PRESENTATION ON DMC PILE FOUNDATION
B Y: S A M I R S A R K A R
A S E / C I V I L
INTRODUCTION
Piles are the columnar structure, the most common type of deep foundation, that safely
transfer loads from the super-structure to more competent sub-surface strata by means
of :
Friction,
End Bearing or
A combination of both.
Based on the method of construction, Piles can be broadly classified into the
followings:
Driven (Displacement) Cast-in-situ Piles.
Bored (Replacement) Cast-in-situ Piles.
Driven (Displacement) Precast Piles.
Bored (Replacement) Precast Piles
Based on the materials, Piles can further be classified into the followings:
Concrete
Timber
Steel
Composite
Sand
Among these, the most common type of piles used for majority of construction works
in India are bored cast-in-situ concrete piles.
BORED CAST-IN-SITU PILE BY DMC METHOD
Direct Mud Circulation method of pile foundation is a type of bored cast-in-situ piles.
The method is termed as Direct Mud Circulation because it involves the circulation
of mud from the pile bore directly to the bentonite pit where the pump reuses the
bentonite slurry leaving alone the settled mud.
Direct Mud Circulation method is best suited:
When working-space is a huge constraint.
In Industries and power plants where there is a network of pipelines snaking all
around.
While the other methods are comparatively expensive.
Where the sub-soil be cohesive in nature.
Diameter of Pile varies from 500 mm to 1000 mm and can dug a depth upto 30 m.
APPARATUS USED
1. DMC Rig.
 The Tripod System
Main Shear Leg- Longer than other two leg,
attached with winch. Length- 7.50 m and can be
adjusted with a 20 mm dia pin.
Side Shear Leg- There are two side shear legs,
6.30 m long and they mainly support the tripod
system. The side legs must be placed at least 1.5m
away from the center of the piles.
 Typical arrangement of bentonite tank at site.
DMC ROD
Length (m) 2.70 3.0 3.25
Diameter (mm) 95 75 65
Thread Length (mm) 120
Thread Dia (mm) Tapered
WINCH MACHINE
Capacity 3 Ton (Other capacities can be of 1 Ton
2.5 Ton 5 Ton 7.5 Ton etc.)
Driven wheel dia (mm) 900
TREMIE PIPE
ID (mm) 125
OD(mm) 150
Thickness (mm) 12
PROCEDURE
DMC piling Rig set-up and initiation of boring using the Bailer.
Survey is carried out from main benchmark, and pile points (by verifying co-
ordinates) are marked with iron pegs. Minimum two reference points are kept (at
least 2.00 m away from center of pile) at site to cross-check the center of the Pile.
After the point for boring operation is set out by the surveyor the tripod is paced
such that each side legs are at least 1.50 m away from the center of borehole.
The Bailer is then attached with the rope and the boring operation is initiated.
Insertion of the guide casing.
After bailer reaches its full length into the soil, the guide casing (different dia &
different length) is placed on the top of the bore hole and hammered by the bailer to
insert it into the soil. This will be withdrawn after concreting is over.
Boring with Chisel.
Once the guide casing is placed, the boring is started with chisel. The chisel has 4
nozzles from where bentonite slurry jet is forced on the hard soil layer as the boring
progresses.
Progression of boring and addition of DMC Rods.
DMC rods are added one after another as the depth increases.
DMC head are attached on top of the DMC rods which has the plunge which
receives the slurry from delivery hose.
The whole system is pulled up by the rope and the D-Shackle with the help of the
winch system and then left to fall free, so that the chisel at the bottom cuts the soil
and the boring progresses.
The loose soil produced by boring, mixes with water and comes up and is stored in
the wash vat, where the soil gets precipitated and the water is again usable.
Taking out of the DMC rods and Chisel and Insertion of the reinforcement
cage.
After the boring is complete up to the desired depth, the DMC rods are removed one
by one using the DMC fork and the chisel is also removed.
Prefabricated reinforcement cage is cleaned out of loose material and maintaining
the proper cover throughout the length of the cage. Cage may be made in two or
three parts. Cage lowering to be done from bottom to top (one after another) by
welding the main vertical reinforcement. The cage should be welded in between the
main vertical rod and stiffeners to maintain rigidity
Concreting and finalization of the process
The tremie pipes are inserted one by one using the Tremie fork and then the
bore hole is washed with the Bentonite water and the Muck is completely
removed and the hole is filled with bentonite slurry.
The Transit mixer arrives and the Hopper is attached
on top of the tremie pipe.
 The TM puts concrete mix into the hopper and the
valve opens. The bore hole is gradually filled with
concrete which is compacted by gradual vibration
of tremie pipes. This filling of concrete from the
bottom is done to avoid segregation of the concrete
mix.
Concreting and finalization of the process
As the concrete fills the hole from bottom, Bentonite slurry escapes the hole.
The tremie pipes are detached one by one and thus the hole gets filled
completely.
After the hole is fully filled, the Guide casing shall be lifted immediately and
no pouring shall be allowed thereafter. Concrete is left 28 days to gain full
strength.
Drilling Mud (Bentonite) confirming IS: 2911-2010.
The liquid limit of bentonite when tested in accordance with IS 2720 (Part 5) shall be
400 percent or more.
The bentonite suspension shall be made by mixing it with fresh water using a pump for
circulation.
To achieve the requisite specific gravity of the bentonite solution, the concentration of
bentonite per 1 cum of water is calculated as under:
Ys=1+0.006 x Cs
Ys= Desired specific gravity of bentonite., Cs= Concentration of bentonite (by weight
per cum of water).
So, Cs=1/6 x (Ys -1) x1000 =% by weight of 1000 L water.
First flushing: When the earth is being bored, bentonite suspension of specific gravity
between 1.03 to 1.10 is to be maintained.
PROCEDURE
The density of bentonite after contamination with deleterious material in the bore
hole may rise and should be brought down to at least 1.12 g/ml by flushing before
concreting.
The marsh viscosity of bentonite suspension when tested by a marsh cone shall be
between 30 to 60 stokes; in special cases it may be allowed upto 90 s.
The pH value of the bentonite suspension shall be between 9 and 11.5.
PROCEDURE
Typical Mud circulation process
CONCLUSION
DMC piling is the most common piling methods used in India. For moderate sized
piles, that is 450mm to 1000mm diameter and 25m to 30m depth piles; it is also most
convenient and economic way of piling. Larger piles that are of diameter up to
1500mm can also be founded by this method, but those are not that convenient. Other
process like Reduced Mud Circulation (RMC) is also in use.
T H A N K Y O U

More Related Content

What's hot

Microtunneling presentation 2014
Microtunneling presentation 2014Microtunneling presentation 2014
Microtunneling presentation 2014
Jamal A'Bed
 
Driven & Bored Piles
Driven & Bored PilesDriven & Bored Piles
Driven & Bored Piles
Ahmed Zanaty
 
Construction equipment
Construction equipmentConstruction equipment
Construction equipment
Tareq Shreehah
 

What's hot (20)

Cast in situ Pile
Cast in situ PileCast in situ Pile
Cast in situ Pile
 
Pile driving problems and solutions by Dr. Malek Smadi of GEOTILL
Pile driving problems and solutions by Dr. Malek Smadi of GEOTILLPile driving problems and solutions by Dr. Malek Smadi of GEOTILL
Pile driving problems and solutions by Dr. Malek Smadi of GEOTILL
 
Earthwork
EarthworkEarthwork
Earthwork
 
Transportation of concrete
Transportation of concreteTransportation of concrete
Transportation of concrete
 
Microtunneling presentation 2014
Microtunneling presentation 2014Microtunneling presentation 2014
Microtunneling presentation 2014
 
Driven & Bored Piles
Driven & Bored PilesDriven & Bored Piles
Driven & Bored Piles
 
Shore pile
Shore pileShore pile
Shore pile
 
Presentation tos
Presentation tosPresentation tos
Presentation tos
 
NATM ppt sumit
NATM ppt sumitNATM ppt sumit
NATM ppt sumit
 
Box Pushing Technique
Box Pushing TechniqueBox Pushing Technique
Box Pushing Technique
 
Diaphragm Wall Presentation By Gagan
Diaphragm Wall Presentation By GaganDiaphragm Wall Presentation By Gagan
Diaphragm Wall Presentation By Gagan
 
Pile foundation
Pile foundationPile foundation
Pile foundation
 
Well Foundation
Well FoundationWell Foundation
Well Foundation
 
Pile foundation
Pile foundationPile foundation
Pile foundation
 
pile foundation and pile cap presentation
pile foundation and pile cap presentationpile foundation and pile cap presentation
pile foundation and pile cap presentation
 
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PDF
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PDFCTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PDF
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PDF
 
Piling equipment and installation
Piling equipment and installationPiling equipment and installation
Piling equipment and installation
 
Construction equipment
Construction equipmentConstruction equipment
Construction equipment
 
Civil Engineering Construction Techniques
Civil Engineering  Construction TechniquesCivil Engineering  Construction Techniques
Civil Engineering Construction Techniques
 
Tremie concreting
Tremie concretingTremie concreting
Tremie concreting
 

Similar to Dmc pile

LEC 15hsjsjjsjdjjdjdnnhdhdhdbdhdndd F C.ptx
LEC 15hsjsjjsjdjjdjdnnhdhdhdbdhdndd  F C.ptxLEC 15hsjsjjsjdjjdjdnnhdhdhdbdhdndd  F C.ptx
LEC 15hsjsjjsjdjjdjdnnhdhdhdbdhdndd F C.ptx
krishnarajgire71
 

Similar to Dmc pile (20)

construction procedure of DMC piling
construction procedure of DMC pilingconstruction procedure of DMC piling
construction procedure of DMC piling
 
DMC Piling
DMC PilingDMC Piling
DMC Piling
 
Anantpur Report
Anantpur ReportAnantpur Report
Anantpur Report
 
mbl
mblmbl
mbl
 
Well Foundation
Well FoundationWell Foundation
Well Foundation
 
Special Concreting Techniques
Special Concreting Techniques Special Concreting Techniques
Special Concreting Techniques
 
signature bridge short presentation
signature bridge short presentationsignature bridge short presentation
signature bridge short presentation
 
Gwe paper material
Gwe paper materialGwe paper material
Gwe paper material
 
Construction Sequence.pptx
Construction Sequence.pptxConstruction Sequence.pptx
Construction Sequence.pptx
 
Diaphragm wall construction
Diaphragm wall constructionDiaphragm wall construction
Diaphragm wall construction
 
LEC 15hsjsjjsjdjjdjdnnhdhdhdbdhdndd F C.ptx
LEC 15hsjsjjsjdjjdjdnnhdhdhdbdhdndd  F C.ptxLEC 15hsjsjjsjdjjdjdnnhdhdhdbdhdndd  F C.ptx
LEC 15hsjsjjsjdjjdjdnnhdhdhdbdhdndd F C.ptx
 
workability test of concrete
workability test of concreteworkability test of concrete
workability test of concrete
 
Preperation of concrete
Preperation of concretePreperation of concrete
Preperation of concrete
 
UNIT-2.pptx
UNIT-2.pptxUNIT-2.pptx
UNIT-2.pptx
 
Method Statement D Wall
Method Statement D WallMethod Statement D Wall
Method Statement D Wall
 
Road, Culvert & Bridge Training
Road, Culvert & Bridge TrainingRoad, Culvert & Bridge Training
Road, Culvert & Bridge Training
 
Manufacturing process of concrete (for civil engineering)
Manufacturing process of concrete (for civil engineering) Manufacturing process of concrete (for civil engineering)
Manufacturing process of concrete (for civil engineering)
 
Concrete
ConcreteConcrete
Concrete
 
Ay 2020 2021 fe supply key
Ay 2020 2021 fe supply keyAy 2020 2021 fe supply key
Ay 2020 2021 fe supply key
 
3 tunnel
3 tunnel3 tunnel
3 tunnel
 

Recently uploaded

1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
AldoGarca30
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
ssuser89054b
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Kandungan 087776558899
 

Recently uploaded (20)

HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdf
 
UNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptxUNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptx
 
Worksharing and 3D Modeling with Revit.pptx
Worksharing and 3D Modeling with Revit.pptxWorksharing and 3D Modeling with Revit.pptx
Worksharing and 3D Modeling with Revit.pptx
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...
 
Augmented Reality (AR) with Augin Software.pptx
Augmented Reality (AR) with Augin Software.pptxAugmented Reality (AR) with Augin Software.pptx
Augmented Reality (AR) with Augin Software.pptx
 
Introduction to Geographic Information Systems
Introduction to Geographic Information SystemsIntroduction to Geographic Information Systems
Introduction to Geographic Information Systems
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network Devices
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech students
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
Introduction to Artificial Intelligence ( AI)
Introduction to Artificial Intelligence ( AI)Introduction to Artificial Intelligence ( AI)
Introduction to Artificial Intelligence ( AI)
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
Linux Systems Programming: Inter Process Communication (IPC) using Pipes
Linux Systems Programming: Inter Process Communication (IPC) using PipesLinux Systems Programming: Inter Process Communication (IPC) using Pipes
Linux Systems Programming: Inter Process Communication (IPC) using Pipes
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.
 

Dmc pile

  • 1. PRESENTATION ON DMC PILE FOUNDATION B Y: S A M I R S A R K A R A S E / C I V I L
  • 2. INTRODUCTION Piles are the columnar structure, the most common type of deep foundation, that safely transfer loads from the super-structure to more competent sub-surface strata by means of : Friction, End Bearing or A combination of both. Based on the method of construction, Piles can be broadly classified into the followings: Driven (Displacement) Cast-in-situ Piles. Bored (Replacement) Cast-in-situ Piles. Driven (Displacement) Precast Piles. Bored (Replacement) Precast Piles
  • 3. Based on the materials, Piles can further be classified into the followings: Concrete Timber Steel Composite Sand Among these, the most common type of piles used for majority of construction works in India are bored cast-in-situ concrete piles.
  • 4. BORED CAST-IN-SITU PILE BY DMC METHOD Direct Mud Circulation method of pile foundation is a type of bored cast-in-situ piles. The method is termed as Direct Mud Circulation because it involves the circulation of mud from the pile bore directly to the bentonite pit where the pump reuses the bentonite slurry leaving alone the settled mud. Direct Mud Circulation method is best suited: When working-space is a huge constraint. In Industries and power plants where there is a network of pipelines snaking all around. While the other methods are comparatively expensive. Where the sub-soil be cohesive in nature. Diameter of Pile varies from 500 mm to 1000 mm and can dug a depth upto 30 m.
  • 5. APPARATUS USED 1. DMC Rig.  The Tripod System
  • 6. Main Shear Leg- Longer than other two leg, attached with winch. Length- 7.50 m and can be adjusted with a 20 mm dia pin. Side Shear Leg- There are two side shear legs, 6.30 m long and they mainly support the tripod system. The side legs must be placed at least 1.5m away from the center of the piles.  Typical arrangement of bentonite tank at site.
  • 7. DMC ROD Length (m) 2.70 3.0 3.25 Diameter (mm) 95 75 65 Thread Length (mm) 120 Thread Dia (mm) Tapered WINCH MACHINE Capacity 3 Ton (Other capacities can be of 1 Ton 2.5 Ton 5 Ton 7.5 Ton etc.) Driven wheel dia (mm) 900 TREMIE PIPE ID (mm) 125 OD(mm) 150 Thickness (mm) 12
  • 8. PROCEDURE DMC piling Rig set-up and initiation of boring using the Bailer. Survey is carried out from main benchmark, and pile points (by verifying co- ordinates) are marked with iron pegs. Minimum two reference points are kept (at least 2.00 m away from center of pile) at site to cross-check the center of the Pile. After the point for boring operation is set out by the surveyor the tripod is paced such that each side legs are at least 1.50 m away from the center of borehole. The Bailer is then attached with the rope and the boring operation is initiated.
  • 9. Insertion of the guide casing. After bailer reaches its full length into the soil, the guide casing (different dia & different length) is placed on the top of the bore hole and hammered by the bailer to insert it into the soil. This will be withdrawn after concreting is over. Boring with Chisel. Once the guide casing is placed, the boring is started with chisel. The chisel has 4 nozzles from where bentonite slurry jet is forced on the hard soil layer as the boring progresses.
  • 10.
  • 11. Progression of boring and addition of DMC Rods. DMC rods are added one after another as the depth increases. DMC head are attached on top of the DMC rods which has the plunge which receives the slurry from delivery hose. The whole system is pulled up by the rope and the D-Shackle with the help of the winch system and then left to fall free, so that the chisel at the bottom cuts the soil and the boring progresses. The loose soil produced by boring, mixes with water and comes up and is stored in the wash vat, where the soil gets precipitated and the water is again usable.
  • 12. Taking out of the DMC rods and Chisel and Insertion of the reinforcement cage. After the boring is complete up to the desired depth, the DMC rods are removed one by one using the DMC fork and the chisel is also removed. Prefabricated reinforcement cage is cleaned out of loose material and maintaining the proper cover throughout the length of the cage. Cage may be made in two or three parts. Cage lowering to be done from bottom to top (one after another) by welding the main vertical reinforcement. The cage should be welded in between the main vertical rod and stiffeners to maintain rigidity
  • 13. Concreting and finalization of the process The tremie pipes are inserted one by one using the Tremie fork and then the bore hole is washed with the Bentonite water and the Muck is completely removed and the hole is filled with bentonite slurry. The Transit mixer arrives and the Hopper is attached on top of the tremie pipe.  The TM puts concrete mix into the hopper and the valve opens. The bore hole is gradually filled with concrete which is compacted by gradual vibration of tremie pipes. This filling of concrete from the bottom is done to avoid segregation of the concrete mix.
  • 14. Concreting and finalization of the process As the concrete fills the hole from bottom, Bentonite slurry escapes the hole. The tremie pipes are detached one by one and thus the hole gets filled completely. After the hole is fully filled, the Guide casing shall be lifted immediately and no pouring shall be allowed thereafter. Concrete is left 28 days to gain full strength.
  • 15. Drilling Mud (Bentonite) confirming IS: 2911-2010. The liquid limit of bentonite when tested in accordance with IS 2720 (Part 5) shall be 400 percent or more. The bentonite suspension shall be made by mixing it with fresh water using a pump for circulation. To achieve the requisite specific gravity of the bentonite solution, the concentration of bentonite per 1 cum of water is calculated as under: Ys=1+0.006 x Cs Ys= Desired specific gravity of bentonite., Cs= Concentration of bentonite (by weight per cum of water). So, Cs=1/6 x (Ys -1) x1000 =% by weight of 1000 L water. First flushing: When the earth is being bored, bentonite suspension of specific gravity between 1.03 to 1.10 is to be maintained.
  • 16. PROCEDURE The density of bentonite after contamination with deleterious material in the bore hole may rise and should be brought down to at least 1.12 g/ml by flushing before concreting. The marsh viscosity of bentonite suspension when tested by a marsh cone shall be between 30 to 60 stokes; in special cases it may be allowed upto 90 s. The pH value of the bentonite suspension shall be between 9 and 11.5.
  • 18. CONCLUSION DMC piling is the most common piling methods used in India. For moderate sized piles, that is 450mm to 1000mm diameter and 25m to 30m depth piles; it is also most convenient and economic way of piling. Larger piles that are of diameter up to 1500mm can also be founded by this method, but those are not that convenient. Other process like Reduced Mud Circulation (RMC) is also in use.
  • 19. T H A N K Y O U