregate:  1. Incompatible gasses must be stored apart.  2. Empty and full gas cylinders must be stored apart. Gas cylinder stores must:  Be well ventilated  Be sheltered from indirect heating.  Be free from naked flame.  Be secured so as to prevent unauthorized entry and access to the cylinders.  Gas cylinders must be stored in an upright position and secured in trolley and chains so that they cannot fall over. 2 2 4 HSE/QA & QC Project Management
  • 4. RISK REGISTER Ref. No: Date: Page 4 of 8 HSE Risk Register Hazardous / Flammable Substances Storage Resulting in Fire, explosion, release of a toxic substance, release of a corrosive substance. 4 4 16  Hazardous substances to be stored according to guidance in COSHH assessment or Material Safety Data Sheet provided by supplier  Hazardous/Flammable Substances must be stored in ventilated area or ventilated cabinets  Hazardous substances must be in original container with labels and hazard warnings.  Minimize amount of storage and use of hazardous substances.  Dry Powder or CO2 fire extinguisher to be kept in place where hazardous chemicals are stored.  Authorized personnel to access store or cupboard 2 2 4 HSE/QA & QC Project Management Fire in case of poor electrical sockets, connection or installation. 4 4 16  All broken or poor electrical sockets must be rectified.  All Staff to be briefed for immediate actions in case of fire referring to fire emergency procedures. 2 2 4 HSE/QA & QC Project Management Falling objects from height, ceiling or storage cabinets incase not secured, poorly installed or Sited too high/overloaded 3 4 12  Items must be properly secured or fixed in place.  Shelves must not be overloaded.  Storage must be organized with heavy objects at lower levels.  Restricted access to authorized persons.  Controlled limits of items stored. 2 2 4 HSE/QA &QC Project Management Improper Housekeeping in rest areas & store room resulting in slip, trip and fall 3 3 9  Rubbish to be removed regularly.  Recycling bins to be provided and used. 2 2 4 HSE/QA & QC Project Management Manual Handling Resulting in back pain, strain etc 2 3 6  Staff to be briefed about the dangers of manual handling and instruct to assess the load before handling.  Staff to wear appropriate PPE.  Minimize repetitive bends and ensure to take regular breaks.  In case of heavy weight, more than one staff or mechanical aid to be used. 2 2 4 HSE/QA & QC Project Management
  • 5. RISK REGISTER Ref. No: Date: Page 5 of 8 HSE Risk Register Disposing Hazardous Chemicals 3 4 12  Staff to be given training on safe handling and disposing of hazardous chemicals.  Staff to wear appropriate PPE at all time when disposing hazardous chemicals in order to avoid contact with skin, eyes or inhalation of fumes or vapours.  All hazardous chemicals to be disposed as per local regulations. 2 2 4 HSE/QA & QC Project Management Hygiene and Potential contact with bio hazard waste 3 4 12  Staff to be given training on safe handling and disposing of bio hazard waste.  Staff to wear appropriate PPE (Hand gloves)  Staff to wash hands and forearms before eating, drinking, going to toilet.  Staff to cover any cut or wound and not to expose to avoid infection 2 2 4 HSE/QA & QC Project Management Not carrying Hand tools / Sharp tools Properly and resulting in falling or slipping out of hands 2 3 6  Proper toolbox or bag to be provided in order to carry hand tools/sharp tools. 2 2 4 HSE/QA & QC Project Management Paint Splashing back causing eyes, skin irritation and stains on clothes 4 4 16  Staff to be given orientation/training before commencing of job by Supervisor  Staff to carry out safe work practise  Staff to be given cover all and safety goggles to protect their skin and eyes. 2 2 4 HSE/QA & QC Project Management Staff inhaling fumes emitted by paints/chemicals 4 3 12  Staff to be given orientation/training before commencing of job by Supervisor.  Proper ventilation to be provided in working area  Staff to be provided with nose mask 2 2 4 HSE/QA & QC Project Management Unsafe or improper use of Power toools etc (Hilti machine) causing property damage or injury 4 4 16  Staff to be fully trained in safe use and handling.  Equipment to be checked before each use to ensure that there are no defects in the cable (electric), casing, plug or chuck, etc.  Operator will ensure that there is plenty of room to move comfortably around the material being worked on and that the material is securely clamped where possible 2 2 4 HSE/QA & QC Project Management
  • 6. RISK REGISTER Ref. No: Date: Page 6 of 8 HSE Risk Register  If drilling into walls, the user will check for hidden cables, water pipes etc and if present re-plan work.  If working at height, area to be cordoned off and warning signs erected Vibration/Noise/Dust during equipment usage. 3 4 12  Suitable gloves, goggles, ear defenders and dust mask to be provided to employees when using the equipment.  Dust generated to be removed and disposed of properly 2 2 4 HSE/QA & QC Project Management Jobs related to Confined Space or Hot Work (Cutting, Mixing, Grinding) 4 4 16  In case of any need for hot work or access to confined space, permit to work shall be issued &/or risk assessment shall be provided by HSE/QA & QC dept. 2 2 4 HSE/QA & QC Project Management Use of flammable chemicals at work place 3 4 12  All sources related to fire hazard must be removed before using flammable chemicals at workplace.  Workplace must have proper ventilation or appropriate temperature before using flammable chemicals. 2 2 4 HSE/QA & QC Project Management Tools or machinery With fault or inadequate guarding resulting in personal injury 4 4 16  Safety guards must never be removed or tampered  Low voltage tools to be used  Equipment must visually checked before use  Defective equipment must not be used and reported to supervisor/Manager 2 2 4 HSE/QA & QC Project Management Inadequate Lighting Levels / Dark areas affecting job 2 3 6  Portable lighting or helmet with fixed torch to be used if lighting levels becomes inadequate 2 2 4 HSE/QA & QC Project Management Use of extension leads resulting in tripping, overloading and external use. 3 4 12  Ensure sufficient sockets provided and do not overload sockets.  Use extension leads and adaptors only when necessary ensure they are of a suitable length (preferably no longer than 2 metres) and rated high enough for the job.  Use of cable covers where cables are a trip hazard  Work in progress signage to be in place.  RCD (Residual Current Device) to be used whenever equipment is used externally.  Test RCD regularly to check that its mechanism is free and functioning 2 2 4 HSE/QA & QC Project Management
  • 7. RISK REGISTER Ref. No: Date: Page 7 of 8 HSE Risk Register Fall from height while working at Mobile Scaffolding resulting in fatality, personal injury and damage to property. 4 5 20  Ensure the platform is fully boarded out and guard-rails and toe-boards are in place.  Mobile scaffold s must only be used on firm surfaces in case ground is soft, adequate support must be provided.  The gap between toe-boards and mid guard-rails, and between mid and top guard-rails, must not exceed 470 mm unless otherwise stated by manufacturer.  Never climb up the outside of a mobile scaffold – use the stairway or ladder on the inside. Unless ladder is designed outside  Follow manufacturer’s instructions on base to height ratio.  Don’t pull the mobile scaffold along while standing on it.  Once on mobile scaffold platform use full body harness and properly connect it to the scaffold body 2 2 4 HSE/QA & QC Project Management Contact with overhead objects/ electrocutions while working at Mobile Scaffolding 3 4 12  When moving mobile scaffold s ensure there are no potholes, obstructions or overhead power lines in the way.  When working, ensure the access hatch is closed on the platform (if any). 2 2 4 HSE/QA & QC Project Management Work in extreme weather condition at Mobile Scaffolding. 4 5 20  Work out door using mobile scaffold is not allowed in case of heavy and storm, rain. In summer work outdoor directly under sun is not allowed (midday break rule) 2 2 4 HSE/QA & QC Project Management Overturning of Mobile Scaffolding 4 4 16  Check wheels for effective rotation  Check brakes and locking devices  Ensure that the surface on which the mobile scaffold will be erected is even, rigid and will cope with the scaffold load plus the people and material that will be placed on it.  Don’t move mobile scaffold on ramps 2 2 4 HSE/QA & QC Project Management Using Scaffold in Traffic/ Vehicle manoeuvring area 3 4 12  In case of the use of mobile scaffold to various work tasks in vehicles traffic area then warning tape and traffic cones shall be placed to warn drivers and if required a flag man who is wearing high reflective jacket shall be positioned to warn drivers 2 2 4 HSE/QA & QC Project Management
  • 8. RISK REGISTER Ref. No: Date: Page 8 of 8 HSE Risk Register Use of defective mobile scaffold 3 4 12  Ensure that all parts of MS are in good physical and operational condition. If any part of the scaffold found to be defective it shall be replaced otherwise MS shall never be used  Once scaffold is erected then put a green tape or tag on it to indicate it is safe to be used, but if it is not ready yet then put a red tape / tag. These colours shall be communicated and explained to all those who might use the Mobile scaffold. 2 2 4 HSE/QA & QC Project Management Prepared by: Date: