SlideShare a Scribd company logo
1 of 26
Management and Mitigation of Groundwater infiltration in
underground rock excavation
Angelo Indelicato
Underground excavation often involves dealing with groundwater infiltration. The
management and mitigation of water inflow is important during tunnelling work, as it
affects both the construction area and the surroundings. This session will focus on the
following key elements:
• Where groundwater comes from
• How to measure water infiltration
• Mitigation measures
• Past Cases
• Conclusions
Synopsys
Why is groundwater infiltration important?
Essentially because we want to avoid that this….… turns into this.
Groundwater Infiltration Problems
Groundwater-related problems can be direct or indirect and can be subdivided into 5
categories (Loew, S. et al. 2010):
1. Excavation and safety problems;
2. Instability problems;
3. Impacts on surface springs and wetlands;
4. Settlements of sensitive surface layers (soils);
5. Large scale rock mass deformation due to deep tunnel drainage and pore pressure
drawdown.
NB: Designer specification regarding water inflow has to be also included (This do not affect
the stability of the tunnel. However, if the water inflow exceeds the design limit, it must be
addressed.)
Where does groundwater come from?
Groundwater finds its own way
inside the underground excavation
through rock joints and faults. It
also reach the shaft/tunnel
excavation through cracks and
crevices present in the shotcrete.
The water infiltration can be also
facilitated by operations such as
probe or blast holes drilling.
50L/min. water inflow during probing
Examples of how to measure groundwater infiltration during
rock excavation
From the underground area
(quantitative methods):
• Kibble method
• Pumping method
• Pipe channel
• Probing
• V-notch weir
From the surface area
(qualitative methods):
• Piezometers
Shaft excavation
Tunnel excavation
Shaft & Tunnel
Kibble Method
This method consists of using a sealed bucket
(kibble) to collect water from the shaft bottom.
During the weekend, when no operation was
carried out within the shaft, the water pump was
switched off to allow the groundwater to
accumulate at the end of the last excavation.
The water was then pumped into the kibble and
carried up to the surface, where the total
volume was calculated.
At times, more than one kibble was needed to
rid the shaft of water.
Pro: Very effective in estimating the water
inflow in the shaft
Con: No operation can be carried out during
the calculation
Example of volume
calculation using
the kibble method
As the water inflow is
higher than the design
limits, the area needs
remedial works
Pumping Method
This method is carried out on the sinking stage
inside the shaft and a container of known volume is
used to collect the water.
The water pump is placed inside the container and
the time it takes to pump 100 litres of water into the
container is measured.
Pro: The measuring can be done without switching
the water pump on and off and slowing down
production.
Con: The stage is not fixed. It shifts in height and
prevents the pump from working at a constant rate. If
the stage is very high, the force of gravity will burden
the pump as it draws the water out. This can affect
both the validity of the test and the calculation of the
volume of water infiltration.
Example of
pumping
method test
Pipe Channel Method
This method uses a catchment pipe ring
around the shaft walls, which is
embedded into the shotcrete layer.
Any water leaking from the shaft wall
surface can be collected within this
structure and subsequently quantified.
Pro: Same as pumping method
Con: The catchment ring only lasts for
a very short time and most of the water
is not collected by this system, making
water inflow calculations imprecise.
Probing
The main purpose of probe drilling is to identify potential geological or hydrogeological
hazards. After the initial holes are completed, a hydraulic inflatable packer is installed at 2-
3 metres from the collar and the water inflow rate is calculated. If the water inflow is below
the design criteria, the holes are filled with grout. If the water inflow exceeds the design
criteria, more holes are drilled. This operation is carried out until the last holes (control
holes) have an acceptable water inflow.
Material used to grout holes: colloidal silica, microfine or nanofine cement.
Pro: Very effective in assessing the ground water in both shaft and tunnel.
Con: Expensive in terms of grouting and it takes several shifts to drill and grout the holes
affecting the production cycle.
V-notch weir uses a metal slab
with a V-shape opening. Water is
collected in a pool and after the
slab is opened, the water level is
measured so that the water inflow
can be calculated. This type of
measurement is used mainly to
check if the post grouting work has
been effective.
Pro: It is quite cheap and easy
Con: Not always very reliable as
water is used inside the tunnel for
excavation and construction so it
is difficult to distinguish its origin.
V-notch Weir
Piezometers
Piezometres are used to monitor changes in the
piezometric head, which indicates changes in
groundwater conditions. Their great advantage is
that they are small in scale and provide useful
information.
Piezometers are normally used together with
settlement markers. They are located in the
buildings and streets adjacent to the underground
excavation. Their levels are measured before
excavation starts and periodically during the
excavation. They do not measure water but they
record any subsidence caused by excavation and
related to groundwater infiltration.
Pro: they provide valuable data regarding any
possible subsidence caused by the underground
work.
Con: They do not give us information about
groundwater infiltration.
Mitigation Measures
• Pre-excavation Grouting
• Post Grouting
• Concrete Lining
Example of high pressure water inflow
through shotcreted crown (Zhang C. et al.
2016)
Pre-excavation Grouting
If probing shows a water inflow higher than
the client’s established limit, extra holes must
be drilled around the shaft.
They are then filled with grout and they will
form a “fan’ around the excavation area,
reducing the water inflow to an acceptable
level. Once completed, control holes are
drilled to ensure water infiltration is reduced to
a proper level.
Sometimes initial probing shows low levels of
water infiltration and the initial probe holes are
considered enough. But not the entire
excavation area is probed, leaving some
zones untreated. If issues are detected later,
post grout work may be required.
Typical length of probe holes 25m with an angle of 8°
Pre-excavation Grouting in Tunnel
Post Grouting
This technique is used as remedial work if the previous did not achieve substantial results
in mitigating groundwater infiltrations.
This system involves the injection of grout into semi-horizontal holes drilled in the specific
areas where water infiltration was most severe in order to reduce it.
Concrete lining
Concrete lining is a permanent structure
that can be cast-in-place or made by a
precast unit.
The type is chosen according to the
ground conditions of construction areas,
the tunnelling method and the use of the
underground areas.
A layer of waterproof material is placed
between the excavated rock and the
concrete lining. Sometimes other
materials such as gravel and mortar can
be placed around the concrete to facilitate
the movement of the groundwater to the
level below.
Hazards related to groundwater mismanagement
Case 1
Loetschberg Tunnel – Switzerland
Tunnel completed in 1912, it is 13.7km
long.
The tunnel was flooded after the
excavation reached the contact
between limestone and alluvium of the
Kander torrent 201m above. Within
seconds, the excavated area filled up
with water, boulders, silt mud and
sand, causing the death of 25 miners.
The main cause of the accident was
the poor knowledge of the
hydrogeologic conditions of the area.
Case 2
Seoul Metro Line 5 – Phase 2, South Korea, January 1993
Construction of metro tunnel with drill and blast method
Tunnel collapse after removing spoil and an water inflow of up to
300 Lt/min was recorded.
High groundwater pressure was among the possible causes.
Remedial work included backfilling and grout work.
Sinkhole in Yongdungpo, Seoul from Shin J. et al. 2006
Case 3
Ping Lin Pilot Tunnel – Taiwan 1996
The Ping Lin is a 12.9km long tunnel excavated by TBM. During the excavation of the
pilot tunnel in 1996, groundwater infiltration reached 750 Lt./s, causing a severe
collapse with a huge volume of debris flow. The TBM was trapped with the consequent
delay of work. Freeing the TBM and water sealing/consolidating grouting lasted several
months, considerably affecting the budget (Tseng D. et al. 2001, Kipko E. et al. 1998).
Plan view of the 10th stoppage of pilot tunnel TBM, Tseng D. et al. 2001
Case 4
HATS STAGE 1 – Tunnel C and F, Hong Kong 1995 - 2000
Both tunnel have been excavated using TBM. Tunnel C is approximately 5.3km and
Tunnel F is 3.57km in length. During the first phase of excavation a water inflow of
1400lt/min was recorded. Tunnel excavation was stopped for almost 2 years without any
concern about the water in the tunnel. A settlement up to 750mm affected building within
a 1.5km radius occurred as result.
General ground lowering at TKOIE (Endicott J. 2013)
Conclusion
The combination of the methods above
manage and mitigate the groundwater
infiltration within shafts, tunnels and
generally all underground excavations.
Keeping in mind Burland’s triangle and its
principle, we can say that:
1. ground investigation can help to identify
any potential hazards, generating
ground models and helping with the
design.
2. Field tests and observations aid in
verifying the hydrogeological model and
the relationship with the actual ground
profile.
Important: A contingency plan is also
considered wise, in case of high water
infiltration exceeding the design or more
serious issues.
Idealisation,
conceptual, physical
or analytical model
Ground
profile
Appropriat
e model
Observed
behaviour
Precedent
Experience
Ground exploration
and description
Observation,
measurement,
lab & field testing
References:
• Benton I. 2015 - A comparative engineering geological study of HATS stage 1 Tunnels C and F, Hong Kong
University, MSc Dissertation;
• Indelicato A. 2012 – Management & Mitigation of Groundwater within Deep Excavation Shaft – The HATS2A
project experience in 32nd Annual Seminar, Geotechnical Division, Hong Kong Institute of Engineers, pp.111-
117.
• Kipko E., Spichak Y., Pozolov Y. 1998 – Water Sealing of Fault Zones at Ping Lin Pilot Tunnel in Taiwan in
Proceedings of International Mine Water Association Symposium, Johannesburg, South Africa, 1998, pp.141-
148.
• Loew S., Barla G. and Diederichs M. 2010 - Keynote Paper: Engineering Geology of Alpine Tunnels: Past,
Present and Future. In Proceedings of the International Association of Engineering Geologists. Auckland, New
Zealand, September 2010, 34pgs.
• Shin J., Lee I., Lee Y., Shin H. 2006 – Lessons from Serial Tunnel Collapse during Construction of the Seoul
Subway Line 5 in Proceedings of the World Tunnel Congress and 32nd ITA Assembly, Seoul, Korea, April
2006, pp. 22-27.
• Stratskraba V. 1984 – Groundwater as a nuisance in International Journal of Mine Water, Vol.3 (1), pp.25-40.
• Tseng D., Tsai B., Chang L. 2001 – A case study on ground treatment for a rock tunnel with high groundwater
ingression in Taiwan in Tunnelling and Underground Space Technology, Vol.16, Issue 3, pp.175-183.
• Zhang C., Liu N., Chu W. 2016 – Key technologies and risk management of deep tunnel construction at
Jinping II hydropower station in Journal of Rock Mechanics and Geotechnical Engineering, Vol. 8, pp.499-512.

More Related Content

What's hot

0 SWECO PP-TNa Report Grouting TH3
0 SWECO PP-TNa Report Grouting TH30 SWECO PP-TNa Report Grouting TH3
0 SWECO PP-TNa Report Grouting TH3Tomasz Najder
 
Dewatering techniques
Dewatering techniquesDewatering techniques
Dewatering techniquesjamali husain
 
Underground construction Techniques civil final year seminar
Underground construction Techniques civil final year seminarUnderground construction Techniques civil final year seminar
Underground construction Techniques civil final year seminarPavan Kumar N
 
Environmental Impacts of Groundwater Control and Dewatering
Environmental Impacts of Groundwater Control and DewateringEnvironmental Impacts of Groundwater Control and Dewatering
Environmental Impacts of Groundwater Control and DewateringMartin Preene
 
Construction dewatering
Construction dewateringConstruction dewatering
Construction dewateringShubham Parab
 
Vacuum consolidation method worldwide practice and the lastest improvement ...
Vacuum consolidation method   worldwide practice and the lastest improvement ...Vacuum consolidation method   worldwide practice and the lastest improvement ...
Vacuum consolidation method worldwide practice and the lastest improvement ...John Tran
 
Impacts from groundwater comtrol in urban areas
Impacts from groundwater comtrol in urban areasImpacts from groundwater comtrol in urban areas
Impacts from groundwater comtrol in urban areasMartin Preene
 
5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTU
5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTU5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTU
5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTUVATSAL PATEL
 
Presentation application-of-geosynthetics-in-canal
Presentation application-of-geosynthetics-in-canalPresentation application-of-geosynthetics-in-canal
Presentation application-of-geosynthetics-in-canalIEI GSC
 
Mine dewatering techniques
Mine dewatering techniquesMine dewatering techniques
Mine dewatering techniquesMartin Preene
 
Dewatering process and control in building projects
Dewatering process and control in building projectsDewatering process and control in building projects
Dewatering process and control in building projectsUmar Faruk
 
Civil Engineering-Dewatering
Civil Engineering-DewateringCivil Engineering-Dewatering
Civil Engineering-DewateringMoe Abadla
 
Dewatering for open pit mines and quarries
Dewatering for open pit mines and quarriesDewatering for open pit mines and quarries
Dewatering for open pit mines and quarriesMartin Preene
 
Miraculous Solution to Asia Pacific Soft Ground Improvement
Miraculous Solution to Asia Pacific Soft Ground ImprovementMiraculous Solution to Asia Pacific Soft Ground Improvement
Miraculous Solution to Asia Pacific Soft Ground ImprovementADFIAP
 

What's hot (20)

0 SWECO PP-TNa Report Grouting TH3
0 SWECO PP-TNa Report Grouting TH30 SWECO PP-TNa Report Grouting TH3
0 SWECO PP-TNa Report Grouting TH3
 
Dewatering techniques
Dewatering techniquesDewatering techniques
Dewatering techniques
 
Underground construction Techniques civil final year seminar
Underground construction Techniques civil final year seminarUnderground construction Techniques civil final year seminar
Underground construction Techniques civil final year seminar
 
Environmental Impacts of Groundwater Control and Dewatering
Environmental Impacts of Groundwater Control and DewateringEnvironmental Impacts of Groundwater Control and Dewatering
Environmental Impacts of Groundwater Control and Dewatering
 
Construction dewatering technology data sheet
Construction dewatering technology data sheetConstruction dewatering technology data sheet
Construction dewatering technology data sheet
 
Construction dewatering
Construction dewateringConstruction dewatering
Construction dewatering
 
Vacuum consolidation method worldwide practice and the lastest improvement ...
Vacuum consolidation method   worldwide practice and the lastest improvement ...Vacuum consolidation method   worldwide practice and the lastest improvement ...
Vacuum consolidation method worldwide practice and the lastest improvement ...
 
Impacts from groundwater comtrol in urban areas
Impacts from groundwater comtrol in urban areasImpacts from groundwater comtrol in urban areas
Impacts from groundwater comtrol in urban areas
 
5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTU
5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTU5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTU
5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTU
 
Methods of Dewatering
Methods of DewateringMethods of Dewatering
Methods of Dewatering
 
Presentation application-of-geosynthetics-in-canal
Presentation application-of-geosynthetics-in-canalPresentation application-of-geosynthetics-in-canal
Presentation application-of-geosynthetics-in-canal
 
Mine dewatering techniques
Mine dewatering techniquesMine dewatering techniques
Mine dewatering techniques
 
Dewatering process and control in building projects
Dewatering process and control in building projectsDewatering process and control in building projects
Dewatering process and control in building projects
 
Civil Engineering-Dewatering
Civil Engineering-DewateringCivil Engineering-Dewatering
Civil Engineering-Dewatering
 
Mine dewatering techniques
Mine dewatering techniquesMine dewatering techniques
Mine dewatering techniques
 
Dewatering for open pit mines and quarries
Dewatering for open pit mines and quarriesDewatering for open pit mines and quarries
Dewatering for open pit mines and quarries
 
Dewatering techniques
Dewatering techniquesDewatering techniques
Dewatering techniques
 
Dewatering
DewateringDewatering
Dewatering
 
Ground freezing..ll
Ground freezing..llGround freezing..ll
Ground freezing..ll
 
Miraculous Solution to Asia Pacific Soft Ground Improvement
Miraculous Solution to Asia Pacific Soft Ground ImprovementMiraculous Solution to Asia Pacific Soft Ground Improvement
Miraculous Solution to Asia Pacific Soft Ground Improvement
 

Similar to Management & mitigation of groundwater infiltration within underground excavation in rock

2013 12-05 challenging sites-rvss
2013 12-05 challenging sites-rvss2013 12-05 challenging sites-rvss
2013 12-05 challenging sites-rvssMaria Cahill
 
Cut and cover_sections
Cut and cover_sectionsCut and cover_sections
Cut and cover_sectionsjuwes
 
7. TUNNEL ENGINEERING
7. TUNNEL ENGINEERING7. TUNNEL ENGINEERING
7. TUNNEL ENGINEERINGVATSAL PATEL
 
Chapter 4 control of ground water in excavations
Chapter 4 control of ground water in excavationsChapter 4 control of ground water in excavations
Chapter 4 control of ground water in excavationsKHUSHBU SHAH
 
Week 01 Preliminaries Works, Soil Investigate & Ground Water Control
Week 01 Preliminaries Works, Soil Investigate & Ground Water ControlWeek 01 Preliminaries Works, Soil Investigate & Ground Water Control
Week 01 Preliminaries Works, Soil Investigate & Ground Water Controlnik kin
 
Tunneling exploration
Tunneling explorationTunneling exploration
Tunneling explorationjamali husain
 
dewateringtechniques 2.pptx
dewateringtechniques 2.pptxdewateringtechniques 2.pptx
dewateringtechniques 2.pptxCarolTumaneng
 
Presentazione torino 5 aprile 2016 vancouver con note
Presentazione torino 5 aprile 2016 vancouver con notePresentazione torino 5 aprile 2016 vancouver con note
Presentazione torino 5 aprile 2016 vancouver con noteGuido Bentivoglio
 
Ground improvement techniques
Ground improvement techniquesGround improvement techniques
Ground improvement techniquesSravan Muguda
 
Excavation and Ground water control1.pptx
Excavation and Ground water control1.pptxExcavation and Ground water control1.pptx
Excavation and Ground water control1.pptxssusercbae26
 
Ground improvement technique
Ground improvement techniqueGround improvement technique
Ground improvement techniqueSatish Kambaliya
 
Traps and manhole aditya kumar barn1 ar14002
Traps and manhole aditya kumar barn1 ar14002Traps and manhole aditya kumar barn1 ar14002
Traps and manhole aditya kumar barn1 ar14002Aditya kumar
 
Construction of Dams.pptx
Construction of Dams.pptxConstruction of Dams.pptx
Construction of Dams.pptxKhawarSakhani
 
(2010) - Yates M, Krzeminski M, Berthier D, Hamidi B - The Application of Jet...
(2010) - Yates M, Krzeminski M, Berthier D, Hamidi B - The Application of Jet...(2010) - Yates M, Krzeminski M, Berthier D, Hamidi B - The Application of Jet...
(2010) - Yates M, Krzeminski M, Berthier D, Hamidi B - The Application of Jet...Michal Krzeminski
 
The construction method for surface drainage (housing)
The construction method for surface drainage (housing)The construction method for surface drainage (housing)
The construction method for surface drainage (housing)Adib Ramli
 
Physical and social phenomena causing maintenance problems
Physical and social phenomena causing maintenance problemsPhysical and social phenomena causing maintenance problems
Physical and social phenomena causing maintenance problemsMadhabKoirala
 
Effect Of Water On Slope Stability And Investigation Of ΝΝw Drainage Techniqu...
Effect Of Water On Slope Stability And Investigation Of ΝΝw Drainage Techniqu...Effect Of Water On Slope Stability And Investigation Of ΝΝw Drainage Techniqu...
Effect Of Water On Slope Stability And Investigation Of ΝΝw Drainage Techniqu...IJMER
 
Trenchless technology
Trenchless technologyTrenchless technology
Trenchless technologydinesh sharma
 

Similar to Management & mitigation of groundwater infiltration within underground excavation in rock (20)

2013 12-05 challenging sites-rvss
2013 12-05 challenging sites-rvss2013 12-05 challenging sites-rvss
2013 12-05 challenging sites-rvss
 
Cut and cover_sections
Cut and cover_sectionsCut and cover_sections
Cut and cover_sections
 
7. TUNNEL ENGINEERING
7. TUNNEL ENGINEERING7. TUNNEL ENGINEERING
7. TUNNEL ENGINEERING
 
Chapter 4 control of ground water in excavations
Chapter 4 control of ground water in excavationsChapter 4 control of ground water in excavations
Chapter 4 control of ground water in excavations
 
Week 01 Preliminaries Works, Soil Investigate & Ground Water Control
Week 01 Preliminaries Works, Soil Investigate & Ground Water ControlWeek 01 Preliminaries Works, Soil Investigate & Ground Water Control
Week 01 Preliminaries Works, Soil Investigate & Ground Water Control
 
Tunneling exploration
Tunneling explorationTunneling exploration
Tunneling exploration
 
dewateringtechniques 2.pptx
dewateringtechniques 2.pptxdewateringtechniques 2.pptx
dewateringtechniques 2.pptx
 
Drainage system
Drainage systemDrainage system
Drainage system
 
Presentazione torino 5 aprile 2016 vancouver con note
Presentazione torino 5 aprile 2016 vancouver con notePresentazione torino 5 aprile 2016 vancouver con note
Presentazione torino 5 aprile 2016 vancouver con note
 
Ground improvement techniques
Ground improvement techniquesGround improvement techniques
Ground improvement techniques
 
Excavation and Ground water control1.pptx
Excavation and Ground water control1.pptxExcavation and Ground water control1.pptx
Excavation and Ground water control1.pptx
 
Ground improvement technique
Ground improvement techniqueGround improvement technique
Ground improvement technique
 
Traps and manhole aditya kumar barn1 ar14002
Traps and manhole aditya kumar barn1 ar14002Traps and manhole aditya kumar barn1 ar14002
Traps and manhole aditya kumar barn1 ar14002
 
Construction of Dams.pptx
Construction of Dams.pptxConstruction of Dams.pptx
Construction of Dams.pptx
 
(2010) - Yates M, Krzeminski M, Berthier D, Hamidi B - The Application of Jet...
(2010) - Yates M, Krzeminski M, Berthier D, Hamidi B - The Application of Jet...(2010) - Yates M, Krzeminski M, Berthier D, Hamidi B - The Application of Jet...
(2010) - Yates M, Krzeminski M, Berthier D, Hamidi B - The Application of Jet...
 
The construction method for surface drainage (housing)
The construction method for surface drainage (housing)The construction method for surface drainage (housing)
The construction method for surface drainage (housing)
 
Physical and social phenomena causing maintenance problems
Physical and social phenomena causing maintenance problemsPhysical and social phenomena causing maintenance problems
Physical and social phenomena causing maintenance problems
 
Effect Of Water On Slope Stability And Investigation Of ΝΝw Drainage Techniqu...
Effect Of Water On Slope Stability And Investigation Of ΝΝw Drainage Techniqu...Effect Of Water On Slope Stability And Investigation Of ΝΝw Drainage Techniqu...
Effect Of Water On Slope Stability And Investigation Of ΝΝw Drainage Techniqu...
 
Trenchless technology
Trenchless technologyTrenchless technology
Trenchless technology
 
5. Dewatering.pdf
5. Dewatering.pdf5. Dewatering.pdf
5. Dewatering.pdf
 

Recently uploaded

the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxhumanexperienceaaa
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 

Recently uploaded (20)

the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 

Management & mitigation of groundwater infiltration within underground excavation in rock

  • 1. Management and Mitigation of Groundwater infiltration in underground rock excavation Angelo Indelicato
  • 2. Underground excavation often involves dealing with groundwater infiltration. The management and mitigation of water inflow is important during tunnelling work, as it affects both the construction area and the surroundings. This session will focus on the following key elements: • Where groundwater comes from • How to measure water infiltration • Mitigation measures • Past Cases • Conclusions Synopsys
  • 3. Why is groundwater infiltration important? Essentially because we want to avoid that this….… turns into this.
  • 4. Groundwater Infiltration Problems Groundwater-related problems can be direct or indirect and can be subdivided into 5 categories (Loew, S. et al. 2010): 1. Excavation and safety problems; 2. Instability problems; 3. Impacts on surface springs and wetlands; 4. Settlements of sensitive surface layers (soils); 5. Large scale rock mass deformation due to deep tunnel drainage and pore pressure drawdown. NB: Designer specification regarding water inflow has to be also included (This do not affect the stability of the tunnel. However, if the water inflow exceeds the design limit, it must be addressed.)
  • 5. Where does groundwater come from? Groundwater finds its own way inside the underground excavation through rock joints and faults. It also reach the shaft/tunnel excavation through cracks and crevices present in the shotcrete. The water infiltration can be also facilitated by operations such as probe or blast holes drilling. 50L/min. water inflow during probing
  • 6. Examples of how to measure groundwater infiltration during rock excavation From the underground area (quantitative methods): • Kibble method • Pumping method • Pipe channel • Probing • V-notch weir From the surface area (qualitative methods): • Piezometers Shaft excavation Tunnel excavation Shaft & Tunnel
  • 7. Kibble Method This method consists of using a sealed bucket (kibble) to collect water from the shaft bottom. During the weekend, when no operation was carried out within the shaft, the water pump was switched off to allow the groundwater to accumulate at the end of the last excavation. The water was then pumped into the kibble and carried up to the surface, where the total volume was calculated. At times, more than one kibble was needed to rid the shaft of water. Pro: Very effective in estimating the water inflow in the shaft Con: No operation can be carried out during the calculation
  • 8. Example of volume calculation using the kibble method As the water inflow is higher than the design limits, the area needs remedial works
  • 9. Pumping Method This method is carried out on the sinking stage inside the shaft and a container of known volume is used to collect the water. The water pump is placed inside the container and the time it takes to pump 100 litres of water into the container is measured. Pro: The measuring can be done without switching the water pump on and off and slowing down production. Con: The stage is not fixed. It shifts in height and prevents the pump from working at a constant rate. If the stage is very high, the force of gravity will burden the pump as it draws the water out. This can affect both the validity of the test and the calculation of the volume of water infiltration.
  • 11. Pipe Channel Method This method uses a catchment pipe ring around the shaft walls, which is embedded into the shotcrete layer. Any water leaking from the shaft wall surface can be collected within this structure and subsequently quantified. Pro: Same as pumping method Con: The catchment ring only lasts for a very short time and most of the water is not collected by this system, making water inflow calculations imprecise.
  • 12. Probing The main purpose of probe drilling is to identify potential geological or hydrogeological hazards. After the initial holes are completed, a hydraulic inflatable packer is installed at 2- 3 metres from the collar and the water inflow rate is calculated. If the water inflow is below the design criteria, the holes are filled with grout. If the water inflow exceeds the design criteria, more holes are drilled. This operation is carried out until the last holes (control holes) have an acceptable water inflow. Material used to grout holes: colloidal silica, microfine or nanofine cement. Pro: Very effective in assessing the ground water in both shaft and tunnel. Con: Expensive in terms of grouting and it takes several shifts to drill and grout the holes affecting the production cycle.
  • 13. V-notch weir uses a metal slab with a V-shape opening. Water is collected in a pool and after the slab is opened, the water level is measured so that the water inflow can be calculated. This type of measurement is used mainly to check if the post grouting work has been effective. Pro: It is quite cheap and easy Con: Not always very reliable as water is used inside the tunnel for excavation and construction so it is difficult to distinguish its origin. V-notch Weir
  • 14. Piezometers Piezometres are used to monitor changes in the piezometric head, which indicates changes in groundwater conditions. Their great advantage is that they are small in scale and provide useful information. Piezometers are normally used together with settlement markers. They are located in the buildings and streets adjacent to the underground excavation. Their levels are measured before excavation starts and periodically during the excavation. They do not measure water but they record any subsidence caused by excavation and related to groundwater infiltration. Pro: they provide valuable data regarding any possible subsidence caused by the underground work. Con: They do not give us information about groundwater infiltration.
  • 15. Mitigation Measures • Pre-excavation Grouting • Post Grouting • Concrete Lining Example of high pressure water inflow through shotcreted crown (Zhang C. et al. 2016)
  • 16. Pre-excavation Grouting If probing shows a water inflow higher than the client’s established limit, extra holes must be drilled around the shaft. They are then filled with grout and they will form a “fan’ around the excavation area, reducing the water inflow to an acceptable level. Once completed, control holes are drilled to ensure water infiltration is reduced to a proper level. Sometimes initial probing shows low levels of water infiltration and the initial probe holes are considered enough. But not the entire excavation area is probed, leaving some zones untreated. If issues are detected later, post grout work may be required. Typical length of probe holes 25m with an angle of 8°
  • 18.
  • 19. Post Grouting This technique is used as remedial work if the previous did not achieve substantial results in mitigating groundwater infiltrations. This system involves the injection of grout into semi-horizontal holes drilled in the specific areas where water infiltration was most severe in order to reduce it.
  • 20. Concrete lining Concrete lining is a permanent structure that can be cast-in-place or made by a precast unit. The type is chosen according to the ground conditions of construction areas, the tunnelling method and the use of the underground areas. A layer of waterproof material is placed between the excavated rock and the concrete lining. Sometimes other materials such as gravel and mortar can be placed around the concrete to facilitate the movement of the groundwater to the level below.
  • 21. Hazards related to groundwater mismanagement Case 1 Loetschberg Tunnel – Switzerland Tunnel completed in 1912, it is 13.7km long. The tunnel was flooded after the excavation reached the contact between limestone and alluvium of the Kander torrent 201m above. Within seconds, the excavated area filled up with water, boulders, silt mud and sand, causing the death of 25 miners. The main cause of the accident was the poor knowledge of the hydrogeologic conditions of the area.
  • 22. Case 2 Seoul Metro Line 5 – Phase 2, South Korea, January 1993 Construction of metro tunnel with drill and blast method Tunnel collapse after removing spoil and an water inflow of up to 300 Lt/min was recorded. High groundwater pressure was among the possible causes. Remedial work included backfilling and grout work. Sinkhole in Yongdungpo, Seoul from Shin J. et al. 2006
  • 23. Case 3 Ping Lin Pilot Tunnel – Taiwan 1996 The Ping Lin is a 12.9km long tunnel excavated by TBM. During the excavation of the pilot tunnel in 1996, groundwater infiltration reached 750 Lt./s, causing a severe collapse with a huge volume of debris flow. The TBM was trapped with the consequent delay of work. Freeing the TBM and water sealing/consolidating grouting lasted several months, considerably affecting the budget (Tseng D. et al. 2001, Kipko E. et al. 1998). Plan view of the 10th stoppage of pilot tunnel TBM, Tseng D. et al. 2001
  • 24. Case 4 HATS STAGE 1 – Tunnel C and F, Hong Kong 1995 - 2000 Both tunnel have been excavated using TBM. Tunnel C is approximately 5.3km and Tunnel F is 3.57km in length. During the first phase of excavation a water inflow of 1400lt/min was recorded. Tunnel excavation was stopped for almost 2 years without any concern about the water in the tunnel. A settlement up to 750mm affected building within a 1.5km radius occurred as result. General ground lowering at TKOIE (Endicott J. 2013)
  • 25. Conclusion The combination of the methods above manage and mitigate the groundwater infiltration within shafts, tunnels and generally all underground excavations. Keeping in mind Burland’s triangle and its principle, we can say that: 1. ground investigation can help to identify any potential hazards, generating ground models and helping with the design. 2. Field tests and observations aid in verifying the hydrogeological model and the relationship with the actual ground profile. Important: A contingency plan is also considered wise, in case of high water infiltration exceeding the design or more serious issues. Idealisation, conceptual, physical or analytical model Ground profile Appropriat e model Observed behaviour Precedent Experience Ground exploration and description Observation, measurement, lab & field testing
  • 26. References: • Benton I. 2015 - A comparative engineering geological study of HATS stage 1 Tunnels C and F, Hong Kong University, MSc Dissertation; • Indelicato A. 2012 – Management & Mitigation of Groundwater within Deep Excavation Shaft – The HATS2A project experience in 32nd Annual Seminar, Geotechnical Division, Hong Kong Institute of Engineers, pp.111- 117. • Kipko E., Spichak Y., Pozolov Y. 1998 – Water Sealing of Fault Zones at Ping Lin Pilot Tunnel in Taiwan in Proceedings of International Mine Water Association Symposium, Johannesburg, South Africa, 1998, pp.141- 148. • Loew S., Barla G. and Diederichs M. 2010 - Keynote Paper: Engineering Geology of Alpine Tunnels: Past, Present and Future. In Proceedings of the International Association of Engineering Geologists. Auckland, New Zealand, September 2010, 34pgs. • Shin J., Lee I., Lee Y., Shin H. 2006 – Lessons from Serial Tunnel Collapse during Construction of the Seoul Subway Line 5 in Proceedings of the World Tunnel Congress and 32nd ITA Assembly, Seoul, Korea, April 2006, pp. 22-27. • Stratskraba V. 1984 – Groundwater as a nuisance in International Journal of Mine Water, Vol.3 (1), pp.25-40. • Tseng D., Tsai B., Chang L. 2001 – A case study on ground treatment for a rock tunnel with high groundwater ingression in Taiwan in Tunnelling and Underground Space Technology, Vol.16, Issue 3, pp.175-183. • Zhang C., Liu N., Chu W. 2016 – Key technologies and risk management of deep tunnel construction at Jinping II hydropower station in Journal of Rock Mechanics and Geotechnical Engineering, Vol. 8, pp.499-512.

Editor's Notes

  1. Specificherei meglio le differenze tra I diversi metodi