SlideShare a Scribd company logo
1 of 4
n Baldwin
CV: Simon Barkley
barcomm@btinternet.com
Project and Discipline Engineer
BSRIA CIBSE
barcomm@btinternet.com
Tel: 07860 592847
Key Projects:
LUL SWIP Mech Engineer
2016 Managing and
coordinating mechanical
design, scope and
implementation of 20 projects
including mechanical works on
critical rooms such as SERs
CERs and IMRs. Succeeded in
achieving 150 SER/CER
mechanical installs in 3 months
to complete the financial spend
for 2014-2015 by April 5th
2015. Close relationships were
formed with Asset
Performance Directorate and
the Sponsors to make this
possible and work is now
continuing with the addition of
54 SERs for 2015-2016 in
coordination with 4LM. In
addition to the above projects I
was also managing 102 CCU
installs into critical rooms
which were completed by April
2016
Station Modernisation &
Enhancement Programme
Metronet (£80m)
Commissioning Handover &
coordination of all Utilities &
Process equipment on €150m
Euro Chewing Gum Factory for
Cadbury Schweppes (£115m)
Commissioning & Handover
Tubelines Ltd (£100m)
Commissioning Management
& commissioning execution of
all air, water and specialised
systems. Pressurised
environments for all operating
areas and performance testing
of all critical areas.
Russell’s Hall Hospital (£100m)
Commissioning Management
& commissioning execution
of all air, water & specialised
systems.
GCHQ Cheltenham (£100m)
I have over 35 years’ experience on both large-scale and small-scale
Facilities and sound working knowledge of “Mechanical Engineering”
and “Commissioning Management”
I am a highly adaptable Commissioning Project Engineer and
Manager. I have extensive experience on a wide variety of projects
– particularly HVAC, mechanical, Process Systems, BMS Systems
and Validation Qualification and offer:-
• Expertise in Commissioning Management & Project Management.
• Planning, programming and procurement skills.
• Safety awareness and Quality Control talents.
• Organising and co-ordinating flair.
• Administrative proficiency.
Computer literacy – Word Processing Software, Spreadsheets,
Programming & the Internet.
I have carried out a wide range of projects spanning over 25 years as
a contract Commissioning Engineer and Manager for various
facilities.
These projects have encompassed rail, pharmaceutical, commercial
and specialised industries and a wide range of clients.
I was employed by Tubelines in 2005 as a Commissioning and
Handover Manager and was leading the Commissioning handover
process of Knightsbridge, Neasden, North Ealing, Finchley Rd,
Willesden Green and Swiss Cottage Stations.
Since July 2008 I have been working for LUL in the capacity of
Project and Discipline Engineer on Station Modernisation and
Stabilisation Projects. Currently working with SWIP on mechanical
installs in SERs. Coordinating design, scope and implementation of
mechanical assets throughout the underground network.
n Baldwin
CV: Simon Barkley
Selected Relevant Experience
Projects:
Date
2012-
2016
Client
SWIP
LUL
Role
Mech Discipline
Engineer
Volume
£50m
per
annum
Target
Responsibilities
Managing and coordinating design, scope and implementation of all mechanical works on 20 projects including
critical rooms such as SERs CERs and IMRs. Succeeded in achieving 150 SER/CER mechanical installs in 3
months to complete the financial spend for 2014-2015 by April 5th
2015. Close relationships were formed with
Asset Performance Directorate and the Sponsors to make this possible and work is now continuing with the
addition of 54 SERs for 2015-2016 in coordination with 4LM. In addition to the above projects I was also
managing 102 CCU installs into critical rooms which were completed by April 2016
2011- 2012 London Underground Mech Project Engineer £50m Working with a large dedicated team from LUL on three “Modernisation Projects”, Baker St, Paddington and
Embankment Stations, from feasibility through design, implementation to hand back to stakeholders in 2015
Coordinating Design Scope & implementation of “Asset Stabilisation” on 27 LUL stations involving replacement
of mechanical assets in critical rooms before start of Olympics including signing off all above assets for Chief
LUL Engineer Kevin Henebury.
2010 - 2011
2008 - 2010
London Underground
London Underground
Project M&E Manager
Project M&E Manager
£10m
£80m
Coordinating Design Scope & implementation of Asset Stabilisation on 56 LUL stations involving replacement
of mechanical assets including signing off all above assets for Chief LUL Engineer Kevin Henebury.
Coordinating complete Design Scope and Install of all replacement mechanical works on Piccadilly Circus and
Central Line Control Centre
Coordinating M&E installations for Station Refurbishments for London Underground. Works involved running
and coordinating projects from conception through to commissioning and handover to the end user. Numerous
projects completed successfully in a unique and challenging environment.
n Baldwin
CV: Simon Barkley
Projects:
Date Client Role Volume Responsibilities
2007 - 2008 Cadbury Schweppes
(£115m)
Lead Project,
Commissioning and
Handover Manager
€150m Working with a large team of Multi lingual engineers as lead Commissioning Handover Manager for “Bovis
Poland” coordinating all Utilities and Process equipment on a 150 million Euro Chewing Gum Factory that will
produce 30,000 tons per annum. This has been a particularly challenging environment, not only due to the
language barriers, but Cadburys have never built a Chewing Gum Factory before therefore all of the Process
equipment is “Bespoke” and on site changes to design and assembly has been very challenging.
Date Client Role Volume Responsibilities
2006-2007 Tubelines Ltd (£100m) Commissioning and
Handover Manager
£100m I was employed as a commissioning and handover manager to oversee and coordinate HVAC and utilities
installations for facilities upgrades at 6 stations for London Underground.
:
Date Client Role Volume Responsibilities
2005-2006 Mercedes Benz UK
(£2m)
Project manager £2m I was employed as the M&E Project Manager and commissioning agent for a series of high profile Mercedes
showrooms throughout the UK. This involved planning and organising all contractors and ensuring that the
projects were completed to a very high standard and to the clients demanding schedule.
Date Client Role Volume Responsibilities
2005 Imperial College
(£20m)
Hands on Specialist
Commissioning Engineer
£20m On the basis of my experience in specialised facilities I was contracted to oversee the fit out and
commissioning of a facility at the Imperial College, South Kensington for a lunar scientist, who was
experimenting on rock from outer space. This involved a laboratory fitted with only plastic M & E services due
to the highly corrosive materials against metal that were used to cut the specimens
n Baldwin
CV: Simon Barkley
Projects:
Date Client Role Volume
2003-2004 Russel’s Hall Hospital Commissioning
Coordinator and Manager
£100m Commissioning management and commissioning execution of all air, water and specialised systems.
Pressurised environments for all operating theatres and performance testing of all critical areas.
Managing 12 commissioning engineers
Date Client Role Volume Responsibilities
2001-2003 GCHQ Cheltenham Commissioning
Coordinator and Manager
£100m Commissioning management and commissioning execution of all air, water and specialised systems.
Managing 14 commissioning engineers

More Related Content

What's hot (20)

Salakidis Savvas
Salakidis SavvasSalakidis Savvas
Salakidis Savvas
 
Thomas Mensah - CV GE
Thomas Mensah - CV  GEThomas Mensah - CV  GE
Thomas Mensah - CV GE
 
shoukat buildings and Roads -
shoukat buildings and Roads -shoukat buildings and Roads -
shoukat buildings and Roads -
 
Iain Cameron CV presentation oct14
Iain Cameron CV presentation oct14Iain Cameron CV presentation oct14
Iain Cameron CV presentation oct14
 
Alexander_Pace_Resume2016
Alexander_Pace_Resume2016Alexander_Pace_Resume2016
Alexander_Pace_Resume2016
 
R.C.V. (1)
R.C.V. (1)R.C.V. (1)
R.C.V. (1)
 
Abdallah Aboulatta
Abdallah AboulattaAbdallah Aboulatta
Abdallah Aboulatta
 
CV- Project Control Manager PMP
CV- Project Control Manager PMPCV- Project Control Manager PMP
CV- Project Control Manager PMP
 
Igwebuike CV_Project Control Engineer
Igwebuike CV_Project Control EngineerIgwebuike CV_Project Control Engineer
Igwebuike CV_Project Control Engineer
 
Cv Presentation
Cv PresentationCv Presentation
Cv Presentation
 
mohamed_mahmoud_atia - Planning & Cost Control Engineer
mohamed_mahmoud_atia - Planning & Cost Control Engineermohamed_mahmoud_atia - Planning & Cost Control Engineer
mohamed_mahmoud_atia - Planning & Cost Control Engineer
 
Mohamed Farid Gomaa
Mohamed Farid Gomaa  Mohamed Farid Gomaa
Mohamed Farid Gomaa
 
Ramy Emad C.V Project Engineer
Ramy Emad C.V Project EngineerRamy Emad C.V Project Engineer
Ramy Emad C.V Project Engineer
 
CV Presentation May16
CV Presentation May16CV Presentation May16
CV Presentation May16
 
Rahman cv
Rahman cvRahman cv
Rahman cv
 
Resume_updated 2014
Resume_updated 2014Resume_updated 2014
Resume_updated 2014
 
MERAJ UL HUDA CV
MERAJ UL HUDA CVMERAJ UL HUDA CV
MERAJ UL HUDA CV
 
Mina 2016
Mina 2016Mina 2016
Mina 2016
 
Resume
ResumeResume
Resume
 
Jonathan Betts CV 2015
Jonathan Betts CV 2015Jonathan Betts CV 2015
Jonathan Betts CV 2015
 

Similar to 01 CV 2016 Simon Barkley (1)

Bob Goswell CV - December 2015 Mk2
Bob Goswell CV - December 2015 Mk2Bob Goswell CV - December 2015 Mk2
Bob Goswell CV - December 2015 Mk2Bob Goswell
 
Stuart Johnson CV Updated 02-01-15 NEW
Stuart Johnson CV Updated 02-01-15 NEWStuart Johnson CV Updated 02-01-15 NEW
Stuart Johnson CV Updated 02-01-15 NEWstuart johnson
 
Stuart Johnson CV Updated 02-01-15 NEW
Stuart Johnson CV Updated 02-01-15 NEWStuart Johnson CV Updated 02-01-15 NEW
Stuart Johnson CV Updated 02-01-15 NEWstuart johnson
 
R&M Developments Ltd - Turnkey Building & Civils Developments and Contracting...
R&M Developments Ltd - Turnkey Building & Civils Developments and Contracting...R&M Developments Ltd - Turnkey Building & Civils Developments and Contracting...
R&M Developments Ltd - Turnkey Building & Civils Developments and Contracting...Thomas McKenna
 
CV 160105 Paul Magee
CV 160105 Paul MageeCV 160105 Paul Magee
CV 160105 Paul MageePaul Magee
 
Rupert Davison latest CV
Rupert Davison latest CVRupert Davison latest CV
Rupert Davison latest CVRupert Davison
 
CV - Florin Tuluc 2
CV - Florin Tuluc 2CV - Florin Tuluc 2
CV - Florin Tuluc 2FLORIN TULUC
 
Regidor A. Manalo Sub-Agent (Corporate C.V)
Regidor A. Manalo Sub-Agent  (Corporate C.V)Regidor A. Manalo Sub-Agent  (Corporate C.V)
Regidor A. Manalo Sub-Agent (Corporate C.V)Regidor manalo
 
Ron Williams CV Feb 2017
Ron Williams CV Feb 2017Ron Williams CV Feb 2017
Ron Williams CV Feb 2017Ron Williams
 
Challenor-paul 13-01-16
Challenor-paul 13-01-16Challenor-paul 13-01-16
Challenor-paul 13-01-16Paul Challenor
 
Key experience Feb 2016
Key experience Feb 2016Key experience Feb 2016
Key experience Feb 2016Kim Barry
 
2363 - Engineering Assurance regime development
2363 - Engineering Assurance regime development2363 - Engineering Assurance regime development
2363 - Engineering Assurance regime developmentAndy Keasley
 
Mark Simms-CV updated 08-15-16
Mark Simms-CV updated 08-15-16Mark Simms-CV updated 08-15-16
Mark Simms-CV updated 08-15-16Mark Simms
 

Similar to 01 CV 2016 Simon Barkley (1) (20)

KWKCV16
KWKCV16KWKCV16
KWKCV16
 
Bob Goswell CV - December 2015 Mk2
Bob Goswell CV - December 2015 Mk2Bob Goswell CV - December 2015 Mk2
Bob Goswell CV - December 2015 Mk2
 
Stuart Johnson CV Updated 02-01-15 NEW
Stuart Johnson CV Updated 02-01-15 NEWStuart Johnson CV Updated 02-01-15 NEW
Stuart Johnson CV Updated 02-01-15 NEW
 
Stuart Johnson CV Updated 02-01-15 NEW
Stuart Johnson CV Updated 02-01-15 NEWStuart Johnson CV Updated 02-01-15 NEW
Stuart Johnson CV Updated 02-01-15 NEW
 
Simon Murphy CV
Simon Murphy CVSimon Murphy CV
Simon Murphy CV
 
R&M Developments Ltd - Turnkey Building & Civils Developments and Contracting...
R&M Developments Ltd - Turnkey Building & Civils Developments and Contracting...R&M Developments Ltd - Turnkey Building & Civils Developments and Contracting...
R&M Developments Ltd - Turnkey Building & Civils Developments and Contracting...
 
CV 160105 Paul Magee
CV 160105 Paul MageeCV 160105 Paul Magee
CV 160105 Paul Magee
 
CV OG Jan 2016
CV OG Jan 2016CV OG Jan 2016
CV OG Jan 2016
 
william-first-revision
william-first-revisionwilliam-first-revision
william-first-revision
 
Amey CV 2015
Amey CV 2015Amey CV 2015
Amey CV 2015
 
Rupert Davison latest CV
Rupert Davison latest CVRupert Davison latest CV
Rupert Davison latest CV
 
CV - Florin Tuluc 2
CV - Florin Tuluc 2CV - Florin Tuluc 2
CV - Florin Tuluc 2
 
Moncrieff_Craig_CV
Moncrieff_Craig_CVMoncrieff_Craig_CV
Moncrieff_Craig_CV
 
Moncrieff_Craig_CV
Moncrieff_Craig_CVMoncrieff_Craig_CV
Moncrieff_Craig_CV
 
Regidor A. Manalo Sub-Agent (Corporate C.V)
Regidor A. Manalo Sub-Agent  (Corporate C.V)Regidor A. Manalo Sub-Agent  (Corporate C.V)
Regidor A. Manalo Sub-Agent (Corporate C.V)
 
Ron Williams CV Feb 2017
Ron Williams CV Feb 2017Ron Williams CV Feb 2017
Ron Williams CV Feb 2017
 
Challenor-paul 13-01-16
Challenor-paul 13-01-16Challenor-paul 13-01-16
Challenor-paul 13-01-16
 
Key experience Feb 2016
Key experience Feb 2016Key experience Feb 2016
Key experience Feb 2016
 
2363 - Engineering Assurance regime development
2363 - Engineering Assurance regime development2363 - Engineering Assurance regime development
2363 - Engineering Assurance regime development
 
Mark Simms-CV updated 08-15-16
Mark Simms-CV updated 08-15-16Mark Simms-CV updated 08-15-16
Mark Simms-CV updated 08-15-16
 

01 CV 2016 Simon Barkley (1)

  • 1. n Baldwin CV: Simon Barkley barcomm@btinternet.com Project and Discipline Engineer BSRIA CIBSE barcomm@btinternet.com Tel: 07860 592847 Key Projects: LUL SWIP Mech Engineer 2016 Managing and coordinating mechanical design, scope and implementation of 20 projects including mechanical works on critical rooms such as SERs CERs and IMRs. Succeeded in achieving 150 SER/CER mechanical installs in 3 months to complete the financial spend for 2014-2015 by April 5th 2015. Close relationships were formed with Asset Performance Directorate and the Sponsors to make this possible and work is now continuing with the addition of 54 SERs for 2015-2016 in coordination with 4LM. In addition to the above projects I was also managing 102 CCU installs into critical rooms which were completed by April 2016 Station Modernisation & Enhancement Programme Metronet (£80m) Commissioning Handover & coordination of all Utilities & Process equipment on €150m Euro Chewing Gum Factory for Cadbury Schweppes (£115m) Commissioning & Handover Tubelines Ltd (£100m) Commissioning Management & commissioning execution of all air, water and specialised systems. Pressurised environments for all operating areas and performance testing of all critical areas. Russell’s Hall Hospital (£100m) Commissioning Management & commissioning execution of all air, water & specialised systems. GCHQ Cheltenham (£100m) I have over 35 years’ experience on both large-scale and small-scale Facilities and sound working knowledge of “Mechanical Engineering” and “Commissioning Management” I am a highly adaptable Commissioning Project Engineer and Manager. I have extensive experience on a wide variety of projects – particularly HVAC, mechanical, Process Systems, BMS Systems and Validation Qualification and offer:- • Expertise in Commissioning Management & Project Management. • Planning, programming and procurement skills. • Safety awareness and Quality Control talents. • Organising and co-ordinating flair. • Administrative proficiency. Computer literacy – Word Processing Software, Spreadsheets, Programming & the Internet. I have carried out a wide range of projects spanning over 25 years as a contract Commissioning Engineer and Manager for various facilities. These projects have encompassed rail, pharmaceutical, commercial and specialised industries and a wide range of clients. I was employed by Tubelines in 2005 as a Commissioning and Handover Manager and was leading the Commissioning handover process of Knightsbridge, Neasden, North Ealing, Finchley Rd, Willesden Green and Swiss Cottage Stations. Since July 2008 I have been working for LUL in the capacity of Project and Discipline Engineer on Station Modernisation and Stabilisation Projects. Currently working with SWIP on mechanical installs in SERs. Coordinating design, scope and implementation of mechanical assets throughout the underground network.
  • 2. n Baldwin CV: Simon Barkley Selected Relevant Experience Projects: Date 2012- 2016 Client SWIP LUL Role Mech Discipline Engineer Volume £50m per annum Target Responsibilities Managing and coordinating design, scope and implementation of all mechanical works on 20 projects including critical rooms such as SERs CERs and IMRs. Succeeded in achieving 150 SER/CER mechanical installs in 3 months to complete the financial spend for 2014-2015 by April 5th 2015. Close relationships were formed with Asset Performance Directorate and the Sponsors to make this possible and work is now continuing with the addition of 54 SERs for 2015-2016 in coordination with 4LM. In addition to the above projects I was also managing 102 CCU installs into critical rooms which were completed by April 2016 2011- 2012 London Underground Mech Project Engineer £50m Working with a large dedicated team from LUL on three “Modernisation Projects”, Baker St, Paddington and Embankment Stations, from feasibility through design, implementation to hand back to stakeholders in 2015 Coordinating Design Scope & implementation of “Asset Stabilisation” on 27 LUL stations involving replacement of mechanical assets in critical rooms before start of Olympics including signing off all above assets for Chief LUL Engineer Kevin Henebury. 2010 - 2011 2008 - 2010 London Underground London Underground Project M&E Manager Project M&E Manager £10m £80m Coordinating Design Scope & implementation of Asset Stabilisation on 56 LUL stations involving replacement of mechanical assets including signing off all above assets for Chief LUL Engineer Kevin Henebury. Coordinating complete Design Scope and Install of all replacement mechanical works on Piccadilly Circus and Central Line Control Centre Coordinating M&E installations for Station Refurbishments for London Underground. Works involved running and coordinating projects from conception through to commissioning and handover to the end user. Numerous projects completed successfully in a unique and challenging environment.
  • 3. n Baldwin CV: Simon Barkley Projects: Date Client Role Volume Responsibilities 2007 - 2008 Cadbury Schweppes (£115m) Lead Project, Commissioning and Handover Manager €150m Working with a large team of Multi lingual engineers as lead Commissioning Handover Manager for “Bovis Poland” coordinating all Utilities and Process equipment on a 150 million Euro Chewing Gum Factory that will produce 30,000 tons per annum. This has been a particularly challenging environment, not only due to the language barriers, but Cadburys have never built a Chewing Gum Factory before therefore all of the Process equipment is “Bespoke” and on site changes to design and assembly has been very challenging. Date Client Role Volume Responsibilities 2006-2007 Tubelines Ltd (£100m) Commissioning and Handover Manager £100m I was employed as a commissioning and handover manager to oversee and coordinate HVAC and utilities installations for facilities upgrades at 6 stations for London Underground. : Date Client Role Volume Responsibilities 2005-2006 Mercedes Benz UK (£2m) Project manager £2m I was employed as the M&E Project Manager and commissioning agent for a series of high profile Mercedes showrooms throughout the UK. This involved planning and organising all contractors and ensuring that the projects were completed to a very high standard and to the clients demanding schedule. Date Client Role Volume Responsibilities 2005 Imperial College (£20m) Hands on Specialist Commissioning Engineer £20m On the basis of my experience in specialised facilities I was contracted to oversee the fit out and commissioning of a facility at the Imperial College, South Kensington for a lunar scientist, who was experimenting on rock from outer space. This involved a laboratory fitted with only plastic M & E services due to the highly corrosive materials against metal that were used to cut the specimens
  • 4. n Baldwin CV: Simon Barkley Projects: Date Client Role Volume 2003-2004 Russel’s Hall Hospital Commissioning Coordinator and Manager £100m Commissioning management and commissioning execution of all air, water and specialised systems. Pressurised environments for all operating theatres and performance testing of all critical areas. Managing 12 commissioning engineers Date Client Role Volume Responsibilities 2001-2003 GCHQ Cheltenham Commissioning Coordinator and Manager £100m Commissioning management and commissioning execution of all air, water and specialised systems. Managing 14 commissioning engineers