SlideShare a Scribd company logo
1 of 111
1539pk
TRANSIENT (ANGLE)
STABILITY
Copyright © P. Kundur
This material should not be used without the author's consent
1539pkTS - 1
Transient Angle Stability
 Description of Transient Stability
 An elementary view of TS
 Methods of TS analysis
 Time-domain simulation
 Structure of power system model
 Representation faults
 Performance of protective relaying
 Concept of “electrical centre”
 Case studies
 Methods of TS enhancement
 Major blackouts caused by Transient Instability
 November 9, 1965 Northeast US, Ontario
blackout
 March 11, 1999 Brazil blackout
Outline
1539pkTS - 2
What is Transient (Angle) Stability?
 The ability of the power system to maintain
synchronous operation when subjected to a severe
transient disturbance
 faults on transmission circuits, transformers,
buses
 loss of generation
 loss of loads
 Response involves large excursions of generator
rotor angles: influenced by nonlinear power-angle
relationship
 Stability depends on both the initial operating state
of the system and the severity of the disturbance
 Post-disturbance steady-state operating conditions
usually differ from pre-disturbance conditions
1539pkTS - 3
 In large power systems, transient instability may not
always occur as "first swing" instability
 could be as a result of superposition of several
swing modes causing large excursions of rotor
angle beyond the first swing
 Study period of interest in transient stability studies
is usually limited to 3 to 5 seconds following the
disturbance;
 may extend up to about 10 seconds for very large
systems with dominant inter-area swing modes
 Power system designed and operated to be stable for
specified set of contingencies referred to as "normal
design contingencies"
 selected on the basis that they have a reasonable
probability of occurrence
 In the future, probabilistic or risk-based approach
may be used
1539pkTS - 4
1. An Elementary View of Transient
Stability
 Demonstrate the phenomenon using a very simple
system and simple models
 System shown in Fig. 13.1
 All resistances are neglected
 Generator is represented by the classical model
Fig. 13.1 Single machine - infinite bus system
1539pkTS - 5
 The generator's electrical power output is
 With the stator resistance neglected, Pe represents the
air-gap power as well as the terminal power
Fig. 13.2 System representation with generator
represented by classical model


 sinsin max
P
X
EE
P
T
B
e
1539pkTS - 6
Power-Angle Relationship
 Both transmission circuits in-service: Curve 1
 operate at point "a" (Pe = Pm)
 One circuit out-of-service: Curve 2
 lower Pmax
 operate at point "b"
 higher reactance  higher  to transmit same
power
Fig. 13.3 Power-angle relationship
1539pkTS - 7
 The oscillation of  is superimposed on the
synchronous speed a0
 Speed deviation
the generator speed is practically equal to a0, and the
per unit (pu) air-gap torque may be considered to be
equal to the pu air-gap power
torque and power are used interchangeably when
referring to the swing equation.
Equation of Motion or Swing Equation
where:
Pm = mechanical power input (pu)
Pmax = maximum electrical power output (pm)
H = inertia constant (MW-sec/MVA)
L = rotor angle (elec. radians)
t = time (secs)
Effects of Disturbance
  0r dt
d  



sinPP
dt
dH2
maxm2
2
0

1539pkTS - 8
Response to a Short Circuit Fault
 Illustrate the equal area criterion using the following
system:
 Examine the impact on stability of different fault
clearing times
1539pkTS - 9
Stable Case
Response to a fault cleared in tcl seconds - stable case
1539pkTS - 10
Stable Case cont'd
Pre-disturbance:
 both circuits I/S : Pe = Pm, δ = δ0
 operating point a
Fault On:
 operating point moves from a to b
 inertia prevents δ from changing instantaneously
 Pm > Pe  rotor accelerates to operating point c
Post Fault:
 faulted circuit is tripped, operating point shifts to d
 Pe > Pm  rotor decelerates
 rotor speed > 0  δ increases
 operating point moves from d to e such that A1 = A2
 at e, speed = 0, and δ = δ m
 Pe > Pm  rotor decelerates; speed below a0
 δ decreases and operating point retraces e to d
 with no damping, rotor continues to oscillate
1539pkTS - 11
Unstable Case
Response to a fault cleared in tc2 seconds - unstable case
1539pkTS - 12
Unstable Case cont'd
 Area A2 above Pm is less than A1
 When the operating point reaches e, the kinetic
energy gained during the accelerating period has not
yet been completely expended
 the speed is still greater than 0 and  continues to
increase
 Beyond point e, Pe<Pm,  rotor begins to accelerate
again
 The rotor speed and angle continue to increase
leading to loss of synchronism
1539pkTS - 13
Factors Influencing Transient Stability
(a) How heavily the generator is initially loaded.
(b) The generator output during the fault. This depends
on the fault location and type.
(c) The fault clearing time.
(d) The post-fault transmission system reactance.
(e) The generator reactance. A lower reactance increases
peak power and reduces initial rotor angle.
(f) The generator inertia. The higher the inertia, the
slower the rate of change angle. This reduces the
kinetic energy gained during fault, i.e. area A1 is
reduced.
(g) The generator internal voltage magnitude (El). This
depends on the field excitation.
(h) The infinite bus voltage magnitude EB.
1539pkTS - 14
Practical Method of TS Analysis
 Practical power systems have complex network
structures
 Accurate analysis of transient stability requires
detailed models for:
 generating unit and controls
 voltage dependent load characteristics
 HVDC converters, FACTs devices, etc.
 At present, the most practical available method of
transient stability analysis is time domain simulation:
 solution of nonlinear differential equations and
algebraic equations
 step-by-step numerical integration techniques
 complimented by efficient techniques for solving
non-linear highly sparse algebraic equations
1539pkTS - 15
2. Numerical Integration Methods
Differential equations to be solved are nonlinear
ordinary differential equations with known initial
values:
x is the state vector of n dependent variables,
t is the independent variable (time)
Objective: solve x as a function of t, with the initial
values of x and t equal to x0 and t0, respectively.
Methods: Euler's Method
Modified Euler's Method
Runge-Kutta (R-K) Methods
Trapezoidal Rule
 txf
dt
dx
,
1539pkTS - 16
Numerical stability
 Depends on propagation of error
 Numerically stable if early errors cause no significant
errors later
 Numerically unstable otherwise
Important to consider numerical stability in the
application of numerical integration methods
1539pkTS - 17
Stiffness of Differential Equations
 Ratio of largest to smallest time constants or, more
precisely, eigenvalues
 Increases with modelling detail
 Affects numerical stability
 Solution using explicit integration methods may
"blow up" with stiff systems unless very small time
step is used.
1539pkTS - 18
Numerical Stability of Explicit Integration
Methods
Explicit Methods
 Euler's, Predictor-Corrector, and R-K methods
 Dependent variables x at any value of t is computed from
a knowledge of the values of x from the previous time
steps
 xn+1 for (n+1)th step is calculated explicitly by
evaluating f(x,t) with known x
 Easy to implement for the solution of a complex set of
system state equations
Disadvantage
 Not numerically A-stable
 step size limited by small time constants or
eigenvalues
1539pkTS - 19
Implicit Integration Methods
 Consider the differential equation
The solution for x at t=t1=t0+t may be expressed in
the integral form as
 Implicit methods use interpolation functions for the
expression under the integral
 Interpolation implies that the functions must pass
through the yet unknown points at time t1
 Trapezoidal Rule is simplest method
   dxfxx
t
t ,1
001
  00, ttatxxwithtxf
dt
dx

1539pkTS - 20
Trapezoidal Rule
 Simplest implicit method; uses linear interpolation
 Integral approximated by trapezoids
f(x,t)
f(x0,t0)
f(x1,t1)
t0 t1
t
t
Fig. 13.7
1539pkTS - 21
 Trapezoidal rule is given by
A general formula giving the value of x at t=tn+1 is
 Xn+1 appears on both sides of Equation
 implies that the variable x is computed as a function
of its value at the previous time step as well as the
current value (which is unknown)
 an implicit equation must be solved
 Numerically A-stable : stiffness affects accuracy not
stability
 Trapezoidal rule is a second order method
 Higher order methods difficult to program and less
robust
    110001 t,xft,xf
2
t
xx 

    1n1nnnn1n t,xft,xf
2
t
xx  

1539pkTS - 22
3. Simulation of Power System Dynamic
Response
Structure of the Power System Model:
Components:
 Synchronous generators, and the associated excitation
systems and prime movers
 Interconnecting transmission network including static
loads
 Induction and synchronous motor loads
 Other devices such as HVDC converters and SVCs
Monitored Information:
 Basic stability information
 Bus voltages
 Line flows
 Performance of protective relaying, particularly
transmission line protection
1539pkTS - 23
Fig. 13.8 Structure of the complete power system model
for transient stability analysis
1539pkTS - 24
 Models used must be appropriate for transient
stability analysis
 transmission network and machine stator
transients are neglected
 dynamics of machine rotors and rotor circuits,
excitation systems, prime movers and other
devices such as HVDC converters are represented
 Equations must be organized in a form suitable for
numerical integration
 Large set of ordinary differential equations and large
sparse algebraic equations
 differential-algebraic initial value problem
1539pkTS - 25
Overall System Equations
 Equations for each dynamic device:
 where
xd = state vector of individual device
Id = R and I components of current injection from
the device into the network
Vd = R and I components of bus voltage
 Network equation:
where
YN = network mode admittance matrix
I = node current vector
V = node voltage vector
 
 dddd
dddd
VxgI
Vxfx
,
,


VYI N
1539pkTS - 26
 Overall system equations:
comprises a set of first order differentials
and a set of algebraic equations
where
x = state vector of the system
V = bus voltage vector
I = current injection vector
Time t does not appear explicitly in the above
equations
 Many approaches for solving these equations
characterized by:
a) The manner of interface between the differential and
algebraic equations: partitioned or simultaneous
b) Integration method used
c) Method used for solving the algebraic equations:
- Gauss-Seidal method based on admittance matrix
- direct solution using sparsity oriented triangular
factorization
- iterative solution using Newton-Raphson method
 Vxfx ,
  VYVxI N,
1539pkTS - 27
 Analyze transient stability including the effects of
rotor circuit dynamics and excitation control of the
following power plant with four 555 MVA units:
 Disturbance: Three phase fault on circuit #2 at F,
cleared by tripping the circuit
Example 13.2
Fig. E13.6
1539pkTS - 28
Generator parameters:
The four generators of the plant are represented by an equivalent
generator whose parameters in per unit on 2220 MVA base are as
follows:
The above parameters are unsaturated values. The effect of
saturation is to be represented assuming the d- and q-axes have
similar saturation characteristics based on OCC
Excitation system parameters:
The generators are equipped with thyristor exciters with AVR and
PSS as shown in Fig. 13.12, with parameters as follows:
The exciter is assumed to be alternator supplied; therefore EFmax and
EFmin are independent of Et
Pre-fault system condition in pu on 2220 MVA, 24 kV base:
P = 0.9 Q = 0.436 (overexcited)
Et = 1.0 28.34 EB = 0.90081 0
Xd=1.81 Xq=1.76 Xd=0.30 Xq=0.65
Xd=0.23 Xq=0.25 X1=0.15 Ra=0.003
To0=8.0s Tq0=1.0s Td0=0.03s Tqo=0.07s
H = 3.5 K0 = 0
''
'
''
' ''
' '
''
KA= 200 TR= 0.015s EFmax= 7.0 EFmin= -6.4
KSTAB= 9.5 TW= 1.41s T1= 0.154s T2= 0.033s
Vsmax= 0.2 Vsmin= -0.2
1539pkTS - 29
Objective
Examine the stability of the system with the following
alternative forms of excitation control:
(i) Manual control, i.e., constant Efd
(ii) AVR with no PSS
(iii) AVR with PSS
Consider the following alternative fault clearing
times:
a) 0.07 s
b) 0.10 s
1539pkTS - 30
 Computed using the Gill's version of fourth order R-K
integration method with a time step of 0.02 s.
 With constant Efd, the system is transiently stable
 however, the level of damping of oscillations is
low
 With a fast acting AVR and a high exciter ceiling
voltage, the first rotor angle swing is significantly
reduced
 however, the subsequent swings are negatively
damped
 post-fault system small-signal unstable
 With the PSS, the rotor oscillations are very well
damped without compromising the first swing
stability
Case (a): Transient response with the fault clearing
time equal to 0.07 s
1539pkTS - 31
Fig. E13.7(a) Rotor angle response with fault
cleared in 0.07 s
Fig. E13.7(b) Active power response with fault
cleared in 0.07 s
1539pkTS - 32
Fig. E13.7(c) Terminal voltage response with fault
cleared in 0.07 s
Fig. E13.7(d) Exciter output voltage response with
fault cleared in 0.07 s
1539pkTS - 33
 Responses of rotor angle  with the three alternative
forms of excitation control are computed
 With constant Efd, the generator is first swing
unstable
 With a fast acting exciter and AVR, the generator
maintains first swing stability, but loses synchronism
during the second swing
 The addition of PSS contributes to the damping of
second and subsequent swings
Use of a fast exciter having a high ceiling
voltage and equipped with a PSS contributes
significantly to the enhancement of the overall
system stability!
Case (b): Transient response with the fault clearing
time tc equal to 0.1 s
1539pkTS - 34
Fig. E13.8 Rotor angle response with fault cleared
in 0.1 s
1539pkTS - 35
Example 13.3
 For the system considered in previous example, examine
the accuracy and numerical stability of the Gill's version of
the 4th order R-K method and the trapezoidal rule
 Consider the case with rotor circuit dynamics, AVR and
PSS (i.e. stiff system), and the fault cleared in 0.07 s
Results with R-K method:
1539pkTS - 36
 For 0.01 s and 0.0590 s, the results are practically identical
 When increased to 0.09 s, significant errors result; however,
the general characteristics of the overall response is still
retained
 With a step size of 0.093 s, the errors become so large that
the solution blows up after about 1.7 s.
Results with Trapezoidal Rule
1539pkTS - 37
5. Representation of Faults in Stability
Studies
 Positive-sequence network is represented in detail
 Negative- and zero-sequence voltages and currents
throughout the system are usually not of interest in
stability studies
 unnecessary to simulate the complete negative- and
zero-sequence networks in system stability
simulations
 effects represented by equivalent impedances (Z2
and Z0) as viewed at the fault point F
 Impedances are combined appropriately as the
effective fault impedance Zef
1539pkTS - 38
6. Performance of Protective Relaying
 Monitor, detect abnormal conditions, select breakers
to be opened, and energize trip circuits
 Three requirements: selectivity, speed, and reliability
 distinguish between stable swings and out-of-step
 operate when needed and only when needed
 operate sufficiently fast
 coordinate with other relays
 Function of certain relays essential to ensure
transient stability
 Special relaying may be used to separate systems
 Of particular importance is transmission line
protection schemes
1539pkTS - 39
Transmission Line Protection
Two types of relaying schemes widely used currently:
a) Current differential schemes, and
b) Distance relaying schemes
Types of Hardware:
a) Electromechanical relays
b) Static relays
c) Digital or “numerical” relays
Modern “digital relays”, in addition to basic protective
relaying functions, have system monitoring
capability:
 allowing complementary control and monitoring
functions.
1539pkTS - 40
(a) Current Differential Relaying
 Based on the principal that under normal operating
conditions, current injected to the element on one side
is extracted at the other side
 Mainly used in the past for lines too short for reliable
application of distance relaying
 Currently, differential protection schemes using fiber
optic communication medium are increasingly being
used, in particular for:
 series capacitor compensated lines
 short lines in load centers
 multi-terminal lines
 Relaying capability completely dependent on the
availability of telecommunication system
 To meet the requirement for a communication
independent backup protection
 conventional distance protection , typically zone 1
and zone 2 , with time delays are used as backup to
differential protection
1539pkTS - 41
(b) Distance Relaying
 Responds to a ratio of measured voltage to measured
current
 Impedance is a measure of distance along the line
 Good discrimination and selectivity, by limiting relay
operation to a certain range of the impedance
 Types
 impedance relay
 reactance relay
 mho relay
 modified mho and impedance relays, and
 Special shaped characteristics
 Most widely used form for protection of transmission
lines
 Triggering characteristics shown conveniently on
R-X plane
1539pkTS - 42
Fig. 13.28 Distance relay characteristics displayed on a
coordinate system with resistance (R) as the abscissa,
and reactance (X) as the ordinate
1539pkTS - 43
Three zone approach:
 Zone 1 primary protection for protected line
 80% reach and instantaneous
 Zone 2 primary protection for protected line
 120% reach and timed (0.3 - 0.5 s)
 Zone 3 remote backup protection for adjacent line
 covers next line and timed (2 s)
Fig. 13.29 Distance relay characteristic
1539pkTS - 44
Communication assisted
Distance Relaying
 Use communication channels between the terminals
of the line that they protect
 Determine whether the fault is internal or external to
the protected line, and this information is transmitted
 For an internal fault, circuit breakers at all terminals
of the protected line are tripped; for an external fault
the tripping is blocked
 Communication medium may be pilot wire (metallic
wires), power-line carrier, microwave, or fiber optic
 Overall objective is to clear faults at high speed
1539pkTS - 45
Each terminal station of the line has:
 Underreaching zone 1 phase and ground directional
distance relays covering about 75-80% of the line
 trip local breakers instantaneously
 Overreaching zone 2 phase and ground directional
distance relays covering about 120% of the impedance of
the protected line.
 send permissive signal to remote end
 trip local breakers if permissive signal received
from remote end
 if apparent Z remains inside relay characteristic
for fixed time (typically 0.4 s), local breakers
tripped without receiving permissive signal
Fig. 13.30 Permissive overreaching relay
Permissive Overreaching Scheme:
1539pkTS - 46
Fig. 13.31 Relay characteristic at station A
Fig. 13.31 Fault locations F1, F2 and F3
1539pkTS - 47
Fault Clearing Times
 Composed of relay time and breaker operating time
 EHV relays: 1-2 cycles
 Circuit breakers: 2-4 cycles
 Breaker failure backup protection provided for each
breaker on all critical circuits
 if a breaker fails to operate at a local station, trip
signals sent to adjacent zone breakers and remote
end breakers
1539pkTS - 48
Notes:
(i) For purposes of illustration, 2 cycle breakers have been assumed at
A and 3 cycle breakers at B
(ii) Communication time depends on channel medium used. With
power line carrier, the time may be longer
Local (Bus A) breakers 1
and 2
Remote (Bus B) breakers 3
and 4
Primary relay time
(Fault detection)
25 ms 25 ms
Auxiliary relay(s) time 3 ms 9 ms
Communication time - 17 ms (microwave)
Breaker trip module 3 ms 3 ms
Breaker clearing time 33 ms (2 cycles) 50 ms (3 cycles)
Total Time 64 ms 104 ms
Fault cleared from bus A in 64 milliseconds
Fault cleared from bus B in 104 milliseconds
Fig. 13.34 Typical fault clearing times for a normally
cleared fault
1539pkTS - 49
Notes:
Breaker failure timer setting has been assumed to be 90 ms for the 2 cycle breaker 4.
This could vary from one application to another. For a 3 cycle oil breaker a typical
value is 150 ms
Fig. 13.34 Typical fault clearing times for a stuck breaker
fault
Local
Breaker 5
Remote
breakers
6 and 7
Local backup
breaker 3
Remote backup
breakers
1 and 2
Primary relay time (at
bus B)
25 ms 25 ms 25 ms 25 ms
Auxiliary relay(s) time 3 ms 9 ms 6 ms 12 ms
Communication
channel time
- 17 ms - 17 ms
Breaker failure timer
setting
- - 90 ms 90 ms
Breaker tripping
module time
3 ms 3 ms 3 ms 3 ms
Breaker time 33 ms 50 ms 33 ms 33 ms
Total time 64 ms 104 ms 157 ms 180 ms
Fault cleared from bus C in 104 milliseconds
Fault cleared from bus B in 157 milliseconds
Fault cleared from bus A in 180 milliseconds
Breaker 4 assumed to be stuck
Breakers 1, 2, 3, 4, and 5 assumed to be 2 cycle air-blast breakers (33 ms)
Breakers 6 and 7 assumed to be 3 cycle oil breakers (50 ms)
1539pkTS - 50
Relaying Quantities During Swings
The performance of protective relaying during electro-
mechanical oscillations and out-out-step conditions
illustrated by considering the following system:
(a) Schematic diagram
(b) Equivalent circuit
Fig. 13.36 Two machine system
The current I is given by
The voltage at bus C is
T
BA
Z
EE
I
0~ 

IZEE AAC
~~~

1539pkTS - 51
The apparent impedance seen by an impedance relay at
C looking towards the line is given by
If EA=EB=1.0 pu
0EE
E
ZZ
I
~
I
~
ZE
~
I
~
E
~
Z
BA
A
TA
AAC
C







  
























 








2
cot
2
Z
jZ
2
Z
sin2
cos1
j
2
1
ZZ
sinj2
sinjcos1
ZZ
101101
101
ZZ
101
Z
ZZ
T
A
T
TA
TA
TA
T
AC








1539pkTS - 52
During a swing, the angle  changes. Fig. 13.37 shows
the locus of ZC as a function of  on an R-X diagram,
when EA=EB
Note: Origin is assumed to be at C, where the relay is located.
Fig. 13.37 Locus of ZC as a function of , with EA=EB
1539pkTS - 53
 When EA and EB are equal, the locus of ZC is seen to be a
straight line which is the perpendicular bisector of the
total system impedance between A and B, i.e., of the
impedance ZT
 the angle formed by lines from A and B to any
point on the locus is equal to the corresponding
angle 
 When =0, the current I is zero and ZC is infinite
 When =180°, the voltage at the electrical centre is zero
 the relay at C in effect will see a 3-phase fault at
the electrical centre. The electrical centre and
impedance centre coincide in this case.
 If EA is not equal to EB, the apparent impedance loci are
circles, with their centres on extensions of the
impedance line AB
 When EA>EB, the electrical centre will be above the
impedance centre; when EA<EB, the electrical centre will
be below the impedance centre. Fig. 13.38 illustrates the
shape of the apparent impedance loci for three different
values of the ratio EA / EB.
1539pkTS - 54
Fig. 13.38 Loci of ZC with different values of EA/EB
1539pkTS - 55
 For generators connected to the main system through a
weak transmission system (high external impedance),
the electrical centre may appear on the transmission line
 When a generator is connected to the main system
through a strong transmission system, the electrical
centre will be in the step up transformer or possibly
within the generator itself
 Electrical centres in effect are not fixed points: effective
machine reactance and the magnitudes of internal
voltages vary during dynamic conditions.
 Voltage at the electrical centre drops to zero as 
increases to 180° and then increases in magnitude as 
increases further until it reaches 360°
 when  reaches 180°, the generator will have
slipped a pole; when  reaches the initial value
where the swing started, one slip cycle will have
been completed.
1539pkTS - 56
Prevention of Transmission Line Tripping
During Transient Conditions
Requirements for prevention of tripping during swing
conditions fall into two categories:
 Prevention of tripping during stable swings, while
allowing tripping for unstable transients.
 Prevention of tripping during unstable transients, and
forcing separation at another point.
Prevention of tripping during stable transients
 ‘mho’ distance relay characteristic may be too large
and have regions into which stable swings may enter
 In order to minimize the possibility of tripping during
stable swings:
 use of ohm units (blinders)
 composite relays
 shaped relay (lens, peanut, etc.)
1539pkTS - 57
Tripping can occur
only for impedance
between O1 and O2,
and within M
Fig. 13.43 Reduction of mho relay angular range
Fig. 13.44 Shaped Relay
1539pkTS - 58
Out-of-Step Blocking and Tripping Relays
 In some cases, it may be desirable to prevent tripping of
lines at the natural separation point, and choose the
separation point so that:
a) load and generation are better balanced on both
sides, or
b) a critical load is protected, or
c) the separation is at a corporate boundary.
 In certain instances, it may be desirable to trip faster in order
to prevent voltage declining too far.
Principle of out-of-step relaying:
 Movement of the apparent impedance under out-of-step
conditions is slow compared to its movement when a line
fault occurs
 transient swing condition can be detected using two
relays having vertical or circular characteristics on an
R-X plane
 if time required to cross the two characteristics
(OOS2, OOS1) exceeds a specified value, the out-of-
step function is initiated
1539pkTS - 59
Fig. 13.45 Out-of-step relaying schemes
1539pkTS - 60
 In an out-of-step tripping scheme, local breakers
would be tripped. such a scheme could be used to
 speed up tripping to voltage decline
 ensure tripping of a selected line, instead of other
more critical circuits
 In an out-of-step blocking scheme,
 relays are prevented from initiating tripping of the
line monitored, and transfer trip signals are sent to
open circuits of a remote location
 objective is to cause system separation at a more
preferable location
1539pkTS - 61
Generator Out-of-Step Protection
 For situations where the electrical centre is within the
generator or step-up transformer, a special relay must be
provided at the generator
 occurs when a generator pulls out of synchronism in a
system with strong transmission
 low excitation level on the generator (EA<EB) also tends
to contribute to such a condition
Effect of generators operating in out-of-step condition:
 Causes large cyclic variations in currents and voltages of the
affected machine
 the frequency being a function of the rate of slip of its
poles
 The high amplitude currents and off-nominal frequency
operation could result in winding stresses, and pulsating
torques which can excite potentially damaging mechanical
vibrations
 There is also risk of losing the auxiliaries of the affected unit
as well as the auxiliaries of nearby stable units
1539pkTS - 62
Relays for Out-of-Step Tripping of
Generators
 Similar to those used to detect out-of-step conditions on
the transmission system
 No industry standards or commonly used practices
a) Mho element scheme:
(a) System schematic (b) System equivalent circuit
(c) Relay characteristic and swing locus as seen at the HV bus
1539pkTS - 63
 Mho relay monitors the apparent impedance at the HT
terminal (H) of the unit transformer, and is set to reach
into the local generator
 Immediate trip when the apparent impedance enters
the offset mho characteristic
 objective is to allow tripping only for unstable
swings
 typically, the angle c at the point where the swing
impedance enters the relay characteristic is set to
about 120
 If circle is too large, the protection may trip the
generator for stable swings
 If circle is too small (c large), the scheme may not trip
the generator for unstable swings
 also, if c is too large the tripping can occur when
the angular separation approaches 180; this should
be avoided since it subjects the circuit breaker to
the maximum recovery voltage during interruption
1539pkTS - 64
b) Blinder scheme:
 Consists of two blinders, and a supervisory relay with
an offset mho characteristic
 Offers more selectivity than the simple mho element
scheme
 It is easy to coordinate with the transmission line
protection; this permits the reach to extend into the
system beyond the HT bus (H) of the step-up
transformer
Fig. 13.47 Generator out-of-step protection using a blinder
scheme
1539pkTS - 65
7. Case Study - Transient Stability
 The object
 demonstrate transient instability and actions of
protective relaying
 show methods of maintaining stability
 The system
 2279 buses, 467 generators, and 6581 branches
 the focus is on a plant with 8 nuclear units, with a
total capacity of 7000 MW
 all generators and associated controls are modelled
in detail
 loads are modelled using voltage-dependent static
load model (P=50% l + 50% Z, Q=100% Z)
1539pkTS - 66
Fig. 13.52 Diagram of system in the vicinity of a 7000 MW
nuclear power plant
1539pkTS - 67
The Contingency:
 Double line-to-ground (LLG) fault occurs on the 500 kV
double circuit line at Junction X
Time (ms) Event
0 No disturbance
100 Apply LLG fault at Junction X on circuits 1 and 2
164 Local end clearing:
Open breakers at bus 1 for circuit 1
Open breakers at bus 2 for circuit 2
This occurs 64 ms after the fault is applied, and this time is computed as
the sum of fault detection time (25 ms), auxiliary relay time (6 ms), and
the breaker clearing time (33 ms = 2 cycle). At this time, the fault remains
connected on the ends of circuits 1 and 2 at Junction X
187 Remote end clearing:
Open breakers at bus 4 for circuit 2
Open breakers at bus 3 for circuit 1
Clear fault (the line is isolated)
This occurs 87 ms after the fault is applied, and the time is calculated as
the sum of fault detection time (25 ms), auxiliary relay time (12 ms),
communication time (17 ms; microwave), and breaker clearing time (33
ms = 2 cycle)
5000 Terminate simulation
1539pkTS - 68
Simulation:
 A 5 second simulation was performed
 G3 is seen to lose synchronism and becomes
monotonically unstable
 similar behaviour for the other 7 units of the nuclear
plant
 As G1 to G8 become unstable, the rest of the system
becomes generation deficient
 absolute angles of all machines in the system drift
slightly
Fig. 13.53 Rotor angle time response
1539pkTS - 69
Analysis:
How does the system come apart as a result of instability?
 Out-of-step protection does not operate on G3
Fig. 13.54 Unit G3 out-of-step protection
1539pkTS - 70
Fig. 13.55 Line protection (circuit 3) at bus 1
Fig. 13.56 Line protection (circuit 3) at bus 7
1539pkTS - 71
Line Protection:
 Mho distance relays have zone 1 coverage of about 75% of
line length, and zone 2 over-reach of about 125% of line
length
 Apparent impedance enters the zone 2 relays at bus 1 and
enters zone 1 and zone 2 relays at bus 7
 zone 1 relay at bus 7 would trip circuit 3 at bus 7 and
send a transfer trip signal to breakers at bus 1 which
would then trip circuit 3 at bus 1
 true for the companion 500 kV circuit (#4) which would
be tripped in an identical manner
 Following the loss of the 500 kV circuits (at approximately 0.8
seconds), the remaining 230 kV circuits would become
extremely over-loaded and would be lost through protection
actions, thereby completely isolating the unstable plant from
the system
 Impedance plot shows the impedance swing crosses the
circuit at a point about 84% of the line length from bus 1
 represents the electrical centre following the
disturbance, and is theoretically where separation
occurs
1539pkTS - 72
Bus Voltages:
Fig. 13.57 Voltages at buses 1, 7 and the electrical
centre
1539pkTS - 73
Methods of Maintaining Stability:
 Reduction of the pre-contingency output of the plant
 costly to bottle energy in the plant
 Tripping of 2 generating units (generation rejection)
following the disturbance
Fig. 13.58 Unit G3 rotor angle response with and
without generation rejection
1539pkTS - 74
8. Transient Stability Enhancement
Objectives:
 Reduce the disturbing influence by minimizing the
fault severity and duration
 Increase the restoring synchronizing forces
 Reduce accelerating torque through control of prime-
mover mechanical power
 Reduce accelerating torque by applying artificial load
1539pkTS - 75
High-Speed Fault Clearing
 Amount of kinetic energy gained by the generators
during a fault is directly proportional to the fault
duration
 quicker the fault is cleared, the less disturbance it
causes
 Two-cycle breakers, together with high speed relays and
communication, are now widely used in locations where
rapid fault clearing is importance
 In special circumstances, even faster clearing may be
desirable
 development and application of a 1 cycle circuit
breaker by Bonneville Power Administration (BPA)
 combined with a rapid response overcurrent type
sensor, which anticipates fault magnitude, nearly
one-cycle total fault duration is attained
 ultra high speed relaying system for EHV lines based
on traveling wave detection
 not in widespread use
1539pkTS - 76
Reduction of Transmission System
Reactance
 Series inductive reactances of transmission networks
are primary determinants of stability limits
 reduction of reactances of various elements of the
transmission network improves transient stability
by increasing post-fault synchronizing power
transfers
 Most direct way of achieving this is by reducing the
reactances of transmission circuits
 voltage rating, line and conductor configurations,
and number of parallel circuits determine the
reactances of transmission lines
 Additional methods of reducing the network
reactances:
 use of transformers with lower leakage reactances
 series capacitor compensation of transmission
lines
1539pkTS - 77
 Typically, the per unit transformer leakage reactance
ranges between 0.1 and 0.15
 for newer transformers, the minimum acceptable
leakage reactance that can be achieved within the
normal transformer design practices has to be
established in consultation with the manufacturer
 May be a significant economic advantage in opting for a
transformer with the lowest possible reactance
 Series capacitors directly offset the line series reactance
 the maximum power transfer capability of a
transmission line may be significantly increased by
the use of series capacitor banks
 directly translates into enhancement of transient
stability, depending on the facilities provided for
bypassing the capacitor during faults and for
reinsertion after fault clearing
 speed of reinsertion is an important factor in
maintaining transient stability; using nonlinear
resistors of zinc oxide, the reinsertion is practically
instantaneous
1539pkTS - 78
 One problem with series capacitor compensation is the
possibility of subsynchronous resonance with the
nearby turbo alternators
 must be analyzed carefully and appropriate
preventive measures taken
 Series capacitors have been used to compensate very
long overhead lines
 recently, there has been an increasing recognition
of the advantages of compensating shorter, but
heavily loaded, lines using series capacitors
 For transient stability applications, the use of switched
series capacitors offers some advantages
 can be switched in upon detection of a fault or
power swing, and then removed about half second
later
 can be located in a substation where it can serve
several lines
 protective relaying is made more complex when
series compensation is used, and more so if the
series capacitors are switched
1539pkTS - 79
Regulated Shunt Compensation
 Can improve system stability by increasing the flow
of synchronizing power among interconnected
generators (voltage profile control)
 Static VAR compensators can be used for this
purpose
Fig. 11.60 Performance of a 600 km line with an SVS
regulating midpoint voltage
1539pkTS - 80
Regulated Shunt Compensation (cont'd)
Fig. 11.62 Power-angle relationships with regulated
compensation at discrete intervals dividing line
into n independent sections
n θ/n (degrees)
1 44.70 1.00
2 22.35 1.85
3 14.90 2.74
4 11.17 3.63
6 7.45 5.42
8 5.59 7.22
10 4.47 9.03
maxmax PP
1539pkTS - 81
Dynamic Braking
 Uses the concept of applying an artificial electrical
load during a transient disturbance to increase the
electrical power output of generators and thereby
reduce rotor acceleration
 One form of dynamic braking involves switching in
shunt resistors for about 0.5 seconds following a
fault to reduce accelerating power of nearby
generators and remove the kinetic energy gained
during the fault
 BPA has used such a scheme for enhancing
transient stability for faults in the US Pacific
Northwest
 brake consists of a 1400 MW, 240 kV resistor made
up of 45,000 ft. of 1/2" stainless steel wire strung
on 3 towers
1539pkTS - 82
 To date, braking resistors have been applied only to
hydraulic generating stations remote from load centres
 hydraulic units, in comparison to thermal units, are
quite rugged; they can, therefore, withstand the
sudden shock of switching in resistors without any
adverse effect on the units
 If braking resistors are applied to thermal units, the
effect on shaft fatigue life must be carefully examined
 If the switching duty is found unacceptable, the
resistors may have to be switched in three or four steps
spread over one full cycle of the lowest torsional mode
 Braking resistors used to date are all shunt devices
 series resistors may be used to provide the braking
effect
 the energy dissipated is proportional to the generator
current rather than voltage
 way of inserting the resistors in series is to install a
star-connected three-phase resistor arrangement
with a bypass switch in the neutral of the generator-
step-up transformer to reduce resistor insulation and
switch requirements
 resistor is inserted during a transient disturbance by
opening the bypass switch
1539pkTS - 83
 Another form of braking resistor application, which
enhances system stability for only unbalanced
ground faults, consists of a resistor connected
permanently between ground and the neutral of the Y
connected high voltage winding of the generator
step-up transformer
 under balanced conditions no current flows
through the neutral resistor
 when line-to-ground or double line-to-ground
faults occur, current flows through the neutral
connection and the resistive losses act as a
dynamic brake
 With switched form of braking resistors, the
switching times should be based on detailed
simulations
 if the resistors remain connected too long, there is
a possibility of instability on the "backswing"
1539pkTS - 84
Reactor Switching
 Shunt reactors near generators provide a simple and
convenient means of improving transient stability
 Reactor normally remains connected to the network
 Resulting reactive load increases the generator
internal voltage and reduces internal rotor angle
 Following a fault, the reactor is switched out which
further improves stability
1539pkTS - 85
Single-Pole Switching
 Uses separate operating mechanisms on each phase; for
single line-to-ground faults, the relaying is designed to
trip only the faulted phase, followed by fast reclosure
within 0.5 to 1.5 seconds; for multi-phase faults, all three
phases are tripped
 When one phase is open, power is transferred over the
remaining two phases
 As most faults on transmission lines are of the single
line-to-ground type, opening and reclosing of only the
faulted phase results in an improvement in transient
stability over three-phase tripping and reclosing
 Particularly attractive for situations where a single major
line connects two systems or where a single major line
connects a generating station to the rest of the system
 Also used on systems with multiple lines to improve
system security against multiple contingency
disturbances
 Three potential problems:
 secondary arc extinction
 fatigue duty on turbine-generator shafts and turbine
blades
 thermal duty on nearby generators due to negative-
sequence currents
1539pkTS - 86
Steam Turbine Fast Valving
 Applicable to thermal units to assist in maintaining
power system transient stability
 Involves rapid closing and opening of steam valves
in a prescribed manner to reduce the generator
accelerating power, following the recognition of a
severe transmission system fault
 Use recognized in the early 1930s, but it has not been
very widely applied for several reasons
 concerns for any possible adverse effects on the
turbine and energy supply system
 Since the mid-1960s, utilities have realized that fast
valving could be an effective method of improving
system stability in some situations
 number of technical papers have been published
describing the basic concepts and effects of fast
valving
 several utilities have tested and implemented fast
valving on some of their units
1539pkTS - 87
Fast Valving Procedures
 The main inlet control valves (CV) and the reheat intercept
valves (IV) provide a convenient means of controlling the
turbine mechanical power
 Variety of possibilities exist for the implementation of fast
valving schemes
 Common scheme: only the intercept valves are rapidly
closed and then fully reopened after a short time delay
 since the intercept valves control nearly 70% of the
total unit power, this method results in a fairly
significant reduction in turbine power
 More pronounced temporary reduction in turbine power
can be achieved through actuation of both control and
intercept valves
 Procedure of rapid closing and subsequent full opening
of the valves is called momentary fast valving
 Due to the post-fault transmission system being much
weaker than the pre-fault one, it may be desirable to have
the prime-mover power, after being reduced rapidly, return
to a level lower than the initial power
 sustained fast valving
1539pkTS - 88
Generator Tripping
 Selective tripping of generating units for severe
transmission system contingencies has been used as a
method of improving system stability for many years
 Rejection of generation at an appropriate location in the
system reduces power to be transferred over the critical
transmission interfaces
 Units can be tripped rapidly so this is a very effective means
of improving transient stability
 Historically, the application confined to hydro plants; now
used on fossil and nuclear plants
 Many utilities design thermal units so that, after tripping,
they continue to run, supplying unit auxiliaries; permits the
units to re resynchronized to the system and restored to full
load in about 15 to 30 minutes
 Major turbine-generator concerns:
 the overspeed resulting from tripping the generator
 thermal stresses due to the rapid load changes
 high levels of shaft torques due to successive
disturbances
1539pkTS - 89
Controlled System Separation and Load
Shedding
 May be used to prevent a major disturbance in one part of
an interconnected system from propagating into the rest of
the system and causing a severe system breakup
 Severe disturbance usually characterized by sudden
changes in tie line power
 if detected in time and the information is used to
initiate corrective actions, severe system upsets can
be averted
 Impending instability detected by monitoring one or more of
the following: sudden change in power flow through
specific transmission circuits, change of bus voltage angle,
rate of power change, and circuit breaker auxiliary contacts
 Upon detection of the impeding instability, controlled
system separation is initiated by opening the appropriate tie
lines before cascading outages can occur
 In some instances it may be necessary to shed selected
loads to balance generation and load in the separated
systems
1539pkTS - 90
High-Speed Excitation Systems
 Significant improvements in transient stability can be
achieved through rapid temporary increase of generator
excitation
 Increase of generator field voltage during a transient
disturbance has the effect of increasing the internal voltage
of the machine, which in turn increases synchronizing power
 High initial response excitation systems with high ceiling
voltages are most effective in this regard
 ceiling voltages limited by generator rotor insulation
considerations
 for thermal units, limited to about 2.5 to 3.0 times rated-
load field voltage
 Fast excitation response to terminal voltage variations,
required for improvement of transient stability, often leads to
degrading the damping of local plant mode oscillations
 Supplementary excitation control, commonly referred to as
power system stabilizer (PSS) provides a convenient means
of damping system oscillations
 Use of high initial response excitation systems
supplemented with PSS is by far the most effective and
economical method of enhancing the overall system stability
1539pkTS - 91
Discontinuous Excitation Control
 Properly applied PSS provides damping to both local and inter-
area modes of oscillations
 Under large signal or transient conditions, the stabilizer
generally contributes positively to first swing stability
 In the presence of both local and inter-area swing modes,
however, the normal stabilizer response can allow the excitation
to be reduced after the peak of the first local-mode swing and
before the highest composite peak of the swing is reached
 Additional improvements in transient stability can be realized by
keeping the excitation at ceiling, within terminal voltage
constraints, until the highest point of the swing is reached
 Discontinuous excitation control scheme referred to as
Transient Stability Excitation Control (TSEC) has been
developed by Ontario Hydro to achieve the above
 improves transient stability by controlling the generator
excitation so that the terminal voltage is maintained near
the maximum permissible value of about 1.12 to 1.15 pu
over the entire positive swing of the rotor angle
1539pkTS - 92
 uses a signal proportional to change in angle of
the generator rotor, in addition to the terminal
voltage and rotor speed signals
 angle signal is used only during the transient
period of about 2 seconds following a severe
disturbance, since it results in oscillatory
instability if used continuously
 angle signal prevents premature reversal of field
voltage and hence maintains the terminal voltage
at a high level during the positive swing of the
rotor angle
 excessive terminal voltage is prevented by the
terminal voltage limiter
 When TSEC used on several generating stations in an
area;
 system voltage level in the entire area is raised
 increases power consumed by loads in the entire
area, contributing to further improvement in TS
1539pkTS - 93
Fig. 17.7 Block diagram of TSEC scheme
Fig. 17.8 Effect of TSEC on transient stability
1539pkTS - 94
Integrating HVDC Parallel Links
 HVDC links are highly controllable. Possible to take
advantage of this unique characteristic of the HVDC link
to augment the transient stability of the ac system
 Parallel application with ac transmission can be
effectively used to bypass ac network congestion
 Often, provides the best option for using limited right of
way
 Provides a firewall against cascading outages during
major system disturbances
For example, during the August 2003 Blackout of
northeast US and eastern Canada,
 Quebec was unaffected
 AC links from New York to New England tripped;
however, HVDC links from Quebec continued to
supply power to New England
 With the present day technology based on self –
commutated voltage sourced converters, transient
stability augmentation can also be achieved by
controlling the HVDC converters so as to provide
reactive power and voltage support.
1539pkTS - 95
Examples of HVDC Parallel Links
 Pacific HVDC Inter-tie in the US west
 1400 km long 440 kV bipolar HVDC overhead line from
Columbia River in Oregon to Los Angeles, California
 Built in the early 1970s, with a capacity of 1,440 MW;
upgraded over the years to 3,100 MW
 Has operated successfully for over 30 years in parallel
with 500 kV AC transmission
 Itaipu HVDC Link in Brazil
 800 km long 600 kV bipolar HVDC overhead line
from Foz du Iguacu hydro power plant to the load
centre in the city of Sao Paulo
 3,150 MW HVDC link built in the mid 1980s
 Has operated successfully for over 20 years in
parallel with 765 kV AC transmission network
 Quebec- New England multi-terminal HVDC system
 1500 MW, 1500 km 450 kV bipolar HVDC link built
in the early 1990s
 Brings power from James Bay Hydro plants to
Boston, Massachusetts area
 Comprises five terminals; normally operates as a
three-terminal link
1539pkTS - 96
HVDC Technologies
 Electronic converters for HVDC are classified into
two main categories:
 Line-Commutated Converters ( LCC )
 Voltage-Sourced Converters ( VSC )
 LCC converters rely on the natural voltage of the AC
system for commutation
 Converters use electronic switches that can only
be turned on (not off) by control action
 Early LCC systems used mercury-arc valves;
since the 1970s thyristors have been used
 Consume reactive power from the AC system and
result in lower-order harmonics, which in turn call
for counter measures
 VSC converters use semiconductor elements with
current interrupting capabilities to force commutation
at any desired point on the AC cycle
 Thyristors cannot be used; instead transistors,
such as Insulated Gate Bipolar Transistor
(IGBT), are used
 First application in 1977; continued
advancements and applications since
1539pkTS - 97
VSC-Based HVDC Technology
 Self-commutated voltage-sourced converter (VSC)
HVDC technology has the following technical
benefits:
 Does not rely on AC system for commutation
 Active and reactive power can be controlled
independently
 Excellent dynamic response
 Can be connected to very weak ac network
 Harmonic filter requirements are significantly less
 Good “black-start” capability
 Lower overall “footprint”
 VSC-based HVDC converters are relatively more
expensive and have higher losses
 Technical advancements made in recent years
have effectively addressed these issues
 Depending on the nature of the application, these
may not be significant issues
1539pkTS - 98
VSC-Based HVDC Technology Evolution
 The first generation VSC technology was based on
either two-level or three-level converters utilizing
pulse width modulation (PWM)
 Main associated drawbacks were: high levels
of power loss and lack of modularity
 These are addressed in two recent topologies:
Siemens MMC (Modular Multi-Level Converter) and
ABB Cascaded Converter configurations
 Use half-bridge or full bridge modules
depending on the application
 Provide modularity: damaged parts would be
small and readily replaceable
 Use low-frequency switching in each module,
thus reducing losses
Increasingly being used for interconnecting weak
AC systems; for connecting large-scale wind power
to the grid; and for long distance underground and
underwater links
1539pk
November 9, 1965 Blackout of
Northeast US and Ontario
1539pkTS - 100
November 9, 1965 - Blackout of
Northeast US and Canada
 Clear day with mild weather;
Load levels in the regional normal
 Problem began at 5:16 p.m.
 Within a few minutes, there was a complete shut
down of electric service to
 virtually all of the states of New York,
Connecticut, Rhode Island, Massachusetts,
Vermont
 parts of New Hampshire, New Jersey and
Pennsylvania
 most of Ontario, Canada
 Nearly 30 million people were without power for
about 13 hours
 President Johnson ordered Chairman of Federal
Power Commission to conduct an immediate
investigation
 Developments that followed had a major impact on
the industry!
1539pkTS - 101
North American Eastern Interconnected
System
1539pkTS - 102
Events that Caused the 1965 Blackout
 The initial event was the operation of a backup
relay (Zone 3) at Beck GS in Ontario near Niagara
Falls
 opened circuit Q29BD, one of five 230 kV circuits
connecting Beck GS to load centers in Toronto
and Hamilton
 Prior to opening of Q29BD, the five circuits were
carrying
 1200 MW of Beck generation, and
 500 MW import from Western NY State on
Niagara ties
 Net import from NY 300 MW
 Loading on Q29BD was 361 MW at 248 kV;
 The relay setting corresponded to 375 MW
1539pkTS - 103
Events that Caused the 1965 Blackout
(cont'd)
Beck
1539pkTS - 104
Events that Caused the 1965 Blackout
(cont'd)
 Opening of Q29BD resulted in sequential tripping of
the remaining four parallel circuits
 Power flow reversed to New York
 total change of 1700 MW
 Power surge back to Ontario via St. Lawrence ties
 ties tripped by protective relaying
 Generators in Western New York and Beck GS lost
synchronism, followed by cascading outages
 After about 7 seconds from the initial disturbance
 system split into several separate islands
 eventually most generation and load lost;
inability of islanded systems to stabilize
1539pkTS - 105
Special Protections Implemented after the
1965 Blackout
 P Relays on Niagara Ties
 trip Niagara ties to NY;
cross-trip St. Lawrence ties to NY
 in place until mid 1980s
 Under-frequency load shedding (UFLS) throughout
the interconnected system
 beginning of the use of UFLS by industry
1539pkTS - 106
Formation of Reliability Councils
 Northeast Power Coordinating Council (NPCC)
formed in January 1966
 to improve coordination in planning and operation
among utilities in the region that was blacked out
 first Regional Reliability Council (RRC) in North
America
 Other eight RRCs formed in the following months
 National/North American Electric Reliability Council
(NERC) established in 1968
1539pkTS - 107
Reliability Enhancement after the 1965
Blackout
 All utilities in North America began to review
reliability related policies, practices and procedures
 Coordination of activities and information exchange
between neighbouring utilities became a priority
 Each Regional Council established detailed
Reliability criteria and guidelines for member
systems
 Power system stability studies became an important
part of operating studies
 led to the development of improved Transient
Stability programs
 exchange of data between utilities
 Many of these developments has had an influence on
utility practices worldwide
1539pk
March 11, 1999
Brazil Blackout
1539pkTS - 109
March 11, 1999 Brazil Blackout
 Time: 22:16:00h, System Load: 34,200 MW
 Description of the event:
 L-G fault at Bauru substation as a result of lightning
causing a bus insulator flashover
 The bus arrangement at Bauru such that the fault is
cleared by opening five 440 kV lines
 The power system survived the initial event, but
resulted in instability when a short heavily loaded
440 kV line was tripped by zone 3 relay
 Cascading outages of several power plants in Sao
Paulo area, followed by loss of HVDC and 750 kV AC
links from Itaipu
 Complete system break up: 24,700 MW load loss;
several islands remained in operation with a total
load of about 10,000 MW
 Restoration of different regions varied from 30
minutes to 4 hours
 Complete blackout of Sao Paulo and Rio de Janeiro
areas for about 4 hours
1539pkTS - 110
March 11, 1999 Brazil Blackout (cont'd)
 Measures to improve system security:
 Joint Working Group comprising ELECTROBRAS,
CEPEL and ONS staff formed
 Organized activities into 8 Task Forces
 Four international experts as advisors
 Remedial Actions:
 Power system divided into 5 security zones:
regions with major generation and transmission
system protected or emergency controls
 All major EHV substations classified into high,
medium, low risk categories based on
 impact level to system security of bus faults
 intrinsic reliability level of substation (layout,
equipment changes) to reduce risk level
 Improved maintenance of substation equipment
and protection/control equipment
 Better training of operators
 Improved restoration plans

More Related Content

What's hot

Automatic Generation Control
Automatic Generation ControlAutomatic Generation Control
Automatic Generation ControlMINAL RADE
 
Small signal stability analysis
Small signal stability analysisSmall signal stability analysis
Small signal stability analysisbhupendra kumar
 
ETAP - Short circuit analysis iec standard
ETAP - Short circuit analysis iec standardETAP - Short circuit analysis iec standard
ETAP - Short circuit analysis iec standardHimmelstern
 
ETAP - Transient stability 2
ETAP - Transient stability 2ETAP - Transient stability 2
ETAP - Transient stability 2Himmelstern
 
ETAP - unbalanced load flow
ETAP - unbalanced load flowETAP - unbalanced load flow
ETAP - unbalanced load flowHimmelstern
 
Induction motor modelling and applications
Induction motor modelling and applicationsInduction motor modelling and applications
Induction motor modelling and applicationsUmesh Dadde
 
UNSYMMETRICAL FAULTS IN POWER SYSTEM
UNSYMMETRICAL FAULTS IN POWER SYSTEMUNSYMMETRICAL FAULTS IN POWER SYSTEM
UNSYMMETRICAL FAULTS IN POWER SYSTEMerramansaini1947
 
Comparision of svc and statcom
Comparision of svc and statcomComparision of svc and statcom
Comparision of svc and statcomjawaharramaya
 
GENERATING OF HIGH ALTERNATING VOLTAGE
GENERATING OF HIGH ALTERNATING VOLTAGEGENERATING OF HIGH ALTERNATING VOLTAGE
GENERATING OF HIGH ALTERNATING VOLTAGEJamil Abdullah
 
LOAD FREQUENCY AND VOLTAGE GENERATION CONTROL
LOAD FREQUENCY AND VOLTAGE GENERATION CONTROLLOAD FREQUENCY AND VOLTAGE GENERATION CONTROL
LOAD FREQUENCY AND VOLTAGE GENERATION CONTROLPreet_patel
 
ETAP - Load flow and panel rev2014-1
ETAP - Load flow and panel   rev2014-1ETAP - Load flow and panel   rev2014-1
ETAP - Load flow and panel rev2014-1Himmelstern
 

What's hot (20)

Automatic Generation Control
Automatic Generation ControlAutomatic Generation Control
Automatic Generation Control
 
Out of step
Out of stepOut of step
Out of step
 
Small signal stability analysis
Small signal stability analysisSmall signal stability analysis
Small signal stability analysis
 
SYNCHRONOUS MACHINES
SYNCHRONOUS MACHINESSYNCHRONOUS MACHINES
SYNCHRONOUS MACHINES
 
ETAP - Short circuit analysis iec standard
ETAP - Short circuit analysis iec standardETAP - Short circuit analysis iec standard
ETAP - Short circuit analysis iec standard
 
KAUSHAL BOGHNAI
KAUSHAL BOGHNAIKAUSHAL BOGHNAI
KAUSHAL BOGHNAI
 
Heffron phillips model
Heffron phillips modelHeffron phillips model
Heffron phillips model
 
ETAP - Transient stability 2
ETAP - Transient stability 2ETAP - Transient stability 2
ETAP - Transient stability 2
 
Unit commitment
Unit commitmentUnit commitment
Unit commitment
 
Two area system
Two area systemTwo area system
Two area system
 
ETAP - unbalanced load flow
ETAP - unbalanced load flowETAP - unbalanced load flow
ETAP - unbalanced load flow
 
Induction motor modelling and applications
Induction motor modelling and applicationsInduction motor modelling and applications
Induction motor modelling and applications
 
Vivek harmonics
Vivek harmonicsVivek harmonics
Vivek harmonics
 
UNSYMMETRICAL FAULTS IN POWER SYSTEM
UNSYMMETRICAL FAULTS IN POWER SYSTEMUNSYMMETRICAL FAULTS IN POWER SYSTEM
UNSYMMETRICAL FAULTS IN POWER SYSTEM
 
Comparision of svc and statcom
Comparision of svc and statcomComparision of svc and statcom
Comparision of svc and statcom
 
Facts devices
Facts devicesFacts devices
Facts devices
 
GENERATING OF HIGH ALTERNATING VOLTAGE
GENERATING OF HIGH ALTERNATING VOLTAGEGENERATING OF HIGH ALTERNATING VOLTAGE
GENERATING OF HIGH ALTERNATING VOLTAGE
 
Power System Stablity
Power System StablityPower System Stablity
Power System Stablity
 
LOAD FREQUENCY AND VOLTAGE GENERATION CONTROL
LOAD FREQUENCY AND VOLTAGE GENERATION CONTROLLOAD FREQUENCY AND VOLTAGE GENERATION CONTROL
LOAD FREQUENCY AND VOLTAGE GENERATION CONTROL
 
ETAP - Load flow and panel rev2014-1
ETAP - Load flow and panel   rev2014-1ETAP - Load flow and panel   rev2014-1
ETAP - Load flow and panel rev2014-1
 

Similar to TRANSIENT ANGLE STABILITY

POWER SYSTEM SIMULATION - 2 LAB MANUAL (ELECTRICAL ENGINEERING - POWER SYSTEMS)
POWER SYSTEM SIMULATION - 2 LAB MANUAL (ELECTRICAL ENGINEERING - POWER SYSTEMS) POWER SYSTEM SIMULATION - 2 LAB MANUAL (ELECTRICAL ENGINEERING - POWER SYSTEMS)
POWER SYSTEM SIMULATION - 2 LAB MANUAL (ELECTRICAL ENGINEERING - POWER SYSTEMS) Mathankumar S
 
ECE4762008_Lect23.ppt
ECE4762008_Lect23.pptECE4762008_Lect23.ppt
ECE4762008_Lect23.pptVIGNESHRAJR3
 
EEE 411 power system stability analysis .pptx
EEE 411 power system stability analysis .pptxEEE 411 power system stability analysis .pptx
EEE 411 power system stability analysis .pptxShoilieChakma
 
Power System Analysis Unit - V
Power System Analysis Unit - VPower System Analysis Unit - V
Power System Analysis Unit - Varunatshare
 
Transient Stability Analysis of IEEE 9 Bus System in Power World Simulator
Transient Stability Analysis of IEEE 9 Bus System in Power World SimulatorTransient Stability Analysis of IEEE 9 Bus System in Power World Simulator
Transient Stability Analysis of IEEE 9 Bus System in Power World SimulatorIJERA Editor
 
Transient Stability Analysis of IEEE 9 Bus System in Power World Simulator
Transient Stability Analysis of IEEE 9 Bus System in Power World SimulatorTransient Stability Analysis of IEEE 9 Bus System in Power World Simulator
Transient Stability Analysis of IEEE 9 Bus System in Power World SimulatorIJERA Editor
 
DigSILENT PF - 06 (es) short circuit theory
DigSILENT PF - 06 (es) short circuit theoryDigSILENT PF - 06 (es) short circuit theory
DigSILENT PF - 06 (es) short circuit theoryHimmelstern
 
DigSILENT PF - 05 short circuit theory
DigSILENT PF - 05 short circuit theoryDigSILENT PF - 05 short circuit theory
DigSILENT PF - 05 short circuit theoryHimmelstern
 
Effects of Different Parameters on Power System Transient Stability Studies
Effects of Different Parameters on Power System Transient Stability StudiesEffects of Different Parameters on Power System Transient Stability Studies
Effects of Different Parameters on Power System Transient Stability StudiesPower System Operation
 
Short Circuit Calculation Symmetrical & Asymmetrical Fault Currents ?
Short Circuit Calculation Symmetrical & Asymmetrical Fault Currents ?Short Circuit Calculation Symmetrical & Asymmetrical Fault Currents ?
Short Circuit Calculation Symmetrical & Asymmetrical Fault Currents ?Power System Operation
 
Iaetsd power-frequency transient studies
Iaetsd power-frequency transient studiesIaetsd power-frequency transient studies
Iaetsd power-frequency transient studiesIaetsd Iaetsd
 
Ee6501 psa-eee-vst-au-units-v (1)
Ee6501 psa-eee-vst-au-units-v (1)Ee6501 psa-eee-vst-au-units-v (1)
Ee6501 psa-eee-vst-au-units-v (1)Vara Prasad
 
Power system Analysis By Sharif Kakar
Power system Analysis   By Sharif KakarPower system Analysis   By Sharif Kakar
Power system Analysis By Sharif KakarSharif Ullah
 
TCSC
TCSCTCSC
TCSCAli
 

Similar to TRANSIENT ANGLE STABILITY (20)

POWER SYSTEM SIMULATION - 2 LAB MANUAL (ELECTRICAL ENGINEERING - POWER SYSTEMS)
POWER SYSTEM SIMULATION - 2 LAB MANUAL (ELECTRICAL ENGINEERING - POWER SYSTEMS) POWER SYSTEM SIMULATION - 2 LAB MANUAL (ELECTRICAL ENGINEERING - POWER SYSTEMS)
POWER SYSTEM SIMULATION - 2 LAB MANUAL (ELECTRICAL ENGINEERING - POWER SYSTEMS)
 
ECE4762008_Lect23.ppt
ECE4762008_Lect23.pptECE4762008_Lect23.ppt
ECE4762008_Lect23.ppt
 
EEE 411 power system stability analysis .pptx
EEE 411 power system stability analysis .pptxEEE 411 power system stability analysis .pptx
EEE 411 power system stability analysis .pptx
 
Power System Analysis Unit - V
Power System Analysis Unit - VPower System Analysis Unit - V
Power System Analysis Unit - V
 
Transient Stability Analysis of IEEE 9 Bus System in Power World Simulator
Transient Stability Analysis of IEEE 9 Bus System in Power World SimulatorTransient Stability Analysis of IEEE 9 Bus System in Power World Simulator
Transient Stability Analysis of IEEE 9 Bus System in Power World Simulator
 
Transient Stability Analysis of IEEE 9 Bus System in Power World Simulator
Transient Stability Analysis of IEEE 9 Bus System in Power World SimulatorTransient Stability Analysis of IEEE 9 Bus System in Power World Simulator
Transient Stability Analysis of IEEE 9 Bus System in Power World Simulator
 
Power System Stability Introduction
Power System Stability IntroductionPower System Stability Introduction
Power System Stability Introduction
 
Control of Direct Current Machine by the Change of Resistance in Armature Cir...
Control of Direct Current Machine by the Change of Resistance in Armature Cir...Control of Direct Current Machine by the Change of Resistance in Armature Cir...
Control of Direct Current Machine by the Change of Resistance in Armature Cir...
 
2Stability-2.pptx
2Stability-2.pptx2Stability-2.pptx
2Stability-2.pptx
 
DigSILENT PF - 06 (es) short circuit theory
DigSILENT PF - 06 (es) short circuit theoryDigSILENT PF - 06 (es) short circuit theory
DigSILENT PF - 06 (es) short circuit theory
 
DigSILENT PF - 05 short circuit theory
DigSILENT PF - 05 short circuit theoryDigSILENT PF - 05 short circuit theory
DigSILENT PF - 05 short circuit theory
 
F05113439
F05113439F05113439
F05113439
 
Effects of Different Parameters on Power System Transient Stability Studies
Effects of Different Parameters on Power System Transient Stability StudiesEffects of Different Parameters on Power System Transient Stability Studies
Effects of Different Parameters on Power System Transient Stability Studies
 
Short Circuit Calculation Symmetrical & Asymmetrical Fault Currents ?
Short Circuit Calculation Symmetrical & Asymmetrical Fault Currents ?Short Circuit Calculation Symmetrical & Asymmetrical Fault Currents ?
Short Circuit Calculation Symmetrical & Asymmetrical Fault Currents ?
 
VS_SC notes.pdf
VS_SC notes.pdfVS_SC notes.pdf
VS_SC notes.pdf
 
Iaetsd power-frequency transient studies
Iaetsd power-frequency transient studiesIaetsd power-frequency transient studies
Iaetsd power-frequency transient studies
 
Ee6501 psa-eee-vst-au-units-v (1)
Ee6501 psa-eee-vst-au-units-v (1)Ee6501 psa-eee-vst-au-units-v (1)
Ee6501 psa-eee-vst-au-units-v (1)
 
Lecture1
Lecture1Lecture1
Lecture1
 
Power system Analysis By Sharif Kakar
Power system Analysis   By Sharif KakarPower system Analysis   By Sharif Kakar
Power system Analysis By Sharif Kakar
 
TCSC
TCSCTCSC
TCSC
 

More from Power System Operation

Thermography test of electrical panels
Thermography test of electrical panelsThermography test of electrical panels
Thermography test of electrical panelsPower System Operation
 
Big Data Analytics for Power Grid Operations
Big Data Analytics for Power Grid OperationsBig Data Analytics for Power Grid Operations
Big Data Analytics for Power Grid OperationsPower System Operation
 
SPS to RAS Special Protection Scheme Remedial Action Scheme
SPS to RAS Special Protection Scheme  Remedial Action SchemeSPS to RAS Special Protection Scheme  Remedial Action Scheme
SPS to RAS Special Protection Scheme Remedial Action SchemePower System Operation
 
SVC PLUS Frequency Stabilizer Frequency and voltage support for dynamic grid...
SVC PLUS Frequency Stabilizer Frequency and voltage support for  dynamic grid...SVC PLUS Frequency Stabilizer Frequency and voltage support for  dynamic grid...
SVC PLUS Frequency Stabilizer Frequency and voltage support for dynamic grid...Power System Operation
 
Principles & Testing Methods Of Earth Ground Resistance
Principles & Testing Methods Of Earth Ground ResistancePrinciples & Testing Methods Of Earth Ground Resistance
Principles & Testing Methods Of Earth Ground ResistancePower System Operation
 
Gas Insulated Switchgear? Gas-Insulated High-Voltage Switchgear (GIS)
Gas Insulated Switchgear?  Gas-Insulated High-Voltage Switchgear (GIS)Gas Insulated Switchgear?  Gas-Insulated High-Voltage Switchgear (GIS)
Gas Insulated Switchgear? Gas-Insulated High-Voltage Switchgear (GIS)Power System Operation
 
Electrical Transmission Tower Types - Design & Parts
Electrical Transmission Tower  Types - Design & PartsElectrical Transmission Tower  Types - Design & Parts
Electrical Transmission Tower Types - Design & PartsPower System Operation
 
The Need for Enhanced Power System Modelling Techniques & Simulation Tools
The Need for Enhanced  Power System  Modelling Techniques  &  Simulation Tools The Need for Enhanced  Power System  Modelling Techniques  &  Simulation Tools
The Need for Enhanced Power System Modelling Techniques & Simulation Tools Power System Operation
 
Power Quality Trends in the Transition to Carbon-Free Electrical Energy System
Power Quality  Trends in the Transition to  Carbon-Free Electrical Energy SystemPower Quality  Trends in the Transition to  Carbon-Free Electrical Energy System
Power Quality Trends in the Transition to Carbon-Free Electrical Energy SystemPower System Operation
 

More from Power System Operation (20)

ENERGY TRANSITION OUTLOOK 2021
ENERGY TRANSITION OUTLOOK  2021ENERGY TRANSITION OUTLOOK  2021
ENERGY TRANSITION OUTLOOK 2021
 
Thermography test of electrical panels
Thermography test of electrical panelsThermography test of electrical panels
Thermography test of electrical panels
 
What does peak shaving mean
What does peak shaving meanWhat does peak shaving mean
What does peak shaving mean
 
What's short circuit level
What's short circuit levelWhat's short circuit level
What's short circuit level
 
Power System Restoration Guide
Power System Restoration Guide  Power System Restoration Guide
Power System Restoration Guide
 
Big Data Analytics for Power Grid Operations
Big Data Analytics for Power Grid OperationsBig Data Analytics for Power Grid Operations
Big Data Analytics for Power Grid Operations
 
SPS to RAS Special Protection Scheme Remedial Action Scheme
SPS to RAS Special Protection Scheme  Remedial Action SchemeSPS to RAS Special Protection Scheme  Remedial Action Scheme
SPS to RAS Special Protection Scheme Remedial Action Scheme
 
Substation Neutral Earthing
Substation Neutral EarthingSubstation Neutral Earthing
Substation Neutral Earthing
 
SVC PLUS Frequency Stabilizer Frequency and voltage support for dynamic grid...
SVC PLUS Frequency Stabilizer Frequency and voltage support for  dynamic grid...SVC PLUS Frequency Stabilizer Frequency and voltage support for  dynamic grid...
SVC PLUS Frequency Stabilizer Frequency and voltage support for dynamic grid...
 
Principles & Testing Methods Of Earth Ground Resistance
Principles & Testing Methods Of Earth Ground ResistancePrinciples & Testing Methods Of Earth Ground Resistance
Principles & Testing Methods Of Earth Ground Resistance
 
Gas Insulated Switchgear? Gas-Insulated High-Voltage Switchgear (GIS)
Gas Insulated Switchgear?  Gas-Insulated High-Voltage Switchgear (GIS)Gas Insulated Switchgear?  Gas-Insulated High-Voltage Switchgear (GIS)
Gas Insulated Switchgear? Gas-Insulated High-Voltage Switchgear (GIS)
 
Electrical Transmission Tower Types - Design & Parts
Electrical Transmission Tower  Types - Design & PartsElectrical Transmission Tower  Types - Design & Parts
Electrical Transmission Tower Types - Design & Parts
 
What is load management
What is load managementWhat is load management
What is load management
 
What does merit order mean
What does merit order meanWhat does merit order mean
What does merit order mean
 
What are Balancing Services ?
What are  Balancing Services ?What are  Balancing Services ?
What are Balancing Services ?
 
The Need for Enhanced Power System Modelling Techniques & Simulation Tools
The Need for Enhanced  Power System  Modelling Techniques  &  Simulation Tools The Need for Enhanced  Power System  Modelling Techniques  &  Simulation Tools
The Need for Enhanced Power System Modelling Techniques & Simulation Tools
 
Power Quality Trends in the Transition to Carbon-Free Electrical Energy System
Power Quality  Trends in the Transition to  Carbon-Free Electrical Energy SystemPower Quality  Trends in the Transition to  Carbon-Free Electrical Energy System
Power Quality Trends in the Transition to Carbon-Free Electrical Energy System
 
Power Purchase Agreement PPA
Power Purchase Agreement PPA Power Purchase Agreement PPA
Power Purchase Agreement PPA
 
Harmonic study and analysis
Harmonic study and analysisHarmonic study and analysis
Harmonic study and analysis
 
What is leakage current testing
What is leakage current testingWhat is leakage current testing
What is leakage current testing
 

Recently uploaded

Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 

Recently uploaded (20)

Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 

TRANSIENT ANGLE STABILITY

  • 1. 1539pk TRANSIENT (ANGLE) STABILITY Copyright © P. Kundur This material should not be used without the author's consent
  • 2. 1539pkTS - 1 Transient Angle Stability  Description of Transient Stability  An elementary view of TS  Methods of TS analysis  Time-domain simulation  Structure of power system model  Representation faults  Performance of protective relaying  Concept of “electrical centre”  Case studies  Methods of TS enhancement  Major blackouts caused by Transient Instability  November 9, 1965 Northeast US, Ontario blackout  March 11, 1999 Brazil blackout Outline
  • 3. 1539pkTS - 2 What is Transient (Angle) Stability?  The ability of the power system to maintain synchronous operation when subjected to a severe transient disturbance  faults on transmission circuits, transformers, buses  loss of generation  loss of loads  Response involves large excursions of generator rotor angles: influenced by nonlinear power-angle relationship  Stability depends on both the initial operating state of the system and the severity of the disturbance  Post-disturbance steady-state operating conditions usually differ from pre-disturbance conditions
  • 4. 1539pkTS - 3  In large power systems, transient instability may not always occur as "first swing" instability  could be as a result of superposition of several swing modes causing large excursions of rotor angle beyond the first swing  Study period of interest in transient stability studies is usually limited to 3 to 5 seconds following the disturbance;  may extend up to about 10 seconds for very large systems with dominant inter-area swing modes  Power system designed and operated to be stable for specified set of contingencies referred to as "normal design contingencies"  selected on the basis that they have a reasonable probability of occurrence  In the future, probabilistic or risk-based approach may be used
  • 5. 1539pkTS - 4 1. An Elementary View of Transient Stability  Demonstrate the phenomenon using a very simple system and simple models  System shown in Fig. 13.1  All resistances are neglected  Generator is represented by the classical model Fig. 13.1 Single machine - infinite bus system
  • 6. 1539pkTS - 5  The generator's electrical power output is  With the stator resistance neglected, Pe represents the air-gap power as well as the terminal power Fig. 13.2 System representation with generator represented by classical model    sinsin max P X EE P T B e
  • 7. 1539pkTS - 6 Power-Angle Relationship  Both transmission circuits in-service: Curve 1  operate at point "a" (Pe = Pm)  One circuit out-of-service: Curve 2  lower Pmax  operate at point "b"  higher reactance  higher  to transmit same power Fig. 13.3 Power-angle relationship
  • 8. 1539pkTS - 7  The oscillation of  is superimposed on the synchronous speed a0  Speed deviation the generator speed is practically equal to a0, and the per unit (pu) air-gap torque may be considered to be equal to the pu air-gap power torque and power are used interchangeably when referring to the swing equation. Equation of Motion or Swing Equation where: Pm = mechanical power input (pu) Pmax = maximum electrical power output (pm) H = inertia constant (MW-sec/MVA) L = rotor angle (elec. radians) t = time (secs) Effects of Disturbance   0r dt d      sinPP dt dH2 maxm2 2 0 
  • 9. 1539pkTS - 8 Response to a Short Circuit Fault  Illustrate the equal area criterion using the following system:  Examine the impact on stability of different fault clearing times
  • 10. 1539pkTS - 9 Stable Case Response to a fault cleared in tcl seconds - stable case
  • 11. 1539pkTS - 10 Stable Case cont'd Pre-disturbance:  both circuits I/S : Pe = Pm, δ = δ0  operating point a Fault On:  operating point moves from a to b  inertia prevents δ from changing instantaneously  Pm > Pe  rotor accelerates to operating point c Post Fault:  faulted circuit is tripped, operating point shifts to d  Pe > Pm  rotor decelerates  rotor speed > 0  δ increases  operating point moves from d to e such that A1 = A2  at e, speed = 0, and δ = δ m  Pe > Pm  rotor decelerates; speed below a0  δ decreases and operating point retraces e to d  with no damping, rotor continues to oscillate
  • 12. 1539pkTS - 11 Unstable Case Response to a fault cleared in tc2 seconds - unstable case
  • 13. 1539pkTS - 12 Unstable Case cont'd  Area A2 above Pm is less than A1  When the operating point reaches e, the kinetic energy gained during the accelerating period has not yet been completely expended  the speed is still greater than 0 and  continues to increase  Beyond point e, Pe<Pm,  rotor begins to accelerate again  The rotor speed and angle continue to increase leading to loss of synchronism
  • 14. 1539pkTS - 13 Factors Influencing Transient Stability (a) How heavily the generator is initially loaded. (b) The generator output during the fault. This depends on the fault location and type. (c) The fault clearing time. (d) The post-fault transmission system reactance. (e) The generator reactance. A lower reactance increases peak power and reduces initial rotor angle. (f) The generator inertia. The higher the inertia, the slower the rate of change angle. This reduces the kinetic energy gained during fault, i.e. area A1 is reduced. (g) The generator internal voltage magnitude (El). This depends on the field excitation. (h) The infinite bus voltage magnitude EB.
  • 15. 1539pkTS - 14 Practical Method of TS Analysis  Practical power systems have complex network structures  Accurate analysis of transient stability requires detailed models for:  generating unit and controls  voltage dependent load characteristics  HVDC converters, FACTs devices, etc.  At present, the most practical available method of transient stability analysis is time domain simulation:  solution of nonlinear differential equations and algebraic equations  step-by-step numerical integration techniques  complimented by efficient techniques for solving non-linear highly sparse algebraic equations
  • 16. 1539pkTS - 15 2. Numerical Integration Methods Differential equations to be solved are nonlinear ordinary differential equations with known initial values: x is the state vector of n dependent variables, t is the independent variable (time) Objective: solve x as a function of t, with the initial values of x and t equal to x0 and t0, respectively. Methods: Euler's Method Modified Euler's Method Runge-Kutta (R-K) Methods Trapezoidal Rule  txf dt dx ,
  • 17. 1539pkTS - 16 Numerical stability  Depends on propagation of error  Numerically stable if early errors cause no significant errors later  Numerically unstable otherwise Important to consider numerical stability in the application of numerical integration methods
  • 18. 1539pkTS - 17 Stiffness of Differential Equations  Ratio of largest to smallest time constants or, more precisely, eigenvalues  Increases with modelling detail  Affects numerical stability  Solution using explicit integration methods may "blow up" with stiff systems unless very small time step is used.
  • 19. 1539pkTS - 18 Numerical Stability of Explicit Integration Methods Explicit Methods  Euler's, Predictor-Corrector, and R-K methods  Dependent variables x at any value of t is computed from a knowledge of the values of x from the previous time steps  xn+1 for (n+1)th step is calculated explicitly by evaluating f(x,t) with known x  Easy to implement for the solution of a complex set of system state equations Disadvantage  Not numerically A-stable  step size limited by small time constants or eigenvalues
  • 20. 1539pkTS - 19 Implicit Integration Methods  Consider the differential equation The solution for x at t=t1=t0+t may be expressed in the integral form as  Implicit methods use interpolation functions for the expression under the integral  Interpolation implies that the functions must pass through the yet unknown points at time t1  Trapezoidal Rule is simplest method    dxfxx t t ,1 001   00, ttatxxwithtxf dt dx 
  • 21. 1539pkTS - 20 Trapezoidal Rule  Simplest implicit method; uses linear interpolation  Integral approximated by trapezoids f(x,t) f(x0,t0) f(x1,t1) t0 t1 t t Fig. 13.7
  • 22. 1539pkTS - 21  Trapezoidal rule is given by A general formula giving the value of x at t=tn+1 is  Xn+1 appears on both sides of Equation  implies that the variable x is computed as a function of its value at the previous time step as well as the current value (which is unknown)  an implicit equation must be solved  Numerically A-stable : stiffness affects accuracy not stability  Trapezoidal rule is a second order method  Higher order methods difficult to program and less robust     110001 t,xft,xf 2 t xx       1n1nnnn1n t,xft,xf 2 t xx   
  • 23. 1539pkTS - 22 3. Simulation of Power System Dynamic Response Structure of the Power System Model: Components:  Synchronous generators, and the associated excitation systems and prime movers  Interconnecting transmission network including static loads  Induction and synchronous motor loads  Other devices such as HVDC converters and SVCs Monitored Information:  Basic stability information  Bus voltages  Line flows  Performance of protective relaying, particularly transmission line protection
  • 24. 1539pkTS - 23 Fig. 13.8 Structure of the complete power system model for transient stability analysis
  • 25. 1539pkTS - 24  Models used must be appropriate for transient stability analysis  transmission network and machine stator transients are neglected  dynamics of machine rotors and rotor circuits, excitation systems, prime movers and other devices such as HVDC converters are represented  Equations must be organized in a form suitable for numerical integration  Large set of ordinary differential equations and large sparse algebraic equations  differential-algebraic initial value problem
  • 26. 1539pkTS - 25 Overall System Equations  Equations for each dynamic device:  where xd = state vector of individual device Id = R and I components of current injection from the device into the network Vd = R and I components of bus voltage  Network equation: where YN = network mode admittance matrix I = node current vector V = node voltage vector    dddd dddd VxgI Vxfx , ,   VYI N
  • 27. 1539pkTS - 26  Overall system equations: comprises a set of first order differentials and a set of algebraic equations where x = state vector of the system V = bus voltage vector I = current injection vector Time t does not appear explicitly in the above equations  Many approaches for solving these equations characterized by: a) The manner of interface between the differential and algebraic equations: partitioned or simultaneous b) Integration method used c) Method used for solving the algebraic equations: - Gauss-Seidal method based on admittance matrix - direct solution using sparsity oriented triangular factorization - iterative solution using Newton-Raphson method  Vxfx ,   VYVxI N,
  • 28. 1539pkTS - 27  Analyze transient stability including the effects of rotor circuit dynamics and excitation control of the following power plant with four 555 MVA units:  Disturbance: Three phase fault on circuit #2 at F, cleared by tripping the circuit Example 13.2 Fig. E13.6
  • 29. 1539pkTS - 28 Generator parameters: The four generators of the plant are represented by an equivalent generator whose parameters in per unit on 2220 MVA base are as follows: The above parameters are unsaturated values. The effect of saturation is to be represented assuming the d- and q-axes have similar saturation characteristics based on OCC Excitation system parameters: The generators are equipped with thyristor exciters with AVR and PSS as shown in Fig. 13.12, with parameters as follows: The exciter is assumed to be alternator supplied; therefore EFmax and EFmin are independent of Et Pre-fault system condition in pu on 2220 MVA, 24 kV base: P = 0.9 Q = 0.436 (overexcited) Et = 1.0 28.34 EB = 0.90081 0 Xd=1.81 Xq=1.76 Xd=0.30 Xq=0.65 Xd=0.23 Xq=0.25 X1=0.15 Ra=0.003 To0=8.0s Tq0=1.0s Td0=0.03s Tqo=0.07s H = 3.5 K0 = 0 '' ' '' ' '' ' ' '' KA= 200 TR= 0.015s EFmax= 7.0 EFmin= -6.4 KSTAB= 9.5 TW= 1.41s T1= 0.154s T2= 0.033s Vsmax= 0.2 Vsmin= -0.2
  • 30. 1539pkTS - 29 Objective Examine the stability of the system with the following alternative forms of excitation control: (i) Manual control, i.e., constant Efd (ii) AVR with no PSS (iii) AVR with PSS Consider the following alternative fault clearing times: a) 0.07 s b) 0.10 s
  • 31. 1539pkTS - 30  Computed using the Gill's version of fourth order R-K integration method with a time step of 0.02 s.  With constant Efd, the system is transiently stable  however, the level of damping of oscillations is low  With a fast acting AVR and a high exciter ceiling voltage, the first rotor angle swing is significantly reduced  however, the subsequent swings are negatively damped  post-fault system small-signal unstable  With the PSS, the rotor oscillations are very well damped without compromising the first swing stability Case (a): Transient response with the fault clearing time equal to 0.07 s
  • 32. 1539pkTS - 31 Fig. E13.7(a) Rotor angle response with fault cleared in 0.07 s Fig. E13.7(b) Active power response with fault cleared in 0.07 s
  • 33. 1539pkTS - 32 Fig. E13.7(c) Terminal voltage response with fault cleared in 0.07 s Fig. E13.7(d) Exciter output voltage response with fault cleared in 0.07 s
  • 34. 1539pkTS - 33  Responses of rotor angle  with the three alternative forms of excitation control are computed  With constant Efd, the generator is first swing unstable  With a fast acting exciter and AVR, the generator maintains first swing stability, but loses synchronism during the second swing  The addition of PSS contributes to the damping of second and subsequent swings Use of a fast exciter having a high ceiling voltage and equipped with a PSS contributes significantly to the enhancement of the overall system stability! Case (b): Transient response with the fault clearing time tc equal to 0.1 s
  • 35. 1539pkTS - 34 Fig. E13.8 Rotor angle response with fault cleared in 0.1 s
  • 36. 1539pkTS - 35 Example 13.3  For the system considered in previous example, examine the accuracy and numerical stability of the Gill's version of the 4th order R-K method and the trapezoidal rule  Consider the case with rotor circuit dynamics, AVR and PSS (i.e. stiff system), and the fault cleared in 0.07 s Results with R-K method:
  • 37. 1539pkTS - 36  For 0.01 s and 0.0590 s, the results are practically identical  When increased to 0.09 s, significant errors result; however, the general characteristics of the overall response is still retained  With a step size of 0.093 s, the errors become so large that the solution blows up after about 1.7 s. Results with Trapezoidal Rule
  • 38. 1539pkTS - 37 5. Representation of Faults in Stability Studies  Positive-sequence network is represented in detail  Negative- and zero-sequence voltages and currents throughout the system are usually not of interest in stability studies  unnecessary to simulate the complete negative- and zero-sequence networks in system stability simulations  effects represented by equivalent impedances (Z2 and Z0) as viewed at the fault point F  Impedances are combined appropriately as the effective fault impedance Zef
  • 39. 1539pkTS - 38 6. Performance of Protective Relaying  Monitor, detect abnormal conditions, select breakers to be opened, and energize trip circuits  Three requirements: selectivity, speed, and reliability  distinguish between stable swings and out-of-step  operate when needed and only when needed  operate sufficiently fast  coordinate with other relays  Function of certain relays essential to ensure transient stability  Special relaying may be used to separate systems  Of particular importance is transmission line protection schemes
  • 40. 1539pkTS - 39 Transmission Line Protection Two types of relaying schemes widely used currently: a) Current differential schemes, and b) Distance relaying schemes Types of Hardware: a) Electromechanical relays b) Static relays c) Digital or “numerical” relays Modern “digital relays”, in addition to basic protective relaying functions, have system monitoring capability:  allowing complementary control and monitoring functions.
  • 41. 1539pkTS - 40 (a) Current Differential Relaying  Based on the principal that under normal operating conditions, current injected to the element on one side is extracted at the other side  Mainly used in the past for lines too short for reliable application of distance relaying  Currently, differential protection schemes using fiber optic communication medium are increasingly being used, in particular for:  series capacitor compensated lines  short lines in load centers  multi-terminal lines  Relaying capability completely dependent on the availability of telecommunication system  To meet the requirement for a communication independent backup protection  conventional distance protection , typically zone 1 and zone 2 , with time delays are used as backup to differential protection
  • 42. 1539pkTS - 41 (b) Distance Relaying  Responds to a ratio of measured voltage to measured current  Impedance is a measure of distance along the line  Good discrimination and selectivity, by limiting relay operation to a certain range of the impedance  Types  impedance relay  reactance relay  mho relay  modified mho and impedance relays, and  Special shaped characteristics  Most widely used form for protection of transmission lines  Triggering characteristics shown conveniently on R-X plane
  • 43. 1539pkTS - 42 Fig. 13.28 Distance relay characteristics displayed on a coordinate system with resistance (R) as the abscissa, and reactance (X) as the ordinate
  • 44. 1539pkTS - 43 Three zone approach:  Zone 1 primary protection for protected line  80% reach and instantaneous  Zone 2 primary protection for protected line  120% reach and timed (0.3 - 0.5 s)  Zone 3 remote backup protection for adjacent line  covers next line and timed (2 s) Fig. 13.29 Distance relay characteristic
  • 45. 1539pkTS - 44 Communication assisted Distance Relaying  Use communication channels between the terminals of the line that they protect  Determine whether the fault is internal or external to the protected line, and this information is transmitted  For an internal fault, circuit breakers at all terminals of the protected line are tripped; for an external fault the tripping is blocked  Communication medium may be pilot wire (metallic wires), power-line carrier, microwave, or fiber optic  Overall objective is to clear faults at high speed
  • 46. 1539pkTS - 45 Each terminal station of the line has:  Underreaching zone 1 phase and ground directional distance relays covering about 75-80% of the line  trip local breakers instantaneously  Overreaching zone 2 phase and ground directional distance relays covering about 120% of the impedance of the protected line.  send permissive signal to remote end  trip local breakers if permissive signal received from remote end  if apparent Z remains inside relay characteristic for fixed time (typically 0.4 s), local breakers tripped without receiving permissive signal Fig. 13.30 Permissive overreaching relay Permissive Overreaching Scheme:
  • 47. 1539pkTS - 46 Fig. 13.31 Relay characteristic at station A Fig. 13.31 Fault locations F1, F2 and F3
  • 48. 1539pkTS - 47 Fault Clearing Times  Composed of relay time and breaker operating time  EHV relays: 1-2 cycles  Circuit breakers: 2-4 cycles  Breaker failure backup protection provided for each breaker on all critical circuits  if a breaker fails to operate at a local station, trip signals sent to adjacent zone breakers and remote end breakers
  • 49. 1539pkTS - 48 Notes: (i) For purposes of illustration, 2 cycle breakers have been assumed at A and 3 cycle breakers at B (ii) Communication time depends on channel medium used. With power line carrier, the time may be longer Local (Bus A) breakers 1 and 2 Remote (Bus B) breakers 3 and 4 Primary relay time (Fault detection) 25 ms 25 ms Auxiliary relay(s) time 3 ms 9 ms Communication time - 17 ms (microwave) Breaker trip module 3 ms 3 ms Breaker clearing time 33 ms (2 cycles) 50 ms (3 cycles) Total Time 64 ms 104 ms Fault cleared from bus A in 64 milliseconds Fault cleared from bus B in 104 milliseconds Fig. 13.34 Typical fault clearing times for a normally cleared fault
  • 50. 1539pkTS - 49 Notes: Breaker failure timer setting has been assumed to be 90 ms for the 2 cycle breaker 4. This could vary from one application to another. For a 3 cycle oil breaker a typical value is 150 ms Fig. 13.34 Typical fault clearing times for a stuck breaker fault Local Breaker 5 Remote breakers 6 and 7 Local backup breaker 3 Remote backup breakers 1 and 2 Primary relay time (at bus B) 25 ms 25 ms 25 ms 25 ms Auxiliary relay(s) time 3 ms 9 ms 6 ms 12 ms Communication channel time - 17 ms - 17 ms Breaker failure timer setting - - 90 ms 90 ms Breaker tripping module time 3 ms 3 ms 3 ms 3 ms Breaker time 33 ms 50 ms 33 ms 33 ms Total time 64 ms 104 ms 157 ms 180 ms Fault cleared from bus C in 104 milliseconds Fault cleared from bus B in 157 milliseconds Fault cleared from bus A in 180 milliseconds Breaker 4 assumed to be stuck Breakers 1, 2, 3, 4, and 5 assumed to be 2 cycle air-blast breakers (33 ms) Breakers 6 and 7 assumed to be 3 cycle oil breakers (50 ms)
  • 51. 1539pkTS - 50 Relaying Quantities During Swings The performance of protective relaying during electro- mechanical oscillations and out-out-step conditions illustrated by considering the following system: (a) Schematic diagram (b) Equivalent circuit Fig. 13.36 Two machine system The current I is given by The voltage at bus C is T BA Z EE I 0~   IZEE AAC ~~~ 
  • 52. 1539pkTS - 51 The apparent impedance seen by an impedance relay at C looking towards the line is given by If EA=EB=1.0 pu 0EE E ZZ I ~ I ~ ZE ~ I ~ E ~ Z BA A TA AAC C                                             2 cot 2 Z jZ 2 Z sin2 cos1 j 2 1 ZZ sinj2 sinjcos1 ZZ 101101 101 ZZ 101 Z ZZ T A T TA TA TA T AC        
  • 53. 1539pkTS - 52 During a swing, the angle  changes. Fig. 13.37 shows the locus of ZC as a function of  on an R-X diagram, when EA=EB Note: Origin is assumed to be at C, where the relay is located. Fig. 13.37 Locus of ZC as a function of , with EA=EB
  • 54. 1539pkTS - 53  When EA and EB are equal, the locus of ZC is seen to be a straight line which is the perpendicular bisector of the total system impedance between A and B, i.e., of the impedance ZT  the angle formed by lines from A and B to any point on the locus is equal to the corresponding angle   When =0, the current I is zero and ZC is infinite  When =180°, the voltage at the electrical centre is zero  the relay at C in effect will see a 3-phase fault at the electrical centre. The electrical centre and impedance centre coincide in this case.  If EA is not equal to EB, the apparent impedance loci are circles, with their centres on extensions of the impedance line AB  When EA>EB, the electrical centre will be above the impedance centre; when EA<EB, the electrical centre will be below the impedance centre. Fig. 13.38 illustrates the shape of the apparent impedance loci for three different values of the ratio EA / EB.
  • 55. 1539pkTS - 54 Fig. 13.38 Loci of ZC with different values of EA/EB
  • 56. 1539pkTS - 55  For generators connected to the main system through a weak transmission system (high external impedance), the electrical centre may appear on the transmission line  When a generator is connected to the main system through a strong transmission system, the electrical centre will be in the step up transformer or possibly within the generator itself  Electrical centres in effect are not fixed points: effective machine reactance and the magnitudes of internal voltages vary during dynamic conditions.  Voltage at the electrical centre drops to zero as  increases to 180° and then increases in magnitude as  increases further until it reaches 360°  when  reaches 180°, the generator will have slipped a pole; when  reaches the initial value where the swing started, one slip cycle will have been completed.
  • 57. 1539pkTS - 56 Prevention of Transmission Line Tripping During Transient Conditions Requirements for prevention of tripping during swing conditions fall into two categories:  Prevention of tripping during stable swings, while allowing tripping for unstable transients.  Prevention of tripping during unstable transients, and forcing separation at another point. Prevention of tripping during stable transients  ‘mho’ distance relay characteristic may be too large and have regions into which stable swings may enter  In order to minimize the possibility of tripping during stable swings:  use of ohm units (blinders)  composite relays  shaped relay (lens, peanut, etc.)
  • 58. 1539pkTS - 57 Tripping can occur only for impedance between O1 and O2, and within M Fig. 13.43 Reduction of mho relay angular range Fig. 13.44 Shaped Relay
  • 59. 1539pkTS - 58 Out-of-Step Blocking and Tripping Relays  In some cases, it may be desirable to prevent tripping of lines at the natural separation point, and choose the separation point so that: a) load and generation are better balanced on both sides, or b) a critical load is protected, or c) the separation is at a corporate boundary.  In certain instances, it may be desirable to trip faster in order to prevent voltage declining too far. Principle of out-of-step relaying:  Movement of the apparent impedance under out-of-step conditions is slow compared to its movement when a line fault occurs  transient swing condition can be detected using two relays having vertical or circular characteristics on an R-X plane  if time required to cross the two characteristics (OOS2, OOS1) exceeds a specified value, the out-of- step function is initiated
  • 60. 1539pkTS - 59 Fig. 13.45 Out-of-step relaying schemes
  • 61. 1539pkTS - 60  In an out-of-step tripping scheme, local breakers would be tripped. such a scheme could be used to  speed up tripping to voltage decline  ensure tripping of a selected line, instead of other more critical circuits  In an out-of-step blocking scheme,  relays are prevented from initiating tripping of the line monitored, and transfer trip signals are sent to open circuits of a remote location  objective is to cause system separation at a more preferable location
  • 62. 1539pkTS - 61 Generator Out-of-Step Protection  For situations where the electrical centre is within the generator or step-up transformer, a special relay must be provided at the generator  occurs when a generator pulls out of synchronism in a system with strong transmission  low excitation level on the generator (EA<EB) also tends to contribute to such a condition Effect of generators operating in out-of-step condition:  Causes large cyclic variations in currents and voltages of the affected machine  the frequency being a function of the rate of slip of its poles  The high amplitude currents and off-nominal frequency operation could result in winding stresses, and pulsating torques which can excite potentially damaging mechanical vibrations  There is also risk of losing the auxiliaries of the affected unit as well as the auxiliaries of nearby stable units
  • 63. 1539pkTS - 62 Relays for Out-of-Step Tripping of Generators  Similar to those used to detect out-of-step conditions on the transmission system  No industry standards or commonly used practices a) Mho element scheme: (a) System schematic (b) System equivalent circuit (c) Relay characteristic and swing locus as seen at the HV bus
  • 64. 1539pkTS - 63  Mho relay monitors the apparent impedance at the HT terminal (H) of the unit transformer, and is set to reach into the local generator  Immediate trip when the apparent impedance enters the offset mho characteristic  objective is to allow tripping only for unstable swings  typically, the angle c at the point where the swing impedance enters the relay characteristic is set to about 120  If circle is too large, the protection may trip the generator for stable swings  If circle is too small (c large), the scheme may not trip the generator for unstable swings  also, if c is too large the tripping can occur when the angular separation approaches 180; this should be avoided since it subjects the circuit breaker to the maximum recovery voltage during interruption
  • 65. 1539pkTS - 64 b) Blinder scheme:  Consists of two blinders, and a supervisory relay with an offset mho characteristic  Offers more selectivity than the simple mho element scheme  It is easy to coordinate with the transmission line protection; this permits the reach to extend into the system beyond the HT bus (H) of the step-up transformer Fig. 13.47 Generator out-of-step protection using a blinder scheme
  • 66. 1539pkTS - 65 7. Case Study - Transient Stability  The object  demonstrate transient instability and actions of protective relaying  show methods of maintaining stability  The system  2279 buses, 467 generators, and 6581 branches  the focus is on a plant with 8 nuclear units, with a total capacity of 7000 MW  all generators and associated controls are modelled in detail  loads are modelled using voltage-dependent static load model (P=50% l + 50% Z, Q=100% Z)
  • 67. 1539pkTS - 66 Fig. 13.52 Diagram of system in the vicinity of a 7000 MW nuclear power plant
  • 68. 1539pkTS - 67 The Contingency:  Double line-to-ground (LLG) fault occurs on the 500 kV double circuit line at Junction X Time (ms) Event 0 No disturbance 100 Apply LLG fault at Junction X on circuits 1 and 2 164 Local end clearing: Open breakers at bus 1 for circuit 1 Open breakers at bus 2 for circuit 2 This occurs 64 ms after the fault is applied, and this time is computed as the sum of fault detection time (25 ms), auxiliary relay time (6 ms), and the breaker clearing time (33 ms = 2 cycle). At this time, the fault remains connected on the ends of circuits 1 and 2 at Junction X 187 Remote end clearing: Open breakers at bus 4 for circuit 2 Open breakers at bus 3 for circuit 1 Clear fault (the line is isolated) This occurs 87 ms after the fault is applied, and the time is calculated as the sum of fault detection time (25 ms), auxiliary relay time (12 ms), communication time (17 ms; microwave), and breaker clearing time (33 ms = 2 cycle) 5000 Terminate simulation
  • 69. 1539pkTS - 68 Simulation:  A 5 second simulation was performed  G3 is seen to lose synchronism and becomes monotonically unstable  similar behaviour for the other 7 units of the nuclear plant  As G1 to G8 become unstable, the rest of the system becomes generation deficient  absolute angles of all machines in the system drift slightly Fig. 13.53 Rotor angle time response
  • 70. 1539pkTS - 69 Analysis: How does the system come apart as a result of instability?  Out-of-step protection does not operate on G3 Fig. 13.54 Unit G3 out-of-step protection
  • 71. 1539pkTS - 70 Fig. 13.55 Line protection (circuit 3) at bus 1 Fig. 13.56 Line protection (circuit 3) at bus 7
  • 72. 1539pkTS - 71 Line Protection:  Mho distance relays have zone 1 coverage of about 75% of line length, and zone 2 over-reach of about 125% of line length  Apparent impedance enters the zone 2 relays at bus 1 and enters zone 1 and zone 2 relays at bus 7  zone 1 relay at bus 7 would trip circuit 3 at bus 7 and send a transfer trip signal to breakers at bus 1 which would then trip circuit 3 at bus 1  true for the companion 500 kV circuit (#4) which would be tripped in an identical manner  Following the loss of the 500 kV circuits (at approximately 0.8 seconds), the remaining 230 kV circuits would become extremely over-loaded and would be lost through protection actions, thereby completely isolating the unstable plant from the system  Impedance plot shows the impedance swing crosses the circuit at a point about 84% of the line length from bus 1  represents the electrical centre following the disturbance, and is theoretically where separation occurs
  • 73. 1539pkTS - 72 Bus Voltages: Fig. 13.57 Voltages at buses 1, 7 and the electrical centre
  • 74. 1539pkTS - 73 Methods of Maintaining Stability:  Reduction of the pre-contingency output of the plant  costly to bottle energy in the plant  Tripping of 2 generating units (generation rejection) following the disturbance Fig. 13.58 Unit G3 rotor angle response with and without generation rejection
  • 75. 1539pkTS - 74 8. Transient Stability Enhancement Objectives:  Reduce the disturbing influence by minimizing the fault severity and duration  Increase the restoring synchronizing forces  Reduce accelerating torque through control of prime- mover mechanical power  Reduce accelerating torque by applying artificial load
  • 76. 1539pkTS - 75 High-Speed Fault Clearing  Amount of kinetic energy gained by the generators during a fault is directly proportional to the fault duration  quicker the fault is cleared, the less disturbance it causes  Two-cycle breakers, together with high speed relays and communication, are now widely used in locations where rapid fault clearing is importance  In special circumstances, even faster clearing may be desirable  development and application of a 1 cycle circuit breaker by Bonneville Power Administration (BPA)  combined with a rapid response overcurrent type sensor, which anticipates fault magnitude, nearly one-cycle total fault duration is attained  ultra high speed relaying system for EHV lines based on traveling wave detection  not in widespread use
  • 77. 1539pkTS - 76 Reduction of Transmission System Reactance  Series inductive reactances of transmission networks are primary determinants of stability limits  reduction of reactances of various elements of the transmission network improves transient stability by increasing post-fault synchronizing power transfers  Most direct way of achieving this is by reducing the reactances of transmission circuits  voltage rating, line and conductor configurations, and number of parallel circuits determine the reactances of transmission lines  Additional methods of reducing the network reactances:  use of transformers with lower leakage reactances  series capacitor compensation of transmission lines
  • 78. 1539pkTS - 77  Typically, the per unit transformer leakage reactance ranges between 0.1 and 0.15  for newer transformers, the minimum acceptable leakage reactance that can be achieved within the normal transformer design practices has to be established in consultation with the manufacturer  May be a significant economic advantage in opting for a transformer with the lowest possible reactance  Series capacitors directly offset the line series reactance  the maximum power transfer capability of a transmission line may be significantly increased by the use of series capacitor banks  directly translates into enhancement of transient stability, depending on the facilities provided for bypassing the capacitor during faults and for reinsertion after fault clearing  speed of reinsertion is an important factor in maintaining transient stability; using nonlinear resistors of zinc oxide, the reinsertion is practically instantaneous
  • 79. 1539pkTS - 78  One problem with series capacitor compensation is the possibility of subsynchronous resonance with the nearby turbo alternators  must be analyzed carefully and appropriate preventive measures taken  Series capacitors have been used to compensate very long overhead lines  recently, there has been an increasing recognition of the advantages of compensating shorter, but heavily loaded, lines using series capacitors  For transient stability applications, the use of switched series capacitors offers some advantages  can be switched in upon detection of a fault or power swing, and then removed about half second later  can be located in a substation where it can serve several lines  protective relaying is made more complex when series compensation is used, and more so if the series capacitors are switched
  • 80. 1539pkTS - 79 Regulated Shunt Compensation  Can improve system stability by increasing the flow of synchronizing power among interconnected generators (voltage profile control)  Static VAR compensators can be used for this purpose Fig. 11.60 Performance of a 600 km line with an SVS regulating midpoint voltage
  • 81. 1539pkTS - 80 Regulated Shunt Compensation (cont'd) Fig. 11.62 Power-angle relationships with regulated compensation at discrete intervals dividing line into n independent sections n θ/n (degrees) 1 44.70 1.00 2 22.35 1.85 3 14.90 2.74 4 11.17 3.63 6 7.45 5.42 8 5.59 7.22 10 4.47 9.03 maxmax PP
  • 82. 1539pkTS - 81 Dynamic Braking  Uses the concept of applying an artificial electrical load during a transient disturbance to increase the electrical power output of generators and thereby reduce rotor acceleration  One form of dynamic braking involves switching in shunt resistors for about 0.5 seconds following a fault to reduce accelerating power of nearby generators and remove the kinetic energy gained during the fault  BPA has used such a scheme for enhancing transient stability for faults in the US Pacific Northwest  brake consists of a 1400 MW, 240 kV resistor made up of 45,000 ft. of 1/2" stainless steel wire strung on 3 towers
  • 83. 1539pkTS - 82  To date, braking resistors have been applied only to hydraulic generating stations remote from load centres  hydraulic units, in comparison to thermal units, are quite rugged; they can, therefore, withstand the sudden shock of switching in resistors without any adverse effect on the units  If braking resistors are applied to thermal units, the effect on shaft fatigue life must be carefully examined  If the switching duty is found unacceptable, the resistors may have to be switched in three or four steps spread over one full cycle of the lowest torsional mode  Braking resistors used to date are all shunt devices  series resistors may be used to provide the braking effect  the energy dissipated is proportional to the generator current rather than voltage  way of inserting the resistors in series is to install a star-connected three-phase resistor arrangement with a bypass switch in the neutral of the generator- step-up transformer to reduce resistor insulation and switch requirements  resistor is inserted during a transient disturbance by opening the bypass switch
  • 84. 1539pkTS - 83  Another form of braking resistor application, which enhances system stability for only unbalanced ground faults, consists of a resistor connected permanently between ground and the neutral of the Y connected high voltage winding of the generator step-up transformer  under balanced conditions no current flows through the neutral resistor  when line-to-ground or double line-to-ground faults occur, current flows through the neutral connection and the resistive losses act as a dynamic brake  With switched form of braking resistors, the switching times should be based on detailed simulations  if the resistors remain connected too long, there is a possibility of instability on the "backswing"
  • 85. 1539pkTS - 84 Reactor Switching  Shunt reactors near generators provide a simple and convenient means of improving transient stability  Reactor normally remains connected to the network  Resulting reactive load increases the generator internal voltage and reduces internal rotor angle  Following a fault, the reactor is switched out which further improves stability
  • 86. 1539pkTS - 85 Single-Pole Switching  Uses separate operating mechanisms on each phase; for single line-to-ground faults, the relaying is designed to trip only the faulted phase, followed by fast reclosure within 0.5 to 1.5 seconds; for multi-phase faults, all three phases are tripped  When one phase is open, power is transferred over the remaining two phases  As most faults on transmission lines are of the single line-to-ground type, opening and reclosing of only the faulted phase results in an improvement in transient stability over three-phase tripping and reclosing  Particularly attractive for situations where a single major line connects two systems or where a single major line connects a generating station to the rest of the system  Also used on systems with multiple lines to improve system security against multiple contingency disturbances  Three potential problems:  secondary arc extinction  fatigue duty on turbine-generator shafts and turbine blades  thermal duty on nearby generators due to negative- sequence currents
  • 87. 1539pkTS - 86 Steam Turbine Fast Valving  Applicable to thermal units to assist in maintaining power system transient stability  Involves rapid closing and opening of steam valves in a prescribed manner to reduce the generator accelerating power, following the recognition of a severe transmission system fault  Use recognized in the early 1930s, but it has not been very widely applied for several reasons  concerns for any possible adverse effects on the turbine and energy supply system  Since the mid-1960s, utilities have realized that fast valving could be an effective method of improving system stability in some situations  number of technical papers have been published describing the basic concepts and effects of fast valving  several utilities have tested and implemented fast valving on some of their units
  • 88. 1539pkTS - 87 Fast Valving Procedures  The main inlet control valves (CV) and the reheat intercept valves (IV) provide a convenient means of controlling the turbine mechanical power  Variety of possibilities exist for the implementation of fast valving schemes  Common scheme: only the intercept valves are rapidly closed and then fully reopened after a short time delay  since the intercept valves control nearly 70% of the total unit power, this method results in a fairly significant reduction in turbine power  More pronounced temporary reduction in turbine power can be achieved through actuation of both control and intercept valves  Procedure of rapid closing and subsequent full opening of the valves is called momentary fast valving  Due to the post-fault transmission system being much weaker than the pre-fault one, it may be desirable to have the prime-mover power, after being reduced rapidly, return to a level lower than the initial power  sustained fast valving
  • 89. 1539pkTS - 88 Generator Tripping  Selective tripping of generating units for severe transmission system contingencies has been used as a method of improving system stability for many years  Rejection of generation at an appropriate location in the system reduces power to be transferred over the critical transmission interfaces  Units can be tripped rapidly so this is a very effective means of improving transient stability  Historically, the application confined to hydro plants; now used on fossil and nuclear plants  Many utilities design thermal units so that, after tripping, they continue to run, supplying unit auxiliaries; permits the units to re resynchronized to the system and restored to full load in about 15 to 30 minutes  Major turbine-generator concerns:  the overspeed resulting from tripping the generator  thermal stresses due to the rapid load changes  high levels of shaft torques due to successive disturbances
  • 90. 1539pkTS - 89 Controlled System Separation and Load Shedding  May be used to prevent a major disturbance in one part of an interconnected system from propagating into the rest of the system and causing a severe system breakup  Severe disturbance usually characterized by sudden changes in tie line power  if detected in time and the information is used to initiate corrective actions, severe system upsets can be averted  Impending instability detected by monitoring one or more of the following: sudden change in power flow through specific transmission circuits, change of bus voltage angle, rate of power change, and circuit breaker auxiliary contacts  Upon detection of the impeding instability, controlled system separation is initiated by opening the appropriate tie lines before cascading outages can occur  In some instances it may be necessary to shed selected loads to balance generation and load in the separated systems
  • 91. 1539pkTS - 90 High-Speed Excitation Systems  Significant improvements in transient stability can be achieved through rapid temporary increase of generator excitation  Increase of generator field voltage during a transient disturbance has the effect of increasing the internal voltage of the machine, which in turn increases synchronizing power  High initial response excitation systems with high ceiling voltages are most effective in this regard  ceiling voltages limited by generator rotor insulation considerations  for thermal units, limited to about 2.5 to 3.0 times rated- load field voltage  Fast excitation response to terminal voltage variations, required for improvement of transient stability, often leads to degrading the damping of local plant mode oscillations  Supplementary excitation control, commonly referred to as power system stabilizer (PSS) provides a convenient means of damping system oscillations  Use of high initial response excitation systems supplemented with PSS is by far the most effective and economical method of enhancing the overall system stability
  • 92. 1539pkTS - 91 Discontinuous Excitation Control  Properly applied PSS provides damping to both local and inter- area modes of oscillations  Under large signal or transient conditions, the stabilizer generally contributes positively to first swing stability  In the presence of both local and inter-area swing modes, however, the normal stabilizer response can allow the excitation to be reduced after the peak of the first local-mode swing and before the highest composite peak of the swing is reached  Additional improvements in transient stability can be realized by keeping the excitation at ceiling, within terminal voltage constraints, until the highest point of the swing is reached  Discontinuous excitation control scheme referred to as Transient Stability Excitation Control (TSEC) has been developed by Ontario Hydro to achieve the above  improves transient stability by controlling the generator excitation so that the terminal voltage is maintained near the maximum permissible value of about 1.12 to 1.15 pu over the entire positive swing of the rotor angle
  • 93. 1539pkTS - 92  uses a signal proportional to change in angle of the generator rotor, in addition to the terminal voltage and rotor speed signals  angle signal is used only during the transient period of about 2 seconds following a severe disturbance, since it results in oscillatory instability if used continuously  angle signal prevents premature reversal of field voltage and hence maintains the terminal voltage at a high level during the positive swing of the rotor angle  excessive terminal voltage is prevented by the terminal voltage limiter  When TSEC used on several generating stations in an area;  system voltage level in the entire area is raised  increases power consumed by loads in the entire area, contributing to further improvement in TS
  • 94. 1539pkTS - 93 Fig. 17.7 Block diagram of TSEC scheme Fig. 17.8 Effect of TSEC on transient stability
  • 95. 1539pkTS - 94 Integrating HVDC Parallel Links  HVDC links are highly controllable. Possible to take advantage of this unique characteristic of the HVDC link to augment the transient stability of the ac system  Parallel application with ac transmission can be effectively used to bypass ac network congestion  Often, provides the best option for using limited right of way  Provides a firewall against cascading outages during major system disturbances For example, during the August 2003 Blackout of northeast US and eastern Canada,  Quebec was unaffected  AC links from New York to New England tripped; however, HVDC links from Quebec continued to supply power to New England  With the present day technology based on self – commutated voltage sourced converters, transient stability augmentation can also be achieved by controlling the HVDC converters so as to provide reactive power and voltage support.
  • 96. 1539pkTS - 95 Examples of HVDC Parallel Links  Pacific HVDC Inter-tie in the US west  1400 km long 440 kV bipolar HVDC overhead line from Columbia River in Oregon to Los Angeles, California  Built in the early 1970s, with a capacity of 1,440 MW; upgraded over the years to 3,100 MW  Has operated successfully for over 30 years in parallel with 500 kV AC transmission  Itaipu HVDC Link in Brazil  800 km long 600 kV bipolar HVDC overhead line from Foz du Iguacu hydro power plant to the load centre in the city of Sao Paulo  3,150 MW HVDC link built in the mid 1980s  Has operated successfully for over 20 years in parallel with 765 kV AC transmission network  Quebec- New England multi-terminal HVDC system  1500 MW, 1500 km 450 kV bipolar HVDC link built in the early 1990s  Brings power from James Bay Hydro plants to Boston, Massachusetts area  Comprises five terminals; normally operates as a three-terminal link
  • 97. 1539pkTS - 96 HVDC Technologies  Electronic converters for HVDC are classified into two main categories:  Line-Commutated Converters ( LCC )  Voltage-Sourced Converters ( VSC )  LCC converters rely on the natural voltage of the AC system for commutation  Converters use electronic switches that can only be turned on (not off) by control action  Early LCC systems used mercury-arc valves; since the 1970s thyristors have been used  Consume reactive power from the AC system and result in lower-order harmonics, which in turn call for counter measures  VSC converters use semiconductor elements with current interrupting capabilities to force commutation at any desired point on the AC cycle  Thyristors cannot be used; instead transistors, such as Insulated Gate Bipolar Transistor (IGBT), are used  First application in 1977; continued advancements and applications since
  • 98. 1539pkTS - 97 VSC-Based HVDC Technology  Self-commutated voltage-sourced converter (VSC) HVDC technology has the following technical benefits:  Does not rely on AC system for commutation  Active and reactive power can be controlled independently  Excellent dynamic response  Can be connected to very weak ac network  Harmonic filter requirements are significantly less  Good “black-start” capability  Lower overall “footprint”  VSC-based HVDC converters are relatively more expensive and have higher losses  Technical advancements made in recent years have effectively addressed these issues  Depending on the nature of the application, these may not be significant issues
  • 99. 1539pkTS - 98 VSC-Based HVDC Technology Evolution  The first generation VSC technology was based on either two-level or three-level converters utilizing pulse width modulation (PWM)  Main associated drawbacks were: high levels of power loss and lack of modularity  These are addressed in two recent topologies: Siemens MMC (Modular Multi-Level Converter) and ABB Cascaded Converter configurations  Use half-bridge or full bridge modules depending on the application  Provide modularity: damaged parts would be small and readily replaceable  Use low-frequency switching in each module, thus reducing losses Increasingly being used for interconnecting weak AC systems; for connecting large-scale wind power to the grid; and for long distance underground and underwater links
  • 100. 1539pk November 9, 1965 Blackout of Northeast US and Ontario
  • 101. 1539pkTS - 100 November 9, 1965 - Blackout of Northeast US and Canada  Clear day with mild weather; Load levels in the regional normal  Problem began at 5:16 p.m.  Within a few minutes, there was a complete shut down of electric service to  virtually all of the states of New York, Connecticut, Rhode Island, Massachusetts, Vermont  parts of New Hampshire, New Jersey and Pennsylvania  most of Ontario, Canada  Nearly 30 million people were without power for about 13 hours  President Johnson ordered Chairman of Federal Power Commission to conduct an immediate investigation  Developments that followed had a major impact on the industry!
  • 102. 1539pkTS - 101 North American Eastern Interconnected System
  • 103. 1539pkTS - 102 Events that Caused the 1965 Blackout  The initial event was the operation of a backup relay (Zone 3) at Beck GS in Ontario near Niagara Falls  opened circuit Q29BD, one of five 230 kV circuits connecting Beck GS to load centers in Toronto and Hamilton  Prior to opening of Q29BD, the five circuits were carrying  1200 MW of Beck generation, and  500 MW import from Western NY State on Niagara ties  Net import from NY 300 MW  Loading on Q29BD was 361 MW at 248 kV;  The relay setting corresponded to 375 MW
  • 104. 1539pkTS - 103 Events that Caused the 1965 Blackout (cont'd) Beck
  • 105. 1539pkTS - 104 Events that Caused the 1965 Blackout (cont'd)  Opening of Q29BD resulted in sequential tripping of the remaining four parallel circuits  Power flow reversed to New York  total change of 1700 MW  Power surge back to Ontario via St. Lawrence ties  ties tripped by protective relaying  Generators in Western New York and Beck GS lost synchronism, followed by cascading outages  After about 7 seconds from the initial disturbance  system split into several separate islands  eventually most generation and load lost; inability of islanded systems to stabilize
  • 106. 1539pkTS - 105 Special Protections Implemented after the 1965 Blackout  P Relays on Niagara Ties  trip Niagara ties to NY; cross-trip St. Lawrence ties to NY  in place until mid 1980s  Under-frequency load shedding (UFLS) throughout the interconnected system  beginning of the use of UFLS by industry
  • 107. 1539pkTS - 106 Formation of Reliability Councils  Northeast Power Coordinating Council (NPCC) formed in January 1966  to improve coordination in planning and operation among utilities in the region that was blacked out  first Regional Reliability Council (RRC) in North America  Other eight RRCs formed in the following months  National/North American Electric Reliability Council (NERC) established in 1968
  • 108. 1539pkTS - 107 Reliability Enhancement after the 1965 Blackout  All utilities in North America began to review reliability related policies, practices and procedures  Coordination of activities and information exchange between neighbouring utilities became a priority  Each Regional Council established detailed Reliability criteria and guidelines for member systems  Power system stability studies became an important part of operating studies  led to the development of improved Transient Stability programs  exchange of data between utilities  Many of these developments has had an influence on utility practices worldwide
  • 110. 1539pkTS - 109 March 11, 1999 Brazil Blackout  Time: 22:16:00h, System Load: 34,200 MW  Description of the event:  L-G fault at Bauru substation as a result of lightning causing a bus insulator flashover  The bus arrangement at Bauru such that the fault is cleared by opening five 440 kV lines  The power system survived the initial event, but resulted in instability when a short heavily loaded 440 kV line was tripped by zone 3 relay  Cascading outages of several power plants in Sao Paulo area, followed by loss of HVDC and 750 kV AC links from Itaipu  Complete system break up: 24,700 MW load loss; several islands remained in operation with a total load of about 10,000 MW  Restoration of different regions varied from 30 minutes to 4 hours  Complete blackout of Sao Paulo and Rio de Janeiro areas for about 4 hours
  • 111. 1539pkTS - 110 March 11, 1999 Brazil Blackout (cont'd)  Measures to improve system security:  Joint Working Group comprising ELECTROBRAS, CEPEL and ONS staff formed  Organized activities into 8 Task Forces  Four international experts as advisors  Remedial Actions:  Power system divided into 5 security zones: regions with major generation and transmission system protected or emergency controls  All major EHV substations classified into high, medium, low risk categories based on  impact level to system security of bus faults  intrinsic reliability level of substation (layout, equipment changes) to reduce risk level  Improved maintenance of substation equipment and protection/control equipment  Better training of operators  Improved restoration plans