SlideShare a Scribd company logo
1 of 6
Download to read offline
Proceedings of the 8th IEEE GCC Conference and Exhibition, Muscat, Oman, 1-4 February, 2015
978-4799-8422-0/15/$31.00©2015 IEEE
Economic Dispatch in Power Systems
A comparison between vertically integrated and libralized markets
F. N. Al Farsi, M. H. Albadi, N. Hosseinzadeh, A. H. Al Badi
Department of Electrical and Computer Engineering, Sultan Qaboos University, POBox33, Muscat 123, Sultanate of Oman
m065416@student.squ.edu.om
Abstract—Economic Dispatch is an important optimization
problem in power system planning. This article presents an
overview of the economic dispatch problem, its formulation,
and a comparison of addressing the problem between the
vertically integrated market and the liberalized market
environments.
Keywords—Econmic Dispatch; Dispatch Centre; Vertically
Integrated Markets; Libralized Marekts
I. INTRODUCTION
Consider a system consists of N generating units serving
an electrical load as shown in Fig. 1. In this system there are
multiple types of fuel input used to operate the power plant
e.g. (Hydro, Gas, Steam, Diesel, Nuclear, Coal, Solar,
Wind… etc.). Knowing that the power systems should be
operated under a high degree of economy so that the system
will be operated at minimum cost; therefore the economic
dispatch concept will tell how much should be the output of
each generator so that the total operating cost is minimized.
Fig. 1. N Generating Units Serving an Electrical Load [1]
II. ECONOMIC DISPATCH FORMULATION
A. Economic Dispatch Definition
The purpose of the economic dispatch is to schedule the
outputs of all available generation units in the power system
such that the fuel cost is minimized while system constraints
are satisfied. Also it can be explained as the process of
allocating generation among the committed units such that
the constraints imposed are satisfied and the energy
requirements are minimized.
Furthermore, the economic power dispatch for
interconnected power system can be explained as the process
of finding the total real and reactive power schedule of each
power plant in such a way as to minimize the operating cost.
This means that the generator’s real and reactive power is
allowed to vary within certain limits so that it can meet the
demand with minimum fuel cost. This is called the optimal
power flow. The optimal power flow is used to optimize the
power flow solution of large scale power system. This is
done by minimizing selected objective functions while
maintaining an acceptable system performance in terms of
generators capability limits and the output of the
compensating devices [1].
It is useful to divide economic dispatch practices in two
separate stages: unit commitment and unit dispatch. Unit
commitment takes place before real-time operation and
determines the set of generating units that will be available
for dispatch. Unit dispatch occurs in real time and determines
the amount of generation needed from each available unit
[2].
B. Objective of the Power Economic Dispatch
The Main objective of the power economic dispatch is to
find the total power generation output so as to minimize
operating cost. Beside the main objective, there are also
numbers of objectives listed as follows:
• To schedule the committed generating units outputs
so as to meet the required load demand at minimum
operating cost while satisfying all units and system
equality and inequality constraints [3].
• Minimization of the emissions (the gaseous
emission such as SO2, NOx, CO and CO2 produced
by thermal power plants) ;
• Maximization of the profit by reducing the total
cost.
• Maintain System Stability and Security Constraint.
Economic Dispatch Mathematical formulation
 The objective function of an ED problem is to:
• Minimize  = ∑ ( )

(1)
where usually the operating cost of each generator when
generating a specific output power is modeled as
• ( ) =  +   +  

(2)
Authorized licensed use limited to: Pontificia Universidad Javeriana. Downloaded on October 23,2023 at 19:15:17 UTC from IEEE Xplore. Restrictions apply.
Proceedings of the 8th IEEE GCC Conference and Exhibition, Muscat, Oman, 1-4 February, 2015
• ,    represent the cost
coefficients of the jth generating unit.
• ( ) represents the cost function of the
jth generating unit (in $/h),
• 
represents the real output of the jth
generating units (in MW),
•  is the total number of generators in the
power system.
This main objective is subject to a number of constraints.
Theses constraints are classified into two categories as
follows:
1) GENERATION CONSTRAINTS:
• System constraints
∑ 

=  +  (3)
Where the Transmission Line Losses equation is equal to

= ∑ ∑ 
!  




# + ∑ ! $


 + !$$ (4)
 !  :- is the jth element of the
loss coefficient square matrix,
 ! $ :- is the ith element of the
loss coefficient vector,
 B$$ :- is the loss coefficient
constant
• Spinning Reserve Requirement
∑ 
≥

 (
, ) = 1,2, … … . ,  (5)
 
is the spinning reserve
contribution of unit I during the
time interval t;
 SR0
is the system spinning reserve
requirement for interval t;
• Thermal Unit Constraints [4]
 Minimum up time: once the unit
is running, it should not be turned
off immediately.
 Minimum down time: once the
unit is decommitted, there is a
minimum time before it can be
recommitted.
• Must Run Units Constraints [4]
In some cases, some units must
remain online for voltage support
requirements. Others might be needed
to produce steam for water purpose or
to use the steam on the plant itself.
• Fuel Constraint [4]
 Some units have limited fuel
 Fuel must be burn in a specified
time
 Type of fuel
• Generator Location (criteria to be selected
during design stage)
• Generation Limit

1 
   
134
, (5 = 1, … … . . , ) (6)
 Unit ramp rates within the range of
production levels (e.g., the time it takes to
move from one production level to another
while respecting the turbine’s safe thermal
gradients);
i) If power generation increases
 − 
$
≤ 8( (7)
ii) If power generation decreases

$
−  ≤ 9( (8)
Where 
$
(inMW) is the previous
output power and 8((in MW/h) is
the up-ramp limit of the jth generator;
and 9( (in MW/h) is the down-ramp
limit of the jth generator.
 Prohibited Operated Zone (normally will
be given by the manufacturer)
In the actual power system, the load
demand of a power system must avoid the
prohibited zones. Thus, if the constraint in
(1) is taken into account, the feasible
operating zones of the jth generating unit
can be as follows
 
1 
≤  ≤ ,
:
(9)
 ,;
=
≤  ≤ ,;
:
,  =
2,3, … … . , 
(10)
 , @
=
≤  ≤ 
134
(11)
where ,;
:
and ,;
=
are the lower and upper
bound of the jth prohibited zone of the jth
generating unit, and  is the number of
prohibited zones of the jth generating unit. In the
actual power system, the load demand of a
power system must avoid the prohibited zones.
Authorized licensed use limited to: Pontificia Universidad Javeriana. Downloaded on October 23,2023 at 19:15:17 UTC from IEEE Xplore. Restrictions apply.
Proceedings of the 8th IEEE GCC Conference and Exhibition, Muscat, Oman, 1-4 February, 2015
2) TRANSMISSION NETWORK CONSTRAINTS
• Network Security Constraint (Voltage
limit Constraints (+/- 10%) [applicable for
both 132 kV and 220 kV System]
• Line capacities under different power
flows and loadings;
:
134
≤ :

≤ :
134
A = 1,2, … … . . , A (12)
 :

is the active power flow
through transmission line l during
the interval t;
 :
134
is the upper limit on the
active power flow along line l
III. COMPARISON BETWEEN VERTICALLY
INTEGRATED POWER SYSTEMS AND LIBERALIZED
ELECTRICITY MARKET
There are two approaches currently existing for providing
electricity to the end user. The first one is the vertically
integrated market and the second one is the liberalized
market or competitive market.
A. Vertically Integrated Market
Vertically Integrated Market means that the generation,
transmission and distribution belongs to a simple owner e.g.
(Government) [5]. Fig. 2 is an example of a vertically
integrated market where a single agency or company is
responsible for generating, transmitting and distributing the
power to the end user.
Fig. 2. Vertically Integrated Organization [6]
In this model, the provider does not have to compete to
provide the electricity to the customer with low cost and
high quality as there are no other competitors in the market.
Sometimes the provider is asked by the government to meet
the projected goals which can end up in dispatching the
power in inefficient way [4].
1) Advantages of the Vertically Integrated Power
System
The advantages of the Vertically Integrated Power System
(VIPS) are its simplicity and certainty. A single integrated
utility does not require complicated systems to dispatch the
power to multiple providers at the wholesale level, or retail
market platforms that allow for switching of customers
between different retail providers. In the vertically
integrated power system the incentives for innovation are
generally considered to be weak, unless governments are
particularly involved in supporting researches and
development section in areas of dispatching the power in an
economic and efficient way.
2) Example of Dispatch Procedure in the Vertically
Integrated Market
In sultanate of Oman, The Load Dispatch Centre (LDC)
from Oman Electricity Transmission Company (OETC) is
responsible to dispatch the power in the main interconnected
system network in Oman. The way that the LDC is using in
dispatching the power is an example of the vertically
integrated market. First of all, the LDC department in OETC
creates Day-Ahead Load Forecast, based on Data received
from consumers (distribution companies and directly
connected customers), weather forecasts and Day ahead
units availability form all Independent Power Producers.
LDC uses these three main inputs to run unit-commitment
optimization computer programs to get the optimal dispatch
scenarios for the next day forecast before the real
operations. The computer programs take as inputs all the
information on the characteristics of the individual
generating units that are ready to provide electricity on the
following day. These characteristics include current unit
status, minimum and maximum output levels, ramp rate
limits, start-up and shutdown costs, minimum runtimes, and
unit fuel costs at various output levels. Moreover, the
operations planner inputs to the model the utility’s day-
ahead forecast loads, hour by hour. Finally, the inputs
include details on the characteristics of the transmission
system expected for the operating day (in particular, any
lines or transformers out of service for maintenance).
The optimization model is then run with all these inputs in
order to identify the least cost solution to meet the following
day’s electricity demands while maintaining system
constraints. The reliability requirements are the ability to
withstand the loss of any single generation or transmission
element while maintaining normal system operation. The
optimization model performs functions in its search for a
least-cost solution.
Once generators are committed (turned on and synchronized
to the grid), they are ready to provide power to meet
customer loads and reliability requirements. The provisional
running orders for day a head planning used as a guide line
for control engineer. However, during the real time
operation the control engineer in the LDC decides how
much additional (or less) generation is required during the
Authorized licensed use limited to: Pontificia Universidad Javeriana. Downloaded on October 23,2023 at 19:15:17 UTC from IEEE Xplore. Restrictions apply.
Proceedings of the 8th IEEE GCC Conference and Exhibition, Muscat, Oman, 1-4 February, 2015
next interval to meet system requirements. The action taken
by the control engineer in LDC during the real time
operation is to meet the load demand while maintaining all
the system constraints of each generator.
The control engineer during the real time operation has the
authority to decide whether to turn a unit on or not (the unit-
commitment decision), based on the load requirement while
maintain all system constrains and security.
To follow minute-to-minute variations in load, the control
engineer will monitor the system and he will give
instruction to increase or decrease the power to the power
generation unit’s operators.
B. Libralized Market
The objective of the liberalized market is to achieve
higher energy efficiency and lower consumer price and this
can be done by introducing the commercial competition [7].
Liberalization of the electricity market is proposed as an
effective solution in dispatching the power in an economic
and efficient way and this is because the liberalization of the
electricity market forces the breaking of the electric power
industry into competitive and regulated activities. However,
the interaction between participants becomes more and more
complex (Fig. 3) and information volume increases so that
an appropriate information system for decision support is
required [8].
Introducing competition in generation and marketing means
allowing multiple parties to compete to provide electricity to
customers in a given area. Integrated Market means that the
generation, transmission and distribution belongs to a simple
owner e.g. (Government) [5].
Fig. 3. New Electric Energy Landscape [6]
In the liberalized market the whole sale market platform is
organized in such a way where generators can offer their
supply at a specific given price. The cheapest power is
procured first and this allows for the prices to be set
reflecting the conditions of the supply and demand at that
time. In addition to the parties that own the generation,
transmission and distribution infrastructure, there are other
parties that enter the market as marketers or retailers of
electricity. This involves procuring electricity on wholesale
markets and billing the end user customers. Marketers seek
to acquire more customers and this can be done by proving
the electricity with lower prices and good quality [9].
1) Advantages of the Liberalized Market
The main advantage of the liberalized market or the
competitive market is generally addressing the shortcomings
of the vertically integrated model in terms of poor
efficiency, lack of innovation and too high prices. Where
provider must compete to provide generation and marketing
services otherwise their investment will be at risk and they
will end up in running their units inefficiently. As a result of
competition between multiple providers, customers
generally see a more responsive service as well as a less
costly means of supply. It should be noted that the price of
electricity does not necessarily reduces in all situations
under a liberalized electricity market structure. The
electricity price just responds to the market conditions, so it
may decrease or increase based on the conditions. For
example, if the price of fuel is increased hence the prices for
electricity will also increase regardless of the supply model
adopted [8].
2) Example of Dispatch Procedure in the Liberalized
Market
System Components
The overall procedures in the liberalized market at New
York Independent System Operator (NYISO) “Bid-to-Bill”
Process [10] from the time Bids are received to the time that
payments are made consists of the following major Points:
• Bid/Post System
• Day-Ahead Subsystem
• Real-Time Scheduling (RTS) Subsystem
 Real-Time Commitment (RTC)
 Real-Time Dispatch (RTD)
• Settlement Subsystem
Bid/Post System
The purpose of the Bid/Post System is to:
• Accept generator and load bids
• Post the public results of the Real Time Dispatch
(RTD), the Day-Ahead Market and the Real Time
Commitment (RTC).
Day-Ahead Scheduling Subsystem
The Day-Ahead scheduling procedures consist of the
following:
• Compile all the day-ahead transmission outages (if
any); update transfer capabilities of the
Transmission Lines, its constraints and the security
constrained unit commitment (SCUC) model; post
updated total transmission line capability.
Authorized licensed use limited to: Pontificia Universidad Javeriana. Downloaded on October 23,2023 at 19:15:17 UTC from IEEE Xplore. Restrictions apply.
Proceedings of the 8th IEEE GCC Conference and Exhibition, Muscat, Oman, 1-4 February, 2015
• Create Day-Ahead Load Forecast, based on
weather forecasts and the load forecast model.
• Prepare SCUC and scheduling.
• Schedule and evaluate all the non-firm
transactions; in the case of no congestion, the non-
firm transactions are tabulated in sequence up to
the available transfer capabilities of the
transmission system.
• Prepare automated mitigation of generator offers.
Real-Time Scheduling Subsystem
To make sure that the schedules meet all of the reliability
requirements almost every fifteen minutes, a Real-Time
Commitment (RTC) evaluation is performed. By using the
Real Time Commitment (RTC) program the Real-Time
transaction is evaluated independently tacking in
consideration the Day-Ahead transactions and Generator
Bids. Any new External Transactions it will be scheduled by
RTC program, which could displace some of the Day-Ahead
non-firm transactions. If required, 10 and 30-minute
resources will also be scheduled. The results are then
announced every 15 minutes.
Almost every 5 minutes, the Real-Time Dispatch (RTD)
uses Bid curves of the generators to dispatch the system to
meet the load while tacking in consideration the
transmission constraints.
Settlement Subsystem
During each hour of operation, the results of SCUC, RTS
and Automatic Generation Control (AGC) are captured and
saved for later use by the Billing subsystem.Fig.4 shows the
procedures in the liberalized market Bill to Bid Process as
explained in above sections.
The sequence of events in the liberalized market for the
load dispatch (Locational Based Marginal Price Time Line)
LBMPs is shown in Fig.5.
Finalized bids must be submitted day-ahead by 05:00 a.m.
(or by 4:50 A.m.)[10].
By 11:00 a.m. on the day before to the Dispatch Day, the
ISO shall complete the Day-Ahead scheduling process and
announce on the Bid/Post System the Day-Ahead schedule.
Locational Based Marginal Prices (LBMPs) are posted on
the Bid/Post System as public data and commitment
schedules are announced on the Bid/Post System as private
data [10].
Bids may be left standing or withdrawn if not accepted.
Standing bids may be used in Supplemental Resource
Evaluation (SRE).
A reliability study is performed over the seven (7)-day
period that begins with the next Dispatch Day. This study
evaluates if resources with longer start-up times are required
to meet forecasted Load and reserve requirements. Units that
are committed are guaranteed a minimum generation bid cost
[10].
Fig. 4. NYISO Bill to Bid Process [10]
Fig. 5. Locational Based Marginal Prices Time Line [10]
Authorized licensed use limited to: Pontificia Universidad Javeriana. Downloaded on October 23,2023 at 19:15:17 UTC from IEEE Xplore. Restrictions apply.
Proceedings of the 8th IEEE GCC Conference and Exhibition, Muscat, Oman, 1-4 February, 2015
IV. CONCLUSIONS
In this paper, an overview of the economic dispatch problem
was presented. The review included the problem
formulation as well as the objectives and constraints. A
standard mathematical formulation is presented. A
comparison between the economic dispatch problem in the
vertically integrated and the liberalized markets is
discussed. In the vertically integrated market, transmission
and distribution are owned by a single entity, e.g. the
government. In this model, the provider does not have to
compete to provide the electricity to the customer with low
cost and high quality as there are no other competitors in the
market. The advantages of the vertically integrated power
system are its simplicity and certainty. The disadvantage of
the vertically integrated power system is the incentives for
innovation are generally considered to be weak, unless
governments are particularly involved in supporting
researches and development section in areas of dispatching
the power in an economic and efficient way. On the other
hand, the liberalized market environment addresses the
shortcomings of the vertically integrated model in terms of
poor efficiency, lack of innovation and sometimes too high
prices. Energy provider must compete to provide power in
an efficient manner.
REFERENCES
[1] H. Saadat, “Power system analysis,” WCB/McGraw-Hill, 1999.
[2] United States Department of Energy, “The value of economic
dispatch- a report to congress pursuant to section 1234 of the energy
policy ACT of 2005,”.
[3] Coelho, L. Santos, and C. Lee, Solving economic load dispatch
problems in power systems using chaotic and Gaussian particle
swarm optimization approaches, International Journal of Electrical
Power  Energy Systems, 2008, pp. 297-307.
[4] A. J. Wood, and B. F. Wollenberg, “Power generation, operation, and
control,” John Wiley  Sons, 1996.
[5] B. Gjorgiev, Fuzzy-genetic optimization approach for generation
scheduling with system consisted of conventional and renewable
energy sources, PhD diss., Master’s thesis, 2010.
[6] T.Dang, and R. Chéramy, Impacts of electricity market liberalization
on centralized generation and telecontrol infrastructure, 2006 IEEE
International Conference on Industrial Informatics, 16-18 Aug,
Singapore, 2006.
[7] A. Rong, and R. Lahdelma, Optimal operation of combined heat and
power based power systems in liberalized power markets, 2013
avaiable at: http://www.eolss.net/sample-chapters/c05/E6-39-14-
00.pdf
[8] Darry Bigger, “The NEM at 30 – which reforms for the second fifteen
years of the Australian Electricity Market,” the 10th Conference on
European Energy Market, 27-31 May, Stockholm, Sweden, 2013.
[9] M. Baritaud, Securing Power during the transition, Generation
investment and operation, 2012.
[10] New York Indepandent System Operator, “Day-Ahead Scheduling
Manual,” Version 4, 3890 Carman Rd, Schenectady, NY 12303,
February 2013.
Fahad N. Al Farsi received the B.Sc. degree in electrical
and computer engineering from Sultan Qaboos University,
Muscat, Oman in 2010.He is currently working in
WorleyParsons Oman as Electrical Engineer. He is
currently doing his master thesis in the area of power
economic dispatch at Sultan Qaboos University, Muscat,
Oman. His research interests include Power system operation and planning,
Power system economics, power system modeling and analysis and Power
Quality.
Mohammed H. Albadi received the B.Sc. degree in
electrical and computer engineering from Sultan Qaboos
University, Muscat, Oman in 2000; the M.Sc. degree in
electrical engineering from Aachen University of
Technology, Germany in 2003; the Ph.D. degree in
Electrical and Computer Engineering from University of
Waterloo, Canada in 2010. He is currently working as
Assistant Professor in the Electrical  Computer Engineering Department
at Sultan Qaboos University, Muscat, Oman. His research interests include
Renewable energy, Distributed Generation, Power Quality, Distribution
systems, Demand side management, Power system operation and planning,
and Power system economics. He is a Member of the Institute of Electrical
Engineering and Electronics, IEEE, USA.
Nasser Hosseinzadeh received a B.Sc. degree in
electrical engineering from Shiraz University in 1986, an
M.Sc. degree from Iran University of Science and
Technology in 1992, and a Ph.D. degree from Victoria
University Australia, in 1998. He is currently an Associate
Professor at Sultan Qaboos University in Oman, where he
is the Head of Department of Electrical and Computer Engineering. Earlier,
he was with Swinburne University of Technology, Australia, during 2008
to 2011, with Central Queensland University, Australia, from 2003 to 2008,
with Monash University Malaysia in 2002, and with Shiraz University from
1998 to 2001. His fields of interest include power system modeling and
analysis, renewable energy systems, applications of intelligent control in
power engineering, smart grids, and engineering education. He is a Senior
Member of the Institute of Electrical Engineering and Electronics, IEEE,
USA.
Abdullah H. Al-Badi obtained the degree of B.Sc. in
Electrical Engineering from Sultan Qaboos University,
Oman, in 1991. He received the degree of M.Sc. and Ph.D
from UMIST, UK, in 1993 and 1998 respectively. In
September 1991, he joined the Sultan Qaboos University
as demonstrator and, in 1998, he became an Assistant
Professor. Currently he is a Professor at the department of
electrical and computer engineering and the Dean of the College of
Engineering. He has published several papers in International Journals and
Conferences in the field of electrical machines, drives, interference and
high voltage. He carried out several projects on the effect of AC
interferences on pipelines. He is a Senior Member of the Institute of
Electrical Engineering and Electronics, IEEE, USA.
Authorized licensed use limited to: Pontificia Universidad Javeriana. Downloaded on October 23,2023 at 19:15:17 UTC from IEEE Xplore. Restrictions apply.

More Related Content

Similar to Economic_Dispatch_in_power_systems.pdf

Load Forecasting Using LSTM Model
Load Forecasting Using LSTM ModelLoad Forecasting Using LSTM Model
Load Forecasting Using LSTM ModelIRJET Journal
 
Techno-economical Unit Commitment Using Harmony Search Optimization Approach
Techno-economical Unit Commitment Using Harmony Search Optimization ApproachTechno-economical Unit Commitment Using Harmony Search Optimization Approach
Techno-economical Unit Commitment Using Harmony Search Optimization ApproachIJAPEJOURNAL
 
OPTIMAL ECONOMIC LOAD DISPATCH USING FUZZY LOGIC & GENETIC ALGORITHMS
OPTIMAL ECONOMIC LOAD DISPATCH USING FUZZY LOGIC & GENETIC ALGORITHMSOPTIMAL ECONOMIC LOAD DISPATCH USING FUZZY LOGIC & GENETIC ALGORITHMS
OPTIMAL ECONOMIC LOAD DISPATCH USING FUZZY LOGIC & GENETIC ALGORITHMSIAEME Publication
 
Transmission line loadability improvement using facts device
Transmission line loadability improvement using facts deviceTransmission line loadability improvement using facts device
Transmission line loadability improvement using facts deviceeSAT Publishing House
 
roy_emmerich-eurec_dissertation-summary_paper-final
roy_emmerich-eurec_dissertation-summary_paper-finalroy_emmerich-eurec_dissertation-summary_paper-final
roy_emmerich-eurec_dissertation-summary_paper-finalRoy Emmerich
 
IRJET- A Comparative Study of Economic Load Dispatch Optimization Methods
IRJET- A Comparative Study of Economic Load Dispatch Optimization MethodsIRJET- A Comparative Study of Economic Load Dispatch Optimization Methods
IRJET- A Comparative Study of Economic Load Dispatch Optimization MethodsIRJET Journal
 
Optimal load scheduling
Optimal load schedulingOptimal load scheduling
Optimal load schedulingMayank Sharma
 
Economical and Reliable Expansion Alternative of Composite Power System under...
Economical and Reliable Expansion Alternative of Composite Power System under...Economical and Reliable Expansion Alternative of Composite Power System under...
Economical and Reliable Expansion Alternative of Composite Power System under...IJECEIAES
 
DATA DRIVEN ANALYSIS OF ENERGY MANAGEMENT IN ELECTRIC VEHICLES
DATA DRIVEN ANALYSIS OF ENERGY MANAGEMENT IN ELECTRIC VEHICLESDATA DRIVEN ANALYSIS OF ENERGY MANAGEMENT IN ELECTRIC VEHICLES
DATA DRIVEN ANALYSIS OF ENERGY MANAGEMENT IN ELECTRIC VEHICLESvivatechijri
 
Solar power and our application (2)
Solar power and our application (2)Solar power and our application (2)
Solar power and our application (2)Mahesh Chandra Manav
 
Electric power system operation.
Electric power system operation.Electric power system operation.
Electric power system operation.v Kalairajan
 
A Load Shedding Scheme Based On Frequency Response Model With Fast Voltage St...
A Load Shedding Scheme Based On Frequency Response Model With Fast Voltage St...A Load Shedding Scheme Based On Frequency Response Model With Fast Voltage St...
A Load Shedding Scheme Based On Frequency Response Model With Fast Voltage St...IRJET Journal
 
Application of tvac pso for reactive power cost minimization in deregulated e...
Application of tvac pso for reactive power cost minimization in deregulated e...Application of tvac pso for reactive power cost minimization in deregulated e...
Application of tvac pso for reactive power cost minimization in deregulated e...eSAT Journals
 
Energy in Factory Automation and the Role of Industrial Networks
Energy in Factory Automation and the Role of Industrial NetworksEnergy in Factory Automation and the Role of Industrial Networks
Energy in Factory Automation and the Role of Industrial NetworksPlantEngineering
 
Energy in Factory Automation and the Role of Industrial Networks
Energy in Factory Automation and the Role of Industrial Networks Energy in Factory Automation and the Role of Industrial Networks
Energy in Factory Automation and the Role of Industrial Networks ControlEng
 
Congestion Management Approaches in Deregulated Electricity Market: A Compreh...
Congestion Management Approaches in Deregulated Electricity Market: A Compreh...Congestion Management Approaches in Deregulated Electricity Market: A Compreh...
Congestion Management Approaches in Deregulated Electricity Market: A Compreh...Dr. Sudhir Kumar Srivastava
 
A hybrid approach for ipfc location and parameters optimization for congestio...
A hybrid approach for ipfc location and parameters optimization for congestio...A hybrid approach for ipfc location and parameters optimization for congestio...
A hybrid approach for ipfc location and parameters optimization for congestio...eSAT Journals
 

Similar to Economic_Dispatch_in_power_systems.pdf (20)

Load Forecasting Using LSTM Model
Load Forecasting Using LSTM ModelLoad Forecasting Using LSTM Model
Load Forecasting Using LSTM Model
 
I05216877
I05216877I05216877
I05216877
 
Techno-economical Unit Commitment Using Harmony Search Optimization Approach
Techno-economical Unit Commitment Using Harmony Search Optimization ApproachTechno-economical Unit Commitment Using Harmony Search Optimization Approach
Techno-economical Unit Commitment Using Harmony Search Optimization Approach
 
F43022431
F43022431F43022431
F43022431
 
Viva
VivaViva
Viva
 
OPTIMAL ECONOMIC LOAD DISPATCH USING FUZZY LOGIC & GENETIC ALGORITHMS
OPTIMAL ECONOMIC LOAD DISPATCH USING FUZZY LOGIC & GENETIC ALGORITHMSOPTIMAL ECONOMIC LOAD DISPATCH USING FUZZY LOGIC & GENETIC ALGORITHMS
OPTIMAL ECONOMIC LOAD DISPATCH USING FUZZY LOGIC & GENETIC ALGORITHMS
 
Transmission line loadability improvement using facts device
Transmission line loadability improvement using facts deviceTransmission line loadability improvement using facts device
Transmission line loadability improvement using facts device
 
roy_emmerich-eurec_dissertation-summary_paper-final
roy_emmerich-eurec_dissertation-summary_paper-finalroy_emmerich-eurec_dissertation-summary_paper-final
roy_emmerich-eurec_dissertation-summary_paper-final
 
IRJET- A Comparative Study of Economic Load Dispatch Optimization Methods
IRJET- A Comparative Study of Economic Load Dispatch Optimization MethodsIRJET- A Comparative Study of Economic Load Dispatch Optimization Methods
IRJET- A Comparative Study of Economic Load Dispatch Optimization Methods
 
Optimal load scheduling
Optimal load schedulingOptimal load scheduling
Optimal load scheduling
 
Economical and Reliable Expansion Alternative of Composite Power System under...
Economical and Reliable Expansion Alternative of Composite Power System under...Economical and Reliable Expansion Alternative of Composite Power System under...
Economical and Reliable Expansion Alternative of Composite Power System under...
 
DATA DRIVEN ANALYSIS OF ENERGY MANAGEMENT IN ELECTRIC VEHICLES
DATA DRIVEN ANALYSIS OF ENERGY MANAGEMENT IN ELECTRIC VEHICLESDATA DRIVEN ANALYSIS OF ENERGY MANAGEMENT IN ELECTRIC VEHICLES
DATA DRIVEN ANALYSIS OF ENERGY MANAGEMENT IN ELECTRIC VEHICLES
 
Solar power and our application (2)
Solar power and our application (2)Solar power and our application (2)
Solar power and our application (2)
 
Electric power system operation.
Electric power system operation.Electric power system operation.
Electric power system operation.
 
A Load Shedding Scheme Based On Frequency Response Model With Fast Voltage St...
A Load Shedding Scheme Based On Frequency Response Model With Fast Voltage St...A Load Shedding Scheme Based On Frequency Response Model With Fast Voltage St...
A Load Shedding Scheme Based On Frequency Response Model With Fast Voltage St...
 
Application of tvac pso for reactive power cost minimization in deregulated e...
Application of tvac pso for reactive power cost minimization in deregulated e...Application of tvac pso for reactive power cost minimization in deregulated e...
Application of tvac pso for reactive power cost minimization in deregulated e...
 
Energy in Factory Automation and the Role of Industrial Networks
Energy in Factory Automation and the Role of Industrial NetworksEnergy in Factory Automation and the Role of Industrial Networks
Energy in Factory Automation and the Role of Industrial Networks
 
Energy in Factory Automation and the Role of Industrial Networks
Energy in Factory Automation and the Role of Industrial Networks Energy in Factory Automation and the Role of Industrial Networks
Energy in Factory Automation and the Role of Industrial Networks
 
Congestion Management Approaches in Deregulated Electricity Market: A Compreh...
Congestion Management Approaches in Deregulated Electricity Market: A Compreh...Congestion Management Approaches in Deregulated Electricity Market: A Compreh...
Congestion Management Approaches in Deregulated Electricity Market: A Compreh...
 
A hybrid approach for ipfc location and parameters optimization for congestio...
A hybrid approach for ipfc location and parameters optimization for congestio...A hybrid approach for ipfc location and parameters optimization for congestio...
A hybrid approach for ipfc location and parameters optimization for congestio...
 

Recently uploaded

Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 

Recently uploaded (20)

Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 

Economic_Dispatch_in_power_systems.pdf

  • 1. Proceedings of the 8th IEEE GCC Conference and Exhibition, Muscat, Oman, 1-4 February, 2015 978-4799-8422-0/15/$31.00©2015 IEEE Economic Dispatch in Power Systems A comparison between vertically integrated and libralized markets F. N. Al Farsi, M. H. Albadi, N. Hosseinzadeh, A. H. Al Badi Department of Electrical and Computer Engineering, Sultan Qaboos University, POBox33, Muscat 123, Sultanate of Oman m065416@student.squ.edu.om Abstract—Economic Dispatch is an important optimization problem in power system planning. This article presents an overview of the economic dispatch problem, its formulation, and a comparison of addressing the problem between the vertically integrated market and the liberalized market environments. Keywords—Econmic Dispatch; Dispatch Centre; Vertically Integrated Markets; Libralized Marekts I. INTRODUCTION Consider a system consists of N generating units serving an electrical load as shown in Fig. 1. In this system there are multiple types of fuel input used to operate the power plant e.g. (Hydro, Gas, Steam, Diesel, Nuclear, Coal, Solar, Wind… etc.). Knowing that the power systems should be operated under a high degree of economy so that the system will be operated at minimum cost; therefore the economic dispatch concept will tell how much should be the output of each generator so that the total operating cost is minimized. Fig. 1. N Generating Units Serving an Electrical Load [1] II. ECONOMIC DISPATCH FORMULATION A. Economic Dispatch Definition The purpose of the economic dispatch is to schedule the outputs of all available generation units in the power system such that the fuel cost is minimized while system constraints are satisfied. Also it can be explained as the process of allocating generation among the committed units such that the constraints imposed are satisfied and the energy requirements are minimized. Furthermore, the economic power dispatch for interconnected power system can be explained as the process of finding the total real and reactive power schedule of each power plant in such a way as to minimize the operating cost. This means that the generator’s real and reactive power is allowed to vary within certain limits so that it can meet the demand with minimum fuel cost. This is called the optimal power flow. The optimal power flow is used to optimize the power flow solution of large scale power system. This is done by minimizing selected objective functions while maintaining an acceptable system performance in terms of generators capability limits and the output of the compensating devices [1]. It is useful to divide economic dispatch practices in two separate stages: unit commitment and unit dispatch. Unit commitment takes place before real-time operation and determines the set of generating units that will be available for dispatch. Unit dispatch occurs in real time and determines the amount of generation needed from each available unit [2]. B. Objective of the Power Economic Dispatch The Main objective of the power economic dispatch is to find the total power generation output so as to minimize operating cost. Beside the main objective, there are also numbers of objectives listed as follows: • To schedule the committed generating units outputs so as to meet the required load demand at minimum operating cost while satisfying all units and system equality and inequality constraints [3]. • Minimization of the emissions (the gaseous emission such as SO2, NOx, CO and CO2 produced by thermal power plants) ; • Maximization of the profit by reducing the total cost. • Maintain System Stability and Security Constraint. Economic Dispatch Mathematical formulation The objective function of an ED problem is to: • Minimize = ∑ ( ) (1) where usually the operating cost of each generator when generating a specific output power is modeled as • ( ) = + + (2) Authorized licensed use limited to: Pontificia Universidad Javeriana. Downloaded on October 23,2023 at 19:15:17 UTC from IEEE Xplore. Restrictions apply.
  • 2. Proceedings of the 8th IEEE GCC Conference and Exhibition, Muscat, Oman, 1-4 February, 2015 • , represent the cost coefficients of the jth generating unit. • ( ) represents the cost function of the jth generating unit (in $/h), • represents the real output of the jth generating units (in MW), • is the total number of generators in the power system. This main objective is subject to a number of constraints. Theses constraints are classified into two categories as follows: 1) GENERATION CONSTRAINTS: • System constraints ∑ = + (3) Where the Transmission Line Losses equation is equal to = ∑ ∑ ! # + ∑ ! $ + !$$ (4) ! :- is the jth element of the loss coefficient square matrix, ! $ :- is the ith element of the loss coefficient vector, B$$ :- is the loss coefficient constant • Spinning Reserve Requirement ∑ ≥ ( , ) = 1,2, … … . , (5) is the spinning reserve contribution of unit I during the time interval t; SR0 is the system spinning reserve requirement for interval t; • Thermal Unit Constraints [4] Minimum up time: once the unit is running, it should not be turned off immediately. Minimum down time: once the unit is decommitted, there is a minimum time before it can be recommitted. • Must Run Units Constraints [4] In some cases, some units must remain online for voltage support requirements. Others might be needed to produce steam for water purpose or to use the steam on the plant itself. • Fuel Constraint [4] Some units have limited fuel Fuel must be burn in a specified time Type of fuel • Generator Location (criteria to be selected during design stage) • Generation Limit 1 134 , (5 = 1, … … . . , ) (6) Unit ramp rates within the range of production levels (e.g., the time it takes to move from one production level to another while respecting the turbine’s safe thermal gradients); i) If power generation increases − $ ≤ 8( (7) ii) If power generation decreases $ − ≤ 9( (8) Where $ (inMW) is the previous output power and 8((in MW/h) is the up-ramp limit of the jth generator; and 9( (in MW/h) is the down-ramp limit of the jth generator. Prohibited Operated Zone (normally will be given by the manufacturer) In the actual power system, the load demand of a power system must avoid the prohibited zones. Thus, if the constraint in (1) is taken into account, the feasible operating zones of the jth generating unit can be as follows 1 ≤ ≤ , : (9) ,; = ≤ ≤ ,; : , = 2,3, … … . , (10) , @ = ≤ ≤ 134 (11) where ,; : and ,; = are the lower and upper bound of the jth prohibited zone of the jth generating unit, and is the number of prohibited zones of the jth generating unit. In the actual power system, the load demand of a power system must avoid the prohibited zones. Authorized licensed use limited to: Pontificia Universidad Javeriana. Downloaded on October 23,2023 at 19:15:17 UTC from IEEE Xplore. Restrictions apply.
  • 3. Proceedings of the 8th IEEE GCC Conference and Exhibition, Muscat, Oman, 1-4 February, 2015 2) TRANSMISSION NETWORK CONSTRAINTS • Network Security Constraint (Voltage limit Constraints (+/- 10%) [applicable for both 132 kV and 220 kV System] • Line capacities under different power flows and loadings; : 134 ≤ : ≤ : 134 A = 1,2, … … . . , A (12) : is the active power flow through transmission line l during the interval t; : 134 is the upper limit on the active power flow along line l III. COMPARISON BETWEEN VERTICALLY INTEGRATED POWER SYSTEMS AND LIBERALIZED ELECTRICITY MARKET There are two approaches currently existing for providing electricity to the end user. The first one is the vertically integrated market and the second one is the liberalized market or competitive market. A. Vertically Integrated Market Vertically Integrated Market means that the generation, transmission and distribution belongs to a simple owner e.g. (Government) [5]. Fig. 2 is an example of a vertically integrated market where a single agency or company is responsible for generating, transmitting and distributing the power to the end user. Fig. 2. Vertically Integrated Organization [6] In this model, the provider does not have to compete to provide the electricity to the customer with low cost and high quality as there are no other competitors in the market. Sometimes the provider is asked by the government to meet the projected goals which can end up in dispatching the power in inefficient way [4]. 1) Advantages of the Vertically Integrated Power System The advantages of the Vertically Integrated Power System (VIPS) are its simplicity and certainty. A single integrated utility does not require complicated systems to dispatch the power to multiple providers at the wholesale level, or retail market platforms that allow for switching of customers between different retail providers. In the vertically integrated power system the incentives for innovation are generally considered to be weak, unless governments are particularly involved in supporting researches and development section in areas of dispatching the power in an economic and efficient way. 2) Example of Dispatch Procedure in the Vertically Integrated Market In sultanate of Oman, The Load Dispatch Centre (LDC) from Oman Electricity Transmission Company (OETC) is responsible to dispatch the power in the main interconnected system network in Oman. The way that the LDC is using in dispatching the power is an example of the vertically integrated market. First of all, the LDC department in OETC creates Day-Ahead Load Forecast, based on Data received from consumers (distribution companies and directly connected customers), weather forecasts and Day ahead units availability form all Independent Power Producers. LDC uses these three main inputs to run unit-commitment optimization computer programs to get the optimal dispatch scenarios for the next day forecast before the real operations. The computer programs take as inputs all the information on the characteristics of the individual generating units that are ready to provide electricity on the following day. These characteristics include current unit status, minimum and maximum output levels, ramp rate limits, start-up and shutdown costs, minimum runtimes, and unit fuel costs at various output levels. Moreover, the operations planner inputs to the model the utility’s day- ahead forecast loads, hour by hour. Finally, the inputs include details on the characteristics of the transmission system expected for the operating day (in particular, any lines or transformers out of service for maintenance). The optimization model is then run with all these inputs in order to identify the least cost solution to meet the following day’s electricity demands while maintaining system constraints. The reliability requirements are the ability to withstand the loss of any single generation or transmission element while maintaining normal system operation. The optimization model performs functions in its search for a least-cost solution. Once generators are committed (turned on and synchronized to the grid), they are ready to provide power to meet customer loads and reliability requirements. The provisional running orders for day a head planning used as a guide line for control engineer. However, during the real time operation the control engineer in the LDC decides how much additional (or less) generation is required during the Authorized licensed use limited to: Pontificia Universidad Javeriana. Downloaded on October 23,2023 at 19:15:17 UTC from IEEE Xplore. Restrictions apply.
  • 4. Proceedings of the 8th IEEE GCC Conference and Exhibition, Muscat, Oman, 1-4 February, 2015 next interval to meet system requirements. The action taken by the control engineer in LDC during the real time operation is to meet the load demand while maintaining all the system constraints of each generator. The control engineer during the real time operation has the authority to decide whether to turn a unit on or not (the unit- commitment decision), based on the load requirement while maintain all system constrains and security. To follow minute-to-minute variations in load, the control engineer will monitor the system and he will give instruction to increase or decrease the power to the power generation unit’s operators. B. Libralized Market The objective of the liberalized market is to achieve higher energy efficiency and lower consumer price and this can be done by introducing the commercial competition [7]. Liberalization of the electricity market is proposed as an effective solution in dispatching the power in an economic and efficient way and this is because the liberalization of the electricity market forces the breaking of the electric power industry into competitive and regulated activities. However, the interaction between participants becomes more and more complex (Fig. 3) and information volume increases so that an appropriate information system for decision support is required [8]. Introducing competition in generation and marketing means allowing multiple parties to compete to provide electricity to customers in a given area. Integrated Market means that the generation, transmission and distribution belongs to a simple owner e.g. (Government) [5]. Fig. 3. New Electric Energy Landscape [6] In the liberalized market the whole sale market platform is organized in such a way where generators can offer their supply at a specific given price. The cheapest power is procured first and this allows for the prices to be set reflecting the conditions of the supply and demand at that time. In addition to the parties that own the generation, transmission and distribution infrastructure, there are other parties that enter the market as marketers or retailers of electricity. This involves procuring electricity on wholesale markets and billing the end user customers. Marketers seek to acquire more customers and this can be done by proving the electricity with lower prices and good quality [9]. 1) Advantages of the Liberalized Market The main advantage of the liberalized market or the competitive market is generally addressing the shortcomings of the vertically integrated model in terms of poor efficiency, lack of innovation and too high prices. Where provider must compete to provide generation and marketing services otherwise their investment will be at risk and they will end up in running their units inefficiently. As a result of competition between multiple providers, customers generally see a more responsive service as well as a less costly means of supply. It should be noted that the price of electricity does not necessarily reduces in all situations under a liberalized electricity market structure. The electricity price just responds to the market conditions, so it may decrease or increase based on the conditions. For example, if the price of fuel is increased hence the prices for electricity will also increase regardless of the supply model adopted [8]. 2) Example of Dispatch Procedure in the Liberalized Market System Components The overall procedures in the liberalized market at New York Independent System Operator (NYISO) “Bid-to-Bill” Process [10] from the time Bids are received to the time that payments are made consists of the following major Points: • Bid/Post System • Day-Ahead Subsystem • Real-Time Scheduling (RTS) Subsystem Real-Time Commitment (RTC) Real-Time Dispatch (RTD) • Settlement Subsystem Bid/Post System The purpose of the Bid/Post System is to: • Accept generator and load bids • Post the public results of the Real Time Dispatch (RTD), the Day-Ahead Market and the Real Time Commitment (RTC). Day-Ahead Scheduling Subsystem The Day-Ahead scheduling procedures consist of the following: • Compile all the day-ahead transmission outages (if any); update transfer capabilities of the Transmission Lines, its constraints and the security constrained unit commitment (SCUC) model; post updated total transmission line capability. Authorized licensed use limited to: Pontificia Universidad Javeriana. Downloaded on October 23,2023 at 19:15:17 UTC from IEEE Xplore. Restrictions apply.
  • 5. Proceedings of the 8th IEEE GCC Conference and Exhibition, Muscat, Oman, 1-4 February, 2015 • Create Day-Ahead Load Forecast, based on weather forecasts and the load forecast model. • Prepare SCUC and scheduling. • Schedule and evaluate all the non-firm transactions; in the case of no congestion, the non- firm transactions are tabulated in sequence up to the available transfer capabilities of the transmission system. • Prepare automated mitigation of generator offers. Real-Time Scheduling Subsystem To make sure that the schedules meet all of the reliability requirements almost every fifteen minutes, a Real-Time Commitment (RTC) evaluation is performed. By using the Real Time Commitment (RTC) program the Real-Time transaction is evaluated independently tacking in consideration the Day-Ahead transactions and Generator Bids. Any new External Transactions it will be scheduled by RTC program, which could displace some of the Day-Ahead non-firm transactions. If required, 10 and 30-minute resources will also be scheduled. The results are then announced every 15 minutes. Almost every 5 minutes, the Real-Time Dispatch (RTD) uses Bid curves of the generators to dispatch the system to meet the load while tacking in consideration the transmission constraints. Settlement Subsystem During each hour of operation, the results of SCUC, RTS and Automatic Generation Control (AGC) are captured and saved for later use by the Billing subsystem.Fig.4 shows the procedures in the liberalized market Bill to Bid Process as explained in above sections. The sequence of events in the liberalized market for the load dispatch (Locational Based Marginal Price Time Line) LBMPs is shown in Fig.5. Finalized bids must be submitted day-ahead by 05:00 a.m. (or by 4:50 A.m.)[10]. By 11:00 a.m. on the day before to the Dispatch Day, the ISO shall complete the Day-Ahead scheduling process and announce on the Bid/Post System the Day-Ahead schedule. Locational Based Marginal Prices (LBMPs) are posted on the Bid/Post System as public data and commitment schedules are announced on the Bid/Post System as private data [10]. Bids may be left standing or withdrawn if not accepted. Standing bids may be used in Supplemental Resource Evaluation (SRE). A reliability study is performed over the seven (7)-day period that begins with the next Dispatch Day. This study evaluates if resources with longer start-up times are required to meet forecasted Load and reserve requirements. Units that are committed are guaranteed a minimum generation bid cost [10]. Fig. 4. NYISO Bill to Bid Process [10] Fig. 5. Locational Based Marginal Prices Time Line [10] Authorized licensed use limited to: Pontificia Universidad Javeriana. Downloaded on October 23,2023 at 19:15:17 UTC from IEEE Xplore. Restrictions apply.
  • 6. Proceedings of the 8th IEEE GCC Conference and Exhibition, Muscat, Oman, 1-4 February, 2015 IV. CONCLUSIONS In this paper, an overview of the economic dispatch problem was presented. The review included the problem formulation as well as the objectives and constraints. A standard mathematical formulation is presented. A comparison between the economic dispatch problem in the vertically integrated and the liberalized markets is discussed. In the vertically integrated market, transmission and distribution are owned by a single entity, e.g. the government. In this model, the provider does not have to compete to provide the electricity to the customer with low cost and high quality as there are no other competitors in the market. The advantages of the vertically integrated power system are its simplicity and certainty. The disadvantage of the vertically integrated power system is the incentives for innovation are generally considered to be weak, unless governments are particularly involved in supporting researches and development section in areas of dispatching the power in an economic and efficient way. On the other hand, the liberalized market environment addresses the shortcomings of the vertically integrated model in terms of poor efficiency, lack of innovation and sometimes too high prices. Energy provider must compete to provide power in an efficient manner. REFERENCES [1] H. Saadat, “Power system analysis,” WCB/McGraw-Hill, 1999. [2] United States Department of Energy, “The value of economic dispatch- a report to congress pursuant to section 1234 of the energy policy ACT of 2005,”. [3] Coelho, L. Santos, and C. Lee, Solving economic load dispatch problems in power systems using chaotic and Gaussian particle swarm optimization approaches, International Journal of Electrical Power Energy Systems, 2008, pp. 297-307. [4] A. J. Wood, and B. F. Wollenberg, “Power generation, operation, and control,” John Wiley Sons, 1996. [5] B. Gjorgiev, Fuzzy-genetic optimization approach for generation scheduling with system consisted of conventional and renewable energy sources, PhD diss., Master’s thesis, 2010. [6] T.Dang, and R. Chéramy, Impacts of electricity market liberalization on centralized generation and telecontrol infrastructure, 2006 IEEE International Conference on Industrial Informatics, 16-18 Aug, Singapore, 2006. [7] A. Rong, and R. Lahdelma, Optimal operation of combined heat and power based power systems in liberalized power markets, 2013 avaiable at: http://www.eolss.net/sample-chapters/c05/E6-39-14- 00.pdf [8] Darry Bigger, “The NEM at 30 – which reforms for the second fifteen years of the Australian Electricity Market,” the 10th Conference on European Energy Market, 27-31 May, Stockholm, Sweden, 2013. [9] M. Baritaud, Securing Power during the transition, Generation investment and operation, 2012. [10] New York Indepandent System Operator, “Day-Ahead Scheduling Manual,” Version 4, 3890 Carman Rd, Schenectady, NY 12303, February 2013. Fahad N. Al Farsi received the B.Sc. degree in electrical and computer engineering from Sultan Qaboos University, Muscat, Oman in 2010.He is currently working in WorleyParsons Oman as Electrical Engineer. He is currently doing his master thesis in the area of power economic dispatch at Sultan Qaboos University, Muscat, Oman. His research interests include Power system operation and planning, Power system economics, power system modeling and analysis and Power Quality. Mohammed H. Albadi received the B.Sc. degree in electrical and computer engineering from Sultan Qaboos University, Muscat, Oman in 2000; the M.Sc. degree in electrical engineering from Aachen University of Technology, Germany in 2003; the Ph.D. degree in Electrical and Computer Engineering from University of Waterloo, Canada in 2010. He is currently working as Assistant Professor in the Electrical Computer Engineering Department at Sultan Qaboos University, Muscat, Oman. His research interests include Renewable energy, Distributed Generation, Power Quality, Distribution systems, Demand side management, Power system operation and planning, and Power system economics. He is a Member of the Institute of Electrical Engineering and Electronics, IEEE, USA. Nasser Hosseinzadeh received a B.Sc. degree in electrical engineering from Shiraz University in 1986, an M.Sc. degree from Iran University of Science and Technology in 1992, and a Ph.D. degree from Victoria University Australia, in 1998. He is currently an Associate Professor at Sultan Qaboos University in Oman, where he is the Head of Department of Electrical and Computer Engineering. Earlier, he was with Swinburne University of Technology, Australia, during 2008 to 2011, with Central Queensland University, Australia, from 2003 to 2008, with Monash University Malaysia in 2002, and with Shiraz University from 1998 to 2001. His fields of interest include power system modeling and analysis, renewable energy systems, applications of intelligent control in power engineering, smart grids, and engineering education. He is a Senior Member of the Institute of Electrical Engineering and Electronics, IEEE, USA. Abdullah H. Al-Badi obtained the degree of B.Sc. in Electrical Engineering from Sultan Qaboos University, Oman, in 1991. He received the degree of M.Sc. and Ph.D from UMIST, UK, in 1993 and 1998 respectively. In September 1991, he joined the Sultan Qaboos University as demonstrator and, in 1998, he became an Assistant Professor. Currently he is a Professor at the department of electrical and computer engineering and the Dean of the College of Engineering. He has published several papers in International Journals and Conferences in the field of electrical machines, drives, interference and high voltage. He carried out several projects on the effect of AC interferences on pipelines. He is a Senior Member of the Institute of Electrical Engineering and Electronics, IEEE, USA. Authorized licensed use limited to: Pontificia Universidad Javeriana. Downloaded on October 23,2023 at 19:15:17 UTC from IEEE Xplore. Restrictions apply.