2. BACKGROUND
Bi-monthly meetings with Rampart
Extended Working Hours
5:00-6:00pm M-F
Saturdays on case-by-case basis
Only 2 citations to date – working hours
Resolved community issues/complaints
Construction office now onsite
3. DELAYS
6 months
Verizon Telecom Line
Flooding
Fire
Concrete Sub-contractor failure
Make-up
Framing (currently underway)
Interior Finish Out
4. UPDATED SCHEDULE
In Progress: Framing
November 2019
Repave Ellwood
Building A Dry-In
December 2019
Clubhouse Open (Leasing Office)
Building B Dry-In
Building A Façade
February 2020
Building B Façade
Building A Complete (Tenant occupy)
March 2020
Building B Complete (Tenant occupy)
Ribbon Cutting
December - TBD