SlideShare a Scribd company logo
1 of 15
Unit commitment
Ahmed Mohamed abdel-hakeem Elkholy
Economic operation of power system
March 19, 2016
Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 1 of 14
1. Introduction
1.1 Definition
determining the mix of generators and their estimated output
level to meet the expected demand of electricity over a given
time horizon (a day or a week), while satisfying constraints such
as ramp rate limits, up-time and down-time constraints, reserve
and energy requirements. While the load profile is given and also
the unit available to work is given.
Example 1.1
To fully illustrate the uc study the following sample example is
shown. There are three unit with following data.
Unit 1:
PMin = 250 MW, PMax = 600 MW
C1 = 510.0 + 7.9 P1 + 0.00172 P12 $/h
Unit 2:
PMin = 200 MW, PMax = 400 MW
C2 = 310.0 + 7.85 P2 + 0.00194 P22 $/h
Unit 3:
Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 2 of 14
PMin = 150 MW, PMax = 500 MW
C3 = 78.0 + 9.56 P3 + 0.00694 P32 $/h
What combination of units 1, 2 and 3 will produce 550 MW at
minimum cost?
How much should each unit in that combination generate?
Solution:
Taking consideration of above given using excel sheet to solve all
possible scenarios of operations for illustration we will solve one
case manual
Case 6
Scenario is
Unit 1 is off
Unit 1 is on
Unit 1 is on
𝜆 =
𝑝 𝑑 + ∑
𝛽𝑖
2 ∗ 𝛾𝑖
𝑛
𝑖=1
∑
1
2 ∗ 𝛾𝑖
𝑛
𝑖=1
=
550 +
7.85
2 ∗ .00194
+
9.56
2 ∗ .00694
1
2 ∗ .00194
+
1
2 ∗ .00694
= 9.891369369
And the power will be
𝑝 =
𝜆 − 𝛽
2 ∗ 𝛾
Power generated from unit 2 =
Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 3 of 14
=
9.891369369 − 7.85
2 ∗ .00194
= 526.1261261 𝑀𝑊
To meet constrains the power of unit 2 will be 400 mw
P2=400 mw
The power generated from unit3
=
9.891369369 − 9.56
2 ∗ .00694
= 23.87387387 𝑀𝑊
Also to meet constrains of unit 3 will be 150 mw
P2=150 mw
Also we also cheek constrain of power demand that’s
Pload =p1+p2=400+150=550 mw
The total cost by substituted in cost equation (given)
Total cost will be = 5428.55
This is for one case.
All case in table below
Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 4 of 14
in above example for one loading case imagine that we can
consider above example for one hour in a day so we have to
calculate for 24 hour imagine for a week or month
so we find it possible to solve uc problem in that way not just for
long calculation but also considering constrains above example
not taking all constrain as we will illustrate in this report .
But we can learn from example 1.1 that
pmin pmax
U1 U2 U2 250 600 U1 U2 U2
α for units 510 310 78 200 400 510 310 78
β for units 7.9 7.85 9.56 150 500 7.9 7.85 9.56
γ for units 0.0017 0.0019 0.0069 0.002 0.002 0.007
case1 0 0 0 #DIV/0! 0 0 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0!
case2 0 0 1 17.194 150 500 0 0 0 0 0 0 0 0
case3 0 1 0 9.984 200 400 0 0 0 0 0 0 0 0
case4 1 0 0 9.792 250 600 1 550 0 0 5375.3 0 0 5375.3
case5 0 1 1 9.89136937 350 900 1 0 400 150 0 3760.4 1668.15 5428.55
case6 1 1 0 8.87936612 450 1000 1 284.7 265.3 0 2898.538 2529.155 0 5427.693
case7 1 0 1 9.74592148 400 1100 1 400 0 150 3945.2 0 1668.15 5613.35
case8 1 1 1 8.95839745 600 1500
0 0 0 0 0 0 0 0
cost
cost
Units data
λ opration p1 p2 p3
Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 5 of 14
1. When the few units committed then the units can’t meet
the demand.
2. When the units is not enough to be committed then some
units operate above optimum.
3. When the units is many to be committed then some units
below optimum.
4. When the units is too many to be committed then minimum
generation exceeds demand.
5. No-load cost affects choice of optimal combination.
1.2 Type of units or stations.
If we take considerable load profile like
Load
Time
1260 18 24
500
1000
Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 6 of 14
And solve for every hour then
LOAD UNIT 1 UNIT 2 UNIT 3
1100 On On On
1000 On On Off
900 On On Off
800 On On Off
700 On On Off
600 On Off Off
500 On Off Off
From solution we find that
1. There is unit will operate all time so we called it base unit.
2. There is unit will operate part time so we called it
intermediate unit
3. There is unit will operate few time so we called it peak unit
As coming figure describe
Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 7 of 14
2. Constrains
2.1Definition
Constrain is limitations in power system avoiding it cause serious
problem. This limitation can be technical for unit or technical
limitation for power system or can be environmental limitations.
We can classified into
 Unit constrains
 System constrains
 Environmental constraints
 Network Constraints
Load
Time
1260 18 24
Unit 1 or base unit
Unit 2 or intermediate unit
Unit 3 or peak unit
Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 8 of 14
2.2Unit constrains
2.2.1 Maximum generating capacity
That constrain stat that the power generated from the unit
mustn’t exceed specific value because of thermal stability
of the unit exceeding this constrain cause damage to the
unit. Represented in mathematical formula as below.
𝑥( 𝑖, 𝑡) < 𝑝𝑚𝑎𝑥
Where
𝑥( 𝑖, 𝑡) 𝑖𝑠 𝑜𝑢𝑡𝑝𝑢𝑡 𝑝𝑜𝑤𝑒𝑟 𝑜𝑓𝑡ℎ𝑒 𝑢𝑛𝑖𝑡 𝑖 𝑖𝑛 𝑡ℎ𝑒 𝑡𝑖𝑚𝑒 𝑡
2.2.2 Minimum stable generation
As above constrain the power outage from the unit
mustn’t fall down specific value because of technical
limitation like flam stability in the gas and steam units.
Represented in mathematical formula as below.
𝑥( 𝑖, 𝑡) > 𝑝𝑚𝑖𝑛
2.2.3 Minimum up time
This constrain stat that once the unit is running mustn’t
shut down immediately due technical limitation and
mechanical characteristic of the unit. This constrain
represented mathematically as:
Where
If u(i,t) =1 and ti
up
< ti
up,min
then u(i,t +1) =1
Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 9 of 14
2.2.4 Minimum down time
This constrain stat that once the unit is running
mustn’t shut down immediately due technical
limitation and mechanical characteristic of the unit.
This constrain represented mathematically as:
2.2.5 Ramp rates
2.2.5.1 Definition
To avoid damaging the turbine, the
electrical output of a unit cannot change by
more than a certain amount over a period of
time.
2.2.5.2 Ramp Up rate
2.2.5.2.1 Start-up ramp rate
According to this constrain the unit
can’t start immediately but taking
time this time called start up time.
2.2.5.2.2 Running up ramp rate
According to this one in case of
running condition. the unit can’t
u(i,t): Status of unit i at period t
Unit i is on during period tu(i,t) =1:
Unit i is off during period tu(i,t)= 0:
If u(i,t) = 0 and ti
down
< ti
down,min
then u(i,t +1) = 0
Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 10 of 14
immediate changing the power up
without taking time called ramp rate
running up time. The change here
means increasing outage power.
2.2.5.3 Ramp down rate
2.2.5.3.1 Shut down ramp rate
Look like previse constrain the unit take time to
shut down.
2.2.5.3.2 Running down ramp rate
According to this one in case of running condition.
the unit can’t immediate changing the power
down without taking time called ramp rate running
down time. The change here means decreasing
outage power.
2.2.5.4 Mathematical representation
ramp up rate
x i,t +1( )- x i,t( )£ DPi
up,max
ramp down rate
x(i,t)- x(i,t +1) £ DPi
down,max
2.3 Systemconstrains
This constrain that effect more than one unit divide into:
2.3.1 Load / generation balance
Stat as the power generated fromall unit mustbe equal the
load and the losses. Mathematically represented as
∑ 𝑢( 𝑖, 𝑡) ∗ 𝑥( 𝑖, 𝑡) = 𝑙( 𝑡)
𝑛
𝑖=1
𝑤ℎ𝑒𝑟𝑒 𝑙( 𝑡) 𝑖𝑠 𝑡ℎ𝑒 𝑙𝑜𝑎𝑑 𝑝𝑜𝑤𝑒𝑟 𝑎𝑡 𝑡𝑖𝑚𝑒 𝑡
2.3.2 Reserveconstrain
2.3.2.1 Reason to keep reservepower
 Sudden unexpected increasein the load demand
 Forceoutage of some generating units
 Forceoutage of supplementary equipment’s due to stability
problem
 Underestimating the load due to error in load for casting
 Local shortagein the generated power
Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 11 of 14
2.3.2.2 Type of reserve
2.3.2.2.1 Cold reserve
Cold reserveis unit kept reserved for servicebut they are
not available in the immediate loading.
2.3.2.2.2 Hot (spinning) reserve
Hot reserverefers to the extra amount of capacity that
unit can provideimmediately when require.
2.3.2.2.3 Operating reserve
Operating reserveis referring to the capacity that already
in service in excess of peak demand.
2.3.2.3 Other sourceof reserve
There is other sourceof reservelike
 Pumped hydro plants
 Demand reduction (e.g. voluntary load shedding)
2.3.2.4 Condition of reserve
 Reservemust be higher than largest unit
 Should be spread around the network
 Must be able to deploy reserveeven if the network
is congested
 The unit mustoperate at 80-85% of its rated
2.4 Network constrain
Transmission network may havean effect on the
commitment of units because of
 Some units mustrun to providevoltage support
 The output of some units may be limited becausetheir
output would exceed the transmission capacity of the
network
2.5Environmental constrain
uc study is effected by environmentalconstrains becauseof
 constraints on pollutants such SO2, NOxvarious forms:
o Limit on each plant at each hour
o Limit on plant over a year
o Limit on a group of plants over a year
 Constraints on hydro generation
Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 12 of 14
o Protection of wildlife
o Navigation, recreation
2.6Cost constrains
Cost constrain taking two type of costin consideration
2.6.1 Start-up cost
Start-up cost depends on varicosefactor like
 warming up becausethe unit can’t bring on line immediately
 Start-up cost depends on time unit has been off
2.6.2 Running cost
A balance between start-up costs and running costs is
important becauseof
 How long should a unit run to “recover” its start-up
cost?
 Start-up one more large unit or a diesel generator
to cover the peak?
 Shutdown one moreunit at night or run several
units’ part-loaded?
Example:
 Diesel generator: low start-up cost, high running
cost
Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 13 of 14
 Coal plant: high start-up cost, low running cost
3 Summary
The summary of all above that
• Some constraints link periods together
• Minimizing the total cost (start-up + running) mustbe done over the whole
period of study
• Generation scheduling or unit commitment is a more general problem than
economic dispatch
• Economic dispatch is a sub-problemof generation scheduling
4 Type of units according flexibility
4.1Flexible unit
Power output can be adjusting within limits
Example of this unit
– Coal-fired
– Oil-fired
– Open cycle gas turbines
– Combined cycle gas turbines
– Hydro plants with storage
4.2Inflexible unit
Power output cannot be adjusted for technical or commercial reasons
Example of this unit
– Nuclear
– Run-of-the-river hydro
– Renewables (wind, solar,…….)
– Combined heat and power (CHP, cogeneration)
4.2.1.1
4.2.1.2
4.2.2
4.3
4.4
4.4.1.1
4.4.1.2
4.4.1.2.1
Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 14 of 14
4.4.1.2.2
4.4.1.3

More Related Content

What's hot

Load forecasting
Load forecastingLoad forecasting
Load forecastingsushrut p
 
Unit 5 Economic Load Dispatch and Unit Commitment
Unit 5 Economic Load Dispatch and Unit CommitmentUnit 5 Economic Load Dispatch and Unit Commitment
Unit 5 Economic Load Dispatch and Unit CommitmentSANTOSH GADEKAR
 
Economics of power generation
Economics of power generationEconomics of power generation
Economics of power generationAFAQAHMED JAMADAR
 
power flow and optimal power flow
power flow and optimal power flowpower flow and optimal power flow
power flow and optimal power flowAhmed M. Elkholy
 
Economic operation of power system
Economic operation of power systemEconomic operation of power system
Economic operation of power systemBalaram Das
 
Unit 4 Automatic Generation Control
Unit 4 Automatic Generation ControlUnit 4 Automatic Generation Control
Unit 4 Automatic Generation ControlSANTOSH GADEKAR
 
3 reactive power and voltage control
3 reactive power and voltage control3 reactive power and voltage control
3 reactive power and voltage control8141245710
 
Optimization of power sytem
Optimization of power sytemOptimization of power sytem
Optimization of power sytemshawon1981
 
Project on economic load dispatch
Project on economic load dispatchProject on economic load dispatch
Project on economic load dispatchayantudu
 
Power system analysis material -Mathankumar.s VMKVEC
Power system analysis material -Mathankumar.s  VMKVECPower system analysis material -Mathankumar.s  VMKVEC
Power system analysis material -Mathankumar.s VMKVECMathankumar S
 
Overcurrent and Distance Protection in DigSilent PowerFactory
Overcurrent and Distance Protection in DigSilent PowerFactoryOvercurrent and Distance Protection in DigSilent PowerFactory
Overcurrent and Distance Protection in DigSilent PowerFactoryAreeb Abdullah
 
DISTRIBUTED GENERATION TECHNOLOGIES
DISTRIBUTED GENERATION TECHNOLOGIESDISTRIBUTED GENERATION TECHNOLOGIES
DISTRIBUTED GENERATION TECHNOLOGIESEditor IJMTER
 
Distribution System Voltage Drop and Power Loss Calculation
Distribution System Voltage Drop and Power Loss CalculationDistribution System Voltage Drop and Power Loss Calculation
Distribution System Voltage Drop and Power Loss CalculationAmeen San
 
DYNAMIC STABILITY ANALYSIS Small Signal Stability
DYNAMIC STABILITY ANALYSIS Small Signal StabilityDYNAMIC STABILITY ANALYSIS Small Signal Stability
DYNAMIC STABILITY ANALYSIS Small Signal StabilityPower System Operation
 

What's hot (20)

Economic load dispatch
Economic load dispatchEconomic load dispatch
Economic load dispatch
 
Lecture 10
Lecture 10Lecture 10
Lecture 10
 
Load forecasting
Load forecastingLoad forecasting
Load forecasting
 
Unit 5 Economic Load Dispatch and Unit Commitment
Unit 5 Economic Load Dispatch and Unit CommitmentUnit 5 Economic Load Dispatch and Unit Commitment
Unit 5 Economic Load Dispatch and Unit Commitment
 
Economics of power generation
Economics of power generationEconomics of power generation
Economics of power generation
 
CONTROL OF ACTIVE POWER AND FREQUENCY
CONTROL OF ACTIVE POWER AND FREQUENCYCONTROL OF ACTIVE POWER AND FREQUENCY
CONTROL OF ACTIVE POWER AND FREQUENCY
 
TRANSIENT ANGLE STABILITY
TRANSIENT ANGLE STABILITYTRANSIENT ANGLE STABILITY
TRANSIENT ANGLE STABILITY
 
power flow and optimal power flow
power flow and optimal power flowpower flow and optimal power flow
power flow and optimal power flow
 
Economic operation of power system
Economic operation of power systemEconomic operation of power system
Economic operation of power system
 
Unit 4 Automatic Generation Control
Unit 4 Automatic Generation ControlUnit 4 Automatic Generation Control
Unit 4 Automatic Generation Control
 
3 reactive power and voltage control
3 reactive power and voltage control3 reactive power and voltage control
3 reactive power and voltage control
 
Optimization of power sytem
Optimization of power sytemOptimization of power sytem
Optimization of power sytem
 
Project on economic load dispatch
Project on economic load dispatchProject on economic load dispatch
Project on economic load dispatch
 
Economic Dispatch
Economic DispatchEconomic Dispatch
Economic Dispatch
 
Power system analysis material -Mathankumar.s VMKVEC
Power system analysis material -Mathankumar.s  VMKVECPower system analysis material -Mathankumar.s  VMKVEC
Power system analysis material -Mathankumar.s VMKVEC
 
Overcurrent and Distance Protection in DigSilent PowerFactory
Overcurrent and Distance Protection in DigSilent PowerFactoryOvercurrent and Distance Protection in DigSilent PowerFactory
Overcurrent and Distance Protection in DigSilent PowerFactory
 
DISTRIBUTED GENERATION TECHNOLOGIES
DISTRIBUTED GENERATION TECHNOLOGIESDISTRIBUTED GENERATION TECHNOLOGIES
DISTRIBUTED GENERATION TECHNOLOGIES
 
load flow 1
 load flow 1 load flow 1
load flow 1
 
Distribution System Voltage Drop and Power Loss Calculation
Distribution System Voltage Drop and Power Loss CalculationDistribution System Voltage Drop and Power Loss Calculation
Distribution System Voltage Drop and Power Loss Calculation
 
DYNAMIC STABILITY ANALYSIS Small Signal Stability
DYNAMIC STABILITY ANALYSIS Small Signal StabilityDYNAMIC STABILITY ANALYSIS Small Signal Stability
DYNAMIC STABILITY ANALYSIS Small Signal Stability
 

Viewers also liked

Power System Operation and Control
Power System Operation and ControlPower System Operation and Control
Power System Operation and ControlBiswajit Pratihari
 
ECONOMIC LOAD DISPATCH USING PARTICLE SWARM OPTIMIZATION
ECONOMIC LOAD DISPATCH USING PARTICLE SWARM OPTIMIZATIONECONOMIC LOAD DISPATCH USING PARTICLE SWARM OPTIMIZATION
ECONOMIC LOAD DISPATCH USING PARTICLE SWARM OPTIMIZATIONMln Phaneendra
 
Minvrom 06 Mul
Minvrom 06 MulMinvrom 06 Mul
Minvrom 06 Mulaadityaom
 
Dynamic economic load dispatch a review of solution methodologies48
Dynamic economic load dispatch a review of solution methodologies48Dynamic economic load dispatch a review of solution methodologies48
Dynamic economic load dispatch a review of solution methodologies48jiten2k13
 
Optimal load scheduling
Optimal load schedulingOptimal load scheduling
Optimal load schedulingMayank Sharma
 
OPTIMAL ECONOMIC LOAD DISPATCH USING FUZZY LOGIC & GENETIC ALGORITHMS
OPTIMAL ECONOMIC LOAD DISPATCH USING FUZZY LOGIC & GENETIC ALGORITHMSOPTIMAL ECONOMIC LOAD DISPATCH USING FUZZY LOGIC & GENETIC ALGORITHMS
OPTIMAL ECONOMIC LOAD DISPATCH USING FUZZY LOGIC & GENETIC ALGORITHMSIAEME Publication
 
Load Forecasting Techniques.pdf
Load Forecasting Techniques.pdfLoad Forecasting Techniques.pdf
Load Forecasting Techniques.pdfAjay Bhatnagar
 
Load Frequency Control of Two Area System
Load Frequency Control of Two Area SystemLoad Frequency Control of Two Area System
Load Frequency Control of Two Area SystemManash Deka
 
PLANNING ,DECISION MAKING & ORGANIZING
PLANNING ,DECISION MAKING & ORGANIZINGPLANNING ,DECISION MAKING & ORGANIZING
PLANNING ,DECISION MAKING & ORGANIZINGsamsoncj999
 
Commitment management in sap
Commitment management in sapCommitment management in sap
Commitment management in sapRajesh Shanbhag
 

Viewers also liked (20)

Power System Operation and Control
Power System Operation and ControlPower System Operation and Control
Power System Operation and Control
 
ECONOMIC LOAD DISPATCH USING PARTICLE SWARM OPTIMIZATION
ECONOMIC LOAD DISPATCH USING PARTICLE SWARM OPTIMIZATIONECONOMIC LOAD DISPATCH USING PARTICLE SWARM OPTIMIZATION
ECONOMIC LOAD DISPATCH USING PARTICLE SWARM OPTIMIZATION
 
Economic load dispatch
Economic load  dispatchEconomic load  dispatch
Economic load dispatch
 
Minvrom 06 Mul
Minvrom 06 MulMinvrom 06 Mul
Minvrom 06 Mul
 
Ece4762011 lect16
Ece4762011 lect16Ece4762011 lect16
Ece4762011 lect16
 
Dynamic economic load dispatch a review of solution methodologies48
Dynamic economic load dispatch a review of solution methodologies48Dynamic economic load dispatch a review of solution methodologies48
Dynamic economic load dispatch a review of solution methodologies48
 
Lecture 16
Lecture 16Lecture 16
Lecture 16
 
Concept kit: PWM Boost Converter Average Model
Concept kit: PWM Boost Converter Average ModelConcept kit: PWM Boost Converter Average Model
Concept kit: PWM Boost Converter Average Model
 
Optimal load scheduling
Optimal load schedulingOptimal load scheduling
Optimal load scheduling
 
OPTIMAL ECONOMIC LOAD DISPATCH USING FUZZY LOGIC & GENETIC ALGORITHMS
OPTIMAL ECONOMIC LOAD DISPATCH USING FUZZY LOGIC & GENETIC ALGORITHMSOPTIMAL ECONOMIC LOAD DISPATCH USING FUZZY LOGIC & GENETIC ALGORITHMS
OPTIMAL ECONOMIC LOAD DISPATCH USING FUZZY LOGIC & GENETIC ALGORITHMS
 
Economic load dispatch problem solving using "Cuckoo Search"
Economic load dispatch problem solving using "Cuckoo Search"Economic load dispatch problem solving using "Cuckoo Search"
Economic load dispatch problem solving using "Cuckoo Search"
 
Facts controller
Facts controllerFacts controller
Facts controller
 
FACTS Controller.
FACTS Controller.FACTS Controller.
FACTS Controller.
 
Load Forecasting Techniques.pdf
Load Forecasting Techniques.pdfLoad Forecasting Techniques.pdf
Load Forecasting Techniques.pdf
 
Load Frequency Control of Two Area System
Load Frequency Control of Two Area SystemLoad Frequency Control of Two Area System
Load Frequency Control of Two Area System
 
Presentation1
Presentation1Presentation1
Presentation1
 
PLANNING ,DECISION MAKING & ORGANIZING
PLANNING ,DECISION MAKING & ORGANIZINGPLANNING ,DECISION MAKING & ORGANIZING
PLANNING ,DECISION MAKING & ORGANIZING
 
Commitment management in sap
Commitment management in sapCommitment management in sap
Commitment management in sap
 
HVDC & FACTS
HVDC & FACTSHVDC & FACTS
HVDC & FACTS
 
FACTS
FACTS FACTS
FACTS
 

Similar to Unit commitment

Load Forecasting Using LSTM Model
Load Forecasting Using LSTM ModelLoad Forecasting Using LSTM Model
Load Forecasting Using LSTM ModelIRJET Journal
 
Chapter-2.-Variable-Load-Problem_2.pdf
Chapter-2.-Variable-Load-Problem_2.pdfChapter-2.-Variable-Load-Problem_2.pdf
Chapter-2.-Variable-Load-Problem_2.pdfTheBlank5
 
Advanced energy engineering ktu module 1
Advanced energy engineering ktu module 1Advanced energy engineering ktu module 1
Advanced energy engineering ktu module 1NBoss
 
Power_plant_ecomices.pptx
Power_plant_ecomices.pptxPower_plant_ecomices.pptx
Power_plant_ecomices.pptxLucasMogaka
 
Understanding generator set ratings
Understanding generator set ratings   Understanding generator set ratings
Understanding generator set ratings NaveedHussain106
 
Energy, economic and environmental issues of power plants
Energy, economic and environmental issues of power plantsEnergy, economic and environmental issues of power plants
Energy, economic and environmental issues of power plantsBalamurugan Subburaj
 
Variable Frequency Drives and Energy Savings: It‘s More Than Just Fan and Pum...
Variable Frequency Drives and Energy Savings: It‘s More Than Just Fan and Pum...Variable Frequency Drives and Energy Savings: It‘s More Than Just Fan and Pum...
Variable Frequency Drives and Energy Savings: It‘s More Than Just Fan and Pum...Instrument Specialties, Inc.
 
IRJET- An Approach to Offer Price (Generating Station) Arrival Process throug...
IRJET- An Approach to Offer Price (Generating Station) Arrival Process throug...IRJET- An Approach to Offer Price (Generating Station) Arrival Process throug...
IRJET- An Approach to Offer Price (Generating Station) Arrival Process throug...IRJET Journal
 
Load Characteristics
Load CharacteristicsLoad Characteristics
Load CharacteristicsAmeen San
 
Computer Application in Power system: Chapter six - optimization and security
Computer Application in Power system: Chapter six - optimization and securityComputer Application in Power system: Chapter six - optimization and security
Computer Application in Power system: Chapter six - optimization and securityAdama Science and Technology University
 
IRJET- Optimal Generation Scheduling for Thermal Units
IRJET- Optimal Generation Scheduling for Thermal UnitsIRJET- Optimal Generation Scheduling for Thermal Units
IRJET- Optimal Generation Scheduling for Thermal UnitsIRJET Journal
 
IRJET- Optimal Generation Scheduling for Thermal Units
IRJET-  	  Optimal Generation Scheduling for Thermal UnitsIRJET-  	  Optimal Generation Scheduling for Thermal Units
IRJET- Optimal Generation Scheduling for Thermal UnitsIRJET Journal
 
Introducing Electricity Dispatchability Features in TIMES modelling Framework
Introducing Electricity Dispatchability Features in TIMES modelling FrameworkIntroducing Electricity Dispatchability Features in TIMES modelling Framework
Introducing Electricity Dispatchability Features in TIMES modelling FrameworkIEA-ETSAP
 
Controls_for_Remote_Microgrids_with_High_Penetration_Renewable_Generation___P...
Controls_for_Remote_Microgrids_with_High_Penetration_Renewable_Generation___P...Controls_for_Remote_Microgrids_with_High_Penetration_Renewable_Generation___P...
Controls_for_Remote_Microgrids_with_High_Penetration_Renewable_Generation___P...Pieter de Koning, PEng, MBA
 
Protection Schemes for Three Phase Induction Motor
Protection Schemes for Three Phase Induction MotorProtection Schemes for Three Phase Induction Motor
Protection Schemes for Three Phase Induction MotorIRJET Journal
 

Similar to Unit commitment (20)

Load Forecasting Using LSTM Model
Load Forecasting Using LSTM ModelLoad Forecasting Using LSTM Model
Load Forecasting Using LSTM Model
 
Chapter-2.-Variable-Load-Problem_2.pdf
Chapter-2.-Variable-Load-Problem_2.pdfChapter-2.-Variable-Load-Problem_2.pdf
Chapter-2.-Variable-Load-Problem_2.pdf
 
Advanced energy engineering ktu module 1
Advanced energy engineering ktu module 1Advanced energy engineering ktu module 1
Advanced energy engineering ktu module 1
 
UNIT-4-PPT.ppt
UNIT-4-PPT.pptUNIT-4-PPT.ppt
UNIT-4-PPT.ppt
 
Power_plant_ecomices.pptx
Power_plant_ecomices.pptxPower_plant_ecomices.pptx
Power_plant_ecomices.pptx
 
Understanding generator set ratings
Understanding generator set ratings   Understanding generator set ratings
Understanding generator set ratings
 
Economic_Dispatch_in_power_systems.pdf
Economic_Dispatch_in_power_systems.pdfEconomic_Dispatch_in_power_systems.pdf
Economic_Dispatch_in_power_systems.pdf
 
Unit-5.pptx
Unit-5.pptxUnit-5.pptx
Unit-5.pptx
 
Energy, economic and environmental issues of power plants
Energy, economic and environmental issues of power plantsEnergy, economic and environmental issues of power plants
Energy, economic and environmental issues of power plants
 
Variable Frequency Drives and Energy Savings: It‘s More Than Just Fan and Pum...
Variable Frequency Drives and Energy Savings: It‘s More Than Just Fan and Pum...Variable Frequency Drives and Energy Savings: It‘s More Than Just Fan and Pum...
Variable Frequency Drives and Energy Savings: It‘s More Than Just Fan and Pum...
 
IRJET- An Approach to Offer Price (Generating Station) Arrival Process throug...
IRJET- An Approach to Offer Price (Generating Station) Arrival Process throug...IRJET- An Approach to Offer Price (Generating Station) Arrival Process throug...
IRJET- An Approach to Offer Price (Generating Station) Arrival Process throug...
 
K045066265
K045066265K045066265
K045066265
 
Load Characteristics
Load CharacteristicsLoad Characteristics
Load Characteristics
 
Computer Application in Power system: Chapter six - optimization and security
Computer Application in Power system: Chapter six - optimization and securityComputer Application in Power system: Chapter six - optimization and security
Computer Application in Power system: Chapter six - optimization and security
 
IRJET- Optimal Generation Scheduling for Thermal Units
IRJET- Optimal Generation Scheduling for Thermal UnitsIRJET- Optimal Generation Scheduling for Thermal Units
IRJET- Optimal Generation Scheduling for Thermal Units
 
IRJET- Optimal Generation Scheduling for Thermal Units
IRJET-  	  Optimal Generation Scheduling for Thermal UnitsIRJET-  	  Optimal Generation Scheduling for Thermal Units
IRJET- Optimal Generation Scheduling for Thermal Units
 
Introducing Electricity Dispatchability Features in TIMES modelling Framework
Introducing Electricity Dispatchability Features in TIMES modelling FrameworkIntroducing Electricity Dispatchability Features in TIMES modelling Framework
Introducing Electricity Dispatchability Features in TIMES modelling Framework
 
Abb technical guide no.08 revb
Abb technical guide no.08 revbAbb technical guide no.08 revb
Abb technical guide no.08 revb
 
Controls_for_Remote_Microgrids_with_High_Penetration_Renewable_Generation___P...
Controls_for_Remote_Microgrids_with_High_Penetration_Renewable_Generation___P...Controls_for_Remote_Microgrids_with_High_Penetration_Renewable_Generation___P...
Controls_for_Remote_Microgrids_with_High_Penetration_Renewable_Generation___P...
 
Protection Schemes for Three Phase Induction Motor
Protection Schemes for Three Phase Induction MotorProtection Schemes for Three Phase Induction Motor
Protection Schemes for Three Phase Induction Motor
 

More from Ahmed M. Elkholy (10)

Solar system
Solar systemSolar system
Solar system
 
Mep pres
Mep presMep pres
Mep pres
 
Newton raphson
Newton raphsonNewton raphson
Newton raphson
 
Gauss seidel
Gauss seidelGauss seidel
Gauss seidel
 
Ybus
YbusYbus
Ybus
 
Fuel cell
Fuel cellFuel cell
Fuel cell
 
Facts
FactsFacts
Facts
 
COMPETITIVE MARKET
COMPETITIVE MARKET COMPETITIVE MARKET
COMPETITIVE MARKET
 
Optimazation
OptimazationOptimazation
Optimazation
 
power flow and optimal power flow
power flow and optimal power flowpower flow and optimal power flow
power flow and optimal power flow
 

Recently uploaded

High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...Call Girls in Nagpur High Profile
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAbhinavSharma374939
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 

Recently uploaded (20)

High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog Converter
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 

Unit commitment

  • 1. Unit commitment Ahmed Mohamed abdel-hakeem Elkholy Economic operation of power system March 19, 2016
  • 2. Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 1 of 14 1. Introduction 1.1 Definition determining the mix of generators and their estimated output level to meet the expected demand of electricity over a given time horizon (a day or a week), while satisfying constraints such as ramp rate limits, up-time and down-time constraints, reserve and energy requirements. While the load profile is given and also the unit available to work is given. Example 1.1 To fully illustrate the uc study the following sample example is shown. There are three unit with following data. Unit 1: PMin = 250 MW, PMax = 600 MW C1 = 510.0 + 7.9 P1 + 0.00172 P12 $/h Unit 2: PMin = 200 MW, PMax = 400 MW C2 = 310.0 + 7.85 P2 + 0.00194 P22 $/h Unit 3:
  • 3. Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 2 of 14 PMin = 150 MW, PMax = 500 MW C3 = 78.0 + 9.56 P3 + 0.00694 P32 $/h What combination of units 1, 2 and 3 will produce 550 MW at minimum cost? How much should each unit in that combination generate? Solution: Taking consideration of above given using excel sheet to solve all possible scenarios of operations for illustration we will solve one case manual Case 6 Scenario is Unit 1 is off Unit 1 is on Unit 1 is on 𝜆 = 𝑝 𝑑 + ∑ 𝛽𝑖 2 ∗ 𝛾𝑖 𝑛 𝑖=1 ∑ 1 2 ∗ 𝛾𝑖 𝑛 𝑖=1 = 550 + 7.85 2 ∗ .00194 + 9.56 2 ∗ .00694 1 2 ∗ .00194 + 1 2 ∗ .00694 = 9.891369369 And the power will be 𝑝 = 𝜆 − 𝛽 2 ∗ 𝛾 Power generated from unit 2 =
  • 4. Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 3 of 14 = 9.891369369 − 7.85 2 ∗ .00194 = 526.1261261 𝑀𝑊 To meet constrains the power of unit 2 will be 400 mw P2=400 mw The power generated from unit3 = 9.891369369 − 9.56 2 ∗ .00694 = 23.87387387 𝑀𝑊 Also to meet constrains of unit 3 will be 150 mw P2=150 mw Also we also cheek constrain of power demand that’s Pload =p1+p2=400+150=550 mw The total cost by substituted in cost equation (given) Total cost will be = 5428.55 This is for one case. All case in table below
  • 5. Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 4 of 14 in above example for one loading case imagine that we can consider above example for one hour in a day so we have to calculate for 24 hour imagine for a week or month so we find it possible to solve uc problem in that way not just for long calculation but also considering constrains above example not taking all constrain as we will illustrate in this report . But we can learn from example 1.1 that pmin pmax U1 U2 U2 250 600 U1 U2 U2 α for units 510 310 78 200 400 510 310 78 β for units 7.9 7.85 9.56 150 500 7.9 7.85 9.56 γ for units 0.0017 0.0019 0.0069 0.002 0.002 0.007 case1 0 0 0 #DIV/0! 0 0 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! case2 0 0 1 17.194 150 500 0 0 0 0 0 0 0 0 case3 0 1 0 9.984 200 400 0 0 0 0 0 0 0 0 case4 1 0 0 9.792 250 600 1 550 0 0 5375.3 0 0 5375.3 case5 0 1 1 9.89136937 350 900 1 0 400 150 0 3760.4 1668.15 5428.55 case6 1 1 0 8.87936612 450 1000 1 284.7 265.3 0 2898.538 2529.155 0 5427.693 case7 1 0 1 9.74592148 400 1100 1 400 0 150 3945.2 0 1668.15 5613.35 case8 1 1 1 8.95839745 600 1500 0 0 0 0 0 0 0 0 cost cost Units data λ opration p1 p2 p3
  • 6. Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 5 of 14 1. When the few units committed then the units can’t meet the demand. 2. When the units is not enough to be committed then some units operate above optimum. 3. When the units is many to be committed then some units below optimum. 4. When the units is too many to be committed then minimum generation exceeds demand. 5. No-load cost affects choice of optimal combination. 1.2 Type of units or stations. If we take considerable load profile like Load Time 1260 18 24 500 1000
  • 7. Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 6 of 14 And solve for every hour then LOAD UNIT 1 UNIT 2 UNIT 3 1100 On On On 1000 On On Off 900 On On Off 800 On On Off 700 On On Off 600 On Off Off 500 On Off Off From solution we find that 1. There is unit will operate all time so we called it base unit. 2. There is unit will operate part time so we called it intermediate unit 3. There is unit will operate few time so we called it peak unit As coming figure describe
  • 8. Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 7 of 14 2. Constrains 2.1Definition Constrain is limitations in power system avoiding it cause serious problem. This limitation can be technical for unit or technical limitation for power system or can be environmental limitations. We can classified into  Unit constrains  System constrains  Environmental constraints  Network Constraints Load Time 1260 18 24 Unit 1 or base unit Unit 2 or intermediate unit Unit 3 or peak unit
  • 9. Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 8 of 14 2.2Unit constrains 2.2.1 Maximum generating capacity That constrain stat that the power generated from the unit mustn’t exceed specific value because of thermal stability of the unit exceeding this constrain cause damage to the unit. Represented in mathematical formula as below. 𝑥( 𝑖, 𝑡) < 𝑝𝑚𝑎𝑥 Where 𝑥( 𝑖, 𝑡) 𝑖𝑠 𝑜𝑢𝑡𝑝𝑢𝑡 𝑝𝑜𝑤𝑒𝑟 𝑜𝑓𝑡ℎ𝑒 𝑢𝑛𝑖𝑡 𝑖 𝑖𝑛 𝑡ℎ𝑒 𝑡𝑖𝑚𝑒 𝑡 2.2.2 Minimum stable generation As above constrain the power outage from the unit mustn’t fall down specific value because of technical limitation like flam stability in the gas and steam units. Represented in mathematical formula as below. 𝑥( 𝑖, 𝑡) > 𝑝𝑚𝑖𝑛 2.2.3 Minimum up time This constrain stat that once the unit is running mustn’t shut down immediately due technical limitation and mechanical characteristic of the unit. This constrain represented mathematically as: Where If u(i,t) =1 and ti up < ti up,min then u(i,t +1) =1
  • 10. Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 9 of 14 2.2.4 Minimum down time This constrain stat that once the unit is running mustn’t shut down immediately due technical limitation and mechanical characteristic of the unit. This constrain represented mathematically as: 2.2.5 Ramp rates 2.2.5.1 Definition To avoid damaging the turbine, the electrical output of a unit cannot change by more than a certain amount over a period of time. 2.2.5.2 Ramp Up rate 2.2.5.2.1 Start-up ramp rate According to this constrain the unit can’t start immediately but taking time this time called start up time. 2.2.5.2.2 Running up ramp rate According to this one in case of running condition. the unit can’t u(i,t): Status of unit i at period t Unit i is on during period tu(i,t) =1: Unit i is off during period tu(i,t)= 0: If u(i,t) = 0 and ti down < ti down,min then u(i,t +1) = 0
  • 11. Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 10 of 14 immediate changing the power up without taking time called ramp rate running up time. The change here means increasing outage power. 2.2.5.3 Ramp down rate 2.2.5.3.1 Shut down ramp rate Look like previse constrain the unit take time to shut down. 2.2.5.3.2 Running down ramp rate According to this one in case of running condition. the unit can’t immediate changing the power down without taking time called ramp rate running down time. The change here means decreasing outage power. 2.2.5.4 Mathematical representation ramp up rate x i,t +1( )- x i,t( )£ DPi up,max ramp down rate x(i,t)- x(i,t +1) £ DPi down,max 2.3 Systemconstrains This constrain that effect more than one unit divide into: 2.3.1 Load / generation balance Stat as the power generated fromall unit mustbe equal the load and the losses. Mathematically represented as ∑ 𝑢( 𝑖, 𝑡) ∗ 𝑥( 𝑖, 𝑡) = 𝑙( 𝑡) 𝑛 𝑖=1 𝑤ℎ𝑒𝑟𝑒 𝑙( 𝑡) 𝑖𝑠 𝑡ℎ𝑒 𝑙𝑜𝑎𝑑 𝑝𝑜𝑤𝑒𝑟 𝑎𝑡 𝑡𝑖𝑚𝑒 𝑡 2.3.2 Reserveconstrain 2.3.2.1 Reason to keep reservepower  Sudden unexpected increasein the load demand  Forceoutage of some generating units  Forceoutage of supplementary equipment’s due to stability problem  Underestimating the load due to error in load for casting  Local shortagein the generated power
  • 12. Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 11 of 14 2.3.2.2 Type of reserve 2.3.2.2.1 Cold reserve Cold reserveis unit kept reserved for servicebut they are not available in the immediate loading. 2.3.2.2.2 Hot (spinning) reserve Hot reserverefers to the extra amount of capacity that unit can provideimmediately when require. 2.3.2.2.3 Operating reserve Operating reserveis referring to the capacity that already in service in excess of peak demand. 2.3.2.3 Other sourceof reserve There is other sourceof reservelike  Pumped hydro plants  Demand reduction (e.g. voluntary load shedding) 2.3.2.4 Condition of reserve  Reservemust be higher than largest unit  Should be spread around the network  Must be able to deploy reserveeven if the network is congested  The unit mustoperate at 80-85% of its rated 2.4 Network constrain Transmission network may havean effect on the commitment of units because of  Some units mustrun to providevoltage support  The output of some units may be limited becausetheir output would exceed the transmission capacity of the network 2.5Environmental constrain uc study is effected by environmentalconstrains becauseof  constraints on pollutants such SO2, NOxvarious forms: o Limit on each plant at each hour o Limit on plant over a year o Limit on a group of plants over a year  Constraints on hydro generation
  • 13. Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 12 of 14 o Protection of wildlife o Navigation, recreation 2.6Cost constrains Cost constrain taking two type of costin consideration 2.6.1 Start-up cost Start-up cost depends on varicosefactor like  warming up becausethe unit can’t bring on line immediately  Start-up cost depends on time unit has been off 2.6.2 Running cost A balance between start-up costs and running costs is important becauseof  How long should a unit run to “recover” its start-up cost?  Start-up one more large unit or a diesel generator to cover the peak?  Shutdown one moreunit at night or run several units’ part-loaded? Example:  Diesel generator: low start-up cost, high running cost
  • 14. Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 13 of 14  Coal plant: high start-up cost, low running cost 3 Summary The summary of all above that • Some constraints link periods together • Minimizing the total cost (start-up + running) mustbe done over the whole period of study • Generation scheduling or unit commitment is a more general problem than economic dispatch • Economic dispatch is a sub-problemof generation scheduling 4 Type of units according flexibility 4.1Flexible unit Power output can be adjusting within limits Example of this unit – Coal-fired – Oil-fired – Open cycle gas turbines – Combined cycle gas turbines – Hydro plants with storage 4.2Inflexible unit Power output cannot be adjusted for technical or commercial reasons Example of this unit – Nuclear – Run-of-the-river hydro – Renewables (wind, solar,…….) – Combined heat and power (CHP, cogeneration) 4.2.1.1 4.2.1.2 4.2.2 4.3 4.4 4.4.1.1 4.4.1.2 4.4.1.2.1
  • 15. Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 14 of 14 4.4.1.2.2 4.4.1.3